HomeMy WebLinkAboutOrdinance 22183-05-2016 ORDINANCE NO. 22183-05-2016
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE SEWER CAPITAL PROJECTS FUND IN THE
AMOUNT OF$167,700.00,FROM AVAILABLE FUNDS,FOR THE PURPOSE OF
FUNDING WATER AND SANITARY SEWER REPLACEMENT CONTRACT
2015 WSM-B,PART 1;PROVIDING FOR A SEVERABIL ITY CLAUSE; MAKING
THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING
ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN
EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2015-2016 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Sewer
Capital Projects Fund in the amount of$167,700.00, from available funds,for the purpose of funding Water
and Sanitary Sewer Replacement Contract 2015 WSM-B,Part 1.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance No. 21873-09-2015 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas W.Black, ary J! ,
Sr.Assistant City Attorney City Secre a
ADOPTED AND EFFECTIVE:May 3,2016
Ordinance No.22183-05-2016
Page 1 of 1
t
- _.fit .• .. .'..
I
ilk
_ FOR _
I® I
rte ' ®Y r�" !:
• c
la
Iff ow.
mb
Dir
kw
i�' qa r y „ + ., �s �•--: rr�te` J_ - �r 7- tw C• } r.
66A Mir
WIN 1p
P`` e ► � �+fie r _� � ". 'ily' `� ^� �i� '�
INV -
i Sh - '
R� '. -4 ♦ s :' e- _- - 4. __ .1� Vii.: -
I: Lam, i.. ,w ' F
MOIL -w-
m -md �j•F ,F s�,;
z -r. TFT
! `t "" u zi
WiL -a
••S s' ea
n� n _-ter.
•' +
bc
Ir
- s _�# �>.� Sr .,4•y+ 'yam ,�;
• � �� � � � �Swa � :_• f,f" - Yt !Via: _
g
• - • ` s
A . mil.
3
= 1 / E J _ i
� � � • t-ic "r�
• •� r , •Ao ^# ,f
rw. At
na NUT
lwn IF
F "
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 51312016 Ordinance No. 22183-05-2016 & 22184-05-2016';
DATE: Tuesday, May 03, 2016 REFERENCE NO.: **C-27700
LOG NAME: 6015WSMBPI-TEJASC
SUBJECT:
Authorize Execution of a Contract with Tejas Commercial Construction, LLC, in the Amount of$863,813.75
for the Water and Sanitary Sewer Replacement Contract 2015 WSM-B, Part 1 and Adopt Appropriation
Ordinances (COUNCIL DISTRICT 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinances increasing estimated receipts and appropriations in the
Water Capital Projects Fund in the amount of$952,500.00 from available funds and the Sewer Capital
Projects Fund in the amount of$167,700.00 from available funds for a total amount of$1,120,200; and
2. Authorize the City Manager to execute a contract with Tejas Commercial Construction, LLC, in the
amount of$863,813.75 for the Water and Sanitary Sewer Replacement Contract 2015 WSM-B, Part 1.
DISCUSSION:
On February 17, 2015 (Mayor and Council Communication (M&C) C-27191), the City Council authorized
an Engineering Agreement with Dunaway and Associates, L.P. to prepare the plans and specifications for
the Water and Sanitary Sewer Replacement Contract 2015, WSM-B.
This M&C is to authorize a construction contract for the replacement of the deteriorated water and/or
sanitary sewer mains as indicated on the following streets:
F___STREET_ I-- FROM i TO S WORK OF
I Harwen Terrace I W. Gambrel)Street Fuller Avenue Water
Odessa Avenue W. Gambrell Street F_ Binyon Avenue Water
Merida Avenue Drew Street W. Pafford Street I Water/Sewer
1 Wayside Avenue_—(—W.Waggoman Street —F Drew Street Water
The project was advertised for bid on July 2, 2015 and July 9, 2015 in the Fort Worth Star-Telegram. On
July 30, 2015, the following bids were received:
F BIDDER AMOUNT C TIME O ON
FCD Builders, Inc.* _ $ 839,192.02 0160 Calendar Days
R& D Burns Brothers, Inc.**� F $ 850,584.30 _F— -
Tejas Commercial Construction, LLC $ 863,813.75_(—
Woody Contractors, Inc. $ 873,691.15 -
FA-w Construction and Utilities, Inc. $ 898,108.95 Fv -
Logname: 6015WSMBPI-TEJASC Page 1 of 4
CWilliam J. Schultz, Inc. dba Circle"C" Construction Company $ 906,915.00_) _ -
ackson Construction, Ltd. $ 953,26_7.3_0_
Ark Contracting Services, LLC $ 963,249.00 F
IAtkins Brothers Equipment Co, Inc. $1,454,363.00 I
*CD Builders, Inc., has been rejected as not qualified due to repeated failures on multiple contracts to pay
subcontractors and suppliers resulting in its surety contacting the City of Fort Worth and requiring current
contract payments be routed directly to it.
**Due to the passage of time between the bid opening and its award, Staff contacted the next low bidder
to inquire as to its readiness and willingness to perform the work at the bid prices. R&D Burns Brothers
Inc., informed Staff that scheduling conflicts prevented it from being able to perform this project. Staff
recommends award of contract to the third low bidder, Tejas Commercial Construction, LLC, whose bid is
still within the engineer's estimate for the project and has stated its readiness and willingness to perform at
its original bid prices.
