Loading...
HomeMy WebLinkAboutContract 26282 s 3 SPECIFICATIONS CINECREIARy 00 v r AND D.O.E. FILE 17 CONTRACT DOCUMENT ONTRACTOR'S BONDING CO. + Q�NIy 1998 CIP VARIOUS LOCATfONTRUCTION'S COPY CONTRACT 2000C CLIENT DEPARTMENT UNIT I: WATER AND SEWER REPLACEMEN'�'11�V R CT TA Yana boc, NC GRIGGS FROM EASTLAND TO E.BERRY DOE#2671 CRENSHAW FROM VAUGHN TO BINKLEY. DOE#2266 THRALL FROM HANGER TO CUL-DE-SAC DOE#2275 WALLACE FROM RAMEY TO AVENUE J DOE#2274 AVENUE M FROM OTTO TO WALLACE DOE#2272 MILLET FROM CAMPBELL TO WALLACE DOE#2268 ADA FROM VAUGHN TO WALLACE DOE#2267 PW53-060530175930 PS58-070580175170 UNIT II: PAVING IMPROVEMENTS ALTERNATES NO. 1 & NO. 2 CRENSHAW FROM VAUGHN TO BINKLEY. DOE#2266 K-1632 C115-020115040608 THRALL FROM HANGER TO CUL-DE-SAC DOE#2275 K-1623 C115-020115040609 WALLACE FROM RAMEY TO AVENUE J DOE#2274 K-1565 C115-020115040609 AVENUE M FROM OTTO TO WALLACE DOE#2272 K-1634 C115-020115040609 MILLET FROM CAMPBELL TO WALLACE DOE#2268 K-1633 C115-020115040609 ADA FROM VAUGHN TO WALLACE DOE#2267 K-1631 C115-020115040609 IN THE CITY OF FORT WORTH,TEXAS I 2000 KENNETH L. BARR BOB TERRELL MAYOR CITY MANAGER DALE FISSELER, P.E.-•DIRECTORdo PORT WORTH WATER DEPARTMENT RYAN BECK. HUGO A. MALANGA, P.E. -DIRECTOR �j a" 84574 qi DEPARTMENT OF TRANSPORTATION AND PUBLIC WORK?# 4 O. A. DOUGLAS RADEMAKER, P.E. - DIRECTOR DEPARTMENT OF ENGINEERING .ted®o� OF T .gP�........... OFFMA RECORD .. ..a, d `P '.s*' CON� -NORYlow *=f :............................. r. . . . . . . . . . • . . �': a ,� ` � 1�t 0. RICHARD J.ZOHNE W. f�1QiARDAARGOMANZ .. •_ 72 ..... 55363 '�� . . . . . . `` I'� 80560 'eeo�'gFGe T�e,.a'eTW� tjI'n�;•.9�0, �•'��`�A RSiONX ;�:s� tea♦ - ._ oti�t�� (/'��-� City of Fort Worth, Texas "cigar aniC �il ouncCommunication DATE REFERENCE NUMBER LOG NAMEE 10/3/00 **C-18262 301MPROVEMENTS PAG1 of 3 SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO M. E. BURNS CONSTRUCTION, INC. FOR 1998 CIP VARIOUS LOCATIONS CONTRACT 2000C UNIT 1: WATER AND SEWER REPLACEMENTS AND AWARD OF CONTRACT TO J. L. BERTRAM CONSTRUCTION AND ENGINEERING, INC. FOR 1998 CIP VARIOUS LOCATIONS CONTRACT 2000C UNIT 2: PAVING IMPROVEMENTS ALTERNATE NO. 2 RECOMMENDATION: It is recommended that the City Council: 1. Authorize the City Manager to transfer $120,722.50 from the Water and Sewer Operating Fund to the Sewer Capital Project Fund; and 2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Sewer Capital Project Fund in the amount of$120,722.50 from available funds; and 3. Authorize the City Manager to execute a contract with M. E. Burns Construction, Inc. in the amount of $830,298.75 and 170 working days for 1998 Capital Improvement Program (CIP) Various Locations Contract 2000C Unit 1: Water and Sewer Replacements; and 4. Authorize the City Manager to execute a contract with J. L. Bertram Construction and Engineering, Inc. in the amount of $907,373.09 and 155 working days for 1998 CIP Various Locations Contract 2000C Unit 2: Paving Improvements Alternate No. 2. DISCUSSION: Contract 2000C consists of six street reconstruction projects funded by the 1998 CIP. The Water Department has determined that water and/or sanitary sewer lines in these streets need to be replaced prior to street reconstruction. The streets to be reconstructed are: • Crenshaw Avenue from Vaughn Boulevard to Binkley Street; and • Thrall Street from Hanger Avenue to cul-de-sac; and • Wallace Street from Ramey Avenue to Avenue J; and • Avenue M from Otto Street to Wallace Street; and • Millet Avenue from Campbell Avenue to Wallace Street; and • Ada Avenue from Vaughn Boulevard to Wallace Street. The street projects will include the replacement of water and sewer utilities (Unit 1) and reconstruction of the pavement structure (Unit 2). Unit 1 also includes Griggs Street from Eastland Street to East Berry Street. It will not be reconstructed under Unit 2 of this contract but will have paving improvements done under a separate contract. Units 1 and 2 were advertised for bid on June 15 and 22, 2000. On July 13, 2000 the following bids were received: City of Fort Worth, Texas " is Council Comm'Unication a ac and DATE REFERENCE NUMBER LOG NAME PAGE 10/3/00 **C-18262 30IMPROVEMENTS 2 of 3 SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO M. E. BURNS CONSTRUCTION, INC. FOR 1998 CIP VARIOUS LOCATIONS CONTRACT 2000C UNIT 1: WATER AND SEWER REPLACEMENTS AND AWARD OF CONTRACT TO J. L. BERTRAM CONSTRUCTION AND ENGINEERING, INC. FOR 1998 CIP VARIOUS LOCATIONS CONTRACT 2000C UNIT 2: PAVING IMPROVEMENTS ALTERNATE NO. 2 UNIT 1 BIDDERS (Water and Sanitary Sewer) AMOUNT TIME OF COMPLETION M. E. Bums Construction. Inc. $ 830,298.75 170 Working Days Whizcon Utilities, Inc. $ 830,529.10 Cleburne Utility Construction, Inc. $ 845,593.55 Conatser Construction, Inc. $ 888,420.00 Stocke(Enterprises, Inc. $ 889,839.10 Sherman Hudson Utility Construction $ 891,722.22 Jackson Construction, Inc. $ 904,765.63 William J. Schultz, Inc. d/b/a Circle"C" Construction Company $ 932,859.60 Tri-Tech Construction, Inc. $1,052,405.44 Contingencies for Unit 1 change orders are $25,000.00 and $58,121.00 for associated construction inspection and survey. M. E. Bums Construction, Inc. is in compliance with the City's M/WBE Ordinance by committing to 12% M/WBE participation. The City's goal on this project is 12%. The bid documents for Unit 2 paving improvements included two alternates as follows: • Alternate No. 1 included pulverization and HMAC (hot mix asphalt concrete) resurfacing, construction of standard concrete curb and gutter, driveway approaches, and sidewalks where shown on the plans; and • Alternate No. 2 included 5-inch HMAC pavement on 6-inch lime stabilized subgrade, construction of standard concrete curb and gutter, driveway approaches, and sidewalks where shown on the plans. Considering both alternates, Alternate No. 2 will provide a more durable pavement surface. Staff is recommending award for paving improvements Alternate No. 2. UNIT 2 ALTERNATE 2 BIDDERS (Paving) AMOUNT TIME OF COMPLETION J. L. Bertram Construction & Engineering. Inc. $907,373.09 155 Working Days McClendon Construction Company, Inc. $907,515.65 Jackson Construction, Inc. $933,974.60 Stabile &Winn, Inc. $964,428.91 Contingencies for Unit 2 change orders are $27,221.00. City of Fort Worth, Texas "Ayer AnalConsamunication Cil uunc DATE REFERENCE NUMBER LOG NAME PAGE 10/3/00 **C-18262 30IMPROVEMENTS 3 of 3 SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO M. E. BURNS CONSTRUCTION, INC. FOR 1998 CIP VARIOUS LOCATIONS CONTRACT 2000C UNIT 1: WATER AND SEWER REPLACEMENTS AND AWARD OF CONTRACT TO J. L. BERTRAM CONSTRUCTION AND ENGINEERING, INC. FOR 1998 CIP VARIOUS LOCATIONS CONTRACT 2000C UNIT 2: PAVING IMPROVEMENTS ALTERNATE NO. 2 J. L. Bertram Construction & Engineering, Inc. is in compliance with the City's M/WBE Ordinance by committing to 28% M/WBE participation. The City's goal on this project is 28%. Crenshaw Avenue is located in COUNCIL DISTRICT 8. Thrall Street is located in COUNCIL DISTRICT 5. Wallace Street is located in COUNCIL DISTRICT 5. Avenue M is located in COUNCIL DISTRICT 5. Millet Avenue is located in COUNCIL DISTRICT 5. Ada Avenue is located in COUNCIL DISTRICT 5. FISCAL INFORMATION/CERTIFICATION: The Finance Director certifies that upon approval and completion of recommendation No. 1, and adoption of the attached appropriation ordinance, funds will be available in the current capital budgets, as appropriated, of the Water Capital Projects Fund, the Sewer Capital Projects Fund, and the Street Improvements Fund. MG:j Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY Office by: (to) 1&2)PS58 472045 070580175170 $120,722.50 S Mike Groomer 6140 2)PS58 541200 070580175170 $113,166.50 *PROVED Originating Department Head: 2)PS58 531350 030580175170 $ 7,556.00 CITY COUNCILS A.Douglas Rademaker 6157 (from) OCT 3 2000 1)PE45 538070 0709020 $120,722.50 Additional Information Contact: 3)PW53 541200 060530175930 $720,382.25 Y1 3)PS58 541200 070580175170 $109,916.50 City c se d1EIf of ix�-+ C115 541200 020115040608 $ 75,980.88 City o4 Fon Y4,V.4 A.Douglas Rademaker 6157 C115 541200 020115040609 $831,392.21 SPECIFICATIONS AND CONTRACT DOCUMENTS 1998 CIP VARIOUS LOCATIONS CONTRACT 2000C UNIT I: WATER AND SEWER REPLACEMENTS IN GRIGGS FROM EASTLAND TO E.BERRY DOE#2671 CRENSHAW FROM VAUGHN TO BINKLEY. DOE#2266 THRALL FROM HANGER TO CUL-DE-SAC DOE#2275 WALLACE FROM RAMEY TO AVENUE J DOE#2274 AVENUE M FROM OTTO TO WALLACE DOE#2272 MILLET FROM CAMPBELL TO WALLACE DOE#2268 ADA FROM VAUGHN TO WALLACE DOE#2267 PW53-060530175930 PS58-070580175170 UNIT II: PAVING IMPROVEMENTS ALTERNATES NO. 1 & NO. 2 CRENSHAW FROM VAUGHN TO BINKLEY. DOE#2266 K-1632 C115-020115040608 THRALL FROM HANGER TO CUL-DE-SAC DOE#2275 K-1623 C115-020115040609 WALLACE FROM RAMEY TO AVENUE J DOE#2274 K-1565 C115-020115040609 AVENUE M FROM OT-FO TO WALLACE DOE#2272 K-1634 C115-020115040609 MILLET FROM CAMPBELL TO WALLACE DOE#2268 K-1633 C115-020115040609 ADA FROM VAUGHN TO WALLACE DOE#2267 1 K-1631 1 C115-020115040609 IN THE CITY OF FORT WORTH,TEXAS 2000 KENNETH L. BARR BOB TERRELL MAYOR _ CITY MANAGER DALE FISSELER, P.E.-DIRECTOR FORT WORTH WATER DEPARTMENT HUGO A.MALANGA, P.E. -DIRECTOR DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS A.DOUGLAS RADEMAKER, P.E. - DIRECTOR DEPARTMENT OF ENGINEERING TABLE OF CONTENTS 1. Notice to Bidders 2. Special Instructions to Bidders(Water Department) 3. Proposal Unit 1: Water and Sanitary Sewer Replacements 4. Minority and Women Business Enterprises Specifications-Unit I 5. General Conditions(Water Department) 6. Special Conditions(Water Department) 7. Technical Specifications 8. Material Specifications 9. Certificate of Insurance 10. Contractor Compliance With Worker's Compensation Law 11. Performance Bond 12. Payment Bond 13. Maintenance Bond 14. Contract 15. Special Instructions to Bidders(Transportation/Public Works Department) 16. Proposal Unit II:Paving Improvements Alternates No. 1 &No.2 17. Minority and Women Business Enterprises Specifications-Unit II 18. Special Provisions—(Transportation/Public Works)Unit 11 19. Certificate of Insurance 20. Contractor Compliance With Worker's Compensation Law 21. Equipment Schedule(Unit II) 22. Experience Record(Unit II) 23. Performance Bond 24. Payment Bond 25. Maintenance Bond(Unit I) 26. Contract day#P NOTICE TO BIDDERS Sealed proposals for the following: FOR: 1998 CIP VARIOUS LOCATIONS CONTRACT 2000C UNIT I: WATER AND SANITARY SEWER REPLACEMENTS IN: GRIGGS FROM EASTLAND TO E.BERRY DOE#2671 CRENSHAW FROM.VAUGHN TO BINKLEY. DOE#2266 THRALL FROM HANGER TO CUL-DE-SAC DOE#2275 WALLACE FROM RAMEY TO AVENUE J DOE#2274 AVENUE M FROM OTTO TO WALLACE DOE#2272 MILLET FROM CAMPBELL TO WALLACE DOE#2268 ADA FROM VAUGHN TO WALLACE DOE#2267 PW53-060530175930 PS58-070580175170 UNIT II: PAVING IMPROVEMENTS ALTERNATE NO.1 &NO.2 CRENSHAW FROM VAUGHN TO BINKLEY. DOE#2266 K-1632 C115-020115040608 THRALL FROM HANGER TO CUL-DE-SAC DOE#2275 K-1623 C 115-020115040609 WALLACE FROM RAMEY TO AVENUE J DOE#2274 K-1565 C115-020115040609 AVENUE M FROM OTTO TO WALLACE DOE#2272 K-1634 C115-020115040609 MILLET FROM CAMPBELL TO WALLACE DOE#2268 K-1633 C115-020115040609 ADA FROM VAUGHN TO WALLACE DOE#2267 K-1631 C115-020115040609 Addressed to Mr.Bob Terrell,City Manager of the City of Fort Worth,Texas will be received at the Purchasing'Office until I:30 PM,Thursday,July 13,2000 and then publicly opened and read aloud at 2:00 PM in the Council Chambers. Plans, Specifications and Contract Documents for this project may be obtained at the Office of the Department of Engineering,Municipal Office Building, 1000 Throckmorton Street,Fort Worth,Texas. One set of documents will be provided to prospective bidders for a deposit of$50.00; such deposit will be refunded if the document is returned in good condition within(10)days after bids are opened. Additional sets may be purchased on a nonrefundable basis for fifty dollars($50.00)per set. These documents contain additional information for prospective bidders. Bid security is required in accordance with the Special Instruction to Bidders. Submission of Bids: This document is designed as two separate contract documents and proposals and shall not be construed as being a package. The Proposal Sections are designed as two separate proposals and are arranged to allow the Contractor to submit a bid on each individual proposal. The total low bid of each proposal is the apparent successful bidder.If the Contractor only submits a bid on one proposal and is the lowest proposed price total,the Contractor will be the apparent successful bidder for this individual proposal.'However, it.should be-noted that Unit II,Alternates No. 1 &No. 2 are considered to be alternatives to the same proposal.In order to be considered the apparent successful bidder for the paving improvements,the Contractor is required to submit bids(including separate M/WBE information)for both Alternates No. 1 &No. 2. Unit I consists of the water and/or sewer line replacements. Units II Alternates No. 1 &No. 2 consist of the street and/or storm drain improvements. Pre-qualification Requirements for Water Department Work: The water and/or sanitary sewer improvements must be performed by a contractor who is pre- qualified by the Water Department at the time of bid opening. A general contractor who is not pre- qualified by the Water Department,must employ the services of a sub-contractor who is pre- qualified. The procedure for pre-qualification is outlined in the"Special Instructions to Bidders (Water Department)". Bidders shall, if applicable,identify on the last page of the proposal section,the pre-qualified sub- contractor who shall install the water and/or sanitary sewer facilities.' Failure to list a sub-contractor who is pre-qualified by the Water Department shall result in the rejection of the bid as non-responsive. The City reserves the right to reject any and/or all bids and waive any and/or all irregularities. No bid may be withdrawn until the expiration of forty-nine(49)days from the date the M/WBE UTILIZATION FORM,PRIME CONTRACTOR WAIVER FORM and/or the GOOD FAITH EFFORT FORM("Documentation')as appropriate is received by the City. The award of contract, if made,will be within forty-nine(49)days after this documentation is received, but in no case will the award be made until the responsibility of the bidder to whom it is proposed to award the contract has been verified. Bidders are responsible for obtaining all Addenda to the contract documents and acknowledging receipt of the Addenda by initialing the appropriate spaces on the PROPOSAL form. Bids that do not acknowledge receipt of all Addenda may be rejected as being nonresponsive. Information regarding the status of Addenda may be obtained by contacting the Department of•Engineering at 817-871- 7910. In accord with City of Fort Worth Ordinance No. 11923,as amended,the City of Fort Worth has goals for the participation of minority business enterprises and women business enterprises in City contract. A copy of the Ordinance can be obtained from the Office of the City Secretary In addition, the bidder shall submit the MBE/WBE UTILIZATION FORM,PRIME CONTRACTOR WAIVER FORM and/or the GOOD FAITH EFFORT FORM("Documentation")as appropriate. The documentation must be received no later than 5:00 PM,five(5)City business days after the bid opening date. The bidder shall obtain a receipt from the appropriate employee of the managing department to whom delivery was made. Such receipt shall be evidence that the documentation was received by the City. Failure to comply shall render the bid nonresponsive. For additional information,contact Jim Deeter at(817)871-7803. BOB TERRELL GLORIA PEARSON CITY MANAGER CITY SECRETARY A.Douglas Rjdemaker,P.E. Director, De rtfEn ineerin9 By B1 Joh iring, P. . Man ger, Engine Services Advertising Dates: June 15,2000 June 22,2000 SPECIAL INSTRUCTIONS TO BIDDERS (FORT WORTH WATER DEPARTMENT) 1) PREOUALIFICATION REQUIREMENTS: The work required under Unit 1 must be performed by a contractor who has been pre-qualified by the Water Department. In the event a general contractor submitting the lowest responsible bid is not a pre- qualified utility contractor,the contractor performing the water department work for the general contractor is required to be pre-qualified. The following steps are required in order to become pre-qualified. All contractors submitting bids on Water Department work are required to be pre-qualified by the Fort Worth Water Department prior to submitting bids. This pre-qualification process will establish a bid limit based on a technical evaluation and financial analysis of the contractor. It is the bidder's responsibility to submit the following documentation:a current financial statement,an acceptable experience record,an acceptable equipment schedule and any other documents the Department may deem necessary,to the Director of the Water Department at least seven(7)calendar days prior to the date of the opening of bids. a) The financial statement required shall have been prepared by an independent certified public accountant or an independent public accountant holding a valid permit issued by an appropriate State licensing agency and shall have been so prepared as t%reflect the financial status to the submitting company. This statement must be current and not more than one(1)year old. In the case that a bidding date falls within the time a new statement is being prepared,the previous statement shall be updated by proper verification. b) For an experience record to be considered to be acceptable for a given project,it must reflect the experience of the firm seeking qualification in work of both the same nature and technical level as that of the project for which bids are to be received. c) The Director of the Water Department shall be the sole judge as to the acceptability for financial qualification to bid on any Fort Worth Water Department project. d) Bids received in excess of the bid limit shall be considered non-responsive and will be rejected as such. e) The City,in its sole discretion,may reject any bid for failure to demonstrate experience and/or expertise. f) Any proposals submitted by a non-prequalified bidder shall be returned unopened,"and if inadvdrtentlyopened,shall not be considered. g) The City will attempt to notify prospective bidders whose qualifications(financial or experience) are not deemed to be appropriate to the nature and/or magnitude of the project on which bids are to be received. Failure to notify shall not be a waiver of any necessary prequalification. 