HomeMy WebLinkAboutContract 53916-PM1CSC No. 53916-PM1 RCVD 08/20/2020 00 00 10- 1 TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS Page 1 of 5 CITY OF FORT WORTH North City Addition Phase 1 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049 Revised September 1, 2015 SECTION 00 00 10 1 TABLE OF CONTENTS 2 DEVELOPER AWARDED PROJECTS 3 4 Division 00 - General Conditions 5 00 11 13 Invitation to Bidders 6 00 21 13 Instructions to Bidders 7 00 41 00 Bid Form 8 00 42 43 Proposal Form Unit Price 9 00 43 13 Bid Bond 10 00 45 11 Bidders Prequalification’s 11 00 45 12 Prequalification Statement 12 00 45 13 Bidder Prequalification Application 13 00 45 26 Contractor Compliance with Workers' Compensation Law 14 00 45 40 Minority Business Enterprise Goal 15 00 52 43 Agreement 16 00 61 25 Certificate of Insurance 17 00 62 13 Performance Bond 18 00 62 14 Payment Bond 19 00 62 19 Maintenance Bond 20 00 72 00 General Conditions 21 00 73 00 Supplementary Conditions 22 00 73 10 Standard City Conditions of the Construction Contract for Developer Awarded 23 Projects 24 25 Division 01 - General Requirements 26 01 11 00 Summary of Work 27 01 25 00 Substitution Procedures 28 01 31 19 Preconstruction Meeting 29 01 31 20 Project Meetings 30 01 32 16 Construction Progress Schedule 31 01 32 33 Preconstruction Video 32 01 33 00 Submittals 33 01 35 13 Special Project Procedures 34 01 45 23 Testing and Inspection Services 35 01 50 00 Temporary Facilities and Controls 36 01 55 26 Street Use Permit and Modifications to Traffic Control 37 01 57 13 Storm Water Pollution Prevention Plan 38 01 58 13 Temporary Project Signage 39 01 60 00 Product Requirements 40 01 66 00 Product Storage and Handling Requirements 41 01 70 00 Mobilization and Remobilization 42 01 71 23 Construction Staking 43 01 74 23 Cleaning 44 01 77 19 Closeout Requirements 45 01 78 23 Operation and Maintenance Data 46 01 78 39 Project Record Documents 47 48 00 00 10- 2 TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS Page 2 of 5 CITY OF FORT WORTH North City Addition Phase 1 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049 Revised September 1, 2015 Technical Specifications which have been modified by the Engineer specifically for this 1 Project; hard copies are included in the Project’s Contract Documents 2 3 Division 02 - Existing Conditions 4 NONE 5 6 Division 03 - Concrete 7 NONE 8 9 Division 26 - Electrical 10 NONE 11 12 Division 31 - Earthwork 13 NONE 14 15 Division 32 - Exterior Improvements 16 NONE 17 18 Division 33 - Utilities 19 NONE 20 21 Division 34 - Transportation 22 NONE 23 24 25 Technical Specifications listed below are included for this Project by reference and can be 26 viewed/downloaded from the City’s Buzzsaw site at: 27 28 htps://projectpoint.buzzsaw.com/client/fortworthgov/Resources/02%20-29 %20Construction%20Documents/Specifications 30 31 32 Division 02 - Existing Conditions 33 02 41 13 Selective Site Demolition 34 02 41 14 Utility Removal/Abandonment 35 02 41 15 Paving Removal 36 37 Division 03 - Concrete 38 03 30 00 Cast-In-Place Concrete 39 03 34 13 Controlled Low Strength Material (CLSM) 40 03 34 16 Concrete Base Material for Trench Repair 41 03 80 00 Modifications to Existing Concrete Structures 42 43 Division 26 - Electrical 44 26 05 00 Common Work Results for Electrical 45 26 05 10 Demolition for Electrical Systems 46 26 05 33 Raceway and Boxes for Electrical Systems 47 26 05 43 Underground Ducts and Raceways for Electrical Systems 48 26 05 50 Communications Multi-Duct Conduit 49 50 00 00 10- 3 TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS Page 3 of 5 CITY OF FORT WORTH North City Addition Phase 1 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049 Revised September 1, 2015 Division 31 - Earthwork 1 31 10 00 Site Clearing 2 31 23 16 Unclassified Excavation 3 31 23 23 Borrow 4 31 24 00 Embankments 5 31 25 00 Erosion and Sediment Control 6 31 36 00 Gabions 7 31 37 00 Riprap 8 9 Division 32 - Exterior Improvements 10 32 01 17 Permanent Asphalt Paving Repair 11 32 01 18 Temporary Asphalt Paving Repair 12 32 01 29 Concrete Paving Repair 13 32 11 23 Flexible Base Courses 14 32 11 29 Lime Treated Base Courses 15 32 11 33 Cement Treated Base Courses 16 32 11 37 Liquid Treated Soil Stabilizer 17 32 12 16 Asphalt Paving 18 32 12 73 Asphalt Paving Crack Sealants 19 32 13 13 Concrete Paving 20 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 21 32 13 73 Concrete Paving Joint Sealants 22 32 14 16 Brick Unit Paving 23 32 16 13 Concrete Curb and Gutters and Valley Gutters 24 32 17 23 Pavement Markings 25 32 17 25 Curb Address Painting 26 32 31 13 Chain Link Fences and Gates 27 32 31 26 Wire Fences and Gates 28 32 31 29 Wood Fences and Gates 29 32 32 13 Cast-in-Place Concrete Retaining Walls 30 32 91 19 Topsoil Placement and Finishing of Parkways 31 32 92 13 Hydro-Mulching, Seeding, and Sodding 32 32 93 43 Trees and Shrubs 33 34 Division 33 - Utilities 35 33 01 30 Sewer and Manhole Testing 36 33 01 31 Closed Circuit Television (CCTV) Inspection 37 33 03 10 Bypass Pumping of Existing Sewer Systems 38 33 04 10 Joint Bonding and Electrical Isolation 39 33 04 11 Corrosion Control Test Stations 40 33 04 12 Magnesium Anode Cathodic Protection System 41 33 04 30 Temporary Water Services 42 33 04 40 Cleaning and Acceptance Testing of Water Mains 43 33 04 50 Cleaning of Sewer Mains 44 33 05 10 Utility Trench Excavation, Embedment, and Backfill 45 33 05 12 Water Line Lowering 46 33 05 13 Frame, Cover and Grade Rings 47 33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 48 33 05 16 Concrete Water Vaults 49 33 05 17 Concrete Collars 50 00 00 10- 4 TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS Page 4 of 5 CITY OF FORT WORTH North City Addition Phase 1 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049 Revised September 1, 2015 33 05 20 Auger Boring 1 33 05 21 Tunnel Liner Plate 2 33 05 22 Steel Casing Pipe 3 33 05 23 Hand Tunneling 4 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 5 33 05 26 Utility Markers/Locators 6 33 05 30 Exploratory Excavation for Existing Utilities 7 33 11 05 Bolts, Nuts, and Gaskets 8 33 11 10 Ductile Iron Pipe 9 33 11 11 Ductile Iron Fittings 10 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11 33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12 33 11 14 Buried Steel Pipe and Fittings 13 33 11 15 Pre-stressed Concrete Cylinder Pipe 14 33 12 10 Water Services 1-inch to 2-inch 15 33 12 11 Large Water Meters 16 33 12 20 Resilient Seated Gate Valve 17 33 12 21 AWWA Rubber-Seated Butterfly Valves 18 33 12 25 Connection to Existing Water Mains 19 33 12 30 Combination Air Valve Assemblies for Potable Water Systems 20 33 12 40 Dry-Barrel Fire Hydrants 21 33 12 50 Water Sample Stations 22 33 12 60 Blow-off Valves 23 33 31 12 Cured in Place Pipe (CIPP) 24 33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 25 33 31 15 HDPE Pipe For Sanitary Sewers (Gravity and Force Mains) 26 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 27 33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 28 33 31 22 Sanitary Sewer Slip Lining 29 33 31 23 Sanitary Sewer Pipe Enlargement 30 33 31 50 Sanitary Sewer Service Connections and Service Line 31 33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 32 33 39 10 Cast-in-Place Concrete Manholes 33 33 39 20 Precast Concrete Manholes 34 33 39 30 Fiberglass Manholes 35 33 39 40 Wastewater Access Chamber (WAC) 36 33 39 60 Epoxy Liners for Sanitary Sewer Structures 37 33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 38 33 41 11 HDPE Storm Sewer Pipe 39 33 46 00 Sub drainage 40 33 46 01 Slotted Storm Drains 41 33 46 02 Trench Drains 42 33 49 10 Cast-in-Place Manholes and Junction Boxes 43 33 49 20 Curb and Drop Inlets 44 33 49 40 Storm Drainage Headwalls and Wingwalls 45 46 Division 34 – Transportation 47 34 41 10 Traffic Signals 48 34 41 10.01 Attachment A – Controller Cabinet 49 34 41 10.02 Attachment B – Controller Specification 50 00 00 10- 5 TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS Page 5 of 5 CITY OF FORT WORTH North City Addition Phase 1 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049 Revised September 1, 2015 34 41 10.03 Attachment C – Software Specification 1 34 41 11 Temporary Traffic Signals 2 34 41 13 Removing Traffic Signals 3 34 41 15 Rectangular Rapid Flashing Beacon 4 34 41 16 Pedestrian Hybrid Signal 5 34 41 20 Roadway Illumination Assemblies 6 34 41 20.01 Arterial LED Roadway Luminaires 7 34 41 20.02 Freeway LED Roadway Luminaires 8 34 41 20.03 Residential LED Roadway Luminaires 9 34 41 30 Aluminum Signs 10 34 41 50 Single-Mode Fiber Optic Cable 11 34 71 13 Traffic Control 12 13 Appendix 14 GC-4.01 Availability of Lands 15 GC-4.02 Subsurface and Physical Conditions 16 GC-4.04 Underground Facilities 17 GC-4.06 Hazardous Environmental Condition at Site 18 GC-6.06.D Minority and Women Owned Business Enterprise Compliance 19 GC-6.07 Wage Rates 20 GC-6.09 Permits and Utilities 21 GC-6.24 Nondiscrimination 22 GR-01 60 00 Product Requirements 23 24 END OF SECTION 25 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID 004243 DAP -RID PROPOSAL Page I of Bidder's Application Project Item Information Bidder's Proposal Bid'is'Item Description Specification Section Unit of Bid Unit Price Bid Value No. No. Measure Quantity UNIT I: WATER IMPROVEMENTS 1 3312.0001 Fire Hydrant Assembly 331240 EA 6 __ $4,463.00 11 $26,778_00 2 -- 3312.0117 -- _ Connect toEx 4 12" Water -Mad n - 33 - -- 12 25 EA 2 $3,235.50 $6,471.00 3 3312.3105 Cut In Tee & Gate Valve 331220 EA 1 247.00 $5 247.00 _ 4 3305.1102 _12" 16" Steel Encasement not Open Cut 33 12 _ 25 _ _ _ LF 69 _$5 _ $175.00 _ $12 075.00 5 9999.0004 Bore for 12" Water Pipe 33 12 _ 25 LF 69 $175.00 ._ $12,075.00 6 3312.3005 12" Gate Valve - 33 12 20 EA 12 _. $2,407.00 - $28,884.00 ...__..— 7 3312.3003 - -- -----_. ---- 8" Gale Valve 33 1-2-2-0 EA 3 $1,460.00 -, $4,380A0 ___.. 8 3312.3002 _ . _-. _- ._... - 6" Gate Valve _.. 33 33 1220 EA _ 6 ,. _ _ $1,140.00 $61840.00 9 3312.2201 _ 2" Water Service 33 12 20 EA 3 $1,651.00 $4 953.00 10 3312.2103 1 1/2" Water Service 33 12 20 EA 3 $2 158 00 $6,474.00 11 3311.0441 12 Water Pipe 33 11 10s 33 11 12 LF 2818 $43.12 $121 512.00 12 3311.0241 8" Water Pipe 33 11 10, 33 11 12 LF 45 - $35.00 $11575.00 13 - 3311.0141 6" Water Pipe 33 11 10, 33 11 12 LF 108 $29.00 $3 132.00 14 3305.0109 Trench Safety 33 05 10 LF _ 2971 $1.00 $2,971.00 15 3311.0001 Ductile Iron Water Fittings w/Restraint 33 11 105 33 11 12 TON 2.5 $8,030.80 $20,077.00 16 17 18 19.__- 20._.__ 21 CITY OP PORT WORTH STANDARD CONSTRUCTION SPECfPICATION DOCUMENTS -DEVELOPER A\YARDED PROTECTS Pam, Version September 1, 2015 2000G- 004243_RiJ Proposal DAP ReviuJ 04.16.20 004243 DAP -HID PROPOSAL Page 2 or SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID Bidder's Application Project Item Information Bidder's Proposal Bidlist Item Description SpeciOcation Section Unitof Bid Unit Price Bid Value No. No. Measure Quantity UNIT II: SANITARY SEWER IMPROVEMENTS 1 3331.4115 8" Sewer Pipe 33 11 10,33 31 123 LF 30 $36.00 _ _$1,080.00 _ __ 2 ---- 333L4119 8" DIP Sewer Plpe --- --- 3311 10 LF 73 $62.00 $4,526 00 _ 3 3339.1001. 4 Manhole 32 39 -M 33 39 20 EA 2 00 _ $12,052.00 3339.100_4 4' Sha_Ilow_Manhole 33 39 10, 33 39 20 EA 1 _$6,026 $6,026.00 ,. $69026.00 _ _4 _ 5 3339.1101- 5'Manhole -- 33 39 10, 33 39 20 EA 1 _ _ _ $9,814.00 $9,814.00 6 9999.0001 to Ex. Mild w/external drop 00 00 00 EA 1 $8,250.00 _ $8 250,00 __ _ 7 _Connect 9999.0002 Connect totx7mfi 0o o0 00 EA 1 $3,690.00 $3,690.00 8 3305.0113 Trench Water Stop - 330515 EA 2 $1,595.00 $3,190.00 _ 9 3339.0001Epoxy Manhole Liner 333960 VF 65 $482.22 $31,344.30 10 -_. _...---3 3301.0_101 Manhole Vacuum Testing--- _ - --__. 33 01 30 EA 4 _.. $100.00 _. $400.00 _ 11 35.0 ii concrete Encasement 30 33 06 10 CY 2 $54.00 $108.00 12 3301.0002Posl-Giant Inspection 3301 31 - LF 103 $1.00 $103.00 13 3305.0109 Trench Safety 33 05 10 LF 103 $1.00 $103.00 14 15 16 17 18 19 20 21 22 23 24 2-5 26 27 28 29 31 32 33 34 35 ...... ...... __.. _.. ... ____ _.. 36 __ 37 39 40 41 42 43 44 45 46 47___. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS -DEVELOPER AWARDED PROJECTS Foun Version Seplember 1, 2015 20006 - 0042 43_Hid Poapool DAP Revised 04.16.20 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID 004243 DAP-HIDPROPOSAL Page 3 of Bidder's Application Project Item Information Bidder's Proposal Bidlist Item Description Specification Section Unit of Bid Unit Price Bid Value No. No. Measure Quantity TOTAL UNIT It: SANITARY SEWER IMPROVEMENTc $80,686.30 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIPICATION DOCUMENTS -DEVELOPER AIVARDF,D PROJECTS Porm Version September I, 2015 20006- 004243 Hid Proposel_DAP Revised 04.16.20 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID 004243 DAP-BIDPROPOSAL Pap 4 of 6 Bidder's Application Project Item Infomration Bidder's Proposal Bidlist Item Description Specification Section Unit of Bid Unit Price Bid Value No. No. Measure Quantity UNIT III:. DRAINAGE IMPROVEMENTS 10 LF 343 _ $148.00 _ $50,764,.,00 1 3341.0_402 42" RCP, Class III 3341 2 _ 3341.0302 30" RCP, Class III _ 33 41 16 - _ LF _ _ 64 $96.00 _ $6144.00 3 9-13T01— Connect to Ex. Storm 00 00 EA 1 $2 263,00 3137.0102 Rock Rip Rap - Dry �1100 31 3700 SY 40 ,$2,263.00 $108.00 $4,320.00 _ _4 5 _ 3349.0002 _ 5' Storm Junction Box 33 49 10 EA 3 _ _ U1723.00 _ $203169,00 6 3349.1009 42" Flared Headwall, One Pipe - 33 49 40 EA 1 _ $5 623,00 $5,623.00 7 3305.6109 Trench Safety 33 05 10 1 LF 407 $1.00 _ $407.00 9 16 11 12 13 14 15 16 17 18 19 26 21 22 23 24 25 26 27 28 29 36 31 32 33 34 35 36 37 .._ 38 40 41 42 43 _... 44 45 TOTAL UNIT III: DRAINAGE IMPROVEMENT $8900.001 CITY OP PORT \NORTH STANDARD CONSTRUCTION SPECIPICATION DOCUMENTS - DEVELOPER A\YARDED PROJECTS Porm Version September 1, 2015 20006- 00 42 43 Bid Proposal_DAP Revised 04.16.20 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID 004243 In PROPOSAL PROPOSAL Page 5 of Bidder's Application Project Item Information Bidder's Proposal Bidlist Item Description Specification Section Unit of Bid Unit Price Bid Value No. No. Measure Quantity UNIT IV: PAVING IMPROVEMENTS 1 0241.1000 Remove Conc. Pvmt. 024115 SY 265 $27.00 $7,155.00 2 0241.0100 Remove Conc. Sidewalk 0241 _ 13 SY .. 100 _ $10,00 $1,000.00 3 3213 0301 4 Conc. Sidewalk (w Wide) 32 13 20 SF 100 $13,20 $1,320.00 4 _ 3471.00o1 TraNic Control I -- 34 --- - 71 13 _ MO 2 --- -- $3,000,00 __ $6,000.00 _ _ 5 _ _ 3201,0616 Conc. Pvmt. Repair - 32 1129 SY _ _ 265 ..$72 00 ._ $19 080.00 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 _ 35- 36 37 38 39 40 41 43 4-4 _. 45 I TOTAL UNIT IV: PAVING IMPROV EMENT.Sli $3055.00 CITY OP FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS rams Version September I, 2015 20006- 004243 Bid Pmposal_DAP Revised 04.16.20 UNIT PRICE BID SECTION vu 42 4a Developer Awarded Projects - PROPOSAL FORM Pr Ject Item information 004243 DAP -HID PROPOSAL PagetioT6 Bidder's Application Bidde>'s Proposal IBidlNo. Item) Description I Specification No. Section I Measure I Quantity Bid I Unit Price ( Bid Value N UNIT I: WATER IMPROVEMENTS UNIT II: SANITARY SEWER IMPROVEMENTS UNIT III: DRAINAGE IMPROVEMENTS UNIT IV: PAVING IMPROVEMENTS This Bid is submitted by the entity named below: BIDDER: Wright Construction Company 601NP, Wall St Grapevine, TX 76051 Contractor agrees to complete WORK [or FINAL ACCEPTANCE within CONTRACT comroenees to run as provided in the General Conditions. Total Construction Bid BY: TITLE: DATE: sj /;zq iU END OF SECTION 59 . working drys after the date when the CITY OP FORT WORTH STANDARD CONSTRUCTION SPECIPICATION DOCUMENTS - DHVHLOPER AWARDGD PROIF.CTS Pamr Version September I, 2015 20006- 004243_Hid Proposal_DAP Revised 04.16.20 00 45 11 - 1 BIDDERS PREQUALIFICATIONS Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised April 2, 2014 Landmark Quebec Addition 102418 SECTION 00 45 11 BIDDERS PREQUALIFICATIONS 1. Summary. All contractors are required to be prequalified by the City prior to submitting bids. To be eligible to bid the contractor must submit Section 00 45 12, Prequalification Statement for the work type(s) listed with their Bid. Any contractor or subcontractor who is not prequalified for the work type(s) listed must submit Section 00 45 13, Bidder Prequalification Application in accordance with the requirements below. The prequalification process will establish a bid limit based on a technical evaluation and financial analysis of the contractor. The information must be submitted seven (7) days prior to the date of the opening of bids. For example, a contractor wishing to submit bids on projects to be opened on the 7th of April must file the information by the 31st day of March in order to bid on these projects. In order to expedite and facilitate the approval of a Bidder’s Prequalification Application, the following must accompany the submission. a. A complete set of audited or reviewed financial statements. (1) Classified Balance Sheet (2) Income Statement (3) Statement of Cash Flows (4) Statement of Retained Earnings (5) Notes to the Financial Statements, if any b. A certified copy of the firm’s organizational documents (Corporate Charter, Articles of Incorporation, Articles of Organization, Certificate of Formation, LLC Regulations, Certificate of Limited Partnership Agreement). c. A completed Bidder Prequalification Application. (1) The firm’s Texas Taxpayer Identification Number as issued by the Texas Comptroller of Public Accounts. To obtain a Texas Taxpayer Identification number visit the Texas Comptroller of Public Accounts online at the following web address www.window.state.tx.us/taxpermit/ and fill out the application to apply for your Texas tax ID. (2) The firm’s e-mail address and fax number. (3) The firm’s DUNS number as issued by Dun & Bradstreet. This number is used by the City for required reporting on Federal Aid projects. The DUNS number may be obtained at www.dnb.com. d. Resumes reflecting the construction experience of the principles of the firm for firms submitting their initial prequalification. These resumes should include the size and scope of the work performed. e. Other information as requested by the City. 2. Prequalification Requirements a. Financial Statements. Financial statement submission must be provided in accordance with the following: (1) The City requires that the original Financial Statement or a certified copy be submitted for consideration. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised April 2, 2014 Landmark Quebec Addition 102418 00 45 11 - 2 BIDDERS PREQUALIFICATIONS Page 2 of 3 (2) To be satisfactory, the financial statements must be audited or reviewed by an independent, certified public accounting firm registered and in good standing in any state. Current Texas statues also require that accounting firms performing audits or reviews on business entities within the State of Texas be properly licensed or registered with the Texas State Board of Public Accountancy. (3) The accounting firm should state in the audit report or review whether the contractor is an individual, corporation, or limited liability company. (4) Financial Statements must be presented in U.S. dollars at the current rate of exchange of the Balance Sheet date. (5) The City will not recognize any certified public accountant as independent who is not, in fact, independent. (6) The accountant’s opinion on the financial statements of the contracting company should state that the audit or review has been conducted in accordance with auditing standards generally accepted in the United States of America. This must be stated in the accounting firm’s opinion. It should: (1) express an unqualified opinion, or (2) express a qualified opinion on the statements taken as a whole. (7) The City reserves the right to require a new statement at any time. (8) The financial statement must be prepared as of the last day of any month, not more than one year old and must be on file with the City 16 months thereafter, in accordance with Paragraph 1. (9) The City will determine a contractor’s bidding capacity for the purposes of awarding contracts. Bidding capacity is determined by multiplying the positive net working capital (working capital = current assets – current liabilities) by a factor of 10. Only those statements reflecting a positive net working capital position will be considered satisfactory for prequalification purposes. (10) In the case that a bidding date falls within the time a new financial statement is being prepared, the previous statement shall be updated with proper verification. b. Bidder Prequalification Application. A Bidder Prequalification Application must be submitted along with audited or reviewed financial statements by firms wishing to be eligible to bid on all classes of construction and maintenance projects. Incomplete Applications will be rejected. (1) In those schedules where there is nothing to report, the notation of “None” or “N/A” should be inserted. (2) A minimum of five (5) references of related work must be provided. (3) Submission of an equipment schedule which indicates equipment under the control of the Contractor and which is related to the type of work for which the Contactor is seeking prequalification. The schedule must include the manufacturer, model and general common description of each piece of equipment. Abbreviations or means of describing equipment other than provided above will not be accepted. 3. Eligibility to Bid a. The City shall be the sole judge as to a contractor’s prequalification. b. The City may reject, suspend, or modify any prequalification for failure by the contractor to demonstrate acceptable financial ability or performance. c. The City will issue a letter as to the status of the prequalification approval. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised April 2, 2014 Landmark Quebec Addition 102418 00 45 11 - 3 BIDDERS PREQUALIFICATIONS Page 3 of 3 d. If a contractor has a valid prequalification letter, the contractor will be eligible to bid the prequalified work types until the expiration date stated in the letter. END OF SECTION 00 45 12 OAP MQUALIFICATION STATEMENT Page I or t SECTION 00 4512 DAP — PREQUALIFICATION STATEMENT Each Bidder is required to complete the information below by identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Major We Tyne" box provide the complete major work We and actual description as provided by the Watei Department for water and sewer and TPW for paying,, Major Work Type Contractor/Subcontractor Company Name Prequalification Expiration Date Water, Sewer Paving & Wright Construction Co Inc. Drainage Improvements to Serve Lonestar Business Park Water Dist. - 12" Din. & Smaller Wright Construction Co., Inc. 4/30/2021 Sewer Collection System - 8" Din. & Son [let Wright Construction Co., Inc. 4/30/2021 The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are currently prequalified for the work types listed. BIDDER: Wright Construction Co Inc. BY: David retry 601 W. Wall Street Grapevine, Texas 76051 (Signature) TITLE: (fact. f��eSic2ary j DATE: (1 4 f a o END OF SECTION CITY OF FOflT WORTH STANDARD CONSTRUCTION PREQUALIFICATIONSTRTEMENT— DEVELOPER AWARDED PROTECTS 004512_Prequalificatlon Statement 2015 DAP Form Version September 1, 2015 004526-1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Page 1 of 1 1 SECTION 00 45 26 2 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW 3 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it 4 provides worker's compensation insurance coverage for all of its employees employed on City 5 Project No.102418, Contractor further certifies that, pursuant to Texas Labor Code, Section 6 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with 7 worker's compensation coverage. 9 CONTRACTOR: 10 Wright Construction Co Inc. By: 11 (Please Print) � 12 13 601 W. Wall Street Signature: ....... � _->. — ' 14 Address 15 16 Grapevine, Texas 76051 Title: vi C-f pre }" d ems% r 17 City/State/Zip (Please Print) 18 19 20 THE STATE OF TEXAS § 21 22 COUNTY OF TARRANT § 23 24 BEFORE ME, the.undersigned authority, on this day personally appeared known to me to be the person whose name is 26 subscribed to the foregoing instrument, and acknowledged to me that he/she executed the 27 same as the act and deed of i, i� �7f - , I for the purposes and 28 consideration therein expressed and in the capacity therein stated. 29 30 GIVEN UNDER MY HAND AND SEAL OF OFFICE this ' day of 32 33 34 iis���``°�� Deb Donaldson j _;� Notary Public, State of Texas/j,A 35 :� Comm. Expires0l/24/2021 Notary Public in and for the State of Texas 9�0:� Notary lD 11970986 36 END OF SECTION CITY OF FORT WORTH Landmark Quebec Addition STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS 202428 Revised April 2, 2014 00 52 43 - 1 Developer Awarded Project Agreement Page 1 of 4 CITY OF FORT WORTH Landmark Quebec Addition STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102418 Revised June 16, 2016 SECTION 00 52 43 1 AGREEMENT 2 3 THIS AGREEMENT, authorized on _May 21, 2020_is made by and between the Developer, 4 (LONESTAR COMMERCE CENTER I, LLC), authorized to do business in Texas (“Developer”) , and 5 __The Conlan Company_____, authorized to do business in Texas, acting by and through its duly 6 authorized representative, (“Contractor”). 7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree 8 as follows: 9 Article 1. WORK 10 Contractor shall complete all Work as specified or indicated in the Contract Documents for the 11 Project identified herein. 12 Article 2. PROJECT 13 The project for which the Work under the Contract Documents may be the whole or only a part 14 is generally described as follows: 15 Lonestar Business Park 16 102418 17 Article 3. CONTRACT TIME 18 3.1 Time is of the essence. 19 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract 20 Documents are of the essence to this Contract. 21 3.2 Final Acceptance. 22 The Work will be complete for Final Acceptance within _76__ calendar days after the date 23 when the Contract Time commences to run as provided in Paragraph 12.04 of the 24 Standard City Conditions of the Construction Contract for Developer Awarded Projects. 25 3.3 Liquidated damages 26 Contractor recognizes that time is of the essence of this Agreement and that Developer 27 will suffer financial loss if the Work is not completed within the times specified in 28 Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 29 of the Standard City Conditions of the Construction Contract for Developer Awarded 30 Projects. The Contractor also recognizes the delays, expense and difficulties involved in 31 proving in a legal proceeding the actual loss suffered by the Developer if the Work is not 32 completed on time. Accordingly, instead of requiring any such proof , Contractor agrees 33 that as liquidated damages for delay (but not as a penalty), Contractor shall pay 34 Developer _Five Hundred _ Dollars ($_500.00 ) for each day that expires after the time 35 specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of 36 Acceptance. 37 Article 4. CONTRACT PRICE 38 Developer agrees to pay Contractor for performance of the Work in accordance with the 39 Contract Documents an amount in current funds of _ Four Hundred Sixty Eight Thousand and 40 Three hundred Seventy Five Dollars ($_468,375.30_). 41 Article 5. CONTRACT DOCUMENTS 42 5.1 CONTENTS: 43 A. The Contract Documents which comprise the entire agreement between Developer 44 and Contractor concerning the Work consist of the following: 45 005243-2 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 Developer Awarded Project Agreement Page 2 of 4 1. This Agreement. 