HomeMy WebLinkAboutContract 47387-CO1 FORT WORTH City of Fort Worth CONITRACT 010,
Change Order Request
Project Name: Water&Sanitary Sewer Replacement Contract 2015 WSM-C,Part 1 City Sec No.: 47387
Project No.(s): P253-608170243483 and P258-708170243483 I DOE No. 7378 City Proj.No.: 02434
Project Description: Water and Sanitary Sewer Main Replacement on Avenue M,Avenue N,Fitzhugh Avenue,and Freddie Street.
Contractor: William J.Schultz,Inc.dba Circle C Construction,Co. Change Order# 0 Date: 4/26/2016
City Project Mgr. Liam Conlon City Inspector: I Carlos Vasquez
Phone Number: 817 392 6824 Phone Number: 817 992 2600
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $745,965.00 $214,660.00 $960,625.00 160
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $745,965.00 $214,660.00 $960,625.00 160
Amount of Proposed Change Order $26,550.00 $26,550.00 030
Revised Contract Amount $772,515.00 $214,660.00 $987,175.00 190
Original Funds Available for Change Orders $38,000.00 $22,000.00 $60,000.00
Remaining Funds Available for this CO $38,000.00 $22,000.00 $60,000.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 2.76%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $1,200,781.25
JUSTIFICATION (REASONS)FOR CHANGE ORDER
Change order No. 1 provides for the replacement of unsuitable native backfill that was encountered during
construction on Avenue M,with cement stabilized sand material.
ORrO
Staff concurs with the contractor's request for 30 additional calendar days on the change or�
MAY 17 2016
cJTv 0f FORT WORTH OFFICIAL RECORD G
('IiYSEGR CITY SECRETARY
FT. WORTH,TX
It is understood and agreed that the acceptance of this Chenge Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Contractor Signature Date
William J.Schultz,Inc.dba Circle C Construction,Co. Teri Skelly
Inspec r Date Project Man9y1r Date
Assistant Director(Water Dept) Date pstructiop Supervisor(TPW Dept) gate
R 5--t6-/G Ct P
As ttoMQV Date Assistant City Manager Date
A -
Council Action(If Required)
M&C Number N/A M&C Date Approved N/A
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Water&Sanitary Sewer Replacement Contract 2015 WSM-C, Part 1 City Sec No.: 47387
Project No.(s): P253-608170243483 and P258-708170243483 DOE No. 7378 City Proj.No.: 02434
Project Water and Sanitary Sewer Main Replacement on Avenue M,Avenue N, Fitzhugh Avenue,and Freddie Street.
Description
Contractor William J.Schultz, Inc.dba Circle C Construction,Co. Change Order:0 Date: 4/26/2016
71
City Project Mgr. Liam Conlon City Inspector Carlos Vasquez
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
27 New CSS BackFill Material Water 295.00 CY $90.00 $26,550.00
Water $26,550.00
Sewer
Page 2 of 4 Additions Sub Total 1$26,550.00
F"RT WCC RT H City of Fort Worth
Change Order Deletions
Project Name Water&Sanitary Sewer Replacement Contract 2015 WSM-C, Part 1 City Sec No.: 47387
Project No.(s): P253-608170243483 and P258-708170243483 DOE No. 7378 City Proj. No.: 02434
Project Description Water and Sanitary Sewer Main Replacement on Avenue M,Avenue N, Fitzhugh Avenue, and Freddie Street.
Contractor William J. Schultz, Inc.dba Circle C Construction, Co. Change Order: 0 Date 4/26/2016
City Project Mgr. Liam Conlon City Inspector: F Carlos Vasquez
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
Water
Sewer
Page 3 of 4 Deletions Sub Total
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for"- his CO:
Total $0:00;
Previous Change Orders
:DATEAMOUNT
Total
Page 4 of 4