2. BID SECURITY: A cashier's check,or an acceptable bidder's bond,payable to the City of Fort Worth,in an amount of not less than five(5%)percent of the largest possible total of the bid submitted must accompany the bid,and is subject to forfeiture in the event the successful bidder fails to execute the Contract Documents within ten(10)days after the contract has been awarded. To be an acceptable surety on the bond,(1)the name of the surety shall be included on the current U.S.Treasury List,or (2)the surety must have capital and surplus equal to ten times the limit of the bond. The surety must be licensed to do business in the state of Texas. The amount of the bond shall not exceed the amount shown on the treasury list or one-tenth(1/10)the total capital and surplus. 3. BONDS: A performance bond,a payment bond,and a maintenance bond each for one hundred (100%)percent of the contract price will be required,Reference C 3-3.7. 4. WAGE RATES: Not less than the prevailing wage rates established by the City of Fort Worth, Texas,and as set forth in the Contract Documents must be paid on this project. 5. AMBIGUITY: In the case of ambiguity or lack of clearness in stating prices in the Proposal,the City reserves the right to adopt the most advantageous construction thereof to the City or to reject the Proposal. 6. BIDDER LICENSE: Bidder must be a licensed Contractor in the State of Texas. 7. NONRESIDENT BIDDERS: Pursuant to Article 601 g,Texas Revised Civil Statutes,the City of Fort Worth will not award this contract to a nonresident bidder unless the nonresident's bid is lower than the lowest bid submitted by a responsible Texas resident bidder by the same amount that a Texas resident bidder would be required to underbid a nonresident bidder to obtain a comparable contract in the state in which the nonresident's principal place of business in located. "Nonresident bidder"means a bidder whose principal place of business is not in this state,but excludes a contractor whose ultimate parent company or majority owner has its principal place of business in this state. This provision does not apply if this contract involves federal funds. The appropriate blanks of the Proposal must be filled out by all nonresident bidders in order for the bid to meet specifications. The failure of a nonresident contractor to do so will automatically disqualify that bidder. 8. PAYMENT: If the bid amount is$25,000.00 or less,the contract amount shall be paid within forty- five(45)calendar days after completion and acceptance by the City. 9. AGE: In accordance with the policy("Policy")of the Executive Branch of the Federal Government, Contractor covenants that neither it nor any of its officers,members,agents employees,program participants or subcontractors,while engaged in performing this contract,shall,in connection with the employment,advancement or discharge of employees or in connection with the terms,conditions or privileges of their employment,discriminate against persons because of their age except on the bases of a bona fide occupational qualification,retirement plan or statutory requirement. Contractor further covenants that neither it nor its officers,members,agents,employees, subcontractors,program participants,or persons acting on their behalf,shall specify,in solicitations or advertisements for employees to work on this contract,a maximum age limit for such employment unless the specified maximum age limit is based upon a bona fide occupational qualification, retirement plan or statutory requirements. Contractor warrants it will fully comply with the policy and will defend,indemnify and hold City harmless against any claims or allegations asserted by third parties or subcontractor against City arising out of Contractor's and/or its subcontractors'alleged failure to comply with the above referenced Policy concerning age discrimination in the performance of this agreement. 10. DISABILITY: In accordance with the provisions of the Americans With Disabilities Act of 1990 ("ADA"),Contractor warrants that it and any and all of its subcontractors will not unlawfully discriminate on the basis of disability in the provision of services to the general public,nor in the availability,terms and/or conditions of employment for applicants for employment with,or employees of Contractor or airy of its subcontractors. Contractor wan-ants it'will fully comply with ADA's provisions and any other applicable federal,state and local laws concerning disability and will defend, indemnify and hold City harmless against any claims or allegations asserted by third parties or subcontractors against City arising out of Contractor's and/or its subcontractors'alleged failure to comply with the above referenced laws concerning disability discrimination in the performance of this agreement. 11. MINORITY AND WOMEN BUSINESS ENTERPRISES: In accord with City of Fort Worth Ordinance No. 11923,as amended,the City of Fort Worth has goals for the participation of minority business enterprises and women business enterprises in City contracts. A copy of the Ordinance can be obtained from the Office of the City Secretary.The bidder shall submit the MBE/WBE UTILIZATION FORM,PRIME CONTRACTOR WAIVER FORM and/or the GOOD FAITH EFFORT FORM("Documentation")as appropriate. The Documentation must be received by,the managing`depar&ient no later than 5:00 p.m.,five(5)City business days after the bid opening date. The bidder shall obtain a receipt from the appropriate employee of the managing department to whom delivery was made. Such receipt shall be evidence that the documentation was received by the City. Failure to comply shall render the bid non-responsive. 12. Upon request,Contractor agrees to provide the Owner complete and accurate information regarding actual work performed by a Minority Business Enterprise(MBE)on the contract and payment thereof. Contractor further agrees to permit any audit and/or examination of any books,records or files in its possession that will substantiate the actual work performed by an MBE and/or WBE. The misrepresentation of facts(other than a negligent misrepresentation)and/or commission of fraud by the Contractor will be grounds for termination of the contract and/or initiating action under appropriate Federal, State or local laws or ordinances relating to false statements. Further,any such misrepresentation facts(other than a negligent misrepresentation)and/or commission of fraud will result in the Contractor being determined to be irresponsible and barred from participating in City work for a period of time of not less than three(3)years. Revised 9/24/97 PART C - GENERAL CONDITIONS TABLE OF CONTENTS NOVEMBER, 1, 1987 TABLE OF CONTENTS C1-1 DEFINITIONS C1-1.1 Definition of Terms C1-1 (1 ) C1-1.2 Contract Documents Cl-1 (1) C1-1.3 Notice to Bidders C1-1 (2) C1-1.4 Proposal C1-1 (2) Ci-1.5 Bidder Cl-i (2) C1-1.6 General Conditions Cl-1 (2) C1-1.7 Special Conditions Cl-1 (2) C1-1.8 Specifications C1-1 (2) C1-1.9 Bond C1-1 (2) C1-1.10 Contract C1-1 (3) C1-1.11 Plans C1-I (3) C1-1.12 City C1-1 (3) C1-1.13 City Council C1-1 (3) C1-1.14 Mayor C1-1 (3) C1-1.15 City Manager Cl-1 (3) C1-1.16 City Attorney C1-1 (3) C1-1.17 Director of Public Works Cl-1 (4 ) C1-1.18 Director, City Water Department C1-1 (4) C1-1.19 Engineer C1-1 (4 ) C1-1.20 Contractor Cl-1 (4) C1-1.21 Sureties C1-1 (4 ) C1-1.22 The Work or Project Cl-1 (4 ) C1-1.23 Working Day Cl-1 (4) C1-1.24 Calendar Day Cl-1 (4) C1-1.25 Legal Holiday Cl-1 (4 ) C1-1.26 Abbreviations Cl-1 (5) •' C1-1.27 Change Order Cl-1 (6 ) C1-1.28 Paved Streets and Alleys C1-1 (6) C1-1.29 Unpaved Streets and Alleys C1-1 (6) C1-1.30 City Streets Cl-1 (6) C1-1.31 Roadway Cl-1 ('6) C1-1.32 Gravel Street Cl-1 (6) C2-2 INTERPRETATION AND PREPARATION OF PROPOSAL C2-2.1 Proposal Form C2-2 (1) C2-2.2 Interpretation of Quantities C2-2 (1) C2-2.3 Examination of Contract Documents and Site C2-2 (2) C2-2.4 Submitting of Proposal C2-2 (3) C2-2.5 Rejection of Proposals C2-2 (3) C2-2.6 aid Security C2-2 (3) (1) C2-2.7 Delivery of Proposal C2-2 (4 ) C2-2.8 Withdrawing Proposals C2-2 (4 ) C2-2.9 Telegraphic Modification of Proposals C2-2 (4 ) C2-2.10 Public Opening of Proposal C2-2 (4 ) C2-2.11 Irregular Proposals C2-2 (4 ) C2-2.12 Disqualification of Bidders C2-2 (5) C3-3 AWARD AND EXECUTION OF DOCUMENTS C3-3.1 Consideration of Proposals C3-3 (1) C3-3.2 Minority Business Enterpise Women-Owned Business Enterprise C3-3 (1) compliance C3-3.3 Equal Employment Provisions C3-3 (1) C3-3.4 Withdrawal of Proposals C3-3 (2) C3-3.5 Award of Contract C3-3 (2) C3-3.6 Return of Proposal Securities C3-3 (2) C3-3.7 Bonds C3-3 (2) C3-3.8 Execution of Contract C3-3 (4) C3-3.9 Failure to Execute Contract C3-3 (4) C3-3.10 Beginning Work C3-3 (4) C3-3.11 Insurance C3-3 (4 ) C3-3.12 Contractor's Obligations C3-3 (7) C3-3.13 Weekly Payroll C3-3 (7) C3-3.14 Contractor's Contract Administration C3-3 (7) C3-3.15 Venue C3-3 (8) C4-4 SCOPE OF WORK C4-4.1 Intent of Contract Documents C4-4 (1) C4-4.2 Special Provisions C4-4 (1) C4-4.3 Increased or Decreased Quantities C4-4 (1) C4-4.4 Alteration of Contract Documents C4-4 (2) C4-4.S Extra Work C4-4 (2) C4-4.6 Schedule of Operations C4-4 (3) C4-4.7 Progress Schedules for Water and Sewer Plant Facilities C4-4 (4) CS-5 CONTROL OF WORK AND MATERIALS CS-S.1 Authority of Engineer CS-S (1) CS-S.2 Conformity with Plans CS-S (1) CS-S.3 Coordination of Contract Documents CS-5 (2) CS-S.4 Cooperation of Contractor CS-S (2) C5-5.5 Emergency and/or Rectification Work CS-5 (3) C5-S.6 Field Office CS-S (3) CS-5.7 Construction Stakes CS-S (3) CS-5.8 Authority and Duties of Inspectors CS-S (4) C5-S.9 Inspection CS-S (S) CS-5.10 Removal of Defective and Unauthorised work CS-S (5) C5-5.11 Substitute Materials or Squipment CS-S (S) CS-5.12 Samples and Tests of !Materials CS-5 (6) C5-5.13 Storage of Materials CS-5 (6) CS-5.14 Existing Structures and Utilities CS-5 (7) CS-5.15 Interruption of Service CS-S (7) CS-5.16 Mutual Responsibility of Contractors CS-S (8) CS-5.17 Cleanup CS-5 (8) C5-5.18 Final Inspection CS-5 (9) (2) C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY C6-6.1 Laws to be Observed C6-6 (1) C6-6.2 Permits and Licenses C6-6 (1) C6-6.3 Patented Devices, Materials and Processes C6-6 (1) C6-6.4 Sanitary Provisions C6-6 (2) C6-6.5 Public Safety and Convenience C6-6 (2) C6-6.6 Privileges of Contractor in Streets, Alleys, and Right-of-Way C6-6 (3) C6-6.7 Railway Crossings C6-6 (4 ) C6-6.8 Barricades, Warnings and Watchmen C6-6 (4 ) C6-6.9 Use of Explosives, Drop Weight, etc. C6-6 (5) C6-6.10 Work Within Easements C6-6 (6) C6-6.11 Independent Contractor C6-6 (8) C6-6.12 Contractor's Responsibility for Damage Claims C6-6 (8) C6-6.13 Contractor's Claim for Damages C6-6 (10) C6-6.14 Adjustment of Relocation of Public Utilities, etc. C6-6 (10 ) C6-6.15 Temporary Sewer Drain Connections C6-6 (10) C6-6.16 Arrangement and Charges of Water Furnished by City C6-6 (11) F` C6-6.17 Use of a Section of Portion of the Work C6-6 (11) C6-6.18 Contractor's Responsibility for Work C6-6 (11) C6-6.19 No Waiver of Legal Rights C6-6 (12) C6-6.20 Personal Liability of Public Officials C6-6 (12) C6-6.21 State Sales Tax C6-6 (12) C7-7 PROSECUTION AND PROGRESS C7-7.1 Subletting C7-7 (1) C7-7.2 Assignment of Contract C7-7 (1) C7-7.3 Prosecution of the Work C7-7 (1) C7-7.4 Limitations of Operations C7-7 (2) C7-7.5 Character of Workman and Equipment C7-7 (2) C7-7.6 Work Schedule C7-7 (3 ) C7-7.7 Time of Commencement and Completion C7-7 (4 ) C7-7. 8 Extension of time of Completion C7-7 (4 ) C7-7.9 Delays C7-7 (4 ) C7-7.10 Time of Completion C7-7 (5) C7-7.11 Suspension by Court Order C7-7 (-6 ) C7-7.12 Temporary Suspension C7-7 (6) C7-7.13 Termination of Contract due to National Emergency C7-7 (7) C7-7.14 Suspension of Abandonment of the Work and Annulment of Contract C7-7 (7) C7-7.15 Fulfillment of Contract C7-7 (9) C7-7.16 Termination for Convenience of the Onwer C7-7 (10) C7-7.17 Safety Methods and Practices C7-7 (13) ' C8-6 MEASUREMENT AND PAYMENT C8-8.1 Measurement of Quantities C8-8 (1) C8-8.2 Unit Prices C8-8 (1) (3) C8-8.3 Lump Sum CS-8 (l) C8-8.4 Scope of Payment CS-8 (1) Ce-8.5 Partial Estimates and Retainage C8-8 (2) C8-8.6 Withholding Payment C8-8 (3 ) CS-6.7 Final Acceptance C8-8 (3 ) C8-8.8 Final Payment C8-8 (3 ) C8-8.9 Adquacy of Design C8-8 (4 ) CS-8.10 General Guaranty C8-8 (4 ) CS-6.11 Subsidiary Work C8-8 (5) C8-8.12 Miscellaneous Placement of Material C8-8 (5) CS-6.13 Record Documents C8-6 (5) (4) r PART C - GENERAL CONDITIONS C1-1 DEFINITIONS SECTION Cl-1 DEFINITIONS C1-1 . 1 DEFINITIONS OF TERMS : Whenever in these Contract Documents the f ollowing terms or pronouns in place of them are used , the intent and meaning shall be understood and interpreted as follows: C1-1. 2 CONTRACT DOCUMENTS: The Contract Documents are all of the written and drawn documentsp such as specifications , bonds , addenda , plans , etc. , which govern the terms and performance of the contract . These are contained in the General Contract Documents and the Special Contract Documents. a. GENERAL CONTRACT DOCUMENTS: The General Contract Documents govern all Water Department Projects and include the following items: PART A - NOTICE TO BIDDERS (Sample) White PART B - PROPOSAL (Sample) White PART C - GENERAL CONDITIONS (C_) Canary Yellow (Developer) Brown PART D - SPECIAL CONDITIONS Green PART E - SPECIFICATIONS tl-White E2-Golden Rod E2A-White PERMITS/EASEMENTS Blue PART F - BONDS (Sample) White PART G - CONTRACT (Sample) White b. SPECIAL CONTRACT DOCUMENTS: The Special Contract Documents are prepared for each specific project as a supplement to the General Contract Documents and include the following items: PART A - NOTICE TO BIDDERS (Advertisement) Same as above PART B - PROPOSAL (Bid) PART C - GENERAL CONDITIONS PART D - SPECIAL CONDITIONS PART E - SPECIFICATIONS PERMITS/EASEMENTS PART F - BONDS PART G - CONTRACT PART 8 - PLANS (Usually bound separately) C1-1 (1) C1-1 . 3 NOTICE TO BIDDERS : All of the legal publications either actually published in public advertising mediums or furnished direct to interested parties pertaining to the work contemplated under the Contract Documents constitutes the notice to bidders. Cl-1. 4 PROPOSAL: The completed written and signed offer or tender of a bidder to perform the work which the Owner desires to have done, together with the bid security, constitutes the - _ Proposal , which becomes binding upon the Bidder when it is officially received by the Owner, has been publicly opened and read and not rejected by the Owner. C1-1 . 5 BIDDER: Any person, persons , firm, partnership, company, association, corporation, acting directly or through m a duly authorised representative, submitting a proposal for performing the work contemplated under the Contract Documents , constitutes a bidder. C1-1. 6 GENERAL CONDITIONS: The General Conditions are the usual construction and contract requirements which govern the performance of the work so that it will be carried on in accordance with the customary procedure, the local statutes , and requirements of the City of .Fort worth' s charter and promulgated ordinances. Wherever there may be a conflict between the General Conditions and Special Conditions , the latter shall take precedence and shall govern. C1-1 . 7 SPECIAL CONDITIONS: Special conditions are the specific requ rements wh c are necessary for the particular project covered by the Contract Documents and not specifically covered in the General Conditions. when considered with the General Conditions and other elements of the Contract Documents they provide the information which the Contractor and Owner should have in order to gain a thorough knowledge of the project. C1-1. 8 SPECIFICATIONS: The Specifications is that section or part of the Contract Documents which sets forth in detail the requirements which must be met by all materials, construction, workmanship, equipment and services in order to render a completed and useful project. Whenever reference is made to standard specifications, regulations, requirements, statutes, etc. , such referred to documents shall become a part of the Contract Documents just as though they were embodied therein. C1-1 . 9 BOND: The bond or bonds are the written guarantee or security fUrnished by the Contractor for the prompt and C1-1 (2) faithful performance of the contract and include the following: A. Performance Bond (see paragraph C3-3.7) b. Payment Bond (see paragraph C3-3.7) c. Maintenance Bond (see paragraph C3-3.7) d. Proposal or Bid Security (see Special Instructions to Bidders, Part A and C2-2.6) • C1-1 .10 CONTRACT: The Contract is the -formal signed agreement between the Owner and the Contractor covering the mutual understanding of the two contracting parties about the project to be- completed under the Contract Documents. C1-1 . 11 PLANS: The plans are the drawings or reproductions therefrom made by the Owner's representative showing in detail the location, dimension and position of the various elements of the project , including such profiles , typical cross-sections, layout diagrams, working drawings, preliminary drawings and such supplemental drawings as the Owner may issue to clarify other drawings or for the purpose of showing changes in the work hereinafter authorized by the Owner. The plans are usually bound separately from other parts of the Contract Documents , but they are a part of the Contract Documents just as though they were bound therein. C1-1 . 12 CITY: The City of Fort Worth, Texas, a municipal corporation* authorized and chartered under the Texas State Statutes , acting by and through its governing body or its City Manger, each of which is required by charter to perform specific duties . Responsibility for final enforcement of Contracts involving the City of Fort Worth is by Charter vested in the City Manager. The terms City and Owner are synonymous. C1-1 . 13 CITY COUNCIL: The duly elected and qualified governing body of the City of Fort Worth, Texas. C1-1 . 14 MAYOR: The officially elected Mayor, or in his absence, the Mayor Pro tem of the City of Fort Worth, Texas. C1-1.15 CITY MANAGER: The officially appointed and authorized City Manager of the City of Fort Worth, Texas , or his duly authorized representative. C1-1.16 CITY ATTORNEY: The officially appointed City Attorney of the City of Fort Worth, Texas , or his duly authorized representative. Cl-1 (3) C1-1 . 