2. Attachments to this Agreement: a. Bid Form (As provided by Developer) 1) Proposal Farm (DAP Version) 2) Prequalification Statement 3) State and Federal documents (project specific) b. Insurance ACORD Form(s) c. Payment Bond (DAP Version)- d. Performance Bond (DAP Version) e. Maintenance Bond (DAP Version) f. Power of Attorney for the Bonds g. Worker's Compensation Affidavit h. MBE and/or SBE Commitment Form (If required) 3. Standard City General Conditions of the Construction Contract for Developer Awarded Projects. 4. Supplementary Conditions. 5. Specifications specifically made a part of the Contract Documents by attachment or, if not attached, as incorporated by reference and described in the Table of Contents of the Project's Contract Documents. 6. Drawings, 7. Addenda, 8. Documentation submitted by Contractor prior to Notice of Award. 9. The following which may be delivered or issued after the Effective Date of the Agreement and, if issued, become an incorporated part of the Contract Documents: a. Notice to Proceed. b. Field Orders. c. Chadge Orders. d. Letter of Final Acceptance. CITY OF FORT WORTH Landmark quebec Addition STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS 102418 Revised June 16, 2016 006243-3 Developer Awarded Project Agreement Page 3 of 4 77 Article 6. INDEMNIFICATION 78 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own 79 expense, the city, its officers, servants and employees, from and against any and all 80 claims arising out of, or alleged to arise out of, the work and services to be performed by 81 the contractor, its officers, agents, employees, subcontractors, licenses or invitees under 82 this contract. This indemnification provision is specifically intended to operate and be 83 effective even if it is alleged or proven that all or some of the damages being sought 84 were caused in whole or in part, by any act, omission or negligence of the city. This 85 indemnity provision is intended to include, without limitation, indemnity for costs, 86 expenses and legal fees incurred by the city in defending against such claims and causes 87 of actions. 88 89 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, 90 the city, its officers, servants and employees, from and against any and all loss, damage 91 or destruction of property of the city, arising out of, or alleged to arise out of, the work 92 and services to be performed by the contractor, its officers, agents, employees, 93 subcontractors, licensees or invitees under this contract. This indemnification provision 94 is specifically intended to operate and be effective even if it is alleged or proven that all 95 or some of the damages being sought were caused, in whole or in part, by any act, 96 omission or negligence of the city. 97 98 Article 7. MISCELLANEOUS 99 7A Terms, 100 Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of 101 the Construction Contract for Developer Awarded Projects. 102 7.2 Assignment of Contract. 103 This Agreement, including all of the Contract Documents may not be assigned by the 104 Contractor without the advanced' express written consent of the Developer. 105 7.3 Successors and Assigns. 106 Developer and Contractor each binds itself, its partners, successors, assigns and legal 107 representatives to the other party hereto, in respect to all covenants, agreements and 108 obligations contained in the Contract Documents, 109 7.4 Severability, 110 Any provision or part of the Contract Documents held to be unconstitutional, void or 111 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all 112 remaining provisions shall continue to be valid and binding upon DEVELOPER and 113 CONTRACTOR, 114 7.5 Governing Law and Venue. 115 This Agreement, including all of the Contract Documents is performable in the State of 116 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the 117 Northern District of Texas, Fort Worth Division, 118 119 7.6 Authority to Sign. 120 Contractor shall attach evidence of authority to sign Agreement, if other than duly 121 authorized signatory of the Contractor. CITY OF FORT WORTH Landmark Que6ecAddi[ion STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS 102415 Revised tune 16, 2016 006243-4 Developer Awarded Project Agreement Page 4 of 4 122 123 IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple 124 counterparts. 125 126 This Agreement is effective as of the last date signed by the Parties ("Effective Date"). 127 Contractor: The Conlan Company Company Name: By, Ignature) Benjamin Bratcher (Printed Name) Title: Senior Project Manager Address: 1501 LB1 Freeway, Suite 550 City/State/Zip: Farmers Branch, Texas 75234 Date Developer: Lonestar Commerce Center 1, LLC Company name: By. 214 r .__-M f (Signat re) r Curt Hefner (Printed Name) Address: 750 N. Saint Paul Street, Suite 1350 City/State/Zip: Dallas. Texas 75201 r Date CITY OF FORT W ORTH Landmark Quebec Additlan STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS 102418 Revised June 16, 2016 00 62 13 - 1 PERFORMANCE BOND Page 1 of 2 CITY OF FORT WORTH Landmark Quebec Addition STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS 102418 Revised January 31, 2012 SECTION 00 62 13 1 PERFORMANCE BOND 2 3 THE STATE OF TEXAS § BOND NUMBER: 30090314 4 § KNOW ALL BY THESE PRESENTS: 5 COUNTY OF TARRANT § 6 7 That we, The Conlan Company, known as “Principal” herein and Continental Casualty 8 Company, a corporate surety(sureties, if more than one) duly authorized to do business in the 9 State of Texas, known as “Surety” herein (whether one or more), are held and firmly bound unto 10 the Developer, Lonestar Commerce Center, LLC, 750 North Saint Paul Street, Dallas, TX 75201, 11 authorized to do business in Texas (“Developer”) and the City of Fort Worth, a Texas municipal 12 corporation (“City”), in the penal sum of Four-Hundred Sixty – Eight Thousand Three-Hundred 13 and Seventy-Five Dollars and Thirty cents ($468,375.30), lawful money of the United States, to 14 be paid in Fort Worth, Tarrant County, Texas for the payment of which sum well and truly to be 15 made jointly unto the Developer and the City as dual obligees, we bind ourselves, our heirs, 16 executors, administrators, successors and assigns, jointly and severally, firmly by these presents. 17 WHEREAS, Developer and City have entered into an Agreement for the construction of 18 community facilities in the City of Fort Worth by and through a Community Facilities Agreement, 19 CFA Number CFA20-0032 and 20 WHEREAS, the Principal has entered into a certain written contract with the Developer awarded 21 the 21 day of May, 2020, which Contract is hereby referred to and made a part hereof for all 22 purposes as if fully set forth herein, to furnish all materials, equipment labor and other 23 accessories defined by law, in the prosecution of the Work, including any Change Orders, as 24 provided for in said Contract designated as Water and Sanitary Sewer Improvements to Serve 25 Landmark Quebec Addition. 26 NOW, THEREFORE, the condition of this obligation is such that if the said Principal shall 27 faithfully perform it obligations under the Contract and shall in all respects duly and faithfully 28 perform the Work, including Change Orders, under the Contract, according to the plans, 29 specifications, and contract documents therein referred to, and as well during any period of 30 extension of the Contract that may be granted on the part of the Developer and/or City, then 31 this obligation shall be and become null and void, otherwise to remain in full force and effect. 32 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 33 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort 34 Worth Division. 35 This bond is made and executed in compliance with the provisions of Chapter 2253 of 36 the Texas Government Code, as amended, and all liabilities on this bond shall be determined in 37 accordance with the provisions of said statue. 38 00 62 13 - 2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 PERFORMANCE BOND Page 2 of 2 IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED this instrument by duly authorized agents and officers on this the day of 20 PRINCIPAL: The Conlan Company a P"k�_ Nitness as to Principal Nitn s as to Surety Jam s H. Vaughan, V/ BY:A_/�. Signature Name and Title .�`�•.•'`••"'•:�'0y''. ��.• °oaPaN ?� Address: 1800 Parkway Place, Suitd1010 Marietta, Georgia 30067_ SEAL SURETY: �`.,� • •.•�� ••,. ��. Continental Casualtv Com M07 BY: Signature Felisa H. Vaughan, Attorney -in -Fact Name and Title Address: McGriff Insurance Services, Inc. 3100 Royal Blvd. South Alpharetta, GA 30022 Telephone Number: (770) 664-6818 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract from the by-laws showing that this person has authority to sign such obligation. If Surety's physical address is different from its mailing address, both must be provided. The date of the bond shall not be prior to the date the Contract is awarded. CITY OF FORT WORTH STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS Revised January 31, 2012 Landmark Quebec Addition 102418 POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY -IN -FACT Know All Men By These Presents, That Continental Casually Company, an Illinois insurance company, National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company (herein called "the CNA Companies"), are duly organized and existing insurance companies having their principal offices in the City of Chicago, and State of Illinois, and that they do by virtue of the signatures and seals herein affixed hereby make, constitute and appoint Travis G Huffines, Brian E Madden, Deborah B Sasser, Brittany L Triplett, Fedsa H Vaughan, Individually of Alpharetta, GA, their true and ]awful Attomey(s)-in-Fact with full power and authority hereby conferred to sign, seal and execute for and on their behalf bonds, undertakings and other obligatory instruments of similar nature - In Unlimited Amounts - and to bind them [hereby as fully and to the same extent as if such instruments were slgned by a duly authorized officer of their insurance companies and all the acts of said Attorney, pursuant to the authority hereby given Is hereby ratified and confirmed. This Power of Attorney is made and ezecutedpursuant [o and by authority of the By -Law and Reso]utions, printed on the reverse hereof, duly adopted, as indicated, by the Boards of Directors of the insurance companies. In Witness Whereof, the CNA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto affixed on this 30th day of March, 2020. �6A9Uq(rY �� INSURgyc `oMvpPr o<yF, OOPPOPATE L � `PCOePa i T 1t _�W�ry iuisoi i. R� SEAL Y Continental Casualty Company National Fire Insurance Company of Hartford American Ca Ity Company of Re ding, Pennsylvania Paul T. Bruflat'Kee President State of South Dakota, County of Minnehaha, as: On this 30th day of March, 2020, before me personally came Paul T. Bruflat to me known, who, being by me duly sworn, did depose and say: [hat he resides in the City of Sioux Falls, State of South Dakota; that he is a Vice President of Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company described in and which executed the above instrument; that he knows the seals of said insurance companies; that the. sealsaffixed to the said instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said insurance companies and that he signed his. name thereto pursuant to like authority, and acknowledges same to be the act and deed of said insurance companies. �i, J. MOHR �L! • IIII �� My Commission Expires June 23, 2021 J. Mohr v Notary Public CERTIFICATE I, D. Johnson, Assistant Secretary of Continental Casualty any, an Illinois insurance company, National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company ofReading, Pennsylvania, a Pennsylvania insurance company do hereby certify that the. Power of Attorney herein above set forth is. still in force; and further certify chat the By -Law and Resolution of the Board of Directors of the insurance companies printed on the reverse hereof is still in force. In testimony whereof I have hereunto subscribed my name and affixed the seal of the said insurance companies this day of , 2020, P� GAS Uq<)J- 0 pOPP011AiE F �U SEAL 1891 Form F6853-4/2012 CDU,vpnr o<Continental Casualty Company 'roe National Fire Insurance Company of Hartford 5 `PpasroNiira A American Casualty Company of Reading, Pennsylvania t 1U19 7I. f� `sky • D. Johnson Assistant Secretary Go to www.cnasurety.com > Owner /Obligee Services > Validate Bond Coverage, If you want to verify hood authenticity. Authorizing By -Laws and Resolutions ADOPTED BY THEBOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY: This Power of Attorney is made and executed pursuant to and by authority of the following resolution may adopted by the Board of Directors of the Company at a meeting held on May 12, 1995: "RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific cum a, agreements and instruments. an behalf of the Company provided that the time of such authorized officer and a description of the documents, agreements or instruments that such officer may sign wilt be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective." This Power of Attomey is signed by Paul T. Bruflat, Vtce President, who has been authorized pursuant la the above resolution to execute power of attorneys on behalf of Continental Casualty Company. This Power of Attomey is signed and sealed by facsimile under and by the authority of the Pollowing Resolution adopted by the Boars of Directors of the Company by unanimous written consent dated the 25" day of April, 2012: "Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute various policies, bonds, undertakings and other obligatory instruments of like nature; and Whereas, from time to time, the signature of the Authorized Officers, in addition. to being provided in original, hard copy forma[, may be provided vie facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore he it resolved: that the Electronic Signature of any Authorized Officer shall he valid and binding on the Company. " ADOPTED BV THE BOARD OF DIRECTORS OF NATIONAL FIRE INSURANCE COMPANY OF HARTFORD: This Power of Attomey is made and executed pursuant to and by authority of the foflowing resolution duly adopted by the Board of Directors of the Company by unanimous written consent dated May IO2 1995: "RESOLVED: 'that any Senior or Group Vice President may authorize an officer m sign specific documents, agreements and instruments on hetrelfof the Campany provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sigo will he provided in writing by the Senior or Group Vim President to the Secretary of the Company prior to such execution becoming effective." This Power of Attorney is signed by Paul T: Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on behalf of National Fire Insurance Company of Hartford. This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by unanimous written consent dated the 25'" day of Aprfl, 2012: "Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute various policies, hoods, undertakings and other ob0gatory instruments of like nature; and Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may he provided via facsimile or otherwise in an eleetrmric format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any Authorised Officer shall be valid and binding on the Company. " ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING, PENNSYLVANIA: This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the Company by unanimous written consent dated May 10, 1995: "RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective." This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on behalf of American Casualty Company of Reading, Paansylvania. This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by unanimous written consent dated the 250 day of April, 2012: "Whereas, the bylaws of the Company or specific resolution of the Hoard of Directors has authorized various officers (the "Authorized Officers")to execute various policies, lianas, undertakings and other obligatory instruments of like nature; and Whereas, from time to time; the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore he it resolved: that the Electronic Signature of any Authorized Officer shall be valid and binding on the Company. " 00 62 14 - 1 PAYMENT BOND Page 1 of 2 CITY OF FORT WORTH Landmark Quebec Addition STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS 102418 Revised January 31, 2012 SECTION 00 62 14 1 PAYMENT BOND 2 3 THE STATE OF TEXAS § 4 § KNOW ALL BY THESE PRESENTS: 5 COUNTY OF TARRANT § 6 That we, The Conlan Company, known as “Principal” herein, and Continental Casualty 7 Company, a corporate surety ( or sureties if more than one), duly authorized to do business in 8 the State of Texas, known as “Surety” herein (whether one or more), are held and firmly bound 9 unto the Developer, Lonestar Commerce Center, LLC, 750 North Saint Paul Street, Dallas, Texas, 10 authorized to do business in Texas “(Developer”), and the City of Fort Worth, a Texas municipal 11 corporation (“City”), in the penal sum of Four-Hundred Sixty - Eight Thousand Three - Hundred 12 and Seventy-Five Dollars and Thirty cents ($ 468,375.30), lawful money of the United States, to 13 be paid in Fort Worth, Tarrant County, Texas, for the payment of which sum well and truly be 14 made jointly unto the Developer and the City as dual obligees, we bind ourselves, our heirs, 15 executors, administrators, successors and assigns, jointly and severally, firmly by these presents: 16 WHEREAS, Developer and City have entered into an Agreement for the construction of 17 community facilities in the City of Fort Worth, by and through a Community Facilities 18 Agreement, CFA Number CFA20-0032 and 19 WHEREAS, Principal has entered into a certain written Contract with Developer, 20 awarded the 21 day of May, 2020, which Contract is hereby referred to and made a part hereof 21 for all purposes as if fully set forth herein, to furnish all materials, equipment, labor and other 22 accessories as defined by law, in the prosecution of the Work as provided for in said Contract 23 and designated as North City Addition Phase 1. 24 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if Principal shall 25 pay all monies owing to any (and all) payment bond beneficiary (as defined in Chapter 2253 of 26 the Texas Government Code, as amended) in the prosecution of the Work under the Contract, 27 then this obligation shall be and become null and void; otherwise to remain in full force and 28 effect. 29 This bond is made and executed in compliance with the provisions of Chapter 2253 of 30 the Texas Government Code, as amended, and all liabilities on this bond shall be determined in 31 accordance with the provisions of said statute. 32 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED this 33 instrument by duly authorized agents and officers on this the 21 day of May, 2020. 34 35 006214-2 1 2 3 4 5 6 7 8 (Princ/pal) Secretary " Witness as to Principal PAYMENTBOND Page 2 of 2 PRINCIPAL: The Conlan Company Signature /kKFvwy I2 7tAZpi U, P'2C'5)o&/UT Name and Title ••%GONLAN Cp''b. Address: 1800 Parkway Place, Suit quosesee PO :v _ Marietta, Georgia 3006E G OP be SEAL SURETY: • CFORWI ' Continental Casualty Company '--;987,,,,,, „tP ATTEST: /�4 / 8Y: (Surety) Brian E. Madden Alit ss as to Surety es H. V ghan, Jr. a v// Name and Title Felisa H, Vaughan Attorney -in -Fact Address: McGriff Insurance Services: Inc. 3100 ROVaIBIvd,$OUth Alpharetta, Georgia 30022 Telephone Number: (7701 664-6818 Note: If signed by an officer of the Surety, there must be on file a certified extract from the bylaws showing that this person has authority to sign such obligation. If Surety's physical address is different from its mailing address, both must be provided. The date of the bond shall not be prior to the date the Contract is awarded. END OF SECTION. CITY OF FORT WORTH STANDARD CITI CONDITIONS —DEVELOPER AWARDED PROlECrS Revised January 31, 2012 Landmark Quebec Addition 10241g POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY -IN -FACT Know All Men By These Presents, That Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company (herein called "the CNA Companies"), are duly organized and existing insurance companies having their principal offices in the City of Chicago, and State of Illinois, and that they do by virtue of the signatures and seals herein affixed hereby make, constitute and appoint Travis G Hufflnes, Brian E Madden, Deborah B Sasser, Brittany L Triplett, Felisa H Vaughan, Individually of Alpharetta, GA, their true and lawful Attomey(s)-in-Fact with full power and authority hereby conferred to sign, seal and execute for and on their behalf bonds, undertakings and other obligatory instruments of similar nature - In Unlimited Amounts - and to bind them [hereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of their insurance companies and all the acts of said Attorney, pursuant to the authority hereby given is hereby ratified and confirmed. This Power of Attorney is made and executed pursuant to and by authority of the By -Law and Resolutions, printed on the reverse hereof, duly adopted, as indicated, by the Boards of Directors of the insurance companies. In Witness Whereof, the-0NA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto affixed on this 30th day of March, 2020, USEAL �o�uAU>� 1NSURq,� yy��cvnNroA;t, J9i c:'• HA R7F • Continental Casualty Company National Fire Insurance Company of Hartford American Ca ]ty Company of Re ding, Pennsylvania Yaul T. Bruflat Ace President State of South Dakota, County of Minnehaha, as: On this 30th day of March, 202Q, before me personally came Paul T. Bruflat to me known, who, being by me duly sworn, did depose and say: that he resides in the City of Sioux Falls, State of South Dakota; that he is a Vice President of Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company described in and which executed the above instrument; that he knows the seals of said insurance companies; that the seals affixed to the said instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said insurance companies and that he signed his name thereto pursuant to like authority, and acknowledges same to be the act and deed of said insurance companies. e1$xIN! rtN0.Ulain WINMhYw/r///�Mi' My Commission Expires June 23, 2021 L Mohr Notary Public CERTIFICATE 1, D. Johnson, Assistant Secretary of Continental Casualty any, an Illinois insurance company, National Pire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company do hereby certifythat the Power ofAttorney herein above set Forth is still in force, and further certify that the By -Law and Resolution of the Board of Directors of the insurance companies printed on the reverse hereof is still in force. In testimony whereof I have hereunto subscribed my name and affixed the, sea] of the said insurance companies this day of , 2020. a, pnSOAtpy � 10SUR4� ANY M,t, ponPeaAre O^ $ Ypr,99PO9gT� o 1eisoi''�a� u SEAL t ,p 1891 HAIIIii • Form F6853-4/2012 Continental Casualty Company National Fire Insurance Company of Hartford American Casualty Company of Reading, Pennsylvania <0�0 0 j 6 V�� .Johnson Assistant Secretary Go to www.cnasuretv.com > Owner /Obligee Services > Validate Band Coverage, if you want to verify bond authenticity. Authorizing By -Laws and Resolutions ADOPTED BY THE BOARD Or DIRECTORS OF CONTINENTAL CASUALTY COMPANY: This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the Company at a meeting held on May 12, 19951 "RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the Company provided that the time of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective," This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on behalf of Continental Casualty Company. This Power of Attorney is signed and scaled by facsimile under and by the authority of the following Resolution adopted by the Baud of Directors of the Company by unanimous written consent dated the 25's day of April, 2012: "Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute various policies, bonds, undertakings and other obligatory instruments of like nature; and Whereas, from time to time, the signature of the Authorized Officers, in addition to being. provided in original, hard copy format, may he provided via facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any Authorized Officer shall he valid and binding on the Company. " ADOPTED BY THE BOARD OF Dll2HCTORS OP NATIONAL FIRE W SURANCE COMPANY OP HARTFORD: This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the Company by unanimous written consent dated May 10, 1995: "RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective." This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on behalf of National Fire Insurance Company of Hartford. This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by unanimous written consent dated the 251s day of April, 2012: "Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute various policies, bonds, undertakings and other obligatory instruments of like nature; and Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any Authorized Officer shalt be valid and binding on the Company, " ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING, PENNSYLVAMA: This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the Company by unanimous written consent dated May 10, 1995: "RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the Company provided that the time of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective." This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on behalf of American Casualty Company of Reading, Pennsylvania. This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by unanimous written consent dated the 256 day of April, 2012: "Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute various policies, bonds, undertakings and other obligatory instruments of like nature; and Whereas, from time to time, the signature of the Authorized Officers; in addition to being provided in original, hard copy format, may be provided via facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore he it resolved: that the Electronic Signature of my Authorized Officer shall be valid and binding on the Company. " 00 62 19 - 1 MAINTENANCE BOND Page 1 of 4 CITY OF FORT WORTH Landmark Quebec Addition STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS 102418 Revised January 31, 2012 SECTION 00 62 19 1 MAINTENANCE BOND 2 3 THE STATE OF TEXAS § BOND NUMBER: 30090315 4 § KNOW ALL BY THESE PRESENTS: 5 COUNTY OF TARRANT § 6 That we, The Conlan Company, known as “Principal” herein and Continental Casualty 7 Company, a corporate surety (sureties, if more than one), duly authorized to do business in the 8 State of Texas, known as “Surety” herein (whether one or more), are held and firmly bound unto 9 the Developer, Lonestar Commerce Center, LLC, 750 North Saint Paul Street, Dallas, Texas 10 75201, authorized to do business in Texas (“Developer”) and the City of Fort Worth, a Texas 11 municipal corporation (“City”), in the sum of Four-Hundred Sixty – Eight Thousand Three 12 Hundred and Seven-Five Dollars and Thirty cents ($468,375.30), lawful money of the United 13 States, to be paid in Fort Worth, Tarrant County, Texas, for payment of which sum well and truly 14 be made jointly unto the Developer and the City as dual obligees and their successors, we bind 15 ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, 16 firmly by these presents. 