HomeMy WebLinkAboutIR 9835 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 9835
To the Mayor and Members of the City Council January 26, 2016
h�T�i7 Page 1 of 3
�i
�i7 Y
*a SUBJECT: ENTERPRISE RESOURCE PLANNING PROJECTS
#qrF rn
f e'?5
The purpose of this Informal Report is to provide the City Council a summary on the City's
Enterprise Resource Planning (ERP) Projects beginning August 26, 2008 (M&C G-16255) when
Council authorized Phase I of the ERP initiative designed to address weaknesses identified in
several management letters from the City's auditor.
ERP Phase I — Human Capital Management
ERP Phase I encompassed the PeopleSoft Payroll/Timekeeping implementation providing
functionality for: Time & Labor, Payroll, Human Resources, Absence Management, Benefits
Administration, and Recruiting. In October 2010, the Payroll/Timekeeping modules went into
production replacing the previous Genesys system. ERP Phase I stabilization efforts continued
through October of 2012. At that time, the ERP Phase I project was closed and the remaining
project funds were transferred to General Debt Service on March 3, 2015, M&C G-18422.
Capital Investment Summary: ERP Phase I - HCM
Available Funds $25,215,681
Expenditures $24,109,179
Balance $ 1,106,502 Applied to Debt Service
ERP Phase II — Financials
ERP Phase 11 encompassed the PeopleSoft Financials implementation. To address the
operational impacts on the organization, the project was broken down into sub-phases. Phase
IIA went partially into production starting with Asset Management in August 2014. On October 1 ,
2015 the remaining Phase 11 modules of Accounts Payable, Accounts Receivable (Deposit), Cash
Management, Commitment Control, General Ledger, and integration with the PeopleSoft
Payroll/Timekeeping and the BuySpeed Purchasing Systems (collectively known as Enhanced
General Ledger) were moved into production. ERP Phase 11 is scheduled to be closed in
November 2016. The total project expenditures through this date are projected to be
$33,870,316 which include stabilization activities, the achievement of monthly/quarterly financial
management reporting, and year-end close milestones. An estimated balance of$19,594,435 is
expected to be available for future efforts as described in the Informal Report: ERP Financials
Update and Future Phases, provided City Council on 11/17/2015. It is anticipated that this future
work will continue through at least FY2017 and will be prioritized among capital technology needs
across the organization.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 9835
To the Mayor and Members of the City Council January 26, 2016
h�T�i7 Page 2 of 3
�i
�i7 Y
*a SUBJECT: ENTERPRISE RESOURCE PLANNING PROJECTS
#qrF rn
f e'?5
Capital Investment Summary: ERP Phases — Financials
Available Funds Original Funding $57,617,659
Transfer Out/Refunds $ 4,152,908
Net Available Funds $53,464,751
Project Expenses Estimated to Complete Phase IIA $33,870,316
Additional Capital/Reserve for $19,594,435 IR 9821 , 11/17/2015
Future Phases identified additional
modules and
functionality that are
scheduled; the
summary table is
included below.
Planned Use of Additional Capital/Reserve for Future Phases
Track 1 Track 2 Track 3
Accounts Receivable Budget Purchasing & Projects
Receivables Hyperion Workforce Purchasing
Planning
Billing Hyperion Planning Plus eProcurement
Point of Sale System * Hyperion Public Sector Supplier Contract
Planning Budgeting ** Management
eSupplier Connection
eSettlements
* System to be selected and purchased as part of Track 1 Strategic Sourcing
** Module to be purchased as part of Track 2 Inventory Management
Contracts
Grants
Project Costing
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 9835
To the Mayor and Members of the City Council January 26, 2016
h�T�i7 Page 3 of 3
�i
�i7 Y
*a SUBJECT: ENTERPRISE RESOURCE PLANNING PROJECTS
#qrF rn
ye,?5
Recurring Operating Expenses
The ERP system replaces several legacy systems such as Genesys, MARS, and the mainframe
revenue system as well as numerous desktop ad hoc systems based on Excel and MS Access
databases. By decommissioning the MARS and Genesys systems, and migrating the revenue
system to a temporary operating platform, the IBM mainframe has been decommissioned saving
approximately $835,000 annually. This savings will not be fully realized until implementation of
the future billing modules to replace the mainframe revenue system. The estimated annual
operating expense for the current ERP environment is provided in the following table.
Estimated Annual Operating Expense for HCM and FSCM
Staff- 22 AP's (ITS, FMS, HR) $1,771,884 Salaries and Benefits
Outsourced/Contract Support $1,400,000 Project software
development efforts
Software Maintenance $ 576,000 Oracle software licensing
Upgrades $ 500,000 Estimated $1 .5M/3 years
Total $4,247,884
For questions or further information, please contact Kevin Gunn (x2015) or Aaron Bovos (x8517).
David Cooke
City Manager
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS