NO. 4600-02-2016
STATEMENT EXPRESSING
OFFICIAL INTENT TO REIMBURSE
EXPENDITURES WITH PROCEEDS OF FUTURE DEBT FOR THE WATER
AND SANITARY SEWER MAIN RELOCATIONS FOR THE TRINITY RIVER
VISION - CENTRAL CITY PROJECT
WHEREAS, the City of Fort Worth, Texas (the "City") is a home-
rule municipality and political subdivision of the State of Texas; and
WHEREAS, the City expects to pay expenditures in connection with the
design, planning, acquisition and construction for the Water and Sanitary Sewer
Main Relocations for the Trinity River Vision - Central City Project and the Trinity
Uptown Service Area - Phase 4, Project as shown on the attached map (the
"Project") prior to the issuance of obligations by the City in connection with the
financing of the Project from available funds; and
WHEREAS, the City finds, considers, and declares that the
reimbursement of the City for the payment of such expenditures will
be appropriate and consistent with the lawful objectives of the City
and, as such, chooses to declare its intention, in accordance with the
provisions of Section 1.150-2 of the Treasury Regulations, to reimburse
itself for such payments at such time as it issues obligations to finance
the Project;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, TEXAS:
Section 1. The City reasonably expects debt, as one or more series of
obligations, may be issued or incurred by the City with an aggregate maximum
principal amount not to exceed $1,750,000.00 for the purpose of paying the
aggregate costs of the Project.
Section 2. All costs to be reimbursed pursuant hereto will be capital
expenditures. No obligations will be issued by the City in furtherance of this
Statement after a date which is later than 18 months after the later of (1) the
date the expenditures are paid or (2) the date on which the property, with
respect to which such expenditures were made, is placed in service.
Q WORT
Section 3. The foregoing notwithstanding, no obligation will be issued
pursuant to this Statement more than three years after the date any
expenditure which is to be reimbursed is paid.
Adopted this 16th day of Fcbruary, 2016.
ATTEST: °°°°00000°o°°o
�o °t ��
O 0,
QV°o °ZO
BY: 0� °o 00* Jy
°0000°o°° ,cr
Mary J. ser, Ci Secretary �4zt'q X.
ORT WORT
3Atl N39't
LLJ
uj
LU
LLJ
LU
x 1
• E<4' ; �, ,� '-�� � -yam ti�. __� � .
oe r t
1 4 3 7
J CO CO
!
,
,:,.✓.,..tin ?� �+ � - Y6, ,'�' p®il 1 9�.�
. �NUj301S213A121
3AtltlINtlAIAS �. •``e {-'� '—i.'�'t i��.� t krt ;��+
r
V1,
\ � �•1r,, '
IS
GG"Ill
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 211612016 - Ordinance No. 22096-02-2016, 22097-02-2016'
& Resolution No. 4600-02-2016
DATE: Tuesday, February 16, 2016 REFERENCE NO.: C-27628
LOG NAME: 60WSTRAVA4-KHA
SUBJECT:
Authorize Execution of Amendment No. 4 to City Secretary Contract No. 37013 with Kimley-Horn and
Associates, Inc., in the Amount of$1,596,900.00 for Water and Sanitary Sewer Main Relocations for the
Trinity River Vision - Central City Project and the Trinity Uptown Service Area Phase 4, Provide for Project
Costs for a Project Total in the Amount of$9,342,813.00 and Adopt Appropriaton Ordinances and
Reimbursement Resolution (TRV- RELATED EXPENSES ELIGIBLE FOR REIMBURSEMENT FROM
THE TRWD) (COUNCIL DISTRICTS 2 and 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Appropriation Ordinances increasing estimated receipts and appropriations in the
Water Capital Projects Fund in the amount of$283,796.00 and the Sewer Capital Projects Fund in the
amount of$147,535.00;
2. Authorize the execution of Amendment No. 4 to City Secretary Contract No. 37013 with Kimley-Horn
and Associates, Inc. in the amount of$1,596,900.00 for Trinity River Vision - Central City Project and the
Trinity Uptown Service Area Phase 4; and
3. Adopt the attached Resolution expressing official intent to reimburse expenditures with proceeds of
future debt for the Trinity River Vision - Central City Project and the Trinity Uptown Service Area Phase 4.