17 DIRECTOR OF PUBLIC WORKS: The duly appointed official Of the City of Fort Worth, referred to in the Charter as the City Engineer, or his duly authorized representative. C1-1 .16 DIRECTOR CITY WATER DEPARTMENT: The duly appointed Director of the City Water Department of the City of Fort Worth , Texas , or his duly authorized representative , assistant, or agents. C1-1.19 ENGINEER: The Director of Public works, the Director of the Fort Worth City Water Department ,, or- thais duly authorized aassistants , agents , engineers, inspectors , or superintendents, acting within the scope of the particular duties entrusted to them. C1-1 . 20 CONTRACTOR: The person , persons , partnership, company, firm# association, or corporation, entering into a contract with the Owner for the execution of the work, acting directly or through a duly authorised representative. A sub-contractor is a person, firm, corporation, or others under contract with the principal contractor, supplying labor and materials or only labor, for work at the site of the project. C1-1 . 21 SURETIES: The Corporate bodies which are bound by such bonds are required with and for the Contractor . The sureties engaged are to be fully responsible for the entire and satisfactory fulfillment of the Contract and for any and all requirements as set forth in the Contract Documents and approved changes therein. C1-1. 22 TRE WORK OR PROJECTs The completed work contemplated in and covered by the Contract Documents, including but not limited to the furnishing of all labor, materials , tools , equipment, and incidentals necessary to produce a completed and serviceable project. C1-1 . 23 WORKING DAY: A working day is -defined as a calendar May, not including Saturdays, Sundays, and legal holidays, in which the weather or other conditions not under the control of the Contractor permit the performance of the principal unit of work for a period of not less than seven (7 ) hours between 7: 00 a.m. and 6 : 00 p.m. , with exceptions as permitted in paragraph C7-7.6. C1-1. 24 CALENDAR DAYS: A calendar day is any day of the week or month, no days being excepted. C1-1 . 25 LEGAL HOLIDAYS: Legal holidays shall be observed as prescribed by the City Council of the City of Fort Worth for observance by City employees as follows: C1-1 (4) r 1. New Year's Day Januar 1 2. M. L. Ring, Jr. Birthday Third Monday in January 3. Memorial Day Last Monday in May 4. Independence Day July 4 S. Labor Day First Monday in September 6. Thanksgiving Day Fourth Thursday in November 7. Thanksgiving Friday Fourth Friday in November �'" S. Christmas Day December 25 9. Such other days in lieu of holidays as the City Council may determine When one of the above named holidays or a special holiday is declared by the City Council, falls on Saturday, the holiday shall be observed on the preceding Friday or if it falls on Sunday, it shall be observed on the following Monday, by those employees working on working day operations . Employees working calendar day operations will consider the calendar holiday as the holiday. C1-1. 26 ABBREVIATIONS: Wherever the abbreviations defined herein appear in Contract Documents, the intent and meaning shall be as follows: AASETO - American Association of MGD - Million Gallons Per State Highway Transportation Day Officials ASCE - American Society of Civil CFS - Cubic Foot per Engineers Second LAW - In Accordance With ASTM - American Society of Min. - Minimum Testing Materials Mono.- Monolithic AWWA - American Water works it - Percent= Association R - Radius ASA - American Standards Association I.D. - Inside Diameter HI - Hydraulic Institute O. D. - Outside _ Diameter Asph. - Asphalt Elev.- Elevation Ave. - Avenue F - Fahrenheit Blvd. - Boulevard C - Centigrade CI - Cast Iron In. - Inch CL - Center Line ft. - Foot GI - Galvanized Iron St. - Street Lin. - Linear or Lineal CY - Cubic Yard lb. - Pound Yd. - Yard ME - Manhole BY - Square Yard Max. - Maximum L.P. - Linear Foot D.I. - Ductile Iron C1-1 (5) C1-1 . 27 CHANGE ORDER : A " Change Order" is a written supplemental agreement between the Owner and the Contractor covering some added or deducted item or feature which may be found necessary and which was not specifically included in the scope of the project on which bids were submitted. Increase in unit quantities stated in the proposal are not the subject matter of a Change Order unless the increase or decrease is more than 25% of the amount of the particular item or items in the original proposal. All •Change Orders" shall be prepared by the City from information _as_ necessary furnished by the Contractor. I C1-1 . 28 PAVED STREETS AND ALLEYS: A paved street or alley shall be defined as a street or alley having one of the following types of wearing surfaces applied over the natural unimproved surface: 1. Any type of asphaltic concrete with or without separate base material. 2. Any type of asphalt surface treatment , not including an oiled surface , with or without separate base material. 3. Brick, with or without separate base material. 4. Concrete, with or without separate base material. S. Any combination of the above. C1-1. 29 UNPAVED STREETS OR ALLEYS: An unpaved street, alley, roadway or other surface is any area except those defined above for "Paved Streets and Alleys." C1-1. 30 CITY STREETS: A city street is defined as that area between the r ght-of-rap lines as the street is dedicated. C1-1 . 31 ROADWAY: The roadway is defined as the area between parallel Ines two (2 • ) feet back of the curb lines or four ( 4 ' ) feet back of the average edge of pavement where no curb exists. C1-1. 32 GRAVEL STREET: A gravel street is any unpaved street to which has been added one or more applications of gravel or . similar material other than the natural material found on the street surface before any improvement was made. Cl-1 (5) SECTION C - GENERAL CONDITIONS ` C2-2 INTERPRETATION AND PREPARATION OF PROPOSAL ` SECTION C2-2 INTERPRETATION AND PREPARATION OF PROPOSAL C2-2.1 PROPOSAL FORM: The Owner will furnish bidders with proposal form,, which will contain an itemized list of the items of work to be done or materials to be furnished and upon which bid prices are requested. The Proposal form will state • the Bidder ' s general understanding of the project to be completed; -provide a space for furnishing the amount of bid security, and state the basis for entering into a formal contract. The Owner will furnish forms for the Bidder ' s 'Experience Record, ' "Equipment Schedule, " and 'Financial Statement,' all of which must be properly executed and filed with the Director of the City Water Department one week prior to the hour for opening of bids. The financial statement required shall have been prepared by an independent certified public accountant or an independent public accountant holding a valid permit issued by an appropriate state licensing agency, and shall have been to prepared as to reflect the current financial status. This stateument must be current and not more than one (l) year old. In the case that a bidding date falls within the time a new statement is being prepared, the previous statement shall be updated by proper verification. Liquid assets in the amount of ten (10% ) percent of the estimated project cost will be required. For an experience record to be considered to be acceptable for a given project, it must reflect the experience of the firm seeking qualification in work of both the same nature and magnitude as that of the project for which bids are to be received , and such experience must have been on projects completed not more than five (5) years prior to the date on which are to be received . The Director of the Water department shall be sole judge as to the acceptability of experience for qualification to bid on any Fort North Nater Department project. The prospective bidder shall schedule the equipment he has available for the project and state that he will rent such additional equipment as may be required to complete the project on which he submits a bid. C2-2. 2 INTERPRETATION OF QUANTITIESIt The quantities of work and materials to be furnished as may be listed in the proposal C2-2(1) Z forms or other parts of the Contract Documents will be considered as approximate only and will be used for the purpose of comparing bids on a uniform basis. Payment will be made to the Contractor for only the actual quantities of work performed or materials furnished in strict accordance with the Contract Documents and Plans. The quantities of work to be , performed and materials to be furnished may be increased or decreased as hereinafter provided , without in any way invalidating the unit prices bid or any other requirements of the Contract Documents. C2-2. 3 EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF PROJECT: Bidders are advised that the Contract Documents on file with the Owner shall constitute all of the information which the Owner will furnish. All additional information and data which the owner will supply after promulgation of the formal contract documents shall be issued in the form of written addenda and shall become part of the Contract Documents just1 as though such addenda were actually written into the original Contract Documents. a Bidders are required, prior to the filing of proposal, to read and become familiar with the Contract Documents, to visit the site of the project and examine carefully all local ' conditions, to inform themselves by their own independent research and investigations, tests, boring, and by such other means as may be necessary to gain a complete knowledge of the a conditions which will be encountered during the construction of the project . They must judge for themselves the difficulties of the work and all attending circumstances a affecting the cost of doing the work or the time requi;ed for its completion, and obtain all information required to make an intelligent proposal. No information given by the Owner or any representative of the Owner other than that contained in the Contract Documents and officially promulgated addenda thereto, shall be binding upon the Owner. Bidders shall rely exclusively and solely upon their own estimates , investigation, research, tests, explorations, and other data which are necessary for full and complete information upon which the proposal is to be based. It is mutually agreed that the submission of a proposal is prima-facie evidence that the T bidder has made the investigations, examinations and -tests herein required. Claims for additional compensation due to variations between conditions actually encountered in construction and as indicated in the Contract Documents will not be allowed. The logs of Soil Borings, if any, showing on the plans are for general information only and may not be correct. neither the C2-2(2) Owner nor the Engineer guarantee that the data shown is representative of conditions which actually exist. C2-2. 4 SUBMITTING OF PROPOSAL: The Bidder shall submit his Proposal on the form furnished-by the Owner. All blank spaces applicable to the project contained in the form shall be correctly filled in and the Bidder shall state the prices , written in ink in both words and numerals , for which he proposes to do the work contemplated or furnishe the materials required. All such prices shall be written legibly. In case of discrepancy between the price written in words and the price written in numerals, the price most advantageous to the City shall govern. If a proposal is submitted by an individual, his or her name must be signed by him (her) or his (her) duly authorized agent. If a proposal is submitted by a firm, association , or partnership, the name and address of each member must be given, and the proposal must be signed by a member of the firm, association , or partnership, or by a person duly authorized. If a proposal is submitted by a company or -corporation , the company or corporate name and business address must be given, and the proposal signed by an official or duly authorized agent. The corporate seal must be affixed. Power of Attorney authorizing agents or others to sign proposal must be properly certified and must be in writing and submitted with the proposal. C2-2 . 5 REJECTION OF PROPOSALS: Proposals may be rejected if they show any alteration of words or figures, additions not called for , conditional or uncalled for alternate bids , incomplete bids, erasures, or irregularities of any kind, or contain unbalance value of any items. Proposal tendered or delivered after the official time designated for receipt of proposal shall be returned to the Bidder unopened. C2-2.6 BID SECURITY: No proposal will be considered unless it is accompanied y a 'Proposal Security' of the character and in the amount indicated in the *Notice to Bidders* and the "Proposal . * The Bid Security is required by the Owner as evidence of good faith on the part of the Bidder, and by way of a guaranty that if awarded the contract, the Bidder will within the required time execute a formal contract and furnish the required performance and other bonds. The bid security of the three lowest bidders will be retained until the contract is awarded or other disposition is made thereof . The bid security of all other bidders may be returned promptly after the canvass of bids. C2-2(3) C2-2 .7 DELIVERY OF PROPOSAL: No proposal will be considered unless it is delivered , accompanied by its proper Bid Security, to the City Manager or his representative in the official place of business as set forth in the "Notice to Bidders . " It is the Bidder ' s sole responsibility to deliver the proposal at the proper time to the proper place. The more fact that a proposal was dispatched will not be considered. The Bidder must have the proposal actually delivered. Each proposal shall be in a sealed envelope plainly marked with the word "PROPOSAL," and the name or description of the project as designated in the "Notice to Bidders.• The envelope shall be addressed- to --the City Manager, City Ball, Fort Worth. Texas. C2-2 . 8 WITHDRAWING PROPOSALS: Proposals actually filed with the City Manager ca® withdrawn prior to the time set for opening proposals . A request for non-consideration of a proposal must be made in writing , addressed to the City Manager , and filed with him prior to the time set for the opening of proposals. After all proposals not requested for non-consideration are opened and publicly read aloud, the proposals for which non-consideration requests have been properly filed may, at the option of the Owner, be returned unopened. C2-2 . 9 TELEGRAPHIC MODIFICATION OF PROPOSALS: Any bidder may modify his proposal by telegraphic communication at any time prior to the time set for opening proposals, provided such telegraphic communication is received by the City Manager prior to the said proposal opening time, and provided further, that the City Manager is satisfied that a written and duly authenticated confirmation of such telegraphic communication over the signature of the bidder was &ailed prior to the proposal opening time. If such confirmation is not received within forty-eight (48) hours after the proposal opening time, no further consideration will be given to the proposal. C2-2.10 PUBLIC OPENING OF PROPOSAL: Proposals which have been properly filed and for wh c no Non-consideration Request' has been received will be publicly opened and read aloud by the City Manager or his authorised representative at the time and place indicated in the •Notice to Bidders.* All proposals which have been opened and read will remain on file with the Owner until the contract has been awarded. Bidders or their authorised representatives are invited to be present for the ' opening of bids. C2-2.11 IRREGULAR, PROPOSALSs Proposals shall be considered as being "Irregu ar• If t ey s ow any omissions, alterations of form, additions , or conditions not called for, unauthorized alternate bids, or irregularities of any kind. Bowever , the C2-2(l) Owner reserves the right to waive any and all irregularities and to make the award of the contract to the best interest of the City. Tendering a proposal after the closing hour is an irregularity which cannot be waived. C2-2 . 12 DISQUALIFICATION OF BIDDERS : Bidders may be disqualified and their proposals not considered for any of , but not limited to, the following reason: a. Reasons for believingthat collusion exists among g bidders. b._ Reasonable grounds for believing that any bidder is interested in more than one proposal for work contemplated. C. The bidder being interested in any litigation against the Owner or where the Owner may have a claim against or be engaged in litigation against the bidder. d. The bidder being in arrears on any existing contract or having defaulted on a previous contract. e. The bidder, having performed a prior contract in an unsatisfactory manner. f. Lack of competency as revealed by the financial statement, experience record, equipment schedule , and such inquiries as the Owner may see fit to make. g. Uncompleted work which , in the judgment of the Owner, will prevent or hinder the prompt completion of additional work if awarded. h. The bidder not filing with the Owner, one week in advance of the hour of the opening of proposals the following: 1. Financial Statement showing the financial condition of the bidder as specified in Part •A' - Special Instructions. 2. A current experience record showing especially the projects of a nature similar to the one under consideration , which have been successfully completed by the Bidder. 3. An equipment schedule showing the equipment the bidder has available for use on the project. The Bid proposal of a bidder who, in the judgment of the Engineer , is disqualified under the requirements stated herein, shall be set aside and not opened. C2-2(5) PART C - GENERAL CONDITIONS C3-3 AWARD AND EXECUTION OF DOCUMENTS SECTION C3-3 AWARD AND EXECUTION OF DOCUMENTS: C3-3 .1 CONSIDERATION OF PROPOSALS: After proposals have been opened and read alou , the proposals will be tabulated on the basis of the quoted prices , the quantities shown in the proposal , and the application of such formulas or other methods of bringing items to a common basis as may be established in the Contract Documents. The total obtained by taking the sum of the products of unit prices quoted and the estimated quantities plus any lump sum items and such other quoted amounts as may enter into the cost of the completed project will be considered as the amount of the bid. Until the award of the contract is made by the Owner, the right will be reserved to reject any or all proposals and waive technicalities, to re-advertise for new proposals, or to proceed with the work in any manner as maybe considered for the best interest of the Owner. C3-3 . 