STANDARD AGREEMENT FOR PROFESSIONAL SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home-rule municipality
(the "CITY"), and Dunham Engineering, Inc., authorized to do business in Texas, an
independent contractor ("Consultant"), for a PROJECT generally described as: Caylor
Ground Storage Tank Rehabilitation Project.
Article I
Scope of Services
(1) Consultant hereby agrees to perform as an independent contractor the services set
forth in the Scope of Services attached hereto as Attachment "A". These services
shall be performed in connection with Caylor Ground Storage Tank Repair and
Repainting Project, Project No. 02111.
(2) Additional services, if any, will be requested in writing by the City. City shall not pay
for any work performed by Consultant or its subconsultants, subcontractors and/or
suppliers that has not been ordered in writing. It is specifically agreed that
Consultant shall not be compensated for any alleged additional work resulting from
oral orders of any person.
Article II
Compensation
Consultant shall be compensated in accordance with the Fee Schedule shown in
Attachment "B". Payment shall be considered full compensation for all labor, materials,
supplies, and equipment necessary to complete the services described in Attachment "A".
However, the total fee paid by the City shall not exceed a total of $110,000.00 unless the
City and the Consultant mutually agree upon a fee amount for additional services and
amend this Agreement accordingly.
The Consultant shall provide monthly invoices to the City. Payment for services rendered
shall be due within thirty (30) days of the uncontested performance of the particular
services so ordered and receipt by City of Consultant's invoice for payment of same.
Acceptance by Consultant of said payment shall operate as and shall release the City from
all claims or liabilities under this Agreement for anything related to, done, or furnished in
connection with the services for which payment is made, including any act or omission of
the City in connection with such services.
OFFICIAL RECORD
C4 of Fort worth,Texas CITY SECRETARY
Standard Agreement for Professional Services
Revision Date:9/24/2014 FT',WORTH,TX
Page 1 of 8
Article III
Term
Unless terminated pursuant to the terms herein, this Agreement shall be for a term of 3 years,
beginning upon the date of its execution, or until the completion of the subject matter
contemplated herein, whichever occurs first.
Article IV
Independent Contractor
Consultant shall operate hereunder as an independent contractor, and not as an officer,
agent, servant, or employee of the City. Consultant shall have exclusive control of and the
exclusive right to control the details of its work to be performed hereunder and all persons
performing same, and shall be solely responsible for the acts and omissions of its officers,
agents, employees, contractors and subcontractors. The doctrine of respondent superior
shall not apply as between City and Consultant, its officers, agents, employees, contractors,
and subcontractors, and nothing herein shall be construed as creating a partnership or joint
venture between City and Consultant.
Article V
Professional Competence and Indemnification
(1) Work performed by Consultant shall comply in all aspects with all applicable local,
state and federal laws and with all applicable rules and regulations promulgated by
the local, state and national boards, bureaus and agencies. Approval by the City
shall not constitute or be deemed to be a release of the responsibility and liability of
Consultant or its officers, agents, employees, contractors and subcontractors for the
accuracy and competency of its services performed hereunder.
(2) In accordance with Texas Local Government Code Section 271.904, the
Consultant shall indemnify, hold harmless, and defend the City against
liability for any damage caused by or resulting from an act of negligence,
intentional tort, intellectual property infringement, or failure to pay a
subcontractor or supplier committed by the Consultant or Consultant's agent,
consultant under contract, or another entity over which the Consultant's
exercises control.
City of Fort Worth,Texas
Standard Agreement for Professional Services
Revision Date:9/24/2014
Page 2 of 8
Article VI
Insurance
(1) Consultant shall not commence work under this Agreement until it has obtained all
insurance required under this Article and the City has approved such insurance, nor
shall Consultant allow any subcontractor to commence work on its subcontract until
all similar insurance of the subcontractor has been so obtained and approval given
by the City; provided, however, Consultant may elect to add any subconsultant as
an additional insured under its liability policies.
Commercial General Liability
$1,000,000 each occurrence
$1,000,000 aggregate
Automobile Liability
$1,000,000 each accident (or reasonably equivalent limits of
coverage if written on a split limits basis). Coverage shall be
on any vehicle used in the course of the Project.
Worker's Compensation
Coverage A: statutory limits
Coverage B: $100,000 each accident
$500,000 disease - policy limit
$100,000 disease - each employee
(2) Additional Insurance Requirements
a. Except for employer's liability insurance coverage under Consultant's worker's
compensation insurance policy, the City, its officers, employees and servants shall
be endorsed as an additional insured on Consultant's insurance policies.
b. Certificates of insurance shall be delivered to the City Manager, Attention: David
Cooke, 1000 Throckmorton St., Fort Worth, TX 76102, prior to commencement of
work.
c. Any failure on part of the City to request required insurance documentation shall
not constitute a waiver of the insurance requirements specified herein.
d. Each insurance policy shall be endorsed to provide the City a minimum thirty days
notice of cancellation, non-renewal, and/or material change in policy terms or
coverage. A ten days notice shall be acceptable in the event of non-payment of
premium.
City of Fort Worth,Texas
Standard Agreement for Professional Services
Revision Date:9/24/2014
Page 3 of 8
e. Insurers must be authorized to do business in the State of Texas and have a
current A.M. Best rating of A: VII or equivalent measure of financial strength and
solvency.
f. Other than worker's compensation insurance, in lieu of traditional insurance, City
may consider alternative coverage or risk treatment measures through insurance
pools or risk retention groups. The City must approve in writing any alternative
coverage.
g. Workers' compensation insurance policy(s) covering employees employed on the
Project shall be endorsed with a waiver of subrogation providing rights of recovery
in favor of the City.
h. City shall not be responsible for the direct payment of insurance premium costs
for Consultant's insurance.
i. Consultant's insurance policies shall each be endorsed to provide that such
insurance is primary protection and any self-funded or commercial coverage
maintained by City shall not be called upon to contribute to loss recovery.
j. In the course of the Agreement, Consultant shall report, in a timely manner, to
City's officially designated contract administrator any known loss occurrence which
could give rise to a liability claim or lawsuit or which could result in a property loss.
k. Consultant's liability shall not be limited to the specified amounts of insurance
required herein.
I. Upon the request of City, Consultant shall provide complete copies of all
insurance policies required by these Agreement documents.
Article VII
Transfer or Assignment
City and Consultant each bind themselves, and their lawful successors and assigns, to this
Agreement. Consultant, its lawful successors and assigns, shall not assign, sublet or transfer
any interest in this Agreement without prior written consent of the City.
Article VIII
Termination of Contract
(1) City may terminate this Agreement for its convenience on 30 days' written notice.
Either the City or the Consultant for cause may terminate this Agreement if either
Party fails substantially to perform through no fault of the other and does not
City of Fort Worth,Texas
Standard Agreement for Professional Services
Revision Date:9/24/2014
Page 4 of 8
commence correction of such nonperformance with 5 days of written notice and
diligently complete the correction thereafter
(2) If City chooses to terminate this Agreement under Article 8, upon receipt of notice of
termination, Consultant shall discontinue services rendered up to the date of such
termination and City shall compensate Consultant based upon calculations in Article
2 of this Agreement and Exhibit "B" attached hereto and incorporated herein.
(3) All reports, whether partial or complete, prepared under this Agreement, including
any original drawings or documents, whether furnished by the City, its officers,
agents, employees, consultants, or contractors, or prepared by Consultant, shall be
or become the property of the City, and shall be furnished to the City prior to or at
the time such services are completed, or upon termination or expiration of this
Agreement.