17 18 WHEREAS, Developer and City have entered into an Agreement for the construction of 19 community facilities in the City of Fort Worth by and through a Community Facilities Agreement, 20 CFA Number CFA20-0032and 21 WHEREAS, the Principal has entered into a certain written contract with the Developer 22 awarded the 21 day of May, 2020, which Contract is hereby referred to and a made part hereof 23 for all purposes as if fully set forth herein, to furnish all materials, equipment labor and other 24 accessories as defined by law, in the prosecution of the Work, including any Work resulting from 25 a duly authorized Change Order (collectively herein, the “Work”) as provided for in said Contract 26 and designated as Water and Sanitary Sewer Improvement to Landmark Quebec Addition; and 27 28 WHEREAS, Principal binds itself to use such materials and to so construct the Work in 29 accordance with the plans, specifications and Contract Documents that the Work is and will 30 006219-2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 MAINTENANCE BOND Page 2 of 3 WHEREAS, Principal binds itself to use such materials and to so construct the Work in accordance with the plans, specifications and Contract Documents that the Work is and will remain free from defects in materials or workmanship for and during the period of two (2) years after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part upon receiving notice from the Developer and/or City of the need thereof at any time within the Maintenance Period. NOW THEREFORE, the condition of this obligation is such that if Principal shall remedy any defective Work, for which timely notice was provided by Developer or City, to a completion satisfactory to the City, then this obligation shall become null and void; otherwise to remain in full force and effect. PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely noticed defective Work, it is agreed that the Developer or City may cause any and all such defective Work to be repaired and/or reconstructed with all associated costs thereof being borne by the Principal and the Surety under this Maintenance Bond; and PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort Worth Division; and PROVIDED FURTHER, that this obligation shall be continuous in nature and successive recoveries maybe had hereon for successive breaches. CITY OF FORT WORTH STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS Revised January 31, 2012 Landmark Quebec Addition 102418 006219-3 1 2 3 4 5 6 7 8 9 10 11 12 MAINTENANCE BOND Page 3 of 3 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED this instrument by duly authorized agents and officers on this the day of .20 ec� " u�L Witness as to Principal ATTEST: r E- (Suretyf Brian E. Madden Witn ss as to Surety /, Ja es H. Vaughan, PRINCIPAL: The Conlan Company BY: !� Signature X�//K) le-70K�111J EAT Name and Title %'tAUW CO,R�-'''� • SEAL:= ° SURETY: '110a„1987 ls »����`���,. Continental Casualty Company 4/ 4,101 BY: 0 - Signature Address: 1800 Parkway Place, Suite 1 Marietta, Georgia 30067 Felisa H. Vaughan, Attorney -in -Fact Name and Title Address: McGriff Insurance Services, Ift, 3100 Royal Blvd. South Alpharetta, Georgia 30022 Telephone Number: (770) 664-6818 Note: If signed by an officer of the Surety, there must be on file a certified extract from the bylaws showing that this person has authority to sign such obligation. If Surety's physical address is different from its mailing address, bath must be provided. The date of the bond shall not be prior to the date the Contract is awarded. END OF SECTION CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised January 31, 2012 Landmark Quebec Addition 102418 POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY -IN -FACT Know All Men By These Presents, That Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading; Pennsylvania, a Pennsylvania insurance company (herein called "the CNA Companies'), are duly organized and existing insurance companies having their principal offices in the City of Chicago, and State of Illinois, and that they do by virtue of the signatures and seals herein affixed hereby make, constitute and appoint Travis G HufYlnes, Brian E Madden, Deborah H Sasser, Brittany L Triplett, Fensa H Yanghan, Individually of Alpharetta, GA, their true and lawful Attomey(s)-in-Fact with full power and authority hereby conferred to sign, seal and execute for and on their behalf bonds, undertakings and other obligatory instruments of similar nature In Unlimited Amounts - and to bind them thereby as fully and to the same eaten[ as if such insWments were signed by a duly authorized officer of their insurance companies and all the acts of said Attorney, pursuant to the authority hereby given is hereby ratified and confirmed. This Power of Attomey is made and executed pursuant to and by authority ofhe By -Law and Resolutions, printed on the reverse hereof, duly adopted, as indicated, by the Boards of Directors of the insurance companies. In Witness Whereof, the CNA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto affixed on this 30th day of March, 2020, �GASt/q<Ty 1NSURq IL F ��Avpav gAy0, f( U000F:1P0AAr& a�1a0AiPsueiagI.tr0 � L y & HAW* s • Continental Casualty Company National Fire Insurance Company of Hartford American Callty Company of Re ding, Pennsylvania Paul T. Bmflat ce President State of South Dakota, County of Minnehaha, ss: On this 30th day of March, 2020, before me personally came Paul T. Bmflat to me known, who, being by me duly sworn, did depose and say: that he resides in the City of Sioux Falls, State of South Dakota; that he is a Vice President of Continental Casualty Company, an Illinois insurance company; National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company described in and which executed the above instmment; that he knows the seals of said insurance companies; that the seals affixed to the said instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said insurance companies and that he signed his name thereto pursuant to like authority,nod acknowledges same to be the act and deed of said insurance companies. �aourm WOTA� My Commission Expires June 23, 2021 J. Mohr Notary Public CERTIFICATE I, D. Johnson, Assistant Secretary of Continental Casualty any, an Illinoisinsurance company, National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company do hereby certify that the Power of Attorney herein above set forth is still in force, and further certify that the By -Law and Resolution of the Board of Directors of the insurance companies printed on the reverse hereof is still in force.. In testimony whereof I have hereunto subscribed my name and affixed the seal of the said insurance companies this day of 120206 �OAS llgtTy � 1NSU114yc pxr Pe,� F- GQPP: PAif °�, y $ �NCOA11 z �'ZvyG'I3 'J r2 soi �' Y, SEAL ta97. � XARtf� • Joi Form F68534/2012 Continental Casualty Company National Fue Insurance Company of Hartford American Casualty Company of Reading, Pennsylvania <00C 0 j O;V�� .Johnson Ir Assistant Secretary Go to www.cnasurety.com > Owner /Obligee Services > Validate Bond Coverage, if you want to verify bond authenticity. Authorizing By -Laws and Resolutions ADOPTED BY THE BOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY: This Power of Attorney is made and executed pursuant to and by authority of the following resolution duty adopted by the Board of Directors of the Company at a meeting held on May 12, 1995: "RESOLVED: That any can at or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on hehalf of the Company provided that the time of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will he provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective." This Power of Attamey is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution [o execute power ofettomeys on behalf of Continental Casualty Company. Phis Power of Attamey is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Hoard ofDirectors of the Company by unanimous written consent dated the 25" day of April, 2012: "Whereas,. the bylaws afthe Company or specific resolution of the Board ofDirecmrs has authorized various officers (the "Authorized Officers")to execute various policies, bonds, undertakings and other obligatory instruments of like nature; and Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be proviied via facsimile ar otherwise in not electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any Authorized Officer shall be valid and binding on the Company. " ADOPTED BY TBE BOARD OF DIRECTORS OF NATIONAL F[RE INSURANCE COMPANY OF HARTFORD: This. Power of Attomey is made and executed pursuant tc and 6y authority of the following resolution duly adopted by the Hoard of Directors of the Company by unanimous written consent dated May 10, 1995: "RESOLVED: 'Chat any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that sue h officer may sign will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective." This Power of Attomey is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attameys on behalf of Nafional Fire Insurance Company of Hartford. This Power of Attorney is signed and sealed by facsimile under and by the authority of the fallowing Resolution adopted by the Board of Directors of the Company by unmrimouswritten consent dated the 25" day of April, 2012: "Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute various policies, bonds, undertakings and other obligatory instruments of like nature; and Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, herd copy format, may be provided vie facsimile or otherwise in an electronic format (collectively, "Elcelronic Signaures"); Now therefore be it resolved: that the Electronic Signature of any Authorized Officer shall be valid and binding on the Company. " ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING„ PENNSYLVANIA: This Power of Attorney is made and executed pursuant to and by authority of the fo0owing resolution duly adopted by the Board of Directors of Ore Company by unanimous written consent doled May 10,.1995: "RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the Company provided that the name of such euthptized officer and a description pf the documents, agreements or insWments that such officer may sign will be provided inwriting by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective." This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on behalf of American Casualty Company of Reading, Pennsylvania, 'this Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by unanhnaus written consent dated the 25"day of April, 2012: "Whereas, the bylaws of Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute various policies, bonds; undertakings and other obligatory instruments of like nature; and Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore he it resolved: that the Electronic Signature of any Authorized Officer shall be valitl and binding on the Company. " This page has been left blank intentionally. THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. CONTRACTOR’S BLANKET ADDITIONAL INSURED ENDORSEMENT – FORM A This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART Policy Number Agency Number Policy Effective Date Policy Expiration Date Date Account Number Named Insured Agency Issuing Company 1. a. SECTION II - WHO IS AN INSURED is amended to add as an additional insured any person or organization: (1) Whom you are required to add as an additional insured on this policy under a written contract or written agreement relating to your business; or (2) Who is named as an additional insured under this policy on a certificate of insurance. b. The written contract, written agreement, or certificate of insurance must: (1) Require additional insured status for a time period during the term of this policy; and (2) Be executed prior to the "bodily injury", "property damage", or "personal and advertising injury" leading to a claim under this policy. c. If, however: (1) “Your work” began under a letter of intent or work order; and (2) The letter of intent or work order led to a written contract or written agreement within 30 days of beginning such work; and (3) Your customer’s customary contracts require persons or organizations to be named as additional insureds; we will provide additional insured status as specified in this endorsement. 2. The insurance provided under this endorsement is limited as follows: a. That person or organization is an additional insured only with respect to liability caused, in whole or in part, by: (1) Premises you: (a) Own; (b) Rent; (c) Lease; or (d) Occupy; (2) Ongoing operations performed by you or on your behalf. Ongoing operations does not apply to “bodily injury” or “property damage” occurring after: Includes copyrighted material of Insurance Services Office, Inc. CG 70 48 10 15 Pages 1 of 4 CPP205094112 01/01/2020 01/01/2021 The Conlan Company (a) All work to be performed by you or on your behalf for the additional insured(s) at the site of the covered operations is complete, including related materials, parts or equipment (other than service, maintenance or repairs); or (b) That portion of “your work” out of which the injury or damage arises is put to its intended use by any person or organization other than another contractor working for a principal as a part of the same project. (3) Completed operations coverage, but only if: (a) The written contract, written agreement, or certificate of insurance requires completed operations coverage or “your work” coverage; and (b) This coverage part provides coverage for “bodily injury” or “property damage” included within the “products-completed operations hazard”. However, the insurance afforded to such additional insured only applies to the extent permitted by law. b. If the written contract, written agreement, or certificate of insurance: (1) Requires “arising out of” language; or (2) Requires you to provide additional insured coverage to that person or organization by the use of either or both of the following: (a) Additional Insured – Owners, Lessees or Contractors – Scheduled Person Or Organization endorsement CG 20 10 10 01; or (b) Additional Insured – Owners, Lessees or Contractors – Completed Operations endorsement CG 20 37 10 01; then the phrase “caused, in whole or in part, by” in paragraph 2.a. above is replaced by “arising out of”. c. If the written contract, written agreement, or certificate of insurance requires you to provide additional insured coverage to that person or organization by the use of: (1) Additional Insured – Owners, Lessees or Contractors – Scheduled Person Or Organization endorsement CG 20 10 07 04 or CG 20 10 04 13; or (2) Additional Insured – Owners, Lessees or Contractors – Completed Operations endorsement CG 20 37 07 04 or CG 20 37 04 13; or (3) Both those endorsements with either of those edition dates; or (4) Either or both of the following: (a) Additional Insured – Owners, Lessees or Contractors – Scheduled Person Or Organization endorsement CG 20 10 without an edition date specified; or (b) Additional Insured – Owners, Lessees or Contractors – Completed Operations endorsement CG 20 37 without an edition date specified; then paragraph 2.a. above applies. d. Premises, as respects paragraph 2.a.(1) above, include common or public areas about such premises if so required in the written contract or written agreement. e. Additional insured status provided under paragraphs 2.a.(1)(b) or 2.a.(1)(c) above does not extend beyond the end of a premises lease or rental agreement. f. The limits of insurance that apply to the additional insured are the least of those specified in the: (1) Written contract; (2) Written agreement; (3) Certificate of insurance; or (4) Declarations of this policy. The limits of insurance are inclusive of and not in addition to the limits of insurance shown in the Declarations. Includes copyrighted material of Insurance Services Office, Inc. Page 2 of 4 CG 70 48 10 15 g. The insurance provided to the additional insured does not apply to "bodily injury", "property damage", or "personal and advertising injury" arising out of an architect’s, engineer’s, or surveyor’s rendering of, or failure to render, any professional services, including but not limited to: (1) The preparing, approving, or failing to prepare or approve: (a) Maps; (b) Drawings; (c) Opinions; (d) Reports; (e) Surveys; (f) Change orders; (g) Design specifications; and (2) Supervisory, inspection, or engineering services. h. SECTION IV – COMMERCIAL GENERAL LIABILITY CONDITIONS, paragraph 4. Other Insurance is deleted and replaced with the following: 4. Other Insurance. Coverage provided by this endorsement is excess over any other valid and collectible insurance available to the additional insured whether: a. Primary; b. Excess; c. Contingent; or d. On any other basis; but if the written contract, written agreement, or certificate of insurance requires primary and non- contributory coverage, this insurance will be primary and non-contributory relative to other insurance available to the additional insured which covers that person or organization as a Named Insured, and we will not share with that other insurance. i. If the written contract, written agreement, or certificate of insurance as outlined above requires additional insured status by use of CG 20 10 11 85, then the coverage provided under this CG 70 48 endorsement does not apply except for paragraph 2.h. Other Insurance. Additional insured status is limited to that provided by CG 20 10 11 85 shown below and paragraph 2.h. Other Insurance shown above. ADDITIONAL INSURED - OWNERS, LESSEES OR CONTRACTORS (FORM B) This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART. SCHEDULE Name of Person or Organization: Blanket Where Required by Written Contract, Agreement, or Certificate of Insurance that the terms of CG 20 10 11 85 apply (If no entry appears above, information required to complete this endorsement will be shown in the Declarations as applicable to this endorsement.) WHO IS AN INSURED (Section II) is amended to include as an insured the person or organization shown in the Schedule, but only with respect to liability arising out of "your work" for that insured by or for you. CG 20 10 11 85 Copyright, Insurance Services Office, Inc., 1984 Includes copyrighted material of Insurance Services Office, Inc. CG 70 48 10 15 Pages 3 of 4 j. The insurance provided by this endorsement does not apply to any premises or work for which the person or organization is specifically listed as an additional insured on another endorsement attached to this policy. Includes copyrighted material of Insurance Services Office, Inc. Page 4 of 4 CG 70 48 10 15 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. CONTRACTORS GENERAL LIABILITY EXTENSION ENDORSEMENT This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE FORM Under SECTION I - COVERAGE A. BODILY INJURY AND PROPERTY DAMAGE LIABILITY, paragraph 2. EXCLUSIONS, provisions 1. through 6. of this endorsement amend the policy as follows: 1. LIQUOR LIABILITY Exclusion c. Liquor Liability is deleted. 2. NONOWNED WATERCRAFT AND NONOWNED AIRCRAFT (HIRED, RENTED OR LOANED WITH PAID CREW) Exclusion g. Aircraft, Auto or Watercraft, paragraph (2)is deleted and replaced with the following: (2) A watercraft you do not own that is: (a) Less than 51 feet long; and (b) Not being used to carry persons or property for a charge; Exclusion g. Aircraft, Auto or Watercraft, paragraph (6) is added as follows: (6) An aircraft that you do not own that is: (a) Hired; (b) Rented; or (c) Loaned to you; with paid crew for a period of five (5) consecutive days or less. Paragraph (6) does not apply if the insured has any other insurance for “bodily injury or “property damage” liability for such aircraft, whether such other insurance is primary, excess, contingent or on any other basis. 3. PREMISES ALIENATED A. Exclusion j. Damage to Property, paragraph (2) is deleted. B. The following paragraph is also deleted from Exclusion j. Damage to Property: Paragraph (2) of this exclusion does not apply if the premises are “your work” and were never occupied, rented or held for rental by you. 4. PROPERTY DAMAGE LIABILITY - ELEVATORS AND SIDETRACK AGREEMENTS A. Exclusion j. Damage to Property, paragraphs (3), (4), and (6) do not apply to the use of elevators. B. Exclusion k. Damage to Your Product does not apply to: 1. The use of elevators; or 2. Liability assumed under a sidetrack agreement. 5. PROPERTY DAMAGE LIABILITY - BORROWED EQUIPMENT A. Exclusion j. Damage to Property, paragraph (4) does not apply to "property damage" to borrowed equipment while at a jobsite and not being used to perform operations. Includes copyrighted material of Insurance Services Office, Inc. CG 70 49 11 09 Page 1 of 10 B. With respect to any one borrowed equipment item, provision 5.A. above does not apply to "property damage" that exceeds $25,000 per occurrence or $25,000 annual aggregate. 6. PRODUCT RECALL EXPENSE A.Exclusion n. Recall Of Products, Work Or Impaired Property does not apply to “product recall expenses” that you incur for the “covered recall” of “your product”. This exception to the exclusion does not apply to “product recall expenses” resulting from: 1. Failure of any products to accomplish their intended purpose; 2. Breach of warranties of fitness, quality, durability or performance; 3. Loss of customer approval or any cost incurred to regain customer approval; 4. Redistribution or replacement of “your product”, which has been recalled, by like products or substitutes; 5. Caprice or whim of the insured; 6. A condition likely to cause loss, about which any insured knew or had reason to know at the inception of this insurance; 7. Asbestos, including loss, damage or clean up resulting from asbestos or asbestos containing materials; 8. Recall of “your product(s)” that have no known or suspected defect solely because a known or suspected defect in another of “your product(s)” has been found. B.Under SECTION III – LIMITS OF INSURANCE, paragraph 3. is replaced in its entirety as follows and paragraph 8. is added: 3. The Products-Completed Operations Aggregate Limit is the most we will pay for the sum of: a. Damages under COVERAGE A BODILY INJURY AND PROPERTY DAMAGE LIABILITY because of “bodily injury” and “property damage” included in the “products-completed operations hazard” and b. “Product recall expenses”. 8. Subject to paragraph 5.above, $25,000 is the most we will pay for all “product recall expenses” arising out of the same defect or deficiency. The insurance afforded by provisions 1. through 6. of this endorsement is excess over any valid and collectible insurance (including any deductible) available to the insured whether primary, excess or contingent, and SECTION IV.,paragraph 4. Other Insurance is changed accordingly. 7. BLANKET CONTRACTUAL LIABILITY – RAILROADS When a written contract or written agreement requires Contractual Liability - Railroads, the definition of "insured contract" in Section V - Definitions is replaced by the following with respect to operations performed for, or affecting, a railroad: 9. "Insured Contract" means: a. A contract for a lease of premises. However, that portion of the contract for a lease of premises that indemnifies any person or organization for damage by fire to premises while rented to you or temporarily occupied by you with permission of the owner is not an "insured contract"; b. A sidetrack agreement; c. Any easement or license agreement; d. An obligation, as required by ordinance, to indemnify a municipality, except in connection with work for a municipality; Includes copyrighted material of Insurance Services Office, Inc. Page 2 of 10 CG 70 49 11 09 e. An elevator maintenance agreement; f. That part of any other contract or agreement pertaining to your business (including an indemnification of a municipality in connection with work performed for a municipality) under which you assume the tort liability of another party to pay for "bodily injury" or "property damage" to a third person or organization. Tort liability means a liability that would be imposed by law in the absence of any contract or agreement. Paragraph f. does not include that part of any contract or agreement: (1) That indemnifies an architect, engineer or surveyor for injury or damage arising out of: (a) Preparing, approving or failing to prepare or approve maps, shop drawings, opinions, reports, surveys, field orders, change orders or drawings and specifications; or (b) Giving directions or instructions, or failing to give them; (2) Under which the insured, if an architect, engineer or surveyor, assumes liability for an injury or damage arising out of the insured's rendering or failure to render professional services, including those listed in Paragraph (1) above and supervisory, inspection, architectural or engineering activities. 8. CONTRACTUAL LIABILITY - PERSONAL AND ADVERTISING INJURY Under SECTION 1 - COVERAGE B., paragraph 2. Exclusions, paragraph e. Contractual Liability is deleted. 9. SUPPLEMENTARY PAYMENTS Under SECTION I - SUPPLEMENTARY PAYMENTS - COVERAGES A AND B, paragraphs 1.b. and 1.d. are deleted and replaced with the following: b. Up to $2,500 for cost of bail bonds required because of accidents or traffic law violations arising out of the use of any vehicle to which the Bodily Injury Liability Coverage applies. We do not have to furnish these bonds. d. All reasonable expenses incurred by the insured at our request to assist us in the investigation or defense of the claim or “suit”, including actual loss of earnings up to $500 a day because of time off from work. 10. BROADENED WHO IS AN INSURED SECTION II - WHO IS AN INSURED is deleted and replaced with the following: 1. If you are designated in the Declarations as: a. An individual, you and your spouse are insureds, but only with respect to the conduct of a business of which you are the sole owner. b. A partnership or joint venture, you are an insured. Your members, your partners, and their spouses are also insureds, but only with respect to the conduct of your business. c. A limited liability company, you are an insured. Your members are also insureds, but only with respect to the conduct of your business. Your managers are insureds, but only with respect to their duties as your managers. d. An organization other than a partnership, joint venture or limited liability company, you are an insured. Your "executive officers" and directors are insureds, but only with respect to their duties as your officers or directors. Your stockholders are also insureds, but only with respect to their liability as stockholders. e. A trust, you are an insured. Your trustees are also insureds, but only with respect to their duties as trustees. Includes copyrighted material of Insurance Services Office, Inc. CG 70 49 11 09 Page 3 of 10 2. Each of the following is also an insured: a. Your “volunteer workers” only while performing duties related to the conduct of your business, or your "employees," other than either your "executive officers," (if you are an organization other than a partnership, joint venture or limited liability company) or your managers (if you are a limited liability company), but only for acts within the scope of their employment by you or while performing duties related to the conduct of your business. However, none of these "employees" or “volunteer workers” are insured for: (1) "Bodily injury" or "personal and advertising injury": (a) To you, to your partners or members (if you are a partnership or joint venture), to your members (if you are a limited liability company), to a co-"employee" while in the course of his or her employment or performing duties related to the conduct of your business, or to your other “volunteer workers” while performing duties related to the conduct of your business; (b) To the spouse, child, parent, brother or sister of that co-"employee" or “volunteer worker” as a consequence of paragraph (1)(a) above; (c) For which there is any obligation to share damages with or repay someone else who must pay damages because of the injury described in paragraphs (1)(a) or (b) above; or (d) Arising out of his or her providing or failing to provide professional health care services except as provided in provision 11. of this endorsement. Paragraphs (1)(a), (1)(b) and (1)(c) above do not apply to your “employees” who are: (i) Managers; (ii) Supervisors; (iii) Directors; or (iv) Officers; with respect to “bodily injury” to a co-“employee”. (2) "Property damage" to property: (a) Owned, occupied or used by; (b) Rented to, in the care, custody or control of, or over which physical control is being exercised for any purpose by you, any of your "employees," “volunteer workers”, any partner or member (if you are a partnership or joint venture), or any member (if you are a limited liability company). b. Any person (other than your "employee" or “volunteer worker”), or any organization while acting as your real estate manager. c. Any person or organization having proper temporary custody of your property if you die, but only; (1) With respect to liability arising out of the maintenance or use of that property; and (2) Until your legal representative has been appointed. d. Your legal representative if you die, but only with respect to duties as such. That representative will have all your rights and duties under this Coverage Form. e. Your subsidiaries if: (1) They are legally incorporated entities; and (2) You own more than 50% of the voting stock in such subsidiaries as of the effective date of this policy. Includes copyrighted material of Insurance Services Office, Inc. Page 4 of 10 CG 70 49 11 09 If such subsidiaries are not shown in the Declarations, you must report them to us within 180 days of the inception of your original policy. f.