Loading...
HomeMy WebLinkAboutContract 48086 CITY SECRETARY ' f D.O.E. FILE CITY SECRETAW CONTRACTOR'S BONDING CO. CONTRACT N0, CONSTRUCTION'S COVY FORT WORT H CLIENT DEPARTMENT PROJECT MANUAL FOR THE CONSTRUCTION OF Dry Branch Creek Interim Regional Detention Basin City Project No.00485 D.O.E.No.5425 SD No.0416 Betsy Price David Cooke Mayor City Manager Douglas W. Wiersig, P.E. Director,Transportation and Public Works Department OF Prepared for The City of Fort Worth :* At/.................es°.ot�� Transportation &Public Works i CHRISTOPHER FRANKE i Stormwater Division ................. 114273 ; ANAL 2016 BHB Enginee-Ang & Surveying OFFICIAL RECORD CITY SECRETARY ' FT. WORTH TX A� 5 2016 of fa CCCI FORTWORTH. City of Fort Worth Standard Construction Specification Documents Adopted September 2011 000000- 1 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Pagel of 3 SECTION 00 00 00 TABLE OF CONTENTS Division 00- General Conditions 0005 10 Mayor and Council Communication 0005 15 Addenda 00 11 13 Invitation to Bidders 0021 13 Instructions to Bidders 0035 13 Conflict of Interest Affidavit 0041 00 Bid Form 00 42 43 Proposal Form Unit Price 0043 13 Bid Bond 00 43 37 Vendor Compliance to State Law Nonresident Bidder 0045 11 Bidders Prequalifications 0045 12 Prequalification Statement 0045 13 Bidder Prequalification Application 00 45 26 Contractor Compliance with Workers'Compensation Law 00 45 40 Minority Business Enterprise Goal 00 45 41 Small Business Enterprise Goal 00 52 43 Agreement 0061 13 Performance Bond 0061 14 Payment Bond 0061 19 Maintenance Bond 0061 25 Certificate of Insurance 00 72 00 General Conditions 00 73 00 Supplementary Conditions Division 01 - General Requirements 01 11 00 Summary of Work 01 2500 Substitution Procedures 01 31 19 Preconstruction Meeting 01 31 20 Project Meetings 01 32 16 Construction Progress Schedule 01 3233 Preconstruction Video 01 3300 Submittals 01 35 13 Special Project Procedures 01 4523 Testing and Inspection Services 01 5000 Temporary Facilities and Controls 01 5526 Street Use Permit and Modifications to Traffic Control 01 57 13 Storm Water Pollution Prevention Plan 01 58 13 Temporary Project Signage 01 6000 Product Requirements 01 6600 Product Storage and Handling Requirements 01 7000 Mobilization and Remobilization 01 71 23 Construction Staking and Survey 01 7423 Cleaning 01 77 19 Closeout Requirements 01 7823 Operation and Maintenance Data 01 7839 Project Record Documents CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised November 22,2013 000000-2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 2 of 3 Technical Specifications which have been modified by the Engineer specifically for this Project. The sections below specifically apply to this project,and are included in the electronic version of this document,which can be viewed/downloaded from the project buzzsaw folder. Within each specification, some portions have been removed which do not apply to this project. Specifications included in hard copies of this document are only those which contain additional information, added by the Engineer and specific to this project. All portions added by the Engineer are shown in Bold font. Division 02-Existing Conditions 0241 13 Selective Site Demolition 0241 14 Utility Removal/Abandonment Division 31 - Earthwork 31 1000 Site Clearing 31 23 16 Unclassified Excavation 31 2500 Erosion and Sediment Control 31 3700 Riprap Division 32-Exterior Improvements 3231 13 Chain Link Fences and Gates 3231 26 Wire Fences and Gates 3231 29 Wood Fences and Gates 3291 19 Topsoil Placement and Finishing of Parkways 3292 13 Hydro-Mulching, Seeding,and Sodding Division 33-Utilities 33 49 40 Storm Drainage Headwalls and Wingwalls Division 34-Transportation 4 71 13 Traffic Control Appendix Nationwide Permit 43 Geotechnical Study,by LML Engineering,dated May 22, 2014 TROE-2 TROE-3 TROE-4 TCE-2 TCE-3 TCE-4 END OF SECTION CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised November 22,2013 M&C Review Official site of the City of Fort Worth,Texas CITY COUNCIL AGENDA F°RT °RTH COUNCIL ACTION: Approved on 6/21/2016 REFERENCE 20SW DRY BRANCH CREEK DATE: 6121/2016 NO.: C-27788 LOG NAME: INTERIM REGIONAL DETENTION BASIN CODE: C TYPE: NOW PUBLIC NO CONSENT HEARING: SUBJECT: Authorize Execution of Construction Contract with RPM xConstruction, L.L.C., in the Amount of$1,346,113.05 for the Construction of Dry Branch Creek Interim Regional Detention Basin and Provide for Construction Services and Contingencies for a Total Construction Phase Cost of$1,531,413.05 (COUNCIL DISTRICT 9) RECOMMENDATION: It is recommended that the City Council authorize the execution of construction contract with RPM xConstruction, L.L.C., in the amount of$1,346,113.05 for the construction of Dry Branch Creek Interim Regional Detention Basin. DISCUSSION: The purpose of this Mayor and Council Communications (M&C) is to authorize the execution of a construction contract with RPM xConstruction, L.L.C., in the amount of$1,346,113.05 for the construction of Dry Branch Creek Interim Regional Detention Basin and provide for construction services and contingencies for a total construction phase cost of$1,531,413.05. This project will provide for detention of runoff to mitigate flooding of residential properties and commercial properties and roadway overtopping along Dry Branch Creek south of Hollis St. This project was advertised for bid in the Fort Worth Star-Telegram on April 7, 2016 and April 14, 2016. On May 5, 2016, the following bids were received: Bidders J Bid Amount RPM xConstruction, L.L.C. $1,346,113.05 FCS Construction $1,569,627.50 LD Kemp Excavating $1,712,358.75 FA—rkContracting Services $1,738,011.50 It is recommended that a contract be awarded in the amount of$1,346,113.05 to RPM xConstruction, L.L.C. Costs for the implementation of this project will be funded by the Stormwater Capital Projects Bond Fund. The recommended contract award amount includes a pre-established field order allowance of $50,000.00. Other budget items beyond the construction contract amount include $118,300.00 for survey, material testing and inspection and $67,000.00 for contingencies. The total construction budget is $1,531,413.05. Construction is anticipated to start in Summer 2016 and the contract calls for a 280 Calendar Day construction time. M/WBE OFFICE— RPM xConstruction, L.L.C., is in compliance with the City's BDE Ordinance by committing to 15 percent MBE participation. The City's MBE goal on this project is 15 percent. This project is located in COUNCIL DISTRICT 9, Mapsco 63H. M&C Review FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that funds are available in the current capital budget, as appropriated, of the Stormwater Capital Projects Fund (52002), Stormwater Capital Projects - Bonds Fund (59651) and in the Fiscal Year 2016 Stormwater Capital Improvement Plan. Encumbrances Fund Current Budget and Actuals Budget Remaining* Stormwater Capital Projects 52002 $ 764,100.00 $ 0.00 $ 764,100.00 Stormwater Capital Projects-Bonds 59651 $2,321,516.00 $522,730.00 $1,798,786.00 Total $3,085,616.00 $522,730.00 $2,562,886.00 *Numbers rounded for presentation purposes. TO Fund Department Account Project Program Activity Budget Reference# Amount ID ID Year Chartfield 2 FROM Fund Department Account Project Program Activity Budget Reference# Amount ID ID Year Chartfield 2 59651 0200431 1 5740010 IC004851 1 002880 1 1 $1,346,113.05 Submitted for City Manager's Office by: Jay Chapa (5804) Originating Department Head: Douglas Wiersig (7801) Additional Information Contact: Mike Bennett (7891) ATTACHMENTS CP C00485 1295.pdf CP C00485 MAP.pdf 00 11 13- 1 INVITATION TO BIDDERS Page I of 2 1 SECTION 00 11 13 2 INVITATION TO BIDDERS 3 RECEIPT OF BIDS 4 Sealed bids for the construction of Dry Branch Creek Interim Regional Detention Basin,City 5 Project No.00485 will be received by the City of Fort Worth Purchasing Office: 6 7 City of Fort Worth 8 Purchasing Division 9 1000 Throckmorton Street 10 Fort Worth,Texas 76102 11 until 1:30 P.M. CST,Thursday, May 5, 2016,and bids will be opened publicly and read aloud at 12 2:00 PM CST in the Council Chambers. 13 14 GENERAL DESCRIPTION OF WORK 15 The major work will consist of the(approximate)following: Excavation,Tree Removal, Storm 16 Drain Demolition, Storm Drain Headwall Construction, and Site Grading. 17 18 PREQUALIFICATION 19 The improvements included in this project must be performed by a contractor who is pre- 20 qualified by the City at the time of bid opening. The procedures for qualification and pre- 21 qualification are outlined in the Section 00 21 13—INSTRUCTIONS TO BIDDERS. 22 23 DOCUMENT EXAMINATION AND PROCUREMENTS 24 The Bidding and Contract Documents may be examined or obtained on-line by visiting the City 25 of Fort Worth's Purchasing Division website at http://www.fortworthgov.orWt)urcliasine/and 26 clicking on the Buzzsaw link to the advertised project folders on the City's Buzzsaw site.The 27 Contract Documents may be downloaded,viewed, and printed by interested contractors and/or 28 suppliers. 29 30 Copies of the Bidding and Contract Documents may be purchased from Baird,Hampton,and 31 Brown Engineering& Surveying,4550 SH 360, Ste. 180,Grapevine, TX 76051 32 33 The cost of Bidding and Contract Documents is: 34 Set of Bidding and Contract Documents with full size drawings: $50 35 Set of Bidding and Contract Documents with half size(if available)drawings: $30 36 37 PREBID CONFERENCE 38 A prebid conference may be held as described in Section 00 21 13 - INSTRUCTIONS TO 39 BIDDERS at the following location, date,and time: 40 DATE: October 10, 2017 41 TIME: 11:00 AM 42 PLACE: 1000 Throckmorton St. 43 Fort Worth,Texas 76102 44 LOCATION: Room 270, 2nd Floor of City Hall,TPN Department 45 46 47 CITY'S RIGHT TO ACCEPT OR REJECT BIDS 48 City reserves the right to waive irregularities and to accept or reject bids. 49 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 00 11 13-2 INVITATION TO BIDDERS Page 2 of 2 1 2 INQUIRIES 3 All inquiries relative to this procurement should be addressed to the following: 4 Attn: Michael Owen,PE,City of Fort Worth 5 Email: Michael.owen @fortworthtexas.gov 6 Phone: (817) 392-8079 7 AND/OR 8 Attn: Chris Franke, PE, BHB Engineering& Surveying 9 Email: cfranke @bhbinc.com 10 Phone: (817) 251-8550 11 12 ADVERTISEMENT DATES 13 October 5,2017 14 15 16 END OF SECTION CITY OF FORT WORTH Dry Bunch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 0021 13-1 INSTRUCTIONS TO BIDDERS Pagel of 8 1 SECTION 00 2113 2 INSTRUCTIONS TO BIDDERS 3 1. Defined Terms 4 5 1.1.Terms used in these INSTRUCTIONS TO BIDDERS, which are defined in Section 00 72 6 00 -GENERAL CONDITIONS. 7 8 1.2.Certain additional terms used in these INSTRUCTIONS TO BIDDERS have the 9 meanings indicated below which are applicable to both the singular and plural thereof. 10 11 1.2.1. Bidder: Any person, firm,partnership,company, association, or corporation acting 12 directly through a duly authorized representative, submitting a bid for performing 13 the work contemplated under the Contract Documents. 14 15 1.2.2. Nonresident Bidder: Any person, firm,partnership, company, association,or 16 corporation acting directly through a duly authorized representative, submitting a 17 bid for performing the work contemplated under the Contract Documents whose 18 principal place of business is not in the State of Texas. 19 20 1.2.3. Successful Bidder: The lowest responsible and responsive Bidder to whom City 21 (on the basis of City's evaluation as hereinafter provided)makes an award. 22 23 2. Copies of Bidding Documents 24 25 2.1.Neither City nor Engineer shall assume any responsibility for errors or misinterpretations 26 resulting from the Bidders use of incomplete sets of Bidding Documents. 27 28 2.2.City and Engineer in making copies of Bidding Documents available do so only for the 29 purpose of obtaining Bids for the Work and do not authorize or confer a license or grant 30 for any other use. 31 32 3. Prequalification of Bidders(Prime Contractors and Subcontractors) 33 34 N/A 35 36 4. Examination of Bidding and Contract Documents,Other Related Data, and Site 37 38 4.1.Before submitting a Bid, each Bidder shall: 39 40 4.1.1. Examine and carefully study the Contract Documents and other related data 41 identified in the Bidding Documents(including"technical data" referred to in 42 Paragraph 4.2. below). No information given by City or any representative of the 43 City other than that contained in the Contract Documents and officially 44 promulgated addenda thereto, shall be binding upon the City. 45 46 4.1.2. Visit the site to become familiar with and satisfy Bidder as to the general,local and 47 site conditions that may affect cost,progress,performance or furnishing of the 48 Work. 49 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project I`lo.00485 Revised April 27,2015 002113-2 INSTRUCTIONS TO BIDDERS Page 2 of 8 1 4.1.3. Consider federal, state and local Laws and Regulations that may affect cost, 2 progress,performance or furnishing of the Work. 3 4 4.1.4. Study all: (i) reports of explorations and tests of subsurface conditions at or 5 contiguous to the Site and all drawings of physical conditions relating to existing 6 surface or subsurface structures at the Site(except Underground Facilities)that 7 have been identified in the Contract Documents as containing reliable "technical 8 data" and(ii) reports and drawings of Hazardous Environmental Conditions, if any, 9 at the Site that have been identified in the Contract Documents as containing 10 reliable"technical data." 11 12 4.1.5. Be advised that the Contract Documents on file with the City shall constitute all of 13 the information which the City will furnish. All additional information and data 14 which the City will supply after promulgation of the formal Contract Documents 15 shall be issued in the form of written addenda and shall become part of the Contract 16 Documents just as though such addenda were actually written into the original 17 Contract Documents. No information given by the City other than that contained in 18 the Contract Documents and officially promulgated addenda thereto, shall be 19 binding upon the City. 20 21 4.1.6. Perform independent research, investigations,tests,borings, and such other means 22 as may be necessary to gain a complete knowledge of the conditions which will be 23 encountered during the construction of the project. On request, City may provide 24 each Bidder access to the site to conduct such examinations, investigations, 25 explorations,tests and studies as each Bidder deems necessary for submission of a 26 Bid. Bidder must fill all holes and clean up and restore the site to its former 27 conditions upon completion of such explorations, investigations,tests and studies. 28 29 4.1.7. Determine the difficulties of the Work and all attending circumstances affecting the 30 cost of doing the Work, time required for its completion, and obtain all information 31 required to make a proposal. Bidders shall rely exclusively and solely upon their 32 own estimates, investigation, research, tests,explorations, and other data which are 33 necessary for full and complete information upon which the proposal is to be based. 34 It is understood that the submission of a proposal is prima-facie evidence that the 35 Bidder has made the investigation, examinations and tests herein required. Claims 36 for additional compensation due to variations between conditions actually 37 encountered in construction and as indicated in the Contract Documents will not be 38 allowed. 39 40 4.1.8. Promptly notify City of all conflicts, errors,ambiguities or discrepancies in or 41 between the Contract Documents and such other related documents. The Contractor 42 shall not take advantage of any gross error or omission in the Contract Documents, 43 and the City shall be permitted to make such corrections or interpretations as may 44 be deemed necessary for fulfillment of the intent of the Contract Documents. 45 46 4.2. Reference is made to Section 00 73 00—Supplementary Conditions for identification of: 47 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 27,2015 002113-3 INSTRUCTIONS TO BIDDERS Page 3 of 8 1 4.2.1. those reports of explorations and tests of subsurface conditions at or contiguous to 2 the site which have been utilized by City in preparation of the Contract Documents. 3 The logs of Soil Borings, if any,on the plans are for general information only. 4 Neither the City nor the Engineer guarantee that the data shown is representative of 5 conditions which actually exist. 6 7 4.2.2. those drawings of physical conditions in or relating to existing surface and 8 subsurface structures (except Underground Facilities)which are at or contiguous to 9 the site that have been utilized by City in preparation of the Contract Documents. 10 11 4.2.3. copies of such reports and drawings will be made available by City to any Bidder 12 on request. Those reports and drawings may not be part of the Contract 13 Documents,but the "technical data" contained therein upon which Bidder is entitled 14 to rely as provided in Paragraph 4.02. of the General Conditions has been identified 15 and established in Paragraph SC 4.02 of the Supplementary Conditions. Bidder is 16 responsible for any interpretation or conclusion drawn from any "technical data" or 17 any other data, interpretations,opinions or information. 18 19 4.3.The submission of a Bid will constitute an incontrovertible representation by Bidder(i) 20 that Bidder has complied with every requirement of this Paragraph 4, (ii)that without 21 exception the Bid is premised upon performing and furnishing the Work required by the 22 Contract Documents and applying the specific means,methods, techniques, sequences or 23 procedures of construction(if any) that may be shown or indicated or expressly required 24 by the Contract Documents, (iii)that Bidder has given City written notice of all 25 conflicts, errors, ambiguities and discrepancies in the Contract Documents and the 26 written resolutions thereof by City are acceptable to Bidder,and when said conflicts, 27 etc.,have not been resolved through the interpretations by City as described in 28 Paragraph 6.,and(iv)that the Contract Documents are generally sufficient to indicate 29 and convey understanding of all terms and conditions for performing and furnishing the 30 Work. 31 32 4.4.The provisions of this Paragraph 4, inclusive, do not apply to Asbestos,Polychlorinated 33 biphenyls (PCBs),Petroleum,Hazardous Waste or Radioactive Material covered by 34 Paragraph 4.06. of the General Conditions,unless specifically identified in the Contract 35 Documents. 36 37 5. Availability of Lands for Work, Etc. 38 39 5.1.The lands upon which the Work is to be performed, rights-of-way and easements for 40 access thereto and other lands designated for use by Contractor in performing the Work 41 are identified in the Contract Documents. All additional lands and access thereto 42 required for temporary construction facilities,construction equipment or storage of 43 materials and equipment to be incorporated in the Work are to be obtained and paid for 44 by Contractor. Easements for permanent structures or permanent changes in existing 45 facilities are to be obtained and paid for by City unless otherwise provided in the 46 Contract Documents. 47 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 27,2015 002113-4 INSTRUCTIONS TO BIDDERS Page 4 of 8 1 5.2.Outstanding right-of-way, easements, and/or permits to be acquired by the City are listed 2 in Paragraph SC 4.01 of the Supplementary Conditions. In the event the necessary right- 3 of-way, easements, and/or permits are not obtained,the City reserves the right to cancel 4 the award of contract at any time before the Bidder begins any construction work on the 5 project. 6 7 5.3. The Bidder shall be prepared to commence construction without all executed right-of- 8 way, easements, and/or permits, and shall submit a schedule to the City of how 9 construction will proceed in the other areas of the project that do not require permits 10 and/or easements. 11 12 6. Interpretations and Addenda 13 14 6.1.All questions about the meaning or intent of the Bidding Documents are to be directed to 15 City in writing on or before 2 p.m., the Monday prior to the Bid opening. Questions 16 received after this day may not be responded to. Interpretations or clarifications 17 considered necessary by City in response to such questions will be issued by Addenda 18 delivered to all parties recorded by City as having received the Bidding Documents. 19 Only questions answered by formal written Addenda will be binding. Oral and other 20 interpretations or clarifications will be without legal effect. 21 22 Address questions to: 23 24 City of Fort Worth 25 1000 Throckmorton Street 26 Fort Worth,TX 76102 27 Attn: Michael Owen,PE,City of Fort Worth Transportation&Public Works 28 Email: Michael.Owen @fortworthtexas.gov 29 Phone: (817) 382-8079 30 31 32 6.2.Addenda may also be issued to modify the Bidding Documents as deemed advisable by 33 City. 34 35 6.3.A prebid conference may be held at the time and place indicated in the Advertisement or 36 INVITATION TO BIDDERS. Representatives of City will be present to discuss the 37 Project. Bidders are encouraged to attend and participate in the conference. City will 38 transmit to all prospective Bidders of record such Addenda as City considers necessary 39 in response to questions arising at the conference. Oral statements may not be relied 40 upon and will not be binding or legally effective. 41 42 7. Bid Security 43 44 7.1.Each Bid must be accompanied by Bid Bond made payable to City in an amount of five 45 (5)percent of Bidder's maximum Bid price on form attached, issued by a surety meeting 46 the requirements of Paragraphs 5.01 of the General Conditions. 47 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 27,2015 0021 13-5 INSTRUCTIONS TO BIDDERS Page 5 of 8 1 7.2.The Bid Bond of all Bidders will be retained until the conditions of the Notice of Award 2 have been satisfied. if the Successful Bidder fails to execute and deliver the complete 3 Agreement within 10 days after the Notice of Award,City may consider Bidder to be in 4 default, rescind the Notice of Award,and the Bid Bond of that Bidder will be forfeited. 5 Such forfeiture shall be City's exclusive remedy if Bidder defaults. The Bid Bond of all 6 other Bidders whom City believes to have a reasonable chance of receiving the award 7 will be retained by City until final contract execution. 8 9 8. Contract Times 10 The number of days within which, or the dates by which,Milestones are to be achieved in 11 accordance with the General Requirements and the Work is to be completed and ready for 12 Final Acceptance is set forth in the Agreement or incorporated therein by reference to the 13 attached Bid Form. 14 15 9. Liquidated Damages 16 Provisions for liquidated damages are set forth in the Agreement. 17 18 10. Substitute and "Or-Equal" Items 19 The Contract, if awarded,will be on the basis of materials and equipment described in the 20 Bidding Documents without consideration of possible substitute or"or-equal" items. 21 Whenever it is indicated or specified in the Bidding Documents that a "substitute" or"or- 22 equal" item of material or equipment may be furnished or used by Contractor if acceptable to 23 City, application for such acceptance will not be considered by City until after the Effective 24 Date of the Agreement. The procedure for submission of any such application by Contractor 25 and consideration by City is set forth in Paragraphs 6.05A., 6.05B. and 6.05C. of the General 26 Conditions and is supplemented in Section 01 25 00 of the General Requirements. 27 28 11. Subcontractors,Suppliers and Others 29 30 11.1. In accordance with the City's Business Diversity Enterprise Ordinance No. 20020- 31 12-2011 (as amended), the City has goals for the participation of minority business 32 and/or small business enterprises in City contracts. A copy of the Ordinance can be 33 obtained from the Office of the City Secretary. The Bidder shall submit the MBE and 34 SBE Utilization Form, Subcontractor/Supplier Utilization Form,Prime Contractor 35 Waiver Form and/or Good Faith Effort Form with documentation and/or Joint 36 Venture Form as appropriate. The Forms including documentation must be received 37 by the City no later than 2:00 P.M. CST, on the second business days after the bid 38 opening date. The Bidder shall obtain a receipt from the City as evidence the 39 documentation was received. Failure to comply shall render the bid as non- 40 responsive. 41 42 11.2. No Contractor shall be required to employ any Subcontractor, Supplier, other person 43 or organization against whom Contractor has reasonable objection. 44 45 12. Bid Form 46 47 12.1. The Bid Form is included with the Bidding Documents; additional copies may be 48 obtained from the City. 49 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 27,2015 002113-6 INSTRUCTIONS TO BIDDERS Page 6 of 8 1 12.2. All blanks on the Bid Form must be completed by printing in ink and the Bid Form 2 signed in ink. Erasures or alterations shall be initialed in ink by the person signing 3 the Bid Form. A Bid price shall be indicated for each Bid item, alternative,and unit 4 price item listed therein. In the case of optional alternatives,the words "No Bid," 5 "No Change," or"Not Applicable" may be entered. Bidder shall state the prices, 6 written in ink in both words and numerals, for which the Bidder proposes to do the 7 work contemplated or furnish materials required. All prices shall be written legibly. 8 In case of discrepancy between price in written words and the price in written 9 numerals,the price in written words shall govern. 10 11 12.3. Bids by corporations shall be executed in the corporate name by the president or a 12 vice-president or other corporate officer accompanied by evidence of authority to 13 sign. The corporate seal shall be affixed. The corporate address and state of 14 incorporation shall be shown below the signature. 15 16 12.4. Bids by partnerships shall be executed in the partnership name and signed by a 17 partner,whose title must appear under the signature accompanied by evidence of 18 authority to sign. The official address of the partnership shall be shown below the 19 signature. 20 21 12.5. Bids by limited liability companies shall be executed in the name of the firm by a 22 member and accompanied by evidence of authority to sign. The state of formation of 23 the firm and the official address of the firm shall be shown. 24 25 12.6. Bids by individuals shall show the Bidder's name and official address. 26 27 12.7. Bids by joint ventures shall be executed by each joint venturer in the manner 28 indicated on the Bid Form. The official address of the joint venture shall be shown. 29 30 12.8. All names shall be typed or printed in ink below the signature. 31 32 12.9. The Bid shall contain an acknowledgement of receipt of all Addenda,the numbers of 33 which shall be filled in on the Bid Form. 34 35 12.10. Postal and e-mail addresses and telephone number for communications regarding the 36 Bid shall be shown. 37 38 12.11. Evidence of authority to conduct business as a Nonresident Bidder in the state of 39 Texas shall be provided in accordance with Section 00 43 37—Vendor Compliance 40 to State Law Non Resident Bidder. 41 42 13. Submission of Bids 43 Bids shall be submitted on the prescribed Bid Form,provided with the Bidding Documents, 44 at the time and place indicated in the Advertisement or INVITATION TO BIDDERS, 45 addressed to City Manager of the City,and shall be enclosed in an opaque sealed envelope, 46 marked with the City Project Number,Project title,the name and address of Bidder, and 47 accompanied by the Bid security and other required documents. If the Bid is sent through the 48 mail or other delivery system,the sealed envelope shall be enclosed in a separate envelope 49 with the notation "BID ENCLOSED" on the face of it. 50 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 27,2015 0021 13-7 INSTRUCTIONS TO BIDDERS Page 7 of 8 1 14. Modification and Withdrawal of Bids 2 3 14.1. Bids addressed to the City Manager and filed with the Purchasing Office cannot be 4 withdrawn prior to the time set for bid opening. A request for withdrawal must be 5 made in writing by an appropriate document duly executed in the manner that a Bid 6 must be executed and delivered to the place where Bids are to be submitted at any 7 time prior to the opening of Bids. After all Bids not requested for withdrawal are 8 opened and publicly read aloud, the Bids for which a withdrawal request has been 9 properly filed may,at the option of the City, be returned unopened. 10 11 14.2. Bidders may modify their Bid by electronic communication at any time prior to the 12 time set for the closing of Bid receipt. 13 14 15. Opening of Bids 15 Bids will be opened and read aloud publicly at the place where Bids are to be submitted. An 16 abstract of the amounts of the base Bids and major alternates(if any)will be made available 17 to Bidders after the opening of Bids. 18 19 16. Bids to Remain Subject to Acceptance 20 All Bids will remain subject to acceptance for the time period specified for Notice of Award 21 and execution and delivery of a complete Agreement by Successful Bidder. City may, at 22 City's sole discretion, release any Bid and nullify the Bid security prior to that date. 23 24 17. Evaluation of Bids and Award of Contract 25 26 17.1. City reserves the right to reject any or all Bids, including without limitation the rights 27 to reject any or all nonconforming,nonresponsive, unbalanced or conditional Bids 28 and to reject the Bid of any Bidder if City believes that it would not be in the best 29 interest of the Project to make an award to that Bidder,whether because the Bid is 30 not responsive or the Bidder is unqualified or of doubtful financial ability or fails to 31 meet any other pertinent standard or criteria established by City. City also reserves 32 the right to waive informalities not involving price,contract time or changes in the 33 Work with the Successful Bidder. Discrepancies between the multiplication of units 34 of Work and unit prices will be resolved in favor of the unit prices. Discrepancies 35 between the indicated sum of any column of figures and the correct sum thereof will 36 be resolved in favor of the correct sum. Discrepancies between words and figures 37 will be resolved in favor of the words. 38 39 17.1.1. Any or all bids will be rejected if City has reason to believe that collusion exists 40 among the Bidders,Bidder is an interested party to any litigation against City, 41 City or Bidder may have a claim against the other or be engaged in litigation, 42 Bidder is in arrears on any existing contract or has defaulted on a previous 43 contract, Bidder has performed a prior contract in an unsatisfactory manner,or 44 Bidder has uncompleted work which in the judgment of the City will prevent or 45 hinder the prompt completion of additional work if awarded. 46 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 27,2015 0021 13-8 INSTRUCTIONS TO BIDDERS Page 8 of 8 1 17.2. City may consider the qualifications and experience of Subcontractors, Suppliers,and 2 other persons and organizations proposed for those portions of the Work as to which 3 the identity of Subcontractors, Suppliers,and other persons and organizations must 4 be submitted as provided in the Contract Documents or upon the request of the City. 5 City also may consider the operating costs, maintenance requirements,performance 6 data and guarantees of major items of materials and equipment proposed for 7 incorporation in the Work when such data is required to be submitted prior to the 8 Notice of Award. 9 10 17.3. City may conduct such investigations as City deems necessary to assist in the 11 evaluation of any Bid and to establish the responsibility, qualifications,and financial 12 ability of Bidders,proposed Subcontractors, Suppliers and other persons and 13 organizations to perform and furnish the Work in accordance with the Contract 14 Documents to City's satisfaction within the prescribed time. 15 16 17.4. Contractor shall perform with his own organization, work of a value not less than 17 35%of the value embraced on the Contract,unless otherwise approved by the City. 18 19 17.5. If the Contract is to be awarded, it will be awarded to lowest responsible and 20 responsive Bidder whose evaluation by City indicates that the award will be in the 21 best interests of the City. 22 23 17.6. Pursuant to Texas Government Code Chapter 2252.001,the City will not award 24 contract to a Nonresident Bidder unless the Nonresident Bidder's bid is lower than 25 the lowest bid submitted by a responsible Texas Bidder by the same amount that a 26 Texas resident bidder would be required to underbid a Nonresident Bidder to obtain a 27 comparable contract in the state in which the nonresident's principal place of 28 business is located. 29 30 17.7. A contract is not awarded until formal City Council authorization. If the Contract is 31 to be awarded,City will award the Contract within 90 days after the day of the Bid 32 opening unless extended in writing. No other act of City or others will constitute 33 acceptance of a Bid. Upon the contractor award a Notice of Award will be issued by 34 the City. 35 36 17.8. Failure or refusal to comply with the requirements may result in rejection of Bid. 37 38 18. Signing of Agreement 39 When City issues a Notice of Award to the Successful Bidder, it will be accompanied by the 40 required number of unsigned counterparts of the Agreement. Within 14 days thereafter 41 Contractor shall sign and deliver the required number of counterparts of the Agreement to 42 City with the required Bonds, Certificates of Insurance, and all other required documentation. 