Article IX
Right to Audit
(1) Consultant agrees that the City shall, until the expiration of three (3) years after final
payment under this Agreement, have access to and the right to examine any directly
pertinent books, documents, papers and records of Consultant involving transactions
relating to this Agreement. Consultant agrees that the City shall have access during
normal working hours to all necessary facilities and shall be provided adequate and
appropriate workspace in order to conduct audits in compliance with the provisions of
this section. City shall give Consultant reasonable advance notice of intended audits.
(2) Consultant further agrees to include in all its subcontracts hereunder, a provision to
the effect that the subcontracting consultant agrees that the City shall, until the
expiration of three (3) years after final payment under the subcontract, have access
to and the right to examine any directly pertinent books, documents, papers and
records of such sub-consultant, involving transactions to the subcontract, and
further, that City shall have access during normal working hours to all sub-
consultant facilities, and shall be provided adequate and appropriate work space in
order to conduct audits in compliance with the provisions of this article. City shall
give Consultant and any sub-consultant reasonable advance notice of intended
audit.
(3) Consultant and sub-consultants agree to photocopy such documents as may be
requested by the City. The City agrees to reimburse Consultant for the cost of copies
at the rate published in the Texas Administrative Code in effect as of the time copying
is performed.
City of Fort Worth,Texas
Standard Agreement for Professional Services
Revision Date:9/24/2014
Page 5 of 8
Article X
Minority Business and Small Business Enterprise (MBE)(SBE) Participation
In accordance with the City's Business Diversity Enterprise Ordinance No. 20020-12-2011,
as amended, the City has goals for the participation of minority business enterprises and/or
small business enterprises in City contracts. Consultant acknowledges the MBE and SBE
goals established for this Agreement and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent misrepresentation)
and/or the commission of fraud by the Consultant may result in the termination of this
Agreement and debarment from participating in City contracts for a period of time of not less
than three (3) years.
Article XI
Observe and Comply
Consultant shall at all times observe and comply with all federal, state, and local laws and
regulations and with all City ordinances and regulations which in any way affect this
Agreement and the work hereunder, and shall observe and comply with all orders, laws
ordinances and regulations which may exist or may be enacted later by governing bodies
having jurisdiction or authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. Consultant agrees to defend, indemnify and hold harmless City
and all of its officers, agents and employees from and against all claims or liability arising out
of the violation of any such order, law, ordinance, or regulation, whether it be by itself or its
employees.
Form 1295 Certification No. ��'
Article XII
Venue and Jurisdiction
If any action, whether real or asserted, at law or in equity, arises on the basis of any
provision of this Agreement, venue for such action shall lie in state courts located in
Tarrant County, Texas or the United States District Court for the Northern District of Texas
— Fort Worth Division. This Agreement shall be construed in accordance with the laws of
the State of Texas.
Article XIII
Contract Construction
The Parties acknowledge that each party and, if it so chooses, its counsel have reviewed
City of Fort Worth,Texas
Standard Agreement for Professional Services
Revision Date:9/24/2014
Page 6 of 8
and revised this Agreement and that the normal rule of construction to the effect that any
ambiguities are to be resolved against the drafting party must not be employed in the
interpretation of this Agreement or any amendments or exhibits hereto.
Article XIV
Severability
The provisions of this Agreement are severable, and if any word, phrase, clause,
sentence, paragraph, section or other part of this Agreement or the application thereof to
any person or circumstance shall ever be held by any court of competent jurisdiction to be
invalid or unconstitutional for any reason, the remainder of this Agreement and the
application of such word, phrase, clause, sentence, paragraph, section, or other part of this
Agreement to other persons or circumstances shall not be affected thereby and this
Agreement shall be construed as if such invalid or unconstitutional portion had never been
contained therein.
Article XV
Notices
Notices to be provided hereunder shall be sufficient if forwarded to the other Party by
hand-delivery or via U.S. Postal Service certified mail return receipt requested, postage
prepaid, to the address of the other Party shown below:
City of Fort Worth
Attn: City Manager
1000 Throckmorton St.
Fort Worth, Texas 76102
Consultant: Dunham Engineering, Inc.
Attn: Travis C. Tatum
12815 FM 2154, Suite 150
College Station, TX 77845-3981
Article XVI
Headings
The headings contained herein are for the convenience in reference and are not intended
to define or limit the scope of any provision of this Agreement
City of Fort Worth,Texas
Standard Agreement for Professional Services
Revision Date:9/24/2014
Page 7 of 8
Article XVII
Counterparts
This Agreement may be executed in one or more counterparts and each counterpart shall,
for all purposes, be deemed an original, but all such counterparts shall together constitute
but one and the same instrument.
Executed and effective this the IYkday o , 20(�.
BY: BY:
CITY OF FORT WORTH ENGINEER
Dunham Engineering, Inc.
Jesus J. Chapa Travis C. Tatum, P.E.
Assistant City Manager President & CEO
Date: / I tp Date:_ t/A t/op
APPROVAL RECOMMENDED:
By: AA,C'V lt.�
John Carman
Water Director �9
APPROVED AS TO FORM AND LEGALITY M&C No.:1071--4QW>
By: M&C Date:
Douglas . Black
Assistant City Attorney ®� FO�
ATTEST: 0
/M -
Pia Qer r
City Sary
O FFICIAL RECORD
City of Fort Worth,Texas CITY SECRETARY
Standard Agreement for Professional Services FT WOR-rif Ty
Revision Date:9/24/2014 �l �7 A
Page 8 of 8
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR 8 REPAINTING PROJECT
CITY PROJECT NO.:02111
ATTACHMENT A
Scope for Engineering Design Reiated Services for Water
and/or Sanitary Sewer Improvements
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
REPAIR & REPAINTING PROJECT
CITY PROJECT NO. 02111
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
WORK TO BE PERFORMED
Task 1. Design Management
Task 2. Conceptual Design
Task 3. Preliminary Design
Task 4. Final Design
Task 5. Bid Phase Services
Task 6. Construction Phase Services
Task 7. ROW/Easement Services
Task 8. Survey and Subsurface Utility Engineering Services
Task 9. Plan Submittal Checklists
TASK 1. DESIGN MANAGEMENT.
ENGINEER shall ensure efficient and effective use of ENGINEER's and CITY's time and
resources.
ENGINEER shall manage change,
• communicate effectively,
• coordinate internally and externally as needed, and
• proactively address issues with the CITY's Project Manager and others as
necessary to make progress on the work.
1.1. Managing the Team
• Lead, manage and direct design team activities
• Ensure quality control is practiced in performance of the work
• Communicate internally among team members
• Task and allocate team resources
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 1 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR 3 REPAINTING PROJECT
CITY PROJECT NO.:02111
1.2. Communications and Reporting
• Attend a pre-design project kickoff/chartering meeting with CITY staff to confirm and
clarify scope, understand CITY objectives, and ensure economical and functional
designs that meet CITY requirements
• Conduct review meetings with the CITY at the end of each design phase
• Prepare invoices and submit monthly in the format requested by the CITY.
• Prepare and submit monthly progress reports in the format provided by the Water
Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule updates
with a schedule narrative monthly, as required in Attachment D to this Standard
Agreement and according to the City of Fort Worth's Schedule Guidance Document.
• Complete Monthly MWWBE Report Form and Final Summary Payment Report Form at
the end of the project
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to meet
their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub-consultants shall carry readily visible
information identifying the name of the company and the company representative.
