WHEREAS, The City of Fort Worth and Komatsu Architects, Inc. (Architect) made and entered into City Secretary Contract No.
23886(The Contract)which was authorized by the City Council by M&C C-16736,the 21st day of April, 1998;and
WHEREAS,Amendment No. 1 was incorporated earlier to provide for preliminary design of the Medical Incubator area,and
WHEREAS,Amendment No. 2 was incorporated earlier to provide for the development of a concept plan for the renovation of the
Elementary School Building,and
WHEREAS, further amendment is necessary to reimburse the Architect for the design of the renovations to the Gymnasium
Building to house the proposed MedTech Center
NOW THEREFORE, City and Architect, acting herein by and through their duly authorized representatives, enter into the following
agreement which amends the Contract:
SECTION I SERVICES OF THE ARCHITECT
Add the following paragraph to the general scope of work:
"Provide programming, design and construction administration services for renovation of the Gymnasium Building to serve as a
MedTech Center. A detailed Scope of Services and Project Schedule (Attachment 1) is made a part of this Amendment. The
construction budget for the MedTech Center and Elementary School Stabilization is$2,076,500 plus contingencies as shown in the
Project Budget(Attachment 2)."
SECTION V COMPENSATION TO ARCHITECT
Add Paragraph 5.1.6 as follows:
"5.1.6 Programming,design and construction management services for the Fort Worth MedTech Center and stabilization of the
Elementary School by$241,915 fixed fee"
SECTION XII M/WBE GOALS
Add Paragraph 15.2 "The M/WBE Goal for work performed under his Amendment is 38%. The goal on the original Agreement
and earlier amendments remains 25%as set in the original Agreement."
All other provisions of this Contract which not expressly amended herein shall remain in full force and effect.
&
EXECUTED this the �th day of. 2000, in Fort Worth,Tarrant County,Te
By: By:
roaril omatsu,AIA, Pr ident Ramon Guajardo 1.110
matsu Architects, c. Assistant City Manager
Recommend Approval:
U 6Z�
Jan ke rogram Manager,CMO
By: APPROV FOR AND LEGALITY
irect ransportation and
4yecretary
Works By:
Assistant y Attorney
By: a—VwAl
_W
/QA 00IN
Contract Authorization
�- C>( CD
Date
MV ���` U'
Page 1 of 1 , C�"'J�r'I1? � �
FORT WORTH MED TECH CENTER
GUINN SCHOOL COMPLEX
A/E SERVICES SCOPE OF WORK
KOMATSU ARCHITECTURE
KA#0109.1.A
March 2, 2000
SUMMARY
The intent of this Phase 2 program is to address the former 1957 Gymnasium Building that is part
of the three remaining structures of the Guinn School, listed on National Register For Historic
Places in 1998. This program is using federal funds, and will be reviewed by the Texas
Historical Commission (THC) with final consultation by the Advisory Council On Historic
Preservation, for compliance with Section 106 of the National Historic Preservation Act
(NHPA), and if the city elects, it can be reviewed for qualification under the Historic Investment
Tax Credit (ITC) program. The Gymnasium program follows the Phase 1 Guinn School Junior
High School Building program development. The Elementary School Building Annex is to be
considered a separate package under this program for stabilization.
The general scope of work (SOW) includes the exterior modifications using an existing entrance
and following the master plan previously approved by the THC and local preservation review.
The exterior envelope rehabilitation includes a new roof and structural reconditioning or
replacement as may be required; appropriate repair or replacement of metal windows, and minor
repair of masonry. The interior adaptive use will take advantage of the interior volume of the
former gymnasium for a new mezzanine to create a two level series of research & development
(R&D) office cells or pods. A new structure creating two floors will be explored with the THC..
The former shop areas will be developed into special requirements cells that can be adapted on a
build to suit basis for additional utilities or ventilation.
