HomeMy WebLinkAboutContract 45640-CO2 CITY SECRETARY
FORT NORTH® City of Fort Worth CONTRACT NO,
Change Order Request Breakdown
Project Namel HMAC Surface Overlay Contract 2014-3 City Sec# 1 45640
Client Project#(s)l 02258;DOE 7215
Contractor JLB Contracting PM1 K.Sugrim Inspectorl Mike Glover
Change Order Submittal# Date 7/27/2015
Dept. T/PW Water Sewer Contract Time
Totals CD
Original Contract Amount $729,273.66 $364,636.84 $364,636.84 $1,458,547.34 180
Extras to Date $10,298.75 $10,298.75 5
Credits to Date
Pending Change Orders(in MBC Process)
Contract Cost to Date $739 572 41. $364,636.84: ;$364;636.84: $1,468,846.09 185
Amount of Proposed Change Order $172;875'06". : $86,437.65: ::$86;437.65= $345,750.36 135
Revised Contract Amount -$912;447:47..' $451,074.49", >$451;`074:49° $1,814,596.45 320
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO ,$0.00 1 $0:00. 1 $0.00
Additional Funding(if necessary) $172;875:06 :1 $86,437.65` $86;437.65 1 $345,750.36
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 24.470
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,823,184.18
The requested funding on this change order are needed for the addition of College Ave.(Rosedale-Magnolia),Junius St.(Bamett-Normandy),
Medford Rd.(Chelsea-N.Dead-End),and Stratford Park(Medford-N.Dead-End).Water and Sanitary Sewer lines were upgraded on these
streets segments,which made it necessary for T/PW to repave. Therefore,90 days are being added to the contract for the additional streets
segments.Similarly,an additional 45 days are being added to defray utility conflicts and delays related to the abnormal weather conditions
experienced during the months of December 2014 through June 2015.
A nby:
77
J. K r, i
-A.0 FO
Rl'
0
�$ Na
•�C 8 y
9
XAS �a
ti ;IX,
OFFICIAL RECORD a APR 2 2016
CITY SECRETARY Ciay OF FORT WORT[
FT.WORTH,TX \z� G yT tREfARY 14w
`- 16 8 L .c
FORT =H City of Fort Worth
Change Order Additions
Project Name HMAC Surface Cmbaet 20%3 City Sec#
Client Project# 02258;DOE 7215
Co JLB Cartrac8rrg PM K.Sugdm Inspector Mike Glover
Change Order Submittal# 1.-1 Date 7272015
ADDITIONS
OEM rE,9UKII`IIIJN DEPT uty Unit nit Cost Total
REM N RETE UR 8 GUTTER TI-PW- 2 3. LF 3.
3 7'CONCRETE CURB 8 GUTTER TI-PvT-- 0 LF 2.25
4 REMOVECONCRE DRIVEWAY -TIP-VF- 1.2 7. 000 SY ---T2.r5
5CONCRETE DRIVEWAY T/PW1,780. 4.45
6 N RETE DRIVEWAY EXPOSED AREGATE T/PW 2.7 0 0 Y $6.70
7 REMOVE IDE ALK T/PW 379. F $2.25
CONCRETE SIDEWALK T/PW 514,M0000 SF
0 REMOVE CONCRETE ALL UTTER /PW 15.000 0000 SY22. 0
12 'PAVE ENT PULVERIZATION /PW 3,6 0.0000 00 SY 3.
