HomeMy WebLinkAboutOrdinance 22122-03-2016 ORDINANCE NO.22122-03-2016
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER CAPITAL PROJECTS FUND IN THE
AMOUNT OF $86,438.00, FROM AVAILABLE FUNDS, FOR THE PURPOSE OF
FUNDING HOT MIX ASPHALTIC CONCRETE (2014-3) STREET
REHABILITATION; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING
THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING
ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN
EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2015-2016 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
Capital Projects Fund in the amount of$86,438.00, from available funds, for the purpose of funding Hot
Mix Asphaltic Concrete(2014-3) Street Rehabilitation.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance No. 21873-09-2015 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas-7-Black, Mary J. se ,
Sr.Assistant City Attorney City Sec to
ADOPTED AND EFFECTIVE:March 22.2016
Ordinance No.22122-03-2016
Page 1 of 1
MAYOR AND COUNCIL COMMUNICATION MAP
(HMAC 2014-3 CO-2) STREET-REHABILITATION-MAP-PAGE-1
FV
YUCCA AVENUE ; t, ,��,'� 3:ELLIO T°REEpERs ROAD =1
U
• , ' �� � -n DALFORD STREET �,t°� ����� „Q,,r_ I� s'
y Q�
AM XI Z Q
2' 1ST STREET p
-• m Ra .� s� CHENAULT STREET"
Q;. ST FREEWp.
z
a p „ �"Y j DISTRICT: 8
DISTRICT: 8 JUNIUS ST
—GIPSONe W
MEDFORD RD o
STRATFORD PARK DR N Z
_ '� ,r_y- LSANC'gTSTER�i'g1%ENUE_� -t w
'WEST FREEINA�Y � - - y-= --= MEi4DOWBROOK D VE m �
w_ '' PURINGTON AVENU Q , _
Q a CAMILLA STREET PANOLA AVENUE
z HATrTIE STiREET�� � _ Q
p AVE B: __,, HAMPSHIRE BOULEVAR
w ` DISTRICT: 9 u� _ ► w_
w
w
cis COLLEGE AVE >_� �' = AVE G s Q"�' ROSEDALE STREET
a ; . H'� .�.•.
"Q W ALLEN AVENUE AVE I ` AVE J AVE L
Q Q > >' DAMS AVENUE � C�`~ w w
LU RAMEY'AVENUE
LL w
��j to ^
W Q POWECL AVENUE , . �° a w
,4 LL �- '. O w w W -
w" � �
J
ter . a QQ
w S Z
w a
� y Z Ulm BERRY STREET '�_ ' Q r� Q
� w �
LU
LU
W
x Z C��� r REED STREET Y
�W-.A,
BAYLOR STREET ?�� m
BEWICK STREET �RFFj, g ,f, 1NLARGER STREET v w J
RIPY STREET - '>' HOWARD STREET ,,' �:m }m
fight 2011 City of Fort Worth. Unauthorizized reproduction is a violation of applicable laws. E�/: 72 I
roduct is for information purposes and may not have been prepared for or be suitable for legal,engineering,or surveying purposes. D O E# / I
as not represent an on-the-around survev and represents onlv the approximate relative location of property boundaries. n r Tai n n n p r r+ r u. n n n
City of Fort worth, Texas
Mayor and Council Communication
COUNCIL ACTION: ;Approved on 3/22/2016 - Ordinance No. 22121-03-2016 & 22122-03-
2016
DATE: Tuesday, March 22, 2016 REFERENCE NO.: **C-27640
LOG NAME: 20HMAC (2014-3) STREET REHABILITATION CHANGE ORDER NO. 2
SUBJECT:
Authorize Execution of Change Order No. 2 to City Secretary Contract No. 45640 with JLB Contracting,
LLC., in the Amount of$345,750.36 to Rehabilitate Street Sections of College Avenue, Junius Street,
Medford Road and Stratford Park Drive, Thereby Increasing the Total Contract Amount to $1,814,596.45
for Hot Mix Asphaltic Concrete 2014-3 Street Rehabilitation and Adopt Appropriation Ordinances
(COUNCIL DISTRICTS 8 and 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinances increasing estimated receipts and appropriations in the
Water Capital Projects Fund in the amount of$86,438.00 and the Sewer Capital Projects Fund in the
amount of$86,438.00 from available funds; and
2. Authorize the execution of Change Order No. 2 to City Secretary Contract No. 45640 with JLB
Contracting, LLC, in the amount of$345,750.36 for Hot Mix Asphaltic Concrete (2014-3) Street
Rehabilitation, as listed on the chart and thereby, increasing the total contract amount to $1,814,596.45.
