HomeMy WebLinkAboutContract 47561 CITY SECRETARY
REC Iva) CONTRACT NO.
MAR -21016
0 PORTWORTH Developer and Project Information Cover Sheet:
SECRETARY
`
14- -*per Company Name: Hunter Crossroads,LP
Address, State,Zip Code: 3890 West Northwest Hwy Suite 100
Phone&Email: 214-379-4200, sr@42realestate.com Pa
Authorized Signatory,Title: Scott Rohrman,Manager
Project Name and Brief Vista Crossroads ""VV
Description:
Project Location:
Plat Case Number: FP-15-060 Plat Name: Vista Crossroads Addition
Mapsco: 4V Council District: 7 City Project Number: 02668
CFA Number: 2015-120 DOE Number: 7526
To be comple d b staff
J40
Received by Date:
OFFICIAL RECORD
City of Fort worth,Texas CITY SECRETARY
Standard Community Facilities Agreement
CFA Official Release Date:07.30.2015 FT. WORTH, TX
Page 1 of 11
STANDARD COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary
COUNTY OF TARRANT § Contract No.
WHEREAS, Hunter Crossroads LP, ("`Developer"), desires to make certain specific
improvements as described below and on the exhibits attached hereto ("Improvements") related
to a project generally described as Vista Crossroads ("Project") within the City or the
extraterritorial jurisdiction of Fort Worth, Texas ("City"); and
WHEREAS, the City has no obligation to participate in the cost of the Improvements or
Project; and
WHEREAS, any future City participation in this CFA is subject to the availability of
City funds and approval by the Fort Worth City Council and shall be memorialized as an
amendment to this Agreement; and
WHEREAS, the Developer and the City desire to enter into this Community Facilities
Agreement ("CFA" or "Agreement") in connection with the collective Improvements for the
Project.
NOW, THEREFORE, for and in consideration of the covenants and conditions
contained herein,the City and the Developer do hereby agree as follows:
General Requirements
A. The Policy for the Installation of Community Facilities ("Policy") dated March 2001,
approved by the City Council of the City of Fort Worth, as amended, is hereby
incorporated into this Agreement as if copied herein verbatim. Developer agrees to comply
with all provisions of said Policy in the performance of its duties and obligations hereunder
and to cause all contractors hired by Developer to comply with the Policy in connection
with the work performed by said contractors.
B. Developer shall provide financial security in conformance with paragraph 6, Section II, of
the Policy and recognizes that there shall be no reduction in the collateral until the Project
has been completed and the City has officially accepted the Improvements. Developer
further acknowledges that said acceptance process requires the Developer's contractor(s)
City of Fort Worth,Texas
Standard Community Facilities Agreement
CFA Official Release Date: 07.30.2015
Page 2 of 11
to submit a signed affidavit of bills paid and consent of Surety signed by its surety to
ensure the contractor has paid any sub-contractor(s) and suppliers in full. Additionally,
the contractor will provide in writing that the contractor has been paid in full by
Developer for all the services provided under this contract.
C. Developer agrees to cause the construction of the Improvements contemplated by this
Agreement and that said construction shall be completed in a good and workmanlike
manner and in accordance with all City standards and the City-approved construction
plans, specifications and cost estimates provided for the Project and the exhibits attached
hereto.
D. The following checked exhibits describe the Improvements and are incorporated herein:
Water (A) 1E, Sewer (A-1) 0, Paving (B) ❑, Storm Drain (B-1) ❑, Street Lights & Signs
(C) ❑.
E. The Developer shall award all contracts for the construction of the Improvements in
accordance with Section 11, paragraph 7 of the Policy and the contracts shall be
administered in conformance with paragraph 8, Section 11, of the Policy. Developer shall
ensure its contractor(s)pays the then-current City-established wage rates.
F. For all Improvements included in this Agreement for which the Developer awards
construction contract(s), Developer agrees to the following:
i. To employ a construction contractor who is approved by the director of the
department having jurisdiction over the infrastructure to be constructed, said
contractor to meet City's requirements for being prequalified, insured, licensed
and bonded to do work in public ways and/or prequalified to perform
water/wastewater construction as the case may be.
ii. To require its contractor to furnish to the City a payment and performance bond in
the names of the City and the Developer for one hundred percent (100%) of the
contract price of the infrastructure, and a maintenance bond in the name of the
City for one hundred percent(100%) of the contract price of the infrastructure for
a period of two (2) years from the date of final acceptance insuring the
maintenance and repair of the constructed infrastructure during the term of the
City of Fort Worth,Texas
Standard Community Facilities Agreement
CFA Official Release Date: 07.30.2015
Page 3 of 11
maintenance bond. All bonds to be furnished before work is commenced and to
meet the requirements of Chapter 2253, Texas Government Code.