DISCUSSION:
On April 15, 2008, (Mayor and Council Communication (M&C) C-22765) the City Council authorized an
Engineering Agreement in the amount of$2,533,113.00 for water and sanitary sewer main relocations for
the Trinity River Vision - Central City Project and the Trinity Uptown Service Area Phase 4.
The Engineering Agreement was subsequently revised by Amendment No. 1 (M&C C-25303, November
15, 2011) in the amount of$1,580,000.00 to provide for Phase 2A, Amendment No. 2 (M&C C-26276,
May 21, 2013) in the amount of$1,896,000.00 to provide for Phase 2B and Amendment No. 3 (M&C C-
26838, June 10, 2014) in the amount of$1,736,800.00 to provide for Phase 3.
This Amendment No. 4 allows Kimley-Horn and Associates, Inc., to commence with the necessary design
work for Phase 4.
The proposed scope of services for Trinity River Vision - Central City Project and the Trinity Uptown
Service Area Phase 4 includes the following:
Logname: 60WSTRAVA4-KHA Page 1 of 4
• Design for the relocation of conflicting water and/or sanitary sewer mains for Gateway/Oxbow Valley
Storage Site E Channel Segments A, B, C and D;
• Construction phase services;
• Permit acquisition;
• Coordination meetings with TRV Management Team, TRV partners and Staff;
• Subsurface utility engineering;
• Geotechnical investigations;
• Design Program Management;
• Holly Water Systems Analysis;
• Ham Branch Sanitary Sewer Study; and
• Panther Island Sanitary Sewer Master Plan
Kimley-Horn and Associates, Inc., proposes to provide the necessary additional services for a lump sum
fee of$1,596,900.00. Staff considers the fee to be fair and reasonable for the scope of services
proposed.
In addition to the contract amount, $431,331.00 (water: $283,796.00 and sewer: $147,535.00) is required
for program management, real property acquisitions, material testing and inspection. This project will
have no impact on the Water Department's operating budget.
Upon approval of this amendment, the total of these water, sanitary sewer and major storm drain
appropriations for the Trinity River Vision - Central City Project and the Trinity Uptown Service Area Phase
4 Project will be $39,885,975.00. This project is anticipated to be included in a future revenue bond issue
for the Water and Sewer Fund. Available cash within the Water and Sewer portfolio and the City's
portfolio along with the appropriation authority authorized under the Direct Purchase Note (DPN) program
will be used to provide interim financing for this project until debt is issued. To the extent resources other
than the Water and Sewer portfolio are used to provide interim financing, the Water and Sewer Fund will
be charged interest that is equivalent to the overall rate of return being earned by the City portfolio
(currently approximately one-percent annually). Should the City's portfolio not support the liquidity needed
to provide an interim short-term financing source, another funding source will be required, which could
mean issuance of securities under the DPN program or earlier issuance of Water and Sewer revenue
bonds than is currently planned. Once debt associated with this project is sold, bond proceeds will be
used to reimburse the Water and Sewer portfolio and the City' s portfolio in accordance with the attached
Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2016 - 2020 Five-Year Capital Improvement
Plan on February 2, 2016 (M&C G-18662). This City Council-adopted plan includes this specific project,
with funding identified through the DPN program to be reimbursed with future revenue bonds. In
accordance with the provisions of the Financial Management Policy Statements, Staff anticipates
presenting revenue-supported debt issuances to the City Council for consideration within the next three
years. This debt must be issued within approximately three years to provide reimbursement for these
expenses. If that does not occur, the costs will no longer be reimbursable by issuing tax-exempt debt and
the funding source will have to be made whole through other budgetary methods. Adoption of this
resolution does not obligate the City to sell bonds, but preserves the ability to reimburse the City from tax-
exempt bond proceeds.
Logname: 60WSTRAVA4-KHA Page 2 of 4
Appropriations for the Trinity River Vision - Central City and the Trinity Uptown Service Area Phase 4
Project will Conoiat of the following:
Future
rDescription Appropriations Appropriations 1 F Appropriation
Project Management, Real
Property Acquisitions,
Inspection,Testing and
Contingencies $3,674,740.00 $431,331.00 $ 344,175.00 $ 4,450,246.00
JProject Total $39,454,644.00 $431,331.00 $5,585,709.00 $45,471,684.00
° Numbers rounded for presentation purposes.