(1) Any person or organization, other than an architect, engineer or surveyor, required to be named as an additional insured in a "work contract", letter of intent or work order. However, such person or organization shall be an additional insured only with respect to covered "bodily injury," "property damage," and "personal and advertising injury" arising out of “your work" under that "work contract", letter of intent or work order. (2) We will provide additional insured coverage to such person or organization only: (a) for a period of 30 days after the effective date of the applicable "work contract", letter of intent or work order; or (b) until the end of the policy term in effect at the inception of the applicable “work contract”, letter of intent or work order; whichever is earlier. (3) Coverage provided under this paragraph f. is excess over any other valid and collectible insurance available to the additional insured whether primary, excess, contingent, or on any other basis unless the “work contract”, letter of intent or work order requires this insurance be primary, in which case this insurance will be primary without contribution from such other insurance available to the additional insured. (4) This paragraph f. does not apply if form CG 70 48, Contractors Blanket Additional Insured Endorsement, is attached to the policy. g.Any person or organization to whom you are obligated by virtue of a written contract to provide insurance such as is afforded by this policy, but only with respect to liability arising out of the maintenance or use of that part of any premises leased to you, including common or public areas about such premises if so required in the contract. However, no such person or organization is an insured with respect to: (1) Any "occurrence" that takes place after you cease to occupy those premises; or (2) Structural alterations, new construction or demolition operations performed by or on behalf of such person or organization. h. Any state or political subdivision but only as respects legal liability incurred by the state or political subdivision solely because it has issued a permit with respect to operations performed by you or on your behalf. However, no state or political subdivision is an insured with respect to: (1) "Bodily injury", "property damage", and "personal and advertising injury" arising out of operations performed for the state or municipality; or (2) "Bodily injury" or "property damage" included within the "products-completed operations hazard." i. Any person or organization who is the lessor of equipment leased to you to whom you are obligated by virtue of a written contact to provide insurance such as is afforded by this policy, but only with respect to their liability arising out of the maintenance, operation or use of such equipment by you or a subcontractor on your behalf with your permission and under your supervision. However, no such person or organization is an insured with respect to any "occurrence" that takes place after the equipment lease expires. j. Any architect, engineer, or surveyor engaged by you but only with respect to liability arising out of your premises or "your work." Includes copyrighted material of Insurance Services Office, Inc. CG 70 49 11 09 Page 5 of 10 However, no architect, engineer, or surveyor is an insured with respect to "bodily injury," "property damage," or "personal and advertising injury" arising out of the rendering of or the failure to render any professional services by or for you, including: (1) The preparing, approving, or failing to prepare or approve maps, drawings, opinions, reports, surveys, change orders, designs or specifications; or (2) Supervisory, inspection, or engineering services. This paragraph j. does not apply if form CG 70 48, Contractors Blanket Additional Insured Endorsement, is attached to the policy. k. Any manager, owner, lessor, mortgagee, assignee or receiver of premises, including land leased to you, but only with respect to liability arising out of the ownership, maintenance or use of that part of the premises or land leased to you. However, no such person or organization is an insured with respect to: (1) Any "occurrence" that takes place after you cease to occupy that premises, or cease to lease the land; or (2) Structural alteration, new construction or demolition operations performed by or on behalf of that person or organization. 3. Any organization you newly acquire or form, other than a partnership, joint venture or limited liability company and over which you maintain ownership or majority interest, will qualify as a Named Insured if there is no other similar insurance available to that organization. However: a. Coverage under this provision is afforded until the end of the policy period. b. Coverage A does not apply to "bodily injury" or "property damage" that occurred before you acquired or formed the organization. c. Coverage B does not apply to "personal and advertising injury" arising out of an offense committed before you acquired or formed the organization. d. Coverage A does not apply to “product recall expense” arising out of any withdrawal or recall that occurred before you acquired or formed the organization. 4. Any person or organization (referred to below as vendor) with whom you agreed, because of a written contract or agreement to provide insurance is an insured, but only with respect to "bodily injury" or "property damage" arising out of "your products" that are distributed or sold in the regular course of the vendor's business. However, no such person or organization is an insured with respect to: a."Bodily injury" or "property damage" for which the vendor is obligated to pay damages by reason of the assumption of liability in a contract or agreement. This exclusion does not apply to liability for damages that the vendor would have in the absence of the contract or agreement. b. Any express warranty unauthorized by you; c. Any physical or chemical change in “your product” made intentionally by the vendor; d. Repackaging, except when unpacked solely for the purpose of inspection, demonstration, testing, or the substitution of parts under instructions from the manufacturer, and then repackaged in the original container; e. Any failure to make such inspections, adjustments, tests or servicing as the vendor has agreed to make or normally undertakes to make in the usual course of business, in connection with the distribution or sale of “your products”; f. Demonstration, installation, servicing or repair operations, except such operations performed at the vendor's premises in connection with the sale of “your product”; Includes copyrighted material of Insurance Services Office, Inc. Page 6 of 10 CG 70 49 11 09 g. “Your products” which, after distribution or sale by you, have been labeled or relabeled or used as a container, part or ingredient of any other thing or substance by or for the vendor. h. “Bodily injury” or “property damage” arising out of the sole negligence of the vendor for its own acts or omissions or those of its employees or anyone else acting on its behalf. However, this exclusion does not apply to: (1) The exceptions contained in subparagraphs d. or f.; or (2) Such inspections, adjustments, tests or servicing as the vendor has agreed to make or normally undertakes to make in the usual course of business, in connection with the distribution or sale of the products. This insurance does not apply to any insured person or organization from which you have acquired “your products”, or any ingredient, part, or container, entering into, accompanying or containing “your products”. No person or organization is an insured with respect to the conduct of any current or past partnership, joint venture or limited liability company that is not shown as a Named Insured in the Declarations. 11. INCIDENTAL MALPRACTICE LIABILITY As respects provision 10., SECTION II - WHO IS AN INSURED, paragraph 2.a.(1)(d) does not apply to any nurse, emergency medical technician or paramedic employed by you to provide medical or paramedical services, provided that you are not engaged in the business or occupation of providing such services, and your “employee” does not have any other insurance that would also cover claims arising under this provision, whether the other insurance is primary, excess, contingent or on any other basis. Under SECTION III - LIMITS OF INSURANCE, provisions 12. through 14. of this endorsement amend the policy as follows: 12. AGGREGATE LIMITS PER PROJECT The General Aggregate Limit applies separately to each of your construction projects away from premises owned by or rented to you. 13. INCREASED MEDICAL PAYMENTS LIMIT AND REPORTING PERIOD A.The requirement under SECTION I - COVERAGE C MEDICAL PAYMENTS that expenses be incurred and reported to us within one year of the date of the accident is changed to three years. B.SECTION III - LIMITS OF INSURANCE, paragraph 7., the Medical Expense Limit, is subject to all of the terms of SECTION III - LIMITS OF INSURANCE and is the greater of: 1. $10,000; or 2. The amount shown in the Declarations for Medical Expense Limit. C. This provision 13. does not apply if COVERAGE C MEDICAL PAYMENTS is excluded either by the provisions of the Coverage Form or by endorsement. 14. DAMAGE TO PREMISES RENTED TO YOU – SPECIFIC PERILS A.The word fire is changed to "specific perils" where it appears in: 1.The last paragraph of SECTION I – COVERAGE A, paragraph 2. Exclusions; 2. SECTION IV, paragraph 4.b. Excess Insurance. B. The Limits of Insurance shown in the Declarations will apply to all damage proximately caused by the same event, whether such damage results from a "specific peril" or any combination of "specific perils." C. The Damage To Premises Rented To You Limit described in SECTION III - LIMITS OF INSURANCE, paragraph 6., is replaced by a new limit, which is the greater of: 1. $1,000,000; or Includes copyrighted material of Insurance Services Office, Inc. CG 70 49 11 09 Page 7 of 10 2. The amount shown in the Declarations for Damage To Premises Rented To You Limit. D. This provision 14.does not apply if the Damage To Premises Rented To You Limit of SECTION I - COVERAGE A is excluded either by the provisions of the Coverage Form or by endorsement. Under SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, provisions 15. through 17. of this endorsement amend the policy as follows: 15. KNOWLEDGE OF OCCURRENCE Under 2. Duties In The Event Of Occurrence, Offense, Claim, Or Suit, paragraph a. is deleted and replaced and paragraphs e.and f. are added as follows: a.You must see to it that we are notified as soon as practicable of an "occurrence" or an offense, regardless of the amount, which may result in a claim. Knowledge of an "occurrence" or an offense by your “employee(s)” shall not, in itself, constitute knowledge to you unless one of your partners, members, “executive officers”, directors, or managers has knowledge of the "occurrence" or offense. To the extent possible, notice should include: (1) How, when and where the "occurrence" or offense took place; (2) The names and addresses of any injured persons and witnesses; and (3) The nature and location of any injury or damage arising out of the "occurrence" or offense. e. If you report an “occurrence” to your workers compensation carrier that develops into a liability claim for which coverage is provided by the Coverage Form, failure to report such an “occurrence” to us at the time of the “occurrence” shall not be deemed a violation of paragraphs a., b., and c.above. However, you shall give written notice of this “occurrence” to us as soon you become aware that this “occurrence” may be a liability claim rather than a workers compensation claim. f.You must see to it that the following are done in the event of an actual or anticipated “covered recall” that may result in “product recall expense”: (1) Give us prompt notice of any discovery or notification that “your product” must be withdrawn or recalled. Include a description of “your product” and the reason for the withdrawal or recall; (2) Cease any further release, shipment, consignment or any other method of distribution of like or similar products until it has been determined that all such products are free from defects that could be a cause of loss under the insurance. 16. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS Paragraph 6. Representations is deleted and replaced with the following: 6. Representations By accepting this policy, you agree: a. The statements in the Declarations are accurate and complete; b. Those statements are based upon representations you made to us; c. We have issued this policy in reliance upon your representations; and d. This policy is void in any case of fraud by you as it relates to this policy or any claim under this policy. We will not deny coverage under this coverage part if you unintentionally fail to disclose all hazards existing as of the inception date of this policy. You must report to us any knowledge of an error or omission in the description of any premises or operations intended to be covered by the Coverage Form as soon as practicable after its discovery. However, this provision does not affect our right to collect additional premium or exercise our right of cancellation or nonrenewal. Includes copyrighted material of Insurance Services Office, Inc. Page 8 of 10 CG 70 49 11 09 17. TRANSFER OF RIGHTS (BLANKET WAIVER OF SUBROGATION) Paragraph 8. Transfer of Rights Of Recovery Against Others To Us is deleted and replaced with the following: 8. If the insured has rights to recover all or part of any payment we have made under this Coverage Form, those rights are transferred to us. The insured must do nothing after loss to impair them. At our request, the insured will bring "suit" or transfer those rights to us and help us enforce them. However, if the insured has waived rights to recover through a written contract, or if "your work" was commenced under a letter of intent or work order, subject to a subsequent reduction to writing with customers whose customary contracts require a waiver, we waive any right of recovery we may have under this Coverage Form. 18. EXTENDED NOTICE OF CANCELLATION AND NONRENEWAL Paragraph 2.b.of A. Cancellation of the COMMON POLICY CONDITIONS is deleted and replaced with the following: b. 60 days before the effective date of the cancellation if we cancel for any other reason. Under SECTION IV – COMMERCIAL GENERAL LIABILITY CONDITIONS, Paragraph 9. When We Do Not Renew is deleted and replaced with the following: 9. When We Do Not Renew If we decide not to renew this Coverage Part, we will mail or deliver to the first Named Insured shown in the Declarations written notice of the nonrenewal not less than 60 days before the expiration date. If notice is mailed, proof of mailing will be sufficient proof of notice. 19. MOBILE EQUIPMENT REDEFINED Under SECTION V - DEFINITIONS, paragraph 12. "Mobile equipment", paragraph f. (1) does not apply to self- propelled vehicles of less than 1,000 pounds gross vehicle weight. 20. DEFINITIONS 1. SECTION V – DEFINITIONS, paragraph 4. “Coverage territory” is replaced by the following definition: “Coverage territory” means anywhere in the world with respect to liability arising out of “bodily injury,” “property damage,” or “personal and advertising injury,” including “personal and advertising injury” offenses that take place through the Internet or similar electronic means of communication provided the insured’s responsibility to pay damages is determined in a settlement to which we agree or in a “suit” on the merits, in the United States of America (including its territories and possessions), Puerto Rico and Canada. 2. SECTION V – DEFINITIONS is amended by the addition of the following definitions: “Covered recall” means a recall made necessary because you or a government body has determined that a known or suspected defect, deficiency, inadequacy, or dangerous condition in “your product” has resulted or will result in “bodily injury” or “property damage”. “Product Recall expenses" mean only reasonable and necessary extra costs, which result from or are related to the recall or withdrawal of “your product” for: a. Telephone and telegraphic communication, radio or television announcements, computer time and newspaper advertising; b. Stationery, envelopes, production of announcements and postage or facsimiles; c. Remuneration paid to regular employees for necessary overtime or authorized travel expense; d. Temporary hiring by you or by agents designated by you of persons, other than your regular employees, to perform necessary tasks; Includes copyrighted material of Insurance Services Office, Inc. CG 70 49 11 09 Page 9 of 10 e. Rental of necessary additional warehouse or storage space; f. Packaging of or transportation or shipping of defective products to the location you designate; and g. Disposal of “your products” that cannot be reused. Disposal expenses do not include: (1) Expenses that exceed the original cost of the materials incurred to manufacture or process such product; and (2) Expenses that exceed the cost of normal trash discarding or disposal, except as are necessary to avoid “bodily injury” or “property damage”. "Specific Perils" means fire; lightning; explosion; windstorm or hail; smoke; aircraft or vehicles; riot or civil commotion; vandalism; leakage from fire extinguishing equipment; weight of snow, ice or sleet; or "water damage". "Water damage" means accidental discharge or leakage of water or steam as the direct result of the breaking or cracking of any part of a system or appliance containing water or steam. "Work contract" means a written agreement between you and one or more parties for work to be performed by you or on your behalf. Includes copyrighted material of Insurance Services Office, Inc. Page 10 of 10 CG 70 49 11 09 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. ADVANTAGE COMMERCIAL AUTOMOBILE BROAD FORM ENDORSEMENT This endorsement modifies insurance provided under the BUSINESS AUTO COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement. The premium for this endorsement is $ INCLUDED 1. EXTENDED CANCELLATION CONDITION COMMON POLICY CONDITIONS -CANCELLATION, Paragraph A.2. is replaced by the following: 2. We may cancel this policy by mailing or delivering to the first Named Insured written notice of cancellation at least: a. 10 days before the effective date of cancellation if we cancel for nonpayment of premium; or b. 60 days before the effective date of cancellation if we cancel for any other reason. 2. BROADFORMINSURED SECTION II -LIABILITY COVERAGE A.1. WHO IS AN INSURED is amended by the addition of the following: d. Any organization you newly acquire or form, other than a partnership, joint venture or limited liability company, and over which you maintain ownership or a majority interest, will qualify as a Named Insured. However. (1) Coverage under this provision is afforded only until the end of the policy period; (2) Coverage does not apply to "accidents" or "loss" that occurred before you acquired or formed the organization; and (3) Coverage does not apply to an organization that is an "insured" under any other policy or would be an "insured" but for its termination or the exhausting of its limit of insurance. e. Any "employee" of yours using: (1) A covered "auto" you do not own, hire or borrow, or a covered "auto" not owned by the "employee" or a member of his or her household, while performing duties related to the conduct of your business or your personal affairs; or (2) An "auto" hired or rented under a contract or agreement in that "employee's" name, with your permission, while performing duties related to the conduct of your business. However, your "employee" does not qualify as an insured under this paragraph (2) while using a covered "auto" rented from you or from any member of the "employee's" household. f. Your members, if you are a limited liability company, while using a covered "auto" you do not own, hire, or borrow. while performing duties related to the conduct of your business or your personal affairs. g. Any person or organization with whom you agree in a written contract, written agreement or permit, to provide insurance such as is afforded under this policy, but only with respect to your covered "autos". This provision does not apply: (1) Unless the written contract or agreement is executed or the permit is issued prior to the "bodily injury" or "property damage"; lnclud€s copyrighted materia~ of Insurance Services Office, Inc. CA 71 15 11 09 Page 1 of 5 The Conlan Company CA2050943120 (2) To any person or organization included as an insured by an endorsement or in the Declarations; or (3) To any lessor of "autos" unless: (a) The lease agreement requires you to provide direct primary insurance for the lessor; (b) The "auto" is leased without a driver; and (c) The lease had not expired. Leased "autos" covered under this provision will be considered covered "autos" you own and not covered "autos" you hire. h. Any legally incorporated organization or subsidiary in which you own more than 50% of the voting stock on the effective date of this endorsement. This provision does not apply to "bodily injury" or "property damage" for which an "insured" is also an insured under any other automobile policy or would be an insured under such a policy, but for its termination or the exhaustion of its limits of insurance, unless such policy was written to apply specifically in excess of this policy. 3. COVERAGE EXTENSIONS-SUPPLEMENTARY PAYMENTS Under SECTION II-LIABILITY COVERAGE, A.2.a. Supplementary Payments, paragraphs (2) and (4) are deleted and replaced with the following: (2) Up to $2500 for the cost of bail bonds (including bonds for related traffic law violations) required because of an "accident" we cover. We do not have to furnish these bonds. (4) All reasonable expenses incurred by the "insured" at our request, including actual loss of earnings up to $500 a day because of time off from work. 4. AMENDED FELLOW EMPLOYEE EXCLUSION SECTION II -LIABILITY COVERAGE, B. EXCLUSIONS, paragraph 5. Fellow Employee is deleted and replaced by the following: 5. Fellow Employee "Bodily injury" to: a. Any fellow "employee" of the "insured" arising out of and in the course of the fellow "employee's" employment or while performing duties related to the conduct of your business. However, this exclusion does not apply to your "employees" that are officers, managers, supervisors or above. Coverage is excess over any other collectible insurance. b. The spouse, child, parent, brother or sister of that fellow "employee" as a consequence of paragraph a. above. 5. HIRED AUTO PHYSICAL DAMAGE COVERAGE AND LOSS OF USE EXPENSE A. Under SECTION Ill -PHYSICAL DAMAGE COVERAGE, A. COVERAGE, the following is added: If any of your owned covered "autos" are covered for Physical Damage, we will provide Physical Damage coverage to "autos" that you or your "employees" hire or borrow, under your name or the "employee's" name, for the purpose of doing your work. We will provide coverage equal to the broadest physical damage coverage applicable to any covered "auto" shown in the Declarations, Item Three, Schedule of Covered Autos You Own, or on any endorsements amending this schedule. B. Under SECTION Ill -PHYSICAL DAMAGE COVERAGE, A.4. COVERAGE EXTENSIONS, paragraph b. Loss of Use Expenses is deleted and replaced with the following: b. Loss Of Use Expenses Page 2 of 5 For Hired Auto Physical Damage, we will pay expenses for which an "insured" becomes legally responsible to pay for loss of use of a vehicle rented or hired without a driver, under a written rental contract or agreement. We will pay for loss of use expenses if caused by: Includes copyrighted material of Insurance Services Office, Inc. CA711511 09 (1) Other than collision, only if the Declarations indicate that Comprehensive Coverage is provided for any covered "auto"; (2) Specified Causes of Loss, only if the Declarations indicate that Specified Causes Of Loss Coverage is provided for any covered "auto"; or (3) Collision, only if the Declarations indicate that Collision Coverage is provided for any covered "auto". However, the most we will pay for any expenses for loss of use is $30 per day, to a maximum of $2,000. C. Under SECTION IV-BUSINESS AUTO CONDITIONS, paragraph 5.b. Other Insurance is deleted and replaced by the following: b. For Hired Auto Physical Damage Coverage, the following are deemed to be covered "autos" you own: 1. Any covered "auto" you lease, hire, rent or borrow; and 2. Any covered "auto" hired or rented by your "employee" under a contract in that individual "employee's" name, with your permission, while performing duties related to the conduct of your business. However, any "auto" that is leased, hired, rented or borrowed with a driver is not a covered "auto", nor is any "auto" you hire from any of your "employees", partners (if you are a partnership), members (if you are a limited liability company), or members of their households. 6. LOAN OR LEASE GAP COVERAGE Under SECTION Ill -PHYSICAL DAMAGE COVERAGE, A. COVERAGE, the following is added: If a covered "auto" is owned or leased and if we provide Physical Damage Coverage on it, we will pay, in the event of a covered total "loss", any unpaid amount due on the lease or loan for a covered "auto", less: (a) The amount paid under the Physical Damage Coverage Section of the policy; and (b) Any: (1) Overdue lease or loan payments including penalties, interest or other charges resulting from overdue payments at the time of the "loss"; (2) Financial penalties imposed under a lease for excessive use, abnormal wear and tear or high mileage; (3) Costs for extended warranties, Credit Life Insurance, Health, Accident or Disability Insurance purchased with the loan or lease; (4) Security deposits not refunded by a lessor; and (5) Carry-over balances from previous loans or leases. 7. RENTAL REIMBURSEMENT SECTION Ill -PHYSICAL DAMAGE COVERAGE, A. COVERAGE, paragraph 4. Coverage Extensions is deleted and replaced by the following: 4. Coverage Extensions (a) We will pay up to $75 per day to a maximum of $2000 for transportation expense incurred by you because of covered "loss". We will pay only for those covered "autos" for which you carry Collision Coverage or either Comprehensive Coverage or Specified Causes of Loss Coverage. We will pay for transportation expenses incurred during the period beginning 24 hours after the covered "loss" and ending, regardless of the policy's expiration, when the covered "auto" is returned to use or we pay for its "loss". This coverage is in addition to the otherwise applicable coverage you have on a covered "auto". No deductibles apply to this coverage. (b) This coverage does not apply while there is a spare or reserve "auto" available to you for your operation. Includes copyrighted material of Insurance Services Office, Inc. CA 71 15 11 09 Page 3 of 5 8. AIRBAG COVERAGE SECTION Ill -PHYSICAL DAMAGE, B. EXCLUSIONS, Paragraph 3. is deleted and replaced by the following: We will not pay for "loss" caused by or resulting from any of the following unless caused by other "loss" that is covered by this insurance: a. Wear and tear, freezing, mechanical or electrical breakdown. However, this exclusion does not include the discharge of an airbag. b. Blowouts, punctures or other road damage to tires. 9. GLASS REPAIR-WAIVER OF DEDUCTIBLE SECTION Ill-PHYSICAL DAMAGE COVERAGE, D. DEDUCTIBLE is amended to add the following: No deductible applies to glass damage if the glass is repaired rather than replaced. 10. COLLISION COVERAGE-WAIVER OF DEDUCTIBLE SECTION Ill -PHYSICAL DAMAGE COVERAGE, D. DEDUCTIBLE is amended to add the following: When there is a "loss" to your covered "auto" insured for Collision Coverage, no deductible will apply if the "loss" was caused by a collision with another "auto" insured by us. 11. KNOWLEDGE OF ACCIDENT SECTION IV-BUSINESS AUTO CONDITIONS, A. LOSS CONDITIONS, 2. DUTIES IN THE EVENT OF ACCIDENT, CLAIM, SUIT OR LOSS, paragraph a. is deleted and replaced by the following: a. You must see to it that we are notified as soon as practicable of an "accident", claim, "suit" or "loss". Knowledge of an "accident", claim, "suit" or "loss" by your "employees" shall not, in itself, constitute knowledge to you unless one of your partners, executive officers, directors, managers, or members (if you are a limited liability company) has knowledge of the "accident", claim, "suit" or "loss". Notice should include: (1) How, when and where the "accident" or "loss" occurred; (2) The "insured's" name and address; and (3) To the extent possible, the names and addresses of any injured persons and witnesses. 12. TRANSFER OF RIGHTS (BLANKET WAIVER OF SUBROGATION) SECTION IV-BUSINESS AUTO CONDITIONS A.5. TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US is deleted and replaced by the following: If any person or organization to or for whom we make payment under this Coverage Form has rights to recover damages from another, those rights are transferred to us. That person or organization must do everything necessary to secure our rights and must do nothing after "accident" or "loss" to impair them. However, if the insured has waived rights to recover through a written contract, or if your work was commenced under a letter of intent or work order, subject to a subsequent reduction in writing with customers whose customary contracts require a waiver, we waive any right of recovery we may have under this Coverage Form. 13. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS SECTION IV-BUSINESS AUTO CONDITIONS, B. GENERAL CONDITIONS, 2. CONCEALMENT, MISREPRESENTATION OR FRAUD is amended by the addition of the following: We will not deny coverage under this Coverage Form if you unintentionally fail to disclose all hazards existing as of the inception date of this policy. You must report to us any knowledge of an error or omission in your representations as soon as practicable after its discovery. This provision does not affect our right to collect additional premium or exercise our right of cancellation or non-renewal. Includes copyrighted material of Insurance Services Office, Inc. Page 4 of 5 CA 71 15 11 09 14. BLANKET COVERAGE FOR CERTAIN OPERATIONS IN CONNECTION WITH RAILROADS When required by written contract or written agreement, the definition of "insured contract" is amended as follows: The exception contained in paragraph H.3. relating to construction or demolition operations on or within 50 feet of a railroad; and Paragraph H.a. are deleted with respect to the use of a covered "auto" in operations for, or affecting, a railroad. Includes copyrighted material of Insurance Services Office, Inc. CA 7115 11 09 Page 5 of 5 This page has been left blank intentionally. The Conlan Company WC2050942140 This page has been left blank intentionally. CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS TABLE OF CONTENTS Page Article 1 – Definitions and Terminology .......................................................................................................... 1  1.01 Defined Terms ............................................................................................................................... 1  1.02 Terminology .................................................................................................................................. 5  Article 2 – Preliminary Matters ......................................................................................................................... 6  2.01 Before Starting Construction ........................................................................................................ 6  2.02 Preconstruction Conference .......................................................................................................... 6  2.03 Public Meeting .............................................................................................................................. 6  Article 3 – Contract Documents and Amending ............................................................................................... 6  3.01 Reference Standards ..................................................................................................................... 6  3.02 Amending and Supplementing Contract Documents .................................................................. 6  Article 4 – Bonds and Insurance ....................................................................................................................... 7  4.01 Licensed Sureties and Insurers ..................................................................................................... 7  4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7  4.03 Certificates of Insurance ............................................................................................................... 7  4.04 Contractor’s Insurance .................................................................................................................. 9  4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12  Article 5 – Contractor’s Responsibilities ........................................................................................................ 12  5.01 Supervision and Superintendent ................................................................................................. 12  5.02 Labor; Working Hours ................................................................................................................ 13  5.03 Services, Materials, and Equipment ........................................................................................... 13  5.04 Project Schedule .......................................................................................................................... 14  5.05 Substitutes and “Or-Equals” ....................................................................................................... 14  5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16  5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16  5.08 Wage Rates.................................................................................................................................. 18  5.09 Patent Fees and Royalties ........................................................................................................... 19  5.10 Laws and Regulations ................................................................................................................. 19  5.11 Use of Site and Other Areas ....................................................................................................... 19  5.12 Record Documents ...................................................................................................................... 20  5.13 Safety and Protection .................................................................................................................. 21  5.14 Safety Representative ................................................................................................................. 21  5.15 Hazard Communication Programs ............................................................................................. 22  5.16 Submittals .................................................................................................................................... 22  5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23  CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.18 Indemnification ........................................................................................................................... 24  5.19 Delegation of Professional Design Services .............................................................................. 24  5.20 Right to Audit: ............................................................................................................................ 25  5.21 Nondiscrimination....................................................................................................................... 25  Article 6 – Other Work at the Site ................................................................................................................... 26  6.01 Related Work at Site ................................................................................................................... 26  Article 7 – City’s Responsibilities................................................................................................................... 26  7.01 Inspections, Tests, and Approvals .............................................................................................. 26  7.02 Limitations on City’s Responsibilities ....................................................................................... 26  7.03 Compliance with Safety Program ............................................................................................... 27  Article 8 – City’s Observation Status During Construction ........................................................................... 27  8.01 City’s Project Representative ..................................................................................................... 27  8.02 Authorized Variations in Work .................................................................................................. 27  8.03 Rejecting Defective Work .......................................................................................................... 27  8.04 Determinations for Work Performed .......................................................................................... 28  Article 9 – Changes in the Work ..................................................................................................................... 28  9.01 Authorized Changes in the Work ............................................................................................... 28  9.02 Notification to Surety .................................................................................................................. 28  Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28  10.01 Change of Contract Price ............................................................................................................ 28  10.02 Change of Contract Time............................................................................................................ 28  10.03 Delays .......................................................................................................................................... 28  Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29  11.01 Notice of Defects ........................................................................................................................ 29  11.02 Access to Work ........................................................................................................................... 29  11.03 Tests and Inspections .................................................................................................................. 29  11.04 Uncovering Work ....................................................................................................................... 30  11.05 City May Stop the Work ............................................................................................................. 30  11.06 Correction or Removal of Defective Work ................................................................................ 30  11.07 Correction Period ........................................................................................................................ 30  11.08 City May Correct Defective Work ............................................................................................. 31  Article 12 – Completion .................................................................................................................................. 32  12.01 Contractor’s Warranty of Title ................................................................................................... 32  12.02 Partial Utilization ........................................................................................................................ 32  12.03 Final Inspection ........................................................................................................................... 32  12.04 Final Acceptance ......................................................................................................................... 33  Article 13 – Suspension of Work .................................................................................................................... 33  13.01 City May Suspend Work ............................................................................................................ 33  Article 14 – Miscellaneous .............................................................................................................................. 34  14.01 Giving Notice .............................................................................................................................. 34  CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.02 Computation of Times ................................................................................................................ 34  14.03 Cumulative Remedies ................................................................................................................. 34  14.04 Survival of Obligations ............................................................................................................... 35  14.05 Headings ...................................................................................................................................... 35  00 73 10- 1 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 1 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 1 – DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Agreement - The written instrument which is evidence of the agreement between Developer and Contractor covering the Work 2. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 3. Business Day – A business day is defined as a day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 4. Buzzsaw – City’s on-line, electronic document management and collaboration system. 5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight. 6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by, its governing body through its City Manager, his designee, or agents authorized pursuant to its duly authorized charter on his behalf. 7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City for the Construction of one or more following public facilities within the City public right-of- way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs. A CFA may include private facilities within the right-of-way dedicated as private right-of- way or easement on a recorded plat. 8. Contract—The entire and integrated written document incorporating the Contract Documents between the Developer, Contractor, and/or City concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral. 9. Contract Documents—Those items that make up the contract and which must include the Agreement, and it’s attachments such as standard construction specifications, standard City Conditions, other general conditions of the Developer, including: a. An Agreement 00 73 10- 2 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 2 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 b. Attachments to the Agreement i. Bid Form ii. Vendor Compliance with State Law Non-Resident Bidder iii. Prequalification Statement c. Current Prevailing Wage Rates Table (if required by City) d. Insurance Accord Form e. Payment Bond f. Performance Bond g. Maintenance Bond h. Power of Attorney for Bonds i. Workers Compensation Affidavit j. MWBE Commitment Form( If required by City) k. General Conditions l. Supplementary Conditions m. The Standard City Conditions n. Specifications specifically made part of the Contract Documents by attachment, if not attached, as incorporated by reference and described in the Table of Contents of the Project’s Contract Documents o. Drawings p. Documentation submitted by contractor prior to Notice of Award. q. The following which may be delivered or issued after the effective date if the Agreement and, if issued become an incorporated part of the Contract Documents i. Notice to Proceed ii. Field Orders iii. Change Orders iv. Letters of Final Acceptance r. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 10. Contractor—The individual or entity with whom Developer has entered into the Agreement. 11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day. 12. Developer – An individual or entity that desires to make certain improvements within the City of Fort Worth 13. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 14. Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the Developer. 15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. 00 73 10- 3 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 3 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 16. Final Inspection – Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 17. General Requirements—A part of the Contract Documents between the Developer and a Contractor. 18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 20. Milestone—A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 21. Non-Participating Change Order—A document, which is prepared for and reviewed by the City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 22. Participating Change Order—A document, which is prepared for and approved by the City, which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 23. Plans – See definition of Drawings. 24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the Work within the Contract Time. 25. Project—The Work to be performed under the Contract Documents. 26. Project Representative—The authorized representative of the City who will be assigned to the Site. 27. Public Meeting – An announced meeting conducted by the Developer to facilitate public participation and to assist the public in gaining an informed view of the Project. 28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday (excluding legal holidays). 29. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. 00 73 10- 4 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 4 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or Developer upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City or Developer which are designated for the use of Contractor. 32. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 33. Standard City Conditions – That part of the Contract Documents setting forth requirements of the City. 34. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. 35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 36. Superintendent – The representative of the Contractor who is available at all times and able to receive instructions from the City and/or Developer and to act for the Contractor. 37. Supplementary Conditions—That part of the Contract Documents which amends or supplements the General Conditions. 38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. 00 73 10- 5 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 5 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 41. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Participating Change Order, Non-Participating Change Order, or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning. B. Defective: 1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City’s written acceptance. C. Furnish, Install, Perform, Provide: 1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or the word “Supply,” or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. 00 73 10- 6 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 6 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 2 – PRELIMINARY MATTERS 2.01 Before Starting Construction Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting the Work. New schedules will be submitted to City when Participating Change Orders or Non- Participating Change Orders occur. 2.02 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.03 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING 3.01 Reference Standards A. Standards, Specifications, Codes, Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.02 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Participating Change Order or a Non-Participating Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one or more of the following ways: 1. A Field Order; 00 73 10- 7 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 7 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or 2. City’s written interpretation or clarification. ARTICLE 4 – BONDS AND INSURANCE 4.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverage so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided Section 4.04. 4.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor’s obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney-in-fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 4.01 and 4.02.C. 4.03 Certificates of Insurance Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee identified in these Standard City Conditions certificates of insurance (and other evidence of insurance requested by City or any other additional insured) which Contractor is required to purchase and maintain. 00 73 10- 8 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 8 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. The certificate of insurance shall document the City, an as “Additional Insured” on all liability policies. 2. The Contractor’s general liability insurance shall include a, “per project” or “per location”, endorsement, which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property & Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required, written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in these Standard City Conditions. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor’s obligation to maintain such lines of insurance coverage. 6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims-made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In 00 73 10- 9 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 9 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups, must also be approved by City. 10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first-dollar basis, must be acceptable to and approved by the City. 11. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage’s and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 12. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 13. City shall not be responsible for the direct payment of insurance premium costs for Contractor’s insurance. 4.04 Contractor’s Insurance A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’ Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers’ Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor’s performance of the Work and Contractor’s other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor’s employees. 3. The limits of liability for the insurance shall provide the following coverages for not less than the following amounts or greater where required by Laws and Regulations a. Statutory limits b. Employer's liability 00 73 10- 10 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 10 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $100,000 each accident/occurrence 2) $100,000 Disease - each employee 3) $500,000 Disease - policy limit B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy, unless the City approves such exclusions in writing. 1. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project 2. Contractor's Liability Insurance under this Section which shall be on a per project basis covering the Contractor with minimum limits of: a. $1,000,000 each occurrence b. $2,000,000 aggregate limit 3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance) making the General Aggregate Limits apply separately to each job site. 4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U” coverage’s. Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”, defined as autos owned, hired and non-owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. 1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in an amount not less than the following amounts: a. Automobile Liability - a commercial business policy shall provide coverage on "Any Auto", defined as autos owned, hired and non-owned. 00 73 10- 11 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 11 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at least: 2) $250,000 Bodily Injury per person 3) $500,000 Bodily Injury per accident / 4) $100,000 Property Damage D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the following requirements: 1. The Contractor’s construction activities will require its employees, agents, subcontractors, equipment, and material deliveries to cross railroad properties and tracks owned and operated by: ____________________________________________________________ Write the name of the railroad company. (If none, then write none) 2. The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains or other property. Such operations on railroad properties may require that Contractor to execute a “Right of Entry Agreement” with the particular railroad company or companies involved, and to this end the Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute the right-of-entry (if any) required by a railroad company. The requirements specified herein likewise relate to the Contractor’s use of private and/or construction access roads crossing said railroad company’s properties. 