iii. To require the contractor(s) it hires to perform the construction work
contemplated herein to provide insurance equal to or in excess of the amounts
required by the City's standard specifications and contract documents for
developer-awarded infrastructure construction contracts. The City shall be
named as additional insured on all insurance required by said documents and
same will be evidenced on the Certificate of Insurance (ACORD or other state-
approved form) supplied by the contractor's insurance provider and bound in the
construction contract book.
iv. To require its contractor to give 48 hours advance notice of intent to commence
construction to the City's Construction Services Division so that City inspection
personnel will be available; to require the contractor to allow the construction to
be subject to inspection at any and all times by City inspection forces, to not
install or relocate any sanitary sewer, storm drain, or water pipe unless a
responsible City inspector is present and gives his consent to proceed, and to
make such laboratory tests of materials being used as may be required by the City.
v. To require its contractor to have fully executed contract documents submitted to
the City in order to schedule a Pre-Construction Meeting. The submittal should
occur no less than 10 working days prior to the desired date of the meeting. No
construction will commence without a City-issued Notice to Proceed to the
Developer's contractor.
vi. To delay connections of buildings to service lines of sewer and water mains
constructed under this Agreement, if any, until said sewer and water mains and
service lines have been completed to the satisfaction of the Water Department.
G. Developer shall provide at its expense, unless otherwise agreed to by City, all engineering
drawings and documents necessary to construct the improvements under this Agreement.
H. Developer shall cause the installation or adjustment of the required utilities to serve the
development or to construct the Improvements required herein.
City of Fort Worth,Texas
Standard Community Facilities Agreement
CFA Official Release Date: 07.30.2015
Page 4 of 11
I. City shall not be responsible for payment of any costs that may be incurred by Developer in
the relocation of any utilities that are or may be in conflict with any of the community
facilities to be installed hereunder.
J. Developer hereby releases and agrees to indemnify, defend and hold the City harmless
for any inadequacies in the preliminary plans, specifications and cost estimates
supplied by the Developer for this Agreement.
K. Developer agrees to provide, at its expense, all necessary rights of way and easements
across property owned by Developer and required for the construction of the current and
future improvements provided for by this Agreement.
L. The Developer further covenants and agrees to, and by these presents does hereby,
fully indemnify, hold harmless and defend the City, its officers, agents and employees
from all suits, actions or claims of any character, whether real or asserted, brought
for or on account of any injuries or damages sustained by any persons (including
death) or to any property, resulting from or in connection with the construction,
design, performance or completion of any work to be performed by said Developer,
its contractors, subcontractors, officers, agents or employees, or in consequence of
any failure to properly safeguard the work, or on account of any act, intentional or
otherwise, neglect or misconduct of said Developer, its contractors, sub-contractors,
officers, agents or employees, whether or not such injuries, death or damages are
caused, in whole or in part, by the alleged negligence of the City of Fort Worth, its
officers,servants, or employees.
M. Developer will further require its contractors to indemnify, defend and hold harmless
the City,its officers, agents and employees from and against any and all claims, suits or
causes of action of any nature whatsoever, whether real or asserted, brought for or on
account of any injuries or damages to persons or property, including death, resulting
from, or in any way connected with, the construction of the infrastructure
contemplated herein, whether or not such injuries, death or damages are caused, in
whole or in part, by the alleged negligence of the City of Fort Worth, its officers,
servants, or employees. Further, Developer will require its contractors to indemnify,
and hold harmless the City for any losses, damages, costs or expenses suffered by the
City or caused as a result of said contractor's failure to complete the work and
City of Fort Worth,Texas
Standard Community Facilities Agreement
CFA Official Release Date:07.30.2015
Page 5 of 11
construct the improvements in a good and workmanlike manner, free from defects, in
conformance with the Policy, and in accordance with all plans and specifications.
N. Upon completion of all work associated with the construction of the Improvements,
Developer will assign to the City a non-exclusive right to enforce the contracts entered into
by the Developer with its contractor along with an assignment of all warranties given by the
contractor, whether express or implied. Further, Developer agrees that all contracts with
any contractor shall include provisions granting to the City the right to enforce such
contracts as an express intended third party beneficiary of such contracts.