43 City shall thereafter deliver one fully signed counterpart to Contractor. 44 45 46 47 END OF SECTION CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 27,2015 003513-1 CONFLICT OF INTEREST AFFIDAVIT Page 1 of 1 1 SECTION 00 35 13 2 CONFLICT OF INTEREST AFFIDAVIT 3 4 Each bidder, offeror,or respondent(hereinafter also referred to as "you')to a City of Fort Worth 5 (also referred to as"City")procurement are required to complete Conflict of Interest 6 Questionnaire(the attached CIQ Form) and Local Government Officer Conflicts Disclosure 7 Statement(the attached CIS Form)below pursuant to state law.This affidavit will certify that the 8 Bidder has on file with the City Secretary the required documentation and is eligible to bid on 9 City Work.The referenced forms may be downloaded from the website links provided below. 10 11 http://www.ethics.state.tx.us/forms/CIO.Pdf 12 13 http://www.ethics.state.tx.us/forms/CIS.ndf 14 15 Q CIQ Form is on file with City Secretary 16 � 17 F J CIQ Form is being provided to the City Secretary 18 19 Q CIS Form is on File with City Secretary 20 21 F4-1 CIS Form is being provided to the City Secretary 22 23 24 25 BIDDER: 26 27 I J PAx G,a,, Jje /i o iv . 4 L C By: �✓// �i✓�--. 28 Company (Please Print) 29 30 5OZOe7 c IG,✓ aom P,gn w.9d, ! /Z? Signature: 31 Address 32 33 � i✓D TIC Title: 34 City/Sta p (Please Print) 35 36 37 END OF SECTION OFFICIAL RECORD CITY SECRETARY FT.WORTH, TX CITY OF FORT WORTH Dry Branch Creek Interin Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised March 27,2012 00 41 00 BID FORM Page 1 of 3 SECTION 00 41 00 BID FORM TO: The City Manager c/o:The Purchasing Department 1000 Throckmorton Street City of Fort Worth, Texas 76102 FOR: Dry Branch Creek Interim Regional Detention Basin Between NE 28th St and Hollis St City Project No.: 00485 1. Enter Into Agreement The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with City in the form included in the Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents. 2. BIDDER Acknowledgements and Certification 2.1. In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION TO BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those dealing with the disposition of Bid Bond. 2.2. Bidder is aware of all costs to provide the required insurance, will do so pending contract award, and will provide a valid insurance certificate meeting all requirements within 14 days of notification of award. 2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation. 2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid. 2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding. 2.6. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph: a. "corrupt practice" means the offering,giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process. b. "fraudulent practice" means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of City(b)to establish Bid prices at artificial non-competitive levels, or(c)to deprive City of the benefits of free and open competition. c. "collusive practice" means a scheme or arrangement between two or more Bidders, with or without the knowledge of City, a purpose of which is to establish Bid prices at artificial, non- competitive levels. d. "coercive practice" means harming or threatening to harm, directly or indirectly, persons or their CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Dry Branch Creek Interim Regional Detention Basin Form Revised 20120327 City Project No.00485 0041 00 BID FORM Page 2 of 3 property to influence their participation in the bidding process or affect the execution of the Contract. 3. Prequalification N/A 4. Time of Completion 4.1. The Work will be complete for Final Acceptance within 280 days after the date when the the Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions. 4.2. Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work(and/or achievement of Milestones)within the times specified in the Agreement. 5. Attached to this Bid The following documents are attached to and made a part of this Bid: a. This Bid Form, Section 00 41 00 b. Required Bid Bond, Section 00 43 13 issued by a surety meeting the requirements of Paragraph 5.01 of the General Conditions. c. Proposal Form, Section 00 42 43 d. Vendor Compliance to State Law Non Resident Bidder, Section 00 43 37 e. MWBE Forms (optional at time of bid) f. Prequalification Statement, Section 00 45 12 g. Conflict of Interest Affidavit, Section 00 35 13 'If necessary, CIQ or CIS forms are to be provided directly to City Secretary h. Any additional documents that may be required by Section 12 of the Instructions to Bidders CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Dry Branch Creek Interim Regional Detention Basin Form Revised 20120327 City Project No.00485 0041 00 BID FORM Page 3 of 3 6. Total Bid Amount 6.1. Bidder will complete the Work in accordance with the Contract Documents for the following bid amount. In the space provided below, please enter the total bid amount for this project. Only this figure will be read publicly by the City at the bid opening. 6.2. It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is subject to verification and/or modification by multiplying the unit bid prices for each pay item by the respective estimated quantities shown in this proposal and then totaling all of the extended amounts. 6.3. Total Bid $ If 3 q b 113 7. Bid Submittal This Bid is submitted on —f— ;Z-0/ �j by the entity named below. Respectfully su ted, Receipt is acknowledged of the Initial following Addenda: By: Addendum No. 1: ( Ign ure) Addendum No. 2: Addendum No. 3: Addendum No.4: (Printed Name) Title: V in Company: Aeol x Corporate Seal: Address: 5-v-08' v,� r✓ 0 r D State of Incorporation: /}� Email: Phone: 2-3 g— -2 222. END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Dry Branch Creek Interim Regional Detention Basin Form Revised 20120327 City Project No.00485 00 42 43 BID PROPOSAL Page I of 1 SECTION 00 42 43 PROPOSALFORM UNIT PRICE BID Bidder's Application Project Item Information Bidder's Proposal Bidlist Item Specification Unit of Bid Description Unit Price Bid Value No. Section No. Measure Quantity 3471.0001 Traffic Control 3471 13 MO 8 $4,425.00 $35,400.00 3471.0003 Traffic Control Details 3471 13 EA 1 $10,000.00 $10,000.00 3125.0101 SWPPP t 1 acre(NOI/NOT Required) 31 25 00 LS 1 $7,800.00 $7,800.00 3110.0101 Site Clearing 31 1000 LS 1 $59,500.00 $59,500.00 0241.3019 Remove 36"Storm Line 0241 14 LF 70 $50.00 $3,500.00 0241.3021 Remove 42"Storm Line 0241 14 LF 430 $35.00 $15,050.00 0241.3026 Remove 72"Storm Line 0241 14 LF 60 $100.00 $6,000.00 0241.0800 Remove Concrete Rip Rap 0241 13 SY 745 $15.00 $11,175.00 0241.4401 Remove Headwall/SET 0241 14 EA 3 $5,000.00 $15,000.00 0241.0500 Remove Fence 0241 13 LF 200 $3.00 $600.00 9999.0001 Remove Concete Cellar 0241 13 EA 1 $8,000.00 $8,000.00 3123.0101 Unclassified Excavation By Plan 31 23 16 CY 62310 $14.88 $927,172.80 9999.0002 8x3 Box Culvert 3341 10 LF 16 $625.00 $10,000.00 3349.1007 36"Flared Headwall,1 Pipe 33 49 40 EA 1 $4,200.00 $4,200.00 3349.1009 42"Flared Headwall, 1 Pipe 33 49 40 EA 1 $5,200.00 $5,200.00 3349.1015 72"Flared Headwall, 1 Pipe 33 49 40 EA 1 $8,000.00 $8,000.00 3137.0101 Concrete Riprap 31 3700 SY 215 $73.50 $15,802.50 3231.0305 Steel Gate 32 31 26 EA 5 $2,500.00 $12,500.00 3231.0213 Wire Mesh Fence,Metal Posts 32 31 26 LF 225 $10.00 $2,250.00 3291.0100 Topsoil(New or Reused) 3291 19 CY 4400 $4.00 $17,600.00 3292.0500 Seeding,Soil Retention Blanket 32 92 13 SY 16475 $3.39 $55,850.25 3292.0400 Seeding,Hydromulch 32 92 13 SY 23125 $2.66 $61,512.50 9999.0003 Remove 8x3 Box Culvert 0241 14 LF 16 $250.00 $4,000.00 9999.0004 Stormwater Field Order Allowance EA 1 $1.00 $50,000.00 Total Mill $1,346,113.05 END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Dry Branch Credo Interim Regional Detention Basin Form Revised 20120120 City Project No.00485 00 43 13 BID BOND Pape 1 of I SECTION 00 4313 BID BOND KNOW ALL BY THESE PRESENTS: That we,(Bidder Name) RPM xConstruction, LLC hereinafter called the Principal,and(Surety Name) North American Specialty Insurance Company a corporation or firm duly authorized to transact surety business in the State of Texas, hereinafter called the Surety, are held and firmly bound unto the City, hereinafter called the Obligee, in the sum of Five Percent of the Greatest Amount Bid and No/100 Dollars ($5%GAB .00), the payment of which sum will be well and truly made and the said Principal and the said Surety,bind ourselves,our heirs,executors,administrators,successors and assigns,jointly and severally,firm by these presents. WHEREAS, the Principal has submitted a proposal to perform work for the following project of the Obligee, identified as Dry Branch Creek Interim Regional Detention Basin Between NE 28th St and Hollis St NOW, THEREFORE, if the Obligee shall award the Contract for the foregoing project to the Principal, and the Principal shall satisfy all requirements and conditions required for the execution of the Contract and shall enter into the Contract in writing with the Obligee in accordance with the terms of such proposal, then this bond shall be null and void. If the Principal fails to execute such Contract in accordance with the terms of such proposal or fails to satisfy all requirements and conditions required for the execution of the Contract in accordance with the proposal or fails to satisfy all requirements and conditions required for the execution of the Contract in accordance with the proposal, this bond shall become the property of the Obligee, without recourse of the Principal and/or Surety, not to exceed the penalty hereof, and shall be used to compensate Obligee for the difference between Principal's Total Bid Amount and the next selected Bidder's Total Bid Amount. SIGNED this 5th day of May 2016. By: RPM xConstruction, LLC ignature and Title of Principe 'By: aAm erican Specialty Insurance ompany 4\ Andrea Rose Crawford (Signature of Attorney-of-Fact) 'Attach Power of Attorney(Surety)for Attorney-in-Fact Impressed Surety Seal Only END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Dry Branch Creek Interim Regional Detention Basin Form Revised 20110827 City Proled No.00485 NAS SURETY GROUP NORTH AMERICAN SPECIALTY INSURANCE COMPANY WASHINGTON INTERNATIONAL INSURANCE COMPANY GENERAL POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS,THAT North American Specialty Insurance Company,a corporation duly organized and existing under laws of the State of New Hampshire,and having its principal office in the City of Manchester,New Hampshire,and Washington International Insurance Company,a corporation organized and existing under the laws of the State of New Hampshire and having its principal office in the City of Schaumburg,Illinois,each does hereby make,constitute and appoint: SAMMY JOE MULLIS,JR.,JOHN WILLIAM NEWBY,CHERI LYNN IRBY,WILBERT RAYMOND WATSON, CAROLYN J.GOODENOUGH,MICHAEL L.TULLIS,SANDRA LEE RONEY,DEBRA LEE MOON,ANDREA ROSE CRAWFORD, MARY JO ZAKRZEWSKI,JAMES B ROGERS JR.,TROY RUSSELL KEY,and JOINTLY OR SEVERALLY Its true and lawful Attorney(s)-in-Fact,to make,execute,seal and deliver,for and on its behalf and as its act and deed,bonds or other writings obligatory in the nature of a bond on behalf of each of said Companies,as surety,on contracts of suretyship as are or may be required or permitted by law,regulation,contract or otherwise,provided that no bond or undertaking or contract or suretyship executed under this authority shall exceed the amount of: FIFTY MILLION($50,000,000.00)DOLLARS This Power of Attorney is granted and is signed by facsimile under and by the authority of the following Resolutions adopted by the Boards of Directors of both North American Specialty Insurance Company and Washington International Insurance Company at meetings duly called and held on the 9d'of May,2012: "RESOLVED,that any two of the Presidents,any Managing Director,any Senior Vice President,any Vice President,any Assistant Vice President, the Secretary or any Assistant Secretary be,and each or any of them hereby is authorized to execute a Power of Attorney qualifying the attorney named in the given Power of Attorney to execute on behalf of the Company bonds,undertakings and all contracts of surety,and that each or any of them hereby is authorized to attest to the execution of any such Power of Attorney and to attach therein the seal of the Company; and it is FURTHER RESOLVED,that the signature of such officers and the seal of the Company may be affixed to any such Power of Attorney or to any certificate relating thereto by facsimile,and any such Power of Attorney or certificate bearing such facsimile signatures or facsimile seal shall be binding upon the Company when so affixed and in the future with regard to any bond,undertaking or contract of surety to which it is attached." �`�wiuunnup� " fA'' ctz By _ R: S� ;�1 c Stever P.Anderson,Senior Vice President of Wuhlngtoa international lmm�au Company ; s'�L ton S_ &Senior Via President of Nonh American Specialty luonnee Company O Ll �'AMPS 'O$F U':` � �bN+1 " t By Rill Michael A.Iti, • •mpn•y A Senior Vice President of North American Specialty Insurmee Company IN WITNESS WHEREOF,North American Specialty Insurance Company and Washington International Insurance Company have caused their official seals to be hereunto affixed,and these presents to be signed by their authorized officers this 20th day of January 2016 North American Specialty Insurance Company Washington International Insurance Company State of Illinois County of Cook SS: On this 20th day of January ,20L6,before me,a Notary Public personally appeared Steven P.Anderson ,Senior Vice President of Washington International Insurance Company and Senior Vice President of North American Specialty Insurance Company and Michael A.Ito. Senior Vice President of Washington International Insurance Company and Senior Vice President of North American Specialty Insurance Company,personally known to me,who being by me duly sworn,acknowledged that they signed the above Power of Attorney as officers of and acknowledged said instrument to be the voluntary act and deed of their respective companies. OFFICIAL SEAL M ID NNY NOTARY PUBUC,STATE OFIWNOIS M.Kenny,Notary Pubiie�t MY COMMISSION DMES 1210412017 I, Jeffrey Goldberg the duly elected Assistant Secretary of North American Specialty Insurance Company and Washington International Insurance Company,do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney given by said North American Specialty Insurance Company and Washington International Insurance Company,which is still in full force and effect. IN WITNESS WHEREOF,I have set my hand and affixed the seats of the Companies this 5th day of May ,2016 , 'A �oe Jeffrey Gokdbor&Vim President A Assinane Secretary of Washington Jntanatiomd Innsr•nce Company A Noah Anriue Specialty Insurance company North American Specialty Insurance Company Washington International Insurance Company TEXAS CLAIMS INFORMATION IMPORTANT NOTICE ADVISO IMPORTANTE In order to obtain information or make a complaint: Para obtener informacion o pare someter un queja: You may contact Jeffrey Goldberg,Vice President— Puede comunicarse con Jeffrey Goldberg,Vice Claims at 1-800-338-0753 President—Claims,al 1-800-338-0753 You may call Washington International Insurance Usted puede Ilamr al numero de telefono gratis de Company and/or North American Specialty Insurance Washington International Insurance Company and/or Company's toll-free number for information or to North American Specialty Insurance Company's pare make a complaint at: informacion o para someter una queja al: 1-800-338-0753 1-800-338-0753 You may also write to Washington International Usted tambien puede escribir a Washington Insurance Company and/or North American Specialty International Insurance Company and/or North Insurance Company at the following address: American Specialty Insurance Company al: 475 N.Martingale Road 475 N. Martingale Road Suite 850 Suite 850 Schaumburg,IL 60173 Schaumburg,IL 60173 You may contact the Texas Department of Insurance Puede escribir al Departmento de Seguros de Texas to obtain information on companies,coverages, para obtener informacion acerca de companias. rights or complaints at: cobenuras,derechos o quejas al- 1-800-252-3439 1-800-252-3439 You may write the Texas Department of Insurance: Puede escribir al Departmento de Seguros de Texas: P.O. Box 149104 P.O. Box 149104 Austin,TX 78714-9104 Austin,TX 78714-9104 Fax: (512)475-1771 Fax: (512)475-1771 Web: htty://www.tdi.state.tx.us Web: htto://www.tdi.state.tx,us Email:Consume rProtectionOtdi.state.tx.us Email:ConsumerProtection®tdi.state.tx.us PREMIUM OR CLAIM DISPUTES: DISPUTAS SOBRE PRIMAS O RECLAMOS: Should you have a dispute concerning your premium Si tiene una disputa concerniente a su prima o a un or about a claim you should first contact the reclamo,debe comunicarse con el Washington Washington International Insurance Company and/or International Insurance Company and/or North North American Specialty Insurance Company. If the American Specialty Insurance Company primero. Si dispute is not resolved,you may contact the Texas no se resuelve la disputa,puede entonces Department of Insurance. comunicarse con el Departmento de Seguros de Texas. ATTACH THIS NOTICE TO YOUR POLICY: UNA ESTE AVISO A SU POLIZA This notice is for information only and does not Este aviso es solo pare proposito de infromacion y no become a part or condition of the attached se convene en parte o condicion del documento document. adjunto. Revised 5/12 475 N.Martingale Road.Suite 1350.Schaumburg,IL 60173 00 43 37 VENDOR COMPLIANCE TO STATE LAW Page 1 of 1 SECTION 00 43 37 VENDOR COMPLIANCE TO STATE LAW NON RESIDENT BIDDER Texas Government Code Chapter 2252 was adopted for the award of contracts to nonresident bidders. This law provides that, in order to be awarded a contract as low bidder, nonresident bidders (out-of-state contractors whose corporate offices or principal place of business are outside the State of Texas) bid projects for construction, improvements, supplies or services in Texas at an amount lower than the lowest Texas resident bidder by the same amount that a Texas resident bidder would be required to underbid a nonresident bidder in order to obtain a comparable contract in the State which the nonresident's principal place of business is located. The appropriate blanks in Section A must be filled out by all nonresident bidders in order for your bid to meet specifications. The failure of nonresident bidders to do so will automatically disqualify that bidder. Resident bidders must check the box in Section B. A. Nonresident bidders in the State of State Here or Blank, our principal place of business, are required to be 6A Here percent lower than resident bidders by State Law. A copy of the statute is attached. Nonresident bidders in the State of =e Here or Blank, our principal place of business, are not required to underbid resident bidders. B. The principal place of business of our company or our parent company or majority owner is in the State of Texas.,,;el BIDDER: Company Name Here RQM L-L-t- By: Printed Name Here Address Here Address Here or Space (Signature) City, State Zip Code Here Title: Title Here Date: CFT. WORTH,CORD TARY TX END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20110627 00 41 00_00 43 13_00 42 43_00 43 37_00 45 12_00 35 13—Bid Proposal Workbook.xls 0045 11 -1 BIDDERS PREQUALIFICATIONS Page 1 of 3 1 SECTION 00 45 11 2 BIDDERS PREQUALIFICATIONS 3 4 1. Summary.All contractors are required to be prequalified by the City prior to submitting 5 bids.To be eligible to bid the contractor must submit Section 00 45 12,Prequalification 6 Statement for the work type(s) listed with their Bid. Any contractor or subcontractor who is 7 not prequalified for the work type(s) listed must submit Section 00 45 13,Bidder 8 Prequalification Application in accordance with the requirements below. 9 10 The prequalification process will establish a bid limit based on a technical evaluation and 11 financial analysis of the contractor. The information must be submitted seven(7) days prior 12 to the date of the opening of bids. For example,a contractor wishing to submit bids on 13 projects to be opened on the 7th of April must file the information by the 31 st day of March 14 in order to bid on these projects. In order to expedite and facilitate the approval of a Bidder's 15 Prequalification Application,the following must accompany the submission. 16 a. A complete set of audited or reviewed financial statements. 17 (1) Classified Balance Sheet 18 (2) Income Statement 19 (3) Statement of Cash Flows 20 (4) Statement of Retained Earnings 21 (5) Notes to the Financial Statements, if any 22 b. A certified copy of the firm's organizational documents (Corporate Charter, Articles 23 of Incorporation,Articles of Organization,Certificate of Formation,LLC 24 Regulations,Certificate of Limited Partnership Agreement). 25 c. A completed Bidder Prequalification Application. 26 (1) The firm's Texas Taxpayer Identification Number as issued by the Texas 27 Comptroller of Public Accounts. To obtain a Texas Taxpayer Identification 28 number visit the Texas Comptroller of Public Accounts online at the 29 following web address.www.window.state.tx.us/taLcperniit and fill out the 30 application to apply for your Texas tax ID. 31 (2) The firm's e-mail address and fax number. 32 (3) The firm's DUNS number as issued by Dun& Bradstreet. This number 33 is used by the City for required reporting on Federal Aid projects.The DUNS 34 number may be obtained at www.dnb.com. 35 d. Resumes reflecting the construction experience of the principles of the firm for firms 36 submitting their initial prequalification.These resumes should include the size and 37 scope of the work performed. 38 e. Other information as requested by the City. 39 40 2. Prequalification Requirements 41 a. Financial Statements. Financial statement submission must be provided in 42 accordance with the following: 43 (1) The City requires that the original Financial Statement or a certified copy 44 be submitted for consideration. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention.Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 0045 11 -2 BIDDERS PREQUALIFICATIONS Page 2 of 3 1 (2) To be satisfactory,the financial statements must be audited or reviewed 2 by an independent, certified public accounting firm registered and in 3 good standing in any state. Current Texas statues also require that 4 accounting firms performing audits or reviews on business entities within 5 the State of Texas be properly licensed or registered with the Texas State 6 Board of Public Accountancy. 7 (3) The accounting firm should state in the audit report or review whether 8 the contractor is an individual, corporation, or limited liability company. 9 (4) Financial Statements must be presented in U.S. dollars at the current rate 10 of exchange of the Balance Sheet date. 11 (5) The City will not recognize any certified public accountant as 12 independent who is not, in fact, independent. 13 (6) The accountant's opinion on the financial statements of the contracting 14 company should state that the audit or review has been conducted in 15 accordance with auditing standards generally accepted in the United 16 States of America.This must be stated in the accounting firm's opinion. 17 It should: (1) express an unqualified opinion,or(2) express a qualified 18 opinion on the statements taken as a whole. 19 (7) The City reserves the right to require a new statement at any time. 20 (8) The financial statement must be prepared as of the last day of any month, 21 not more than one year old and must be on file with the City 16 months 22 thereafter, in accordance with Paragraph 1. 23 (9) The City will determine a contractor's bidding capacity for the purposes 24 of awarding contracts. Bidding capacity is determined by multiplying the 25 positive net working capital (working capital=current assets—current 26 liabilities)by a factor of 10. Only those statements reflecting a positive 27 net working capital position will be considered satisfactory for 28 prequalification purposes. 29 (10) In the case that a bidding date falls within the time a new financial 30 statement is being prepared,the previous statement shall be updated with 31 proper verification. 32 b. Bidder Prequalification Application. A Bidder Prequalification Application must be 33 submitted along with audited or reviewed financial statements by firms wishing to be 34 eligible to bid on all classes of construction and maintenance projects. Incomplete 35 Applications will be rejected. 36 (1) In those schedules where there is nothing to report,the notation of 37 "None"or"N/A"should be inserted. 38 (2) A minimum of five(5)references of related work must be provided. 39 (3) Submission of an equipment schedule which indicates equipment under 40 the control of the Contractor and which is related to the type of work for 41 which the Contactor is seeking prequalification. The schedule must 42 include the manufacturer,model and general common description of 43 each piece of equipment. Abbreviations or means of describing 44 equipment other than provided above will not be accepted. 45 46 3. Eligibility to Bid 47 a. The City shall be the sole judge as to a contractor's prequalification. 48 b. The City may reject, suspend,or modify any prequalification for failure by the 49 contractor to demonstrate acceptable financial ability or performance. 50 c. The City will issue a letter as to the status of the prequalification approval. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 0045 11 -3 BIDDERS PREQUALIFICATIONS Page 3 of 3 1 d. If a contractor has a valid prequalification letter,the contractor will be eligible to bid 2 the prequalified work types until the expiration date stated in the letter. 3 4 5 6 7 8 END OF SECTION 9 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 004512-1 PREQUALIFICATION STATEMENT Page I of I 1 SECTION 00 45 12 2 PREQUALIFICATION STATEMENT 3 Each Bidder for a City procurement is required to complete the information below by identifying 4 the prequalified contractors and/or subcontractors whom they intend to utilize for the major work 5 type(s)listed. 6 Major Work Prequalification Type Contractor/Subcontractor Company Name Expiration Date N/A 7 8 9 The undersigned hereby certifies that the contractors and/or subcontractors described in 10 the table above are currently prequalified for the work types listed. 11 12 BIDDER: 13 14 By: 15 Company (Please Print) 16 17 Signature: 18 Address 19 20 Title: 21 City/State/Zip (Please Print) 22 23 Date: 24 25 END OF SECTION 26 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 FORTWORTH SECTION 00 4513 BIDDER PREQUALIFICATION APPLICATION Date of Balance Sheet Attached NDA will need to be si ned and emailed to Mendy McCann at mmccann @rpmxconstruction.com-or our om�painancials. Mark only one: Individual Limited Partnership RPM xConstruction, LLC General Partnership Name under which you wish to qualify Corporation X Limited Liability Company Post Office Box City State Zip Code 5208 Tennyson Pkwy Suite 130 Plano TX 75024 Street Address(required) City State Zip Code (214)239-4722 ( 214}239-4799 wbiake @rpmxconstruction.com Telephone Fax Email 12719531910 Texas Taxpayer Identification No. 27-1953191 Federal Employers Identification No. 00603800 DUNS No.(if applicable) MAIL THIS QUESTIONAIRE ALONG WITH FINANCIAL STATEMENTS TO: CITY OF FORT WORTH TEXAS 1000 THROCKMORTON STREET FORT WORTH,TEXAS 76102-6311 AND MARK THE ENVELOPE: "BIDDER PREQUALIFICATION APPLICATION' 0045 13-2 BIDDER PREQUALIFICATION APPLICATION Page 2 of 8 BUSINESS CLASSIFICATION The following should be completed in order that we may properly classify your firm: (Check the block(s)which are applicable—Block 3 is to be left blank if Block 1 and/or Block 2 is checked) Has fewer than 100 employees and/or ElHas less than$6,000,000.00 in annual gross receipts OR Does not meet the criteria for being designated a small business as provided in Section 2006.001 of the Texas Government Code. The classification of your firm as a small or large business is not a factor in determining eligibility to become prequalified. MAJOR WORK CATEGORIES Water Department Augur Boring-24-inch diameter casing and less Augur Boring-Greater than 24-inch diameter casing and greater Tunneling—36-Inches—60—inches,and 350 LF or less Tunneling-36-Inches—60—inches,and greater than 350 LF Tunneling—66"and greater,350 LF and greater Tunneling—66"and greater,350 LF or Less Cathodic Protection Water Distribution, Development, 8-inch diameter and smaller Water Distribution,Urban and Renewal, 8-inch diameter and smaller Water Distribution,Development, 12-inch diameter and smaller Water Distribution,Urban and Renewal, 12-inch diameter and smaller Water Transmission,Development,24-inches and smaller Water Transmission,Urban/Renewal,24-inches and smaller Water Transmission,Development,42-inches and smaller Water Transmission,Urban/Renewal,42-inches and smaller Water Transmission,Development,All Sizes Water Transmission,Urban/Renewal,All Sizes Sewer Bypass Pumping, 18-inches and smaller Sewer Bypass Pumping, 18-inches—36-inches Sewer Bypass Pumping 42-inches and larger CCTV,8-inches and smaller CCTV, 12-inches and smaller CCTV, 18-inches and smaller CCTV,24-inches and smaller CCTV,42-inches and smaller CCTV,48-inches and smaller CITY OF FORT WORTH Dry Branch Creek Interin Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 0045 13-3 BIDDER PREQUALIFICATION APPLICATION Page 3 of 8 MAJOR WORK CATEGORIES,CONTINUED Sewer CIPP, 12-inches and smaller Sewer CIPP,24-inches and smaller Sewer CIPP,42-inches and smaller Sewer CIPP, All Sizes Sewer Collection System, Development, 8-inches and smaller Sewer Collection System, Urban/Renewal, 8-inches and smaller Sewer Collection System, Development, 12-inches and smaller Sewer Collection System, Urban/Renewal, 12-inches and smaller Sewer Interceptors, Development, 24-inches and smaller Sewer Interceptors, Urban/Renewal,24-inches and smaller Sewer Interceptors, Development, 42-inches and smaller Sewer Interceptors, Urban/Renewal,42-inches and smaller Sewer Interceptors, Development,48-inches and smaller Sewer Interceptors, Urban/Renewal,48-inches and smaller Sewer Pipe Enlargement 12-inches and smaller Sewer Pipe Enlargement 24-inches and smaller Sewer Pipe Enlargement,All Sizes Sewer Cleaning,24-inches and smaller Sewer Cleaning,42-inches and smaller Sewer Cleaning, All Sizes Sewer Cleaning, 8-inches and smaller Sewer Cleaning, 12-inches and smaller Sewer Siphons 12-inches or less Sewer Siphons 24-inches or less Sewer Siphons 42-inches or less Sewer Siphons All Sizes Transportation Public Works Asphalt Paving Construction/Reconstruction(LESS THAN 15,000 square yards) Asphalt Paving Construction/Reconstruction(15,000 square yards and GREATER) Asphalt Paving Heavy Maintenance(UNDER$1,000,000) Asphalt Paving Heavy Maintenance($1,000,000 and OVER) Concrete Paving Construction/Reconstruction(LESS THAN 15,000 square yards) Concrete Paving Construct ion/Reconstruction(15,000 square yards and GREATER) Roadway and Pedestrian Lighting CITY OF FORT WORTH Dry Branch Creek Interin Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 0045 13-4 BIDDER PREQUALIFICATION APPLICATION Page 4 of 8 1. List equipment you do not own but which is available by renting DESCRIPTION OF EQUIPMENT NAME AND DETAILED ADDRESS OF OWNER N/A 2. How many years has your organization been in business as a general contractor under your present name? 6 years List previous business names: N/A 3. How many years of experience in 6 years construction work has your organization had: (a) As a General Contractor: (b)As a Sub-Contractor: 6 years 4. *What projects has your organization completed in Texas and elsewhere? CLASS LOCATION NAME AND DETAILED CONTRACT OF DATE CITY-COUNTY- ADDRESS OF OFFICIAL TO AMOUNT WORK COMPLETED STATE WHOM YOU REFER 9,658,209.68 Excavation 1/5/2016 Grand Prairie-Tarrant-TX Pritchard&Assoc-Roger Dahlin,roger@pdtchardassociates.co 2,788,000.00 Excavation 8/6/2015 Frisco-Collin-TX FINDEV,LLC-Bob Finley,finley@yahoo.com 3,980,000.00 Excavation 6/18/2015 Dallas-Dallas-TX Balfour Beatty-Sylvia Schoen,sschoenCl altourbeattyus.com 3,405,728.15 Excavation 12/22/2014 Tyler-Smith-TX dill&Wlkinson-Ryan Shipley,rshipley@hill-%vilkinson.com 3,229,689.54 Excavation 5/10/2015 Dallas-Dallas-TX Billingsley-Steve Jones,sjones @billingsleyco.com 3,651,950.22 Excavation 10/30/2015 McKinney-Collin-TX BT Land Development-Shane White shane.white bt-land.00 565.378.64 Excavation 3/10/2016 Ft Worth-Tarrant-TX Ridgemont-KEvin Mezger,kmezger @ddgemont.com *If requalifying only show work performed since last statement. S.Have you ever failed to complete any work awarded to you? No If so,where and why? 6.Has any officer or owner of your organization ever been an officer of another organization that failed to complete a contract? No If so,state the name of the individual,other organization and reason. 