DISCUSSION:
On May 6, 2014, (M&C C-26795) the City Council authorized the execution of a contract with JLB
Contracting, LLC., in the amount of$1,458,547.34 for Hot Mix Asphaltic Concrete (2014-3), following
water and sewer line replacements. This Change Order is to provide for additional streets segments for
which the Water Department has determined the need to complete additional water and sewer
replacement work.
The recommended Change Order applies to the additional street rehabilitation work to be undertaken in
conjunction with a separate utility contract for the replacement of water and sewer sanitary lines. The
Transportation and Public Works (TPW) and Water Departments share in these resurfacing costs in lieu of
performing trench repair under the utility contract. The TPW portion of the cost on this change order will
be $172,875.06, which is available in the Contract Street Maintenance Fund Budget. The Water
Department will contribute funding in the amount of$172,875.30 for this change order.
The Hot Mix Asphaltic Concrete Street Rehabilitation (2015-4) project budget consists of the following:
Description �IProject Total
Engineering 0.00
Construction $1,814,596.00
Logname: 20HMAC (2014-3) STREET REHABILITATION CHANGE ORDER NO. 2 Page 1 of 3
Project Management, Real Property, Acquisitions, $ 586,426.00
inspection, Testing and Contingencies
Funding for the Hot Mix Asphaltic Concrete Street Rehabilitation i7O15-4\ project iaoafollows:
�Streel Rehabilitation Fund $1,190,142.00
tr
39 t 8
lWater Capital Fund 59601-1 $ 644,026.00
[S—ewer capital Fund 596-07 '1—$ 566,85-4
[Project Total $2,401,022.0-0
° Numbers rounded for presentation.
The streets segments to be added are listed below and TPW Staff has reviewed and verified the quantities
for the additional work on Change Order No. 2.
lCollege Avenue----[-- W. Rosedale Street to W. Magnolia Avenue
liunius Street Barnett Street to Normandy Road
IMedford Road _T__ NW Dead End to Belford Avenue
FS—tratford Park Drive I N Dead End to Medford Road
M/VVBE Office - JLB Contracting, LLC, agrees to maintain its initial MBE commitment of 11 percent that it
made on the original contract and extend and maintain that same MBE commitment of 11 percent toall
prior change orders up to and inclusive of this Change Order No. 2. Tharafora, JLB Contracting, LLC.
remains in compliance with the City's DBE Ordinance and attests to its commitment by its signature on the
Acceptance of Previous MBE Commitment form executed by an authorized representative of its company.
This contract will have no impact to future operating budgets for TPW Department.
These projects are1ooatedinC{}UNC|L [)|STR|CT8Oond9. W1opaco78K8. 78Cand7SA.
CERTIFICATION:FISCAL INFORMATION I
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinances, funds will be available in the current capital budget, as appropriated, of
the Water Capital Projects FundondofthoGawerCapita{ Projects Fund. TheFiscal Year 2O1OWater
Operating Budget includes appropriations of$26,068,353.00 for the purpose of providing pay-as-you-go
funding for Water Capital Projects. After this transfer for Fiscal Year 2O18. the balance will be
$15,976,158.67 and the Fiscal Year 2016 Water Operating Budget includes appropriations of
$20'300.048.00 for the purpose of providing pay-as-you-go funding for Sewer Capital Projects. After this
transfer for Fiscal Year 2U18. the balance will be $31'1O8,5S2.17.
FUND IDENTIFIERS TO
Fund Department Accoun Project ProgramActivi Budget Reference # Amount
.
[oguume: 20[{M/\C (2U]4-3) STREET REHABILITATION CHANGE ORDER NO. 2 Page 2of3
596011 0600430 4956001 CO2258 C01783 2016 $86,438.00
59601 0600430 5740010 CO2258 C01783 2016 $86,438.00
59607 0700430 4956001 CO2258 C01783 2016 $86,438.00
59607 0700430 5740010 CO2258 C01783 2016 $86,438.00
FROM
Fund Department Account Project Program Activity Budget Reference # Amount
ID ID Year Chartfield 2
39408 0200431 5740010 CO2258 C06283 2016 $172,875.06
59601 0600430 5740010 CO2258 C01783 2016 $86,437.65
596071 0700430 5740010 CO2258 C01783 2016 $86,437.65
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Douglas Wiersig (7801)
Additional Information Contact: Kristian Sugrim (8902)
Logname: 20HMAC (2014-3) STREET REHABILITATION CHANGE ORDER NO. 2 Page 3 of 3