HomeMy WebLinkAboutContract 56983-CO2CSC No. 56983-CO2 FORT WORTH® City of Fort Worth Change Order Request Project Name North Z. Boaz Park Improvement Capital Improvements City Sec # 56983 Client Project#(s) 101768 Project This change order includes the hauling of rock for future construction of berms on mountain bike trail, retaining wall revisions and additional back fill for Description grading of wall. Item removed from scope is to be billed to Art Council. Contractor Cole Construction Change Order# 2 Date 1 12/14/2022 City Project Mgr. Helen Florez City Inspector Sergio Garcia Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date PARD I Totals $2,191,356.40 Contract Time I (CD) 230 5 .4 $49,747.57 $49,747.57 $2,241,103.97 $2,241,103.97 $54,191.04 $2,295,295.01 230 60 290 Amount of Proposed Change Order 54,191.04 Revised Contract Amount 2,295,295.01 Original Funds Available for Change Orders $219,135.64 Remaining Funds Available for this CO $169,38..07 Additional Funding (if necessary) CHANGE ORDERS to DATE MAXALLOWABLE CONTRACT $219,135.64 $169,388.07 (INCLUDING THIS ONE) AMOUNT AS % OF ORIGINAL (ORIGINAL CONTRACT CONTRACT COST+ 15%) 4.74% $2,739,195.50 I low JUSTIFICATION (REASONS) FOR CHANGE ORDER Retaining wall was relocated and redesigned requiring additional materials. Rock is being moved for use by Fort Worth Mountain Bike Association in their construction of a mountain bike trail in North Z. Boaz Park. Item removed from scope is to be billed to Art Council. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible forthe monitoring and administration ofthis contract, including ensuring all performance and reporting requirements. 1llKn:t—ra,-t&s Company NameS Contractor (Namen Contract Signature Cole Construction Tim Wade ate Dec 27, 2022 Inspector/Inspection Supervisor Date Project and Contract Compliance Manager Date auv ers gyp„ oogar� Dec 28, 2022�� �'. �p ( 12/27/22 Program Manager Date Senior Capital Project 0 er Date Jan 9, 2023 Jan 9, 2023 nt Director (Dept) Date Director, Contracting Department (Dept) Date Jan 18,2023e Jan 24,2023 Attorney REPOW Date Assistant City Manager Date Jan 24, 2023 Jan 27, 2023 Council Mtion (if required) M&C Number I N/A Jannette Goodall, City Secretary o�vvnp FORto�dA v°moo°�-Id I Ovo o=4 �C & ao p �o 45gp4 M&C Date Approved NIA OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT WORTH City of Fort Worth !'--- Change Order Additions Project Name North Z. Boaz Park Improvement Capital Improvements City Sec # 56983 Client Project# 101768 Contractor Cole Construction PM Helen Florez Inspector Sergio Garcia Change Order Submittal # Date �r ADDITIONS Change Order Additions Page 2 of 4 FORT WORTH City of Fort Worth Change Order Deletions Project Name North Z. Boaz a mprovement Capital Improvements City Sec # Client Project # Contractorl Cole Construction PM Helen Florez Inspectof Sergio Garcia Change Order Submittal # Date DELETIONS Change Order Deletions Page 3 of 4 M/SBE for this Change Order M/SBE Sub I Type of Service Amount for this CO maintaining commitment of original agreement of 15% Total $0.00