13 90-AD95WD--EM SOIL STA131LIZER T 29.000 23.00
1 CEMENT OD AIN(12LY) T W 24.00000000 SY
1 SURFACE MILLING TIPW 2,655.00000000 Y $1.89,
6 PAVEMENT WEDGE MILLING(2'TO EPTH, 'WIDE) T/PW 1,073.00000000 SY 1.8
19 2'ASPHALT PAVEMEN TYPED T/PW 9, 00 Y .75
8 CURB ADDRESSES PAINTING T/PW 22.00 EA 19.6
OCK OD RE LA EMENT T/PW 00 SY 70
2 REMOVE ADA RAMP T/PW-- 1.
3 ADA RAMP /PW 1.0 EA 390.
Water
2 REMOVE CONn=E UTFB&GUTTER Water 61 . LF
3 7'CONCRETE CURB&GUTTER Water 87. 00000 LF 21.25
REMOVE CONCRETE DRIVEWAY Water 634.WMW SY 2.25
5 6"CONCRETE DRIVEWAY ater Y . 5
6 8'CONCRETE DRIVEWAY EXPOSED AGGREGATE Water 2.0 000 SY 6.70
7 REMOVE SIDEW-FLRWater S 2.
8 4"CONCRETE SIDEWFLK SIDEWALKWater 257.00000000 SF $4. 0
10 REMOVe CONCRETE VALLEY GUTTER Water 7.
12 8 PAVEMENT PULVERIZATION Water 1,825.00000 SY 3.87
13 R ADBOND EN1 SOILS BILIZER Water 14.30000000 23.
CEMENT MODIFICATION(12L /SY) Water 1 SY
5 TSURFACE MILLING Water 1,32. 000 SY 89
16 PAVEMENT WEDGE MILLING(2'TO 0 PTH,5 WIDE) Water 53. Y 1.
19 2 ASPHALT PAVEMENT TYPE Water 4,876.30000000 $8.75
28 CURB ADDRESSES PAINTING Water 11.0 EA $19.60
2F-BLOCK SOD REPLACEMENT Water 1 .000 0 SY 6.70
32 REMOVE AA RAMP Wffe-r Toom000 EA00
33 ADA RAMP Water 1.00000000 EA 390.00
Sewer
REMOVE CONCRETE CURB&GUTTER Sewer 616. 000 LF $3.35
7"CONCRETE CURB 8 GUTTER Sewer 875.00000000 LF2.2
REMOVE CONCRETE DRIVEWAY Sewer 6 00000 SY $2.25
6 CONCRETE DRIVEWAY Sewer 90.0 Y .4
8 CONCRETE D I WA E 0 ED AGGREGA E ewer 20,00000000 Y 6.70
REMOVE SIDEWALK ewer 1 .000q SF 2.25
8 4'CONCRETE SIDEWALK- Sewer 257.00000000 SF 4.50
10 REMOVE CONCRETE VALLEY GUTTER Sewer 7.40000000 SY $22.40
12 8" AVE PULVERIZATION Sewer r5 OG-000-0 SY $3.87
13 ROADBOND EN I SOIL STABILIZER Sewer 14.30000000 A 23.00
CEMENT-MODIFICATION(12L ISY) ver 12. 0 SY 119.00
15 2"SURFACE MILLING Sewer 1,327.000000 Y 1.8
16 PAVEMENT WEDGE MILLING(2'TO 0'DEPTH,5'WIDE) Sewer 537.000 0 SY .89
19--2"A PHALT PAVEMENT TYPE D Sewer 876.3 0 Y 8.75
29-CURB ADDRESSES PAINTING ewer I f.00000000EA
2 BLOCK SOD REPCEMENT Sewer 131. Y 6.70
3T---REMOVE ADA RAMP Sewer 1.00000000--U--$46.
3F--- ADA RAMP Sewer 1.000000 EA 390.00
T/PW $172,875.06
Water $86,437.65
Sewer $86,437.65
Sub Total Additions 5,750.36
Change Order Additions Page 1 of 1
FO--R I. city of Fort Worth
Change Order Deletions
Project Name HMAC Surface 2ndff Contract 2014-3 city Sec#
CI'ientProject# 02258;DOE 7215
JLB Cerdraetrng PMJ K&oft IWt.F Mike G.
Change Order Submittal# Data 7/27/!015
DELETIONS
IIEM DESCRIPTION L)EPT Oily Unit Unit Cost Total—
T/Pw $0.00
Water $0.00
Sewer $0.00
Sub Total Deletions
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
CFW Change Order Approval St-COApp02 Page 2 of 5
FORT NORTH. City of Fort Worth
Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: 2
Change Order No.: St-COApp02 Date Started: 2016-03-24
City Sec. No.: 45640 Date Due: 2016-05-13
Project Name: HMAC Surface Overlay (2014-3)
02258 DOE Numbers:
Project Numbers:
DOE No. 7215
Project 50/50 HMAC Street Rehabilitation
Description:
Project Manager: Kristian Sugrim City Inspector: Gary Deyon
Contractor: JLB Contracting, LLC.