2 MINORITY BUSINESS ENTERPRISE IWOMEN-OWNED BUSINESS ENTERPRISE COMPLIANCE: Contractor agrees to provide to Owner , upon request , complete and accurate information regarding actual work performed by a Minority Business Enterprise (MBE) and or a a roman-owned Business Enterprise (WBE) on the contract and the payment therefor. Contractor further agrees , upon request by Owner , to allow and audit and/or an examination of any books, records, or files in the possession of Contractor that will substantiate the actual work performed by the MBE or WBE. Any material misrepresentation of any nature will be grounds for termination of the contract and for initiating any action under appropriate federal , state or local laws and ordinances relating to false statements; further , any such misrepresentation may be grounds for disqualification of Contractor at Owner's discretion for bidding on future Contracts with the Owner for a period of time of not less than six (6) months. C3-3 . 3 EQUAL EMPLOYMENT PROVISIONS: The Contractor shall comply with Current City Ordinance prohibiting discrimination in employment practices. C3-3 (1) The Contractor shall post the required notice to that effect on the project site, and, at his request, will be provided assistance by the City of Fort Worth ' s Equal Employment Officer who will refer any qualified applicant he may have on file in his office to the Contractor. Appropriate notices may be acquired from the Equal Employment Officer. C3-3 . 4 WITHDRAWAL OF PROPOSALS: After a proposal has been read y the Owner it cannot withdrawn by the Bidder within forty-five (45 ) days after the date on which the proposals were opened. C3-3 . 5 AWARD OF CONTRACT: The Owner reserves the right to withholdfi-n-a-1 action on the proposals for a reasonable time, not to exceed forty-five (45 ) days after the date of opening proposals, and in no event will an award be made until after investigations have been made as to the responsibility of the Proposed awardee. . . The award of the contract, if an award is made, will be to the lowest and best responsible bidder. The award of the contract shall not become effective until the Owner has notified the Contractor in writing of such award. C3-3 . 6 RETURN OF PROPOSAL SECURITIES: As soon as proposed price totals have en determined for comparison of bids , the Owner may, at its discretion, return the proposal security which accompanied the proposals which, in its judgment, would not be considered for the award. All other proposal securities, usually those of the three lowest bidders , will be retained by the Owner until the required contract has been executed and bond furnished or the Owner has otherwise disposed of the bids, after which they will be returned by the City Secretary. C3-3 . 7 BONDS: With the execution and delivery of the Contract Documents, the Contractor shall furnish to, and file with the Owner in the amounts herein required, the following bonds: a. PERFORMANCE BOND : A good and sufficient performance Sond in an amount not less than 100 percent of the amount of the contract, as evidenced by the proposal tabulation or otherwise , guaranteeing the full and faithful execution of the work and performance of the contract, and for the protection of the Owner and all other persons against damage by reason of negligence of the Contractor, or improper execution of the work or the use of inferior materials . This performance C3-3 (2) bond shall guarantee the payment for all labor, materials, equipment, supplies , and services used in the construction of the work, and shall remain in full force and effect until provisions as above stipulated are accomplished and final payment is - made on the project by the City. b. MAINTENANCE BOND : A good and sufficient maintenance bond, in the amount of not less than 100 percent of the amount of the contract, as evidenced by the proposal tabulation or otherwise, guaranteeing the prompt , full and faithful performance of the general guaranty which is set forth in paragraph C8-8.10. c. PAYMENT BOND: A .good and sufficient payment bond, in an amount not less than 1D0 percent of the amount of the contract , as evidenced by the ,. proposal tabulation or otherwise, guaranteeing the prompt, full and faithful payment of all claimants as defined in Article 5160, Revised Civil Statutes of Texas , 1925, as amended by House Bill 344 Acts 56th Legislature, Regular Session, 1959 , effective April 27, 1959 , and/or the latest version thereof, supplying labor and materials in the prosecution of the work provided for in the contract being constructed under these specifications. Payment Bond shall remain in force until all payments as above stipulated are made. d. OTHER BONDS: Such other bonds as may be required by these Contract Documents shall be furnished by the Contractor. No sureties will be accepted by the Owner which are at the time in default or delinquent on any bonds or which are interested in any litigation against the owner. All bonds shall be made on the forms furnished by the Owner and shall be executed by an approved surety company doing business in the City of Fort Worth, Texas, and which is acceptable to the owner . In order to be acceptable, the came of the surety shall be included on the current O. S. Treasury list of acceptable sureties, and the amount of bond written by any one acceptable company shall not exceed the amount shown on the Treasury list for that company. Each bond shall be properly executed by both the Contractor and Surety Company. Should any surety on the contract be determined unsatisfactory at any time by the Owner, notice will be given the Contractor to that effect and the Contractor shall immediately provide a C3-3 (3) new surety satisfactory to the Owner. No payment will be made under the contract until the new surety or sureties , as required, have qualified and ,have been accepted by the Owner. The contract shall not be operative nor will any payments be due or paid until approval of the bonds by the Owner. C3-3 . 8 EXECUTION OF CONTRACT: Within ten (10) days after the Owner has y appropriate Meso ution, or otherwise, awarded the contract, the Contractor shall execute and file with the Owner the Contract and such bonds as may be required in the Contract Documents. No contract shall be binding upon the owner until it has been attested by the City Secretary, approved as to form and legality by the City Attorney, and executed for the Owner by either the Mayor or City Manager, C3-3 . 9 FAILURE TO EXECUTE CONTRACT: The failure of the Awardee to execute the require bon or bonds or to sign the required contract within ten (10) days after the contract is awarded shall be considered by the Owner as an abandonment of his proposal, and the Owner may annul the Award. By reason of the uncertainty of the market prices of material and labor, and it being impracticable and difficult to accurately determine the amount of damages occuring to the Owner by reason of said awardee' s failure to execute said bonds and contract within ten (10 ) days , the proposal security accompanying the proposal shall be the agreed amount of damages which Owner will suffer by reason of such failure on the part of the Awardee and shall thereupon immediately be forfeited to the Owner. The filing of a proposal will be considered as an acceptance of this provision by the Bidder. C3-3 .10 BEGINNING WORK: The Contractor shall not commence workuntilaut orize in writing to do so by the Owner. Should the Contractor fail to commence work at the site of the project within the time stipulated in the written authorization usually termed the •Mork Order' or 'Proceed Order•, it is agreed that the Surety Company will, within ten (10 ) days after the commencement date set forth in such written authorization, commence the physical execution of the :ontract. :3-3 . 11 INSURANCE: The Contractor shall not commence work ander this contract until he has obtained all the insurance :squired under the Contract Documents, and such insurance has teen approved by the Owner. The prime Contractor shall be M -esponsible for delivering to the Owner the sub-contractors' w C3-3 (i) e certificate of insurance for approval. The prime contractor shall indicate on the certificate of insurance included in the - documents for execution whether or not his insurance covers sub-contractors. It is the intention of the Owner that the Insurance coverage required herein shall include the coverage Of all sub-contractors. a. COMPENSATION INSURANCE: The Contractor shall maintain , during the life of this contract , Workers ' Compensation Insurance on all of his employees to be engaged in work on the project under this contract, and for all sub-contractors. In case any class of employees engaged in hazardous work on the project under this contract is not protected under the Workers ' Compensation Statute, the Contractor shall provide adequate employer ' s general liability insurance for the protection of such of his employees not so protected. b. COMPREBENSIVE GENERAL LIABILITY INSURANCE: The Contractor shall procure and shall maintain during the life of this contract Contractor ' s Comprehensive General Liability Insurance (Public Liability and Property Damage Insurance) in an amount not less than $ 500 , 000 covering each occurrence on account of bodily injury, including death, and in an amount not less than $500 , 000 covering each occurrence on account of property damage with $2,000,000 umbrella policy coverage. C. ADDITIONAL LIABILITY: The Contractor shall furnish insurance as separate policies or by additional endorsement to one of the above-mentioned policies, and in the amount as set forth for public liability and property damage,, the following insurance: 1. Contingent Liability ( covers :General Contractor ' s Liability for acts of sub-contractors). 2. Blasting, prior -to any blasting being done. 3. Collapse of buildings or structures adjacent to excavation (if excavations are to be performed adjacent to same). 4. Damage to underground utilities for $500,000. C3-3 (5) S. Builder's risk (where above-around structures are involved) . 6. Contractual Liability ( covers all indemnification requirements of Contract) . - d. AUTOMOBILE INSURANCE - BODILY INJURY AND PROPERTY DAMAGES The Contractor shall procure and maintain, ua r ng the life of this Contract, Comprehensive Automobile Liability insurance in an amount not less than $ 250 , 000 for injuries including accidental death to any one person and subject to the same limit for each person an amount not less than $500 , 000 on account of one accident , and automobile property damage insurance in an amount not less than $100,000. e. SCOPE OF INSURANCE AND SPECIAL HAZARD: The insurance require under teabove paragraphs shall provide adequate protection for the Contractor and his sub-contractors, respectively, against damage claims which may arise from operations under this contract, whether such operations be by the insured or by anyone directly or indirectly employed by him, and also against any of the following special hazards which may be encountered in the performance of the Contract. f. PROOF OF CARRIAGE OF INSURANCE: The Contractor shall furnish the Owner with satisfactory proof of coverage by insurance required in these Contract Documents in amounts and by carriers satisfactory to the Owner . (Sample attached. ) A11 insurance requirements made upon the Contractor shall apply to the sub- contractor , should the Prime - Contractor ' s insurance not cover the sub-contractor's work operations. g. LOCAL AGENT FOR INSURANCE AND BONDING: The insurance and bon3ing companies w t w om the Contractor ' s insurance and performance, payment, maintenance and all such other bonds are written shall be represented by an agent or agents having an office located within the city limits of the C3-3 (6) City of Fort Worth, Tarrant County, Texas . • Each such agent shall be a duly qualified, one upon whom service of process may be had , and must have authority and power to act on behalf of the Insurance and/or bonding company to negotiate and settle with the City of Fort Worth, or any other claimant, any claims that the City of Fort Worth or - other claimant or any property owner who has been damaged , may have against the Contractor , insurance, and/or bonding company. If the local insurance representative is not so empowered by the insurance or bonding companies, then such authority must be vested in a local agent or claims officer residing in the Metroplex, the Fort Worth-Dallas area. The name of the agent or agents shall be set forth on all of such bonds and certificates of insurance. C3-3. 12 CONTRACTOR'S OBLIGATIONS: Under the Contract, the Contractor shall pay for all materials, labor and services when due. C3-3 . 13 WEEKLY PAYROLL: A certified copy of each payroll covering payment of wages to all person engaged in work on the project at the site of the project shall be furnished to the Owner's representative within seven (7 ) days after the close of each payroll period. A copy or copies of the applicable minimum wage rates as set forth in the Contract Documents shall be kept posted in a conspicuous place at the site of the project at all times during the course of the Contract. Copies of the wage rates will be furnished the Contractor, by the Owner; however, posting and protection of the wage rates shall be the responsibility of the Contractor. C3-3. 14 CONTRACTOR'S CONTRACT ADMINISTRATION: Any Contractor, whether a person , persons , partnership, company , firm , association , corporation or other who is approved to do i business with and enters into a contract with the City for construction of water and/or sanitary sewer facilities, will have or shall establish a fully operational business office within the Fort Worth-Dallas metropolitan area . The Contractor shall charge, delegate, or assign this office (or he may delegate his Project Superintendent ) with full authority to transact all business actions required in the performance of the Contract. This local authority shall be made responsible to act for the Contractor in all matters pertaining to the work governed by the Contract whether it be administrative or otherwise and as such shall be empowered, thus delegated and directed, to settle all material, labor or other expenditures, all claims against the work or any other 1 C3-3 (7) i UM matter associated such as maintaining adequate and appropriate insurance or security coverage for the project. Such local authority for administration of the work under the Contract shall be maintained until all business transactions executed �■ as part of the Contract are complete. Should the Contractor ' s principal base of operations be other than in the Fort worth-Dallas metropolitan area, notification of the Contractor ' s assignment of local authority shall be made in writing to the Engineer in advance of any work on the ■ project, all appropriately signed and sealed, as applicable, by the Contractor ' s responsible officers with the understanding that this written assignment of authority to a local representative shall become part of the project Contract as though bound directly into the project documents. The intent of these requirements is that all matters associated with the Contractor ' s administration, whether it be oriented ■ in furthering the work, or other, be governed direct by local authority. This same requirement is imposed on insurance and surety coverage. Should the Contractor's local representative Fail to perform to the satisfaction of Engineer, the Engineer, .� at his sole discretion , may demand that such local representative be replaced and the Engineer may, at his sole discretion , stop all work until a new local authority satisfactory to the Engineer is assigned . No credit of working time will be for periods in which work stoppages are in effect for this reason. ■ C3-3 . 15 VENUEs Venue of any action hereinunder shall be exclusively=n Tarrant County, Texas. ■ ■ ■ ■ ■ ■ C3-3 (8 ) ■ - PART C - GENERAL CONDITIONS w C4-4 SCOPE OF WORK SECTION C4-4 SCOPE OF WORK C4-4 . 1 INTENT OF CONTRACT DOCUMENTS: It is the definite intention Of these Contract Documents to provide for a - complete, useful project which the Contractor undertakes to construct or furnish , all in full compliance with the requirements and intent of the Contract Documents. It is definitely understood that the Contractor shall do all work as provided for in the Contract Documents, shall do all extra or Special work as may be considered by the Owner as necessary to complete the project in a satisfactory and acceptable manner. The Contractor shall, unless otherwise specifically stated in these Contract Documents, furnish all labor, tools, materials, machinery, equipment , special services , and incidentals necessary to the prosecution and completion of the project. C4-4 . 2 SPECIAL PROVISIONS: Should any work or conditions which are not thoroughly and satisfactorily stipulated or covered by General or Special Conditions of these Contract Documents be anticipated, or should there be any additional v proposed work which is not covered by these Contract Documents, then •Special Provisions" covering all such work will be prepared by the Owner previous to the time of receiving bids or proposals for such work and furnished to the Bidder in the form of Addenda. All such 'Special Provisions' shall be considered to be a part of the Contract Documents just as though they were originally written therein. C4-4 . 3 INCREASED OR DECREASEDQUANTITIES: The Owner reserves the right to alter the quantities of t e work to be performed or to extend or shorten the improvements at any time when and as found to be necessary, and the Contractor shall perform the work as altered, increased or decreased at the unit prices. Such increased or decreased quantity shall not be more than 25 percent of the contemplated quantity of such item or items. When such changes increase or decrease the original quantity of any item or items of work to be done or materials to be furnished by the 25 percent or more, then either party to the contract shall upon written request to the other party be entitled to a revised consideration upon that portion of the work above or below the 25 percent of the original quantity stated in the proposal= such revised consideration to be determined by special agreement or as hereinafter provided for "Extra Work. ' No allowance will be made for any changes in anticipated profits nor shall such changes be considered as C4-4 (1) waiving or invalidating any conditions or provisions of the Contract Documents. Variations in quantities of sanitary sewer pipes in depth categories , shall be interpreted herein as applying to the overall quantities or sanitary sewer pipe in each pipe size, but not to the various depth categories. C4-4 .4 ALTERATION OF CONTRACT DOCUMENTS: By Change Order, the Owner reserves the right to ma a such c angel in the Contract Documents and in the character or quantities of the work as may be necessary or desirable to insure completion in the most satisfactory manner, provided such changes do not materially alter the original Contract Documents or change the general nature of the project as a whole. Such changes shall not be considered as waiving or invalidating any condition or provision of the Contract Documents. C4-4 . 