HomeMy WebLinkAboutContract 43170-CO1 (2)FORT WORTH,. Project Name' Client Project #(s)I City of Fort Worth Change Order Request Hot In Place Recycling/HMAC Surface Overlay (2012-02) City Project No.: 01864 DOE: 6799 Project Description) HMAC Surface Overlay - Street Maintenance Contractor' Cutler Repaving, Inc. City Project Mgr.' Kristian Sugrim (817) 392-8902 Enter Department(s) to the Right and Contract Day Type Original Contract Amount $1,110,038.90 Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1,110,038.90 !Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO $0.00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) Change Order # TY SECRETARY C,ONTRACTNO. c I City Sec # I 43170 1 I Date I 8/4/2012 City Inspector I David W. Bowers TPW $0.00 $1,110,038.90 (817) 350-3522 Totals $1,110,038.90 $1,110,038.90 $1,110,038.90 $0.00 0.00% $1,387,548.63 Contract Time (CD) 80 80 45 125 JUSTIFICATION (REASONS) FOR CHANGE ORDER This change order is being submitted to request the addition of a new line item, 13 eight inches Reinforced Concrete Bus Pads on Boca Raton Blvd. (Woodhaven Blvd - E. Loop 820). Additionally, 45 Calendar Days (CD) is being requested to complete the added work. 47 Attested by. �� o°°°"$0���� OFFICIAL RECORD a)4IP .4 / CITY SECRETARY Ka set po Q� FT. WORTH,TX MaryJ. J y��Cty °oo It is understood and agreed that the acceptance of this Change kirtebcontractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Cutler Repaving, Inc. Inspector/Ins ectioq/S,pervisgr ,4),7 M&C Number I n// 4 Date ��Asy;0l):,Y�y Manager q Council Action (if required) M&C Date Approved Contractor (Name) Contract Sign�tuurre/ Q 4i G►''d f/zey , pate Date Project Mang, er/Program Manacier , Date ho(-ICE • /AJ 141 c6l12. Date lektor, C9ptrac g Departmen (Dept) Date CJf_ 0 . c 0/l6/i z 6 % . ate,, g /Z///4 CicicA I 4., of kFORT WORTH,, City of Fort Worth Change Order Request Project Name' Hot In Place Recycling/HMAC Surface Overlay (2012-02) 1 City Sec # I 43170 Client Project #(s)I City Project No.: 01864 DOE: 6799 Project Description) HMAC Surface Overlay - Street Maintenance Contractor' Cutler Repaving, Inc. City Project Mgr.' Kristian Sugrim (817) 392-8902 Enter Department(s) to the Right and Contract Day Type Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Change Order # I 1 I Date I 8/4/2012 City Inspector I David W. Bowers (817) 350-3522 TPW Totals $1,110,038.90 $1,110,038.90 Contract Cost to Date $1,110,038.90 $1,110,038.90 !Amount of Proposed Change Order $0.00 Revised Contract Amount $1,110,038.90 $1,110,038.90 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) I $1,387,548.63 0.00% JUSTIFICATION (REASONS) FOR CHANGE ORDER This change order is being submitted to request the addition of a new line item, 13 eight inches Reinforced Concrete Bus Pads on Boca Raton Blvd. (Woodhaven Blvd - E. Loop 820). Additionally, 45 Calendar Days (CD) is being requested to complete the added work. Contract Time (CD) 80 80 45 125 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Cutler Repaving, Inc. Inspector/Inspection 6petvis r, /9 ifei4,4=— Assistant Director? (Dept Assistant afi Attorney M&C Number A// A. Contractor (Name)e f 77 Gl ,rC>Li�l"- Contract Signature Date /i0//2 LDate Project Man er/Program Manager„ 1>>:11; Date Dire tor, Contracting Departmen (Dept) Date tJ4 i -/ -7-/2i ,,, C-J • LJ c,,-- h //L/ z Z .1 L " anager d ---" g/.2/ 41 it te (Ok Council Action (if required) M&C Date Approved ' -FORT WORTH. City of Fort Worth Change Order Request Project Name Hot In Place Recycling/HMAC Surface Overlay (2012-02) Client Project #(s)I City Project No.: 01864 Project Description) HMAC Surface Overlay - Street Maintenance Contractor Cutler Repaving, Inc. City Project Mgr.' Kristian Sugrim Enter Department(s) to the Right and Contract Day Type Original Contract Amount $1,110,038.90 Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1,110,038.90 !Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER This change order is being submitted to request the addition of a new line item, 13 eight inches Reinforced Concrete Bus Pads on Boca Raton Blvd. (Woodhaven Blvd - E. Loop 820). Additionally, 45 Calendar Days (CD) is being requested to complete the added work. (817) 392-8902 DOE: 6799 Change Order # I 1 Col/A( NI- of /I. I(..