COUNCIL ACTION (If Required):
M&C Log Name: 20HMAC (2014-3) Street Rehabilitation Change Order No.2
M&C Number: C-27640 M&C Date: 2016-03-22
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
TPW $ 172,875.06 39408-0200431-5740010-CO2258-C 135
Water $ 86,438.00 59601-0600430-5740010-CO2258-C
Sewer $ 86,438.00 59607-0700430-5740010-CO2258-C
Total Cost: $ 345,751.06 Total Requested Days: 135
Approval Status:
https://projeetpoint.buzzsaw.com/ bz web/Forms/FomiPrint.aspx?SiteId=51500&Processl... 4/27/2016
CFW Change Order Approval St-COApp02 Page 4 of 5
Approved: Yes
Comments:
User: Tara Fishback
Date: 2016-03-25 11:01 AM
Approved: Yes
Comments:
User: Sam Davis
Date: 2016-03-25 11:16 AM
Approved: Yes
Comments:
User: Kristian Sugrim
Date: 2016-03-25 11:32 AM
Approved: Yes
Comments:
User: Najib Fares
Date: 2016-03-25 11:39 AM
Approved: Yes
Comments:
User: Tara Fishback
Date: 2016-03-28 1:26 PM
Approved: Yes
Comments:
User: Sam Davis
Date: 2016-03-28 2:24 PM
Approved: Yes
Comments:
User: Kristian Sugrim
Date: 2016-03-28 3:02 PM
Approved: Yes
Comments:
User: Najib Fares
Date: 2016-04-06 3:51 PM
Approved: Yes
Comments:
User: Todd Blomstrom
Date: 2016-04-08 4:12 PM
Approved: Yes
Cnmments-
https://projectpoint.buzzsaw.com/ bz web/Fonns/FormPrint.aspx?SiteId=51500&ProcessI... 4/27/2016
CFW Change Order Approval St-COApp02 Page 5 of 5
User: Doug Wiersig
Date: 2016-04-10 11:53 PM
Approved: Yes
Comments:
User: Richard McCracken
Date: 2016-04-27 8:55 PM
Approved: Yes
Comments:
User: Jay Chapa
Date: 2016-04-27 4:19 PM
Action Required:
https://projectpoint.buzzsaw.com/ bz_web/Forms/FonnPrint.aspx?Siteld=51500&ProcessI... 4/27/2016
CFW Change Order Approval St-COApp02 Page 1 of 5
Routing
Assigned To: Due Date:
Assigned By: Due Time:
Links 3
fortworthgov/Infrastructure Proiects/02258 - HMAC Surface Overlay (2014-3)/Contractor/Change
Orders/20150804042454494.odf
fortworthgov/Infrastructure Proiects/02258 - HMAC Surface Overlay (2014-3)/Contractor/Change Orders/HMAC 2014-
3 CO 2.)d
fortworthgov/Infrastructure Proiects/02258 -'HMAC Surface Overlay (2014-3)/Contractor/Change Orders/Change Order
Breakdown CO #2 DOE 7215.xls.xlsx
Attachments(0)
No Attachments have been added to this form.