7.Has any officer or owner of your organization ever failed to complete a contract executed in his/her name? No If so,state the name of the individual,name of owner and reason. CITY OF FORT WORTH Dry Branch Creek Interin Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 004513-5 BIDDER PREQUALIFICATION APPLICATION Page 5 of 8 8. In what other lines of business are you financially interested? NIA 9. Have you ever performed any work for the City? NIA If so,when and to whom do you refer? 10. State names and detailed addresses of all producers from whom you have purchased principal materials during the last three years. NAME OF FIRM OR COMPANY DETAILED ADDRESS Holt Cat-John Burke-972.721.2803 2000 E.Airport Fnvy,Irving,TX 75062 US Lime-Henry Rodriquez-972.991.8400 5429 LBJ Frvvy,Dallax,TX 75240 Reeder Distributors-Susan Tisano-817.429.6957 5450 Wilbar ,er,Fort Worth TX 76119 RDO Equipment-Jason Kreps-701.526.9706 3230 E.Airport Frw ,Irving TX 75062 Hanes Geo-Jason Martin-817.527.4519 1 615 Westport Pkwy,Suite 300,Grapevine,TX 76051 LHoist North America-Deborah Hickey-817.806.163 5274 Paysphere Circle,Chicago,IL 60674 11. Give the names of any affiliates or relatives currently debarred by the City. Indicate your relationship to this person or firm. NIA 12. What is the construction experience of the principal individuals in your organization? PRESENT MAGNITUDE POSITION OR YEARS OF AND TYPE OF IN WHAT NAME OFFICE EXPERIENCE WORK CAPACITY Bill Penz VP-Estimating 22 yrs Estimating 100% Barry Rich President 27 yrs Overall Operations 100% Peter Dawson VP-General Manager 27 yrs Internal Operations 100% 13. If any owner,officer,director,or stockholder of your firm is an employee of the City,or shares the same household with a City employee,please list the name of the City employee and the relationship.In addition,list any City employee who is the spouse,child,or parent of an owner,officer,stockholder,or director who does not live in the same household but who receives care and assistance from that person as a direct result of a documented medical condition.This includes foster children or those related by adoption or marriage. NIA CITY OF FORT WORTH Dry Branch Creek Interi Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2D12 L'Ty 3RC RETARy WORTH,TX CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 004540-1 MINORITY AND WOMEN BUSINESS ENTERPRISE GOAL Page 1 of 1 1 SECTION 00 45 40 2 MINORITY BUSINESS ENTERPRISE GOAL 3 APPLICATION OF POLICY 4 If the total dollar value of the contract is greater than $50,000, then the MBE subcontracting goal 5 may be applicable. If the total dollar value of the contract is $50,000 or less, the MBE 6 subcontracting goal is not applicable. 7 8 POLICY STATEMENT 9 It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minority 10 Business Enterprises (MBE) in the procurement of all goods and services. All requirements and 11 regulations stated in the City's current Business Diversity Enterprise Ordinance apply to this bid. 12 13 MBE PROJECT GOAL 14 The City's MBE goal on this project is 15 % of the total bid (Base bid applies to Parks and 15 Community Services). Note: If both MBE and SBE subcontracting goals are established for this 16 project,then an Offeror must submit both a MBE Utilization Form and a SBE Utilization Form to be 17 deemed responsive. 18 19 COMPLIANCE TO BID SPECIFICATIONS 20 On City contracts greater than $50,000 where a MBE subcontracting goal is applied, bidders are 21 required to comply with the intent of the City's Business Diversity Ordinance by one of the 22 following: 23 1. Meet or exceed the above stated MBE goal through MBE subcontracting participation,or 24 2. Meet or exceed the above stated MBE goal through MBE Joint Venture participation,or 25 3. Good Faith Effort documentation,or; 26 4. Waiver documentation. 27 Failure to comply with the City's M/WBE Ordinance, shall result in the Bid being considered non- 28 responsive.Any questions,please contact the M/WBE Office at(817) 392-6104. 29 30 SUBMITTAL OF REQUIRED DOCUMENTATION 31 The applicable documents must be received by the Managing Department, within the following 32 times allocated, in order for the entire bid to be considered responsive to the specifications. The 33 01fercir shall deliver the MBE documentation in person to the appropriate employee of the MOO" 34 Departrricilt and obtain a date/time receipt. Such receipt shall be evidence that the City received#lam 35 on in the time allocated. .A, xedcopy will not be al;ccc ted 1. Subcontractor Utilization Form,if goal rcccived by 2:00 p.m., on the second City business days after is met or exceeded: the bid opening date,exclusive of the bid opening date. 2. Good Faith Effort and Subcontractor received by 2:00 p.m., on the second City business days after Utilization Form, if participation is less the bid opening date,exclusive of the bid opening date. than stated goal: 3. Good Faith Effort and Subcontractor received by 2:00 p.m., on the second City business days after Utilization Form, if no MBE participation: the bid opening date, exclusive of the bid opening date. 4. Prime Contractor Waiver Form,if firm received by 2:00 p.m., on the second City business days after will perform all subcontracting/supplier the bid opening date, exclusive of the bid opening date. work: 5. Joint Venture Form, if utilizing a joint received by 2:00 p.m., on the second City business days after venture to meet or exceed goal. the bid opening date,exclusive of the bid opening date. 36 END OF SECTION CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 17,2015 004541-1 SMALL BUSINESS ENTERPRISE GOAL Page 1 of 1 1 SECTION 00 45 41 2 SMALL BUSINESS ENTERPRISE GOAL 3 APPLICATION OF POLICY 4 If the total dollar value of the contract is greater than$50,000,then the SBE subcontracting goal may 5 be applicable. If the total dollar value of the contract is $50,000 or less,the SBE subcontracting goal 6 is not applicable. 7 8 POLICY STATEMENT 9 It is the policy of the City of Fort Worth to ensure the full and equitable participation by Small 10 Business Enterprises (SBE) in the procurement of all goods and services. All requirements and 11 regulations stated in the City's current Business Diversity Enterprise Ordinance apply to this bid. 12 13 SBE PROJECT GOAL 14 The City's SBE goal on this project is % of the total bid (Base bid applies to Parks and 15 Community Services). Note: If both MBE and SBE subcontracting goals are established for this 16 project,then an Offeror must submit both a MBE Utilization Form and a SBE Utilization Form to be 17 deemed responsive. 18 19 COMPLIANCE TO BID SPECIFICATIONS 20 On City contracts greater than $50,000 where a SBE subcontracting goal is applied, bidders are 21 required to comply with the intent of the City's Business Diversity Ordinance by one of the 22 following: 23 1. Meet or exceed the above stated SBE goal through SBE subcontracting participation,or 24 2. Meet or exceed the above stated SBE goal through SBE Joint Venture participation,or 25 3. Good Faith Effort documentation,or; 26 4. Waiver documentation. 27 Failure to comply with the City's Business Diversity Ordinance, shall result in the Bid being 28 considered non-responsive.Any questions,please contact the M/WBE Office at(817)392-6104. 29 30 SUBMITTAL OF REQUIRED DOCUMENTATION 31 The applicable documents must be received by the Managing Department, within the following 32 times allocated, in order for the entire bid to be considered responsive to the specifications. The 33 'shall deliver the SBE documentation in person to the appropriate employee of the 11+'lanai#sing 34 ( and obtain a date/time receipt. Such receipt shall be evidence_that the_City received the 35 kmwneakWort in the time allocated. A faxed copy will not be pgpoto. 1. Subcontractor Utilization Form, if goal is received by 2:00 p.m.,on the second City business days after met or exceeded: the bid opening date,exclusive of the bid opening date. 2. Good Faith Effort and Subcontractor received by 2:00 p.m., on the second City business days after Utilization Form,if participation is less than the bid opening date,exclusive of the bid opening date. stated goal: 3. Good Faith Effort and Subcontractor received by 2:00 p.m.,on the second City business days after Utilization Form,if no MBE participation: the bid opening date,exclusive of the bid opening date. 4. Prime Contractor Waiver Form, if firm will received by 2:00 p.m.,on the second City business days after perform all subcontracting/supplier work: the bid opening date,exclusive of the bid opening date. 5. Joint Venture Form, if utilizing a joint received by 2:00 p.m.,on the second City business days after venture to meet or exceed goal. the bid opening date,exclusive of the bid opening date. 36 END OF SECTION CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 17,2015 00 52 43- 1 Agreement Page l of 4 1 SECTION 00 52 43 2 AGREEMENT 3 THIS AGREEMENT, authorized on June 21, 2016 is made by and between the City of Forth 4 Worth, a Texas home rule municipality, acting by and through its duly authorized City Manager, 5 ("City"), and RPM xConstruction, L.L.C, authorized to do business in Texas, acting by and 6 through its duly authorized representative, ("Contractor"). 7 City and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as 8 follows: 9 Article 1. WORK 10 Contractor shall complete all Work as specified or indicated in the Contract Documents for the 11 Project identified herein. 12 Article 2.PROJECT 13 The project for which the Work under the Contract Documents may be the whole or only a part is 14 generally described as follows: 15 Dry Branch Creek Interim Regional Detention Basin 16 City Proieet Number C00485 17 Article 3. CONTRACT TIME 18 3.1 Time is of the essence. 19 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract 20 Documents are of the essence to this Contract. 21 3.2 Final Acceptance. 22 The Work will be complete for Final Acceptance within 280 days after the date when the 23 Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions. 24 3.3 Liquidated damages 25 Contractor recognizes that time is of the essence of this Agreement and that City will 26 suffer financial loss if the Work is not completed within the times specified in Paragraph 27 3.2 above, plus any extension thereof allowed in accordance with Article 12 of the 28 General Conditions. The Contractor also recognizes the delays, expense and difficulties 29 involved in proving in a legal proceeding, the actual loss suffered by the City if the Work 30 is not completed on time. Accordingly, instead of requiring any such proof, Contractor 31 agrees that as liquidated damages for delay (but not as a penalty), Contractor shall pay 32 City Six Hundred Fifty Dollars ($650.00) for each day that expires after the time 33 specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of 34 Acceptance. CITY OF FORT WORTH Dn BranC17 Creek/nlerim Regional Del^rtriarr Basin STANDARD CONSTRUCTION SPECIFICATION DOCIIMEN TS Cily Project Number('00485 Revised August 17,2012 005243-2 Agreement Page 2 of 4 35 Article 4. CONTRACT PRICE 36 City agrees to pay Contractor for performance of the Work in accordance with the Contract 37 Documents an amount in current funds of ONE MILLION, THREE HUNDRED FORTY-SIX 38 THOUSAND, ONE HUNDRED THIRTEENAND 051100 DOLLARS ($1,346,113.05). 39 Article 5. CONTRACT DOCUMENTS 40 5.1 CONTENTS: 41 A. The Contract Documents which comprise the entire agreement between City and 42 Contractor concerning the Work consist of the following: 43 1. This Agreement. 44 2. Attachments to this Agreement: 45 a. Bid Form 46 1) Proposal Form 47 2) Vendor Compliance to State Law Non-Resident Bidder 48 3) Prequalification Statement 49 4) State and Federal documents(project specific) 50 b. Current Prevailing Wage Rate Table 51 c. Insurance ACORD Form(s) 52 d. Payment Bond 53 e. Performance Bond 54 f. Maintenance Bond 55 g. Power of Attorney for the Bonds 56 h. Worker's Compensation Affidavit 57 i. MBE and/or SBE Commitment Form 58 3. General Conditions. 59 4. Supplementary Conditions. 60 5. Specifications specifically made a part of the Contract Documents by attachment 61 or, if not attached, as incorporated by reference and described in the Table of 62 Contents of the Project's Contract Documents. 63 6. Drawings. 64 7. Addenda. 65 8. Documentation submitted by Contractor prior to Notice of Award. 66 9. The following which may be delivered or issued after the Effective Date of the 67 Agreement and, if issued, become an incorporated part of the Contract Documents: 68 a. Notice to Proceed. 69 b. Field Orders. 70 c. Change Orders. 71 d. Letter of Final Acceptance. 72 73 CITY OF FORT WORTI I Diy Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Citl Project Number('00485 Revised August 17,2012 005243-3 Agreement Page 3 of 4 74 Article 6. INDEMNIFICATION 75 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own 76 expense, the city, its officers, servants and employees, from and against any and all 77 claims arising out of, or alleged to arise out of, the work and services to be performed 78 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees 79 under this contract. This indemnification provision is specifically intended to operate 80 and be effective even if it is alleged or proven that all or some of the damaLles being 81 sought were caused, in whole or in part, by any act, omission or negligence of the city. 82 This indemnity provision is intended to include, without limitation, indemnity for 83 costs, expenses and legal fees incurred by the city in defending against such claims and 84 causes of actions. 85 86 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, 87 the city,its officers,servants and employees,from and against any and all loss, damage 88 or destruction of property of the city, arising out of,or alleged to arise out of,the work 89 and services to be performed by the contractor, its officers, agents, employees, 90 subcontractors, licensees or invitees under this contract. This indemnification 91 provision is specifically intended to operate and be effective even if it is alleged or 92 proven that all or some of the damages beinp, sought were caused, in whole or in part, 93 by any act, omission or negligence of the city. 94 95 Article 7. MISCELLANEOUS 96 7.1 Terms. 97 Terms used in this Agreement which are defined in Article 1 of the General Conditions will 98 have the meanings indicated in the General Conditions. 99 7.2 Assignment of Contract. 100 This Agreement, including all of the Contract Documents may not be assigned by the 101 Contractor without the advanced express written consent of the City. 102 7.3 Successors and Assigns. 103 City and Contractor each binds itself, its partners, successors, assigns and legal 104 representatives to the other party hereto, in respect to all covenants, agreements and 105 obligations contained in the Contract Documents. 106 7.4 Severability. 107 Any provision or part of the Contract Documents held to be unconstitutional, void or 108 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all 109 remaining provisions shall continue to be valid and binding upon CITY and 110 CONTRACTOR. 111 7.5 Governing Law and Venue. 112 This Agreement, including all of the Contract Documents is performable in the State of 113 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the 114 Northern District of Texas, Fort Worth Division. CITY OF FORT WORTH Dt1 Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project Number('00485 Revised August 17,2012 005243-4 Agreement Page 4 of 4 115 7.6 Other Provisions. 116 The Contractor agrees to pay at least minimum wage per hour for all labor as the same is 117 classified, promulgated and set out by the City, a copy of which is attached hereto and 118 made a part hereof the same as if it were copied verbatim herein. 119 7.7 Authority to Sign. 120 Contractor shall attach evidence of authority to sign Agreement, if other than duly 121 authorized signatory of the Contractor. 122 123 IN WITNESS WHEREOF, City and Contractor have executed this Agreement in multiple 124 counterparts. 125 126 This Agreement is effective as of the last date signed by the Parties("Effective Date"). 127 Contractor: City of Fort Worth B Jay Chapa B : Assistant City Mana (Signature) _ pQRA Date Attest: g� (Printed Name) City Sec etary Title: (Seal) 1. -�C,S� � AA Address: ^as -Ten ii isi rl — M&C C-2777$ Fear, 4&W:Z09y-SS45�,1 Z. 101,1 C Date: 4/Z, Il V -City/St e/Zi : `t' Approved as to Form and Legality: Date B Assistant City Attorney p�w�ty 128 129 130 AP Z R OVAL RECOMM' ENDED: 131 132 r � 133 t�J 134 Douglas 'ersig, P.E. 135 DIRECT 6k, 136 Transportation &Public Works Department 137 MICIAL RECORD CITY SECRETARY CITY OF FORT WORTH ft WORTH,+H,Tx Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DO - City Project Number C00485 Revised August 17,2012 006113-1 PERFORMANCE BOND Pap 142 1 SECTION 00 6113 BOND 8 2216192 2 PERFORMANCE BOND 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 That we,RPMxConstruction.LLG,known as"Principal"herein and 8 North American Specialty Insurance Company a corporate surety(sureties,if more than 9 one)duly authorized to do business in the State of Texas,known as"Surety"herein(whether one 10 or more),are held and firmly bound unto the City of Fort Worth,a municipal corporation created I I pursuant to the laws of Texas,known as"City"herein,in the penal sum of,ONE MILLION, 12 THREE HUNDRED FORTY-SIX THOUSAND,ONE HUNDRED THIRTEENAND O5/100 13 Dollars($1.346.113.05), lawful money of the United Statcs,to be paid in Fort Worth,Tarrant 14 County,Texas for the payment of which sum well and truly to be made,we bind ourselves,our 15 heirs,executors,administrators,successors and assigns,jointly and severally,firmly by these 16 presents. 17 WHEREAS,the Principal has entered into a certain written contract with the City 18 awarded the 21st day of June,2016,which Contract is hereby referred to and made a part hereof 19 for all purposes as if fully set forth herein,to furnish all materials,equipment labor and other 20 accessories defined by law,in the prosecution of the Work,including any Change Orders,as 21 provided for in said Contract designated as Dry Branch Creek Interim Rerionat Ddention 22 Basin,City Proiect No. C00485: 23 NOW,THEREFORE,the condition of this obligation is such that if the said Principal 24 shall faithfully perform it obligations under the Contract and shall in all respects duly and 25 faithfully perform the Work,including Change Orders,under the Contract,according to the plans, 26 specifications,and contract documents therein referred to,and as well during any period of 27 extension of the Contract that may be granted on the part of the City,then this obligation shall be 28 and become null and void,otherwise to remain in full force and effect. 29 PROVIDED FURTHER,that if any legal action be filed on this Bond,venue shall lie in 30 Tarrant County,Texas or the United States District Court for the Northern District of Texas,Fort 31 Worth Division. 32 This bond is made and executed in compliance with the provisions of Chapter 2253 of the 33 Texas Government Code,as amended,and all liabilities on this bond shall be determined in 34 accordance with the provisions of said statue. 35 IN WITNESS WHEREOF,the Principal and the Surety have SIGNED and SEALED 36 this instrument by duly authorized agents and officers on this 21st day of June.2016. CRY OF FORT WORTH Dry fimmch Cme41ht*A*ftwn l DeNafim Hash STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Prod NmaberC00485 Revised July 1.201 I 006113-2 PERFORMANCE BOND Page 2 an 1 PRINCIPAL: 2 RIPM aConstructlon LLC 3 _. 4 5 BY: 6 Signature 7 9 10 ci tary hJatne;and 11 12 Address:.3205 Tennyson Pkwy#130 13 Plano,TX 75024 14 15 - 16 witness as to Prigpil5il 17 SURETY: 18 North American Specialty Insurance Company 19 20 21 B' 22 S 23 24 Debra Lee Moon,AttornMin-Fact 25 Name and Title 26 27 Address: 650 Elm Street 29 Manchester,NH 03101 29 30 31 W Is ato$Wgy Telephone Number. (603)644-6600 32 33 34 35 'Note: If signed by an officer of the Surety Company,there must be on file a certified extract 36 from the by-laws showing that this person has authority to sign such obligation, If 37 Surety's physical address is different from its mailing address, both must be provided 38 The date of the bond shall not be prior to the date the Contract is awarded. 39 OFFICIAL RECORD CITY SECRETARY FT, WORTill Tx =y9vf0kTWOvM Dry Bm wh rmk 1nted a Rsgtmd D ruwA►►go* �17t1t11�1,�tR'FIOttSPECIFICATION DOCUMENTS CivPrWMivUWb"C0W5 >ts4t`scd 1Wg 1i20t1 006114-1 PAYMENT BOND Page 1 of 2 SECTION 00 61 14 2 PAYMENT BOND BOND#2216192 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 That we, RPM xConstruction. L.L.C., known as "Principal' herein, and 8 North American&MIally Insurance Compa®y a corporate surety 9 (sureties duly authorized to do business in the State of Texas, known as "Surety" herein 10 (whether one or more), are held and firmly bound unto the City of Fort Worth, a municipal I l corporation created pursuant to the laws of the State of Texas, known as "City"herein, in the 12 penal sum of ONE MILLION, THREE HUNDRED FORTY-SIX THOUSAND. ONE 13 HUNDRED THIRTEEN AND 05 1100 Dollars ($1346.113.05), lawful money of the United 14 States, to be paid in Fort Worth,Tarrant County,Texas,for the payment of which sum well and 15 truly be made, we bind ourselves, our heirs, executors, administrators, successors and assips- 16 jointly and severally,firmly by these presents: 17 WHEREAS,Principal has entered into a certain written Contract with City,awarded the 18 21st day of June.2016,which Contract is hereby referred to and made a part hereof for all 19 purposes as if fully set forth herein,to furnish all materials,equipment, labor and other 20 accessories as defined by law,in the prosecution of the Work as provided for in said Contract and 21 designated as Dry Branch Creek Interim Regional Detention Basin,City Proiect No. C00485, 22 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if 23 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in 24 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under 25 the Contract, then this obligation shall be and become null and void; otherwise to remain in full 26 force and effect. 27 This bond is made and executed in compliance with the provisions of Chapter 2253 of the 28 Texas Government Code, as amended, and all liabilities on this bond shall be determined in 29 accordance with the provisions of said statute. 30 CITY OF FORT WORTH Dry&wick Crn4 hWrtm Don dw Hach STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS C10,A*0 MM6erC0*M Revsed July 1,2011 006114-2 PAYMENT BOND Fa$¢2 oft i IN WITNESS WHEREOF,the Principal and Surety have each SIGNED and SEALED 2 this instrument by duty authorized agents and officers on this the 21st day of June,2016. 3 PRINCIPAL: RPM xConstraction.LLC ATTEST: BY: , Signature (Principal)Secretary Wmi; ad Title Address: 5205 Tennyson Pkwy#130 Plano,TX 75024 Witness as to Porcipal SURETY: North American Sneclaill Inanrance rampany ATTEST: -..- Signature zebra L•le Mean.Attnrecv i�n.Fact (Surety)Secretary Name and Title Address: „fig Elm street Manchester,NH 03101 Telephone Number. (603)644-"N 4 5 Note: If signed by an officer of the Surety, there must be on file a certified extract from the 6 bylaws showing that this person has authority to sign such obligation. If Surety'3 physical 7 address is different from its mailing address,both must be provided. 8 9 The date of the bond shall not be prior to the date the Contract is awarded. 10 END OF SECTION 11 OFFICIAL RECORD CITY SECRETARY FT- WORTH, TX CITY 01F FORT WORTH Dry Branch Cmek interim Regiao l Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City P°rrli>a Nmwber C0048S RcvhW Ady 1,2011 006119-1 MAKIINANCE WND Page 100 I SECTION 00 6119 2 MAINTENANCE BOND BOND#2216193 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 8 That we RPMxConstraetion,L.L.C.,known as"Principal"herein and 9 North American Specialty Insurance Company ,a corporate surety(sureties,if more than 10 one)duly authorized to do business in the State of Texas,known as"Surety"herein(whether one 11 or more),are held and firmly bound unto the City of Fort Worth,a municipal corporation created 12 pursuant to the laws of the State of Texak known as"City"herein,in the sum of ONE 13 MILLION, THREE HUNDRED FORTY-SIX THOUSAND. ONE HUNDRED THIRTEEN 14 AND 05/100 Dollars(S1346,113.05), lawful money of the United States,to be paid in Fort 15 Worth,Tarrant County,Texas,for payment of which sum well and truly be made unto the City 16 and its successors,we bind ourselves,our heirs,executors,administrators,successors and assigns, 17 jointly and severally,firmly by these presents. 18 19 WHEREAS,the Principal has entered into a certain written contract with the City awarded the 20 21st day of June,2016,which Contract is hereby referred to and a made part hereof for all 21 purposes as if fully set forth herein,to furnish all materials,equipment labor and other accessories 22 as defined by law,in the prosecution of the Work,including any Work resulting from a duly 23 authorized Change Order(collectively herein,the"Work")as provided for in said contract and 24 designated as Dry Branch Creek Interim Regional Detention Basin,City Proiect No. C00485: 25 and 26 27 WHEREAS,Principal binds itself to use such materials and to so construct the Work in 28 accordance with the plans,specifications and Contract Documents that the Work is and will 29 remain free from defects in materials or workmanship for and during the period of two(2)years 30 after the date of Final Acceptance of the Work by the City("Maintenance Period");and 31 32 WHEREAS,Principal binds itself to repair or reconstruct the Work in whole or in part 33 upon receiving notice from the City of the need therefor at any time within the Maintenance 34 Period. 35 CITY OF FORT WORTH Dry a mm eh Curt M Urim Rd$khd DeUnNon Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CayProjaartldnikrC00485 RrAscd July 1,2011 dA61 19-2 MAIIi71 WA1M BOND POV2of3 i NOW THEREFORE,the condition of this obligation is such that if Principal shall 2 remedy any defective Work,for which timely notice was provided by City,to a completion 3 satisfactory to the City,then this obligation shall became null and void;otherwise to remain in 4 full force and effect. 5 6 PROVIDED,HOWEVER, if Principal shall fail so to repair or deconstruct any timely 7 noticed defective Work,it is agreed that the City may cause any and all such defective Work to 8 be repaired and/or reconstructed with all associated costs thereof being borne by the Principal and 9 the Surety under this Maintenance bond;and 10 11 PROVIDED FURTHER,that if ony legs)action be filed on this Bond,venue shall lie in 12 Tarrant County,'Texas or the United States District Court for the Northern District of Texas,Fort 13 Worth Division;and 14 15 PROVIDED FURTHER,that this obligation shall be continuous in nature and 16 successive recoveries may be had hereon for successive breaches. 17 18 19 CITY OF FflA7' m9m Dry Branch Cm k 1^WAv*AsXk0W DOWWai Saft 0tAWMWC*NM0CWN SPBCWATMDOCUMENTS C[&PfrlwaAFwuherttiooM krAs1t0,1'otyr 1,lot 1 006119-3 MADI ENANt3;90M Per 3 eta 1 IN WITNESS WHEREOF,the Principal and the Surety have each SIGNED and SEALED this 2 instrument by duly authorized agents and officers on this the 21st day of June,2016. 3 4 PRINCIPAL: 5 RPM:Construction.LLC 6 7 8 BY: 9 Signature 10 11 - 12 13 �Cipal retary N1 . 14 15 Address: 5208 Tennyson Pkwv#130 16 Plano,TX 750241 17 18 10-- 19 Widn ss as to NnchA 20 SURETY: 21 _North American Specialty Insur2nep re mpany 22 23 24 Bl': 25 Signature 26 27 Debra Lee Moon,Attorney-in-Fact 28 ATTEST: Name and Title 29 30 Address: 650 Elm Street 31 (Surety)Secretary Manchester,NH 03101 33 33 34 w*S0 ► � Telephone Number: (603)644-6600 35 36 *Note: If signed by an officer of the Surety Company, there must be on file a certified c&tr4-t 37 from the by-laws showing that this person has authority to sign such obligation. if 38 Surety's physical address is different from its mailing address, both must be provided. 39 The date of the bond shal I not be prior to the date the Contract is awarded. 40 (1) OFFICIAL RECORD CITY SECRETARY FT, MRTH, Tx CrrY OF FORT WORTH Dry Dmnch Cmt lnterlm ftgk ndl Dostw1on Butbo STANDARD CONSTRUCTION SPECIPWATION DOCUMENTS CIV PrgW#Number CM40 RevWed July t.2011 NAS SURETY GROUP NORTH AMERICAN SPECIALTY INSURANCE COMPANY WASHINGTON INTERNATIONAL INSURANCE COMPANY GENERAL POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS,THAT North American Specialty Insurance Company,a corporation duly organized and existing under laws of the State of New Hampshire,and having its principal office in the City of Manchester,New Hampshire,and Washington International Insurance Company,a corporation organized and existing under the laws of the State of New Hampshire and having its principal office in the City of Schaumburg,Illinois,each does hereby make,constitute and appoint: SAMMY JOE MULLIS,JR.,JOHN WILLIAM NEWBY,CHERI LYNN IRBY,WILBERT RAYMOND WATSON, CAROLYN J.GOODENOUGH,MICHAEL L.TULLIS,SANDRA LEE RONEY,DEBRA LEE MOON,ANDREA ROSE CRAWFORD, MARY JO ZAKRZEWSKI,JAMES B ROGERS JR.,TROY RUSSELL KEY,and JOINTLY OR SEVERALLY Its true and lawful Attorney(s)-in-Fact,to make,execute,seal and deliver,for and on its behalf and as its act and deed,bonds or other writings obligatory in the nature of a bond on behalf of each of said Companies,as surety,on contracts of suretyship as are or may be required or permitted by law,regulation,contract or otherwise,provided that no bond or undertaking or contract or suretyship executed under this authority shall exceed the amount of FIFTY MILLION($50,000,000.00)DOLLARS This Power of Attorney is granted and is signed by facsimile under and by the authority of the following Resolutions adopted by the Boards of Directors of both North American Specialty Insurance Company and Washington International Insurance Company at meetings duly called and held on the 9`s of May,2012: "RESOLVED,that any two of the Presidents,any Managing Director,any Senior Vice President,any Vice President,any Assistant Vice President, the Secretary or any Assistant Secretary be,and each or any of them hereby is authorized to execute a Power of Attorney qualifying the attorney named in the given Power of Attorney to execute on behalf of the Company bonds,undertakings and all contracts of surety,and that each or any of them hereby is authorized to attest to the execution of any such Power of Attorney and to attach therein the seal of the Company; and it is FURTHER RESOLVED,that the signature of such officers and the seal of the Company may be affixed to any such Power of Attorney or to any certificate relating thereto by facsimile,and any such Power of Attorney or certificate bearing such facsimile signatures or facsimile seal shall be binding upon the Company when so affixed and in the future with regard to any bond,undertaking or contract of surety to which it is attached." ` Nlllflb ���� TY 4 NA( ��ji1t)I(jTGa= g y apStO �r`Y. 43"'opro' • SERI. = Steven P.Anderson,Sealy Vice PmWcut of Washington Interaatlaaal Itwrance Caopoq SEAL . 1 V3 �1r n e Senior Vice hetWent e(Nenh Annerican Specialty insurance Company j Michael A. 00prr .•.