ASSUMPTIONS
• 15 MWBE reports will be prepared
• 4 meetings with city staff
• 15 monthly water department progress reports will be prepared
• 15 monthly project schedule updates will be prepared
DELIVERABLES
A. Meeting summaries with action items
B. Monthly invoices
C. Monthly progress reports
D. Baseline design schedule
E. Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 2 of 17
ATTACHMENTA
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR S REPAINTING PROJECT
CITY PROJECT NO.:02111
F. Monthly M/WBE Report Form and Final Summary Payment Report Form
G. Plan Submittal Checklists (See Task 9)
TASK 2. CONCEPTUAL DESIGN (30 PERCENT).
The Conceptual Design shall be submitted to CITY per the approved Project Schedule.
The purpose of the conceptual design is for the ENGINEER to
• Study the project,
• Identify and develop alternatives that enhance the system,
• Present (through the defined deliverables) these alternatives to the CITY
• Recommend the alternatives that successfully addresses the design problem, and
• Obtain the CITY's endorsement of this concept.
ENGINEER will develop the conceptual design of the infrastructure as follows.
2.1. Data Collection
• In addition to data obtained from the CITY, ENGINEER will research proposed
improvements in conjunction with any other planned future improvements that
may influence the project.
• The ENGINEER will also identify and seek to obtain data for existing conditions
that may impact the project including but not limited to; utilities, agencies (TxDOT
and railroads), City Master Plans, and property ownership as available from the
Tax Assessor's office.
• The data collection efforts will also include conducting special coordination
meetings with affected property owners and businesses as necessary to develop
sewer re-routing plans.
• The ENGINEER shall visit the project site and obtain the meter numbers and sizes
on all existing meters to be replaced on the project and shall identify existing
sample stations and fire line locations.
2.2. Geotechnical Investigations
• ENGINEER shall advise the CITY of test borings and other subsurface
investigations that may be needed for the project. If the CITY determines that
such borings or investigations are needed, then the ENGINEER shall work with
the CITY and CITY's geotechnical consultant to draw up specifications for such
testing program. The cost of such testing will be paid for by the CITY.
2.3. Fire Line Reconnection
2.4. The Conceptual Design Package shall include the following:
• Cover Sheet
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 3 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CITY PROJECT NO.:02111
• Graphic exhibits and written summary of alternative design concepts considered,
strengths and weaknesses of each, and the rationale for selecting the
recommended design concept.
• Proposed phasing of any water and sanitary sewer work that is included in this
project documented in both the project schedule and narrative form.
• Documentation of key design decisions.
• Estimates of probable construction cost.
ASSUMPTIONS
• 0 Geotechnical borings are expected for this project.
_3_copies of the conceptual design package (30% design) will be delivered..
Report shall be letter sized and comb-bound with a clear plastic cover. Drawings
will be_11 x17 size fold outs bound in the report
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in Buzzsaw
• ENGINEER shall prepare the meeting minutes of the Concept Review meeting
and revise the report, if needed.
• ENGINEER shall not proceed with Preliminary Design activities without obtaining
written approval by the CITY of the Conceptual Design Package.
DELIVERABLES
A. Conceptual Design Package
TASK 3. PRELIMINARY DESIGN (60 PERCENT).
Preliminary plans and specifications shall be submitted to CITY per the approved Project
Schedule.
ENGINEER will develop the preliminary design of the infrastructure as follows.
3.1. Development of Preliminary Design Drawings and Specifications shall include the
following:
Cover Shoat
• A Protect Control Sheet, showing all Control Points, used or set while gathering
data. Generally on a scale of not less than 1:400. The following information shall
be indicated for each Control Point: Identified (existing City Monument#8901, PK
Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an identified coordinate system,
and a referred bearing base. Z coordinate on City Datum only; descriptive location
(i.e. set in the centerline of the inlet in the South curb line of North Side Drive at the
East end of radius at the Southeast corner of North Side Drive and North Main
Street).
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 4 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CITY PROJECT NO.:02111
• Overall project easement layout sheet(s) with property owner information.
• Overall project water and/or sanitary sewer layout sheets. The water layout sheet
shall identify the proposed water main improvement/existing water mains in the
vicinity and all water appurtenances along with pressure plane boundaries, water
tanks, pump stations, valves, and fire hydrants. The sewer layout sheet shall
identify the proposed sewer main improvement/existing sewer mains and all
sewer appurtenances in the vicinity.
• Overall water and/or sanitary sewer abandonment sheet.
• Coordinates on all P.C.'s, P.T.'s, P.I.'s, manholes, valves, mainline fittings, etc.,
in the same coordinate system as the Control Points.
• Bench marks per 1,000 ft of plan/profile sheet—two or more.
• Bearings given on all proposed centerlines, or baselines.
• Station equations relating utilities to paving, when appropriate.
• Plan and profile sheets which show the following: proposed water and/or sanitary
sewer plan/profile and recommended pipe size, fire hydrants, water service lines
and meter boxes, gate valves, isolation valves, manholes, existing meter
numbers and sizes that are to be replaced, existing sample locations, existing fire
line locations, existing utilities and utility easements, and all pertinent information
needed to construct the project. Legal description (Lot Nos., Block Nos., and
Addition Names) along with property ownership shall be provided on the plan
view.
• The ENGINEER shall make provisions for reconnecting all identifiable water and/or
wastewater service lines which connect directly to any main being replaced,
including replacement of existing service lines within City right-of-way or utility
easement. When the existing alignment of a water and sanitary sewer main or
lateral is changed, provisions will be made in the final plans and/or specifications
by the ENGINEER to relocate all service lines which are connected to the existing
main and connect said service lines to the relocated main.
• The following shall be applicable at all locations where it is necessary to relocate or
reroute the existing private sanitary sewer service line due to the abandonment or
realignment of the existing public sanitary sewer lateral or main: The CITY shall
furnish the ENGINEER with a sample format of how the sewer service line
reroute/relocation should be designed and submitted for construction. During
design survey, if a rod can be inserted through the cleanout to the bottom of the
service line, the ENGINEER will obtain the flow line'elevation and design the
service line prior to advertising the project for bid. If the service flow line
information cannot be obtained during design survey, the ENGINEER shall delay
the design of the sewer service line until after a Quality Level A Subsurface Utility
Engineering (SUE investigation has been performed). The Level A SUE will be
performed; (1) by the ENGINEER if included in the fee proposal; or(2) by the CITY
prior to bidding if the CITY determines that it is needed for satisfactory completion
of the design; or(3) by the Contractor after the project has been bid, by means of a
bid item to that effect. In all options, the ENGINEER shall propose appropriate de-
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 5 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CRY PROJECT NO.:02111
hole locations in the project and collect flow line elevation and other applicable
information of the sewer service line. The ENGINEER shall use this information to
provide the design for the sanitary sewer service line to be rerouted or relocated.
• Provide map showing location of new manhole construction at the end of existing
sewer segments, 90 degree bends, or tee connections. Site survey or specific
design plans for manhole construction is not included as part of the scope. The
contract documents shall specify that it is the Contractor's responsibility to
coordinate utility location, etc. manhole construction.
• The ENGINEER will prepare standard and special detail sheets for water line
installation and sewer rehabilitation or replacement that are not already included in
the D-section of the CITY's specifications. These may included connection details
between various parts of the project, tunneling details, boring and jacking details,
waterline relocations, details unique to the construction of the project, trenchless
details, and special service lateral reconnections.
3.2. Geotechnical Investigation
• Soil investigations, including field and laboratory tests, borings, related
engineering analysis and recommendations for determining soil conditions will be
made. In addition to the above investigations, borings and appropriate field and
laboratory analysis will be made at reasonable intervals along the project
alignment for the Contractor's use in determining soil conditions for preparing
bids and a Trench Safety Plan.