https://projectpoint.buzzsaw.com/ bz web/Forms/ForinPrint.aspx?SiteId=51500&ProcessI... 4/27/2016
M&C Review Page 1 of 3
offldal site of the qty of Fort Worth,Texas
rf WORTH
CITY COUNCIL AGENDA F0-
COUNCIL ACTION: Approved on 3/22/2016-Ordinance No. 22121-03-2016&22122-03-2016
REFERENCE ** 20HMAC (2014-3) STREET
DATE: 3/22/2016 NO.: C-27640 LOG NAME: REHABILITATION CHANGE
ORDER NO. 2
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Change Order No. 2 to City Secretary Contract No.45640 with JLB
Contracting, LLC., in the Amount of$345,750.36 to Rehabilitate Street Sections of College
Avenue, Junius Street, Medford Road and Stratford Park Drive, Thereby Increasing the
Total Contract Amount to$1,814,596.45 for Hot Mix Asphaltic Concrete 2014-3 Street
Rehabilitation and Adopt Appropriation Ordinances(COUNCIL DISTRICTS 8 and 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinances increasing estimated receipts and appropriations in
the Water Capital Projects Fund in the amount of$86,438.00 and the Sewer Capital Projects Fund in
the amount of$86,438.00 from available funds; and
2. Authorize the execution of Change Order No. 2 to City Secretary Contract No.45640 with JLB
Contracting, LLC, in the amount of$345,750.36 for Hot Mix Asphaltic Concrete(2014-3) Street
Rehabilitation, as listed on the chart and thereby, increasing the total contract amount to
$1,814,596.45.
DISCUSSION:
On May 6, 2014, (MSC C-26795)the City Council authorized the execution of a contract with JLB
Contracting, LLC., in the amount of$1,458,547.34 for Hot Mix Asphaltic Concrete(2014-3), following
water and sewer line replacements. This Change Order is to provide for additional streets segments
for which the Water Department has determined the need to complete additional water and sewer
replacement work.
The recommended Change Order applies to the additional street rehabilitation work to be undertaken
in conjunction with a separate utility contract for the replacement of water and sewer sanitary
lines. The Transportation and Public Works (TPW)and Water Departments share in these
resurfacing costs in lieu of performing trench repair under the utility contract. The TPW portion of the
cost on this change order will be$172,875.06,which is available in the Contract Street Maintenance
Fund Budget. The Water Department will contribute funding in the amount of$172,875.30 for this
change order.
The Hot Mix Asphaltic Concrete Street Rehabilitation (2015-4) project budget consists of the
following:
Description IlProject Total
En ineerin $ 0.00
Construction $1,814,596.00
Project Management, Real Property, Acquisitions, $ 586,426.00
Inspection, Testing and Contingencies
Project Total $2,401,022.00
http://apps.cfwnet.org/council_packet/mc review.asp?ID=22066&councildate=3/22/2016 3/23/2016
M&C Review Page 2 of 3
Funding for the Hot Mix Asphaltic Concrete Street Rehabilitation (2015-4) project is as follows:
Fund A ro riations*
Street Rehabilitation Fund
39408 $11
190,142.00
Water Capital Fund 59601 $ 644,026.00
Sewer Capital Fund 59607 $ 566,854
Project Total $2,401,022.00
"Numbers rounded for presentation.
The streets segments to be added are listed below and TPW Staff has reviewed and verified the
quantities for the additional work on Change Order No. 2.
Streets Limits
Colle a Avenue W. Rosedale Street to W. Magnolia Avenue
Junius Street Barnett Street to Normandy Road
Medford Road NW Dead End to Belford Avenue
Stratford Park Drive N Dead End to Medford Road
M/WBE Office-JLB Contracting, LLC, agrees to maintain its initial MBE commitment of 11 percent
that it made on the original contract and extend and maintain that same MBE commitment of 11
percent to all prior change orders up to and inclusive of this Change Order No. 2. Therefore, JLB
Contracting, LLC, remains in compliance with the City's DBE Ordinance and attests to its commitment
by its signature on the Acceptance of Previous MBE Commitment form executed by an authorized
representative of its company.
This contract will have no impact to future operating budgets for TPW Department.
These projects are located in COUNCIL DISTRICTS 8 and 9, Mapsco 76M, 78C and 79A.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of
the attached appropriation ordinances,funds will be available in the current capital budget, as
appropriated, of the Water Capital Projects Fund and of the Sewer Capital Projects Fund. The Fiscal
Year 2016 Water Operating Budget includes appropriations of$26,068,353.00 for the purpose of
providing pay-as-you-go funding for Water Capital Projects. After this transfer for Fiscal Year 2016,
the balance will be$15,976,158.67 and the Fiscal Year 2016 Water Operating Budget includes
appropriations of$26,300,046.00 for the purpose of providing pay-as-you-go funding for Sewer
Capital Projects. After this transfer for Fiscal Year 2016,the balance will be$21,108,592.17.