5 EXTRA WORK: Additional work made necessary by changes and alterations of the Contract Documents or of quantities or for other reasons for which no prices are provided in the Contract Documents, shall be defined as 'Extra Work" and shall be performed by the Contractor in accordance with these Contract Documents or approved additions thereto= provided, however, that before any extra work is begun a 'Change Order' shall be executed or written order issued by the Owner to do the work for payments or credits as shall be determined by one or more combination of the following methods: a. Unit bid price previously approved. b. hn agreed lump sum. c. The actual reasonable cost of (1) labor, (2) rental of equipment used on the extra work for the time so used at hasociated General Contractors of hmerica current equipment rental rates = ( 3 ) materials entering permanently into the project, and (4 ) actual cost of insurance , bonds , and social security as determined by the Owner, plus a fixed fee to be agreed upon but not to exceed 10% of the actual cost of such extra work. The fixed fee is not to include any additional profit to the Contractor for rental of equipment owned by him and used for the extra work. The fee shall be full and complete compensation to cover the cost of superintendence, overhead, other profit, general and all other expense not included in (1) , (2 ) , ( 3 ) , and ( 4 ) above. The Contractor shall keep accurate cost records on the form and in the method C4-4 (2) suggested by the Owner and shall give the Owner access to all accounts , bills , vouchers , and records relating to the Extra Work. No "Change Order" shall become effective until it has been IC approved and signed by each of the Contracting parties. No claim for Extra Work of any kind will be allowed unless ordered in writing by the Owner . In case any orders or instructions, either oral or written, appear to the Contractor to involve Extra Work for which he should receive compensation, he shall make written request to the Engineer for written orders authorizing such Extra Work, prior to beginning such work. Should a difference arise as to what does or does not constitute Extra Work, or as to the payment thereof, and the Engineer insists upon its performance, the Contractor shall proceed with the work after making written request for written orders and shall keep an accurate account of the actual reasonable cost thereof as provided under method ( Item C ) . Claims for extra work will not be* paid unless the Contractor shall file his claim with the Owner within five ( 5 ) days before the time for making the first estimate after such work is done and unless the claim is supported by satisfactory vouchers and certified payrolls covering all labor and materials expended upon the said Extra Work. The Contractor shall furnish the Owner such installation records of all deviations from the original Contract Documents as may be necessary to enable the Owner to prepare for permanent record a corrected set of plans showing the actual Al installation. The compensation agreed upon for 'extra work' whether or not iniitiated by a 'change order ' shall be a full, complete and ' final payment For all costs Contractor incurs as a result or relating to the change or extra work, whether said costs are known , unknown, foreseen or unforeseen at that time, including without limitation, any costs for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged work as a result or the change or extra work. r� C4-4 . 6 SCHEDULE OF OPERATIONS: Before commencing any work under this contract, the Contractor shall submit to the Owner and receive the Owner ' s approval thereof, a 'Schedule of Operations , " showing by a straight line method the date of commencing and finishing each of the major elements of the contract. There shall be also shows the estimated monthly cost of work for which estimates are to be expected. There 4 C4-4 (3 ) i shall be presented also a composite graph showing the anticipated progress of construction with the time being :lotted horizontally and the percentage of completion plotted vertically. The progress charts shall be prepared on 8-1/2" x 11" sheets and at least five black or blue line prints shall be furnished to the Owner. C4-4 . 7 PROGRESS SCHEDULES FOR WATER AND SEWER PLANT FACILITIES: Within ten ( 0 ) days prior to submission o first monthly progress payment , the Contractor shall prepare and submit to the Owner for approval six copies of the schedule. in which the Contractor proposes to carry on the work, the date of which he will start the several major activities (including procurement of materials, plans, and equipment ) and the contemplated dates for completing the same . The schedule shall be in the form of a time schedule Critical Path Method (CPM) network diagram. As 'the work progresses, the Contractor shall enter on the diagram the actual progress at the end of each partial payment period or at such intervals as directed by the Engineer. The Contractor shall also revise the schedule to reflect any adjustments in contract time approved by the Engineer. Three copies of the updated schedule shall be delivered at such intervals as directed by the Owner. As a minimum, the construction schedule shall incorporate all work elements and activities indicated in the proposal and in the technical specifications. Prior to the final drafting of the detailed construction schedule, the Contractor shall review the draft schedule with the Engineer to ensure the Contractor's understanding of the contract requirements. The following guidelines shall be adhered to in preparing the construction schedules a. Milestone dates and final project completion dates shall be developed to conform to time constraints , sequencing requirements and completion time. b. The construction process shall be divided into activities with time durations of approximately fourteen (14 ) days and construction values not to exceed $50 , 000 . Fabrication , delivery and submittal activities are exceptions to this guideline. C4-4 (4) C, Durations shall be in calendar days and normal holidays and weather conditions over the duration of the contract shall be accounted for within the duration of each activity. d. One critical path shall be shown on the construction schedule. e. Float time is defined as the amount of time between the earliest start date and the latest start date of a chain of activities of the CPM construction schedule. Float time is not for the -exc-lusive use or benefit of either the Contractor or the Owner. f. Thirty days shall be used for submittal review unless otherwise specified. The construction schedule shall as a minimum be divided into general categories as indicated in the Proposal and Technical Specifications and each general category shall be broken down into activities in enough detail to achieve activities of approximately fourteen' (14 ) days duration. For each general category, the construction schedule shall identify all trades or subcontracts whose work is represented by activities that follow the guidelines of this Section. For each of the trades or subcontracts , the construction schedule shall indicate the following procurements , construction and preacceptance activities and events in their logical sequence for equipment and materials. 1. Preparation and transmittal of submittals. 2. Submittal review periods. 3 . Shop fabrication and delivery. 4 . Erection or installation. 5. Transmittal of manufacturer ' s operation and maintenance instructions. 6. Installed equipment and materials testing. 7. Owner 's operator instruction (if applicable) . S. Final inspection. C4-4 (5) 9. Operational testing. 10. rinal inspection. If , in the opinion of the Owner , work accomplished falls behind that scheduled , the Contractor shall take such action as necessary to improve his progress. In addition, the Owner may require the Contractor to submit a revised schedule demonstrating his program and proposed plan to make up lag in scheduled progress and to insure completion of the work- -within the contract time. If the Owner finds the proposed plan not acceptable , he may require the Contractor to increase the work force, the construction plant and equipment, the number of work shifts or the overtime operations without additional cost to the Owner. railure of the Contractor to comply with these requirements shall be considered grounds for determination by the Owner that the Contractor is failing to prosecute the work with such diligence as will insure its completion within the time specified. 4 C4-4 (6) FART C - GENERAL CONDITIONS C5-5 CONTROL OF WORK AND MATERIALS .h SECTION CS-5 CONTROL OF WORK AND MATERIALS r C5-5.1 AUTHORITY OF ENGINEER: The work shall be performed to the satisfaction o the Engineer and in strict compliance with the Contract Documents. He shall decide all questions which arise as to the quality and acceptability of materials furnished , work performed, rate of progress of the work, overall sequence of the construction, interpretation of the Contract Documents, acceptable fulfillment of the contract, compensation, mutual rights between Contractor and Owner under these Contract Documents, supervision of the work, resumption of operations, and all other questions or disputes which may arise . Engineer will not be responsible for Contractor' s means , methods , techniques , sequences or procedures of construction, or the safety precaution and programs incident thereto, and he will not be responsible for Contractor ' s failure to perform the work in accordance with the contract documents. He shall determine the amount and quality of the work completed and materials furnished, and his decisions and estimates shall be final. Bis estimates in such event shall be a condition to the right of the Contractor to receive money due him under the Contract. The Owner shall have executive authority to enforce and make effective such necessary decisions and orders as the Contractor fails to carry out promptly. In the event of any dispute between the Engineer and Contractor over the decision of the Engineer on any such matters , the Engineer must, within a reasonable time, upon written request of the Contractor, render and deliver to both - the Owner and Contractor, a written decision on the matter in controversy. CS-5. 2 CONFORMITY WITB PLANS: The finished project in all cases shall conform with lines , grades , cross-sections , finish , and dimensions shown on the plans or any other requirements otherwise described in the Contract Documents . Any deviation from the approved Contract Documents required by the Engineer during construction will in all cases be determined by the Engineer and authorised by the Owner by Change Order. C5-5 (1) CS-5 . 3 COORDINATION OF CONTRACT DOCUMENTS: The Contract Documents are made up of several sections , which , taken together, are intended to describe and provide for a complete and useful project, and any requirements appearing in one of the sections is as binding as though it occurred in all sections. In case of discrepancies, figured dimension shall govern over scaled dimensions , plans shall govern over specifications, special conditions shall govern over general "onditions and standard specifications, and quantities shown on the plans shall govern over those shown in the proposal. The Contractor shall not take advantage of any apparent error or omission in the Contract Documents, and the Owner shall be permitted to make such corrections or interpretations as may be deemed necessary for the fulfillment of the intent of the Contract Documents. In the event the Contractor discovers an apparent error or discrepancy, he shall immediately call this condition to the attention of the Engineer. In the event of a conflict in the drawings, specifications, or other portions of the Contract Documents which were not reported prior to the award of Contract, the Contractor shall be deemed to have quoted the most expensive resolution of the conflict. CS-5 . 4 COOPERATION OF CONTRACTORt The Contractor will be furnished with three sets of the Contract Documents and shall have available on the site of the project at all times one set of such Contract Documents. The Contract shall give to the work the constant attention necessary to facilitate the progress thereof and shall cooperate with the Engineer, his inspector , and other Contractors in every possible way. The Contractor shall at all times have competent personnel available to the project site for proper performance of the work. The Contractor shall provide and maintain at all times at the site of the project a competent, English-speaking superintendent and an assistant who are fully authorised to act as the Contractor ' s agent on the work . Such superintendent and his assistant shall be capable of reading and understanding the Contract Documents and shall receive and fulfill instructions from the Owner, the Engineer, or his authorized representatives. Pursuant to this responsibility of the Contractor, the Contractor shall designate in writing to the project superintendent, to act as the Contractor ' s agent on the work. Such assistant project superintendent shall be a resident of Tarrant County, Texas and shall be subject to call, as is the project Superintendent, at any time of the day or night on any day of• the week on which the Engineer determines that circumstances require the presence on the project site of a representative of the Contractor to CS-S (2) adequately provide for the safety or convenience of the traveling public or the owners of property across which the project extends or the safety of property contiguous to the project routing. The Contractor shall provide all facilities to enable the Engineer and his inspector to examine and inspect the p workmanship and materials entering into the work. CS-5 . 5 EMERGENCY AND/OR RECTIFICATION WORK: When, in the opinion of the Owner or Engineer, a condition of emergency exists related to any part of the work, the Contractor, or the Contractor through his designated representative , shall respond with dispatch to a verbal request made by the Owner or Engineer to alleviate the emergency condition . Such a response shall occur day or night, whether the project is scheduled on a calendar-day or on a working-day basis. Should the Contractor fail to respond to a request from the Engineer to rectify any discrepancies , omissions , or corrections necessary to conform with the requirements of the project specifications or plans, the Engineer shall give the Contractor written notice that such work or changes are to be performed. The written notice shall direct attention to the discrepant condition and request the Contractor to take remedial action to correct the condition. In the event the Contractor does not take positive steps to fulfill this written request, or does not show just cause for not taking the proper action, within 24 hours, the City may take such remedial action with City forces or by contract. The City shall then deduct an amount equal to the entire costs for such remedial action, plus 25% . from any funds due the Contractor on the project. CS-5 . 6 FIELD OFFICE: The Contractor shall provide, at no extra compensation, an adequate field office for use of the Engineer, if specifically called for. The field office shall be not less than 10 by 14 feet in floor area, substantially constructed,, well heated, air conditioned , lighted, and weather-proof, so that documents will not be damaged by the elements. AP CS-5 .7 CONSTRUCTION STAKES: The City, through its Engineer, will furnish the Contractor with all lines , grades , and - measurements necessary to the proper prosecution and control of the work contracted for under these Contract Documents, and lines , grades and measurements will be established by means of stakes or other customary method of marking as may be found consistent with good practice. C5-5 (3) These stakes or markings shall be set sufficiently in advance of construction operations to avoid delay. Such stakes or markings as may be established for the Contractor ' s use or guidance shall be preserved by the Contractor until he is authorized by the Engineer to remove them. Whenever, in the opinion of the Engineer, any stakes or markings have been carelessly or willfully destroyed, disturbed, or removed by the Contractor or any of his employees , the full cost of replacing such stakes or marks plus 254 will be charged against the--Contractor, and the full amount will be deducted from payment due the Contractor. CS-5 . 