O. Inspection and material testing fees are required as follows:
i. Developer shall pay in cash water and wastewater inspection fees and material
testing fees equal to two percent (2%) for a total of 4% of the developer's share of
the total construction cost as stated in the construction contract.
ii. Developer shall pay in cash paving and storm drain inspection fees equal to four
percent (4%) and material testing fees equal to two percent (2%) for a total of 6%
of the developer's share of the total construction cost as stated in the construction
contract.
iii. Developer shall pay in cash the total cost of streetlights or if the city is not
installing the streetlights, inspection fees equal to four percent (4%) of the
developer's share of the streetlight construction cost as stated in the construction
contract.
iv. Developer shall pay in cash the total cost of street signs.
P. COMPLETION WITHIN 2 YEARS
i. Developer shall complete the Improvements within two (2) years, provided,
however, if construction of the Improvements has started within the two year
period, the developer may request that the CFA be extended for one additional
year.
ii. Nothing contained herein is intended to limit the Developer's obligations
under the Policy, this Agreement, its financial guarantee, its agreement with
its contractor or other related agreements.
iii. The City may utilize the Developer's financial guarantee submitted for this
Agreement to cause the completion of the construction of the Improvements if at
City of Fort Worth,Texas
Standard Community Facilities Agreement
CFA Official Release Date: 07.30.2015
Page 6 of 11
the end of two (2) years from the date of this Agreement (and any extension
period) the Improvements have not been completed and accepted.
iv. The City may utilize the Developer's financial guarantee to cause the completion
of the construction of the Improvements or to cause the payment of costs for
construction of same before the expiration of two (2) years if the Developer
breaches this Agreement, becomes insolvent or fails to pay costs of construction
and the financial guarantee is not a Completion Agreement. If the financial
guarantee is a Completion Agreement and the Developer's contractors and/or
suppliers are not paid for the costs of supplies and/or construction, the contractors
and/or suppliers may put a lien upon the property which is the subject of the
Completion Agreement.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
City of Fort Worth, Texas
Standard Community Facilities Agreement
CFA Official Release Date: 07.30.2015
Page 7 of 11
Cost Summary Sheet
Project Name: Vista Crossroads
CFA No.: 2015-120 DOE No.: 7526
An Engineer's Estimate of Probable Cost is acceptable. However,the construction contract price
will ultimately determine the amount of CFA fees and financial guarantee. The bid price and
any additional CFA payments will be required prior to scheduling a pre-construction meeting.
An itemized estimate corresponding to each project-specific exhibit is required to support the
following information.
Items Developers Cost
A. Water and Sewer Construction
1. Water Construction $ 112,709.75
2.Sewer Construction $ 35,904.50
Water and Sewer Construction Total $ 148,614.25
B. TPW Construction
1.Street $ -
2.Storm Drain $ -
3.Street Lights Installed by Developer $ -
4. Signals $
TPW Construction Cost Total $ -
Total Construction Cost(excluding the fees): $ 148,614.25
Construction Fees:
C. Water/Sewer Inspection Fee(2%) $ 2,972.29
D. Water/Sewer Material Testing Fee(2%) $ 2,972.29
Sub-Total for Water Construction Fees $ 5,944.57
E. TPW Inspection Fee(4%) $ -
F. TPW Material Testing(2%) $ -
G. Street Light Inspsection Cost $ -
H. Signals Inspection Cost $ -
H. Street Signs Installation Cost $ -
Sub-Total for TPW Construction Fees $ -
Total Construction Fees: $ 5,944.57
Choice
Financial Guarantee Options,choose one Amount Mark one
Bond=100% $ 148,614.25
Completion Agreement=100%/Holds Plat $ 148,614.25
Cash Escrow Water/Sanitary Sewer=125% $ 185,767.81
Cash Escrow Paving/Storm Drain=125% $ -
Letter of Credit=125%w/2yr expiration period $ 185,767.81
City of Fort Worth,Texas
Standard Community Facilities Agreement
CFA Official Release Date:07.30.2015
Page 8 of 11
ACCORDINGLY,the City of Fort Worth and Developer have each caused this instrument to be
executed in quadruplicate in each entity's respective name by its duly authorized signatories effective as
of the date executed by the City's City Manager or his/her designee.
CITY OF FORT WORTH DEVELOPER
Hunter Crossroads,LP
Jesus J. Chapa
Assistant City Manager Name: Scott Rohrman 6/'
Title: Manager �}-
Date:
Date: o
Recommended by:
ATTEST: (Only if required by Developer)
r
Wendy Chi- bulal, EMBA,P.E.