3.3. Constructability Review
• Prior to the 60 percent review meeting with the CITY, the ENGINEER shall
schedule and attend a project site visit with the CITY Project Manager and
Construction personnel to walk the project. The ENGINEER shall summarize the
CITY's comments from the field visit and submit this information to the CITY in
writing.
3.4. Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, private utilities and government agencies to determine the
approximate location of above and underground utilities, and other facilities
(current and future) that have an impact or influence on the project. ENGINEER
will design CITY facilities to avoid or minimize conflicts with existing utilities, and
where known and possible consider potential future utilities in designs.
• The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in Buzzsaw for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
3.5. Traffic Control Plan
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 6 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR d REPAINTING PROJECT
CITY PROJECT NO.:02111
• Overall proiect easement layout sheet(s) with property owner information.
• Overall project water and/or sanitary sewer layout sheets. The water layout sheet
shall identify the proposed water main improvement/existing water mains in the
vicinity and all water appurtenances along with pressure plane boundaries, water
tanks, pump stations, valves, and fire hydrants. The sewer layout sheet shall
identify the proposed sewer main improvement/existing sewer mains and all
sewer appurtenances in the vicinity.
• Overall water and/or sanitary sewer abandonment sheet.
• Coordinates on all P.C.'s, P.T.'s, P.I.'s, manholes, valves, mainline fittings, etc.,
in the same coordinate system as the Control Points.
• Bench marks per 1,000 ft of plan/profile sheet—two or more.
• Bearings given on all proposed centerlines, or baselines.
• Station equations relating utilities to paving, when appropriate.
• Plan and profile sheets which show the following: proposed water and/or sanitary
sewer plan/profile and recommended pipe size, fire hydrants, water service lines
and meter boxes, gate valves, isolation valves, manholes, existing meter
numbers and sizes that are to be replaced, existing sample locations, existing fire
line locations, existing utilities and utility easements, and all pertinent information
needed to construct the project. Legal description (Lot Nos., Block Nos., and
Addition Names) along with property ownership shall be provided on the plan
view.
• The ENGINEER shall make provisions for reconnecting all identifiable water and/or
wastewater service lines which connect directly to any main being replaced,
including replacement of existing service lines within City right-of-way or utility
easement. When the existing alignment of a water and sanitary sewer main or
lateral is changed, provisions will be made in the final plans and/or specifications
by the ENGINEER to relocate all service lines which are connected to the existing
main and connect said service lines to the relocated main.
• The following shall be applicable at all locations where it is necessary to relocate or
reroute the existing private sanitary sewer service line due to the abandonment or
realignment of the existing public sanitary sewer lateral or main: The CITY shall
furnish the ENGINEER with a sample format of how the sewer service line
reroute/relocation should be designed and submitted for construction. During
design survey, if a rod can be inserted through the cleanout to the bottom of the
service line, the ENGINEER will obtain the flow line elevation and design the
service line prior to advertising the project for bid. If the service flow line
information cannot be obtained during design survey, the ENGINEER shall delay
the design of the sewer service line until after a Quality Level A Subsurface Utility
Engineering (SUE investigation has been performed). The Level A SUE will be
performed; (1) by the ENGINEER if included in the fee proposal; or(2) by the CITY
prior to bidding if the CITY determines that it is needed for satisfactory completion
of the design; or(3) by the Contractor after the project has been bid, by means of a
bid item to that effect. In all options, the ENGINEER shall propose appropriate de-
City of Fort\AIo0h,Texas
Attachment A
PMO Release Date:08.1.2014
Page 5 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CITY PROJECT NO.:02111
hole locations in the project and collect flow line elevation and other applicable
information of the sewer service line. The ENGINEER shall use this information to
provide the design for the sanitary sewer service line to be rerouted or relocated.
• Provide map showing location of new manhole construction at the end of existing
sewer segments, 90 degree bends, or tee connections. Site survey or specific
design plans for manhole construction is not included as part of the scope. The
contract documents shall specify that it is the Contractor's responsibility to
coordinate utility location, etc. manhole construction.
• The ENGINEER will prepare standard and special detail sheets for water line
installation and sewer rehabilitation or replacement that are not already included in
the D-section of the CITY's specifications. These may included connection details
between various parts of the project, tunneling details, boring and jacking details,
waterline relocations, details unique to the construction of the project, trenchless
details, and special service lateral reconnections.
3.2. Geotechnical Investigation
• Soil investigations, including field and laboratory tests, borings, related
engineering analysis and recommendations for determining soil conditions will be
made. In addition to the above investigations, borings and appropriate field and
laboratory analysis will be made at reasonable intervals along the project
alignment for the Contractor's use in determining soil conditions for preparing
bids and a Trench Safety Plan.
3.3. Constructability Review
• Prior to the 60 percent review meeting with the CITY, the ENGINEER shall
schedule and attend a project site visit with the CITY Project Manager and
Construction personnel to walk the project. The ENGINEER shall summarize the
CITY's comments from the field visit and submit this information to the CITY in
writing.
3.4. Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, private utilities and government agencies to determine the
approximate location of above and underground utilities, and other facilities
(current and future) that have an impact or influence on the project. ENGINEER
will design CITY facilities to avoid or minimize conflicts with existing utilities, and
where known and possible consider potential future utilities in designs.
• The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in Buzzsaw for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
3.5. Traffic Control Plan
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 6 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CITY PROJECT NO.:02111
• Develop a traffic control plan utilizing standard traffic reroute configurations
posted as "Typicals" on the CITY's Buzzsaw website. The typicals need not be
sealed individually, if included in the sealed contract documents.
• Develop supplemental traffic control drawings as needed for review and approval
by the Traffic Division of the Transportation and Public Works Department.
These drawings shall be sealed by a professional engineer registered in the
State of Texas.
ASSUMPTIONS
_0_ public meeting(s) will be conducted or attended during the preliminary
design phase.
• _0_ borings at an average bore depth of_NA feet each will be provided.
• Traffic Control "Typicals" will be utilized to the extent possible. It is assumed an
additional 0_project specific traffic control sheets will be developed for
• _3_ sets of 11x17 size plans will be delivered for the
Constructability Review.
• _3_ sets of 11x17 size plans will be delivered for the Preliminary
Design (60% design).
• _3 sets of specifications will be delivered for the Preliminary Design (60%
design).
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in Buzzsaw.
• The CITY's front end and technical specifications will be used. The ENGINEER
shall supplement the technical specifications if needed.
• 3 sets of 11x17 size drawings will be delivered for Utility Clearance.
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design plans.
DELIVERABLES
A. Preliminary Design drawings and specifications
B. Utility Clearance drawings
C. Traffic Control Plan
D. Storm Water Pollution Prevention Plan
E. Estimates of probable construction cost
F. Data Base listing names and addresses of residents and businesses affected by
the project.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 7 of 17
ATTACKMENTA
DESIGN SERVICES FOR
CAYLOR SMG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CrrY PROJECT NO.:02111
TASK 4. FINAL DESIGN (90 PERCENT) AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT).
Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows:
• For projects that disturb an area greater than one (1) acre, the Contractor will be
responsible for preparing and submitting the Storm Water Pollution Prevention Plan
(SWPPP) with appropriate regulatory agencies. The Engineer will prepare the iSWM
Construction Plan according to the current CITY iSWM Criteria Manual for Site
Development and Construction which will be incorporated into the SWPPP by the
contractor.