Appropriations for the Trinity River Vision - Central City and the Trinity Uptown Service Area Phase 4
Project will consist of the following by fund:
[S—Pecially Funded Projects Fund 39007 $10,715,680.00
Water and—Sewer Bond 201M—M6-007 ---[—$6,167,422.00
ater Capital Fund 59601 $14,404,709.00
ISewer Capital Fund-Legacy—59607 $7,328,473.00
F Project Total $45,471,684.00
° Numbers rounded for presentation purposes.
Of the $1,596,900.00 cost of this amendment, the amount of$1,368,784.00 is necessitated by the Trinity
River Vision /TRV\ Project while tha remaining amount of$228.110.00 is non-TRVre|ated. Having met its
$2O.0 million commitment to the TRV Project, theQtyxviUberuimburaadtheomountof$1.388.784.0Uby
the Tarrant Regional Water District (TRVVO) upon contract completion, in accordance with the provisions
of the executed Interlocal Agreement between the City and the TRWD (City Secretary Contract No.
43425). Staff will record a receivable every month for reimbursable expenses and the TRV Program
Manager in the Planning and Development Department will be responsible for collecting the full
reimbursement from TRVV[) upon project oomp|eUun. Available resources in the 2O17 Water and Sewer
Revenue Bonds Capital Project Fundvxi|} beuaedtoprovideinterimfinancingunti/ roimbunaemontocouna.
Once reimbursement is received, the revenue will be receipted to the 2017 Water and Sewer Revenue
Capital Project Fund.
K8/VVBE OFFICE: Kinn|ey - Horn and Associates, Inc., in in compliance with the City's M/VVBE {}ndinenua
by committing to 25 percent M/WBE participation on this Amendment No. 4. The City's goal onthis
amendment ie35percent.
This project io /ocatadinCOUNC|LO|GTR|CT82and9. K8opoco82UandO2V.
CERTIFICATION:FISCAL INFORMATION /
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinances, funds will be available in the Water Capital Projects Fundandthe
Sewer{}opito| Projects Fund. After the appropriations for this project are comp|atad, the balance in the
Water Capital Projects Fundvvi|| ba $11.510.5O8.00andthaba|encainthe8evverCapito/ Projects Fund
will be $14.S21.522.OD. In addition, funds are available as directed by M&C G-18375 in the 2017 Water
[ogouuze: 60WSTR4VA4-KHA Page 3of4
and Sewer Revenue Bonds Capital Project Fund for funding the Trinity River Vision-Central City Project
and the Trinity Uptown Service Area Phase 4 Project to pay expenses which will be incurred on this
contract until reimbursement is received from the TRWD, as depicted in the following table:
It-Xi-s-tin-g- dditional
Fund Appropriations rA4ppropriations Future Appropriations Project Total*
F ecially Funded Projects nd 39007 __ $ 5,129,971.00 I 0.00 $5,585,709.00 ,$10,715,680.00
6005 Sewer DPN Fund F$ 6,855,400.00 �$ 0.00 ($ O.00i ,855,400.00
Water&Sewer Bond
2015A 56007 $ 663 167 422.00 $ 0.00 1$ 0.00 $ 6,167,422.00
(Water Capital Fund 59601 $14,120,912.00 �, 283,796.00 �$ 0.00 a $14,404,708.00
Sewer Legacy 5 Capital Fund- Fs7,180,938.00 j$147,535.00 $ 0.00 f$ 7,328,473.00
Project Total v 39,454,643.00 $431,331.00 1$5,585,709.00 $45,471,683.00
* Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department Accouni Project Program Activity Budget Reference # Amount
ID ID Year (Chartfield 2)
59601 0600430 4905420 C00969 2016 $283,796.00
59607 0700430 4905420 C00969 2016 $147,535.00
59601 0600430 5110101 C00969 C01780 2016 $283,769.00.00
59607 0700430 5110101 C00969 C01780 2016 $147,535
FROM
Fund Department Accouni Project Program Activity Budget Reference # Amount
ID ID Year Chartfield 2
59601 0600430 5110101 C00969 C01780 2016 $283,769.00
59607 0700430 5110101 C00969 C01780 2016 $147,535.00
56005 0600430 5330500 C00969 C01733 2016 $291,368.00
56005 0700430 5330500 C00969 C01733 2016 $1,3051532.00
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (6122)
Originating Department Head: John Carman (8246)
Additional Information Contact: Liam Conlon (6824)
Logname: 60WSTRAVA4-KHA Page 4 of 4