HomeMy WebLinkAboutContract 46527-CO2 FORT WURTI-i City of Fort Worth CITY SECRETARY
Change Order Request CONTRACT NO.
Project Name I Little Fossil Creek Interceptor M-292 Improvements,Part 1 City Sec No. 46527
Project No.(s) P258-701170196083 I DOE No. 7046 City Proj.No. 01960
Project Description: Sanitart sewer improvements from NE Loop 820 north Frontage Road to Missy Lane.
Contractor: PM Construction and Rehab, L.P. Change Order: 0 Date: 6/6/2016
City Project Mgr.1 Roberto C. Sauceda City Inspector: I Paul Gieger
Phone Number:1 817-392-2387 Phone Number: 817-392-8371
Dept. Sewer Totals Contract Time
(Calender days)
Original Contract Amount $2,966,514.00 $2,966,514.00 220
Extras to Date
Credits to Date $0.38 $0.38
Pending Change Orders(in MSEC Process)
Contract Cost to Date $2,966,513.62 $2,966,513.62 220
Amount of Proposed Change Order $46,348.90 $46,348.90 030
Revised Contract Amount $3,012,862.52 $3,012,862.52 250
Original Funds Available for Change Orders $90,000.00 $90,000.00
Remaining Funds Available for this CO $90,000.38 $90,000.38
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 1.56%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $3,708,142.50
The change order will providc for the ailciitiOTi (}f the fol Inwitag Haat are necessary on the }project:
• 8-inch pipe enlargement of sanitary sewer line.
• Pre and post TV inspection.
• Rehabilitation of manholes and sidewalk repairs. ®'� IFO��► `
Staff concurs with the contractor's request for 30 additional calendars on a e �
AU
M J. se , C- Secretary
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
PM Construction and Rehab, L.P. Robert Donath
?416-
D I G zd Ib FFICIAL ii fti
M&C Number N/A M&C Date Approved
FORT WOaxIII City of Fort Worth
Change Order Additions
Project Name Little Fossil Creek Interceptor M-292 Improvements,Part 1 City Sec No. 46527
Project No.(s) P258-701170196083 DOE No.F-7-046--1 City Proj.No. 01960
Project Sanitart sewer improvements from NE Loop 820 north Frontage Road to Missy Lane.
Description
Contractor PM Construction and Rehab,L.P. Change Order: ® Date: 6/6/2016
City Project Mgr. Roberto C. Sauceda City Inspector Paul Gieger
ADDITIONS
ITEM DEPThilt t11 Thai
22 Remobilization Sewer 1.00 LS $10,000.00 $10,000.00
23 8"Pipe Enlargement Sewer 3369.00 LF $46.00 $154,974.00
24 8"Pre Clean CCTV Sewer 3369.00 LF $4.00 $13,476.00
25 8"Post Clean CCTV Sewer 3369.00 LF $1.75 $5,895.75
26 Manhole rehabilitation Sewer 54.00 VF $330.00 $17,820.00
Sewer $202,165.75
Page 2 of 4 lAdditions Sub Total $202,165.75
F4::1RT NORTH City of Fort Worth
Change Order Deletions
Project Name Little Fossil Creek Interceptor M-292 Improvements, Part 1 City Sec No. 46527
Project No.(s) P258-701170196083 DOE No. 7046 City Proj. No. 01960
Project Description Sanitart sewer improvements from NE Loop 820 north Frontage Road to Missy Lane.
Contractor PM Construction and Rehab, L.P. Change Order: 0 Date 6/6/2016
City Project Mgr. Roberto C.Sauceda City Inspector Paul Gieger
DELETIONS
ITEM DEWRIPTION DEPT Qty Unit Unit Cost Total
5 Trench Safety Sewer 4723.00 LF $0.01 $47.23
10 6'Chain Link,Aluminum Sewer 150.00 LF $15.00 $2,250.00
12 21"Sewer Pipe,Point Repair Sewer 30.00 LF $500.00 $15,000.00
13 24"Sewer Pipe, Point Repair Sewer 1346.89 LF $58.00 $78,119.62
14 Large Stone Riprap Sewer 419.00 SY $100.00 $41,900.00
15 Portable Message Signs Sewer 34.00 LS $500.00 $17,000.00
18 Exploratory Excavation Sewer 1.00 JEA $1,500.00 $1,500.00
Sewer $155,816.85
Page 3 of 4 Deletions Sub Total 1$155,816.85
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
Page 4 of 4