• .. !Sador Vice President of North Aaserlcan Spechth,Issoronce Casapary IN WITNESS WHEREOF,North American Specialty Insurance Company and Washington International Insurance Company have caused their official seals to be hereunto affixed,and these presents to be signed by their authorized officers this 20th day of January ,2016 . North American Specialty Insurance Company Washington International Insurance Company State of Illinois County of Cook SS' On this 20th day of January ,201 before me,a Notary Public personally appeared Steven P.Anderson ,Senior Vice President of Washington International Insurance Company and Senior Vice President of North American Specialty Insurance Company and Michael A.Ito. Senior Vice President of Washington International Insurance Company and Senior Vice President of North American Specialty Insurance Company,personally known to me,who being by me duly sworn,acknowledged that they signed the above Power of Attorney as officers of and acknowledged said instrument to be the voluntary act and deed of their respective companies. pFfICIAL:W:OF M ItENNOTARY PUBLIC.ST ti1JN018 %L Koasoy,Notary rnbtia MY COMMASSION E70IAE8 tZ%W7 I, Jemmy Goldberg . the duly elected Assistant SecEMa of North American Specialty Insurance Company and Washington International Insurance Company,do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney given by said North American Specialty Insurance Company and Washington International Insurance Company,which is still in full force and effect. IN WITNESS WHEREOF,I have set my hand and affixed the seals of the Companies this 21 st day of June ,20 16 . Jeffrey Grtdberg,via PraWat 3 Aasistrat samerary of Washington Intcrandow t Insurance Conwoty&North Aroerim Specialty Inaruee Comomy North American Specialty Insurance Company Washington International Insurance Company TEXAS CLAIMS INFORMATION IMPORTANT NOTICE ADVISO IMPORTANTE In order to obtain information or make a complaint: Para obtener information o pare someter un queja: You may contact Jeffrey Goldberg,Vice President- Puede comunicarse con Jeffrey Goldberg,Vice Claims at 1-800-338-0753 President-Claims,al 1-800-338-0753 You may call Washington International Insurance Listed puede Ilamr al numbro de telefono gratis de Company and/or North American Specialty Insurance Washington International Insurance Company and/or Company's toll-free number for information or to North American Specialty Insurance Company's pare make a complaint at: informacion o para someter una queja al: 1-800.338-0753 1-800-338-0753 You may also write to Washington International Listed tambten puede escribir a Washington insurance Company and/or North American Specialty International Insurance Company and/or North Insurance Company at the following address: American Specialty Insurance Company al: 475 N.Martingale Road 475 N. Martingale Road Suite 850 Suite 850 Schaumburg,IL 80173 Schaumburg,IL 60173 You may contact the Texas Department of Insurance Puede escribir al Departmento de Seguros de Texas to obtain information on companies,coverages, pare obtener informacion acerca de companias, rights or complaints at: coberturas,derechos o quejas al: 1-800-252-3439 1-800-252-3439 You may write the Texas Department of Insurance: Puede escribir al Departmento de Seguros de Texas: P.O.Box 149104 P.O. Box 149104 Austin,TX 78714.9104 Austin,TX 78714-9104 Fax: (512)475-1771 Fax (812)475-1771 Web: httra:/lwww.tdi.state.tx us Web: hfto://www.tdi;st to e.tx us Email:ConsumorProtectionOtdi.state.tx.us Email:ConsumerProtectio nOtdi.stete.tx.us PREMIUM OR CLAIM DISPUTES: DISPUTES SOBRE PRIMAS O RECLAMOS: Should you have a dispute conceming your premium Si tiene una disputa concemiente a su prima o a un or about a claim you should first contact the reclemo,debe comunicarse con el Washington Washington International Insurance Company and/or International Insurance Company and/or North North American Speciatty Insurance Company. If the American Specialty Insurance Company primero. Si dispute is not resolved,you may contact the Texas no se resuelve Is dispute,puede entonces Department of Insurance. comunicarse con el Departmento de Seguros de Texas, ATTACH THIS NOTICE TO YOUR POLICY: UNA ESTE AVISO A SU POUZA This notice is for information only and does not Este aviso es solo pare proposito de infromacion y no become a part or condition of the attached se converte en parts o condition del documento document. adjunto. Revised 5/12 475 N.Martingale Road,Suite 850,Schaumburg,tl 60173 ACC)RIDO® CERTIFICATE OF LIABILITY INSURANCE DATE(MM/DD/YYYY) 7/1/2016 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER,AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy,certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). PRODUCER CONTACT Miranda Amyx Mullis Newby Hurst PHONE (972)201-0100 F'qX (972)201-0123 5057 Keller Springs Rd Ste 400 E-MAIL ac No: ADDRESS:mamyx @mnhins.com INSURERS AFFORDING COVERAGE NAIC# Addison TX 75001 INSURER AAmerisure Partners Insurance 11050 INSURED INSURER B Ameri3Ure Insurance Company 19488 RPM xConstruction, LLC INSURER CNavi ators Insurance Co 42307 5208 Tennyson Parkway, INSURER D: Suite 130 INSURER E: Plano TX 75024 INSURER F: COVERAGES CERTIFICATE NUMBER:16-17 Standard REVISION NUMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES.LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR I A DOE FS U®R - LTR TYPE OF INSURANCE POLICY NUMBER POLICY POLICY LIMITS X COMMERCIAL GENERAL LIABILITY EACH OCCURRENCE $ 1,000,000 A CLAIMS-MADE F OCCUR DAMAGE TO RENTED 1,000 00 PREMISES Ea occurrence $ 1,000,000 CPP2068767 4/1/2016 4/1/2017 MED EXP(Any one person) $ 10,000 -PERSONAL BADVINJURY $ 1,000,000 GENT AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $ 2,000,000 POLICY K PROT- F7] PRODUCTS PRODUCTS-COMP/OP AGG $ 2,000,000 OTHER: $ AUTOMOBILE LIABILITY COMBINED SINGLE LIMIT Ea accident $ 1,000,000 B X ANY AUTO BODILY INJURY(Per person) $ ALL OWNED SCHEDULED CA 2068766 4/1/2016 4/1/2017 BODILY INJURY(Per accident) $ AUTOS AUTOS NON-OWNED PROPERTY DAMAGE X HIRED AUTOS X AUTOS Per accident $ $ X UMBRELLA LIAB X OCCUR EACH OCCURRFNCE $ 5,000,000 B EXCESS LIAB CLAIMS-MADE AGGREGATE $ 5,000,000 DED I I RETENTION$ CU2068769 4/1/2016 4/1/2017 $ WORKERS COMPENSATION AND EMPLOYERS'LIABILITY YIN PTER ER ANY PROPRIETOR/PARTNER/EXECUTIVE E.L.EACH ACCIDENT $ 1,000,000 OFFICER/MEMBEREXCLUDED? FN] B (Mandatory in NH) WC2068770 4/1/2016 4/1/2017 E.L.DISEASE-EA EMPLOYEE $ 1,000,000 R yes,describe under DESCRIPTION OF OPERATIONS below E.L.DISEASE-POLIC Y LIMIT $ 1,000,000 C Excess Liability of H016EXC7278121V 4/1/2016 4/1/2017 Per Occurrence or Event $10,000,000 AmerisurePrimary/Umbrella General Aggregate $10,000,000 DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES (ACORD 101,Additional Remarks Schedule,may be attached if more space is required) Re: 1584 Dry Branch Creek Detention Basin Certificate Holders include: City of Fort Worth, Baird, Hampton & Brown, Inc. and their respective officers, directors,agents and employees CERTIFICATE HOLDER CANCELLATION (817)392-8941 OFFICIAL RECORD SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE City of Fort Worth ( THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN 1000 Throckmorton CITY SECRETARY ACCORDANCE WITH THE POLICY PROVISIONS. Fort Worth, TX 76102 FT. WORTH, TX AUTHORIZED REPRESENTATIVE Sam Mullis/MIRAND ©1988-2014 ACORD CORPORATION. All rights reserved. ACORD 25(2014/01) The ACORD name and logo are registered marks of ACORD INS025 r2ntmrn COMMENTS/REMARKS The General Liability, Automobile and Umbrella policies include a blanket additional insured endorsement that provides additional insured status to the certificate holder only when there is a written contract between the named insured and the certificate holder that requires such status. The General Liability policy includes a blanket additional insured endorsement that provides additional insured status to the certificate holder for ongoing and completed operations only when there is written contract between the named insured and the certificate holder that requires such status. The General Liability, Automobile and Umbrella policies contain an endorsement with primary and noncontributory wording that may apply only when there is a written contract between the named insured and the certificate holder that may require such status. The General Liability, Automobile, Workers Compensation and Umbrella policies include a blanket waiver of subrogation endorsement that provides this feature only when there is a written contract between the named insured and the certificate holder that requires this. OFREMARK COPYRIGHT 2000, AMS SERVICES INC. '4CoRO® CERTIFICATE OF LIABILITY INSURANCE DA 7/1/2016 6 DD/Y 7/1/ THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER,AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy,certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). PRODUCER NAME: Miranda Amyx Mullis Newby Hurst PHONE (972)201-0100 A/C No: (972)201-0123 5057 Keller Springs Rd Ste 400 E-MAIL x ADDRESS:mam Y @mnhins.com INSURERS AFFORDING COVERAGE NAIC# Addison TX 75001 INSURER AAmerisure Partners Insurance 11050 INSURED INSURER B Ameri sure Insurance Company 19488 RPM xConstruction, LLC INSURER CNavi ators Insurance Co 42307 5208 Tennyson Parkway, INSURER D: Spite 130 INSURER E: Plano TX 75024 INSURER F: COVERAGES CERTIFICATE NUMBER:16-17 Standard REVISION NUMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES.LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR TYPE OF INSURANCE ADDL R POLICY EFF POLICY EXP LTR POLICY NUMBER MM/DD/YYYY MM/DD/YYYY LIMITS X COMMERCIAL GENERAL LIABILITY EACH OCCURRENCE $ 1,000,000 A CLAIMS OCCUR DAMAGE TO RENTED 1,000,000 PREMISES Ea occurrence $ CPP2068767 4/1/2016 4/1/2017 MED EXP(Any one person) $ 10,000 PERSONAL BADVINJURY $ 1,000,000 GENT AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $ 2,000,000 POLICY[K ipnoi FI LOC PRODUCTS-COMP/OP AGG $ 2,000,000 OTHER: $ AUTOMOBILE LIABILITY COMBINED SINGLE LIMIT Ea accident $ 1,000,000 B X ANY AUTO BODILY INJURY(Per person) $ ALL OWNED SCHEDULED CA 2068766 4/1/2016 4/1/2017 BODILY INJURY(Per accident) $ AUTOS AUTOS X HIRED AUTOS FX NON-OWNED PROPERTY DAMAGE $ AUTOS Per accident X UMBRELLA LIAB X OCCUR EACH OCCURRENCE $ 5,000,000 B ECESS LIAB CLAIMS-MADE AGGREGATE $ 5,000,000 I I RETENTION CU2068769 4/1/2016 4/1/2017 $ WORKERS COMPENSATION X PER OTH- AND EMPLOYERS'LIABILITY YIN STATUTE ER ANY OFFICER/MEIMBOER EXCLUDED? F`N] NIA XECUTIVE XCLUDEDXECUTIVE � N/A E.L.EACH ACCIDENT $ 1,0 0 000 B (Mandatory in NH) WC2068770 4/1/2016 4/1/2017 E.L.DISEASE-EA EMPLOYEE $ 1,000,000 If yes,describe under DESCRIPTION OF OPERATIONS below E.L.DISEASE-POLICY LIMIT $ 1,000,000 C Excess Liability of H016EXC727812IV 4/1/2016 4/1/2017 Per Occurrence or Event $10,000,000 AmerisurePrimary/Umbrella General Aggregate $10,000,000 DESCRIPTION OF OPERATIONS I LOCATIONS I VEHICLES (ACORD 101,Additional Remarks Schedule,may be attached if more space is required) Re: 1584 Dry Branch Creek Detention Basin Certificate Holders include: City of Fort Worth, Baird, Hampton 6 Brown, Inc. and their respective officers, directors,agents and employees CERTIFICATE HOLDER CANCELLATION (817)392-8941 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE City of Fort Worth THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN 1000 Throckmorton ACCORDANCE WITH THE POLICY PROVISIONS. Fort Worth, TX 76102 AUTHORIZED REPRESENTATIVE Sam Mullis/MIRAND ©1988-2014 ACORD CORPORATION. All rights reserved. ACORD 25(2014/01) The ACORD name and logo are registered marks of ACORD INS025 onta m COMMENTS/REMARKS The General Liability, Automobile and Umbrella policies include a blanket additional insured endorsement that provides additional insured status to the certificate holder only when there is a written contract between the named insured and the certificate holder that requires such status. The General Liability policy includes a blanket additional insured endorsement that provides additional insured status to the certificate holder for ongoing and completed operations only when there is written contract between the named insured and the certificate holder that requires such status. The General Liability, Automobile and Umbrella policies contain an endorsement with primary and noncontributory wording that may apply only when there is a written contract between the named insured and the certificate holder that may require such status. The General Liability, Automobile, Workers Compensation and Umbrella policies include a blanket waiver of subrogation endorsement that provides this feature only when there is a written contract between the named insured and the certificate holder that requires this. OFREMARK COPYRIGHT 2000, AMS SERVICES INC. THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. TEXAS CONTRACTOR'S BLANKET ADDITIONAL INSURED ENDORSEMENT This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE FORM Policy Number Agency Number Policy Effective Date CPP2068767 776315 4/1/2016 Policy Expiration Date Date Account Number 4/1/2017 4/1/2016 20045262 Named Insured Agency Issuing Company RPM XConstructlon, LLC Mullis Newby Hurst Amerisure Partners Insurance Company 1. a. SECTION II -WHO IS AN INSURED is amended to add as an insured any person or organization: Whom you are required to add as an additional insured on this policy under a written contract or written agreement relating to your business. b. The written contract or written agreement must: (1) Require additional insured status for a time period during the term of this policy; and (2) Be executed prior to the "bodily injury", "property damage", or"personal and advertising injury" leading to a claim under this policy. C. If, however: (1) "Your work" began under a letter of intent or work order; and (2) The letter of intent or work order led to a written contract or written agreement within 30 days of beginning such work ;and (3) Your customer's customary contracts require persons or organizations to be named as additional insureds; we will provide additional insured status as specified in this endorsement. However, if you have entered into a construction contract subject to Subchapter C of Chapter 151 of Subtitle C of Title 2 of the Texas Insurance Code with the additional insured, the insurance afforded to such person(s) or organization(s) only applies to the extent permitted by Subchapter C of Chapter 151 of Subtitle C of Title 2 of the Texas Insurance Code. 2. SECTION 11 -WHO IS AN INSURED is amended to add the following: If the additional insured is: a. An individual, their spouse is also an additional insured. b. A partnership or joint venture, members, partners, and their spouses are also additional insureds. c. A limited liability company, members and managers are also additional insureds. d. An organization other than a: (1) Partnership; (2) Joint venture;or Includes copyrighted material of Insurance Services Office, Inc. CG 70 85 09 13 Page 1 of 3 (3) Limited liability company; executive officers and directors of the organization are also additional insureds. Stockholders are also additional insureds, but only with respect to their liability as stockholders. e. A trust, trustees are also insureds, but only with respect to their duties as trustees. 3. The insurance provided under this endorsement is limited as follows: a. That person or organization is an additional insured only with respect to liability arising out of: (1) Premises you: (a) Own; (b) Rent; (c) Lease; or (d) Occupy; or (2) Ongoing operations performed by you or on your behalf. If, however, the written contract or written agreement also requires completed operations coverage, we will also provide completed operations coverage for that additional insured. b. Premises, as respects paragraph 3,a.(1) above, include common or public areas about such premises if so required in the written contract or written agreement. c. Additional insured status provided under paragraphs 3.a.(1)(b) or 3.a.(1)(c) above does not extend beyond the end of a premises lease or rental agreement. d. Ongoing operations, as respects paragraph 3.a (2) above, does not apply to "bodily injury' or"property damage" occurring after: (1) All work to be performed by you or on your behalf for the additional insured(s) at the site of the covered operations is complete including related materials, parts or equipment (other than service, maintenance or repairs); or (2) That portion of"your work" out of which the injury or damage arises is put to its intended use by any person or organization other than another contractor working for a principal as a part of the same project. e. The limits of insurance that apply to the additional insured are the least of those specified in the; (1) Written contract; (2) Written agreement; or (3) Declarations of this policy. The limits of insurance are inclusive of and not in addition to the limits of insurance shown in the Declarations. f. The insurance provided to the additional insured does not apply to "bodily injury", "property damage", or "personal and advertising injury" arising out of an architect's, engineer's, or surveyor's rendering of, or failure to render, any professional services, including but not limited to: (1) The preparing, approving, or failing to prepare or approve: (a) Maps; (b) Drawings; (c) Opinions; (d) Reports; (e) Surveys; Includes copyrighted material of Insurance Services Office, Inc. CG 70 85 09 13 Page 2 of 3 (f) Change orders; (g) Design specifications; and (2) Supervisory, inspection, or engineering services. g. SECTION IV—COMMERCIAL GENERAL LIABILITY CONDITIONS, paragraph 4. Other Insurance is deleted and replaced with the following: 4. Other Insurance. Coverage provided by this endorsement is excess over any other valid and collectible insurance available to the additional insured whether: a. Primary; b. Excess; c. Contingent; or d. On any other basis; unless the written contract or written agreement requires this insurance be primary. In that case, this insurance will be primary without contribution from such other insurance available to the additional insured. h. If the written contract or written agreement as outlined above requires additional insured status by use of CG 20 10 11 85, then the terms of that endorsement, shown below, are incorporated into this endorsement, to the extent such terms do not restrict coverage otherwise provided by this endorsement: ADDITIONAL INSURED -OWNERS, LESSEES OR CONTRACTORS (FORM B) This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART. SCHEDULE Name of Person or Organization: Blanket Where Required by Written Contract or Agreement that the terms of CG 20 10 11 85 apply. (If no entry appears above, information required to complete this endorsement will be shown in the Declarations as applicable to this endorsement.) WHO IS AN INSURED (Section II) is amended to include as an insured the person or organization shown in the Schedule, but only with respect to liability arising out of "your work"for that insured by or for you. Copyright, Insurance Services Office, Inc., 1984 CG 20 10 11 85 L If the written contract or written agreement as outlined above requires additional insured status by use of an Insurance Services Office (ISO) endorsement, then the coverage provided under this CG 70 85 endorsement does not apply. Additional insured status is limited to that provided by the ISO endorsement. Includes copyrighted material of Insurance Services Office, Inc. CG 70 85 09 13 Page 3 of 3 "\ " It l-lJ11,ID L.1 LL1 1..1 V11 I 1 JJ� Policy ##CPP2068767 Eff . 4/1/2016 - 4/1/2017 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. TEXAS CONTRACTOR'S GENERAL LIABILITY EXTENSION ENDORSEMENT This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE FORM Under SECTION I - COVERAGE A. BODILY INJURY AND PROPERTY DAMAGE LIABILITY, paragraph 2. EXCLUSIONS, provisions 1. through 6. of this endorsement amend the policy as follows: 1. LIQUOR LIABILITY Exclusion c. Liquor Liability is deleted. 2. NONOWNED WATERCRAFT Exclusion g.Aircraft,Auto or Watercraft, subparagraph(2) is deleted and replaced with the following: (2) A watercraft you do not own that is: (a) Less than 51 feet long;and (b) Not being used to carry persons or property for a charge. 3. PREMISES ALIENATED A. Exclusion j. Damage to Property, subparagraph (2)is deleted. B. The following paragraph is deleted from Exclusion j. Damage to Property; Paragraph (2)of this exclusion does not apply if the premises are 'your work" and were never occupied, rented or held for rental by you. 4. PROPERTY DAMAGE LIABILITY- ELEVATORS AND SIDETRACK AGREEMENTS A. Exclusion j. Damage to Property, paragraphs(3), (4), and (6)do not apply to the use of elevators. B. Exclusion k. Damage to Your Product does not apply to: 1. The use of elevators; or 2. Liability assumed under a sidetrack agreement. 5. PROPERTY DAMAGE LIABILITY- BORROWED EQUIPMENT A. Exclusion j. Damage to Property, paragraph(4)does not apply to "property damage"to borrowed equipment while at a jobsite and not being used to perform operations. B. With respect to any one borrowed equipment item, provision 5.A, above does not apply to"property damage"that exceeds $25,000 per occurrence or$25,000 annual aggregate. 6. PRODUCT RECALL EXPENSE A. Exclusion n. Recall of Products,Work or Impaired Property does not apply to"product recall expenses" that you incur for the"covered recall'of"your product'. This exception to the exclusion does not apply to "product recall expenses" resulting from: 1. Failure of any products to accomplish their intended purpose; 2. Breach of warranties of fitness, quality, durability or performance; 3. Loss of customer approval or any cost incurred to regain customer approval; 4. Redistribution or replacement of"your product', which has been recalled, by like products or substitutes; 5. Caprice or whim of the insured; Includes copyrighted material of Insurance Services Office, Inc. CG 70 63 07 12 Page 1 of 9 6. A condition likely to cause loss, about which any insured knew or had reason to know at the inception of this insurance; 7. Asbestos, including loss, damage or clean up resulting from asbestos or asbestos containing materials; 8. Recall of"your product(s)"that have no known or suspected defect solely because a known or suspected defect in another of"your product(s)"has been found. B. Under SECTION III -LIMITS OF INSURANCE, paragraph 3. is replaced in its entirety as follows and paragraph 8. is added: 3. The Products-Completed Operations Aggregate Limit is the most we will pay for the sum of: a. Damages under COVERAGE A BODILY INJURY AND PROPERTY DAMAGE LIABILITY because of"bodily injury"and"property damage"included in the "products-completed operations hazard"and b. "Product recall expenses". 8. Subject to paragraph S. above, $25,000 is the most we will pay for all"product recall expenses" arising out of the same defect or deficiency. The insurance afforded by reason of provisions 1. through 6. of this endorsement is excess over any valid and collectible insurance(including any deductible) available to the insured whether primary, excess or contingent,and SECTION IV., paragraph 4. Other Insurance is changed accordingly. 7. BLANKET CONTRACTUAL LIABILITY—RAILROADS When a written contract or written agreement requires Contractual Liability- Railroads, the definition of"insured contract"in Section V- Definitions is replaced by the following with respect to operations performed for, or affecting, a railroad: 9. "Insured Contract" means: a. A contract for a lease of premises. However,that portion of the contract for a lease of premises that indemnifies any person or organization for damage by fire to premises while rented to you or temporarily occupied by you with permission of the owner is not an "insured contract"; b. A sidetrack agreement; c. Any easement or license agreement; d. An obligation, as required by ordinance, to indemnify a municipality, except in connection with work for a municipality; e. An elevator maintenance agreement; f. That part of any other contract or agreement pertaining to your business (including an indemnification of a municipality in connection with work performed for a municipality) under which you assume the tort liability of another party to pay for"bodily injury"or"property damage" to a third person or organization. Tort liability means a liability that would be imposed by law in the absence of any contract or agreement. Paragraph f. does not include that part of any contract or agreement: (1) That indemnifies an architect, engineer or surveyor for injury or damage arising out of: (a) Preparing, approving,or failing to prepare or approve, maps, shop drawings,opinions, reports, surveys,field orders,change orders or drawings and specifications;or (b) Giving directions or instructions,or failing to give them; (2) Under which the insured, if an architect, engineer or surveyor, assumes liability for an injury or damage arising out of the insured's rendering or failure to render professional services, including those listed in Paragraph(1)above and supervisory, inspection,architectural or engineering activities. 8. CONTRACTUAL LIABILITY- PERSONAL AND ADVERTISING INJURY Includes copyrighted material of Insurance Services Office, Inc. Page 2 of 9 CG 70 63 0712 Under SECTION 1 -COVERAGE B., paragraph 2. Exclusions, paragraph e. Contractual Liability is deleted. 9. SUPPLEMENTARY PAYMENTS Under SECTION I - SUPPLEMENTARY PAYMENTS-COVERAGES A AND B, paragraph 1.b. is deleted and replaced with the following: 1. b. Up to $2,500 for cost of bail bonds required because of accidents or traffic law violations arising out of the use of any vehicle to which the Bodily Injury Liability Coverage applies. We do not have to furnish these bonds. 10. BROADENED WHO IS AN INSURED SECTION II -WHO IS AN INSURED is deleted and replaced with the following: 1. If you are designated in the Declarations as: a. An individual,you and your spouse are insureds, but only with respect to the conduct of a business of which you are the sole owner. b. A partnership or joint venture,you are an insured. Your members,your partners, and their spouses are also insureds, but only with respect to the conduct of your business. c. A limited liability company, you are an insured. Your members are also insureds, but only with respect to the conduct of your business. Your managers are insureds, but only with respect to their duties as your managers. d. An organization other than a partnership,joint venture or limited liability company,you are an insured. Your"executive officers'and directors are insureds, but only with respect to their duties as your officers or directors. Your stockholders are also insureds, but only with respect to their liability as stockholders. Paragraphs(1)(a), (1)(b)and (1)(c) above do not apply to your"employees"who are: (i) Managers; (ii) Supervisors; (iii) Directors; or (iv) Officers; with respect to"bodily injury"to a co-"employee". 2. Each of the following is also an insured: a. Your "volunteer workers'only while performing duties related to the conduct of your business, or your"employees," other than either your"executive officers,"(if you are an organization other than a partnership,joint venture or limited liability company) or your managers (if you are a limited liability company), but only for acts within the scope of their employment by you or while performing duties related to the conduct of your business. However, none of these "employees"or"volunteer workers' are insured for: (1) "Bodily injury'or "personal and advertising injury': (a) To you, to your partners or members(if you are a partnership or joint venture),to your members (if you are a limited liability company), to a co-"employee"while in the course of his or her employment or performing duties related to the conduct of your business, or to your other"volunteer workers'while performing duties related to the conduct of your business; (b) To the spouse, child, parent, brother or sister of that co-"employee"or volunteer worker as a consequence of paragraph (1)(a)above; (c) For which there is any obligation to share damages with or repay someone else who must pay damages because of the injury described in paragraphs(1)(a) or (b) above; or (d) Arising out of his or her providing or failing to provide professional health care services except as provided in Provision 11. of this endorsement. Includes copyrighted material of Insurance Services Office, Inc. CG 70 63 07 12 Page 3 of 9 (2) "Property damage"to property: (a) Owned, occupied or used by; (b) Rented to, in the care, custody or control of, or over which physical control is being exercised for any purpose by you, any of your"employees,""volunteer workers", any partner or member(if you are a partnership or joint venture), or any member(if you are a limited liability company). b. Any person (other than your"employee"or"volunteer worker"), or any organization while acting as your real estate manager. c. Any person or organization having proper temporary custody of your property if you die, but only; (1) With respect to liability arising out of the maintenance or use of that property; and (2) Until your legal representative has been appointed. d. Your legal representative if you die, but only with respect to duties as such. That representative will have all your rights and duties under this Coverage Form. e. Your subsidiaries if: (1) They are legally incorporated entities; and (2) You own more than 50% of the voting stock in such subsidiaries as of the effective date of this policy. If such subsidiaries are not shown in the Declarations,you must report them to us within 180 days of the inception of your original policy. f. (1) Any person or organization,other than an architect, engineer or surveyor, required to be named as an additional insured in a "work contract", letter of intent or work order. However, such person or organization shall be an additional insured only with respect to covered "bodily injury," "property damage," and "personal and advertising injury" arising out of"your work" under that "work contract", letter of intent or work order. (2) We will provide additional insured coverage to such person or organization only: (a) for a period of 30 days after the effective date of the applicable "work contract', letter of intent or work order; or (b) until the end of the policy term in effect at the inception of the applicable"work contract', letter of intent or work order; whichever is earlier. (3) Coverage provided under this paragraph f. is excess over any other valid and collectible insurance available to the additional insured whether primary, excess,contingent, or on any other basis unless the "work contract', letter of intent or work order requires this insurance be primary, in which case this insurance will be primary without contribution from such other insurance available to the additional insured. (4) This paragraph f. does not apply if form CG 70 85, Texas Contractors Blanket Additional Insured Endorsement, is attached to the policy. g. Any person or organization to whom you are obligated by virtue of a written contract to provide insurance such as is afforded by this policy, but only with respect to liability arising out of the maintenance or use of that part of any premises leased to you, including common or public areas about such premises if so required in the contract. However, no such person or organization is an insured with respect to: (1) Any'occurrence"that takes place after you cease to occupy those premises; or (2) Structural alterations, new construction or demolition operations performed by or on behalf of such person or organization. Includes copyrighted material of Insurance Services Office, Inc. Page 4 of 9 CG 70 63 07 12 h. Any state or political subdivision but only as respects legal liability incurred by the state or political subdivision solely because it has issued a permit with respect to operations performed by you or on your behalf. However, no state or political subdivision is an insured with respect to: (1) "Bodily injury", "property damage", "personal and advertising injury"arising out of operations performed for the state or municipality; or (2) 'Bodily injury"or"property damage"included within the"products-completed operations hazard." I. Any person or organization who is the lessor of equipment leased to you, to whom you are obligated by virtue of a written contact to provide insurance such as is afforded by this policy, but only with respect to their liability arising out of the maintenance,operation or use of such equipment by you or a subcontractor on your behalf with your permission and under your supervision. However, if you have entered into a construction contract subject to Subchapter C of Chapter 151 of Subtitle C of Title 2 of the Texas Insurance Code with the additional insured,the insurance afforded to such person(s) or organization(s)only applies to the extent permitted by Subchapter C of Chapter 151 of Subtitle C of Title 2 of the Texas Insurance Code. No such person or organization,however, is an insured with respect to any'occurrence"that takes place after the equipment lease expires. j. Any architect, engineer, or surveyor engaged by you but only with respect to liability arising out of your premises or"your work." However, if you have entered into a construction contract subject to Subchapter C of Chapter 151 of Subtitle C of Title 2 of the Texas Insurance Code with the additional insured,the insurance afforded to such person only applies to the extent permitted by Subchapter C of the Chapter 151 of Subtitle C of Title 2 of the Texas Insurance Code. No architect, engineer,or surveyor, however, is an insured with respect to"bodily injury,""property damage,"or"personal and advertising injury"arising out of the rendering of or the failure to render any professional services by or for you, including: (1) The preparing, approving, or failing to prepare or approve maps, drawings, opinions, reports, surveys, change orders,designs or specifications;or (2) Supervisory, inspection, or engineering services. This paragraph j, does not apply if form CG 70 85, Texas Contractors Blanket Additional Insured Endorsement, is attached to the policy. k. Any manager, owner, lessor, mortgagee,assignee or receiver of premises, including land leased to you, but only with respect to liability arising out of the ownership, maintenance or use of that part of the premises or land leased to you. However, no such person or organization is an insured with respect to: (1) Any"occurrence"that takes place after you cease to occupy that premises, or cease to lease the land; or (2) Structural alteration, new construction or demolition operations performed by or on behalf of that person or organization. 3. Any organization you newly acquire or form,other than a partnership,joint venture or limited liability company and over which you maintain ownership or majority interest,will qualify as a Named Insured if there is no other similar insurance available to that organization. However: a. Coverage under this provision is afforded only until the end of the policy period; b. Coverage A does not apply to "bodily injury" or"property damage"that occurred before you acquired or formed the organization; c. Coverage B does not apply to"personal and advertising injury" arising out of an offense committed before you acquired or formed the organization. d. Coverage A does not apply to"product recall expense"arising out of any withdrawal or recall that occurred before you acquired or formed the organization. Includes copyrighted material of Insurance Services Office, Inc. CG 70 63 07 12 Page 5 of 9 4. Any person or organization (referred to below as vendor)with whom you agreed, because of a written contract or agreement to provide insurance is an insured, but only with respect to"bodily injury"or "property damage"arising out of"your products"that are distributed or sold in the regular course of the vendor's business. However, no such person or organization is an insured with respect to: a. "Bodily injury"or"property damage"for which the vendor is obligated to pay damages by reason of the assumption of liability in a contract or agreement. This exclusion does not apply to liability for damages that the vendor would have in the absence of the contract or agreement. b. Any express warranty unauthorized by you; c. Any physical or chemical change in 'your product"made intentionally by the vendor; d. Repackaging, except when unpacked solely for the purpose of inspection, demonstration,testing, or the substitution of parts under instructions from the manufacturer,and then repackaged in the original container: e. Any failure to make such inspections,adjustments,tests or servicing as the vendor has agreed to make or normally undertakes to make in the usual course of business, in connection with the distribution or sale of"your products"; f. Demonstration, installation,servicing or repair operations,except such operations performed at the vendor's premises in connection with the sale of the"your product'; g. "Your products"which,after distribution or sale by you, have been labeled or relabeled or used as a container, part or ingredient of any other thing or substance by or for the vendor. h. "Bodily injury"or"property damage"arising out of the sole negligence of the vendor for its own acts or omissions or those of its employees or anyone else acting on its behalf. However,this exclusion does not apply to: (1) The exceptions contained in subparagraphs d. or f.; or (2) Such inspections,adjustments,tests or servicing as the vendor has agreed to make or normally undertakes to make in the usual course of business, in connection with the distribution or sale of the products. This insurance does not apply to any insured person or organization from which you have acquired"your products", or any ingredient, part, or container, entering into, accompanying or containing"your products". No person or organization is an insured with respect to the conduct of any current or past partnership,joint venture or limited liability company that is not shown as a Named Insured in the Declarations. 11. INCIDENTAL MALPRACTICE LIABILITY As respects provision 10., SECTION II—WHO IS AN INSURED, paragraph 2.a.(1)(d)does not apply to any nurse, emergency medical technician or paramedic employed by you to provide medical or paramedical services, provided that you are not engaged in the business or occupation of providing such services, and your "employee"does not have any other insurance that would also cover claims arising under this provision, whether the other insurance is primary, excess, contingent or on any other basis. Under SECTION III -LIMITS OF INSURANCE, provisions 12.through 14. of this endorsement amend the policy as follows: 12. AGGREGATE LIMITS PER PROJECT The General Aggregate Limit applies separately to each of your construction projects away from premises owned by or rented to you. 13. INCREASED MEDICAL PAYMENTS LIMITS AND REPORTING PERIOD A. The requirement under SECTION I—COVERAGE C MEDICAL PAYMENTS that expenses be incurred and reported to us within one year of the date of the accident is changed to three years. B. SECTION III -LIMITS OF INSURANCE, paragraph 7.,the Medical Expense Limit, is subject to all the terms of SECTION III—LIMITS OF INSURANCE and is the greater of: Includes copyrighted material of Insurance Services Office, Inc. Page 6 of 9 CG 70 63 07 12 1. $10,000; or 2. The amount shown in the Declarations for Medical Expense Limit. C. This provision 13.does not apply if COVERAGE C MEDICAL PAYMENTS is excluded either by the provisions of the Coverage Form or by endorsement. 14. DAMAGE TO PREMISES RENTED TO YOU—SPECIFIC PERILS A. The word fire is changed to "specific perils"where it appears in: 1. The last paragraph of SECTION I—COVERAGE A, paragraph 2. Exclusions; 2. SECTION IV, paragraph 4.b. Excess Insurance. B. The Limits of Insurance shown in the Declarations will apply to all damage proximately caused by the same event, whether such damage results from a "specific peril"or any combination of"specific perils." C. The Damage To Premises Rented To You Limit described in SECTION III - LIMITS OF INSURANCE, paragraph 6., is replaced by a new limit, which is the greater of: 1. $1,000,000; or 2. The amount shown in the Declarations for Damage To Premises Rented To You Limit. D. This provision 14. does not apply if the Damage To Premises Rented To You Limit of SECTION I - COVERAGE A is excluded either by the provisions of the Coverage Form or by endorsement. Under SECTION IV- COMMERCIAL GENERAL LIABILITY CONDITIONS, provisions 15.through 17. of this endorsement amend the policy as follows: 15. KNOWLEDGE OF OCCURRENCE Under 2. Duties In The Event Of Occurrence, Offense, Claim, Or Suit, paragraph a. is deleted and replaced and paragraphs e. and f. are added as follows: a. You must see to it that we are notified as soon as practicable of an 'occurrence"or an offense, regardless of the amount, which may result in a claim. Knowledge of an 'occurrence"or an offense by your "employee(s)"shall not, in itself, constitute knowledge to you unless one of your partners, members, "executive officers,"directors, or managers has knowledge of the 'occurrence"or offense. To the extent possible, notice should include: (1) How,when and where the 'occurrence"or offense took place; (2) The names and addresses of any injured persons and witnesses; and (3) The nature and location of any injury or damage arising out of the 'occurrence"or offense. e. If you report an `occurrence"to your workers compensation carrier that develops into a liability claim for which coverage is provided by the Coverage Form, failure to report such an "occurrence"to us at the time of the 'occurrence"shall not be deemed a violation of paragraphs a., b., and c. above. However,you shall give written notice of this"occurrence"to us as soon you become aware that this'occurrence"may be a liability claim rather than a workers compensation claim. f. You must see to it that the following are done in the event of an actual or anticipated "covered recall'that may result in "product recall expense": (1) Give us prompt notice of any discovery or notification that"your product' must be withdrawn or recalled. Include a description of"your product'and the reason for the withdrawal or recall; (2) Cease any further release, shipment, consignment or any other method of distribution of like or similar products until it has been determined that all such products are free from defects that could be a cause of loss under the insurance. 16. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS Paragraph 6. Representations is deleted and replaced with the following: 6. Representations By accepting this policy, you agree: Includes copyrighted material of Insurance Services Office, Inc. CG 70 63 07 12 Page 7 of 9 a. The statements in the Declarations are accurate and complete; b. Those statements are based upon representations you made to us; and c. We have issued this policy in reliance upon your representations. We will not deny coverage under this coverage part if you unintentionally fail to disclose all hazards existing as of the inception date of this policy. You must report to us any knowledge of an error or omission in the description of any premises or operations intended to be covered by the Coverage Form as soon as practicable after its discovery. However, this provision does not affect our right to collect additional premium or exercise our right of cancellation or nonrenewal. 17. TRANSFER OF RIGHTS (BLANKET WAIVER OF SUBROGATION) Paragraph 8. Transfer of Rights Of Recovery Against Others To Us is deleted and replaced with the following: 8. If the insured has rights to recover all or part of any payment we have made under this Coverage Form, those rights are transferred to us. The insured must do nothing after loss to impair them. At our request, the insured will bring "suit" or transfer those rights to us and help us enforce them. However, if the insured has waived rights to recover through a written contract, or if"your work"was commenced under a letter of intent or work order, subject to a subsequent reduction to writing with customers whose customary contracts require a waiver, we waive any right of recovery we may have under this Coverage Form, 18. EXTENDED NOTICE OF CANCELLATION AND NONRENEWAL Paragraph 2.b. of A. Cancellation of the COMMON POLICY CONDITIONS is deleted and replaced with the following: b. 60 days before the effective date of the cancellation if we cancel for any other reason. Under SECTION IV—COMMERCIAL GENERAL LIABILITY CONDITIONS, Paragraph 9. When We Do Not Renew is deleted and replaced with the following: 9. When We Do Not Renew a. We may elect not to renew this policy except, that under the provisions of the Texas Insurance Code, we may not refuse to renew this policy solely because the policyholder is an elected official. b. If we elect not to renew this policy,we may do so by mailing or delivering to the first Named Insured, at the last mailing address known to us, written notice of nonrenewal, stating the reason for nonrenewal, at least 60 days before the expiration date. If notice is mailed or delivered less than 60 days before the expiration date, this policy will remain in effect until the 61 st day after the date on which the notice is mailed or delivered. Earned premium for any period of coverage that extends beyond the expiration date will be computed pro rata based on the previous year's premium. c. If notice is mailed, proof of mailing will be sufficient proof of notice. d. The transfer of a policyholder between admitted companies within the same insurance group is not considered a refusal to renew, 19. MOBILE EQUIPMENT REDEFINED Under SECTION V-DEFINITIONS, paragraph 12. "Mobile equipment", paragraph f. (1) does not apply to self- propelled vehicles of less than 1,000 pounds gross vehicle weight that are not designed for highway use. 20. DEFINITIONS 1. SECTION V—DEFINITIONS, paragraph 4. "Coverage territory"is replaced by the following definition: "Coverage territory"means anywhere in the world with respect to liability arising out of"bodily injury," "property damage,"or "personal and advertising injury," including"personal and advertising injury offenses that take place through the Internet or similar electronic means of communication provided the insured's responsibility to pay damages is determined in a settlement to which we agree or in a "suit'on the merits, in the United States of America (including its territories and possessions), Puerto Rico and Canada. Includes copyrighted material of Insurance Services Office, Inc. Paqe 8 of 9 CG 70 63 07 12 2. SECTION V—DEFINITIONS is amended by the addition of the following definitions: "Covered recall"means a recall made necessary because you or a government body has determined that a known or suspected defect, deficiency, inadequacy, or dangerous condition in "your product'has resulted or will result in "bodily injury"or"property damage". "Product Recall expenses"mean only reasonable and necessary extra costs, which result from or are related to the recall or withdrawal of"your product'for: a. Telephone and telegraphic communication, radio or television announcements,computer time and newspaper advertising; b. Stationery, envelopes, production of announcements and postage or facsimiles; c. Remuneration paid to regular employees for necessary overtime or authorized travel expense; d. Temporary hiring by you or by agents designated by you of persons, other than your regular employees,to perform necessary tasks; e. Rental of necessary additional warehouse or storage space; f. Packaging of or transportation or shipping of defective products to the location you designate; and g. Disposal of"your products"that cannot be reused. Disposal expenses do not include: (1) Expenses that exceed the original cost of the materials incurred to manufacture or process such product; and (2) Expenses that exceed the cost of normal trash discarding or disposal, except as are necessary to avoid "bodily injury" or"property damage". "Specific Perils" means fire; lightning; explosion;windstorm or hail; smoke; aircraft or vehicles; riot or civil commotion;vandalism; leakage from fire extinguishing equipment; weight of snow, ice or sleet; or "water damage." "Water damage" means accidental discharge or leakage of water or steam as the direct result of the breaking or cracking of any part of a system or appliance containing water or steam. "Work contract" means a written agreement between you and one or more parties for work to be performed by you or on your behalf. Includes copyrighted material of Insurance Services Office, Inc. CG 70 63 07 12 Page 9 of 9 RPM xConstruction, LLC Policy #CPP2068767 Eff . 4/1/2016 - 4/1/2017 COMMERCIAL GENERAL LIABILITY CG 20 01 04 13 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. PRIMARY AND NONCONTRIBUTORY - OTHER INSURANCE CONDITION This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART The following is added to the Other Insurance (2) You have agreed in writing in a contract or Condition and supersedes any provision to the agreement that this insurance would be contrary: primary and would not seek contriibution Primary And Noncontributory Insurance from any other insurance available to the additional insured. This insurance is primary to and will not seek contribution from any other insurance available to an additional insured under your policy provided that: (1) The additional insured is a Named Insured under such other insurance; and CG 20 01 04 13 © Insurance Services Office, Inc., 2012 Page 1 of 1 ----- --------- Policy #CPP2068767 Eff . 4/1/2016 - 4/1/2017 THIS ENDORSEMENT CHANGES THE POLICY, PLEASE READ IT CAREFULLY. NOTICE OF CANCELLATI ON, NONRENEWAL OR MATERIAL CHANGE - THIRD PARTY This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM BUSINESS AUTO PHYSICAL DAMAGE COVERAGE FORM COMMERCIAL GENERAL LIABILITY COVERAGE FORM COMMERCIAL UMBRELLA LIABILITY COVERAGE FORM GARAGE COVERAGE FORM MOTOR CARRIER COVERAGE FORM PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE FORM TRUCKERS COVERAGE FORM Subject to the cancellation provisions of the Coverage Form to which this endorsement is attached, we will not: 1. Cancel; 2. Nonrenew; or, 3. Materially change (reduce or restrict) this Coverage Form, except for nonpayment of premium, until we provide at least 6 0 days written notice of such cancellation, nonrenewal or material change. Written notice will be to the person or organization named in the Schedule. Such notice will be by certified mail with return receipt requested. This notification of cancellation, nonrenewal or material change to the person or organization named in the Schedule is intended as a courtesy only. Our failure to provide such notification will not: 1. Extend any Coverage Form cancellation date; 2. Negate the cancellation as to any insured or any certificate holder; 3. Provide any additional insurance that would not have been provided in the absence of this endorsement; or 4. Impose liability of any kind upon us. This endorsement does not entitle the person or organization named in the Schedule to any benefits, rights or protection under this Coverage Form. SCHEDULE Name Of Person Or Organization Mailing Address Any person or organization holding a certificate of insurance issued The address shown for that person or organization in for you, provided the certificate: that certificate of insurance 1. Refers to this policy; 2. States that notice of: a. Cancellation; b. Nonrenewal; or c. Material change reducing or restricting coverage; will be provided to that person or organization; 3. Is in effect at the time of the: a. Cancellation; b. Nonrenewal; or c. Material change reducing or restricting coverage; and 4. Is on file at your agent or broker's office for this policy It 70 66 11117 1A Policy #CA2068766 Eff. 4/1/2016 - 4/1/2017 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. TEXAS ADVANTAGE COMMERCIAL AUTOMOBILE BROAD FORM ENDORSEMENT This endorsement modifies insurance provided under the BUSINESS AUTO COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement. The premium for this endorsement is $ 500 . 00 1. BROAD FORM INSURED SECTION II- LIABILITY COVERAGE,A.1.Who Is An Insured is amended by the addition of the following: d. Any organization you newly acquire or form, other than a partnership,joint venture or limited liability company, and over which you maintain ownership or a majority interest, will qualify as a Named Insured. However, (1) Coverage under this provision is afforded only until the end of the policy period; (2) Coverage does not apply to "accidents"or"loss"that occurred before you acquired or formed the organization;and (3) Coverage does not apply to an organization that is an"insured"under any other policy or would be an "insured"but for its termination or the exhausting of its limit of insurance. e. Any"employee"of yours using: (1) A covered"auto"you do not own, hire or borrow, or a covered"auto"not owned by the"employee"or a member of his or her household, while performing duties related to the conduct of your business or your personal affairs; or (2) An"auto"hired or rented under a contract or agreement in that"employee's"name, with your permission, while performing duties related to the conduct of your business. However,your "employee"does not qualify as an insured under this paragraph (2) while using a covered "auto" rented from you or from any member of the"employee's"household, f. Your members, if you are a limited liability company,while using a covered"auto"you do not own, hire or borrow and while performing duties related to the conduct of your business or your personal affairs. g. Any person or organization with whom you agree in a written contract, written agreement or permit,to provide insurance such as is afforded under this policy, but only with respect to your covered "autos". This provision does not apply: (1) Unless the written contract or agreement is executed or the permit is issued prior to the"bodily injury" or"property damage"; (2) To any person or organization included as an insured by an endorsement or in the Declarations; or (3) To any lessor of"autos" unless: (a) The lease agreement requires you to provide direct primary insurance for the lessor; (b) The"auto"is leased without a driver;and Includes copyrighted material of Insurance Services Office, Inc. CA 71 18 11 09 Page 1 of 5 (c) The lease had not expired. Leased "autos"covered under this provision will be considered covered "autos"you own and not covered "autos"you hire. h. Any legally incorporated organization or subsidiary in which you own more than 50% of the voting stock on the effective date of this endorsement. This provision does not apply to"bodily injury"or"property damage"for which an "insured" is also an insured under any other automobile policy or would be an insured under such a policy, but for its termination or the exhaustion of its limits of insurance, unless such policy was written to apply specifically in excess of this policy. 2. COVERAGE EXTENSIONS- SUPPLEMENTARY PAYMENTS Under Section II - LIABILITY COVERAGE, A.2.a. Supplementary Payments, paragraphs(2) and (4) are deleted and replaced as follows: (2) Up to $2,500 for the cost of bail bonds (including bonds for related traffic law violations) required because of an "accident'we cover. We do not have to furnish these bonds. (4) All reasonable expenses incurred by the "insured" at our request, including actual loss of earnings up to $500 a day because of time off from work. 3. AMENDED FELLOW EMPLOYEE EXCLUSION Under SECTION II - LIABILITY COVERAGE, B. EXCLUSIONS, paragraph 5. Fellow Employee is deleted and replaced by the following: 5. Fellow Employee "Bodily injury"to: a. Any fellow"employee"of the"insured"arising out of and in the course of the fellow"employee's" employment or while performing duties related to the conduct of your business. However, this exclusion does not apply to your"employees"that are officers, managers, supervisors or above. Coverage is excess over any other collectible insurance. b. The spouse, child, parent, brother or sister of that fellow"employee"as a consequence of paragraph a. above. 4. HIRED AUTO PHYSICAL DAMAGE COVERAGE AND LOSS OF USE EXPENSE A. Under SECTION III - PHYSICAL DAMAGE COVERAGE,A. COVERAGE, the following is added: If any of your owned covered "autos" are covered for Physical Damage, we will provide Physical Damage coverage to "autos"that you or your"employees" hire or borrow, under your name or the "employee's" name, for the purpose of doing your work. We will provide coverage equal to the broadest physical damage coverage applicable to any covered "auto" shown in the Declarations, Item Three, Schedule of Covered Autos You Own, or on any endorsements amending this schedule. B. Under SECTION III - PHYSICAL DAMAGE COVERAGE,A.4. Coverage Extensions. paragraph b. Loss Of Use Expenses is deleted and replaced with the following: b. Loss Of Use Expenses For Hired Auto Physical Damage, we will pay expenses for which an "insured" becomes legally responsible to pay for loss of use of a vehicle rented or hired without a driver, under a written rental contract or agreement. We will pay for loss of use expenses if caused by: (1) Other than collision, only if the Declarations indicate that Comprehensive Coverage is provided for any covered "auto'; Includes copyrighted material of Insurance Services Office, Inc. Page 2 of 5 CA 71 18 11 09 (2) Specified Causes of Loss, only if the Declarations indicate that Specified Causes Of Loss Coverage is provided for any covered "auto"; or (3) Collision,only if the Declarations indicate that Collision Coverage is provided for any covered "auto". However,the most we will pay for any expenses for loss of use is $30 per day,to a maximum of $2,000. C. Under SECTION IV—BUSINESS AUTO CONDITIONS, B. General Conditions, 5. Other Insurance, paragraph b. is replaced by the following: b. For Hired Auto Physical Damage, the following are deemed to be covered "autos"you own: 1. Any covered"auto"you lease, hire, rent or borrow; and 2. Any covered "auto"hired or rented by your"employees"under a contract in that individual "employee's"name, with your permission, while performing duties related to the conduct of your business. However, any"auto"that is leased, hired, rented or borrowed with a driver is not a covered "auto", nor is any"auto"you hire from any of your"employees", partners (if you are a partnership), members (if you are a limited liability company), or members of their households. 5. LOAN OR LEASE GAP COVERAGE Under SECTION III— PHYSICAL DAMAGE COVERAGE,A.COVERAGE, the following is added: If a covered "auto" is owned or leased and if we provide Physical Damage Coverage on it, we will pay, in the event of a covered total "loss", any unpaid amount due on the lease or loan for a covered "auto", less: (a) The amount paid under the Physical Damage Section of the policy; and: (b) Any: (1) Overdue lease or loan payments including penalties, interest or other charges resulting from overdue payments at the time of the"loss"; (2) Financial penalties imposed under a lease for excessive use, abnormal wear and tear or high mileage; (3) Costs for extended warranties, Credit Life Insurance, Health, Accident or Disability Insurance purchased with the loan or lease; (4) Security deposits not refunded by a lessor; and (5) Carry-over balances from previous loans or leases. 6. RENTAL REIMBURSEMENT Under SECTION III - PHYSICAL DAMAGE COVERAGE, A.4, Coverage Extensions, paragraph a. Transportation Expenses is deleted and replaced by the following: a. Transportation Expenses (1) We will pay up to $75 per day to a maximum of$2,000 for transportation expense incurred by you because of covered "loss". We will pay only for those covered "autos"for which you carry Collision Coverage or either Comprehensive Coverage or Specified Causes of Loss Coverage. We will pay for transportation expenses incurred during the period beginning 24 hours after the covered "loss" and ending, regardless of the policy's expiration, when the covered "auto" is returned to use or we pay for its"loss". This coverage is in addition to the otherwise applicable coverage you have on a covered "auto". No deductibles apply to this coverage. Includes copyrighted material of Insurance Services Office, Inc. CA 71 18 11 09 Page 3 of 5 (2) This coverage does not apply while there is a spare or reserve "auto"available to you for your operation. 7. AIRBAG COVERAGE Under SECTION III - PHYSICAL DAMAGE, B. EXCLUSIONS, paragraph 3. is deleted and replaced by the following: 3. We will not pay for"loss" caused by or resulting from any of the following unless caused by other"loss" that is covered by this insurance: (1) Wear and tear, freezing, mechanical or electrical breakdown. However, this exclusion does not include the discharge of an airbag. (2) Blowouts, punctures or other road damage to tires. 8. GLASS REPAIR—WAIVER OF DEDUCTIBLE Section III—PHYSICAL DAMAGE COVERAGE, D. Deductible is amended to add the following: No deductible applies to glass damage if the glass is repaired rather than replaced. 9. COLLISION COVERAGE—WAIVER OF DEDUCTIBLE Under Section III - PHYSICAL DAMAGE COVERAGE, D. Deductible is amended to add the following: When there is a loss to your covered "auto"insured for Collision Coverage, no deductible will apply if the loss was caused by a collision with another"auto" insured by us. 10. KNOWLEDGE OF ACCIDENT Under SECTION IV- BUSINESS AUTO CONDITIONS,A. Loss Conditions, 2. Duties In The Event Of Accident,Claim, Suit Or Loss, paragraph a. is deleted and replaced by the following: a. You must see to it that we are notified as soon as practicable of an "accident", claim, "suit" or"loss". Knowledge of an "accident', claim, "suit' or"loss" by your"employees"shall not, in itself, constitute knowledge to you unless one of your partners, executive officers, directors, managers, or members (if you are a limited liability company) has knowledge of the "accident', claim, "suit"or"loss". Notice should include: (1) How, when and where the "accident' or"loss"occurred; (2) The "insured's" name and address; and (3) To the extent possible, the names and addresses of any injured persons and witnesses. 11. TRANSFER OF RIGHTS (BLANKET WAIVER OF SUBROGATION) Under SECTION IV- BUSINESS AUTO CONDITIONS, A. Loss Conditions paragraph 5. Transfer Of Rights Of Recovery Against Others To Us is deleted and replaced by the following: 5. Transfer Of Rights Of Recovery Against Others To Us If any person or organization to or for whom we make payment under this Coverage Form has rights to recover damages from another, those rights are transferred to us. That person or organization must do everything necessary to secure our rights and must do nothing after"accident"or"loss"to impair them. However, if the "insured" has waived rights to recover through a written contract, or if your work was commenced under a letter of intent or work order, subject to a subsequent reduction in writing with customers whose customary contracts require a waiver, we waive any right of recovery we may have under this Coverage Form. Includes copyrighted material of Insurance Services Office, Inc. Page 4 of 5 CA 71 18 11 09 12. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS Under SECTION IV- BUSINESS AUTO CONDITIONS , B. General Conditions , paragraph 2. Concealment, Misrepresentation Or Fraud is amended by the addition of the following: We will not deny coverage under this Coverage Form if you unintentionally fail to disclose all hazards existing as of the inception date of this policy. You must report to us any knowledge of an error or omission in your representations as soon as practicable after its discovery. This provision does not affect our right to collect additional premium or exercise our right of cancellation or non-renewal. 13. BLANKET COVERAGE FOR CERTAIN OPERATIONS IN CONNECTION WITH RAILROADS When required by written contract or written agreement, the definition of"insured contract' is amended as follows: — The exception contained in paragraph H.3. relating to construction or demolition operations on or within 50 feet of a railroad; and — Paragraph H.a. are deleted with respect to the use of a covered "auto" in operations for, or affecting, a railroad. Includes copyrighted material of Insurance Services Office, Inc, CA 71 18 11 09 Page 5 of 5 COMMERCIAL AUTO CA 7165 10 07 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. DESIGNATED INSURED - PRIMARY COVERAGE This endorsement modifies insurance provided under the BUSINESS AUTO COVERAGE FORM The provisions of the Coverage Form apply unless changed by this endorsement. This endorsement identifies person(s)or organization(s)who are "insured" under the Who Is An Insured Provision of the Coverage Form. This endorsement changes the policy on the inception date of the policy, unless another date is shown below. Endorsement Effective 4/1/2016 Countersigned By: Named Insured: RPM xConstruction, LLC (Authorized Representative) (No entry may appear above. If so, information to complete this endorsement is in the Declarations.) Section II — Liability Coverage, A. Coverage, 1. Who Is An Insured is amended to add: Any Person or Organization with whom you have an "insured contract'which requires: i. that Person or Organization to be added as an "insured" under this policy; and ii. this policy to be primary and non-contributory to any like insurance available to the Person or Organization. Each such person or organization is an "insured"for Liability Coverage. They are an "insured"only if that person or organization is an "insured" under in SECTION II of the Coverage Form. The contract between the Named Insured and the person or organization is an "insured contract'. Includes copyrighted material of the Insurance Services Office, Inc., with its permission. CA 71 65 10 07 Insurance Services Office., 1998. Page 1 of 1 KYIvl Xl UI1SLr UCL1Ui1, LLl Policy #CA2068766 Eff . 4/1/2016 - 4/1/2017 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. NOTICE OF CANCELLATI ON, NONRENEWAL OR MATERIAL CHANGE - THIRD PARTY This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM BUSINESS AUTO PHYSICAL DAMAGE COVERAGE FORM COMMERCIAL GENERAL LIABILITY COVERAGE FORM COMMERCIAL UMBRELLA LIABILITY COVERAGE FORM GARAGE COVERAGE FORM MOTOR CARRIER COVERAGE FORM PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE FORM TRUCKERS COVERAGE FORM Subject to the cancellation provisions of the Coverage Form to which this endorsement is attached, we will not: 1. Cancel; 2. Nonrenew; or, 3. Materially change (reduce or restrict) this Coverage Form, except for nonpayment of premium, until we provide at least 6 0 days written notice of such cancellation, nonrenewal or material change. Written notice will be to the person or organization named in the Schedule. Such notice will be by certified mail with return receipt requested. This notification of cancellation, nonrenewal or material change to the person or organization named in the Schedule is intended as a courtesy only. Our failure to provide such notification will not: 1. Extend any Coverage Form cancellation date; 2. Negate the cancellation as to any insured or any certificate holder; 3. Provide any additional insurance that would not have been provided in the absence of this endorsement; or 4. Impose liability of any kind upon us. This endorsement does not entitle the person or organization named in the Schedule to any benefits, rights or protection under this Coverage Form. SCHEDULE Name Of Person Or Organization Mailing Address Any person or organization holding a certificate of insurance issued The address shown for that person or organization in for you, provided the certificate: that certificate of insurance 1. Refers to this policy; 2. States that notice of: a. Cancellation; b. Nonrenewal; or c, Material change reducing or restricting coverage; will be provided to that person or organization; 3. Is in effect at the time of the: a. Cancellation; b. Nonrenewal; or c. Material change reducing or restricting coverage; and 4. Is on file at your agent or broker's office for this policy IL7nFFmIA xilm xuonsurUcuion, LL(_; Policy #CU2068769 Eff . 4/1/2016 - 4/1/2017 COMMERCIAL LIABILITY UMBRELLA CU 22 82 06 04 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. TEXAS WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US This endorsement modifies insurance provided under the following: COMMERCIAL LIABILITY UMBRELLA COVERAGE PART SCHEDULE Name Of Person Or Organization: ANY PERSON OR ORGANIZATION REQUIRED BY WRITTEN CONTRACT. Information required to complete this Schedule, if not shown above, will be shown in the Declarations. The Transfer Of Rights Of Recovery Against Others To Us Condition under Section IV — Conditions is amended by the addition of the following: We waive any right of recovery we may have against the person or organization shown in the Schedule above because of payments we make for "bodily injury" or "property damage" arising out of your ongoing operations or "your work" done under a contract with that person or organization and included in the"products-completed opera- tions hazard". This waiver applies only to the person or organization shown in the Schedule above. CU 22 82 06 04 © ISO Properties, Inc., 2003 Page 1 of 1 RPM xConstruction, LLC Policy #CU2068769 Eff . 