The SOW for the Elementary School Annex is to provide exterior and structural stabilization of
the structure. This is anticipated to include: additional clean up and removal of debris or
collapsed structure; interim stabilization/bracing of walls; new appropriate roof and structure;
second floor structure; exterior stabilization and preservation of walls; weatherization of exterior
with rehabilitation and appropriate replacement of wood windows, doors, and other exterior
openings. No interior work, building systems work other than electrical power for work light and
smoke detection/intrusion alarm system is included at this time.
We have organized the required task efforts into three categories typically recognized in
professional standards for Pre-design,Basic Design, and Supplemental services. This identifies
the traditional service level and fee allocation as separate from the additional effort required in
this type of program defined in the Pre-Design and Supplemental Services categories.
j A0109\Contract\0109Fee000.228 -�
CITY OF FORT WORTH GUINN SCHOOL COMPLEX
FW MED TECH CENTER
FEBRUARY 28, 2000
PAGE 2
PRE DESIGN SERVICES
I. Existing Conditions Survey (update and complete prior reconnaissance)
H. Preliminary NHPA Section 106 Consultation & Coordination
III. Phasing & Demolition
BASIC SERVICES
IV. Design: FW Med Tech Center staff final planning session(s)
V. Construction Documentation
A. Documentation of base building and public common areas per City standard A/E
contract format reference to AIA B 141
B. 50% & 100% documentation submittals with cost estimates
C. MEP to document all "base building" systems; provide "tenant' HVAC
distribution, lighting, and other support needs per typical commercial standard or
base building standards established by FW Med Tech requirements; special use or
above base standard areas to be provided as a special engineering fee component
or as an additional service
SUPPLEMENTAL SERVICES
VI Final Section 106 Review, including coordination with the THC; presentation preparation
to City of Fort Worth Historical & Cultural Landmark Commission and Historic Fort
Worth, Inc. representing city wide preservation community, with the Tarrant County
Black Historical & Genealogical Society.
VII Tax Act Application - currently not requested by the city; should this be elected, services
required above the Section 106 review requirements, i.e. Parts 2, and 3 compliance
procedures and forms, would be provided as an additional service
VIII Space Planning & Interior Design Tasks -preliminary concept plans have been previously
developed; FW Med Tech Center has requested changes that have been addressed on a
pro bono basis; Design Development space planning and final interior design addressing
public areas and base "tenant' or"Med Tech" building standards will be developed;
hypothetical furniture layout plans will be illustrated; however, individual or customized
layouts are not included in this scope, but may be provided on an hourly or fixed fee as an
additional service to either the City or FW Med Tech Center
IX Construction Administration
J A0109\Contract\0109Fee000.228
CITY OF FORT WORTH GUINN SCHOOL COMPLEX
FW MED TECH CENTER
FEBRUARY 28, 2000
PAGE 3
A. Provide services per definitions referenced in the AIA B141 and standard City
contract, with conditions stated below
B. Construction Period for the purposes of providing A/E support services is
identified as ten (10) months; any extension of time or involvement not in the
Architect's control shall be provided on a monthly basis as additional services
C. Provide Request For Information (RFI) support and Shop Drawing Review w/two
reviews and rejections; subsequent submittal reviews and actions would then be
on an hourly basis
D. Site Observation Visits - to be provided in conjunction with one monthly progress
meeting and averaging three total visits per month, as appropriate to work
activities in accordance with AIA B141 definitions and City Contract; full time
site representation is not a part of this scope of work
E. MEP, Civil, and Structural Engineering visits at three milestone checks:
1. Foundation or footing placement; structural mezzanine placement; and as
the engineer of record may deem appropriate
2. Installation pre cover of utilities
3. Installation of MEP systems prior to ceiling closure or enclosure of
elements
4. Pre Final or Final punch list walk through
X. REIMBURSABLE EXPENSES
A. Fees for reviews, i.e. TDLR, THC, NPS, if required, and other federal, state, or
municipal fees, filings, etc
B. Reproduction
1. Progress Plots and Submittals for City and other reviews, presentations,
and information
2. Final Reproducible and Record Document Plots and Sets, i.e. reproducible
and other archival sets
3. Bid Set Printing of Documents and Specifications
4. Mail, Express Delivery, Courier Delivery, and Telecommunications for
reviews or information distribution to the City or its procedural
representatives
C. Record Document Set-produced from Contractor's field set indicating only those
items as recorded by the Contractor provided in electronic format. Cost of
reproduction for mylar or record set reproductions is not included but can be
provided as a direct cost to the City.
