HomeMy WebLinkAboutContract 46527-CO4 CITY SECRETAW
Ap FORT Wc>wrH City of Fort Worth CONMCTNO.�C,91
Change Order Request
Project Name I Little Fossil Creek Interceptor M-292 Improvements,Part 1 City Sec No. 1 46527
Project No.(s) P258-701170196083 = DOE No. 7046 CityProj.No.1 01960
Project Description: Little Fossil Creek Interceptor Improvements Part I from NE Loop 820 North Frontage Rd.to Missy Lane
Contractor: PM Construction and Rehab,L.P. Change Order: 0 Date: 1/20/2016
City Project Mgr. Roberto Sauceda City Inspector: Paul Gieger
Phone Number: 817-392-2387 Phone Number: 817-392-8371
Dept. Sewer Totals Contract Time
(Calender days)
Original Contract Amount $2,966,514.00 $2,966,514.00 220
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,966,514.00 $2,966,514.00 220
Amount of Proposed Change Order 40.38 -$0.38
Revised Contract Amount $2,966,513.62 $2,966,513.62 220
Original Funds Available for Change Orders $90,000.00 $901000.00
Remaining Funds Available for this CO $90,000.00 $90,000.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $3,708,142.50
The change order will provide compensation for additiaonal pay item quanitites of concrete channel
removal/replacement,concrete sidewalk removal/replacement and seeding that were are necessary to
complete the project.The change order will also allow for the deletion of the pay item quanitity for 24-
inch sewer point repair that is no longer needed on the
v0Rr�
X OFFICIAL RECORD
*` ° CITY SECRETARY
FT.WORTH,TX
Y er, ty :
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
IPM Construction and Rehab,L.P. Robert Donath
r- - /Zf
%on S s o a 4r A rJ 4COO w C1
M&C Number N/A M&C Date Approved N/A
e
FORT WORTH City of Fort Worth
00- Change Order Additions
Project Name Little Fossil Creek Interceptor M-292 Improvements,Part 1 City Sec No. 1 46527
Project No.(s) P258-701170196083 DOE No.= City Proj.No. 01960
Project Little Fossil Creek Interceptor Improvements Part I from NE Loop 820 North Frontage Rd.to Missy Lane
Description
Contractor PM Construction and Rehab,L.P. Change Order: L__',J Date: 112012016
City Project Mgr. Roberto Sauceda City Inspector F Paul Gieger
ADDITIONS
DIESMIFTION - DEFIT Qty JUnit JUAItCostTotai
19 Remove/Replace 6"Concrete in Channel Sewer 110.00 SF $16.00 $1,760.00
20 Remove/Replace 4"Concrete sidewalk Sewer 840.00 SF $10.00 $8,400.00
21 Seeding Restoration Sewer 55000.00 SF $0.04 $2,200.00
Sewer $12,360.00
Page 2 of 4 Additions Sub Total 1$12,360.00
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Little Fossil Creek Interceptor M-292 Improvements,Part 1 City Sec No. 46527
Project No.(s) P258-701170196083 DOE No. EKI City Proj.No. Q1960
Project Description Little Fossil Creek Interceptor Improvements Part I from NE Loop 820 North Frontage Rd.to Missy Lane
Contractor PM Construction and Rehab, L.P. Change Order: 0 Date 1120/2016
City Project Mgr. Roberto Sauceda City Inspector F Paul Gieger
DELETIONS
ITEM DESCRlPTIN DEPT Qty Unit Unit Cost Total
13 24"Sewer Pipe,Point Repair Sewer 213.11 LF $58.00 $12,360.38
Sewer $12,360.38
Page 3 of 4 Deletions Sub Total 1$12,360.38
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 4 of 4