3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide coverage for not less than the following amounts, issued by companies satisfactory to the City and to the Railroad Company for a term that continues for so long as the Contractor’s operations and work cross, occupy, or touch railroad property: a. General Aggregate: _____________________________________ Enter limits provided by Railroad Company (If none, write none) b. Each Occurrence: : _____________________________________ Enter limits provided by Railroad Company (If none, write none) 4. With respect to the above outlined insurance requirements, the following shall govern: a. Where a single railroad company is involved, the Contractor shall provide one insurance policy in the name of the railroad company. However, if more than one grade separation or at-grade crossing is affected by the Project at entirely separate locations on the line or lines of the same railroad company, separate coverage may be required, each in the amount stated above. b. Where more than one railroad company is operating on the same right-of-way or where several railroad companies are involved and operated on their own separate rights-of- 00 73 10- 12 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 12 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 way, the Contractor may be required to provide separate insurance policies in the name of each railroad company. c. If, in addition to a grade separation or an at-grade crossing, other work or activity is proposed on a railroad company’s right-of-way at a location entirely separate from the grade separation or at-grade crossing, insurance coverage for this work must be included in the policy covering the grade separation. d. If no grade separation is involved but other work is proposed on a railroad company’s right-of-way, all such other work may be covered in a single policy for that railroad, even though the work may be at two or more separate locations. 5. No work or activities on a railroad company’s property to be performed by the Contractor shall be commenced until the Contractor has furnished the City with an original policy or policies of the insurance for each railroad company named, as required above. All such insurance must be approved by the City and each affected Railroad Company prior to the Contractor’s beginning work. 6. The insurance specified above must be carried until all Work to be performed on the railroad right-of-way has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. Such insurance must name the railroad company as the insured, together with any tenant or lessee of the railroad company operating over tracks involved in the Project. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured. There shall be no time credit for days not worked pursuant to this section. 4.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the Developer and City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the Developer or City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the Developer or City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES 5.01 Supervision and Superintendent A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the 00 73 10- 13 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 13 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor’s representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 5.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City’s written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication) to perform Work: 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 5.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up, and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. 00 73 10- 14 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 14 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. 5.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and the General Requirements) proposed adjustments in the Project Schedule. 2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 9. Adjustments in Contract Time for projects with City participation shall be made by participating change orders. 5.05 Substitutes and “Or-Equals” A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or-equal” item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an “or-equal” item, in which case review and approval of the proposed item may, in City’s sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and 00 73 10- 15 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 15 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City’s sole discretion an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 01 25 00 and: 1) shall certify that the proposed substitute item will: i. perform adequately the functions and achieve the results called for by the general design; ii. be similar in substance to that specified; iii. be suited to the same use as that specified; and 2) will state: i. the extent, if any, to which the use of the proposed substitute item will prejudice Contractor’s achievement of final completion on time; ii. whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; iii. whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: i. all variations of the proposed substitute item from that specified; ii. available engineering, sales, maintenance, repair, and replacement services; and 00 73 10- 16 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 16 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 5.05.A.2. C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents. F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or “or-equal” at Contractor’s expense. G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Participating Change Order. 5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) A. The Contractor and any subcontractors are required to be prequalified for the work types requiring pre-qualification 5.07 Concerning Subcontractors, Suppliers, and Others A. Minority and Women Owned Business Enterprise Compliance: 00 73 10- 17 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 17 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Required for this Contract. (Check this box if there is any City Participation) Not Required for this Contract. It is City policy to ensure the full and equitable participation by Minority and Women Business Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent of the City’s MWBE Ordinance (as amended) by the following: 1. Contractor shall, upon request by City, provide complete and accurate information regarding actual work performed by a MWBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records, or files in the possession of the Contractor that will substantiate the actual work performed by an MWBE. Material misrepresentation of any nature will be grounds for termination of the Contract. Any such misrepresentation may be grounds for disqualification of Contractor to bid on future contracts with the City for a period of not less than three years. B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract Documents: 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. C. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract 00 73 10- 18 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 18 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents, Contractor shall provide City contract numbers and reference numbers to the Subcontractors and/or Suppliers. 5.08 Wage Rates Required for this Contract. Not Required for this Contract. A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs, pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City’s determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show (i) the name and 00 73 10- 19 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 19 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258, Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 5.09 Patent Fees and Royalties A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 5.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor’s responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor’s obligations under Paragraph 3.01. 5.11 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or 00 73 10- 20 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 20 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and shall be entitled to recover its cost in doing so. The City may withhold Final Acceptance until clean-up is complete and cost are recovered. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 5.12 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved 00 73 10- 21 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 21 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 5.13 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property. C. Contractor shall comply with the applicable requirements of City’s safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any, with which City’s employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 5.14 Safety Representative Contractor shall inform City in writing of Contractor’s designated safety representative at the Site. 00 73 10- 22 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 22 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.15 Hazard Communication Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 5.16 Submittals A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal will be identified as required by City. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 5.16.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For-Information-Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 5.16.C. B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City’s review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City’s Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City’s review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 00 73 10- 23 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 23 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City’s review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 5.17 Contractor’s General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor’s warranty and guarantee. B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City or Developer of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection, test, or approval by others; or 00 73 10- 24 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 24 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 4.02.B. The City will give notice of observed defects with reasonable promptness. 5.18 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. 5.19 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to City. 00 73 10- 25 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 25 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City’s review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 5.16.C. 5.20 Right to Audit: A. The City reserves the right to audit all projects utilizing City funds B. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 5.21 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit- related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. 00 73 10- 26 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 26 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 6 – OTHER WORK AT THE SITE 6.01 Related Work at Site A. City may perform other work related to the Project at the Site with City’s employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work; and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City’s employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor’s Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects in the work provided by others. ARTICLE 7 – CITY’S RESPONSIBILITIES 7.01 Inspections, Tests, and Approvals City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 11.03. 7.02 Limitations on City’s Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13. 00 73 10- 27 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 27 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7.03 Compliance with Safety Program While at the Site, City’s employees and representatives shall comply with the specific applicable requirements of Contractor’s safety programs of which City has been informed pursuant to Paragraph 5.13. ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION 8.01 City’s Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City’s representative during construction are set forth in the Contract Documents. A. City’s Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor’s executed Work. Based on information obtained during such visits and observations, City’s Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City’s Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City’s Project Representative’s visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents. 8.02 Authorized Variations in Work City’s Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City Developer, and also on Contractor, who shall perform the Work involved promptly. 8.03 Rejecting Defective Work City will have authority to reject Work which City’s Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or completed. 00 73 10- 28 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 28 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 8.04 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City’s Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City’s written decision will be final (except as modified to reflect changed factual conditions or more accurate data). ARTICLE 9 – CHANGES IN THE WORK 9.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Participating Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a project with City participation, a Field Order may be issued by the City. 9.02 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 10.01 Change of Contract Price A. The Contract Price may only be changed by a Participating Change Order for projects with City participation. 10.02 Change of Contract Time A. The Contract Time may only be changed by a Participating Change Order for projects with City participation. 10.03 Delays A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. 00 73 10- 29 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 29 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 11.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected, or accepted as provided in this Article 13. 11.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s safety procedures and programs so that they may comply therewith as applicable. 11.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by City. D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible, with Contractor; 2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. 00 73 10- 30 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 30 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Developer/Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance until the Testing Lab is Paid E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. 11.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s expense. 11.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them. 11.06 Correction or Removal of Defective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07, Contractor shall take no action that would void or otherwise impair City’s special warranty and guarantee, if any, on said Work. 11.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract 00 73 10- 31 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 31 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor’s use by City or permitted by Laws and Regulations as contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City’s written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 11.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor and Developer should such additional warranty coverage be required. Contractor’s obligations under this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 11.08 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are 00 73 10- 32 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 32 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants, employees, and City’s other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City’s rights and remedies under this Paragraph 11.09. ARTICLE 12 – COMPLETION 12.01 Contractor’s Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment will pass to City no later than the time of Final Acceptance and shall be free and clear of all Liens. 12.02 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor’s performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 12.03 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: 00 73 10- 33 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 33 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. 12.04 Final Acceptance A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction of the following: 1. All documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; 2. consent of the surety, if any, to Final Acceptance; 3. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and 4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. 5. after all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s insurance provider for resolution. 6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. ARTICLE 13 – SUSPENSION OF WORK 13.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will stop contract time on City participation projects. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not 00 73 10- 34 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 34 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. ARTICLE 14 – MISCELLANEOUS 14.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if: 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 14.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 14.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. 00 73 10- 35 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 35 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 14.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. 01 31 19 - 1 DAP PRECONSTRUCTION MEETING Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 SECTION 01 31 19 PRECONSTRUCTION MEETING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provisions for the preconstruction meeting to be held prior to the start of Work to clarify construction contract administration procedures B. Deviations from this City of Fort Worth Standard Specification 1. No construction schedule required unless requested by the City. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Attend preconstruction meeting. 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents. 3. Meeting administered by City may be tape recorded. a. If recorded, tapes will be used to prepare minutes and retained by City for future reference. B. Preconstruction Meeting 1. A preconstruction meeting will be held within 14 days after the delivery of the distribution package to the City. a. The meeting will be scheduled and administered by the City. 2. The Project Representative will preside at the meeting, prepare the notes of the meeting and distribute copies of same to all participants who so request by fully completing the attendance form to be circulated at the beginning of the meeting. 3. Attendance shall include: a. Developer and Consultant b. Contractor's project manager c. Contractor's superintendent d. Any subcontractor or supplier representatives whom the Contractor may desire to invite or the City may request 01 31 19 - 2 DAP PRECONSTRUCTION MEETING Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 e. Other City representatives f. Others as appropriate 4. Preliminary Agenda may include: a. Introduction of Project Personnel b. General Description of Project c. Status of right-of-way, utility clearances, easements or other pertinent permits d. Contractor’s work plan and schedule e. Contract Time f. Notice to Proceed g. Construction Staking h. Progress Payments i. Extra Work and Change Order Procedures j. Field Orders k. Disposal Site Letter for Waste Material l. Insurance Renewals m. Payroll Certification n. Material Certifications and Quality Control Testing o. Public Safety and Convenience p. Documentation of Pre-Construction Conditions q. Weekend Work Notification r. Legal Holidays s. Trench Safety Plans t. Confined Space Entry Standards u. Coordination with the City’s representative for operations of existing water systems v. Storm Water Pollution Prevention Plan w. Coordination with other Contractors x. Early Warning System y. Contractor Evaluation z. Special Conditions applicable to the project aa. Damages Claims bb. Submittal Procedures cc. Substitution Procedures dd. Correspondence Routing ee. Record Drawings ff. Temporary construction facilities gg. MBE/SBE procedures hh. Final Acceptance ii. Final Payment jj. Questions or Comments 01 31 19 - 3 DAP PRECONSTRUCTION MEETING Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 [Insert Project Name] [Insert Project Number] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 32 33 - 1 DAP PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 SECTION 01 32 33 PRECONSTRUCTION VIDEO PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative and procedural requirements for: a. Preconstruction Videos B. Deviations from this City of Fort Worth Standard Specification 1. Though not mandatory, it is highly recommended on infill developer projects. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Preconstruction Video 1. Produce a preconstruction video of the site/alignment, including all areas in the vicinity of and to be affected by construction. a. Provide digital copy of video upon request by the City. 2. Retain a copy of the preconstruction video until the end of the maintenance surety period. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] 01 32 33 - 2 DAP PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 33 00 - 1 DAP SUBMITTALS Page 1 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 SECTION 01 33 00 DAP SUBMITTALS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. General methods and requirements of submissions applicable to the following Work-related submittals: a. Shop Drawings b. Product Data (including Standard Product List submittals) c. Samples d. Mock Ups B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Notify the City in writing, at the time of submittal, of any deviations in the submittals from the requirements of the Contract Documents. 2. Coordination of Submittal Times a. Prepare, prioritize and transmit each submittal sufficiently in advance of performing the related Work or other applicable activities, or within the time specified in the individual Work Sections, of the Specifications. b. Contractor is responsible such that the installation will not be delayed by processing times including, but not limited to: a) Disapproval and resubmittal (if required) b) Coordination with other submittals c) Testing d) Purchasing e) Fabrication f) Delivery g) Similar sequenced activities c. No extension of time will be authorized because of the Contractor's failure to transmit submittals sufficiently in advance of the Work. 01 33 00 - 2 DAP SUBMITTALS Page 1 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 d. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor. B. Submittal Numbering 1. When submitting shop drawings or samples, utilize a 9-character submittal cross- reference identification numbering system in the following manner: a. Use the first 6 digits of the applicable Specification Section Number. b. For the next 2 digits number use numbers 01-99 to sequentially number each initial separate item or drawing submitted under each specific Section number. c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical submittal number would be as follows: 03 30 00-08-B 1) 03 30 00 is the Specification Section for Concrete 2) 08 is the eighth initial submittal under this Specification Section 3) B is the third submission (second resubmission) of that particular shop drawing C. Contractor Certification 1. Review shop drawings, product data and samples, including those by subcontractors, prior to submission to determine and verify the following: a. Field measurements b. Field construction criteria c. Catalog numbers and similar data d. Conformance with the Contract Documents 2. Provide each shop drawing, sample and product data submitted by the Contractor with a Certification Statement affixed including: a. The Contractor's Company name b. Signature of submittal reviewer c. Certification Statement 1) “By this submittal, I hereby represent that I have determined and verified field measurements, field construction criteria, materials, dimensions, catalog numbers and similar data and I have checked and coordinated each item with other applicable approved shop drawings." D. Submittal Format 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches. 2. Bind shop drawings and product data sheets together. 3. Order a. Cover Sheet 1) Description of Packet 2) Contractor Certification b. List of items / Table of Contents c. Product Data /Shop Drawings/Samples /Calculations E. Submittal Content 1. The date of submission and the dates of any previous submissions 01 33 00 - 3 DAP SUBMITTALS Page 3 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 2. The Project title and number 3. Contractor identification 4. The names of: a. Contractor b. Supplier c. Manufacturer 5. Identification of the product, with the Specification Section number, page and paragraph(s) 6. Field dimensions, clearly identified as such 7. Relation to adjacent or critical features of the Work or materials 8. Applicable standards, such as ASTM or Federal Specification numbers 9. Identification by highlighting of deviations from Contract Documents 10. Identification by highlighting of revisions on resubmittals 11. An 8-inch x 3-inch blank space for Contractor and City stamps F. Shop Drawings 1. As specified in individual Work Sections includes, but is not necessarily limited to: a. Custom-prepared data such as fabrication and erection/installation (working) drawings b. Scheduled information c. Setting diagrams d. Actual shopwork manufacturing instructions e. Custom templates f. Special wiring diagrams g. Coordination drawings h. Individual system or equipment inspection and test reports including: 1) Performance curves and certifications i. As applicable to the Work 2. Details a. Relation of the various parts to the main members and lines of the structure b. Where correct fabrication of the Work depends upon field measurements 1) Provide such measurements and note on the drawings prior to submitting for approval. G. Product Data 1. For submittals of product data for products included on the City’s Standard Product List, clearly identify each item selected for use on the Project. 