j:\0109\Contract\0109Fee000.228
Crr
`
z ` yv �o�-
SENT BY:KOHATSL ARCHITECTLRE 1 4-12- u , 2•01F.%1 KUNIA1JL AXLni1U-L1enc- u1i Q . �, •-
KROMATSUH
April 12, 2000
M5 Nancy Richardson
Architectural Services Division
City of Fort Worth
3409 Harley
Fort Worth, TX 76107
RE: Guinn MedTrch Design and Approval Schedule
KAI project No. 0109
Dear MS Richardson:
Listed below is our projected schedule for completion of construction documents for the
above program. As you are aware, the necessity to work by the direction and requirements
of the Texas Historical Commission and the National park Service make presenting a
definitive time schedule impossible. For the purpose of estimating our overall time
schedule, the THC may complete their review and comments in approximately six weeks,
and then forward the submittal on to the National Pork Service. The NPS may then take up
to an additional four weeks for their review and response. Therefore, we have not inserted
a time period for any outside agency, City of Fort Worth or Landmark Commission reviews
and responses. Time periods listed below in days represent normal work week days,
exclusive of weekends and holidays.
KAI receives approval of A/E proposal
10 days Revise concept Architectural floor plan and develop building section and
elevations according to phone comments from Brad Patterson
2 days Plot and print revised concept design for THC preliminary comments and
concurrently to City
Review Receive THC and City comments
15 days Adjust concept design plans to THC and City comments, confirm plan
layout and design with MedTech Tenant, and proceed to completion of
preliminary design
2 days Plot and print preliminary design for City and Fort Worth Historic, Cultural
and Landmark Commission review
Review Receive City and Commission review comments
50 days Continue Architectural development, begin Structural, Civil and MEP
construction documents to 50%completion
Concurrent Interim presentation to City and MedTech Tenant for interior finishes
2 days Plot and print 50% design for City and THC interim reviews
Review Receive City and THC review comments
550 ISAIIEY AVENUt SUIR 1(1"1• PURI WOR IH,ill 76107-1111 • 617132 1014 VOICE •617 479 7 F7-47.N-4 JAX
1 )� Q����
I, h
SENT °Y:KOXAT5U ARCH ITECTLRE : 4-12- 0 : 2:02PM :KOHATSL, ARCHITECTLRE- 817 871 8466-= 3; 3
April 12, 2000
Ms Nancy Richardson
Page 2
50 days Continue preparation of Architectural, Structural, Civil and MEP
construction documents to 95%
2 days Plot and print 95%design drawings and specifications for City and final
THC and NPS reviews and tax credit approval
Review Receive final City, THC and NPS Certification reviews and requirements
