Change Order Request Breakdown
Project Namel Old Decatur Road and Angle Ave Roundabout City Sec# 1 2014
Client Project#(s)l 3023
Contractorl Jackson Construction,Ltd PM Lissette Acevedo Inspectorl Michael Collier
Change Order Submittal# Date IM2016
Dept. TPW WATER SEWER Contract Time
Totals CD
Original Contract Amount $1,620,708.86 $148,215.00 $205,457.00 $1,974,380.86 150
Extras to Date
Credits to Date
Pending Change Orders(in MBC Process)
Contract Cost to Date $1,620,708.86 $148 215.00 $205 457.00 $1,974,380.86 150
Amount of Proposed Change Order $73,060.90 $5,464.26 $11,136.33 $89,661.49 30
Revised Contract Amount $1,693,769.76 $153,679.26 $216,593.33 $2,064,042.35 180
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00 $0.00 $0.00
Additional Funding(if necessary) $73060.90 $51464.26 $11,136.33 $89,661.49
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 4.54%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,467,976.08
JUSTII ATiON(REMNS) FUR CHANGE OR13ER
This change order provides an adjustment in the prices for an increase cost in mobilization,utility and asphalt pavement due to the extended
project schedule whic began construction in June 2015,summer season versus winter season.The ROW acquisition tokk longer than orginially
estimated The city is granting 30 days to accomodate for the change of notice to proceed from summer season to winter season.This change
order resolves all request for increase in cost of unit prices due to delay start and time extentions due to typical bad weather days.The city also
added the construction staking to the contract to expedite construction.
A ®* F0
0 "
Y ty 3ecrotary $ ��
j0
AS
�. Ap
F�o T�wog�x City of Fort Worth
T Change Order Additions
City Sec#
Project NaOld Decaur Road and le Ave Roundabout
Nam 2014
Client Project# 3023
Conbecmr Jackson CansWctbn,Ltd PM Lissette Acevedo Inspector Mkdkael Cdller
Charge Order Submittal# O1 Date 1(/12016
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit ni os o
MINER—MATERIAL ESCALATION TPW ----7MMM LS 533,645.75 $33,645.7
MAI rKIAL ESCALATION ---Lg-- 7. 5
MATERIAL ESCALATION A ER 7 .
PHAL V Y& ITI N —T15W-- L 5
I LUMINAT TPW Twow L
N TRU STAKINGW 1. L 7. 7
CONSTRUCTION AKIN SEWER L
CONSTRUCTIONAKIN WA ER 1.00000wL
TPW $73,060.90
WATER $5,464.26
SEWER $11,136.33
---Sub Total Additions
Change Order Additions Page 1 of 1
,r
F r Wo City of Fort Worth
Change Order Deletions
Project Name Old Decatur Road and Angle Ave Roundabout City Sec# 2014
ClierdProjeet# 3023
Jadgon CorrsWctlon,Ltd PM LisseHe Acevedo lnspwtorF Mchael Collier
Charge Order Submittal# 0 Date 1(7f2016
DELETIONS
nit Unit Cost Total
TPW $0.00
WATER $0.00
SEWER $0.00
Sub lotal Deletions
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
COWTOWN REDI MIX SUPPLIER OF REDI MIX $4,483.07
Total $4,483.07
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
-CFW'Change Order Approval St-COApp01 Page 2 of 5
FORT WORTH,: City of Fort worth
Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: 1
Change Order No.: St-COApp01 Date Started: 2016-02-01
City Sec. No.: 47192 Date Due: 2016-03-22
Project Name: Old Decatur Rd and Angle Ave Roundabout TPW-2014-000089
Project Numbers: 02014 DOE Numbers:
6938
Project Construction of a roundabout at the intersection of Old
Description: Decatur at Angle Ave.
Project Manager: Lissette Acevedo City Inspector: Mike Collier
Contractor: Jackson Construction
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number: M&C Date:
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
TPW $ 89,661.49 34014 0200431 5740010 C03980 2 30
Total Cost: $ 89,661.49 Total Requested Days: 30
Approval Status:
https://projectpoint.buzzsaw.com/ bz web/Forms/FonuPrint.aspx?Site1d=51500&ProcessI... 3/22/2016
CFW Change Order Approval St-COApp01 Page 4 of 5
Approved: Yes
Comments:
User: Tara Fishback
Date: 2016-02-01 2:08 PM
Approved: Yes
Comments:
User: Troy Jackson
Date: 2016-02-01 2:34 PM
Approved: Yes
Comments:
User: Lissette Acevedo
Date: 2016-02-04 2:45 PM
Approved: Yes
Comments:
User: Tara Fishback
Date: 2016-02-23 11:01 AM
Approved: No
Comments:
User: Carmen Estep
Date: 2016-02-23 11:28 AM
Approved: Yes
Comments:
User: Lissette Acevedo
Date: 2016-02-23 12:38 PM
Approved: Yes
Comments:
User: Todd Estes
Date: 2016-02-25 8:54 AM
Approved: Yes
Comments: See Comment, fdg
User: Andy Anderson
Date: 2016-03-02 2:49 PM
Approved: Yes
Comments:
User: Doug Wiersig
Date: 2016-03-11 1:54 PM
Approved: Yes
CnmmentS-
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessI... 3/22/2016
,-CFW Change Order Approval St-COApp01 Page 5 of 5
User: Doug Black
Date: 2016-03-17 8:01 AM
Approved: Yes
Comments:
User: ]ay Chapa
Date: 2016-03-21 5:41 PM
Action Required: please approved