Development Engineering Manager Signature
Water Department Name:
� F0
ATTEST: j f-4
�F1�A00S
Diglas UT Blark 1LXJ CaQ. A. A4C4rr. jLC t Mary J. K y r
Assistant City Attorney City Secret
M&C No. NtA
Date: s t" ! /4
F W^44 l ztr fQ`/—
OFFICIAL RECORD
CITY SECRETARY
City of Fort Worth,Texas FT. WORTH TX
Standard Community Facilities Agreement
CFA Official Release Date:07.30.2015
Page 9 of 11
Check items associated with the project being undertaken; checked items must be
included as Attachments to this Agreement
Included Attachment
U Attachment 1 -Changes to Standard Community Facilities Agreement
Location Map
Exhibit A: Water Improvments
Q Water Cost Estimate
D Exhibit A-1: Sewer Improvements
R Sewer Cost Estimate
❑ Exhibit B: Paving Improvements
❑ Paving Cost Estimate
❑ Exhibit B-1: Storm Drain Improvements
❑ Storm Drain Cost Estimate
01 Exhibit C: Street Lights and Signs Improvements
❑ Street Lights and Signs Cost Estimate
(Remainder of Page Intentionally Left Blank)
City of Fort Worth,Texas
Standard Community Facilities Agreement
CFA Official Release Date:07.30.2015
Page 10 of 11
ATTACHMENT"1"
Changes to Standard Agreement
Community Facilities Agreement
City Project No. 02668
None
City of Fort Worth,Texas
Standard Community Facilities Agreement
CFA Official Release Date: 07.30.2015
Page 11 of 11
AVONDALE — HASLET
FORT
718 WORTH
PROJECT
B287 LIMITS
P
287
fip
SCALE CITY OF FORT WORTH, TEXAS
teague nail & perkins HTR 15127
N A 1100 Macon Street OFFSITE WATER AND SEWER IMPROVEMENTS TO SERVE
Fad Worth,Texas 76107 VISTA CROSSROADS
np
DATE 817.336.3773 ph 817.336.2813 fx
DEC 2015 TBPERe81s1ralionNo.F•230 LOCATION MAP
www.eap:a�.,am
WAL-MART STORES TE(ASy LLC /
/VST. #D207385M
DRT.CT.
1 LOT 1 \ \
hGNTER CROSSROADS LP
FUTURE COM WWWL LOT \ /ILST. #D207294400 LEGEND
DRT,CT. EXISTING SSMH
CO�CT TO U S LAE �� — — EX SEWER LINE
BLOCK 1 ----4 PROP SEWER LINE
PROP SSMH
? \ 8a SS LM-'
MIE r SS LAT A-e- 4'SSW
\ — - - - - - - - - - - — a ZDTdU- - - -��
854
LA A
SS LST A�11 PRbP IF Y SEWER 8'SS A-3' '
ESVT BY�ffr 7F
MTRUWSVT
( I 'FilTiIRE CMfRM FiJTt�'
LOT ii ` LOT 12 \\
I III BLow i
co
I
I TAC10 BEZL
(BY OThMS)
° I LOT v US ML1�IWAY 287 SO?WW ROAD
I 100 0 50 100
aom L
I
GRAPHIC SCALE
I
SME CITY OF FORT WORTH. TEXAS W PROXCT
= League nail & perkins HTR 15127
1"=1 , 1100 Macon Street OFFSITE WATER AND SEWER IMPROVEMENTS TO SERVE
"" For,Worth,Texas 76102 VISTA CROSSROADS
DATE 817.336.3773 ph 817.336.2813fx
DEC 2015 t n pTBPE Rpls:Non No.F-230 EXHIBIT A-1
w W.Mpfn cam
/ I
WAL-MART STORES TFXA$ C ! I
NST. #D207365136,1
DR T.0 T.