• Draft Final plans (90%) and specifications shall be submitted to CITY per the approved
Project Schedule.
• Following a 90% construction plan review meeting with the CITY, the ENGINEER shall
submit Construction Documents (100%)to the CITY per the approved Project Schedule.
Each plan sheet shall be stamped, dated, and signed by the ENGINEER registered in
State of Texas.
• The ENGINEER shall submit a final design estimate of probable construction cost with
both the 90% and 100% design packages. This estimate shall use ONLY standard CITY
bid items.
ASSUMPTIONS
• _3 sets of_11 x17 size drawings and sets of size drawings
and 3_specifications will be delivered for the 90% Design package.
• A DWF file for the 90% Design will be created from design CAD drawings and will be
uploaded to the project folder in Buzzsaw.
• 3 sets of_11 x17_size drawings and_3 specifications will be delivered for
the 100% Design package.
• A DWF file for the 100% Design will be created from design CAD drawings and will be
uploaded to the project folder in Buzzsaw.
DELIVERABLES
A. 90% construction plans and specifications.
B. 100% construction plans and specifications.
C. Detailed estimates of probable construction costs including summaries of bid items and
quantities using the CITY's standard bid items and format.
D. Original cover mylar for the signatures of authorized CITY officials.
TASK 5. BID PHASE SERVICES.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 8 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CITY PROJECT NO.:02111
ENGINEER will support the bid phase of the project as follows.
5.1. Bid Support
• The ENGINEER shall upload all plans and contract documents onto Buzzsaw for
access to potential bidders.
• Contract documents shall be uploaded in a .xIs file.
• Unit Price Proposal documents are to be created utilizing CFW Bidtools only
and combined in a specified spreadsheet workbook, Bid Proposal Worksheet
Template, and will be populated and configured so that all pages are
complete and the Summary Worksheet(s) in the workbook detail and
automatically summarize the totals from the inserted Unit Price Proposal
document worksheets.
• Plan Sets are to be uploaded to Buzzsaw in two formats, .pdf and .dwf files.
The .pdf will consist of one file of the entire plan set. The .dwf will consist of
individual files, one for each plan sheet, and will be numbered and named in
a manner similar to that of the plan set index.
• The ENGINEER shall sell contract documents and maintain a plan holders list on
Buzzsaw from documents sold and from Contractor's uploaded Plan Holder
Registrations in Buzzsaw.
• The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and requests
and the response thereto. The log shall be housed and maintained in the
project's Buzzsaw folder titled Request for Information. The ENGINEER will
provide technical interpretation of the contract bid documents and will prepare
proposed responses to all bidders questions and requests, in the form of
addenda. The ENGINEER shall upload all approved addenda onto Buzzsaw and
mail addenda to all plan holders.
• Attend the prebid conference in support of the CITY.
• Assist the CITY in determining the qualifications and acceptability of prospective
contractors, subcontractors, and suppliers.
• When substitution prior to award of contracts is allowed in the contract
documents, the ENGINEER will advise the CITY as to the acceptability of
alternate materials and equipment proposed by bidders.
• Attend the bid opening in support of the CITY.
• Tabulate and review all bids received for the construction project, assist the CITY
in evaluating bids, and recommend award of the contract. A copy of the Bid
Tabulation and the CFW Data Spreadsheet created utilizing CFW Bidtools only
are to be uploaded into the project's Bid Results folder on Buzzsaw.
• Incorporate all addenda into the contract documents and issue conformed sets.
5.2 Final Design Drawings
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 9 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR SMG GROUND STORAGE TANK REPAIR 3 REPAINTING PROJECT
CITY PROJECT NO.:02111
1) Final Design Drawings shall be submitted in both Adobe Acrobat PDF format
(version 6.0 or higher) format and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
the Water plan set. Each PDF and DWF file shall be created from the original
CAD drawing files and shall contain all associated sheets of the particular plan
set. Singular PDF and DWF files for each sheet of a plan set will not be
accepted. PDF and DWF files shall conform to naming conventions as follows:
I. TPW file name example — "W-1956—org47.pdf' where "W-1956" is the
assigned file number obtained from the CITY, "_org" designating the file is
of an original plan set, "47" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example — "X-35667—org36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, 1136" shall be the total number
of sheets in this file.
Example: X-12755_org18.pdf
Both PDF and DWF files shall be uploaded to the project's Final Drawing folder in
Buzzsaw.
2) In addition to the PDF and DWF files, the ENGINEER shall submit each plan sheet
as an individual DWG file with all reference files integrated into the sheet. If the
plans were prepared in DGN format, they shall be converted to DWG prior to
uploading. The naming convention to be used for the DWG files shall be as
follows:
I. TPW files shall use the W number as for PDF and DWF files, but shall
include the sheet number in the name — "W-1956_SHT01.dwg", "W-
1956_SHT02.dwg", etc.
II. Water and Sewer file names shall use the X number as for PDF and
DWF files, but shall include the sheet number in the name — "X-
12155_SHT01.dwg", "X-12755_SHT02.dwg", etc.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number(817) 392-8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 10 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR 8 REPAINTING PROJECT
CITY PROJECT NO.:02111
ASSUMPTIONS
• The project will be bid only once and awarded to one contractor.
• _15_ sets of construction documents will be sold to and made available on
Buzzsaw for plan holders and/or given to plan viewing rooms.
• _3 sets of_11x17 size and sets of size drawings
plans and _3_specifications (conformed, if applicable) will be delivered to the
CITY.
• PDF, DWF and DWG files will be uploaded to Buzzsaw.
DELIVERABLES
A. Addenda
B. Bid tabulations
C. CFW Data Spreadsheet
D. Recommendation of award
E. Construction documents (conformed, if applicable)
TASK 6. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
6.1 Construction Support
• The ENGINEER shall attend the preconstruction conference.
• After the pre-construction conference, the ENGINEER shall provide project
exhibits and attend public meeting to help explain the proposed project to
residents. The CITY shall select a suitable location and mail the invitation letters
to the affected customers.
• The ENGINEER shall visit the project site at requested intervals as construction
proceeds to observe and report on progress.
• As requested by the CITY, the ENGINEER shall provide necessary interpretations
and clarifications of contract documents, review change orders, and make
recommendations as to the acceptability of the work.
The ENGINEER shall attend the "Final" project walk through and assist with preparation of
final punch list
6.2 Record Drawings
• The ENGINEER shall prepare Record Drawings from information provided by
the CITY depicting any changes made to the Final Drawings during construction.
The following information shall be provided by the CITY,
• As-Built Survey
• Red-Line Markups from Contractor
City of Fort Worth,Texas
Attachment A
PMO Release Date.08.1.2014
Page 11 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR 8 REPAINTING PROJECT
CITY PROJECT NO.:02111
• Red-Line Markups from City Inspector
• Copies of Approved Change Orders
• Approved Substitutions
• The ENGINEER shall modify the Final Drawings electronically and shall place a
stamp on the plans indicating that they represent Record Drawings of the project
as constructed. The stamp shall be signed and dated by the ENGINEER and
shall be placed on each plan sheet, whether there are any revisions on the sheet
or not. Each sheet shall clearly indicate all changes which apply to that sheet by
clouding and numbering, or other suitable means.
• The following disclaimer shall be included with the Record Drawing stamp:
o These Record Drawings were prepared using information provided by
others and represent the as constructed conditions to the extent that
documented changes were provided for recording. The ENGINEER
assumes no liability for undocumented changes and certifies only that the
documented changes are accurately depicted on these drawings.