In addition to the contract cost, $180,700.00 (water: $133,100.00; sewer: $47,600.00) is required for
engineering, project management, inspection, material testing, negative balances and $75,686.00 (water:
$51,025.00; sewer: $24,661.00) is provided for project contingencies.
Appropriations for the Water and Sanitary Sewer Replacement Contract 2015, WSM-B Project will consist
of the following:
Existing Additional Future
Description Appropriations Appropriations,Appropriations Project Total
Engineering _ $424,132.00 J$ 0.00 $ 0.00 $424,132.00
Project
Management,
Inspection,
Testing and
Contingencies $49,000.00_ $ 256,386.0_0_ $ 526,214.00 $ 831,600.00
Construction I $ 0.00_1$ 863,814.00 1$2,586,586.00* ,$3,45 00040 0
Project Total 1 $473,132.00 1 $1,120,200.00 $3,112,800.00 $4,70 02316 0
Amounts rounded for presentation purposes.
*Two future construction contracts and associated project costs are anticipated to be approved in
Spring/Summer 2016.
Appropriations for the Water and Sanitary Sewer Replacement Contract 2015, WSM-B Project will consist
of the following:
r FUND Appropriations
Water Capital Projects Fund 59601 r $3,743,066.00
Sewer Capital Projects Fund 59607 1$ 963,066.00
Project Total $4,706,132.00
Amounts rounded for presentation purposes.
Construction is anticipated to commence in May 2016. The project is estimated to be completed by the
end of October 2016.
This project will have no impact on the Water Department's operating budget.
M/WBE OFFICE - Tejas Commercial Construction, LLC, is in compliance with City's BDE Ordinance by
Logname: 6015WSMBPI-TEJASC Page 2 of 4
committing to 10 percent MBE participation. The City's MBE goal on this project is seven
percent. Additionally, Tejas Commercial Construction, LLC, is a certified M/WBE firm.
The project is located in COUNCIL DISTRICT 9, Mapsco 90 F, 90 H and 90 J.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinances, funds will be available in the current capital budget, as appropriated, of
the Water Capital Projects Fund and the Sewer Capital Projects Fund. The Fiscal Year 2016 Water
Operating Budget includes appropriations of$26,068,353.00 for the purpose of providing pay-as-you-go
funding for capital projects. After this transfer for Fiscal Year 2016, of$952,500.00, the balance will be
$13,311,469.00. The Fiscal Year 2016 Sewer Operating Budget includes appropriations of
$26,300,046.00 for the purpose of providing pay-as-you go funding for capital projects. After this transfer
for Fiscal Year 2016 in the amount of$167,700.00, the balance will be $20,215,760.00.
Existing Additional Future Revised
Fund Appropriations Appropriations Appropriations Appropriations*
Water Operating 596011 $371,866.00 $ 952,500.00 ( $2,418,700.00 $3,743,066.00
(Sewer Operating $101,266.00 _167,700.00 �$ 694,100.00 I_ $ 963,066.00 _
59607
Project Total $473,132.00 $1,120,200.00 $3,112,800.00 r $4,706,132.00
*Amounts rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department Account Project Program Activity Budget Reference # Amount
ID ID Year (Chartfield 2)
1 59601 0600430 4956001 CO2436 C017ZZ 2016 $952,500.00
1 59601 0600430 5110101 CO2436 C01780 2016 $14,400.00
1 59601 0600430 5110101 CO2436 C01730 2016 $15,000.00
1 59601 0600430 5310350 CO2436 C01773 2016 $8,000.00
1 59601 0600430 5310350 CO2436 C01752 2016 $20,000.00
1 59601 0600430 5740010 CO2436 C01783 2016 $819,400.00
1 59601 0600430 5330500 CO2436 C01784 2016 $16,400.00
1 59601 0600430 5310350 CO2436 C01784 2016 $4,000.00
1 59601 0600430 5310350 CO2436 C01785 2016 $53,300.00
1)59601 0600430 5110101 CO2436 C01790 2016 $2,000.00
1)59607 0700430 4956001 CO2436 C017ZZ 2016 $167,700.00
1 59607 0700430 5110101 CO2436 C01780 2016 $2,200.00
1 59607 0700430 5110101 CO2436 C01730 2016 $1,000.00
1 59607 0700430 5310350 CO2436 C01752 2016 $5,000.00
1).59607 0700430 5740010 CO2436 C01783 2016 $120,100.00
1 59607 0700430 5310350 CO2436 C01783 2016 $2,000.00
1 59607 0700430 5330500 CO2436 C01783 2016 $2,500.00
1 59607 0700430 5310350 CO2436 C01785 2016 $7,900.00
1 59607 0700430 5110101 CO2436 C01790 2016 $2,000.00
1)596071 0700430 5330500 CO2436 C01751 2016 $25,000.00
FROM
Logname: 6015WSMBPI-TEJASC Page 3 of 4
Fund Department ccount Project Program ctivity Budget Reference # Amount
ID ID Year ChartfieId 2
2 596011 0600430 5740010 1 CO2436 C01783 2016 $768,375.30
25596071 0700430 57400101 CO2436 C01783 2016 $95,438.45
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: John Carman (8246)
Additional Information Contact: Walter Norwood (5026)
Logname: 6015WSMBPI-TEJASC Page 4 of 4