8 AUTHORITY AND DUTIES OF CITY INSPECTORS : City Inspectors will Fe authorized to -inspect all work one and to be done and all materials furnished. Such inspection may extend to all or any part of the work, and the preparation or manufacturing of the materials to be used or equipment to be installed. A City Inspector may be stationed on the work to report to the Engineer as to the progress of the work and the manner in which it is being performed, to report any evidence that the materials being furnished or the work being performed by the Contractor fails to fulfill the requirements of the Contract Documents , and to call the attention of the Contractor to any such failure or other infringements . Such inspection or lack of inspection will not relieve the Contractor from any obligation to perform the work in accordance with the requirements of the Contract Documents. In case of any dispute arising between the Contractor and the City Inspector as to the materials or equipment furnished or the manner of performing the work, the City Inspector will have authority to reject materials or equipment to suspend work until the question at issue can be referred to and be decided by the Engineer. The City Inspector will not, however, be authorised to revoke, alter, enlarge, or release any requirement of these Contract Documents, nor to approve or accept any portion or section of the work, nor to issue any instructions contrary to the requirements of * the Contract Documents. He will in no case act as superintendent or f oreman or ,perform any other duties for the Contractor, or interfere with the management or operation of the work. Be will not accept from the Contractor any compensation in any form for performing any duties. The Contractor shall regard and obey the directions and instructions of the City Inspector or Engineer when the same are consistent with the obligations of the Contract Documents, provided, however, should the Contractor object to any orders or instructions of the City Inspector, the Contractor may within six days make written appeal to the Engineer for his decision on the matter in controversy. CS-S (4) CS-S. 9 INSPECTION: The Contractor shall furnish the Engineer with every reasonable facility for ascertaining whether or not the work as performed is in accordance with the requirements of the Contract Documents. If• the Engineer so requests, the r Contractor shall , at any time before acceptance of the work, remove or uncover such portion of the finished work as may be directed. After examination, the Contractor shall restore .. said portions of the work to the standard required by the • Contract Documents. Should the work exposed or examined prove acceptable, the uncovering- or removing and replacing of the covering or making good of the parts removed shall be paid for as extra work, but should be work so exposed or examined prove to be unacceptable, the uncovering or removing and the replacing of all adjacent defective or damaged parts shall be at the Contractor 's expense. No work shall be done or materials used without suitable supervision or inspection. C5-5. 10 REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK: All work, materials, or equipment which has been refected shall be remedied or removed and replaced in an acceptable manner by the Contractor at his own expense. Work done beyond the lines and grades given or as shown on the plans, except as herein specifically provided, or 'any Extra work done without written authority, will be considered as unauthorised and done at the expense of the Contractor and will not be paid f or by the Owner . work so done may be ordered removed at the Contractor 's expense. Upon the failure on the part of the Contractor to comply with any order of the Engineer made under the provisions of this paragraph, the Engineer will have the authority to cause defective work to be remedied or removed and replaced and unauthorised work to be removed, and the cost thereof may be deducted from any money due or to become due to the Contractor. Failure to require the removal of any defective or unauthorised work shall not constitute acceptance of such works. CS - 5 . 11 SUBSTITUTE MATERIALS OR EQUIPMENT : If the Specifications, law, ordinance, codas or regu at ons permit Contractor to furnish or use a substitute that is equal to any material or equipment specified, and if Contractor wishes to furnish or use a proposed substitute, be shall, prior to the preconstruction conference , make written application to ENGINEER for approval of such substitute certifying in writing that the proposed substitute will perform adequately the functions called for by the general design, be similar and of equal substance to that specified and be suited to the same use and capable of performing the same function as that specified= and identifying all variations of the proposed C5-5 (5) :substitute from that specified and indicating available maintenance service . No substitute shall be ordered or installed without the written .approval of Engineer who will be the judge of the equality and may require Contractor to furnish such other data about the proposed substitute as he considers pertinent. No substitute shall be ordered or installed without such performance guarantee and bonds as Owner may require which shall be furnished at Contractor ' s •expense. Contractor shall indemnify and hold harmless Owner and Engineer and anyone directly or indirectly employed by either of them from and against the claims , damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. CS-5. 12 SAMPLES AND TESTS OR MATERIALS: Where# in the opinion R the Engineer, or as called or n the Contract Documents , tests of materials or equipment are necessary, such tests will be made at the expense of and paid for direct to the testing agency by the Owner unless otherwise specifically provided. :he failure of the Owner to make any tests of materials shall De in no way relieve the Contractor of his responsibility of " furnishing materials and equipment fully conforming to the requirements of the Contract Documents. Tests and sampling of materials , unless otherwise specified, will be made in accordance with the latest methods prescribed by the American Society for Testing Materials or specific requirements of the Owner. The Contractor shall provide such facilities as the Engineer may require for collecting and forwarding samples and shall not , without specific written permission of the Engineer, use the materials represented by the samples until tests have been made and the materials approved for use. The Contractor will furnish adequate samples without charge to the Owner. In case of concrete, the aggregates, design minimum, and the mixing and transporting equipment shall be approved by the Engineer before any concrete is placed, and the Contactor shall be responsible for replacing any concrete which does not meet the requirements of the Contract Documents. Tests shall be made at least 9 days prior to the placing of concrete, using samples from the same aggregate, cement, and mortar which are to be used later in the concrete. Should the source of supply change, new tests shall be made prior to the use of the new materials. - CS-5. 13 STORAGE OF MATERIALS: All materials which are to be used in the construction operation shall be stored so as to insure the preservation of the quality and fitness of the work. When directed by the Engineer, they shall be placed on wooden platforms or other hard, clean durable surfaces and not on the C5-5 (6) A ground, and shall be placed under cover When directed. Stored ■ materials shall be placed and located so as to facilitate prompt inspection. ■ CS-5.14 EXISTING STRUCTURES AND UTILITIES: The location and dimensions shown on the Plans relative to existing utilities are based on the best information available. Omission from, or the inclusion of utility locations on the Plans is not to be ■ considered as the nonexistence of, or a definite location of, existing underground utilities. The location of many gas mains , water mains, conduits, sewer lines and service lines ■ for all utilities , etc. , is unknown to the Owner , and the , Owner assumes no responsibility for failure to show any or all such structures and utilities on the plans or to show them in their exact location. It is mutually agreed that such failure ' will not be considered sufficient basis for claims for additional compensation for Extra Mork or for increasing the pay quantities in any manner whatsoever, unless an obstruction encountered is such as to necessitate changes in the lines and : grades of considerable magnitude or requires the building of special works, provision for which is not made in the Contract Documents , in which case the provision in these Contract Documents for Extra Mork shall apply. It shall be the Contractors responsibility to verify locations of adjacent and/or conflicting utilities sufficiently in advance of construction in order that he may negotiate such local adjustments as necessary in the construction process to provide adequate clearances. The Contractor shall take all necessary precautions in order to protect all existing utilities , structures and service lines. Verification of existing utilities, structures and service lines shall include ' notification of all utility companies at least forty eight (46) hours in advance of construction including exploratory excavation if necessary. All verification of existing utilities and their adjustment shall be considered as subsidiary work. CS-5.15 INTERRUPTION OF SERVICE: a. Normal Prosecution: In the normal prosectuion of work where the interruption of service is necessary, the Contractor, at least 24 hours in advance, shall be required to: 1. Notify the slater Department' s Distribution m Division as to location, time, and schedule of service interruption. CS-5 (7) 2. Notify each customer personally through responsible personnel as to time and schedule of the interruption of their service, or 3. In the event that personal notification of a customer cannot be made, a prepared tag form shall be attached to the customer ' s entrance door knob . The tag shall be durable in composition, and in large bold type shall say: •NOTICE" Due to Utility Improvement in your neighborhood, your (water) (sewer) service will be inter- rupted on between the hours of a a _. This inconvenience will be as short as possible. Thank you, Contractor ess Phone b. Emer enc : In the event that an unforeseen service Interruption occurs, notice shall be as above,but immediate. CS-5.16 MUTUAL RESPONSIBILITY OF CONTRACTORS: If , through acts or neglect on the part of the Contractor , any other Contractor or 'any sub-contractor shall suffer loss or damage on the work, the Contractor agrees to settle with such other Contractor or sub-contractor by agreement or arbitration. It such other Contractor or sub-contractor shall assert any claim against the Owner on account of any damage alleged to have been sustained, the Owner will notify the Contractor , who shall indemnify and save harmless the Owner against any such claim. . CS-5 . 17 CLEAN-UPs Clean-up of surplus and/or waste materials accumulated on t e job site during the prosecution of the work under these Contract Documents shall be accomplished in keeping with a daily routine established to the the satisfaction of the Engineer . Twenty-fours fours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the Engineer , if the Contractor fails to correct the CS-5 (8) unsatisfactory procedure, the City may take such direct action as the Engineer deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice, and the costs of such direct action , plus 25% of such costs , shall be deducted from monies due or to become due to the Contractor. Upon the completion of the project as a whole as covered by these Contract Documents, and before final acceptance and final payment will be made, the Contractor shall clean and remove from-the site of the project all surplus and discarded materials , temporary structures, and debris of every kind. He shall leave the site of all work in a neat and orderly condition equal to that which originally existed. Surplus and waste materials removed from the site of the work shall be disposed of at locations satisfactory to the Engineer. The Contractor shall thoroughly clean all equipment and materials installed by him and shall deliver over such materials and equipment in a bright, clean , polished and new appearing condition . No extra compensation will be made to the Contractor for any clean-up required on the project. C5-5 . 16 FINAL INSPECTION: Whenever the work provided for in and contemplate un er the Contract Documents has been satisfactorily completed and final cleanup performed, the Engineer will notify the proper officials of the Owner and request that the Final inspection be made. Such inspection will be made within 10 days after such notification. After such final inspection, if the work and materials and equipment are found satisfactory, the Contractor will be notified in writing of the acceptance of the same after the proper resolution has been passed by the City Council . No time charge will be made against the Contractor between said date of notification of the Engineer and the date of final inspection of the work. C5-5 (9) PART C - GENERAL CONDITIONS C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY SECTION C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY C6-6.1 LAWS TO BE OBSERVED: The Contractor shall at all times observe and comply with all Federal and State Laws and City ordinances and regulations which in any way affect the conduct' of the work or his operations, and shall observe and comply with all orders, laws, ordinances and regulations which exist or which -may be enacted later by bodies having jurisdiction or authority for such enactment. No plea of misunderstanding or ignorance thereof will be considered. The Contractor and his Sureties shall indemnify and save harmless the City and all of its officers, agents, and employees against any and all claims or liability arising from or based on the violation of any such law, ordinance, regulation, or order, whether it be by himself or his employees. C6-6. 2 PERMITS AND LICENSES: The Contractor shall procure all permits and licenses, pay all charges, costs and fees, and give all notices necessary and incident to the due and lawful prosecution of the work. C6-6 . 3 PATENTED DEVICES MATERIALS AND PROCESSES: If the Contractor is required or desires to use any design, device, material, or process covered by letter, patent, or copyright, he shall provide for such use by suitable legal agreement with the patentee or owner of such patent, letter, or copyrighted design. It is mutually agreed and understood that without P exception the contract prices shall include all royalties or cost arising from patents, trade-marks, and copy rights in any way involved in the work. The Contractor and his sureties shall indemnify and save harmless the owner from any and all claims for infringement by reason of the use of any such patented design , device , material or process , or any trade-mark or copy right in connection with the work agreed to be performed under these Contract Documents , and shall indemnify the Owner for any cost, expense, or damage which it may be obliged to pay by reason of such infringement at any F time during the prosecution of the work or after completion of the work, provided, however, that 'the Owner will assume the responsibility to defend any and all suits brought for the infringement of any patent claimed to be infringed upon by- the design , type of construction or material or equipment specified in the Contract Documents furnished the Contractor by the Owner, and to hold the Contractor harmless on account of such suits. : C6-6 (1) C6-6 . + SANITARY PROVISIONS: The Contractor shall establish and enforce among his emp ogees such regulations in regard to cleanliness and disposal of garbage and waste as will tend to prevent the inception and spread of infectious or contagious diseases and to effectively prevent the creation of a nuisance about the work on any property either public or private, and such regulations as are required by Law shall be put into immediate force and effect by the Contractor. The necessary sanitary conveniences for use of laborers on the work, properly secluded from public observation , shall be constructed and maintained by the Contractor and their use shall be strictly enforced by the Contractor . All such facilities shall be kept in a clean and sanitary condition, free from objectionable odors so as not to cause a nuisance. All sanitary laws and regulations of the State of Texas and the City shall be strictly complied with. C6-6 . 5 PUBLIC SAFETY AND CONVENIENCE: Materials or equipment stored about the work shall be so placed and used, and the work shall at all times be so conducted, as to cause no greater obstruction or inconvenience to the public than is considered to be absolutely necessary by the Engineer. The Contractor is required to maintain at all times all phases of his work in such a manner as not to impair the safety or convenience of the public, including, but not limited to, safe and convenient ingress and egress to property contiguous to the work area. The Contractor shall make adequate provisions to render reasonable ingress and egress for normal vehicular traffic, except during actual trenching or pipe installation operations, at all driveway crossings. Such provisions may include bridging, placement of crushed stone or gravel or such other means of providing proper ingress and egress for the property served by the driveway as the Engineer may approve as appropriate. Such other means may include the diversion of driveway traffic, with specific approval by the Engineer. If diversion of traffic is approved by the Engineer at any ! location, the Contractor shall make arrangements satisfactory to the Engineer at any location, the Contractor shall make arrangements satisfactory to the Engineer for the diversion of traffic, and shall, at his own expense, provide all materials and perform all work necessary for the construction and maintenance of roadways and bridges for such diversion of traffic. Sidewalks must not be obstructed except by special permission of the Engineer. The materials excavated and the construction materials such as pipe used in the construction of the work shall be placed so as not to endanger the work or prevent free access to all f ire hydrants, fire alarm boxes, police call boxes, water valves , C6-6 (2) R gas valves , or manholes in the vicinity. The Owner reserves the right to remedy any neglect on the part of the Contractor as regards to public convenience and safety which may come to its attention, after twenty-four hours notice in writing to the Contractor, save in cases of emergency when it shall have the right to remedy any neglect without notice, and in either case, the cost of such work done or materials furnished by the Owner or by the City shall be deducted from monies due or to become due to the Contractor. The Contractor, after approval of the Engineer, shall notify the Fire Department Headquarters, Traffic Engineer, and Police Department-, when any street or alley is requested to be closed or obstructed or any fire hydrant is to be made inaccessible, and, when so directed by the Engineer, shall keep any street, J streets, or highways in condition for unobstructed use by fire apparatus . The Contractor shall promptly notify the Fire Department Headquarters when all such obstructed streets , alleys, or hydrants are again placed back in service. Where the Contractor is required to construct temporary bridges or make other arrangements for crossing over ditches or streams , his responsibility for accidents in connection with such crossings shall include the roadway approaches as well as the structures of such crossings. ti The Contractor shall at all times conduct his operation and the use of construction machinery so as not to damage or destroy trees and shrubs located in close proximity to or on ' the site of the work. Wherever any such damage may be done , the Contractor shall immediately satisfy all claims of property owners, and no payment will be made by the Owner in I settlement of such claims. The Contractor shall file with the Engineer a written statement showing all such claims adjusted. C6-6 . 