(( City Sec # I 43170 City Inspector I David W. Bowers Date I 8/4/2012 (817) 350-3522 TPW $1,110,038.90 $1,110,038.90 $0.00 $1,110,038.90 $0.00 Totals $1,110,038.90 $0.00 0.00% $1,387,548.63 Contract Time (CD) 80 80 45 125 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Cutler Repaving, Inc. Inspector/Inspectiop Gpervisor Assistant Director' (Dept) Assistant;City ,4ttorney Contractor (Name) Contract Signature Date Project Manager/Program Manager. t lttl ot.r;;f'.,,,n, Date Director, Contracting Department (Dept) Date AssistantC1tyManager 21.1 1-- Council Action (if required) Date Date Date ‘,k 44 M&C Number I M&C Date Approved I FORT WORTH, City of Fort Worth Change Order Request Project Namel Hot In Place Recycling/HMAC Surface Overlay (2012-02) Client Project #(s)I City Project No.: 01864 DOE: 6799 Project Description) HMAC Surface Overlay - Street Maintenance Contractor) Cutler Repaving, Inc. City Project Mgr.' Kristian Sugrim (817) 392-8902 Enter Department(s) to the Right and Contract Day Type Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date 'Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) I City Sec # I 43170 Change Order # I 1 I Date I 8/4/2012 City Inspector I David W. Bowers (817) 350-3522 TPW $1,110,038.90 $1,110,038.90 $0.00 $1,110,038.90 $0.00 Totals Contract Time (CD) $1,110,038.90 80 $1,110,038.90 80 45 $1,110,038.90 125 $0.00 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00% I MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) I $1,387,548.63 JUSTIFICATION (REASONS) FOR CHANGE ORDER This change order is being submitted to request the addition of a new line item, 13 eight inches Reinforced Concrete Bus Pads on Boca Raton Blvd. (Woodhaven Blvd - E. Loop 820). Additionally, 45 Calendar Days (CD) is being requested to complete the added work. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Cutler Repaving, Inc. Inspector/Inspection Supervisor Assistant Director (Dept) Assistant City Attorney Contractor (Name) Date Date Date Contract Signature Project Manager/Program Manager Director, Contracting Department (Dept) Assistant City Manager Date Date Date Date Council Action (if required) M&C Number M&C Date Approved FORT WORTH City of Fort Worth Change Order Additions Project Name I Hot In Place Recycling/HMAC Surface Overlay (2012-02) Client Project # I City Project No.: 01864 Project Description Contractor City Project Mgr. HMAC Surface Overlay - Street Maintenance Cutler Repaving, Inc. Kristian Sugrim ITEM 28 (New) 8" Concrete bus Pads UES(:FUP I IUN (817) 392-8902 DOE: 6799 I Change Order # 1 City Inspector I David W. Bowers ADDITIONS ULP l I PO/ Uty Unit YbU.UU SY City Sec # I 43170 Date I 8/4/2012 (817) 350-3522 unit Uost 1 otal $12U.b9 $114,bbb.bU Change Order Additions Page 1 of 2 TPW $114,655.50 Sub Total Additions $114,655.50 Change Order Additions Page 2 of 2 FORT WORTH City of Fort Worth Change Order Deletions Project Name I Hot In Place Recycling/HMAC Surface Overlay (2012-02) Client Project # I City Project No.: 01864 DOE: 6799 Project Description HMAC Surface Overlay - Street Maintenance Contractor Cutler Repaving, Inc. I Change Order # City Project Mgr. Kristian Sugrim (817) 392-8902 11E141 8 (Uec) Unclassified Excavation 10 (Dec) Asphalt Base Repair 11 (Dec) 1" Hot In Place Recycling 13 (Dec) Flex Base Type "A" 14 (Dec) 1" Asphalt Type "D" 15 (Dec) Asphalt Pavement Level Up 16 (Dec) 6" Concrete Pavement (2:27) UESCKIP I IUN DELETIONS 1 I City Sec # I 43170 Date I 8/4/2012 City Inspector I David W. Bowers (817) 350-3522 UEP I t�ty Unit Unit Cost I otal I PVV SU.UU UY $24.UU $ti,000.UU TPW 165.00 CY $190.00 $31,350.00 TPW 4,083.79 SY $2.40 $9,801.1D TPW 799.00 SY $9.00 $7,19T.00 TPW 234.00 TN $85.40 $19,983.8U TPW 191.00 TN $89.00 - -- $T6,999-00 TPW 799.00 SY $29.20 $23,33U.8U Change Order Deletions Page 1 of 2 TPW $114,655.50 Sub Total Deletions $114,655.50 Change Order Deletions Page 2 of 2 MWBE Sub MBE Breakdown for this Change Order Type of Service Amount for this CO Total $0.00 Previous Change Orders Co# DATE AMOUNT Total $0.00 PROJECT SUMMARY SHEET (Change Order Attachment) PROJECT NAME: Hot In -Place Recycling 2012-2 BuySpeed No (T/PW): PO-12-00071712 BuySpeed No (Water): N/A City Project No: 01864 Contract No: CS43170 Original M & C approved 04-17-12, C-25566 D.O.E. No: 6799 Attachment to Change Order No: 1 Today's Date: 8/8/12 TOTAL Original Contract Amount: $ 1,110,038.90 Extras to Date: $ Credits to Date: $ Contract Amount to Date: $ 1,110,038.90 Amount of Proposed Change Order: TIME ONLY Revised Contract Amount: $ 1,110,038.90 Contingency Funds Avail. for Admin. Change Orders: Remaining Funds Available for Change Orders: Additional Funding (if necessary): Original Days: 80 Additional Time Requested CO#1: 45 Total Days: 125 $ $ $ Prepared By: Christy Ezernack T/PW Construction Services