FORT WORTH City of Fort Worth CONTRACT A10. CO3
Change Order Request Breakdown
Project Namel Old Decatur Road and Angle Ave Roundabout City Sec# 2014
Client Project#(s)l 3023
Contractor Jackson Construction, Ltd PM Lissette Acevedo inspectorl Michael Collier
Change Order Submittal# Date 5/2/2016
Dept. TPW WATER SEWER Contract Time
Totals CD
Original Contract Amount $1,620,708.86 $148,215.00 $205,457.00 $1,974,380.86 150
Extras to Date $73,060.90 $37,633.03 $12,793.37 $123,487.30 37
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,693,769.76 $185,848.03 $218,250.37 $2,097,868.16 187
Amount of Proposed Change Order $16,195.19 $0.00 $0.00 $16,195.19 0
Revised Contract Amount $1,709,964.95 $185,848.03 $218,250.37 $2,114,063.35 187
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00 $0.00 $0.00
Additional Funding(if necessary) $16,195.19 $16,195.19
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 7.07%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $2,467,976.08
sTrrr7lmmm puss s)r-aR 01iANG E +JRD ER
Light Pole: not part of the original project layout; Electric Service Pedestal: listed on the plans,however there is not a pay item for it.
Temporary lighting:not part of the original project layout;Metro Signs: City is no longer supplying the signs;Pedestrian Buffer: bid item for
was 4"however 10.5"is required. Reduce lime stabilization from 48lbs/sy double application to 38lbs/sy single application.
OPICIAL RECORD
'dlfiY'SECR@1"ARy
a&25 2�6 WORT#19 TX
G�Yo(SF � _1y�
Fo TO Wow City of Fort Worth
T Change Order Additions
Project Name I Old Decatur Road and Angle Ave Roundabout City Sec# 2014
Client Project# 1 3023
Contractor! Jackson Construction,Ltd PM Lissette Acevedo Inspector Michael Collier
Change Order Submittal# Date 5f212016
ADDITIONS
ITEM DESCRIP ION DEPT Qty Unit nit Cost Total
Remove existing light pole west of e roundabout re-route/repair existing TP
conduit and pull new cable(not part of e original protect layout)
Sheet of e plans call for an electric service pedestal o be installed. --T5—,76M--IrMM
The City detail sheet is included in the plans, There is
not a pay item for the seance pedestal
Additional temporary lighting not part of e ongina project layout) TPW 1.00000000 LS $2.245.58 $2,245.59
Furnish metro sign(City is no longer supp ymg a signs W
Integral colored/textured concrete pe estan buffer(Bid item was for 5.
plans call for .5')
Lime Material(38lbs/sy) T W 145.77000000 7 .
Lime Treatment single application) W ----7-,677.00000000 5
TPW $tt4,394.55
WATER $0.00
SEWER $0.00
Sub ota Additions
Change Order Additions Page 1 of 1
a
Fo T� Wow City of Fort Worth
Change Order Deletions
Project Name I Old Decatur Road and Angle Ave Roundabout City Sec# 2014
Client Project# r 3023
Co Jackson Construction,Ltd PM Lissette Acevedo Inspector Michael Collier
Change Order Submittal# 0 Date F 5/212016
DELETIONS
ITEM DESCMPTM- DEPT City Unit nit ost Total
Integral oar oncre e Pedestrain Butter(Bid i em was or ,pans ca
or .5
Lime Material sy 7 .
Lime Treatment single app icaton) 77 7 .
TPW $98,199.36
WATER $0.00
SEWER $0.00
Sub ota a etions
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
CO#1 1/7/2016 $4,483.07
Total $4,483.07
CVW Change Order Approval St-COApp08 Page 2 of 3
FORT WORTH, city of Fort Worth
Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: 3
Change Order No.: St-COApp08 Date Started: 2016-06-20
City Sec. No.: 47192 Date Due: 2016-08-09
Project Name: Old Decatur Rd and Angle Ave Roundabout TPW-2014-000089
02014 DOE Numbers:
Project Numbers:
6938
Project Old Decatur Rd. reconstruction from IH 820 to Angle Ave.
Description: including a roundabout at the intersection of Angle Ave.
Project Manager: Lissette Acevedo City Inspector: Mike Collier
Contractor:
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number: M&C Date:
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
TPW $ 16,195.19
Total Cost: $ 16,195.19 Total Requested Days: 0
Approval Status:
S10-11b 0%
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&ProcessI... 7/25/2016
s .
CFW Change Order Approval St-COApp08 Page 3 of 3
Approved: Yes
Comments:
User: Tara Fishback
Date: 2016-06-20 4:39 PM
Approved: Yes
Comments:
User: Carmen Estep
Date: 2016-06-21 4:58 PM
Approved: Yes
Comments:
User: Lissette Acevedo
Date: 2016-06-22 9:54 AM
Approved: Yes
Comments:
User: Todd Estes
Date: 2016-06-27 9:43 AM
Approved: Yes
Comments:
User: Todd Blomstrom
Date: 2016-07-18 12:26 PM
Approved: Yes
Comments:
User: Doug Wiersig
Date: 2016-07-20 3:26 PM
Approved: Yes
Comments:
User: Doug Black
Date: 2016-07-20 4:37 PM
Approved. Yes A bye* A. o
Comments:
User: Jay Chapa NO
Date: 2016-07-24 6:20 PM J. e City S
Action Required:
OFFICIAR RECORD
CITY SECRETARY
FT. WORTH, TX
https:Hprojectpoint.buzzsaw.com/ bz_web/Forms/FormPrint.aspx?Siteld=51500&ProcessI... 7/25/2016