• The ENGINEER shall submit a set of sealed Final Drawings, modified and
stamped as Record Drawings, on mylar for record storage. The ENGINEER may
keep copies of the information provided by the CITY for their files, but all original
red-lined drawings shall be returned to the CITY with the mylars.
2) Record Drawings shall also be submitted in both Adobe Acrobat PDF format
(version 6.0 or higher)format and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
the Water plan set. Each PDF and DWF file shall contain all associated sheets
of the particular plan set. Singular PDF and DWF files for each sheet of a
plan set will not be accepted. PDF and DWF files shall conform to naming
conventions as follows:
I. TPW file name example — "W-1956_rec47.pdf' where "W-1956" is the
assigned file number obtained from the CITY, "_rec" designating the file is
of a record drawing plan set, "47" shall be the total number of sheets in this
file.
Example: W-0053_rec3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example — "X-35667_rec36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_rec"
designating the file is of a record drawing plan set, "36" shall be the total
number of sheets in this file.
Example: X-12755_rec18.pdf
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 12 of 17
ATTACHMENTA
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CITY PROJECT NO.:02111
Both PDF and DWF files shall be uploaded to the project's Record Drawings folder
in Buzzsaw.
ASSUMPTIONS
• RFI's are assumed.
• Change Orders are assumed
• One copy of full size (22"x34") mylars will be delivered to the CITY.
DELIVERABLES
A. Public meeting exhibits
B. Response to Contractor's Request for Information
C. Review of Change Orders
D. Review of shop drawings
E. Final Punch List items
F. Record Drawings on Mylar
TASK 7. ROW/EASEMENT SERVICES.
ENGINEER will support and perform activities related to ROW and land as outlined below,
per scoping direction and guidance from the CITY's Project Manager.
7.1. Right-of-Way Research
• The ENGINEER shall determine rights-of-way, easements needs for construction of the
project. Required temporary and permanent easements will be identified based on available
information and recommendations will be made for approval by the CITY.
7.2. Right-of-Way/Easement Preparation and Submittal.
• The ENGINEER shall prepare documents to be used to obtain right-of-way and
permanent and/or temporary easements required to construct the improvements.
• The ENGINEER shall submit the right-of-way and/or easement documents to CITY PM
for real property acquisition
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's Buzzsaw site.
7.3. Temporary Right of Entry Preparation and Submittal
• Prior to construction, the ENGINEER shall prepare and submit Temporary Right of Entry
documents for landowners to CITY PM for real property acquisition. It is assumed that letters
will only be required for land owners adjacent to temporary construction easements or who
are directly affected by the project and no easement is required to enter their property.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 13 of 17
ATTACHMENTA
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CITY PROJECT NO.:02111
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's Buzzsaw site.
ASSUMPTIONS
• _0 Easements or right-of-way documents will be necessary.
• 0 Temporary right-of-entry documents will be necessary.
• Right-of-Way research and mapping includes review of property/right-of-way records
based on current internet based Tarrant Appraisal District (TAD) information available at the
start of the project and available on-ground property information (i.e. iron rods, fences,
stakes, etc.). It does not include effort for chain of title research, parent track research,
additional research for easements not included in the TAD, right-of-way takings, easement
vacations and abandonments, right-of-way vacations, and street closures.
DELIVERABLES
A. Easement exhibits and meets and bounds provided on CITY forms.
B. Temporary Right of Entry Letters
TASK 8. SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES.
ENGINEER will provide survey support as follows.
8.1. Design Survey
• ENGINEER will perform field surveys to collect horizontal and vertical elevations and
other information needed by ENGINEER in design and preparation of plans for the project.
Information gathered during the survey shall include topographic data, elevations of all
sanitary and adjacent storm sewers, rim/invert elevations, location of buried utilities,
structures, trees (measure caliper, identify overall canopy, and have qualified arborist
identify species of trees), and other features relevant to the final plan sheets. Existing
drainage at intersections will be verified by field surveys. Spot elevations will be shown on
intersection layouts with cross slope to fit intersecting grade lines.
• The minimum survey information to be provided on the plans shall include the following:
— A Project Control Sheet, showing ALL Control Points, used or set while gathering data.
Generally on a scale of not less than 1:400:
— The following information about each Control Point;
a. Identified (Existing. CITY Monument#8901, PK Nail, 5/8" Iron Rod)
b. X, Y and Z Coordinates, in an identified coordinate system, and a referred bearing
base. Z coordinate on CITY Datum only.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 14 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR&REPAINTING PROJECT
CITY PROJECT NO.:02111
C. Descriptive Location (Ex. Set in the centerline of the inlet in the South curb line of
North Side Drive at the East end of radius at the Southeast corner of North Side Drive and
North Main Street).
— Coordinates on all P.C.'s, P.T.'s, P.I.'s, Manholes, Valves, etc., in the same coordinate
system, as the Control.
— No less than two horizontal bench marks, per line or location.
— Bearings given on all proposed centerlines, or baselines.
— Station equations relating utilities to paving, when appropriate.
8.2. Temporary Right of Entry Preparation and Submittal
• Prior to entering property, the ENGINEER shall prepare and submit Temporary Right of
Entry for landowners to CITY PM.
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's Buzzsaw site.
ASSUMPTIONS
• Topographic survey at intersection will include no more than 100 ft. in each direction.
• _0_ survey documents will be necessary.
DELIVERABLES
A. Copies of field survey data and notes signed and sealed by a licensed surveyor.
B. Drawing of the project layout with dimensions and coordinate list.
TASK 9. PLAN SUBMITTAL CHECKLISTS
Engineer shall complete and submit Plan Submittal Checklists in accordance with the
following table:
PLAN SUBMITTAL CHECKLIST REQUIREMENTS
Traffic Traffic Traffic
Street Water Control Control Control
Attachment"A" Signal Engineering
Traffic Storm Storm Lights /Sewer Traffic 30% 60% 90%
Water Water (Submit (Submit
Type (Submit All (Submit All
30% 60% All @ All @
° 60%
@ 30/°) 30% 60%) Required for all work in City
ROW
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 15 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR 8 REPAINTING PROJECT
CITY PROJECT NO.:02111
Street X X X X X. X X X X
Storm Water X X X X X
Water/Sewer X X X X
*If included in street project
ASSUMPTIONS
DELIVERABLES
A.
B.
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services described in
the tasks above. However, ENGINEER can provide these services, if needed, upon the
CITY's written request. Any additional amounts paid to the ENGINEER as a result of any
material change to the Scope of the Project shall be agreed upon in writing by both parties
before the services are performed. These additional services include the following:
• Negotiation of easements or property acquisition including temporary right-of-
entries.
Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre-qualification, bid protests, bid rejection and
re-bidding of the contract for construction.
• Construction management and inspection services
• Periodic site visits during construction phase
Design phase public meetings
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 16 of 17
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK REPAIR 8 REPAINTING PROJECT
CITY PROJECT NO.:02111
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of
God.
• Services related to warranty claims, enforcement and inspection after final
completion.
• Services related to submitting for permits (ie.TxDOT, railroad, etc...)
• Services related to Subsurface Utility Engineering Levels A, B, C or D
• Services related to Survey Construction Staking
• Services related to acquiring real property including but not limited to easements,
right-of-way, and/or temporary right-of-entries.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Construction Shop drawing review, samples and other submittals submitted by the
contractor.
