HomeMy WebLinkAboutOrdinance 22020-12-2015 ORDINANCE NO.22020-12-2015
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER CAPITAL PROJECTS FUND IN THE
AMOUNT OF $1,716,450.00, FROM AVAILABLE FUNDS, FOR THE PURPOSE
OF FUNDING THE WATER AND SANITARY SEWER REPLACEMENT
CONTRACT 2015 WSM-C, PART 2; PROVIDING FOR A SEVERABIL,ITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2015-2016 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
Capital Projects Fund in the amount of$1,716,450.00, from available funds, for the purpose of funding the
Water and Sanitary Sewer Replacement Contract 2015 WSM-C, Part 2.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance No. 21873-09-2015 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:,;' °°"
Douglas W. Black, ar J. k#1
Sr.Assistant City Attorney City Seerdt
ADOPTED AND EFFECTIVE:December 15,2015
Ordinance No.22020-12-2015
Page 1 of 1
I
COMMUNICATION MAYOR AND COUNCIL
r�) I
I t
AO .
����J,,;,,,, �.,... '110,�. i� i � .' SQL u � I '. �✓i i �I
8 I
I
I lil oil I
r ,
r
o
d 0 G MEADOWBROOK+DR
0i
Qw..
MEADOWS � Q
r
�— PURINGTON AVE
I,
UR INGTON AVE
a
MOUNT VER
m
n
LANCASTER AVE
' �,.Ir- Z � ❑ �,,,, i Ana „�,, � „„ �� n �v H „d, � �� r ,
MCLEAN ST w �� �ST
m
/ r
a
f 1 ff rr�y/�J PANOLA ST � ,� PANOLA STS
t ,,
HAZE LINE RD
FORTWOR
mr �
w
/
wax
!.m
COMMUNICATION MAYOR AND COUNCIL
,
d� /i✓w>;� v;r G%N`.�kn a ✓ �fi/ ➢ ;° / ri rail
STHY—�-�ROSEDALE ST
11
' n
v
n / /
e
,
,,,,, ,„ „.. ,�i �✓° ,N�, n � ,rrore umymmw �7H we��w ,. �,wmw°«, 1°"iw v� �,. 'i";G� ""'
vv
/
H ! �
M IIIIIII,�! i I
✓�/ of a n� � � " , ',
t y
,
/
r
/
/
r
EN 'ii ,✓/„/,/,,,,,,,,,,��,,,a,,,,,,,,,,�,,,,,,,/,,,//,//,/,,r,,�/�l�I ri�,°, ��1�/r, ,�i//� r �� lii r, r< , �/1 ,,/�,, � , , , ,a
//i//wn✓ 1, / �/ �� � l' ,� �.�. ,.��� ,;;:.;� ✓ / � a.
UJ
FORT WO
a
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 12/15/2015 -Ordinance No. 22020-12-2015
DATE: Tuesday, December 15, 2015 REFERENCE NO.: C-27577
LOG NAME: 6015WSMCP2 - WOODY
SUBJECT:
Authorize Execution of a Contract with Woody Contractors, Inc., in the Amount of$1,516,450.00 for Water
and Sanitary Sewer Replacement Contract 2015 WSM-C, Part 2 on Canyon Ridge Avenue, Jamaica Lane,
Toronto Avenue, Purington Avenue, Avenue H and Avenue I, Provide for Project Costs and Contingencies
in the Amount of$200,000.00 for a Project Total in the Amount of$1,716,450.00 and Adopt Appropriation
Ordinance (COUNCIL DISTRICTS 5 and 8)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Appropriation Ordinance increasing estimated receipts and appropriations in the
Water Capital Projects Fund in the amount of$1,716,450 from available funds; and
2. Authorize the execution of a contract with Woody Contractors, Inc., in the amount of$1,516,450.00. for
Water and Sanitary Sewer Replacement Contract 2015 WSM-C, Part 2.
DISCUSSION:
On February 17, 2015 (M&C C-27192), the City Council authorized an Engineering Agreement with Baird,
Hampton & Brown, Inc., to prepare the plans and specifications for Water and Sanitary Sewer
Replacement Contract 2015 WSM-C.