4/1/2016 - 4/1/2017 COMMERCIAL LIABILITY UMBRELLA CU 74 69 08 10 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. TEXAS ADDITIONAL INSURED - PRIMARY/NON -CONTRIBUTORY COVERAGE WHEN REQUIRED BY WRITTEN CONTRACT OR WRITTEN AGREEMENT This endorsement modifies insurance provided under the following: COMMERCIAL LIABILITY UMBRELLA COVERAGE FORM All policy terms apply except as stated below. Under SECTION II—WHO IS AN INSURED, the following is added to paragraph 3: If coverage provided to any additional insured is required by a written contract or written agreement, wee will provide coverage to the additional insured on a primary basis without contribution from any other valid and collectible insurance available to the additional insured. Under SECTION IV—CONDITIONS, paragraph 5. Other Insurance does not apply to coverage provided by this endorsement. Includes copyrighted material of Insurance Services Office, Inc. CU 74 69 08 10 Policy #CU2068769 Eff . 4/1/2016 - 4/1/2017 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. NOTICE OF CANCELLATI ON, NONRENEWAL OR MATERIAL CHANGE - THIRD PARTY This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM BUSINESS AUTO PHYSICAL DAMAGE COVERAGE FORM COMMERCIAL GENERAL LIABILITY COVERAGE FORM COMMERCIAL UMBRELLA LIABILITY COVERAGE FORM GARAGE COVERAGE FORM MOTOR CARRIER COVERAGE FORM PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE FORM TRUCKERS COVERAGE FORM Subject to the cancellation provisions of the Coverage Form to which this endorsement is attached, we will not: 1. Cancel; 2. Nonrenew; or, 3. Materially change (reduce or restrict) this Coverage Form, except for nonpayment of premium, until we provide at least 60 days written notice of such cancellation, nonrenewal or material change. Written notice will be to the person or organization named in the Schedule. Such notice will be by certified mail with return receipt requested. This notification of cancellation, nonrenewal or material change to the person or organization named in the Schedule is intended as a courtesy only. Our failure to provide such notification will not: 1. Extend any Coverage Form cancellation date; 2. Negate the cancellation as to any insured or any certificate holder; 3. Provide any additional insurance that would not have been provided in the absence of this endorsement; or 4. Impose liability of any kind upon us, This endorsement does not entitle the person or organization named in the Schedule to any benefits, rights or protection under this Coverage Form. SCHEDULE Name Of Person Or Organization Mailing Address Any person or organization holding a certificate of insurance issued The address shown for that person or organization in for you, provided the certificate. that certificate of insurance 1. Refers to this policy; 2. States that notice of: a. Cancellation; b. Nonrenewal; or c. Material change reducing or restricting coverage; will be provided to that person or organization; 3. Is in effect at the time of the: a. Cancellation; b. Nonrenewal; or c. Material change reducing or restricting coverage; and 4. Is on file at your agent or broker's office for this policy IL 7n fif; n7 1a WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE POLICY WC 42 03 04 B (Ed, 6-14) TEXAS WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENT This endorsement applies only to the insurance provided by the policy because Texas is shown in Item 3.A. of the Information Page. We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our right against the person or organization named in the Schedule, but this waiver applies only with respect to bodily injury arising out of the operations described in the Schedule where you are required by a written contract to obtain this waiver from us. This endorsement shall not operate directly or indirectly to benefit anyone not named in the Schedule. The premium for this endorsement is shown in the Schedule. Schedule 1. ( ) Specific Waiver Name of person or organization (X) Blanket Waiver Any person or organization for whom the Named Insured has agreed by written contract to furnish this waiver. 2. Operations: 3. Premium: The premium charge for this endorsement shall be 0.020 percent of the premium developed on payroll in connection with work performed for the above person(s) or organization(s) arising out of the operations described. 4. Advance Premium: S 18,121 WC 4z0304B (Ed. 6-14) O Copyright 21114 Nation at Council on Cam pen sation Insurance,Inc.At Rights Reserved. Policy #WC2068770 Eff . 4/1/2016 - 4/1/2017 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. EARLIER NOTICE OF CANCELLATION PROVIDED BY US Number of Days Notice _ 60 For any statutorily permitted reason other than nonpayment of premium,the number of days required for notice of cancellation is increased to the number of days shown in the Schedule above. If this policy is cancelled by us we will send the Named Insured and any party listed in the following schedule notice of cancellation based on the number of days notice shown above, SCHEDULE Name of Person or Organization The Name of Person or Organization is any person or organization holding a certificate of insurance issued for you, provided the certificate: 1. Refers to this policy; 2. States that notice of: a. Cancellation; b. Nonrenewal; or c. Material change reducing or restricting coverage; will be provided to that person or organization; 3. Is in effect at the time of the: a. Cancellation; b. Nonrenewal; or c. Material change reducing or restricting coverage; and 4. Is on file at your agent or broker's office for this policy. Mailing Address The Mailing Address is the address shown for that person or organization in that certificate of insurance. IL 70 45 05 07 W7100-2 S( PPLEMENTARI'CONDITIONS Page 2 ol'5 1 Utilities or obstructions to be removed, adjusted, and/or relocated 2 3 The following is list of utilities and or obstruction;that have not been removed. adjusted. and/or relocated 4 as of 5 EXPECTED U HLITY AND LOCATION TARGET DA fE OF OWNER ADJUSI MLN'I No11e 6 The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed, 7 and do not bind the Citv. 8 9 SC-4.02A.,"Subsurface and Physical Conditions" l0 1 1 The f011oxN ing are reports of explorations and tests of subarrlace conditions at the site of the Work: 12 13 A Ceotechnical Report No. 22801 ,dated May 22,2014 , prepared by L.N1I, Lngincering a sub- 14 consultant of I111B Engineering.a consultant of the City,pro%iding geotechnical stud-. 15 16 l he 1611owino are drawings of plivsical conditions in or rclatim_ lo (sistin" surface and subsurface 17 stnictures (c,scc)t Underground I acilitics) Much are at or contiguous Io the site of tihc XVork: 18 None 19 20 SC-4.00A.,"Ilazardous Environmental Conditions at Site" 21 22 The Iollowing are reports and drawings of existing hazardous environmental conditions known to the City: 23 A'one 24 25 SC-5.03A.,"Certificates of Insurance" 26 27 The entities listed bclo%� are "additional insureds as their interest may appear" including their respective 28 officers.directors, agents and employees. 29 30 (1) City 31 (2) Consultant: 13aird. I Iampton& I3ro%rn, hlc. 32 (3) Other: A"one 33 34 SC-5.04A.,"Contractor's Insurance" 35 36 The limits of liabilitv for the insurance required by Paragraph GC-5.04 shall provide the following 37 coverages for not less than the following amounts or greater where required by laws and regulations: 38 39 5.04A. Workers' Compensation, under Paragraph GC-5.04:x. 40 41 S'talulorr limits 42 Emplo.ver'.o liabiliti• 43 100,00(1 ouch uccidcnt uccvcrrcnce 44 S100,000 Oise asc-each employee 45 5500,000 Oiscetse holier limit 46 47 SC-5.046.,"Contractor's Insurance" 48 CITY OI'FOR1 WORTH Dix Branch Crcck Interim Regional Detention Basin STANDARD CONS RUCTION SPECIFICATION DOCUME\I S Ciq Project No.00495 Revised April 1,2013 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decwi r2l,2012 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT TABLE OF CONTENTS Page Article1 —Definitions and Terminology..........................................................................................................1 1.01 Defined Terms...............................................................................................................................l 1.02 Terminol ogy..................................................................................................................................6 Article2—Preliminary Matters.........................................................................................................................7 2.01 Copies of Documents....................................................................................................................7 2.02 Commencement of Contract Time;Notice to Proceed................................................................7 2.03 Starting the Work..........................................................................................................................8 2.04 Before Starting Construction........................................................................................................8 2.05 Preconstruction Conference..........................................................................................................8 2.06 Public Meeting..............................................................................................................................8 2.07 Initial Acceptance of Schedules....................................................................................................8 Article 3—Contract Documents: Intent,Amending,Reuse............................................................................8 3.01 Intent............................................................................................................................................;8 3.02 Reference Standards...... ...............................................................................................................9 3.03 Reporting and Resolving Discrepancies.......................................................................................9 3.04 Amending and Supplementing Contract Documents.................................................................10 3.05 Reuse of Documents...................................................................................................................10 3.06 Electronic Data............................................. ...........................................................................11 Article 4—Availability of Lands; Subsurface and Physical Conditions;Hazardous Environmental Conditions;Reference Points...................<.......................................................................................11 4.01 Availability of Lands..................................................................................................................11 4.02 Subsurface and Physical Conditions..........................................................................................12 4.03 Differing Subsurface or Physical Conditions.............................................................................12 4.04 Underground Facilities ...............................................................................................................13 4.05 Reference Points.........................................................................................................................14 4.06 Hazardous Environmental Condition at Site..............................................................................14 Article5—Bonds and Insurance.....................................................................................................................16 5.01 Licensed Sureties and Insurers...................................................................................................16 5.02 Performance,Payment, and Maintenance Bonds.......................................................................16 5.03 Certificates of Insurance.............................................................................................................16 5.04 Contractor's Insurance................................................................................................................18 5.05 Acceptance of Bonds and Insurance; Option to Replace...........................................................19 Article6—Contractor's Responsibilities........................................................................................................19 6.01 Supervision and Superinte ndence...............................................................................................19 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber2l,2012 6.02 Labor; Working Hours................................................................................................................20 6.03 Services,Materials,and Equipment...........................................................................................20 6.04 Project Schedule..........................................................................................................................21 6.05 Substitutes and"Or-Equal s".......................................................................................................21 6.06 Concerning Subcontractors, Suppliers,and Others....................................................................24 6.07 Wage Rates....................................................................., ................................................... .......25 6.08 Patent Fees and Royalties...........................................................................................................26 6.09 Permits and Utilities....................................................................................................................27 6.10 Laws and Regulations.................................................................................................................27 6.11 Taxes ...........................................................................................................................................28 6.12 Use of Site and Other Areas.......................................................................................................28 6.13 Record Documents......................................................................................................................29 6.14 Safety and Protection..................................................................................................................29 6.15 Safety Representative..................................................................................................................30 6.16 Hazard Communication Programs .............................................................................................30 6.17 Emergencies and/or Rectification...............................................................................................30 6.18 Submittals....................................................................................................................................31 6.19 Continuing the Work...................................................................................................................32 6.20 Contractor's General Warranty and Guarantee..........................................................................32 6.21 Indemnification................................................................... ................33 6.22 Delegation of Professional Design Services..............................................................................34 6.23 Right to Audit........................................................................................ 34 6.24 Nondiscrimination.................................... .................................................................................35 Article7-Other Work at the Site...................................................................................................................35 7.01 Related Work at Site...................................................................................................................35 7.02 Coordination................................................................................................................................36 Article8-City's Responsibilities...................................................................................................................36 8.01 Communications to Contractor...................................................................................................36 8.02 Furnish Data................................................................................................................................36 8.03 Pay When Due ............................................................................................................................36 8.04 Lands and Easements;Reports and Tests...................................................................................36 8.05 Changc Orders.............................................................................................................................36 8.06 Inspections,Tests, and Approvals..............................................................................................36 8.07 Limitations on City's Responsibilities.......................................................................................37 8.08 Undiscloscd Hazardous Environmcntal Condition....................................................................37 8.09 Compliance with Safety Program...............................................................................................37 Article 9-City's Observation Status During Construction...........................................................................37 9.01 City's Project Representative .....................................................................................................37 9.02 Visits to Site................................................................................................................................37 9.03 Authorized Variations in Work..................................................................................................38 9.04 Rejecting Defective Work..........................................................................................................38 9.05 Determinations for Work Performed..........................................................................................38 9.06 Decisions on Requirements of Contract Documents and Acceptability of Work.....................38 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dacanber2l,2012 Article10-Changes in the Work; Claims;Extra Work...................................... ........................................38 10.01 Authorized Changes in the Work...............................................................................................38 10.02 Unauthorized Changes in the Work...........................................................................................39 10.03 Execution of Change O rders.......................................................................................................39 10.04 Extra Work..................................................................................................................................39 10.05 Notification to Surety..................................................................................................................39 10.06 Contract Claims Process.............................................................................................................40 Article 11 -Cost of the Work;Allowances; Unit Price Work;Plans Quantity Measurement......................41 11.01 Cost of the Work.........................................................................................................................41 11.02 Allowances..................................................................................................................................43 11.03 Unit Price Work..........................................................................................................................44 11.04 Plans Quantity Measurement......................................................................................................45 Article 12-Change of Contract Price; Change of Contract Time.................................................................46 12.01 Change of Contract Price............................................................................................................46 12.02 Change of Contract Time............................................................................................................47 12.03 Delays..........................................................................................................................................47 Article 13-Tests and Inspections; Correction,Removal or Acceptance of Defective Work......................48 13.01 Notice of Defects ........................................................................................................................48 13.02 Access to Work...........................................................................................................................48 13.03 Tests and Inspections..................................................................................................................48 13.04 Uncovering Work...................................................................... . ...............................................49 13.05 City May Stop the Work................................................... . ......................................................49 13.06 Correction or Removal of Defective Work................................................................................50 13.07 Correction Period........................................................................................................................50 13.08 Acceptance of Defective Work...................................................................................................51 13.09 City May Correct Defective Work.............................................................................................51 Article 14-Payments to Contractor and Completion....................................................................................52 14.01 Schedule of Values......................................................................................................................52 14.02 Progress Payments......................................................................................................................52 14.03 Contractor's Warranty of Title...................................................................................................54 14.04 Partial Utilization........................................................................................................................55 14.05 Final Inspection...........................................................................................................................55 14.06 Final Acceptance..................................._,...................................................................................55 14.07 Final Payment..............................................................................................................................56 14.08 Final Completion Delayed and Partial Rctainage Release ........................................................56 14.09 Waiver of Claims........................................................................................................................57 Article 15-Suspension of Work and Termination........................................................................................57 15.01 City May Suspend Work.............................................................................................................57 15.02 City May Terminate for Cause...................................................................................................58 15.03 City May Terminate For Convenience.......................................................................................60 Article16-Dispute Resolution......................................................................................................................61 16.01 Methods and Procedures.............................................................................................................61 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:December 21,2012 Article17—Miscellaneous..............................................................................................................................62 17.01 Giving Notice..............................................................................................................................62 17.02 Computation of Times................................................................................................................62 17.03 Cumulative Remedies.............................................................................................................. ..62 17.04 Survival of Obligations...............................................................................................................63 17.05 Headings......................................................................................................................................63 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dember21,2012 007200-1 General Conditions Page 1 ef63 ARTICLE 1–DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct,or change the Bidding Requirements or the proposed Contract Documents. 2. Agreement—The written instrument which is evidence of the agreement between City and Contractor covering the Work. 3. Application for Payment—The form acceptable to City which is to be used by Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents. 4. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 5. Award–Authorization by the City Council for the City to enter into an Agreement. 6. Bic-The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed. 7. Bidder—The individual or entity who submits a Bid directly to City. 8. Bidding Documents—The Bidding Requirements and the proposed Contract Documents (including all Addenda). 9. Bidding Requirements—The advertisement or Invitation to Bid, Instructions to Bidders, Bid security of acceptable form, if any,and the Bid Form with any supplements. 10. Business Day– A business day is defined as a day that the City conducts normal business, generally Monday through Friday,except for federal or state holidays observed by the City. 11. Buzzsaw–City's on-line,electronic document management and collaboration system. 12. Calendar Day–A day consisting of 24 hours measured from midnight to the next midnight. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Do=nber2l,2012 007200-1 General Conditions Page 2 of 63 13. Change Order—A document, which is prepared and approved by the City, which is signed by Contractor and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 14. City— The City of Fort Worth, Texas, a home-rule municipal corporation, authorized and chartered under the Texas State Statutes, acting by its governing body through its City Manager, his designee, or agents authorized under his behalf, each of which is required by Charter to perform specific duties with responsibility for final enforcement of the contracts involving the City of Fort Worth is by Charter vested in the City Manager and is the entity with whom Contractor has entered into the Agreement and for whom the Work is to be performed. 15. City Attorney–The officially appointed City Attorney of the City of Fort Worth, Texas, or his duly authorized representative. 16. City Council - The duly elected and qualified governing body of the City of Fort Worth, Texas. 17. City Manager – The officially appointed and authorized City Manager of the City of Fort Worth,Texas,or his duly authorized representative. 18. Contract Claim—A demand or assertion by City or Contractor seeking an adjustment of Contract Price or Contract Time, or both, or other relief with respect to the terms of the Contract.A demand for money or services by a third party is not a Contract Claim. 19. Contract—The entire and integrated written document between the City and Contractor concerning the Work. The Contract contains the Agreement and all Contract Documents and supersedes prior negotiations,representations,or agreements,whether written or oral. E 20. Contract Documents--Those items so designated in the Agreement. All items listed in the Agreement are Contract Documents. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. f 21. Contract .Price—The moneys payable by City to Contractor for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of Paragraph 11.03 in the case of Unit Price Work). 22. Contract .Time The number of days or the dates stated in the Agreement to: (i) achieve Milestones, if any and(ii)complete the Work so that it is ready for Final Acceptance. 23. Contractor—The individual or entity with whom City has entered into the Agreement. 24. Cost of the Work—See Paragraph 11.01 of these General Conditions for definition. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decwta2l,2012 E 007200-1 General Conditions Page 3 of 63 25. Damage Claims – A demand for money or services arising from the Project or Site from a third party,City or Contractor exclusive of a Contract Claim. 26. Day or day–A day, unless otherwise defined, shall mean a Calendar Day. 27. Director of Aviation –The officially appointed Director of the Aviation Department of the City of Fort Worth,Texas,or his duly appointed representative,assistant, or agents. 28. Director of Parks and Community Services–The officially appointed Director of the Parks and Community Services Department of the City of Fort Worth, Texas, or his duly appointed representative, assistant, or agents. 29. Director of Planning and Development–The officially appointed Director of the Planning and Development Department of the City of Fort Worth, Texas, or his duly appointed representative, assistant,or agents. 30. Director of Transportation Public Works – The officially appointed Director of the Transportation Public Works Department of the City of Fort Worth, Texas, or his duly appointed representative,assistant,or agents. 31. Director of Water Department–The officially appointed Director of the Water Department of the City of Fort Worth,Texas,or his duly appointed representative,assistant,or agents. 32. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 33. Effective Date of the Agreement—The date indicated in the Agreement on which it becomes effective, but if no such date is indicated, it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver. 34. Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the City. 35. Extra Work – Additional work made necessary by changes or alterations of the Contract Documents or of quantities or for other reasons for which no prices are provided in the Contract Documents.Extra work shall be part of the Work. 36. Field Order—A written order issued by City which requires changes in the Work but which does not involve a change in the Contract Price, Contract Time, or the intent of the Engineer. Field Orders are paid from Field Order Allowances incorporated into the Contract by funded work type at the time of award. 37. Final Acceptance – The written notice given by the City to the Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deoe rnk=2l,2012 007200-1 General Conditions Page 4 of 63 38. Final Inspection – Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 39. General Requirements—Sections of Division 1 of the Contract Documents. 40. Hazardous Environmental Condition—The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, Radioactive Material, or other materials in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto. 41. Hazardous Waste—Hazardous waste is defined as any solid waste listed as hazardous or possesses one or more hazardous characteristics as defined in the federal waste regulations, as amended from time to time. 42. Laws and Regulations Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 43. Liens--Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 44. Major Item–An Item of work included in the Contract Documents that has a total cost equal to or greater than 5%of the original Contract Price or$25,000 whichever is less. 45. Milestone—A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 46. Notice of Award—The written notice by City to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed therein, City will sign and deliver the Agreement. 47.Notice to Proceed—A written notice given by City to Contractor fixing the date on which the Contract Time will commence to run and on which Contractor shall start to perform the Work specified in Contract Documents. 48. PCBs----Polychlorinated biphenyls. 49. Petroleum Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and crude oils. 50. Plans–See definition of Drawings. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decentw2l,2012 007200-1 General Conditions Page 5 of 63 51. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor's plan to accomplish the Work within the Contract Time. 52. Project—The Work to be performed under the Contract Documents. 53. Project Representative—The authorized representative of the City who will be assigned to the Site. 54. Public Meeting – An announced meeting conducted by the City to facilitate public participation and to assist the public in gaining an informed view of the Project. 55. Radioactive Material—Source, special nuclear, or byproduct material as defined by the Atomic Energy Act of 1954(42 USC Section 2011 et seq.)as amended from time to time. 56. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday(excluding legal holidays). 57. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. 58. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 59. Schedule of Values—A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment. 60. Site—Lands or areas indicated in the Contract Documents as being furnished by City upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City which are designated for the use of Contractor. 61. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 62. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deoember2l,2012 007200-1 General Conditions Page 6 of 63 63. Submittals All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 64. Successful Bidder—The Bidder submitting the lowest and most responsive Bid to whom City makes an Award. 65. Superintendent— The representative of the Contractor who is available at all times and able to receive instructions from the City and to act for the Contractor. 66. Supplementary Conditions—That part of the Contract Documents which amends or supplements these General Conditions. 67. Supplier A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 68. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water,wastewater, storm water, other liquids or chemicals,or traffic or other control systems. 69. Unit Price Work—See Paragraph 11.03 of these General Conditions for definition. 70. Weekend Working Hours— Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. 71. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Change Order or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction,all as required by the Contract Documents. 72. Working Day—A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.B through E are not defined but, when used in the Bidding Requirements or Contract Documents,have the indicated meaning. B. Intent of Certain Terms or Adjectives: CnY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dember2l,2012 007200-1 General Conditions Page 7 of 63 1. The Contract Documents include the terms "as allowed," "as approved," "as ordered," "as directed" or terms of like effect or import to authorize an exercise of judgment by City. In addition, the adjectives "reasonable," "suitable," "acceptable," "proper," "satisfactory," or adjectives of like effect or import are used to describe an action or determination of City as to the Work. It is intended that such exercise of professional judgment, action, or determination will be solely to evaluate, in general, the Work for compliance with the information in the Contract Documents and with the design concept of the Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). C. Defective: 1. The word "defective," when modifying the word "Work," refers to Work that is unsatisfactory,faulty,or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City's written acceptance. D. Furnish, Install, Perform, Provide: 1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or the word "Supply," or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. E. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. ARTICLE 2—PRELIMINARY MATTERS 2.01 Copies of Documents City shall furnish to Contractor one (1) original executed copy and one (1) electronic copy of the Contract Documents, and four (4) additional copies of the Drawings. Additional copies will be furnished upon request at the cost of reproduction. 2.02 Commencement of Contract Time;Notice to Proceed The Contract Time will commence to run on the day indicated in the Notice to Proceed. A Notice to Proceed may be given at any time within 14 days after the Effective Date of the Agreement. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decenber2l,2012 007200-1 General Conditions Page 8 of 63 2.03 Starting the Work Contractor shall start to perform the Work on the date when the Contract Time commences to run. No Work shall be done at the Site prior to the date on which the Contract Time commences to run. 2.04 Before Starting Construction Baseline Schedules: Submit in accordance with the Contract Documents, and prior to starting the Work. 2.05 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.06 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. 2.07 Initial Acceptance of Schedules No progress payment shall be made to Contractor until acceptable schedules are submitted to City in accordance with the Schedule Specification as provided in the Contract Documents. ARTICLE 3—CONTRACT DOCUMENTS: INTENT,AMENDING,REUSE 3.01 Intent A. The Contract Documents are complementary; what is required by one is as binding as if required by all. B. It is the intent of the Contract Documents to describe a functionally complete project (or part thereof) to be constructed in accordance with the Contract Documents. Any labor, documentation, services, materials, or equipment that reasonably may be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the indicated result will be provided whether or not specifically called for, at no additional cost to City. C. Clarifications and interpretations of the Contract Documents shall be issued by City. D. The Specifications may vary in form, format and style. Some Specification sections may be written in varying degrees of streamlined or declarative style and some sections may be relatively narrative by comparison. Omission of such words and phrases as "the Contractor shall," "in conformity with," "as shown," or "as specified" are intentional in streamlined sections. Omitted words and phrases shall be supplied by inference. Similar types of provisions may appear in various parts of a section or articles within a part depending on the format of the CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanber2l,2012 007200-1 General Conditions Page 9 of 63 section. The Contractor shall not take advantage of any variation of form, format or style in making Contract Claims. E. The cross referencing of specification sections under the subparagraph heading "Related Sections include but are not necessarily limited to:" and elsewhere within each Specification section is provided as an aid and convenience to the Contractor. The Contractor shall not rely on the cross referencing provided and shall be responsible to coordinate the entire Work under the Contract Documents and provide a complete Project whether or not the cross referencing is provided in each section or whether or not the cross referencing is complete. 3.02 Reference Standards A. Standards, Specifications,Codes,Laws,and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations,whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision of any such standard, specification, manual, or code, or any instruction of a Supplier, shall be effective to change the duties or responsibilities of City, Contractor, or any of their subcontractors, consultants, agents, or employees, from those set forth in the Contract Documents. No such provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.03 Reporting and Resolving Discrepancies A. Reporting Discrepancies: 1. Contractor's Review of Contract Documents Before Starting Work: Before undertaking each part of the Work, Contractor shall carefully study and compare the Contract Documents and check and verify pertinent figures therein against all applicable field measurements and conditions. Contractor shall promptly report in writing to City any conflict, error, ambiguity, or discrepancy which Contractor discovers, or has actual knowledge of, and shall obtain a written interpretation or clarification from City before proceeding with any Work affected thereby. 2. Contractor's Review of Contract Documents During Performance of Work: If, during the performance of the Work, Contractor discovers any conflict, error, ambiguity, or discrepancy within the Contract Documents, or between the Contract Documents and (a) any applicable Law or Regulation , (b)any standard, specification,manual, or code, or(c) any instruction of any Supplier, then Contractor shall promptly report it to City in writing. Contractor shall not proceed with the Work affected thereby (except in an emergency as required by Paragraph MY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deomnber2l,2012 0072 00-1 General Conditions Page 10 of 63 6.17.A) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in Paragraph 3.04. 3. Contractor shall not be liable to City for failure to report any conflict, error, ambiguity, or discrepancy in the Contract Documents unless Contractor had actual knowledge thereof. B. Resolving Discrepancies: 1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Contract Documents and the provisions of any standard, specification, manual, or the instruction of any Supplier(whether or not specifically f incorporated by reference in the Contract Documents). 2. In case of discrepancies, figured dimensions shall govern over scaled dimensions, Plans shall govern over Specifications, Supplementary Conditions shall govern over General Conditions and Specifications, and quantities shown on the Plans shall govern over those shown in the proposal. 3.04 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one or more of the following ways: 1. A Field Order; 2. City's review of a Submittal (subject to the provisions of Paragraph 6.18.C); or 3. City's written interpretation or clarification. 3.05 Reuse of Documents A. Contractor and any Subcontractor or Supplier shall not: 1. have or acquire any title to or ownership rights in any of the Drawings, Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer, including electronic media editions;or 2. reuse any such Drawings, Specifications, other documents, or copies thereof on extensions of the Project or any other project without written consent of City and specific written verification or adaptation by Engineer. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber2l,2012 00 72 00-1 General Conditions Page 1 I of 63 B. The prohibitions of this Paragraph 3.05 will survive final payment, or termination of the Contract. Nothing herein shall preclude Contractor from retaining copies of the Contract Documents for record purposes. 3.06 Electronic Data A. Unless otherwise stated in the Supplementary Conditions,the data furnished by City or Engineer to Contractor, or by Contractor to City or Engineer, that may be relied upon are limited to the printed copies included in the Contract Documents (also known as hard copies) and other Specifications referenced and located on the City's Buzzsaw site. Files in electronic media format of text, data, graphics, or other types are furnished only for the convenience of the receiving party. Any conclusion or information obtained or derived from such electronic files will be at the user's sole risk. If there is a discrepancy between the electronic files and the hard copies,the hard copies govern. B. When transferring documents in electronic media format, the transferring party makes no representations as to long term compatibility, usability, or readability of documents resulting from the use of software application packages, operating systems, or computer hardware differing from those used by the data's creator. ARTICLE 4—AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS 4.01 Availability of Lands A. City shall furnish the Site. City shall notify Contractor of any encumbrances or restrictions not of general application but specifically related to use of the Site with which Contractor must comply in performing the Work. City will obtain in a timely manner and pay for easements for permanent structures or permanent changes in existing facilities. 1. The City has obtained or anticipates acquisition of and/or access to right-of-way, and/or easements. Any outstanding right-of-way and/or easements are anticipated to be acquired in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding right-of-way, and/or easements. 2. The City has or anticipates removing and/or relocating utilities, and obstructions to the Site. Any outstanding removal or relocation of utilities or obstructions is anticipated in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding utilities or obstructions to be removed,adjusted, and/or relocated by others. B. Upon reasonable written request, City shall furnish Contractor with a current statement of record legal title and legal description of the lands upon which the Work is to be performed. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dombar2l,2012 007200-1 General Conditions Page 12 of 63 C. Contractor shall provide for all additional lands and access thereto that may be required for construction facilities or storage of materials and equipment. 4.02 Subsurface and Physical Conditions A. Reports and Drawings: The Supplementary Conditions identify: 1. those reports known to City of explorations and tests of subsurface conditions at or contiguous to the Site; and 2. those drawings known to City of physical conditions relating to existing surface or subsurface structures at the Site(except Underground Facilities). B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Supplementary Conditions. Contractor may not make any Contract Claim against City, or any of their officers, directors,members,partners,employees,agents,consultants,or subcontractors with respect to: 1. the completeness of such reports and drawings for Contractor's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions, and information contained in such reports or shown or indicated in such drawings;or 3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such other data, interpretations,opinions,or information. 4.03 Differing Subsurface or Physical Conditions A. Notice: If Contractor believes that any subsurface or physical condition that is uncovered or revealed either: 1. is of such a nature as to establish that any"technical data" on which Contractor is entitled to rely as provided in Paragraph 4.02 is materially inaccurate;or 2. is of such a nature as to require a change in the Contract Documents;or 3. differs materially from that shown or indicated in the Contract Documents;or 4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents; CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dewnber2l,2012 007200-1 General Conditions Page 13 of 63 then Contractor shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical conditions or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.17.A),notify City in writing about such condition. B. Possible Price and Time Adjustments Contractor shall not be entitled to any adjustment in the Contract Price or Contract Time if: 1. Contractor knew of the existence of such conditions at the time Contractor made a final commitment to City with respect to Contract Price and Contract Time by the submission of a Bid or becoming bound under a negotiated contract;or 2. the existence of such condition could reasonably have been discovered or revealed as a result of the examination of the Contract Documents or the Site; or 3. Contractor failed to give the written notice as required by Paragraph 4.03.A. 4.04 Underground Facilities A. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the Site is based on information and data furnished to City or Engineer by the owners of such Underground Facilities, including City, or by others. Unless it is otherwise expressly provided in the Supplementary Conditions: 1. City and Engineer shall not be responsible for the accuracy or completeness of any such information or data provided by others;and 2. the cost of all of the following will be included in the Contract Price, and Contractor shall have full responsibility for: a. reviewing and checking all such information and data; b. locating all Underground Facilities shown or indicated in the Contract Documents; c. coordination and adjustment of the Work with the owners of such Underground Facilities, including City,during construction; and d. the safety and protection of all such Underground Facilities and repairing any damage thereto resulting from the Work. B. Not Shown or Indicated: 1. If an Underground Facility which conflicts with the Work is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decenba2l,2012 0072 00-1 General Conditions Page 14 of 63 Work in connection therewith (except in an emergency as required by Paragraph 6.17.A), identify the owner of such Underground Facility and give notice to that owner and to City. City will review the discovered Underground Facility and determine the extent, if any, to which a change may be required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. Contractor shall be responsible for the safety and protection of such discovered Underground Facility. 2. If City concludes that a change in the Contract Documents is required, a Change Order may be issued to reflect and document such consequences. 3. Verification of existing utilities, structures, and service lines shall include notification of all utility companies a minimum of 48 hours in advance of construction including exploratory excavation if necessary. 4.05 Reference Points A. City shall provide engineering surveys to establish reference points for construction, which in City's judgment are necessary to enable Contractor to proceed with the Work. City will provide construction stakes or other customary method of marking to establish line and grades for roadway and utility construction, centerlines and benchmarks for bridgework. Contractor shall protect and preserve the established reference points and property monuments, and shall make no changes or relocations. Contractor shall report to City whenever any reference point or property monument is lost or destroyed or requires relocation because of necessary changes in grades or locations. The City shall be responsible for the replacement or relocation of reference points or property monuments not carelessly or willfully destroyed by the Contractor. The Contractor shall notify City in advance and with sufficient time to avoid delays. B. Whenever, in the opinion of the City, any reference point or monument has been carelessly or willfully destroyed, disturbed, or removed by the Contractor or any of his employees, the full cost for replacing such points plus 25% will be charged against the Contractor, and the full amount will be deducted from payment due the Contractor. 4.06 Hazardous Environmental Condition at Site A. Reports and Drawings: The Supplementary Conditions identify those reports and drawings known to City relating to Hazardous Environmental Conditions that have been identified at the Site. B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Supplementary Conditions. Contractor may not make any Contract Claim against City, or any of their officers, directors,members,partners, employees, agents,consultants, or subcontractors with respect to: 1. the completeness of such reports and drawings for Contractor's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanber2l,2012 007200-1 General Conditions Page 15 of 63 construction to be employed by Contractor and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings;or 3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such other data,interpretations,opinions or information. C. Contractor shall not be responsible for any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work. Contractor shall be responsible for a Hazardous Environmental Condition created with any materials brought to the Site by Contractor, Subcontractors, Suppliers,or anyone else for whom Contractor is responsible. D. If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone for whom Contractor is responsible creates a Hazardous Environmental Condition, Contractor shall immediately: (i) secure or otherwise isolate such condition; (ii) stop all Work in connection with such condition and in any area affected thereby (except in an emergency as required by Paragraph 6.17.A); and (iii) notify City(and promptly thereafter confirm such notice in writing). City may consider the necessity to retain a qualified expert to evaluate such condition or take corrective action, if any. E. Contractor shall not be required to resume Work in connection with such condition or in any affected area until after City has obtained any required permits related thereto and delivered written notice to Contractor: (i) specifying that such condition and any affected area is or has been rendered suitable for the resumption of Work; or (ii) specifying any special conditions under which such Work may be resumed. F. If after receipt of such written notice Contractor does not agree to resume such Work based on a reasonable belief it is unsafe, or does not agree to resume such Work under such special conditions, then City may order the portion of the Work that is in the area affected by such condition to be deleted from the Work. City may have such deleted portion of the Work performed by City's own forces or others. G. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City,from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to a Hazardous Environmental Condition created by Contractor or by anyone for whom Contractor is responsible. Nothing in this Paragraph 4.06G shall obligate Contractor to indemnify any individual or entity from and against the consequences of that individual's or entity's own negligence. H. The provisions of Paragraphs 4.02, 4.03, and 4.04 do not apply to a Hazardous Environmental Condition uncovered or revealed at the Site. MY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deoanber2l,2012 007200-1 General Conditions Page 16 of 63 ARTICLE 5—BONDS AND INSURANCE 5.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverages so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 5.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor's obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of"Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney-in-fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 5.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 5.01 and 5.02.C. 5.03 Certificates of Insurance Contractor shall deliver to City, with copies to each additional insured and loss payee identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by City or any other additional insured)which Contractor is required to purchase and maintain. 1. The certificate of insurance shall document the City, and all identified entities named in the Supplementary Conditions as"Additional Insured"on all liability policies. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanber2l,2012 00 7200-1 General Conditions Page 17 of 63 2. The Contractor's general liability insurance shall include a, "per project" or "per location", endorsement,which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property&Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers' compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required,written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in the Supplementary Conditions 6. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor's obligation to maintain such lines of insurance coverage. 7. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 8. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If coverage is underwritten on a claims-made basis,the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims-made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 9. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 10. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders'equity. In CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber2l,2012 007200-1 General Conditions Page 18 of 63 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups,must also be approved by City. 11. Any deductible in excess of$5,000.00, for any policy that does not provide coverage on a first-dollar basis,must be acceptable to and approved by the City. 12. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage's and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 13. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 14. City shall not be responsible for the direct payment of insurance premium costs for Contractor's insurance. 5.04 Contractor's Insurance A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers' Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers' Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor's performance of the Work and Contractor's other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers' compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor's employees. B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:December 21,2012 007200-I Generel Conditions Page 19 of 63 insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy, unless the City approves such exclusions in writing. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project (if identified in the Supplementary Conditions). C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto", defined as autos owned, hired and non-owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the requirements identified in the Supplementary Conditions. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured.There shall be no time credit for days not worked pursuant to this section. 5.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 6—CONTRACTOR'S RESPONSIBILITIES 6.01 Supervision and Superintendence A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means,methods,techniques,sequences,and procedures of construction. MY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Damnber2l,2012 007200-1 General Conditions Page 20 of 63 B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor's representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 6.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City's written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication)to perform Work: 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 6.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor,transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up,and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not spccified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests)as to the source, kind,and quality of materials and equipment. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De=nber2l,2012 007200-1 General Conditions Page 21 of 63 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier,except as otherwise may be provided in the Contract Documents. D. All items of standard equipment to be incorporated into the Work shall be the latest model at the time of bid,unless otherwise specified. fi.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.07 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.07 and the General Requirements) proposed adjustments in the Project Schedule that will not result in changing the Contract Time. Such adjustments will comply with any provisions of the General Requirements applicable thereto. 2. Contractor shall submit to City a monthly Project Schedule with a monthly progress payment for the duration of the Contract in accordance with the schedule specification 01 32 16. 3. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 12. Adjustments in Contract Time may only be made by a Change Order. 6.05 Substitutes and "Or-Equals" A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or "or-equal" item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. "Or-Equal"Items: If in City's sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an "or-equal" item, in which case review and approval of the proposed item may, in City's sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 6.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. the City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength,and design characteristics; CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber2l,2012 007200-1 General Conditions Page 22 of 63 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service;and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City's sole discretion an item of material or equipment proposed by Contractor does not qualify as an "or-equal" item under Paragraph 6.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 0125 00 and: 1) shall certify that the proposed substitute item will: a) perform adequately the functions and achieve the results called for by the general design; b) be similar in substance to that specified; c) be suited to the same use as that specified; and 2) will state: a) the extent, if any, to which the use of the proposed substitute item will prejudice Contractor's achievement of final completion on time; b) whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; CITY OF FORT WORTH STANDARD CONSTRUCTTON SPECIFCATION DOCUMENTS Revision:De=nber2l,2012 007200-1 General Conditions Page 23 of 63 c) whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: a) all variations of the proposed substitute item from that specified; b) available engineering, sales,maintenance,repair,and replacement services;and 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City's sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 6.05.A.2. C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 6.05.A and 6.05.B. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No "or-equal" or substitute will be ordered, installed or utilized until City's review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an "or-equal."City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 6.05.A.2 and 6.05.13. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents (or in the provisions of any other direct contract with City)resulting from the acceptance of each proposed substitute. F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or "or-equal"at Contractor's expense. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dxenber2l,2012 007200-1 General Conditions Page 24 of 63 G. City Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Change Order. H. Time Extensions:No additional time will be granted for substitutions. 6.06 Concerning Subcontractors, Suppliers, and Others A. Contractor shall perform with his own organization, work of a value not less than 35% of the value embraced on the Contract,unless otherwise approved by the City. B. Contractor shall not employ any Subcontractor, Supplier, or other individual or entity, whether initially or as a replacement, against whom City may have reasonable objection. Contractor shall not be required to employ any Subcontractor, Supplier, or other individual or entity to furnish or perform any of the Work against whom Contractor has reasonable objection (excluding those acceptable to City as indicated in Paragraph 6.06.C). C. The City may from time to time require the use of certain Subcontractors, Suppliers, or other individuals or entities on the project, and will provide such requirements in the Supplementary Conditions. D. Business Diversity Enterprise Ordinance Compliance: It is City policy to ensure the full and equitable participation by Minority and Small Business Enterprises (MBE)(SBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MBE and/or SBE goal, Contractor is required to comply with the intent of the City's Business Diversity Ordinance(as amended)by the following: 1. Contractor shall, upon request by the City, provide complete and accurate information regarding actual work performed by a MBE and/or SBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records, or files in the possession of the Contractor that will substantiate the actual work performed by an MBE and/or SBE. Material misrepresentation of any nature may be grounds for termination of the Contract in accordance with Paragraph 15.02.A. Any such misrepresentation may be grounds for disqualification of Contractor to bid on future contracts with the City for a period of not less than three years. E. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract Documents: CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Detanber2l,2012 007200-1 General Conditions Page 25 of 63 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity;nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. F. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. G. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. H. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the benefit of City. 6.07 Wage Rates A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs,pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31 st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City's determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanber2l,2012 0072 00-1 General Conditions Page 26 of 63 D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show (i)the name and occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii)the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258,Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 6.08 Patent Fees and Royalties A. Contractor shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, product, or device which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product, or device is specified in the Contract Documents for use in the performance of the Work and if,to the actual knowledge of City, its use is subject to patent rights or copyrights calling for the payment of any licensc fee or royalty to others, the existence of such rights shall be disclosed by City in the Contract Documents. Failure of the City to disclose such information does not relieve the Contractor from its obligations to pay for the use of said fees or royalties to others. B. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City,from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deurnber21,2012 007200-1 General Conditions Page 27 of 63 the incorporation in the Work of any invention, design,process,product, or device not specified in the Contract Documents. 