TO
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year Chartfield 2
59601 0600430 4956001 CO2258 C01783 2016 $86,438.00
59601 0600430 5740010 CO2258 C01783 2016 $86,438.0
59607 0700430 4956001 CO2258 C01783 2016 $86,438.00
59607 0700430 5740010 CO2258 C01783 2016 $86,438.00
FROM
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year Chartfleld 2
39408 0200431 5740010 CO2258 C06283 2016 $172,875.06
59601 1 0600430 5740010 CO2258 C01783 2016 $86,437.6
1596071 0700430 5740010 CO2258 C01783 2016 $86,437.65
http://apps.cfwnet.org/council packet/mc review.asp?ID=22066&councildate=3/22/2016 3/23/2016
M&C Review Page 3 of 3
Submitted for City Manager's Office by_ Jay Chapa (5804)
Originating Department Head: Douglas Wiersig (7801)
Additional Information Contact: Kristian Sugrim (8902)
ATTACHMENTS
20HMAC (2014-3) STREET REHABILITATION CHANGE ORDER NO. 2 sewer AO.docx
20HMAC (2014-3) STREET REHABILITATION CHANGE ORDER NO. 2 water AO.docx
Form 1295 Certificate 2014-3 change order 2 notarized.pdf
Map H2O14-3 CO.gdf
http://apps.cfwnet.org/council_packet/mc review.asp?ID=22066&councildate=3/22/2016 3/23/2016
rw° City of Fort Worth
ACCEPTANCE OF PREVIOUS MBE COMMITMENT FORM
(for use with CHANGE ORDERS or AMENDMENTS greater than$80,000) _
To be Completed by City Project Manager
Change Order(for Construction Contract)
Project Name: City Project Number
02258
HMAC 2014-3 STREET REHABILITATION
City Project Manager
Contractor: KRISTIAN SUGRIM
JLB-CONTRACTING, LLC. Clty's MBE Project Goal: 11 96
Original Amount of Contract: $1,468,547.34 Accepted MBE Commitment: 11 %
Total of Previous Change Orders: $10,298.75 Date of Last MBE Report:
Amount for this Change Order: $345,750.36 Change Order#: 2
Revised Amount of Contract: $1,814,596.45 Date: 813/2015
Language to be inserted in the M&C for this Contract
JLB CONTRACTING, LLC. agrees to maintain its initial MBE commitment of 11%that it made on
the original contract and extend and maintain that same MBE commitment of 11%to all prior
change orders up to and Inclusive of this Change Order No. 2. Therefore JLB CONTRACTING,
LLC. remains in compliance with the City's BDE Ordinance and attests to its commitment by its
signature on the Acceptance of Previous MBE Commitment form executed by an authorized
representative of its company.
c' To be Completed by the Representative of the Contr ctor Q
Printed Signature Title Authorized Signature/Date
JLB CONTRACTING,LLC.
Company Name Contact Name(if different)
1y0 32y, 74 l3 ! <0J✓tSC?JL3 c<►•-•�AtTr,,.C.Coy~
Address E-mail address
Cgg?-r" c�XTW Tom' ?G i Z�- s 1��Z.(-I --Z99,� , U - 09-
City/Stateop T Phone number Fax Number
4- as of3 I C
MBE%Paid to Date Date
ity Pro"Ject Manager has reviewed fSe work assoclate3 with s Change Oraer,
considers It the same or similar to work In the original Contract, and recommends that the
Contractor have the option to retain and coriffln its existing MBE commitment.
KRISTIAN SUGRIM Qp g
City Project Manager City Project Man4ger Signature Date
Attach Complete Change Order Documentation to MIWBE office
ComplianceTo be Completed by the M/WBE
ari rea\ MI 6 L yio
MNVBE C pllance Staff ID# MBE urrent% Level via Last Report Recd
hl of ' .
NVBE Signature Date