• Performance of miscellaneous and supplemental services related to the project as
requested by the CITY.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014
Page 17 of 17
ATTACHMENT B
COMPENSATION
Design Services for
Caylor 5MG Ground Storage Tank Repair& Repainting Project
City Project No. 02111
Lump Sum Project
I. Compensation
A. The ENGINEER shall be compensated a total lump sum fee of $110,000.00 as
summarized in Exhibit B-1 — Engineer Invoice and Section IV— Summary of Total
Project Fees. The total lump sum fee shall be considered full compensation for
the services described in Attachment A, including all labor materials, supplies,
and equipment necessary to deliver the services.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. Partial payment shall be made to the ENGINEER monthly upon City's approval of
an invoice prepared and submitted by the ENGINEER in the format and including
content as presented in Exhibit B-1, Progress Reports as required in item III. of
this Attachment B, and Schedule as required in Attachment D to this Agreement.
B. The estimated current physical percent complete as required on the invoice shall
be calculated from the progress schedule as required in Attachment D to this
Standard Agreement and according to the current version of the City of Fort
Worth's Schedule Guidance Document.
C. The cumulative sum of such monthly partial fee payments shall not exceed the
total current project budget including all approved Amendments.
D. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Water Department monthly progress reports and schedules in the format
required by the City.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 1 of 3
B-1
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Firm Primary Responsibility Fee Amount %
Prime Consultant
Dunham Engineering Engineer of Record $96,800 88%
Proposed MBE/SBE Sub-Consultants
EJES Civil Engineering/Project Mgmt. $13,200 12%
Non-MBE/SBE Consultants
TOTAL $_$110,000 100%
Project Number & Name Total Fee MBE/SBE Fee MBE/SBE
Caylor 5MG GST Repair & Repainting $110,000 $13,200 12%
Project. Project No. 02111
City MBE/SBE Goal = _12_% Consultant Committed Goal =_12_%
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 2 of 3
B-2
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across work types and work phases.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 3 of 3
B-3
00 00 0 °o °o
0 0 0 0
C a o_o 0 0 0 0°
C U
C N 0 0 0
E m
m m
c d
v
0
> >
U �
O 0
h C >O
v — d
L w
Y O
° a �
° aI
0
a c y a
o `(D E
a 0
a a U
v
i D Q
� D �
(Q n Q1
E C
a m CL O
E o E E
C v m L) Q
c Y
m m
E N N o 0 0 0 J00--
C 0 0 0 0 y 0 0 0 0 d
d U X X CD 10 N N N a
CD 0
v o_ o [n E O
z' a o Q U
N N
o �j'j F rn rn C Q1
c a m d m
v .o o s E
m n U U
m E v
E Q d
CL
N ° w cn rn
° a E N v
0N 0 0 N °o v°
0
L O 0 v0
0 0 0 O 0 y 0
O m
o
F Q)
c N N
N U1
`v L aI `
v E m E o
.Y EC)m A m '++
IL C d O r LL CL
(6
~ N d
a) 7
� O d
7 C
C O d o 0-
d m
E (D C
rn u f9 a F-
a
aLr) v E LL L) N
w
fA
V O i m E o ~
� o r w' aiiv
U) y 3k
C # ai
1° a
O � � ?�
•LO ++ N Z C G C Ql 10 N n O N to
LO u�F .w N O. +, C❑.0+0 y a a a a a a
d y w� E m0_
O O _T _T C C T E❑ O Q1 Y Y Y Y Y Y
EL 0- U U U U>EL Lt -5 013: 3:1
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
Caylor 5MG Ground Storage Tank Repair & Repainting Project
City Project No. 02111
<List any changes to the Standard Agreement>
NONE
City of Fort Worth,Texas
Attachment C
PMO Release Date:05.19.2010
Page IofI
Consulting Contract Schedule Specifications FORT WORTH
City of Fort Worth Capital Improvement Program (-
Attachment D — Project Schedule
This PRO ECT requires a Tier << >> schedule as defined herein and in the City's Schedule
Guidance Document.
D1. CONSULTING SERVICES SCHEDULE DEVELOPMENT: The CONSULTANT shall
prepare schedules for consulting services that meet the requirements described in this
specification, showing by Critical Path Method (CPM) the planned sequence and timing of
the Work associated with the Agreement. All submittals shall be submitted in PDF format,
and schedule files shall also be submitted in native file format (i.e. file formats associated
with the scheduling software). The approved scheduling software systems for creating the
schedule files are:
— Primavera (Version 6.1 or later or approved by CITY)
— Primavera Contractor (Version 6.1 or later or approved by CITY)
— Microsoft Project (Version 2003/2007 or later or approved by CITY)(PHASING OUT)
D2. BASELINE CONSULTING SERVICES SCHEDULE: Following notice-to-proceed, the
CONSULTANT shall develop, submit and review the draft detailed baseline consulting
services schedule with the CITY to demonstrate the CONSULTANT's understanding of the
Agreement requirements and approach for performing the work. The CONSULTANT will
prepare the final detailed baseline consulting services schedule based on CITY comments, if
any, and submit to the CITY no later than the submittal of the first project invoice.
The following guidelines shall be adhered to in preparing the baseline schedule, and as
described in further detail in the CITY's Schedule Guidance Document.
a. The scope shall be subdivided by work breakdown structure (WBS) representing the
tasks,subtasks, and activities associated with delivering the work.
b. The schedule shall accurately describe the major work activities, key milestones, and
dependencies/relationships as appropriate to the work.
c. The schedule should include appropriate meetings, review periods, critical decision
points,including third party utility dependencies and reviewing agencies.
D3. PROGRESS CONSULTING SERVICES SCHEDULE: The CONSULTANT shall prepare
and submit monthly to the CITY for approval the updated schedule in accordance with D1
and D2 and the CITY's Schedule Guidance Document inclusive. As the Work progresses,
the CONSULTANT shall enter into the schedule and record actual progress as described in
the CITY's Schedule Guidance Document.
The updated schedule submittal shall also include a concise schedule narrative that
highlights the following,if appropriate and applicable:
• Changes in the critical path,
• Expected schedule changes,
• Potential delays,
• Opportunities to expedite the schedule,
• Coordination issues the CITY should be aware of or can assist with,
City of Fort Worth,Texas
Attachment D
PMO Release Date:02.15.2011
Page 1 of 2
Other schedule-related issues that the CONSULTANT wishes to communicate to the
CITY.
D4. PERFORMANCE AND CONSULTING SERVICES SCHEDULE: If the work
accomplished falls behind that scheduled due to factors within the CONSULTANT's
control, the CONSULTANT shall take such action as necessary to improve the progress of
the Work. In addition, the CITY may require the CONSULTANT to submit a revised
schedule demonstrating the proposed plan to make up the delay in schedule progress and
to ensure completion of the Work within the allotted Agreement time.
D5. SCHEDULE TIERS SPECIAL INSTRUCTIONS:
The requirements for the schedule are determined based on the nature and needs of the
project. The schedule tier for this project is stated at the top of this document.
CONSULTANT shall submit each schedule relying on the CrIY's current Schedule
Guidance Document.
D6. SCHEDULE SUBMITTAL AND PAYMENT:
As stated in III.A.(1). of the Agreement, CONSULTANT shall provide the information
required by Attachment D. CONSULTANT's monthly invoices will not be accepted and
processed for payment without monthly schedule updates that are submitted in the time
and manner required by Attachment D and the CITY's current Schedule Guidance
Document.