LOT f
/i BLOW
fUV7E7q CROSMAM LP LEGEND
IN, WT. =072W" — — EX WATER LINE
Fl/TGRE CON�ERQ�AL LOT
CANIECT TO U V' WL DRT.CT. PROP WATER LINE
f�C ///1 }r SEA AX LW(DAIfI) (TRACT U PROP f5• WATER N PROP GATE VALVE I
" �� 1-1nk8'r4A�G1>IOY4 TEF(fly) LOT a
B'PVC WL �1 SLOQK 1 ESMT BY SEPARATE/f1ES1ALaCrE1NT � PROP FIRE HYDRANT
I
/ v PVC WL !-110'x8'AACYOR TEF#fW I
r I r PVC WL (F1 )
d 854
,t
I lY I r v�LiE 2`s�vx, \
fry MW 8' WL-1001A
s (f TOT
AU i� \ xr Pvc WL
8a PV O�EJ
I I I FUT�E CON�l4t]4GfG4L PLgw \ STD FH ASSEA�LY
j I LOT 1JLQT \ W14UTOau 77C allSIO?
II ,
WY POWER PACK) !
r PVC WL
c '
f � fII
I
4-g
m.col .. i
I TACO BELL 100 0 50 100
(BY 07WS)
e I LOT 1.10 USS l>MFRNAY 287 SER AX R AD
I
&OCK f I GRAPHIC SCALE
I j
SCA E CITY OF FORT WORTH, TEXAS ""°
League Hall � parkins HTR ,151,z�
1=1z , 1100 Macon So OFFSITE WATER AND SEWER IMPROVEMENTS TO SERVE
Fort Worth,Texas 76102 VISTA CROSSROADS
np
DATE 617.336.5773 ph 1117.336.2813f:
TRPE Rapisfwllon No.F-230 EXHIBIT A-2
DEC 2015 www.tnpinacom
(Ni 41 nii- 1
13117 FORM
i'.+ge! of;
SECTION 00 41 00
BID FORA
This proposal must net be removed from this book of Contract Documents.
TO: I-hinter Crossroads. LP
3890 West Northwest Hwy. Suite 100
Dallas, Texas 75220
PROPOSAL FOR: Water and Sanitary Sewer Improvements to serve
Vista Crossroads
City Project No. 02668.
Water Project No. P265-607150266883.
Sewer Project No. P275-707130266881
DOE No. 7526,
X No. X-23289
Includes the furnishing of all materials, except materials specified to he furnished by the City,
equipment and labor for the installation of all facilities and all necessary appurtenances and
incidental work to provide a complete and serviceable project designated as:
WATER AND SANITARY SEWER IMPROVEMENTS TO SERVE
VISTA CROSSROADS
Construction staking for this project shall be performed by the Contractor.
The Bidder acknowledges that all work types must be performed only by prequalified contractors
and subcontractors.
Pursuant to the foregoing 'Invitation to Bidders'. the undersigned Bidder, having thoroughly
examined the Contract Documents, including plans, the site of the project and understanding the
amount of work to be done, and the prevailing conditions, hereby proposes to do all the work.
furnish all labor, equipment and material except as specified to be furnished by the City, which is
necessary to fully complete the work as provided in the Plans and Contract Documents and
subject to the inspection and approval of the City of Fort Worth, Texas: and binds himself upon
acceptance of this Proposal to execute a contract and furnish an approved Performance Bond.,
Payment Bond. Maintenance Bond, and such other bonds, if any, as may be required by the
Contract Documents for the performing and completing of the said work. Contractor proposes to
do the work within the time stated and for the sum listed in the Proposal Form. Section 00 42 43.
. HF),_,. ;4;f.
y
tai 41tX'-2
kilt)FORM
Atter acceptance of this Proposal, the undersigned will execute the formal contract and will
deliver approved bonds as required bN the Contract Documents, for the faithful performance of
the Contract.
The Bidder agrees to begin construction within calendar days after issue of the work order,
and to complete the contract within _ 6d calendar days after beginning construction as set forth
in the written work order to be furnished by the Owner.