15 days Complete)00%Bid Package
3 days Plot and print for bid, TDLR occessobility review and building permit
30 days Bid Period
90 days Construction contract preparation and City Council approval
300 days Construction Period
Construction closeout and filing of Part 3 Tax Credit submittal
M)x4w
David McCord, AIA
Project Manager
File: 09sch000.412
QJ ' 'I��C►
Gry "1 � �M8 E),T
r
06/30/2000, 2:32 PM PROJECT BUDGET Page 1 of 2
GUINN CAMPUS
MEDTECH AND ELEMENTARY SCHOOL
DESCRIPTION Total Project Phase I Phase II Alt 1 Alt 2
June 30,2000 Business MedTech Site Improve Elementary
Assistance Complex School -
Center Stabilization
ALLOTMENT
COMMUNITY DEV,BLOCK GRANT(CDBG) 25,000.00 25,000.00
COMMUNITY DEV BLOCK GRANT(CDBG) 165,450.00 165,450.00
COMMUNITY DEV BLOCK GRANT(CDBG) 274,550.00 274,550.00
COMMUNITY DEV BLOCK GRANT(CDBG) 60,000.00 60,000.00
COMMUNITY DEV BLOCK GRANT(CDBG) 124,000.00 124,000.00
COMMUNITY DEV,BLOCK GRANT(CDBG) 200,000.00 200,000.00
COMMUNITY DEV BLOCK GRANT(CDBG) 125,000.00 125,000.00
COMMUNITY DEV BLOCK GRANT(CDBG) 50,000.00 50,000.00
TEXAS DEPT OF ECONOMIC DEV (EDA) 575,000.00 575,000.00
FEDERAL EDA GRANT 3,100,000.00 1,900,000.00 1,200,000
Other funds -
Tax Credits from BAG 558,000.00 558,000
Tax Credits Medtech(Medtech and Elem?) 328,000.00 328,000
Tax Credits Stabilization Elementary School ? -
TOTALALLOTMENT 5,585,000 4,057,000 1,200,000 328,000 -
CONSTRUCTION
Business Assistance Center -
Construction(R.J. Miller) 2,269,000 2,269,000
Change Order 1 6,878 6,878
Change Order 2 11,800 11,800
ARC Abatement 161,097 161,097
Medtech Center
Site Work(TPW breakout) - t
Parking 185,000 85,000 :100,000
Landscaping and circulation 165,500 158,000 ',7,500'
Medtech Building 1,437,000 1,437,000
Plywood windows covers(dropped est$9,000) - ~;«' delete
Elementary School Roof 55,500
Exterior Masonry Repair 17,500 pig 17,500
Structural Stabilization(TPW estimate) 50,000 50,000
Elementary School windows(TPW estimate) 166,000 �-466,000
Miscellenous 5,500 5,500
Construction 4,530,775 2,454,275 1,522,000 258,000 296,500
Contingency 328,223 120,573 152,200 25,800 29,650
SUBTOTAL CONSTRUCTION 4,858,998 2,574,848 1,674,200 283,800 326,150
CONTRACTUAL OVERHEAD
Design and Construction assist Business Assistance 299,550 299,550
Amendment 1 MedTech concept plan 12,000 12,000
Amendment 2 Elementary School Floorplan 5,000 5,000
Amendment 3 MedTech Center
Basic Design 158,235 106,750 ;;51;485
Construction Services 49,550 41,850
Survey existing conditions; 3,600 3,600
Verify Program 1,800 1,800
Abatement design and Management 2,348 2,348
McDunn Partnership(evaluate property) 2,000 2,000 a A .