2. For submittals of product data for products not included on the City’s Standard Product List, submittal data may include, but is not necessarily limited to: a. Standard prepared data for manufactured products (sometimes referred to as catalog data) 1) Such as the manufacturer's product specification and installation instructions 2) Availability of colors and patterns 3) Manufacturer's printed statements of compliances and applicability 4) Roughing-in diagrams and templates 5) Catalog cuts 6) Product photographs 01 33 00 - 4 DAP SUBMITTALS Page 4 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 7) Standard wiring diagrams 8) Printed performance curves and operational-range diagrams 9) Production or quality control inspection and test reports and certifications 10) Mill reports 11) Product operating and maintenance instructions and recommended spare-parts listing and printed product warranties 12) As applicable to the Work H. Samples 1. As specified in individual Sections, include, but are not necessarily limited to: a. Physical examples of the Work such as: 1) Sections of manufactured or fabricated Work 2) Small cuts or containers of materials 3) Complete units of repetitively used products color/texture/pattern swatches and range sets 4) Specimens for coordination of visual effect 5) Graphic symbols and units of Work to be used by the City for independent inspection and testing, as applicable to the Work I. Do not start Work requiring a shop drawing, sample or product data nor any material to be fabricated or installed prior to the approval or qualified approval of such item. 1. Fabrication performed, materials purchased or on-site construction accomplished which does not conform to approved shop drawings and data is at the Contractor's risk. 2. The City will not be liable for any expense or delay due to corrections or remedies required to accomplish conformity. 3. Complete project Work, materials, fabrication, and installations in conformance with approved shop drawings, applicable samples, and product data. J. Submittal Distribution 1. Electronic Distribution a. Confirm development of Project directory for electronic submittals to be uploaded to City’s Buzzsaw site, or another external FTP site approved by the City. b. Shop Drawings 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals b) If Contractor requires more than 1 hard copy of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. c. Product Data 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals d. Samples 1) Distributed to the Project Representative 2. Hard Copy Distribution (if required in lieu of electronic distribution) 01 33 00 - 5 DAP SUBMITTALS Page 5 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 a. Shop Drawings 1) Distributed to the City 2) Copies a) 8 copies for mechanical submittals b) 7 copies for all other submittals c) If Contractor requires more than 3 copies of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. b. Product Data 1) Distributed to the City 2) Copies a) 4 copies c. Samples 1) Distributed to the Project Representative 2) Copies a) Submit the number stated in the respective Specification Sections. 3. Distribute reproductions of approved shop drawings and copies of approved product data and samples, where required, to the job site file and elsewhere as directed by the City. a. Provide number of copies as directed by the City but not exceeding the number previously specified. K. Submittal Review 1. The review of shop drawings, data and samples will be for general conformance with the design concept and Contract Documents. This is not to be construed as: a. Permitting any departure from the Contract requirements b. Relieving the Contractor of responsibility for any errors, including details, dimensions, and materials c. Approving departures from details furnished by the City, except as otherwise provided herein 2. The review and approval of shop drawings, samples or product data by the City does not relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms of the Contract. a. All risks of error and omission are assumed by the Contractor, and the City will have no responsibility therefore. 3. The Contractor remains responsible for details and accuracy, for coordinating the Work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly and for performing Work in a safe manner. 4. If the shop drawings, data or samples as submitted describe variations and show a departure from the Contract requirements which City finds to be in the interest of the City and to be so minor as not to involve a change in Contract Price or time for performance, the City may return the reviewed drawings without noting an exception. 5. Submittals will be returned to the Contractor under 1 of the following codes: a. Code 1 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or comments on the submittal. a) When returned under this code the Contractor may release the equipment and/or material for manufacture. b. Code 2 01 33 00 - 6 DAP SUBMITTALS Page 6 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the notations and comments IS NOT required by the Contractor. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. c. Code 3 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned when notations and comments are extensive enough to require a resubmittal of the package. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. b) This resubmittal is to address all comments, omissions and non-conforming items that were noted. c) Resubmittal is to be received by the City within 15 Calendar Days of the date of the City's transmittal requiring the resubmittal. d. Code 4 1) "NOT APPROVED" is assigned when the submittal does not meet the intent of the Contract Documents. a) The Contractor must resubmit the entire package revised to bring the submittal into conformance. b) It may be necessary to resubmit using a different manufacturer/vendor to meet the Contract Documents. 6. Resubmittals a. Handled in the same manner as first submittals 1) Corrections other than requested by the City 2) Marked with revision triangle or other similar method a) At Contractor’s risk if not marked b. Submittals for each item will be reviewed no more than twice at the City’s expense. 1) All subsequent reviews will be performed at times convenient to the City and at the Contractor's expense, based on the City's or City Representative’s then prevailing rates. 2) Provide Contractor reimbursement to the City within 30 Calendar Days for all such fees invoiced by the City. c. The need for more than 1 resubmission or any other delay in obtaining City's review of submittals, will not entitle the Contractor to an extension of Contract Time. 7. Partial Submittals a. City reserves the right to not review submittals deemed partial, at the City’s discretion. b. Submittals deemed by the City to be not complete will be returned to the Contractor, and will be considered "Not Approved" until resubmitted. c. The City may at its option provide a list or mark the submittal directing the Contractor to the areas that are incomplete. 8. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, then written notice must be provided thereof to the Developer at least 7 Calendar Days prior to release for manufacture. 01 33 00 - 7 DAP SUBMITTALS Page 7 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 9. When the shop drawings have been completed to the satisfaction of the City, the Contractor may carry out the construction in accordance therewith and no further changes therein except upon written instructions from the City. 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days following receipt of submittal by the City. L. Mock ups 1. Mock Up units as specified in individual Sections, include, but are not necessarily limited to, complete units of the standard of acceptance for that type of Work to be used on the Project. Remove at the completion of the Work or when directed. M. Qualifications 1. If specifically required in other Sections of these Specifications, submit a P.E. Certification for each item required. N. Request for Information (RFI) 1. Contractor Request for additional information a. Clarification or interpretation of the contract documents b. When the Contractor believes there is a conflict between Contract Documents c. When the Contractor believes there is a conflict between the Drawings and Specifications 1) Identify the conflict and request clarification 2. Sufficient information shall be attached to permit a written response without further information. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] 01 33 00 - 8 DAP SUBMITTALS Page 8 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days 01 31 19 - 1 DAP PRECONSTRUCTION MEETING Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 SECTION 01 31 19 PRECONSTRUCTION MEETING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provisions for the preconstruction meeting to be held prior to the start of Work to clarify construction contract administration procedures B. Deviations from this City of Fort Worth Standard Specification 1. No construction schedule required unless requested by the City. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Attend preconstruction meeting. 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents. 3. Meeting administered by City may be tape recorded. a. If recorded, tapes will be used to prepare minutes and retained by City for future reference. B. Preconstruction Meeting 1. A preconstruction meeting will be held within 14 days after the delivery of the distribution package to the City. a. The meeting will be scheduled and administered by the City. 2. The Project Representative will preside at the meeting, prepare the notes of the meeting and distribute copies of same to all participants who so request by fully completing the attendance form to be circulated at the beginning of the meeting. 3. Attendance shall include: a. Developer and Consultant b. Contractor's project manager c. Contractor's superintendent d. Any subcontractor or supplier representatives whom the Contractor may desire to invite or the City may request 01 31 19 - 2 DAP PRECONSTRUCTION MEETING Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 e. Other City representatives f. Others as appropriate 4. Preliminary Agenda may include: a. Introduction of Project Personnel b. General Description of Project c. Status of right-of-way, utility clearances, easements or other pertinent permits d. Contractor’s work plan and schedule e. Contract Time f. Notice to Proceed g. Construction Staking h. Progress Payments i. Extra Work and Change Order Procedures j. Field Orders k. Disposal Site Letter for Waste Material l. Insurance Renewals m. Payroll Certification n. Material Certifications and Quality Control Testing o. Public Safety and Convenience p. Documentation of Pre-Construction Conditions q. Weekend Work Notification r. Legal Holidays s. Trench Safety Plans t. Confined Space Entry Standards u. Coordination with the City’s representative for operations of existing water systems v. Storm Water Pollution Prevention Plan w. Coordination with other Contractors x. Early Warning System y. Contractor Evaluation z. Special Conditions applicable to the project aa. Damages Claims bb. Submittal Procedures cc. Substitution Procedures dd. Correspondence Routing ee. Record Drawings ff. Temporary construction facilities gg. MBE/SBE procedures hh. Final Acceptance ii. Final Payment jj. Questions or Comments 01 31 19 - 3 DAP PRECONSTRUCTION MEETING Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 [Insert Project Name] [Insert Project Number] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 32 33 - 1 DAP PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 SECTION 01 32 33 PRECONSTRUCTION VIDEO PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative and procedural requirements for: a. Preconstruction Videos B. Deviations from this City of Fort Worth Standard Specification 1. Though not mandatory, it is highly recommended on infill developer projects. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Preconstruction Video 1. Produce a preconstruction video of the site/alignment, including all areas in the vicinity of and to be affected by construction. a. Provide digital copy of video upon request by the City. 2. Retain a copy of the preconstruction video until the end of the maintenance surety period. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] 01 32 33 - 2 DAP PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 33 00 - 1 DAP SUBMITTALS Page 1 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 SECTION 01 33 00 DAP SUBMITTALS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. General methods and requirements of submissions applicable to the following Work-related submittals: a. Shop Drawings b. Product Data (including Standard Product List submittals) c. Samples d. Mock Ups B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Notify the City in writing, at the time of submittal, of any deviations in the submittals from the requirements of the Contract Documents. 2. Coordination of Submittal Times a. Prepare, prioritize and transmit each submittal sufficiently in advance of performing the related Work or other applicable activities, or within the time specified in the individual Work Sections, of the Specifications. b. Contractor is responsible such that the installation will not be delayed by processing times including, but not limited to: a) Disapproval and resubmittal (if required) b) Coordination with other submittals c) Testing d) Purchasing e) Fabrication f) Delivery g) Similar sequenced activities c. No extension of time will be authorized because of the Contractor's failure to transmit submittals sufficiently in advance of the Work. 01 33 00 - 2 DAP SUBMITTALS Page 1 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 d. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor. B. Submittal Numbering 1. When submitting shop drawings or samples, utilize a 9-character submittal cross- reference identification numbering system in the following manner: a. Use the first 6 digits of the applicable Specification Section Number. b. For the next 2 digits number use numbers 01-99 to sequentially number each initial separate item or drawing submitted under each specific Section number. c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical submittal number would be as follows: 03 30 00-08-B 1) 03 30 00 is the Specification Section for Concrete 2) 08 is the eighth initial submittal under this Specification Section 3) B is the third submission (second resubmission) of that particular shop drawing C. Contractor Certification 1. Review shop drawings, product data and samples, including those by subcontractors, prior to submission to determine and verify the following: a. Field measurements b. Field construction criteria c. Catalog numbers and similar data d. Conformance with the Contract Documents 2. Provide each shop drawing, sample and product data submitted by the Contractor with a Certification Statement affixed including: a. The Contractor's Company name b. Signature of submittal reviewer c. Certification Statement 1) “By this submittal, I hereby represent that I have determined and verified field measurements, field construction criteria, materials, dimensions, catalog numbers and similar data and I have checked and coordinated each item with other applicable approved shop drawings." D. Submittal Format 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches. 2. Bind shop drawings and product data sheets together. 3. Order a. Cover Sheet 1) Description of Packet 2) Contractor Certification b. List of items / Table of Contents c. Product Data /Shop Drawings/Samples /Calculations E. Submittal Content 1. The date of submission and the dates of any previous submissions 01 33 00 - 3 DAP SUBMITTALS Page 3 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 2. The Project title and number 3. Contractor identification 4. The names of: a. Contractor b. Supplier c. Manufacturer 5. Identification of the product, with the Specification Section number, page and paragraph(s) 6. Field dimensions, clearly identified as such 7. Relation to adjacent or critical features of the Work or materials 8. Applicable standards, such as ASTM or Federal Specification numbers 9. Identification by highlighting of deviations from Contract Documents 10. Identification by highlighting of revisions on resubmittals 11. An 8-inch x 3-inch blank space for Contractor and City stamps F. Shop Drawings 1. As specified in individual Work Sections includes, but is not necessarily limited to: a. Custom-prepared data such as fabrication and erection/installation (working) drawings b. Scheduled information c. Setting diagrams d. Actual shopwork manufacturing instructions e. Custom templates f. Special wiring diagrams g. Coordination drawings h. Individual system or equipment inspection and test reports including: 1) Performance curves and certifications i. As applicable to the Work 2. Details a. Relation of the various parts to the main members and lines of the structure b. Where correct fabrication of the Work depends upon field measurements 1) Provide such measurements and note on the drawings prior to submitting for approval. G. Product Data 1. For submittals of product data for products included on the City’s Standard Product List, clearly identify each item selected for use on the Project. 2. For submittals of product data for products not included on the City’s Standard Product List, submittal data may include, but is not necessarily limited to: a. Standard prepared data for manufactured products (sometimes referred to as catalog data) 1) Such as the manufacturer's product specification and installation instructions 2) Availability of colors and patterns 3) Manufacturer's printed statements of compliances and applicability 4) Roughing-in diagrams and templates 5) Catalog cuts 6) Product photographs 01 33 00 - 4 DAP SUBMITTALS Page 4 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 7) Standard wiring diagrams 8) Printed performance curves and operational-range diagrams 9) Production or quality control inspection and test reports and certifications 10) Mill reports 11) Product operating and maintenance instructions and recommended spare-parts listing and printed product warranties 12) As applicable to the Work H. Samples 1. As specified in individual Sections, include, but are not necessarily limited to: a. Physical examples of the Work such as: 1) Sections of manufactured or fabricated Work 2) Small cuts or containers of materials 3) Complete units of repetitively used products color/texture/pattern swatches and range sets 4) Specimens for coordination of visual effect 5) Graphic symbols and units of Work to be used by the City for independent inspection and testing, as applicable to the Work I. Do not start Work requiring a shop drawing, sample or product data nor any material to be fabricated or installed prior to the approval or qualified approval of such item. 1. Fabrication performed, materials purchased or on-site construction accomplished which does not conform to approved shop drawings and data is at the Contractor's risk. 2. The City will not be liable for any expense or delay due to corrections or remedies required to accomplish conformity. 3. Complete project Work, materials, fabrication, and installations in conformance with approved shop drawings, applicable samples, and product data. J. Submittal Distribution 1. Electronic Distribution a. Confirm development of Project directory for electronic submittals to be uploaded to City’s Buzzsaw site, or another external FTP site approved by the City. b. Shop Drawings 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals b) If Contractor requires more than 1 hard copy of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. c. Product Data 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals d. Samples 1) Distributed to the Project Representative 2. Hard Copy Distribution (if required in lieu of electronic distribution) 01 33 00 - 5 DAP SUBMITTALS Page 5 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 a. Shop Drawings 1) Distributed to the City 2) Copies a) 8 copies for mechanical submittals b) 7 copies for all other submittals c) If Contractor requires more than 3 copies of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. b. Product Data 1) Distributed to the City 2) Copies a) 4 copies c. Samples 1) Distributed to the Project Representative 2) Copies a) Submit the number stated in the respective Specification Sections. 3. Distribute reproductions of approved shop drawings and copies of approved product data and samples, where required, to the job site file and elsewhere as directed by the City. a. Provide number of copies as directed by the City but not exceeding the number previously specified. K. Submittal Review 1. The review of shop drawings, data and samples will be for general conformance with the design concept and Contract Documents. This is not to be construed as: a. Permitting any departure from the Contract requirements b. Relieving the Contractor of responsibility for any errors, including details, dimensions, and materials c. Approving departures from details furnished by the City, except as otherwise provided herein 2. The review and approval of shop drawings, samples or product data by the City does not relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms of the Contract. a. All risks of error and omission are assumed by the Contractor, and the City will have no responsibility therefore. 3. The Contractor remains responsible for details and accuracy, for coordinating the Work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly and for performing Work in a safe manner. 4. If the shop drawings, data or samples as submitted describe variations and show a departure from the Contract requirements which City finds to be in the interest of the City and to be so minor as not to involve a change in Contract Price or time for performance, the City may return the reviewed drawings without noting an exception. 5. Submittals will be returned to the Contractor under 1 of the following codes: a. Code 1 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or comments on the submittal. a) When returned under this code the Contractor may release the equipment and/or material for manufacture. b. Code 2 01 33 00 - 6 DAP SUBMITTALS Page 6 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the notations and comments IS NOT required by the Contractor. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. c. Code 3 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned when notations and comments are extensive enough to require a resubmittal of the package. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. b) This resubmittal is to address all comments, omissions and non-conforming items that were noted. c) Resubmittal is to be received by the City within 15 Calendar Days of the date of the City's transmittal requiring the resubmittal. d. Code 4 1) "NOT APPROVED" is assigned when the submittal does not meet the intent of the Contract Documents. a) The Contractor must resubmit the entire package revised to bring the submittal into conformance. b) It may be necessary to resubmit using a different manufacturer/vendor to meet the Contract Documents. 6. Resubmittals a. Handled in the same manner as first submittals 1) Corrections other than requested by the City 2) Marked with revision triangle or other similar method a) At Contractor’s risk if not marked b. Submittals for each item will be reviewed no more than twice at the City’s expense. 1) All subsequent reviews will be performed at times convenient to the City and at the Contractor's expense, based on the City's or City Representative’s then prevailing rates. 2) Provide Contractor reimbursement to the City within 30 Calendar Days for all such fees invoiced by the City. c. The need for more than 1 resubmission or any other delay in obtaining City's review of submittals, will not entitle the Contractor to an extension of Contract Time. 7. Partial Submittals a. City reserves the right to not review submittals deemed partial, at the City’s discretion. b. Submittals deemed by the City to be not complete will be returned to the Contractor, and will be considered "Not Approved" until resubmitted. c. The City may at its option provide a list or mark the submittal directing the Contractor to the areas that are incomplete. 8. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, then written notice must be provided thereof to the Developer at least 7 Calendar Days prior to release for manufacture. 01 33 00 - 7 DAP SUBMITTALS Page 7 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 9. When the shop drawings have been completed to the satisfaction of the City, the Contractor may carry out the construction in accordance therewith and no further changes therein except upon written instructions from the City. 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days following receipt of submittal by the City. L. Mock ups 1. Mock Up units as specified in individual Sections, include, but are not necessarily limited to, complete units of the standard of acceptance for that type of Work to be used on the Project. Remove at the completion of the Work or when directed. M. Qualifications 1. If specifically required in other Sections of these Specifications, submit a P.E. Certification for each item required. N. Request for Information (RFI) 1. Contractor Request for additional information a. Clarification or interpretation of the contract documents b. When the Contractor believes there is a conflict between Contract Documents c. When the Contractor believes there is a conflict between the Drawings and Specifications 1) Identify the conflict and request clarification 2. Sufficient information shall be attached to permit a written response without further information. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] 01 33 00 - 8 DAP SUBMITTALS Page 8 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days 01 45 23 - 1 DAP TESTING AND INSPECTION SERVICES Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 SECTION 01 45 23 TESTING AND INSPECTION SERVICES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Testing and inspection services procedures and coordination B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. a. Contractor is responsible for performing, coordinating, and payment of all Quality Control testing. b. City is responsible for performing and payment for first set of Quality Assurance testing. 1) If the first Quality Assurance test performed by the City fails, the Contractor is responsible for payment of subsequent Quality Assurance testing until a passing test occurs. a) Final acceptance will not be issued by City until all required payments for testing by Contractor have been paid in full. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Testing 1. Complete testing in accordance with the Contract Documents. 2. Coordination a. When testing is required to be performed by the City, notify City, sufficiently in advance, when testing is needed. b. When testing is required to be completed by the Contractor, notify City, sufficiently in advance, that testing will be performed. 3. Distribution of Testing Reports a. Electronic Distribution 1) Confirm development of Project directory for electronic submittals to be uploaded to City’s Buzzsaw site, or another form of distribution approved by the City. 01 45 23 - 2 DAP TESTING AND INSPECTION SERVICES Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Landmark Quebec Addition 102418 2) Upload test reports to designated project directory and notify appropriate City representatives via email of submittal posting. 3) Hard Copies a) 1 copy for all submittals submitted to the Project Representative b. Hard Copy Distribution (if required in lieu of electronic distribution) 1) Tests performed by City a) Distribute 1 hard copy to the Contractor 2) Tests performed by the Contractor a) Distribute 3 hard copies to City’s Project Representative 4. Provide City’s Project Representative with trip tickets for each delivered load of Concrete or Lime material including the following information: a. Name of pit b. Date of delivery c. Material delivered B. Inspection 1. Inspection or lack of inspection does not relieve the Contractor from obligation to perform work in accordance with the Contract Documents. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 55 26 - 1 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Landmark Quebec Addition 102418 SECTION 01 55 26 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative procedures for: a. Street Use Permit b. Modification of approved traffic control c. Removal of Street Signs B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 34 71 13 – Traffic Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES A. Reference Standards 1. Reference standards cited in this specification refer to the current reference standard published at the time of the latest revision date logged at the end of this specification, unless a date is specifically cited. 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 1.4 ADMINISTRATIVE REQUIREMENTS A. Traffic Control 1. General a. When traffic control plans are included in the Drawings, provide Traffic Control in accordance with Drawings and Section 34 71 13. b. When traffic control plans are not included in the Drawings, prepare traffic control plans in accordance with Section 34 71 13 and submit to City for review. 1) Allow minimum 10 working days for review of proposed Traffic Control. B. Street Use Permit 1. Prior to installation of Traffic Control, a City Street Use Permit is required. a. To obtain Street Use Permit, submit Traffic Control Plans to City Transportation and Public Works Department. 01 55 26 - 2 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Landmark Quebec Addition 102418 1) Allow a minimum of 5 working days for permit review. 2) Contractor’s responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. C. Modification to Approved Traffic Control 1. Prior to installation traffic control: a. Submit revised traffic control plans to City Department Transportation and Public Works Department. 1) Revise Traffic Control plans in accordance with Section 34 71 13. 2) Allow minimum 5 working days for review of revised Traffic Control. 3) It is the Contractor’s responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. D. Removal of Street Sign 1. If it is determined that a street sign must be removed for construction, then contact City Transportation and Public Works Department, Signs and Markings Division to remove the sign. E. Temporary Signage 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting requirements of the latest edition of the Texas Manual on Uniform Traffic Control Devices (MUTCD). 2. Install temporary sign before the removal of permanent sign. 3. When construction is complete, to the extent that the permanent sign can be reinstalled, contact the City Transportation and Public Works Department, Signs and Markings Division, to reinstall the permanent sign. F. Traffic Control Standards 1. Traffic Control Standards can be found on the City’s Buzzsaw website. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION 01 55 26 - 3 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Landmark Quebec Addition 102418 Revision Log DATE NAME SUMMARY OF CHANGE 01 71 23 - 1 DAP CONSTRUCTION STAKING AND SURVEY Page 1 of 4 CITY OF FORT WORTH Lonestar Business Park STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Project Number: 102418 Revised April 7, 2014 SECTION 01 71 23 1 CONSTRUCTION STAKING AND SURVEY 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Requirements for construction staking and construction survey 6 B. Deviations from this City of Fort Worth Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10 2. Division 1 – General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Construction Staking 14 a. Measurement 15 1) This Item is considered subsidiary to the various Items bid. 16 b. Payment 17 1) The work performed and the materials furnished in accordance with this 18 Item are subsidiary to the various Items bid and no other compensation will 19 be allowed. 20 2. Construction Survey 21 a. Measurement 22 1) This Item is considered subsidiary to the various Items bid. 23 b. Payment 24 1) The work performed and the materials furnished in accordance with this 25 Item are subsidiary to the various Items bid and no other compensation will 26 be allowed. 27 1.3 REFERENCES [NOT USED] 28 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 29 1.5 SUBMITTALS 30 A. Submittals, if required, shall be in accordance with Section 01 33 00. 31 B. All submittals shall be approved by the City prior to delivery. 32 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 33 A. Certificates 34 1. Provide certificate certifying that elevations and locations of improvements are in 35 conformance or non-conformance with requirements of the Contract Documents. 36 a. Certificate must be sealed by a registered professional land surveyor in the 37 State of Texas. 38 01 71 23 - 2 DAP CONSTRUCTION STAKING AND SURVEY Page 2 of 4 CITY OF FORT WORTH Lonestar Business Park STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Project Number: 102418 Revised April 7, 2014 B. Field Quality Control Submittals 1 1. Documentation verifying accuracy of field engineering work. 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE 5 A. Construction Staking 6 1. Construction staking will be performed by the City. 7 2. Coordination 8 a. Contact City’s Project Representative at least 2 weeks in advance for 9 scheduling of Construction Staking. 10 b. It is the Contractor’s responsibility to coordinate staking such that construction 11 activities are not delayed or negatively impacted. 12 3. General 13 a. Contractor is responsible for preserving and maintaining stakes furnished by 14 City. 15 b. If in the opinion of the City, a sufficient number of stakes or markings have 16 been lost, destroyed or disturbed, by Contractor’s neglect, such that the 17 contracted Work cannot take place, then the Contractor will be required to pay 18 the City for new staking with a 25 percent markup. The cost for staking will be 19 deducted from the payment due to the Contractor for the Project. 20 B. Construction Survey 21 1. Construction Survey will be performed by the City. 22 2. Coordination 23 a. Contractor to verify that control data established in the design survey remains 24 intact. 25 b. Coordinate with the City prior to field investigation to determine which 26 horizontal and vertical control data will be required for construction survey. 27 c. It is the Contractor’s responsibility to coordinate Construction Survey such that 28 construction activities are not delayed or negatively impacted. 29 d. Notify City if any control data needs to be restored or replaced due to damage 30 caused during construction operations. 31 1) City shall perform replacements and/or restorations. 32 3. General 33 a. Construction survey will be performed in order to maintain complete and 34 accurate logs of control and survey work as it progresses for Project Records. 35 b. The Contractor will need to ensure coordination is maintained with the City to 36 perform construction survey to obtain construction features, including but not 37 limited to the following: 38 1) All Utility Lines 39 a) Rim and flowline elevations and coordinates for each manhole or 40 junction structure 41 2) Water Lines 42 a) Top of pipe elevations and coordinates for waterlines at the following 43 locations: 44 (1) Every 250 linear feet 45 01 71 23 - 3 DAP CONSTRUCTION STAKING AND SURVEY Page 3 of 4 CITY OF FORT WORTH Lonestar Business Park STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Project Number: 102418 Revised April 7, 2014 (2) Horizontal and vertical points of inflection, curvature, etc. (All 1 Fittings) 2 (3) Cathodic protection test stations 3 (4) Sampling stations 4 (5) Meter boxes/vaults (All sizes) 5 (6) Fire lines 6 (7) Fire hydrants 7 (8) Gate valves 8 (9) Plugs, stubouts, dead-end lines 9 (10) Air Release valves (Manhole rim and vent pipe) 10 (11) Blow off valves (Manhole rim and valve lid) 11 (12) Pressure plane valves 12 (13) Cleaning wyes 13 (14) Casing pipe (each end) 14 b) Storm Sewer 15 (1) Top of pipe elevations and coordinates at the following locations: 16 (a) Every 250 linear feet 17 (b) Horizontal and vertical points of inflection, curvature, etc. 18 c) Sanitary Sewer 19 (1) Top of pipe elevations and coordinates for sanitary sewer lines at 20 the following locations: 21 (a) Every 250 linear feet 22 (b) Horizontal and vertical points of inflection, curvature, etc. 23 (c) Cleanouts 24 c. Construction survey will be performed in order to maintain complete and 25 accurate logs of control and survey work associated with meeting or exceeding 26 the line and grade required by these Specifications. 27 d. The Contractor will need to ensure coordination is maintained with the City to 28 perform construction survey and to verify control data, including but not 29 limited to the following: 30 1) Established benchmarks and control points provided for the Contractor’s 31 use are accurate 32 2) Benchmarks were used to furnish and maintain all reference lines and 33 grades for tunneling 34 3) Lines and grades were used to establish the location of the pipe 35 4) Submit to the City copies of field notes used to establish all lines and 36 grades and allow the City to check guidance system setup prior to 37 beginning each tunneling drive. 38 5) Provide access for the City to verify the guidance system and the line and 39 grade of the carrier pipe on a daily basis. 40 6) The Contractor remains fully responsible for the accuracy of the work and 41 the correction of it, as required. 42 7) Monitor line and grade continuously during construction. 43 8) Record deviation with respect to design line and grade once at each pipe 44 joint and submit daily records to City. 45 9) If the installation does not meet the specified tolerances, immediately notify 46 the City and correct the installation in accordance with the Contract 47 Documents. 48 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 49 01 71 23 - 4 DAP CONSTRUCTION STAKING AND SURVEY Page 4 of 4 CITY OF FORT WORTH Lonestar Business Park STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Project Number: 102418 Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS [NOT USED] 3 PART 3 - EXECUTION 4 3.1 INSTALLERS [NOT USED] 5 3.2 EXAMINATION [NOT USED] 6 3.3 PREPARATION [NOT USED] 7 3.4 APPLICATION 8 3.5 REPAIR / RESTORATION [NOT USED] 9 3.6 RE-INSTALLATION [NOT USED] 10 3.7 FIELD [OR] SITE QUALITY CONTROL 11 A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the 12 City in accordance with this Specification. 13 B. Do not change or relocate stakes or control data without approval from the City. 14 3.8 SYSTEM STARTUP [NOT USED] 15 3.9 ADJUSTING [NOT USED] 16 3.10 CLEANING [NOT USED] 17 3.11 CLOSEOUT ACTIVITIES [NOT USED] 18 3.12 PROTECTION [NOT USED] 19 3.13 MAINTENANCE [NOT USED] 20 3.14 ATTACHMENTS [NOT USED] 21 END OF SECTION 22 23 Revision Log DATE NAME SUMMARY OF CHANGE 24 01 77 19 - 1 DAP CLOSEOUT REQUIREMENTS Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 SECTION 01 77 19 CLOSEOUT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. The procedure for closing out a contract B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Guarantees, Bonds and Affidavits 1. No application for final payment will be accepted until all guarantees, bonds, certificates, licenses and affidavits required for Work or equipment as specified are satisfactorily filed with the City. B. Release of Liens or Claims 1. No application for final payment will be accepted until satisfactory evidence of release of liens has been submitted to the City. 1.5 SUBMITTALS A. Submit all required documentation to City’s Project Representative. 01 77 19 - 2 DAP CLOSEOUT REQUIREMENTS Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 CLOSEOUT PROCEDURE A. Prior to requesting Final Inspection, submit: 1. Project Record Documents in accordance with Section 01 78 39 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 01 74 23. C. Final Inspection 1. After final cleaning, provide notice to the City Project Representative that the Work is completed. a. The City will make an initial Final Inspection with the Contractor present. b. Upon completion of this inspection, the City will notify the Contractor, in writing within 10 business days, of any particulars in which this inspection reveals that the Work is defective or incomplete. 2. Upon receiving written notice from the City, immediately undertake the Work required to remedy deficiencies and complete the Work to the satisfaction of the City. 3. Upon completion of Work associated with the items listed in the City's written notice, inform the City, that the required Work has been completed. Upon receipt of this notice, the City, in the presence of the Contractor, will make a subsequent Final Inspection of the project. 4. Provide all special accessories required to place each item of equipment in full operation. These special accessory items include, but are not limited to: a. Specified spare parts b. Adequate oil and grease as required for the first lubrication of the equipment c. Initial fill up of all chemical tanks and fuel tanks d. Light bulbs e. Fuses f. Vault keys g. Handwheels h. Other expendable items as required for initial start-up and operation of all equipment D. Notice of Project Completion 01 77 19 - 3 DAP CLOSEOUT REQUIREMENTS Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 1. Once the City Project Representative finds the Work subsequent to Final Inspection to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet). E. Supporting Documentation 1. Coordinate with the City Project Representative to complete the following additional forms: a. Final Payment Request b. Statement of Contract Time c. Affidavit of Payment and Release of Liens d. Consent of Surety to Final Payment e. Pipe Report (if required) f. Contractor’s Evaluation of City g. Performance Evaluation of Contractor F. Letter of Final Acceptance 1. Upon review and acceptance of Notice of Project Completion and Supporting Documentation, in accordance with General Conditions, City will issue Letter of Final Acceptance and release the Final Payment Request for payment. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 78 23 - 1 DAP OPERATION AND MAINTENANCE DATA Page 1 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 SECTION 01 78 23 OPERATION AND MAINTENANCE DATA PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Product data and related information appropriate for City's maintenance and operation of products furnished under Contract 2. Such products may include, but are not limited to: a. Traffic Controllers b. Irrigation Controllers (to be operated by the City) c. Butterfly Valves B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Schedule 1. Submit manuals in final form to the City within 30 calendar days of product shipment to the project site. 1.5 SUBMITTALS A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be approved by the City prior to delivery. 1.6 INFORMATIONAL SUBMITTALS A. Submittal Form 1. Prepare data in form of an instructional manual for use by City personnel. 2. Format a. Size: 8 ½ inches x 11 inches b. Paper 1) 40 pound minimum, white, for typed pages 2) Holes reinforced with plastic, cloth or metal c. Text: Manufacturer’s printed data, or neatly typewritten 01 78 23 - 2 DAP OPERATION AND MAINTENANCE DATA Page 1 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 d. Drawings 1) Provide reinforced punched binder tab, bind in with text 2) Reduce larger drawings and fold to size of text pages. e. Provide fly-leaf for each separate product, or each piece of operating equipment. 1) Provide typed description of product, and major component parts of equipment. 2) Provide indexed tabs. f. Cover 1) Identify each volume with typed or printed title "OPERATING AND MAINTENANCE INSTRUCTIONS". 2) List: a) Title of Project b) Identity of separate structure as applicable c) Identity of general subject matter covered in the manual 3. Binders a. Commercial quality 3-ring binders with durable and cleanable plastic covers b. When multiple binders are used, correlate the data into related consistent groupings. 4. If available, provide an electronic form of the O&M Manual. B. Manual Content 1. Neatly typewritten table of contents for each volume, arranged in systematic order a. Contractor, name of responsible principal, address and telephone number b. A list of each product required to be included, indexed to content of the volume c. List, with each product: 1) The name, address and telephone number of the subcontractor or installer 2) A list of each product required to be included, indexed to content of the volume 3) Identify area of responsibility of each 4) Local source of supply for parts and replacement d. Identify each product by product name and other identifying symbols as set forth in Contract Documents. 2. Product Data a. Include only those sheets which are pertinent to the specific product. b. Annotate each sheet to: 1) Clearly identify specific product or part installed 2) Clearly identify data applicable to installation 3) Delete references to inapplicable information 3. Drawings a. Supplement product data with drawings as necessary to clearly illustrate: 1) Relations of component parts of equipment and systems 2) Control and flow diagrams b. Coordinate drawings with information in Project Record Documents to assure correct illustration of completed installation. c. Do not use Project Record Drawings as maintenance drawings. 4. Written text, as required to supplement product data for the particular installation: a. Organize in consistent format under separate headings for different procedures. b. Provide logical sequence of instructions of each procedure. 01 78 23 - 3 DAP OPERATION AND MAINTENANCE DATA Page 3 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 5. Copy of each warranty, bond and service contract issued a. Provide information sheet for City personnel giving: 1) Proper procedures in event of failure 2) Instances which might affect validity of warranties or bonds C. Manual for Materials and Finishes 1. Submit 5 copies of complete manual in final form. 2. Content, for architectural products, applied materials and finishes: a. Manufacturer's data, giving full information on products 1) Catalog number, size, composition 2) Color and texture designations 3) Information required for reordering special manufactured products b. Instructions for care and maintenance 1) Manufacturer's recommendation for types of cleaning agents and methods 2) Cautions against cleaning agents and methods which are detrimental to product 3) Recommended schedule for cleaning and maintenance 3. Content, for moisture protection and weather exposure products: a. Manufacturer's data, giving full information on products 1) Applicable standards 2) Chemical composition 3) Details of installation b. Instructions for inspection, maintenance and repair D. Manual for Equipment and Systems 1. Submit 5 copies of complete manual in final form. 2. Content, for each unit of equipment and system, as appropriate: a. Description of unit and component parts 1) Function, normal operating characteristics and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Operating procedures 1) Start-up, break-in, routine and normal operating instructions 2) Regulation, control, stopping, shut-down and emergency instructions 3) Summer and winter operating instructions 4) Special operating instructions c. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Alignment, adjusting and checking d. Servicing and lubrication schedule 1) List of lubricants required e. Manufacturer's printed operating and maintenance instructions f. Description of sequence of operation by control manufacturer 1) Predicted life of parts subject to wear 2) Items recommended to be stocked as spare parts g. As installed control diagrams by controls manufacturer h. Each contractor's coordination drawings 1) As installed color coded piping diagrams 01 78 23 - 4 DAP OPERATION AND MAINTENANCE DATA Page 4 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 i. Charts of valve tag numbers, with location and function of each valve j. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage k. Other data as required under pertinent Sections of Specifications 3. Content, for each electric and electronic system, as appropriate: a. Description of system and component parts 1) Function, normal operating characteristics, and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Circuit directories of panelboards 1) Electrical service 2) Controls 3) Communications c. As installed color coded wiring diagrams d. Operating procedures 1) Routine and normal operating instructions 2) Sequences required 3) Special operating instructions e. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Adjustment and checking f. Manufacturer's printed operating and maintenance instructions g. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage h. Other data as required under pertinent Sections of Specifications 4. Prepare and include additional data when the need for such data becomes apparent during instruction of City's personnel. 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Provide operation and maintenance data by personnel with the following criteria: 1. Trained and experienced in maintenance and operation of described products 2. Skilled as technical writer to the extent required to communicate essential data 3. Skilled as draftsman competent to prepare required drawings 01 78 23 - 5 DAP OPERATION AND MAINTENANCE DATA Page 5 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.5.A.1 – title of section removed 4/7/2014 M.Domenech Revised for DAP Application 01 78 39 - 1 DAP PROJECT RECORD DOCUMENTS Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 SECTION 01 78 39 PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Work associated with the documenting the project and recording changes to project documents, including: a. Record Drawings b. Water Meter Service Reports c. Sanitary Sewer Service Reports d. Large Water Meter Reports B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to City’s Project Representative. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Accuracy of Records 1. Thoroughly coordinate changes within the Record Documents, making adequate and proper entries on each page of Specifications and each sheet of Drawings and other Documents where such entry is required to show the change properly. 2. Accuracy of records shall be such that future search for items shown in the Contract Documents may rely reasonably on information obtained from the approved Project Record Documents. 01 78 39 - 2 DAP PROJECT RECORD DOCUMENTS Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 3. To facilitate accuracy of records, make entries within 24 hours after receipt of information that the change has occurred. 4. Provide factual information regarding all aspects of the Work, both concealed and visible, to enable future modification of the Work to proceed without lengthy and expensive site measurement, investigation and examination. 1.10 STORAGE AND HANDLING A. Storage and Handling Requirements 1. Maintain the job set of Record Documents completely protected from deterioration and from loss and damage until completion of the Work and transfer of all recorded data to the final Project Record Documents. 2. In the event of loss of recorded data, use means necessary to again secure the data to the City's approval. a. In such case, provide replacements to the standards originally required by the Contract Documents. 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 2.2 RECORD DOCUMENTS A. Job set 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no charge to the Contractor, 1 complete set of all Documents comprising the Contract. B. Final Record Documents 1. At a time nearing the completion of the Work and prior to Final Inspection, provide the City 1 complete set of all Final Record Drawings in the Contract. 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 MAINTENANCE DOCUMENTS A. Maintenance of Job Set 1. Immediately upon receipt of the job set, identify each of the Documents with the title, "RECORD DOCUMENTS - JOB SET". 01 78 39 - 3 DAP PROJECT RECORD DOCUMENTS Page 3 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 2. Preservation a. Considering the Contract completion time, the probable number of occasions upon which the job set must be taken out for new entries and for examination, and the conditions under which these activities will be performed, devise a suitable method for protecting the job set. b. Do not use the job set for any purpose except entry of new data and for review by the City, until start of transfer of data to final Project Record Documents. c. Maintain the job set at the site of work. 3. Coordination with Construction Survey a. At a minimum clearly mark any deviations from Contract Documents associated with installation of the infrastructure. 4. Making entries on Drawings a. Record any deviations from Contract Documents. b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the change by graphic line and note as required. c. Date all entries. d. Call attention to the entry by a "cloud" drawn around the area or areas affected. e. In the event of overlapping changes, use different colors for the overlapping changes. 5. Conversion of schematic layouts a. In some cases on the Drawings, arrangements of conduits, circuits, piping, ducts, and similar items, are shown schematically and are not intended to portray precise physical layout. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) However, design of future modifications of the facility may require accurate information as to the final physical layout of items which are shown only schematically on the Drawings. b. Show on the job set of Record Drawings, by dimension accurate to within 1 inch, the centerline of each run of items. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in ceiling plenum", "exposed", and the like). 3) Make all identification sufficiently descriptive that it may be related reliably to the Specifications. c. The City may waive the requirements for conversion of schematic layouts where, in the City's judgment, conversion serves no useful purpose. However, do not rely upon waivers being issued except as specifically issued in writing by the City. B. Final Project Record Documents 1. Transfer of data to Drawings a. Carefully transfer change data shown on the job set of Record Drawings to the corresponding final documents, coordinating the changes as required. b. Clearly indicate at each affected detail and other Drawing a full description of changes made during construction, and the actual location of items. c. Call attention to each entry by drawing a "cloud" around the area or areas affected. 01 78 39 - 4 DAP PROJECT RECORD DOCUMENTS Page 4 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Landmark Quebec Addition 102418 d. Make changes neatly, consistently and with the proper media to assure longevity and clear reproduction. 2. Transfer of data to other Documents a. If the Documents, other than Drawings, have been kept clean during progress of the Work, and if entries thereon have been orderly to the approval of the City, the job set of those Documents, other than Drawings, will be accepted as final Record Documents. b. If any such Document is not so approved by the City, secure a new copy of that Document from the City at the City's usual charge for reproduction and handling, and carefully transfer the change data to the new copy to the approval of the City. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP Application