6 PRIVILEGES OF CONTRACTOR IN STREETS ALLEYS A4�D RIGHT-OF-WAY: For the performance of the contract , the Contractor will be permitted to use and occupy such portions of the public streets and alleys, or other public places or other rights-of-way as provided for in the ordinances of the City, as shown in the Contract Documents , or as may be specifically authorised in writing by the Engineer. A reasonable amount of tools, materials , and equipment for construction purposes may be stored in such space, but no more than is necessary to avoid delay in the construction operations. Excavated and waste materials shall be piled or stacked in such a way as not to interfere with the use of spaces that may be designated to be left free and unobstructed and so as not to inconvenience occupants of adjacent property. If the street is occupied by railway tracks, the work shall be C6-6 (3) r carried on in such manner as not to interfere with the ' operation of trains, loading or unloading of carat etc. Other contractors of the Owner may, ,for all purposes required by the contract , enter upon the work and premises used by the Contractor and shall be provided all reasonable facilities and assistance for the completion of adjoining work . Any additional grounds desired by the Contractor for his use shall be provided by him at his own cost and expense. C6-6.7 RAILWAY CROSSINGSr When the work encroaches upon any right-of-way -of any railway, the City will secure the necessary easement for the work. inhere the railway tracks are to be crossed , the Contractor shall observe all the regulations and instructions of the railway company as to the methods of performing the work and take all precautions for safety of property and the public. Negotiations with the railway companies for permits shall be done by and through the City. The Contractor shall give the City notice not less than f ive days prior to the time of his intentions to begin Mork on that portion of the project which is related to the railway properties . The Contractor will not be given extra or additional compensation for such railway crossings unless specifically set forth in the Contract Documents. C6-6 . 8 BARRICADES WARNINGS AND WATCHMEN: Where the work is carried on in or adjacent to any street, alley, or public place, the Contractor shall at his own expense furnish, erect, and maintain such barricades , fences , lights and danger signals, shall provide such watchmen, and shall take all such other precautionary measures for the protection of persons or property and of the work as are necessary. Barricades and fences shall be painted in a color that will be visible at night. Prom sunset to sunrise the Contractor shall furnish and maintain at least one easily visible burning light at each barricade. A sufficient number of barricades shall be erected and maintained to keep pedestrians away from, and vehicles from being driven on or into, any work under construction or being maintained. The Contractor shall furnish watchmen and keep them at their respective assignments in sufficient numbers to protect the work and prevent accident or damage. All installations and procedures shall be consistent with the provisions set forth in the •1980 Texas Manual on Uniform Traffic Control Devices for Streets and Highways• issued under the authority of the •State of Texas Uniform Act Regulating Tiaff is on Highways• , codified as Article 6701d Veron's Civil Statutes, pertinent sections being Section Nos. 27, 29 , 30 and 31. C6-6 (4) r The Contractor will not remove any regulatory sign , instructional sign, street -name sign, or other sign which has been erected by the City. If it is determined that a sign must be removed to permit iequired construction , the Contractor shall contact the Transportation and Public Works department , Signs and Markings Division ( phone number 8780-8075 ) , to remove the sign. In the case of regulatory signs, the Contractor must replace the permanent sign with a temporary sign meeting the requirements of the above referenced manual and such temporary sign must be installed prior to the removal of the permanent sign. If the temporary sign is not installed correctly or if it does not meet the required -specifications, the permanent sign shall be left in Place until the temporary sign requirements are met. When construction work is completed to the extent that the permanent 'sign can be re-installed, the Contractor shall again contact the Signs and Markings Division to re-install the permanent sign and shall leave his temporary sign in place until such re-installation is completed. The Contractor will be held responsible for all damage to the work or the public due to failure of barricades , signs , fences , lights , or watchmen to protect them. Whenever evidence is found of such damage to the work the Engineer may order the damaged portion immediately removed and replaced by the Contractor at the Contractor ' s own expense . The Contractor 's responsibility for the maintenance of barricades, signs, fences and lights, and for providing watchmen shall not cease until the project shall have been completed and accepted by the owner. No compensation , except as specifically provided in these Contract Documents, will be paid to the Contractor for the work and materials involved in the constructing, providing, and maintaining of barricades, signs , fences, and lights or for salaries of watchmen, for the subsequent removal and disposal of such barricades , signs , or for any other ! incidentals necessary for the proper protection, safety, and convenience of the public during the contract period, as this work is considered to be subsidiary to the several items for which unit or lump sum prices are requested in the Proposal. C6-6 . 9 USE OF EXPLOSIVES DROP WEIGHT, ETC. : Should the Contractor elect to use explosives, drop weight, etc. , in the prosecution of the work, the utmost care shall be exercised at all times so as not to endanger life or property. The * Contractor shall notify the proper representative of any public service corporation, any company, individual , or utility, and the Owner, not less than twenty-four hours in I C6-6 (5) i r r. advance of the use of any activity which might damage or endanger their or his property along or adjacent to the work. Where the use of explosives is to. be permitted on the project, as specified in the Special Contract Documents , or the use of explosives is requested, the Contractor shall submit notice to the Engineer in writing twenty-four hours prior to commencing and shall furnish evidence that he has insurance coverage to protect against any damages and/or injuries arising out of such use of explosives. - All claims arising out of the use of explosives shall be investigated and a written report made by the Contractor ' s insurers to the Engineer within ten (10) days after receipt of written notice of the claim to the Contractor from either the City or the claimant. The City shall proceed to give notice to the Contractor of any such claim. The use of explosives may be suspended by the Engineer if any complaint is received and such use shall not be resumed until the cause of the complaint has been addressed. Whenever explosives are stored or kept, they shall be stored in a safe and secure manner and all storage places shall be plainly marked •DARGEROUS EXPLOSIVES• and shall be under the care of a competent watchman at all times. All. vehicles in which explosives are being transported shall be plainly marked as mentioned above and shall, insofar as possible, not use heavy traffic routes. Cf-6. 10 WORK wITHIw EASEMENTS: where the work passes over, through, or into private property, the Owner will provide such sight-of-way or easement privileges as the City may deem necessary for the prosecution of the work. Any additional - rights-of-way or work area considered necessary by the Contractor shall be provided by him at his own expense. Such additional rights-of-way or work area shall be acquired for the benefit of the City. The City shall be notified in writing as to the rights so acquired before work begins in the affected area. The Contractor shall not enter upon private property for any purpose without having previously obtained permission from the owner of such property. The Contractor will not be allowed to store equipment or material on private property unless and until the specified approval of the property owner has been secured in writing by the Contractor and a copy furnished to the Engineer. Unless specifically provided otherwise , the Contractor shall clear all rights-of-way or easements of obstructions which must be removed to make possible proper prosecution of the work as a part of the project construction operations. The Contractor shall be responsible for the preservation of and shall use C6-6 (6) every precaution to prevent damage to all trees , shrubbery, plants, lawns, fences, culverts, curbing , and all other types of structures or improvements, to all water , sewer, and gas lines, to all conduits, overhead pole lines , or appurtenances thereof, including the construction of temporary fences, and to all other public or private property along adjacent to the work. The Contractor shall notify the proper representatives of owners or occupants of public or private lands or interest in lands which might be affected by the work. Such notice shall be made at-least 48 hours in advance of the beginning of the work. Notices shall be applicable to both public and private utility companies or any corporation, company, individual, or other, either as owners or occupants, whose land or interest in land might affected by the work. The Contractor shall be responsible for all damage or injury to property of any character resulting from any act, omission , neglect, or misconduct in the manner or method or execution of the work, or at any time due to defective work, material, or equipment. When and where any direct or indirect or injury is done to public or privata property on account of any act, omission, neglect, or misconduct in the execution of the work, or in consequence of the non-execution thereof on the part of the Contractor, be shall restore or have restored at his own cost and expense such property to a condition at least equal to that existing before such damage or injury was done, by repairing, rebuilding, or otherwise replacing and restoring as may be directed by the Owner, or he shall make good such damages or injury in a manner acceptable to the owner of the property and the Engineer. All fences encountered and removed during construction of this project shall be restored to the original or a better than original condition upon completion of this project. When wire fencing, either wire mesh or barbed wire is to be crossed, the Contractor shall set cross braced posts on either side of permanent easement before the fence is cut. Should additional fence cuts be necessary, the Contractor shall provide cross braced posts at point of the proposed cut in addition to the cross braced posts provided at the permanent easements limits, before the fence is cut. Temporary fencing shall be erected in place of the fencing removed whenever the work is not in progress and when the site is vacated overnight, and/or at all times to prevent livestock from entering the construction area. The cost for fence removal, temporary closures and replacement shall be subsidiary to the various items bid in the project C6-6 (7) proposal. Therefore, no separate payment shall be allowed for any service associated with this work. In case of failure on the part of the Contractor to restore such property to make good such damage or injury, the Owner may, upon 48 hour written notice under ordinary circumstances, and without notice when a nuisance or hazardous condition results , proceed to repair, rebuild, or otherwise restore such property as may be determined by the Owner to be necessary, and the cost thereby will be deducted from° any monies due or to become due to the Contractor under' this Contract. C6-6.11 INDEPENDENT CONTRACTOR: It is understood and agreed y the parties hereto that Contractor shall perform all work and services hereunder as an independent contractor, and not as an officer , agent, servant or employee of the Owner . Contractor shall have exclusive control of and the exclusive right to control the details of all the work and services performed hereunder, and all persons performing same, and shall be solely responsible for the acts and omissions of its officers , agents , servants , employees , contractors , subcontractors, licensees and invitees . The doctrine of respondeat superior shall not apply as between Owner and Contractor, its officers , agents, employees, contractors and subcontractors , and nothing herein shall be construed as creating a partnership or joint enterprise between Owner and Contractor. C6-6 . 12 CONTRACTOR ' S RESPONSIBILITY FOR DAMAGE CLAIMS : Contractor covenants and agrees to, and does hereby indemni y, hold harmless and defend Owner, its officers , agents , servants, and employees from and against any an all claims or suits for property damage or loss and/or personal injury, including death, to any and all persons, of whatsoever kind or character , whether real or asserted, arising out of or in connection with, directly or indirectly, the work and services to be performed hereunder by Contractor, its officers, agents, employees, contractors, subcontractors, licensees or invitees , whether or not caused, in whole or in part, by alleged negligence on the part of officers , agents , servants # employees, contractors, subcontractors, licensees and invitees of the Owner; and said Contractor does hereby covenant and agree to assume all liability and responsibility of Owner, its officers agents, servants and employees for property damage or loss , and/or personal injuries, including death, to any and all persons of whatsoever kind or character, whether real or asserted, arising out of or in connection with, directly or indirectly, the work and services to be performed hereunder by Contractor , its officers , agents employees, contractors , subcontractors, licensees and invitees, whether or not caused, C6-6 (8) ON As in whole or in part , by alleged negligence of officers , dagents , servants, employees, contractors, subcontractors , 'licensees or invitees of the Owner. Contractor likewise covenants and agrees to, and does hereby, indemnify and hold harmless Owner from and against any and all injuries,loss or damages to property of the Owner during the performance of any Of the terms and conditions of this Contract, whether arising out of or in connection with or resulting from, in whole or in part, any and all alleged acts or omissions of officers , agents, servants , employees, contractors, subcontractors , licenses, or invitees of the Owner. In the -event a written claim for damages against the contractor or its subcontractors remains unsettled at the time all work on the project has been completed to the satisfaction of the Director of the Water Department, as evidenced by a final inspection, final payment to the Contractor shall not be recommended by the Director of the Water Department for a period of 30 days after the date of such final inspection, unless the Contractor shall submit written evidence satisfactory to the Director that the claim has been settled and a release has been obtained from the claimant involved. If the claim concerned remains unsettled as of the expiration of the above 30-day period, the Contractor may be deemed to be entitled to a semi-final payment for work completed, such semi-final payment to be in an amount equal to the total dollar amount then due less the dollar value of any written -� claims pending against the Contractor arising out of the performance of such work, and such semi-final payment may then be recommended by the Director. The Director shall not recommend final payment to a Contractor against whom such a claim for damages is outstanding for a period of six months following the date of the acceptance of the work performed unless the Contractor submits evidence in writing satisfactory to the Director that: 1. The claim has been settled and a release has been obtained from the claimant involved, or 2. Good faith efforts have been made to settle such outstanding claims, and such good faith efforts have failed. If condition (1) above is met at any time within the six month period, the Director shall recommend that the final payment to the Contractor be made. If condition (2) above is met at any time within the six month period, the Director may recommend that the final payment to the Contractor be made. At the C6-6 (9) expiration of the six month period the Director may recommend that final payment be made if all other work has been Performed and all other obligations of the Contractor have been met to the satisfaction of the Director. The Director may, if he deems it appropriate, refuse to accept bids on other Water Department Contract work from a Contractor against whom a claim for damages is outstanding as a result of work performed under a City contract. C6-6 .13 CONTRACTOR'S CLAIM FOR DAMAGES: Should the Contractor claim compensation or any alleged Namage by reason of the acts or omissions of the Owner, he shall within three days after the actual sustaining of such alleged damage, make a written statement to the Engineer, setting out in detail the nature of the alleged damage, and on or before the 25th day of the month succeeding that in which any such damage is claimed to have been sustained, the Contractor shall file with the Engineer an itemised statement of the details and amount of such alleged damage and, upon request, shall give the Engineer access to all books of account, receipts, vouchers, bills of lading, and other books or papers containing any evidence as to the amount of such alleged damage. Unless such statements shall be filed as hereinabove required, the Contractor' s claim for compensation shall be waived, and he shall not be entitled to payment on account of such damages. C6-6 . 14 ADJUSTMENT OR RELOCATION OF PUBLIC UTILITIES ETC. : In case it is necessary to change, move, or a ter in any manner the property of a public utility or others, the said property shall not be moved or interfered with until orders r thereupon have been issued by the Engineer. The right is reserved to the owners of public utilities to enter the geographical limits of the Contract for the purpose of making such changes or repairs to their property that may be necessary by the performance of this contract. C6-6 . 15 TEMPORARY SEWER AND DRAIN CONNECTIONS: When existing - sewer lines have to be taken up or removed, the Contractor shall , at his own expense and cost, provide and maintain temporary outlets and connections for all private or public drains and sewers. The Contractor shall also take care of all sewage and drainage which will be received from these drains and sewers , and for this purpose he shall provide and maintain, at his own cost and expense, adequate pumping facilities and temporary outlets or diversions. The Contractor, at his own cost and expense, shall construct - such troughs, pipes, or other structures necessary, and be prepared at all times to dispose of drainage and sewage C6-6 (10) received from these temporary connections until such *times as s the permanent connections are built and are in service. The existing sewers and connections shall be kept in service and maintained under the Contract , except when specified or ordered to be abandoned by the Engineer. All water, sewage, and other waste shall be disposed of in a satisfactory manner so that no nuisance is created and so that the work under construction will be adequately protected. ■ ' C6-6.16 ARRANGEMENT AND CHARGES FOR WATER FURNISHED BY THE CITY-: When the Contractor desires to use City water in connection with any construction work, he shall make complete and satisfactory arrangements with the Fort Worth City Water Department for so doing. i City water furnished to the Contractor shall be delivered to the Contractor from a connection on an existing City main . All piping required beyond the point of delivery shall be installed by the Contractor at his own expense. The Contractor 's responsibility in the use of all existing fire hydrant and/or valves is detailed in Section E2-1.2 USE OF FIRE HYDRANTS AND VALVES in these General Contract Documents. I When meters are used to measure the water, the charges, if any, for water will be at the regular established rates. When meters are not used , the charges , if any , will be as I prescribed by the City Ordinance , or where no ordinance applies , payment shall be made on estimates and rates established by the Director of the Fort Worth Water Department. C6-6.17 USE OF A SECTION OR PORTION OF THE WORK: Whenever, in the opinion of the Engineer, any section or portion of the work or any structure is in suitable condition, it may be put into use upon the written order of the Engineer , and such usage shall not be held to be in any way an acceptance of said work or structure or any part thereof or as a waiver of any of - the provisions of these Contract Documents. All necessary repairs and removals of any section of the work so put into use, due to defective materials or workmanship, equipment, or to deficient operations on the part of the Contractor, shall be performed by the Contractor at his own expense. C6-6 . 18 CONTRACTOR ' S RESPONSIBILITY FOR THE WORK: Until written acceptance by the Owner as provided or in these Contract Documents, the work shall be under the charge and care of the Contractor, and he shall take every necessary precaution to prevent injury or damage to the work or any part C6-6 (11) thereof by action of the elements or from any cause whatsoever, whether arising from the execution or nonexecution of the work. The Contractor shall rebuild, repair, restore, and make good at his own expense all injuries or damage to any portion of the work occasioned by any of the hereinabove causes. C6-6. 19 NO WAIVER OF LEGAL RIGHTS: Inspection by the Engineer or any order by the Owner by payment of money or any payment for or acceptance of any work, or Any extension of time, or any possession taken by the City shall not operate as a waiver of any provision of the Contract Documents. Xny waiver of any breach or Contract shall not be held to be a waiver of any other or subsequent breach. The Owner reserves the right to correct any error that may be discovered in any estimate that may have been paid and to adjust the same to meet the requirements of the Contract Documents. C6-6. 20 PERSONAL LIABILITY OF PUBLIC OFFICIALS: In carrying But the provisions of these Contract Documents or in exercising any power of authority granted thereunder, there shall be no liability upon the authorized representatives of the Owner, either personally or otherwise as they are agents and representatives of the City. C6-6. 21 STATE SALES TAX: On a contract awarded by the City of Fort Worth, an organization which qualifies for exemption pursuant the provisions of Article 20. 04 (8) of the Texas Limited Sales, excise, and Use Tax Act, the Contractor may purchase, rent or lease all materials, supplies and equipment used or consumed in the performance of this contract by issuing to his supplier an exemption certificate in lieu of the tax, said exemption certificate to comply with State Comptroller ' s Ruling . 007. Any such exemption certificate issued by the Contractor in lieu of the tax shall be subject to and shall comply with the provisions of State Comptroller's Ruling . 011, and any other applicable State Comptroller rulings pertaining to the Texas Limited Sales, Excise, and Use Tax Act. On a contract awarded by a developer for the construction of a publicly-owned improvement in a street right-of-way or other easement which has been dedicated to the public and the City of Fort Worth, an organization which qualifies for exemption pursuant to the provisions of Article 20.04 (H) of the Texas limited Sales, Excise, and Use Tax Act, the Contractor can probably be exempted in the same manner stated above. C6-6 (12) Limited Sale, Excise and Use Tax permits and information can be obtained from: Comptroller of Public Accounts Sale Tax Division Capitol Station Austin, TX i i i C6-6 (13) r t r PART C - GENERAL CONDITIONS 4 C7-7 PROSECUTION AND PROGRESS .r ' SECTION C7-7 PROSECUTION AND PROGRESS: C7-7. 1 SUBLETTING: The Contractor shall perform with his own rr organisation, and with the assistance of workman under his immediate super intendance, Mork of a value of not less than fifty (50%) percent of the value embraced in the contract. If the Contractor sublets any part of the Mork to be done under these Contract Documents, he will not under any circumstances be relieved of the responsibility and obligation assumed under these Contract Documents. All transactions of the Engineer will be with the Contractor . Subcontractors will be considered only in the capacity of employees or workmen of the Contractor and shall be subject to the same requirements as to character and competency. The Owner will not recognise any subcontractor on the work. The Contractor shall at all times, when the work is in operation, be represented either in person or by a superintendent or other designated representatives. C7-7 . 2 ASSIGNMENT OF CONTRACT: The Contractor shall not assign, transfer, sublet, convey, or otherwise dispose of the contract or his rights, title, or interest in or to the same or any part thereof without the previous consent of the Owner expressed by resolution of the City Council and concurred in by the Sureties. If the Contractor does, without such previous consent, assign, transfer, sublet, convey, or otherwise dispose of the contract or his right, title, or interest therein or any part thereof, to any person or persons, partnership, company, firm, or corporation, or does by bankruptcy# voluntary or involuntary, or by assignment under the insolvency laws of any state , ' attempt to dispose of the contract may, at the option of the Owner be revoked and annulled, unless the Sureties shall successfully complete said contract, and in the event of any such revocation or annulment, any monies due or to become due under or by virtue of said contract shall be retained by the Owner as liquidated damages for the reason that it would be impracticable and extremely difficult to fiz the actual damages. C7-7 . 3 PROSECUTION OF THE WORK: Prior to beginning any construction operation, the Contractor shall submit to the Engineer in five or more copies, if requested by the Engineer, a progress schedule preferably in chart or diagram form, or a brief outlining in detail and step by step the manner of C7-7 (1) a i� prosecuting the work and ordering materials and equipment which he expects to follow in order to complete the project in the scheduled time. There shall also be submitted a table of estimated amounts to be earned by the Contractor during each monthly estimate period. The Contractor shall commence the work to be performed under this contract within the time limit stated in these Contract Documents and shall conduct the work in a continuous manner and with Buff i-cient equipment, materials, and labor as is necessary to insure its completion within the time limit. The sequence requested of all construction operations shall be at all times as specified in the Special Contract Documents. Any deviation from scup sequencing shall be submitted to the Engineer for his approval. Contractor shall not proceed with any deviation until he has received written approval from the Engineer. Such specification or approval by the Engineer shall not relieve the Contractor from the full responsibility of the complete performance of the Contract. ' The contract time may be changed only as set forth in Section C7-7.6 'Extension of Time of Completion" of this Agreement, and a progress schedule shall not constitute a change in the contract time. C7-7 . 4 LIMITATIONS OF OPERATIONSs The working operations shall at all times be eon ucte y the Contractor so as to create a minimum amount of inconvenience to the public. At any time when, in the judgment of the Engineer, the Contractor ' has obstructed or closed or is carrying on operations in a portion of a street or public way greater than is necessary �T for the proper execution of the work, the Engineer may require the Contractor to finish the section on which operations are in progress before the work is commenced on any additional section or street. , C7-7.5 CHARACTER OF WORKMEN AND NUIPMENTs Local labor shall e used by the Contractor is available. The Contractor may bring in from outside the City of port North his key men and ' his superintendent. All other workioen, including equipment operators , may be imported only after the local supply is exhausted . The Contractor shall employ only such ' superintendents , foremen , and workmen who are careful , competent, and fully qualified to perform the duties or tasks assigned to them, and the Engineer may demand and secure the summary dismissal of any person or persons employed by the Contractor in or about or on the work who, in the opinion of the Owner , shall misconduct himself or be found to be r incompetent, disrespectful , intemperate , dishonest, or C7-7 (2) - otherwise objectionable or neglectful in the proper performance of his or their duties, or who neglects or refuses to comply with or carry out the directions of the Owner, and such person or persons shall not be employed again thereon without written consent of the Engineer. All workmen shall have sufficient skill , ability , and experience to properly perform the work assigned to them and operate any equipment necessary to properly carry out the • performance of the assigned duties. The Contractor shall furnish and maintain on the work all such equipment as is considered to be necessary for prosecution of the work in an acceptable manner and at a satisfactory rate of Progress. All equipment , tools , and machinery used for handling materials and executing any part of the work shall be subject to the approval of the Engineer and shall be maintained in a satisfactory, safe and efficient working condition. Equipment on any portion of the work shall be such that no injury to the work, workmen or adjacent property will result from its use. C7-7. 6 WORK SCHEDULE: Elapsed working days shall be computed starting with the first day of work completed as defined in C1-1 . 23 *WORKING DAY• or the date stipulated in the •WORK ORDER" for beginning work, wbichever comes first. Nothing in these Contract Documents shall be construed as prohibiting the Contractor from working on Saturday, Sunday or Legal Holidays , providing that the following requirements are met: a. A request to work on a specific Saturday, Sunday or Legal Holiday must be made to the Engineer no later than the proceeding Thursday. b. Any work to be done on the project on such a specific Saturday, Sunday or Legal Holiday must be, in the opinion of the Engineer, essential to the timely completion of the project. The Engineer ' s decision shall be final in response to such a request for approval to work on a specific Saturday, Sunday or Legal Holiday, and no extra compensation shall be allowed to the Contractor for any work performed on such a specific Saturday, Sunday of Legal Holiday. Calendar Days shall be defined in C1-1.24 and the Contractor may work as he so desires. C7-7 (3) 1 C7-7.7 TIME OF COMMENCEMENT AND COMPLETION: The Contractor shall commence the working operations within the time specified in the Contract Documents and set forth in the Mork Order. Failure to do so shall' be considered by the Owner as abandonment of the Contract by the Contractor and the Owner may proceed as he sees fit. The Contractor shall maintain a rate of progress such as will insure that the whole work will be performed and the premises cleaned up- in- accordance with the Contract Documents and within the time established in such documents and such extension of time as may be properly authorized by the Owner. C7-7. 8 EXTENSION OF TIME COMPLETION: The Contractor's request or an extens on of time of comp etion shall be considered only when the request for such extension is submitted in writing to the Engineer within seven days from and after the time alleged cause of delay shall have occurred. Should an extension of the time of completion be requested such request will be forwarded to the City Council for approval . In adjusting the contract time for completion of work , consideration will be given to unforseeable causes beyond the control of and without the fault or negligence of the Contractor, including but limited to acts of the public enemy, acts of the Owner , fire, flood, tornadoes , epidemics , quarantine restrictions, strikes, freight embargoes , or delays of sub-contractors due to such causes. When the date of completion is based on a calendar day bid, a request for extension of time because of inclement weather will not be considered. A request for extension of time due to inability to obtain supplies and materials will be considered only when a review of the Contractor ' s purchase -- order dates and other pertinent data as requested by the Engineer indicates that the Contractor has made a bonafide attempt to secure delivery on schedule. This shall include _ efforts to obtain the supplies and materials from alternate sources in case the first source cannot make delivery. If satisfactory execution and completion of the contract should require work and materials in greater amounts or quantities than those set forth in the approved Contract Documents, then the contract time may be increased by Change Order. COY-7. 5 DELAYS: The Contractor shall receive no compensation ?* delays or hindrances to the work, except when direct and u voidable extra cost to the Contractor is caused by the failure of the City to provide information or material, if o , C7-7 (4) A ■ A ■ any, which is to be furnished by the City. When such extra e compensation is claimed a written statement thereof shall be ' presented by the Contractor to the Engineer and if by him found correct shall be approved and referred by him to the R Council for final approval or disapproval; and the action thereon by the Council shall be final and binding. If delay is caused by specific orders given by the Engineers to stop work, or by the performance of extra work, or by the failure Of the City to provide material or necessary instructions for carrying on the work, then such delay will entitle the Contractor to an equivalent extension of time, his application s for which shall, however, be subject to the approval of the City Council ; and no such extension of time shall release the ■ Contractor or the surety on his performance bond from all his obligations hereunder which shall remain in full force until the discharge of the contract. C7-7 . 10 TIME OF COMPLETION: The time of completion is an s essential element of the contract. Each bidder shall indicate in the appropriate place on the last page of the Proposal the ■ number of working days or calendar days that he will require R to fully complete this contract or the time of completion will be specified by the City in the Proposal section of the ■ contract documents. s The number of days indicated shall be a realistic estimate of the time required to complete the work covered by the specific contract being bid upon. The amount of time so stated by the s successful bidder or the City will become the time of completion specified in the Contract Documents. ■ For each calendar day that any work shall remain uncompleted after the time specified in the Contract Documents , or the increased time granted by the Owner, or as automatically ■ increased by additional work or materials ordered after the s contract is signed, the sum per day given -in the following schedule, unless otherwise specified in other parts of the ■ Contract Documents , will be deducted from monies due the w Contractor, not as a penalty, but as liquidated damages suffered by the Owner. ■ AMOUNT OF CONTRACT ■ Less than $ 50000 inclusive $ 35.00 ■ $ 51,001 to $ 15,000 inclusive $ 45.00 $ 15,001 to $ 25,000 inclusive $ 63.00 $ 25,001 to $ 50,000 inclusive $ 105.00 $ 50,001 to $ 100,000 inclusive $ 154.00 $ 100,001 to $ 500,000 inclusive $ 210.00 C7-7 (5)