Grant Assistance(A/E) 10,000 ',e' 6;0QQ,� �VtO* N0
Supplemental Services 16,730 16,730g;4Y:
Surveying I
Reimbursables 500 500
Expenses 1,500 1,100
Amendment 3, Attachment 2 �"° �Iv�u�U �b
06130/2000, 2:32 PM PROJECT BUDGET Page 2 of 2
GUINN CAMPUS
MEDTECH AND ELEMENTARY SCHOOL
DESCRIPTION Total Project Phase[ Phase II Alt 1 Alt 2
June 30,2000 Business MedTech Site Improve Elementary
Assistance Complex School
Center Stabilization
Other Architectural fees -
National Development Council 85,000 85,000
National Development Council 60,000 60,000
SUBTOTAL CONTRACTUAL 707,813 465,898 178,330 - 63,585
CITY OVERHEAD
City Management(10%Design) 34,192 10,000 17,833 - 6,359
CM and Inspection(2.0%construction) 85,683 40,000 33,484 5,676 6,523
Advertising,printing and Award 3,779 1,779 2,000
Environmental Consultants 12,982 12,982
Geotech Engineering -
Materials testing 10,000 5,000 5,000
Electrical Utilities 30,000 20,000 10,000
Water/Sewer Tap Fees 2,450 2,450
Water Tap 500 500
Sewer Tap 1,500 1,500
TDLR Design Review 870 425 445
TDLR Inspection 445 inc 445
National Park Service 350 350
OTHER OVERHEAD -
Relocation Expenses -
Land Acquisition 83,560 83,560
Mowing and Irrigation 9,029 9,029
Business Assistance Center operations and debt 200,000 200,000
Reserve
SUBTOTAL CITY OVERHEAD 475,339 385,574 71,207 5,676 12,882
TOTAL PROJECT COST 6,042,150 3,426,320 1 1,923,737 1 289,476 402,617
TOTAL AVAILABLE PHASE BALANCE (457,150) 630,680 (723,737) 38,524 (402,617)
CUMULATIVE BALANCE(contingency) 630,680 1 (93,057) (54,533) (457,150)
Phase 1:Renovate Middle School into Business Dev Ctr,parking lot
Phase II:Renovate gym into offices and expand parking for new space
Alt 1::Site enhancements,entry,new parking surface,complex landscaping
Alt 2:Replace Roof and windows,Stabalize walls
Phase III:Interior finish Elementary School
CFFBC0Q0
CUR MC aky
0 t"vL.�ilc• •
Amendment 3, Attachment 2
City of Fort Worth, Texas
ey!jor and Council Communication
DATE REFERENCE NUMBER LOG NAME PAGE
6/20/00 C-18088 20KOMAT 1 of 1
SUBJECT APPROVAL OF AMENDMENT TO ARCHITECTURAL CONTRACT WITH KOMATSU
ARCHITECTURE FOR THE DESIGN OF THE FORT WORTH MEDTECH CENTER
AND ELEMENTARY SCHOOL STABILIZATION AT THE GUINN SCHOOL COMPLEX
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Amendment No. 3 with
Komatsu Architecture for a fixed fee of $241,915 for the programming, design and construction
monitoring of the Fort Worth MedTech Center (existing Gymnasium Building) and the stabilization of the
Elementary School building.
DISCUSSION:
A U.S. Department of Housing and Urban Development (HUD) grant has allocated $1,300,000 for the
design and historic renovation of the gymnasium building at the Guinn School complex located on
Rosedale Avenue and 1-35 to house the Fort Worth MedTech Center.
This project is Phase II of the Guinn School Business Development complex. The proposed MedTech
Center will house a medical business incubator which will include office suites, computer areas and
research and development areas. The Elementary School building will be stabilized to prevent further
deterioration in anticipation of future renovation.
On April 21, 1998 (M&C C-16736), Council approved a design agreement in the amount of$299,550 to
Komatsu Architecture for the design of the Guinn School Business Assistance Center (Guinn Middle
School). Amendments 1 and 2, totaling $17,000, have been executed for the development of concept
plans for the MedTech Center and the Elementary School. Upon approval of Amendment No. 3, the
total fee will be $558,465.
Komatsu Architecture has committed to a goal ofd/o M/WBE participation for the Phase II design.
The City's goal on this project is 27%.
The MedTech Center will be located in COUNCIL DISTRICT 8.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current operating budget, as appropriated,
of the Grants Fund.
MG:I
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
APPROVED
Mike Groomer 6140 CITY COUNCIL
Originating Department Head: CITY 1
(from) JUN 20 2000
Hugo Malanga 7801 GR76 539120 020206088930 $25,000.00
Additional Information Contact: GR76 539120 020206101720 $12,000.00
GR76 539120 013206101720 $88,000.00
Ike
GR76 539120 013206112680 $66,915.00 Citi dCity of Fort Worth.Tees"
Hugo Malanga 7801 GR76 539120 013206108910 $50,000.00