Loading...
HomeMy WebLinkAboutContract 46853-CO1 FORT WORTH.., City of Fort Worth conn-C-7 . ' s Change Order Request Breakdown Project Namel North Z. Boaz Park-Dog Park Improvements City Sec# 1 46853 Client Project#(s)l C210/541200/803490221883 Contractor Raydon, Inc. PM Scott Penn I Inspectorl Adilda Cazorla Change Order Submittal# 0 Date 9/4/2015 Dept. PACSD Totals Contract Time CD Original Contract Amount $585,575.70 $585,575.70 120 Extras to Date $0.00 Credits to Date $0.00 Pending Change Orders(in M&C Process) Contract Cost to Date $585,575.70 $585,575.70 120 Amount of Proposed Change Order $11,194.00 $11,194.00 10 Revised Contract Amount $596,769.70 $596,769.70 130 Original Funds Available for Change Orders $20,000.00 $20,000.00 Remaining Funds Available for this CO $20,000.00 $20,000.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 1.91 MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $731,969.63 JUSTIFICATION (REASONS) FOR CHANGE ORDER ADDITIONS:Add Unit 1 -Line Item 19, purchase of 232 LF of 18"RCP;Add Unit 1 -Line Item 20, Installation of 220 LF of 18"RCP for out flow and cover/stabilize;Add Unit 1 -Line Item 21,installation of 12 LF of 18"RCP at in flow and cover/stabilize. ` °0e6- o 000"a� 1 M . K eri ecretary .01 XAAS n FFMLL. E3G CORP F f. 9 UK PORT WORTii City of Fort Worth v--- Change Order Additions Project Name North Z.Boaz Park-Dog Park Improvements CitySec# 46853 Client Project# C210I541200I803490221883 Contractor Raydon,Inc. PMF Scott Penn Inspector AdildaCazorla Change Order Submittal# Date 9/412015 ADDITIONS ITEM DESCRIPTION DEPT Qty unit Unit Cost Total Purchase of 18'RCP PAGSD 232.00000000 $6,090.00 Installation of 8"RCP-pipe&fill existing channel(out flow of pond) PACSD 220.00000000 TF Installation of "RCP-pipe 8 fill existing channel(in flow of pond) PAGSD 0 LF PACSD $11,194.00 Sub Total A ibons Change Order Additions Page 2 of 5 FOR I'WORTH City of Fort Worth —"v--- Change Order Deletions Project Name North Z.Boaz Park-Dog Park Improvements CitySec# 46853 Client Project# C210I 541200/803490221883 Contractorl Raydon,Inc. PM[— Scott Penn Inspector' Adilda Cazoda Change Order Submittal# 0 Date 9/4/2015 DELETIONS ITEM DFSMMION DEPT Qty Unit Unit Cost Total PACSD $0.00 Sub ota Deletions Change Order Deletions Page 4 of 5 M/SBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO NA Total $0.00 Previous Change Orders CO# DATE AMOUNT NA Total $0.00 CFW Change Order Approval Pa- COApp01 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links 2 fortworthgov/PACS/02218 - North Z Boaz Community Park - Phase II/Contractor/Change Orders/RE M&C Review Reauest {Purple Slip} 80NZ BOAZ CO#2 .msg fortworthgov/PACS/02218 - North Z Boaz Community Park - Phase II/Contractor/Change Orders/Change Order Breakdown 9-4-15 (3).xls Attachments(0) No Attachments have been added to this form. �o https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&Processld... 2/2/2016 CFW Change Order Approval Pa- COApp01 Page 2 of 3 FORT WORTH. City of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: 1 Change Order No.: Pa - COApp01 Date Started: '2015-09-03 City Sec. No.: Date Due: 2015-10-23 Project Name: North Z Boaz Community Park - Phase I 02218 DOE Numbers: Project Numbers: Project ,Dog Park Improvements at North Z. Boaz Park Description: Project Manager: 'Scott Penn City Inspector: Adilda Cazorla Contractor: Raydon, Inc. COUNCIL ACTION (If Required): M&C Log Name: 'na M&C Number: M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: Parks and Recreation ;$ 11,194.00 C210-541200-803490221883 10 Total Cost: $_11,194.00 Total Requested Days: '10 Approval Status: https://projeetpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&ProcessId... 2/2/2016 CFW Change Order Approval Pa- COApp01 Page 3 of 3 Approved: Yes Comments: Approved User: Debra Rose Date: 2015-09-26 9:08 AM ;Approved: Yes Comments: User: Brian Smith Date: 2015-09-27 12:59 PM Approved: Yes Comments: User: Scott Penn Date: 2015-09-28 7:02 AM Approved: Yes Comments: User: Joel McElhany Date: 2015-09-28 8:28 AM Approved: Yes Comments: User: Richard Zavala Date: 2015-09-29 8:39 AM Approved: Yes Comments: User: Doug Black Date: 2015-10-09 10:28 AM "Approved: Yes Comments: Fred Griffin for User: Susan Alanis Date: 2015-10-13 2:14 PM Action Required: https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?SiteId=51500&ProcessId... 2/2/2016