City of Fort Worth,Texas
Attachment D
PMO Release Date:02.15.2011
Page 2 of 2
6LOZ-unf
6LOZ-ALA
6LOZ-jdy
-- -
6LOZ-JeW
6LOZ-qa�
6LOZ-uef
9 LOZ-094--
9LOZ-noN -
8 LOZ-70O
9LOZ-daS -
9 L OZ-6ny
9 LOZ-inf
9LOZ-unf
-- 9LOZ-ALW
--9LOZ-ALA—
9LOZ-qa�
9LOZ-uef
- LLOZ-oaa�
LLOZ-AON
LLOZ-;00
LLOZ-daS
LLOZ-6ny—
LLOZ-Inf
LLOZ-unr
LLOZ-ALA
L LOZ-ady
LLOZ-JLW
LLOZ-qa_A-
LLOZ-uef
9 L OZ-094
9LOZ-noN T
-9LOZ-loOJ '��®■
9LOZ-daS
- 9LOZ
,9LOZYInf
m
C
(D 0 6uiumway step Lo 0 C, °� ti v
m
N (5 a;aldwoo s�(e4 0 0 0 0 0 0 0 0 0 0 0 0
7 'E
s(e4 6uIiloM u� N = W N u� m
�i
m a;aldwoo 0 0 0 0 0 0 0 0 0 0 0
0 `'o 0 000 0 0 0000
y
(s(e4)uop; np
0
~ (D co co CD co co CD w co N co t•
cn
N N c- C7 f`7 N O N
C 10 m m a0 m O O O V c� t
O W 7 0 0 -° N N C -0 O D
G F > F F F
(� i >
L LL1 CD CD CD CO CD CO c0 co co to co
N N to N O� N N Imo.
y: ;�� � �� a a as
� U-LL 0 0 0 0 7
Q
r 7 .3
w � C O L
CL F-
0
0
m
I°r ° m m m
C
O m ° o a _
axi JD v, m E2
N Y rn U 'C 6 o C
t y a U O CU
° ~ y c a> rnQm E ¢� 2
�i c ai"E U c v .� E m E ti v n
:Ej° �wc� aic �c°� o°t.i �c�
O LL
>,o
m
U U c`? — N h C N
.- N N N N N CI O c�i
a F3 w� 11 � •� " .
•' • �'°
1300 N CaP r Foci
yp�P
LUMP
1 UV • • • 11 • • •.•
,a
r it w
ch
_ � w
1300 N Caylor rid +'
2�
-
` «��
-
. .
OMG Caylor GST lo . - 1300 N.Caylor . ^
Page 2 of 2
kM&C Review Page 1 of 3
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FoRTIR1111TH
COUNCIL ACTION: Approved on 6/21/2016 - Resolution No. 4638-06-2016
DATE: 6/21/2016 REFERENCE **C-27782 LOG NAME: 60REPAINTING OF 5MG
NO.: CAYLOR GST
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of an Engineering Agreement with Dunham Engineering, Inc., in the
Amount of$110,000.00 for Engineering Services for the Repair and Repainting of the Five
Million Gallon Caylor Ground Storage Tank and Adopt Reimbursement Resolution
(COUNCIL DISTRICT 7)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of an Engineering Agreement with Dunham Engineering, Inc., in the amount
of$110,000.00 for Engineering Services for repair and repainting of the Five Million Gallon Caylor
Ground Storage Tank; and
2. Adopt the attached resolution expressing official Intent to Reimburse expenditures with proceeds
of future debt for the repainting of the Five Million Gallon Caylor Ground Storage Tank.
DISCUSSION:
The Caylor Ground Storage Tank, located at 1300 North Caylor Road, was built in 1988 by Tank
Builders, Inc., and was last repainted in 1996.
In December 2015, a Request for Qualifications (RFQ) was issued for several Water Department
Projects including the potable water Storage Tank Rehabilitation Project. In January 2016 a total of
six proposals were received from engineering consultants for the tank rehabilitation project. A staff
selection committee recommended Dunham Engineering, Inc., for the Five Million Gallon (MG) Caylor
Ground Storage Tank Repaint and Rehabilitation Project.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer
Fund. Available cash within the Water and Sewer portfolio and the City's portfolio along with the
appropriation authority authorized under the Direct Purchase Note (DPN) Program will be used to
provide interim financing for this project until debt is issued. To the extent resources other than the
Water and Sewer portfolio are used to provide interim financing, the Water and Sewer Fund will be
charged interest that is equivalent to the overall rate of return being earned by the City portfolio
(currently approximately one-percent annually). Should the City's portfolio not support the liquidity
needed to provide an interim short-term financing source, another funding source will be required,
which could mean issuance of securities under the DPN Program or earlier issuance of Water and
Sewer revenue bonds than is currently planned. Once debt associated with this project is sold, bond
proceeds will be used to reimburse the Water and Sewer portfolio and the City's portfolio in
accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2016-2020 Five-Year Capital
Improvement Plan on February 2, 2016 (M&C G-18662). This City Council adopted plan includes this
specific project, with funding identified through the DPN Program to be reimbursed with future
revenue bonds. In accordance with the provisions of the Financial Management Policy Statements,
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=22365&councildate=6/21/2016 7/7/2016
,,M&C Review Page 2 of 3
Staff anticipates presenting revenue-supported debt issuances to the City Council for consideration
within the next three years. This debt must be issued within approximately three years to provide
reimbursement for these expenses. If that does not occur, the costs will no longer be reimbursable
by issuing tax-exempt debt and the funding source will have to be made whole through other
budgetary methods. Adoption of this resolution does not obligate the City to sell bonds, but
preserves the ability to reimburse the City from tax-exempt bond proceeds.
The Engineering Agreement being approved is only a portion of the project that includes project
management, inspection, contingencies and construction cost with an overall budget for this project
of$1,175,000.00.
Engineering services are anticipated to commence in June 2016 and estimated to be complete by
October 2016, with construction starting in December of 2016 to be complete by the end of April
2017.
In addition to the Engineering Agreement funding, $65,000.00 is needed for inspection, project
management and project contingencies. This project will have no impact on the Water Department's
operating budget when complete.
M/WBE OFFICE —Dunham Engineering, Inc., is in compliance with the City's BIDE Ordinance
by committing to 12 percent SBE participation. The City's goal on this project is 12 per ent.
This project is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that the appropriation is available as directed by M&C -18375 in
the Water/Sewer DPN Fund for the Repainting of the Five MG Caylor Ground Storage roject.
Appropriations for the Repainting of the Five MG Caylor Ground Storage by fund will consist of the
following:
FUND Existing Additional Future Project
Appropriations Appropriations Appropriations Total*
Water/Sewer
DPN Fund $175,000.00 $0.00 $ 0.00 $ 175,000.00
56005
Future
Revenue $ 0.00 $0.00 $1,000,000.00 $1,000,000.00
Bond
Project $175 000.00 $1 000 000.00 $1,175 000.00
Total $0.00 '
* Numbers rounded for presentation purposes.
TO
Fund I Department Account Project I Program Activity I Budget Reference# Amount
ID ID Year Chartfield 2
FROM
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year Chartfield 2
56005 0600430 5330500 100071 001830 2016 $110,000.0
Submitted for City Manager's Office by: Jay Chapa (5804)
http://apps.cfwnet.org/council_packet/mc review.asp?1D=22365&councildate=6/21/2016 7/7/2016
M&C Review Page 3 of 3
Originating Department Head: John Carman (8246)
Additional Information Contact: Seiavash Mir(8404)
ATTACHMENTS
60repainting Caylor GST 100071 REIMB RESOLUTION.doc
60REPAINTING OF 5MG CAYLOR GST Form 1295.pdf
60REPAINTING OF 5MG CAYLOR GST MAP.pdf
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=22365&councildate=6/21/2016 7/7/2016