This Mayor and Council Communication is to authorize a construction contract for the replacement of the
deteriorated water mains on the following streets:
Street I From T To
Canyon Ridge Avenue i a-ma i cm Lane IS. Ayers Avenue
Jamaica Lane IPanola Avenue Canyon Ridge Avenue
Toronto Avenue I Bomar Avenue IPurington Avenue
Purington Avenue Ben Street ITandy Lane
Avenue H S. Beach Street McKenzie Street
Avenue I S. Beach Street McKenzie Street
The project was advertised for bid on August 6, 2015 and August 13, 2015 in the Fort Worth Star-
Telegram. On September 3, 2015 the following bids were received:
Logname: 6015WSMCP2 - WOODY Page 1 of 3
Bidder Amount ITime of Completion
Woody Contractors, Inc. $1,516,450.00 190 Calendar Days
Conatser Construction TX, LP $1,597,075.00
Ark Contracting Services, LLC $1,624,125.00
R & D Burns Brothers, Inc. $1,964,402.00
IM-CO Construction, Inc. $2,178,385.00
Atkins Brothers Equipment Company, Inc. $2,221,105.00
In addition to the contract cost, $120,000.00 is required for project management, inspection and material
testing and $80,000.00 is provided for project contingencies.
Appropriations for the Water and Sanitary Sewer Replacement Contract 2015 WSM-C, Part 1 and 2
Project will consist of the following:
F Description Amount
Baird, Hampton & Brown Inc. $1 85,120.00
William J. Schultz, Inc. dba Circle "C "Construction Company $ 960,625.00
(Woody Contractors, Inc. $1,516,450.00
Project Management, Inspection, Material Testing and $ 369,448.00
Contingencies I T
Total Project Budget $3,031,643.00
Funding for the Water and Sanitary Sewer Replacement Contract 2015 WSM-C, Part 1 and 2 Project will
consist of the following:
FUND 1:ppropriations'evised
Water Capital Projects Fund 59601 $ 2,745,557.00
Sewer Capital Projects Fund 59607 __ [$ 286,086.00
(Project Total $ 3,031,643.00
**Appropriations are dependent upon approval of M&C Log Name 6015WSMCP1 - CIRCLEC.
Construction is anticipated to commence in January 2016. With a contract time of 190 calendar days, the
project is estimated to be complete by mid July 2016.
This project will have no impact on the Water Department operating budget.
M/WBE OFFICE -Woody Contractors, Inc., is in compliance with City's BIDE Ordinance by committing to
nine percent MBE participation on this project. The City's MBE goal on this project is seven percent.
The project is located in COUNCIL DISTRICTS 5 and 8, Mapsco 7813, 78F, 78G, 78K, 78J.
Logname: 6015WSMCP2 - WOODY Page 2 of 3
The Financial Management Services Director certifies that upon approval of the above recommendations
and adoption of the attached appropriation ordinance, funds will be available in the current capital budget,
as appropriated, of the Water Capital Projects Fund. The Fiscal Year 2016 Water Operating Budget
includes appropriations of$26,068,353.00 for the purpose of providing pay-as-you-go funding for capital
projects. After this transfer for Fiscal Year 2016, the balance will be $19,154,996.67.
Pending
Fund Project Encumbrances Remaining
Appropriations and Balance
Expenditures
Water
Capital $2 ,745,557.00 $ 2,734,609.01 $10,947.99
(59601)
Sewer
Capital $ 286,086.00 $ 285,619.40 $ 466.60
(59607)
FUND IDENTIFIERS (FIDs):
TO
Fund Department Accouni Project Program Activity Budget Reference # Amount
ID ID Year Chartfield 2
59601 0600430 4956001 CO2434 C01783 2016 $1,716,450.00
3 1596011 0600430 5740010 CO2434 C01783 2016 $1,516,450.00
FROM
Fund Department Accoun Project Program ctivit Budget Reference # Amount
ID ID Year (Chartfield 2)
13)596011 0600430 15740010 1 CO2434 I C017831 2016 1 $1,516,450.00
CERTIFICATIONS:
Submitted for City Manager's Office by_ Jay Chapa (6122)
Originating Department Head: John Carman (8246)
Additional Information Contact: Liam Conlon (6824)
Logname: 6015WSMCP2 - WOODY Page 3 of 3