I (we) acknowledge receipt of the following addenda to the plans and specifications, all of the
provisions and requirements of which have been taken into consideration on preparation of the
foregoing bid:
Addendum No. I (Initials) Addendum No. 3 (Initials)
Addendum No. 2 (Initials) Addendum No. 4 (Initials)
004243
DAP-80 PROPOSAL
Psge 101`3
SECnON 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Prow Item information Bidder's Proposal
Bidlist Description Specification Unit of Bid Quantity Unit PrigBid Value
Item No. Section No. Measure
Unit 1:Water IMDEQMonts
I-1 3305.0109 Trench Safety 330510 LF 1160 $1 $1,160.00
1-2 3311.0001 Ductile Iron Water Fittings w/Restraint 3311 11 TON 2.0 $4,025.00 $8,050.0
1-3 3311.0061 2"PVC Water Pipe 3311 12 LF 131
$75.. $9,825.00
1-4 3311.0161 8"PVC Water Pipe 33 11 12 LF 113 $35.2 $3,983.2
1-5 3311.0261 t3"PVC Water Pipe 33 11 12 LF 46 $41,0 $1,886.0
1-6 3311.0381 10"PVC Water Pipe 3311 12 LF 1001 $45.50 $45,545•
1-7 3312.0001 Fire Hydrant 331240 EA 2 $3,885.0 $7,710.0
ng $1,150.00 _$1,150.00
!-8 3312.0117 Connection to Exisfi 4'-12"Water Main 33 12 2b EA 1
1-9 3312.3002 8"Gate VaNe 3312 20 EA 7 $1,520.0 _ $10,640.0
1-10 3312.3003 8"Gate Valve M12'20 EA 2 $2,030.00 $4,060.0
1-11 3312.3004 10"Gate Valve 331220 EA 2 $2,500.00 $5,000.00
9999.9999 Automatic Flusher(Edipse#97001 w/24 VDC
1-12 Power Pad() EA 1 $13,700.0 .$13,700.0
TgW_U0jLLfi&ff-1mgrovqm2gtsj $112,709.75
CITY OF FORT WORTH
STA'JDARD CONSTRUCTION SPECIFICATION DOCUNaNTTS-DEVELOPER AWARDED PROJECTS
Form Version ApritZ 2014 00 42 43 Proposal Foo As
004243
DAP-BID PROPOSAL
Pag 2 or 3
SECTION 00 42 43
Dcvcloper Awarded Projccts-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Hrformmum Bidder's Proposal
Bidliet Specification Unit of
Item No. Destr� °n Section No. Measure $ ° Unit Price Bid Value
SajijoEg r
II-1 3301.0002 Post-CCN Inspection 33 01 31 LF 371 $1.0 $371.00
II-2 3305.0109 Trench Safety 330610 LF 371 $1. $3.71.0
11-3 3301.0101 Msnhofe Vaccum Testing 33 01 30 EA 2 $250.0
3311 10,
11-4 3331,4108 6"Sewer Pipe 3331 12, LF 40
33 31 20 $40.00 $1,600.0
3311 10,
11-5 3331.4109 6"Sewer Pipe,CSS Backfill 33 31 12, LF 40
33 31 20 $64.50 $2,580.00
331110,
11-6 3331.4115 8"Sewer Pipe 3331 12, LF 266
33 31 20 $45.50 $12,103.00
33 11 10,
II-7 3331.4116 8"Sewer Pipe,CSS Backfill 33 31 12, LF 25
33 31 20 $114.50 $2,862.5
11-8 3339.0003 Wastewater Access Chamber 33 39 40 EA 4 $2,070.00 . $8,280.00
I1-9 3339.1001 4'Manhole 333910, EA 2
33 39 20 $2,724.50 $5,449.0
11-10 3339.1003 4'Extra Depth Manhole 333910. VF 5
33 39 20 $300.00 $1,500.00
11-11 9999.9999 Connect to Usting Sewer Line EA 1 $288.00 $288.0
T I: ovi—W Imigoijival35 904.
MY OF Foal WORTH
STM WARD CONSTRUCTION SPECEFICATION OOCUMFNTS-DEVELOPER AWARDED PROJECTS
Form Vmsios AprH2.2014 0042 43 PmpomW Form,ds
Oo12u
DAP-BLD PROPOSAL
Ppp)or)
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project item Information Bidders Proposal
Bidlist Description Specification Unit of Bid Quantity Unit Price Bid Value
Item No. Section No. Measure
m
Unit l:Water Improvements $912,709.7
Unit 11:Sanitary Beyer Improvements $35,904.50
Total Construction Bid l 1
Contractor agrees to complete WORK for FINAL ACCEPTANCE within 60 calendar days after the date when the CONTRACT commences to
run as provided in the General Conditions
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEaC 71CATTOV DOCUMENTS-DEVELOPER AWARDED PROJECTS
Fo m Varokn Apiil2.2014 00 47 43 Pfopoul Fa m.xlf
A)4(Oft-
1311)FOWN't
Parc 3 04 3
Respectfully submitted.
:
By (Si ature)
By (Si W;
11PPlease Print or "type)
'(40�et*
1
Title
ContractW
Oooci 5&44�_ko LJ
Business Address
SU,f3SL—ZVI 11 al 6)
Telephone Number FAX Number
Indicate whether— Individual
Partnership
Corporation
A-ITEST:
Secretary.