6.09 Permits and Utilities A. Contractor obtained permits and licenses. Contractor shall obtain and pay for all construction pen-nits and licenses except those provided for in the Supplementary Conditions or Contract Documents. City shall assist Contractor, when necessary, in obtaining such permits and licenses. Contractor shall pay all governmental charges and inspection fees necessary for the prosecution of the Work which are applicable at the time of opening of Bids, or, if there are no Bids, on the Effective Date of the Agreement, except for permits provided by the City as specified in 6.09.B. City shall pay all charges of utility owners for connections for providing permanent service to the Work. B. City obtained permits and licenses. City will obtain and pay for all permits and licenses as provided for in the Supplementary Conditions or Contract Documents. It will be the Contractor's responsibility to carry out the provisions of the permit. If the Contractor initiates changes to the Contract and the City approves the changes, the Contractor is responsible for obtaining clearances and coordinating with the appropriate regulatory agency. The City will not reimburse the Contractor for any cost associated with these requirements of any City acquired permit. The following are permits the City will obtain if required: 1. Texas Department of Transportation Permits 2. U.S.Army Corps of Engineers Permits 3. Texas Commission on Environmental Quality Permits 4. Railroad Company Permits C. Outstanding permits and licenses. The City anticipates acquisition of and/or access to permits and licenses. Any outstanding permits and licenses are anticipated to be acquired in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding permits and licenses. 6.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decenber2l,2012 007200-1 General Conditions Page 28 of 63 court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor's responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor's obligations under Paragraph 3.02. C. Changes in Laws or Regulations not known at the time of opening of Bids having an effect on the cost or time of performance of the Work may be the subject of an adjustment in Contract Price or Contract Time. 6.11 Taxes A. On a contract awarded by the City, an organization which qualifies for exemption pursuant to Texas Tax Code, Subchapter H, Sections 151.301-335 (as amended), the Contractor may purchase, rent or lease all materials, supplies and equipment used or consumed in the performance of this contract by issuing to his supplier an exemption certificate in lieu of the tax, said exemption certificate to comply with State Comptroller's Ruling .007. Any such exemption certificate issued to the Contractor in lieu of the tax shall be subject to and shall comply with the provision of State Comptroller's Ruling .011, and any other applicable rulings pertaining to the Texas Tax Code, Subchapter H. B. Texas Tax permits and information may be obtained from: 1. Comptroller of Public Accounts Sales Tax Division Capitol Station Austin,TX 78711;or 2. h!W://www.window.state.tx.us/taxinfo/taxforrns/93-forms.html, 6.12 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment,the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deowd=21,2012 007200-1 General Conditions Page 29 of 63 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 621, Contractor shall indemnify and hold harmless City,from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and the costs of such direct action, plus 25 % of such costs, shall be deducted from the monies due or to become due to the Contractor. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 6.13 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 6.14 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decenba2l,2012 007200-1 General Conditions Page 30 of 63 take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal,relocation,or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal,relocation, and replacement of their property. C. Contractor shall comply with the applicable requirements of City's safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any, with which City's employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 6.14.A.2 or 6.14.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work,or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 6.15 Safety Representative Contractor shall inform City in writing of Contractor's designated safety representative at the Site. 6.16 Hazard Communication.Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 6.17 Emergencies andlor Rectification A. In emergencies affecting the safety or protection of persons or the Work or property at the Site or adjacent thereto, Contractor is obligated to act to prevent threatened damage, injury, or loss. Contractor shall give City prompt written notice if Contractor believes that any significant CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Do=nber2l,2012 007200-1 General Conditions Page 31 of 63 changes in the Work or variations from the Contract Documents have been caused thereby or are required as a result thereof. If City determines that a change in the Contract Documents is required because of the action taken by Contractor in response to such an emergency, a Change Order may be issued. B. Should the Contractor fail to respond to a request from the City to rectify any discrepancies, omissions, or correction necessary to conform with the requirements of the Contract Documents, the City shall give the Contractor written notice that such work or changes are to be performed. The written notice shall direct attention to the discrepant condition and request the Contractor to take remedial action to correct the condition. In the event the Contractor does not take positive steps to fulfill this written request, or does not show just cause for not taking the proper action, within 24 hours, the City may take such remedial action with City forces or by contract. The City shall deduct an amount equal to the entire costs for such remedial action, plus 25%, from any funds due or become due the Contractor on the Project. 6.18 Submittals A. Contractor shall submit required Submittals to City for review and acceptance in accordance with the accepted Schedule of Submittals (as required by Paragraph 2.07).Each submittal will be identified as City may require. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 6.18.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For-Information-Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier,pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 6.18.C. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deewnber2l,2012 007200-1 General Conditions Page 32 of 63 B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City's review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City's Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City's review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 2. City's review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City's review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City's review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 6.19 Continuing the Work Except as otherwise provided, Contractor shall carry on the Work and adhere to the Project Schedule during all disputes or disagreements with City. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as City and Contractor may otherwise agree in writing. 6.20 Contractor's General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor's warranty and guarantee. B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber2l,2012 007200-1 General Conditions Page 33 of 63 2. normal wear and tear under normal usage. C. Contractor's obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor's obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection,test,or approval by others; or 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 5.02.13.The City will give notice of observed defects with reasonable promptness. 6.21 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICAL.L.Y INTENDED TO OPERATE AND BE EFFECTIVE FVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIC.FNCF, OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De=nber2l,2012 007200-1 General Conditions Page 34 of 63 SPECIFICALLY INTENDED TO OPERATE-AND BF—EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES B IN SOUGHT WERE CAUSED, IN WHOLE OR IN PART. BY ANY ACT. OMISSION OR NEGLIGENCE DF THE CITY, 6.22 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor's responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional's written approval when submitted to City. C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 6.22, City's review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City's review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 6.18.C. 6.23 Right to Audit A. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. B. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deem ber2l,2012 007200-1 General Conditions Page 35 of 63 Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. C. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 6.24 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit- related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. ARTICLE 7—OTHER WORK AT THE SITE 7.01 Related Work at Site A. City may perform other work related to the Project at the Site with City's employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work;and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City's employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and F properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that F Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor's Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor's Work. Contractor's failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor's Work except for latent defects in the work provided by others. r CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deomter2l,2012 007200-1 General Conditions Page 36 of 63 7.02 Coordination A. If City intends to contract with others for the performance of other work on the Project at the Site,the following will be set forth in Supplementary Conditions: 1. the individual or entity who will have authority and responsibility for coordination of the activities among the various contractors will be identified; 2. the specific matters to be covered by such authority and responsibility will be itemized; and 3. the extent of such authority and responsibilities will be provided. B. Unless otherwise provided in the Supplementary Conditions, City shall have authority for such coordination. ARTICLE 8—CITY'S RESPONSIBILITIES 8.01 Communications to Contractor Except as otherwise provided in the Supplementary Conditions, City shall issue all communications to Contractor. 8.02 Furnish Data City shall timely furnish the data required under the Contract Documents. 8.03 Pay When Due City shall make payments to Contractor in accordance with Article 14. 8.04 Lands and Easements;Reports and Tests City's duties with respect to providing lands and easements and providing engineering surveys to establish reference points are set forth in Paragraphs 4.01 and 4.05. Paragraph 4.02 refers to City's identifying and making available to Contractor copies of reports of explorations and tests of subsurface conditions and drawings of physical conditions relating to existing surface or subsurface structures at or contiguous to the Site that have been utilized by City in preparing the Contract Documents. 8.05 Change Orders City shall execute Change Orders in accordance with Paragraph 10.03. 8.06 Inspections, Tests, and Approvals City's responsibility with respect to certain inspections,tests, and approvals is set forth in Paragraph 13.03. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decelnber2l,2012 007200-1 General Conditions Page 37 of 63 8.07 Limitations on City's Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor's means, methods,techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor's failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 6.14. 8.08 Undisclosed Hazardous Environmental Condition City's responsibility with respect to an undisclosed Hazardous Environmental Condition is set forth in Paragraph 4.06. 8.09 Compliance with Safety Program While at the Site, City's employees and representatives shall comply with the specific applicable requirements of Contractor's safety programs of which City has been informed pursuant to Paragraph 6.14. ARTICLE 9—CITY'S OBSERVATION STATUS DURING CONSTRUCTION 9.01 City's Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City's representative during construction are set forth in the Contract Documents. The Project Representative(s) will be as provided in the Supplementary Conditions. 9.02 Visits to Site A. City's Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor's executed Work. Based on information obtained during such visits and observations, City's Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City's Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City's Project Representative's efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City's Project Representative's visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents including those set forth in Paragraph 8.07. MY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deartiber2l,2012 007200-1 General Conditions Page 38 of 63 9.03 Authorized Variations in Work City's Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City and also on Contractor,who shall perform the Work involved promptly. 9.04 Rejecting Defective Work City will have authority to reject Work which City's Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 13, whether or not the Work is fabricated, installed, or completed. 9.05 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City's Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City's written decision will be final (except as modified to reflect changed factual conditions or more accurate data). 9.06 Decisions on Requirements of Contract Documents and Acceptability of Work A. City will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. B. City will render a written decision on any issue referred. C. City's written decision on the issue referred will be final and binding on the Contractor, subject to the provisions of Paragraph 10.06. ARTICLE 10—CHANGES IN THE WORK; CLAIMS; EXTRA WORK 10.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Change Order which may or may not precede an order Of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price, a Field Order may be issued by the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dearnber2l,2012 00 7200-1 General Conditions Page 39 of 63 10.02 Unauthorized Changes in the Work Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Time with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented as provided in Paragraph 3.04, except in the case of an emergency as provided in Paragraph 6.17. 10.03 Execution of Change Orders A. City and Contractor shall execute appropriate Change Orders covering: 1. changes in the Work which are: (i) ordered by City pursuant to Paragraph 10.01.A, (ii) required because of acceptance of defective Work under Paragraph 13.08 or City's convection of defective Work under Paragraph 13.09,or(iii)agreed to by the parties; 2. changes in the Contract Price or Contract Time which are agreed to by the parties, including any undisputed sum or amount of time for Work actually performed. 10.04 Extra Work A. Should a difference arise as to what does or does not constitute Extra Work, or as to the payment thereof, and the City insists upon its performance, the Contractor shall proceed with the work after making written request for written orders and shall keep accurate account of the actual reasonable cost thereof. Contract Claims regarding Extra Work shall be made pursuant to Paragraph 10.06. B. The Contractor shall furnish the City such installation records of all deviations from the original Contract Documents as may be necessary to enable the City to prepare for permanent record a corrected set of plans showing the actual installation. C. The compensation agreed upon for Extra Work whether or not initiated by a Change Order shall be a full, complete and final payment for all costs Contractor incurs as a result or relating to the change or Extra Work, whether said costs are known, unknown, foreseen or unforeseen at that time, including without limitation, any costs for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged work as a result of the change or Extra Work. 10.05 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor's responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwe nber2l,2012 007200-1 General Conditions Page 40 of 63 10.06 Contract Claims Process A. City's Decision Required: All Contract Claims, except those waived pursuant to Paragraph 14.09, shall be referred to the City for decision. A decision by City shall be required as a condition precedent to any exercise by Contractor of any rights or remedies he may otherwise have under the Contract Documents or by Laws and Regulations in respect of such Contract Claims. B. Notice: 1. Written notice stating the general nature of each Contract Claim shall be delivered by the Contractor to City no later than 15 days after the start of the event giving rise thereto. The responsibility to substantiate a Contract Claim shall rest with the party making the Contract Claim. 2. Notice of the amount or extent of the Contract Claim, with supporting data shall be delivered to the City on or before 45 days from the start of the event giving rise thereto (unless the City allows additional time for Contractor to submit additional or more accurate data in support of such Contract Claim). 3. A Contract Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of Paragraph 12.01. 4. A Contract Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of Paragraph 12.02. 5. Each Contract Claim shall be accompanied by Contractor's written statement that the adjustment claimed is the entire adjustment to which the Contractor believes it is entitled as a result of said event. 6. The City shall submit any response to the Contractor within 30 days after receipt of the claimant's last submittal (unless Contract allows additional time). C. City's Action: City will review each Contract Claim and, within 30 days after receipt of the last submittal of the Contractor, if any,take one of the following actions in writing: 1. deny the Contract Claim in whole or in part; 2. approve the Contract Claim;or 3. notify the Contractor that the City is unable to resolve the Contract Claim if, in the City's sole discretion, it would be inappropriate for the City to do so. For purposes of further resolution of the Contract Claim, such notice shall be deemed a denial. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:DecmiW21,2012 007200-1 General Conditions Page 41 of 63 D. City's written action under Paragraph 10.06.0 will be final and binding, unless City or Contractor invoke the dispute resolution procedure set forth in Article 16 within 30 days of such action or denial. E. No Contract Claim for an adjustment in Contract Price or Contract Time will be valid if not submitted in accordance with this Paragraph 10.06. ARTICLE 11 —COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK; PLANS QUANTITY MEASUREMENT 11.01 Cost of the Work A. Costs Included: The term Cost of the Work means the sum of all costs, except those excluded in Paragraph 11.013, necessarily incurred and paid by Contractor in the proper performance of the Work. When the value of any Work covered by a Change Order, the costs to be reimbursed to Contractor will be only those additional or incremental costs required because of the change in the Work. Such costs shall not include any of the costs itemized in Paragraph 11.01.B, and shall include but not be limited to the following items: 1. Payroll costs for employees in the direct employ of Contractor in the performance of the Work under schedules of job classifications agreed upon by City and Contractor. Such employees shall include, without limitation, superintendents, foremen, and other personnel employed full time on the Work. Payroll costs for employees not employed full time on the Work shall be apportioned on the basis of their time spent on the Work. Payroll costs shall include; a. salaries with a 55%markup,or b. salaries and wages plus the cost of fringe benefits, which shall include social security contributions, unemployment, excise, and payroll taxes, workers' compensation, health and retirement benefits, bonuses, sick leave, vacation and holiday pay applicable thereto. The expenses of performing Work outside of Regular Working Hours, Weekend Working Hours, or legal holidays, shall be included in the above to the extent authorized by City. 2. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers' field services required in connection therewith. 3. Rentals of all construction equipment and machinery, and the parts thereof whether rented from Contractor or others in accordance with rental agreements approved by City, and the costs of transportation, loading, unloading, assembly, dismantling, and removal thereof. All such costs shall be in accordance with the terms of said rental agreements. The rental of any such equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the Work. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De=nber2l,2012 007200-1 General Conditions Page 42 of 63 4. Payments made by Contractor to Subcontractors for Work performed by Subcontractors. If required by City, Contractor shall obtain competitive bids from subcontractors acceptable to City and Contractor and shall deliver such bids to City, who will then determine, which bids, if any, will be acceptable. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work and fee shall be determined in the same manner as Contractor's Cost of the Work and fee as provided in this Paragraph 11.01. 5. Costs of special consultants (including but not limited to engineers, architects, testing laboratories, surveyors, attorneys, and accountants) employed for services specifically related to the Work. 6. Supplemental costs including the following: a. The proportion of necessary transportation, travel, and subsistence expenses of Contractor's employees incurred in discharge of duties connected with the Work. b. Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, office, and temporary facilities at the Site, and hand tools not owned by the workers, which are consumed in the performance of the Work, and cost, less market value, of such items used but not consumed which remain the property of Contractor. c. Sales, consumer, use, and other similar taxes related to the Work, and for which Contractor is liable not covered under Paragraph 6.11, as imposed by Laws and Regulations. d. Deposits lost for causes other than negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable,and royalty payments and fees for permits and licenses. e. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by Contractor in connection with the performance of the Work, provided such losses and damages have resulted from causes other than the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and approval of City. No such losses, damages, and expenses shall be included in the Cost of the Work for the purpose of determining Contractor's fee. f. The cost of utilities,fuel, and sanitary facilities at the Site. g. Minor expenses such as telegrams, long distance telephone calls, telephone and communication services at the Site, express and courier services, and similar petty cash items in connection with the Work. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber21,2012 0072 00-1 General Conditions Page 43 of 63 h. The costs of premiums for all bonds and insurance Contractor is required by the Contract Documents to purchase and maintain. B. Costs Excluded: The term Cost of the Work shall not include any of the following items: 1. Payroll costs and other compensation of Contractor's officers, executives, principals (of partnerships and sole proprietorships), general managers, safety managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, expediters, timekeepers, clerks, and other personnel employed by Contractor, whether at the Site or in Contractor's principal or branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in Paragraph 11.0I.A.I or specifically covered by Paragraph 11.0LAA, all of which are to be considered administrative costs covered by the Contractor's fee. 2. Expenses of Contractor's principal and branch offices other than Contractor's office at the Site. 3. Any part of Contractor's capital expenses, including interest on Contractor's capital employed for the Work and charges against Contractor for delinquent payments. 4. Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to, the correction of defective Work, disposal of materials or equipment wrongly supplied, and making good any damage to property. 5. Other overhead or general expense costs of any kind. C. Contractor's Fee: When all the Work is performed on the basis of cost-plus, Contractor's fee shall be determined as set forth in the Agreement. When the value of any Work covered by a Change Order for an adjustment in Contract Price is determined on the basis of Cost of the Work, Contractor's fee shall be determined as set forth in Paragraph 12.01.C. D. Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to Paragraphs I LOLA and 11.01.13, Contractor will establish and maintain records thereof in accordance with generally accepted accounting practices and submit in a form acceptable to City an itemized cost breakdown together with supporting data. 11.02 Allowances A. Specified Allowance. It is understood that Contractor has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be performed for such sums and by such persons or entities as may be acceptable to City. B. Pre-bid Allowances: 1. Contractor agrees that: CrrY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanber2l,2012 0072 00-1 General Conditions Page 44 of 63 a. the pre-bid allowances include the cost to Contractor of materials and equipment required by the allowances to be delivered at the Site,and all applicable taxes; and b. Contractor's costs for unloading and handling on the Site, labor, installation, overhead, profit, and other expenses contemplated for the pre-bid allowances have been included in the allowances, and no demand for additional payment on account of any of the foregoing will be valid. C. Contingency Allowance: Contractor agrees that a contingency allowance, if any, is for the sole use of City. D. Prior to final payment, an appropriate Change Order will be issued to reflect actual amounts due Contractor on account of Work covered by allowances, and the Contract Price shall be correspondingly adjusted. 11.03 Unit Price Work A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the unit price for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement. B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by Contractor will be made by City subject to the provisions of Paragraph 9.05. C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to cover Contractor's overhead and profit for each separately identified item. Work described in the Contract Documents, or reasonably inferred as required for a functionally complete installation, but not identified in the listing of unit price items shall be considered incidental to unit price work listed and the cost of incidental work included as part of the unit price. D. City may make an adjustment in the Contract Price in accordance with Paragraph 12.01 i£ 1. the quantity of any item of Unit Price Work performed by Contractor differs materially and significantly from the estimated quantity of such item indicated in the Agreement; and 2. there is no corresponding adjustment with respect to any other item of Work. E. .Increased or Decreased Quantities: The City reserves the right to order Extra Work in accordance with Paragraph 10.01. 1. If the changes in quantities or the alterations do not significantly change the character of work under the Contract Documents, the altered work will be paid for at the Contract unit price. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decenber2l,2012 007200-1 General Conditions Page 45 of 63 2. If the changes in quantities or alterations significantly change the character of work, the Contract will be amended by a Change Order. 3. If no unit prices exist, this will be considered Extra Work and the Contract will be amended by a Change Order in accordance with Article 12. 4. A significant change in the character of work occurs when: a. the character of work for any Item as altered differs materially in kind or nature from that in the Contract or b. a Major Item of work varies by more than 25%from the original Contract quantity. 5. When the quantity of work to be done under any Major Item of the Contract is more than 125% of the original quantity stated in the Contract, then either party to the Contract may request an adjustment to the unit price on the portion of the work that is above 125%. 6. When the quantity of work to be done under any Major Item of the Contract is less than 75% of the original quantity stated in the Contract, then either party to the Contract may request an adjustment to the unit price. 11.04 Plans Quantity Measurement A. Plans quantities may or may not represent the exact quantity of work performed or material moved, handled, or placed during the execution of the Contract. The estimated bid quantities are designated as final payment quantities,unless revised by the governing Section or this Article. B. If the quantity measured as outlined under"Price and Payment Procedures" varies by more than 25% (or as stipulated under "Price and Payment Procedures" for specific Items) from the total estimated quantity for an individual Item originally shown in the Contract Documents, an adjustment may be made to the quantity of authorized work done for payment purposes. The party to the Contract requesting the adjustment will provide field measurements and calculations showing the final quantity for which payment will be made. Payment for revised quantity will be made at the unit price bid for that Item,except as provided for in Article 10. C. When quantities are revised by a change in design approved by the City, by Change Order, or to correct an error, or to correct an error on the plans, the plans quantity will be increased or decreased by the amount involved in the change, and the 25% variance will apply to the new plans quantity. D. If the total Contract quantity multiplied by the unit price bid for an individual Item is less than $250 and the Item is not originally a plans quantity Item, then the Item may be paid as a pia.ns quantity Item if the City and Contractor agree in writing to fix the final quantity as a plans quantity. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decetnber2l,2012 007200-1 General Conditions Page 46 of 63 E. For callout work or non-site specific Contracts,the plans quantity measurement requirements are not applicable. ARTICLE 12—CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 12.01 Change of Contract Price A. The Contract Price may only be changed by a Change Order. B. The value of any Work covered by a Change Order will be determined as follows: 1. where the Work involved is covered by unit prices contained in the Contract Documents, by application of such unit prices to the quantities of the items involved (subject to the provisions of Paragraph 11.03);or 2. where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed lump sum or unit price (which may include an allowance for overhead and profit not necessarily in accordance with Paragraph 12.01.C.2), and shall include the cost of any secondary impacts that are foreseeable at the time of pricing the cost of Extra Work; or 3. where the Work involved is not covered by unit prices contained in the Contract Documents and agreement to a lump sum or unit price is not reached under Paragraph 12.01.13.2, on the basis of the Cost of the Work (determined as provided in Paragraph 11.01) plus a Contractor's fee for overhead and profit(determined as provided in Paragraph 12.01.C). C. Contractor's Fee: The Contractor's additional fee for overhead and profit shall be determined as follows: 1. a mutually acceptable fixed fee; or 2. if a fixed fee is not agreed upon,then a fee based on the fallowing percentages of the various portions of the Cost of the Work: a. for costs incurred under Paragraphs 11.01.A.1, 11.01.A.2. and 11.01.A.3, the Contractor's additional fee shall be 15 percent except for: 1) rental fees for Contractor's own equipment using standard rental rates; 2) bonds and insurance; b. for costs incurred under Paragraph 11.01.A.4 and 11.01.A.5,the Contractor's fee shall be five percent(5%); 1) where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of Paragraphs 12.01.C.2.a and 12.01.C.2.b is that the Subcontractor who actually performs the Work, at whatever CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deomnber2l,2012 007200-1 General Conditions Page 47 of 63 tier,will be paid a fee of 15 percent of the costs incurred by such Subcontractor under Paragraphs 11.0l.A.1 and 11.0l.A.2 and that any higher tier Subcontractor and Contractor will each be paid a fee of five percent (5%) of the amount paid to the next lower tier Subcontractor, however in no case shall the cumulative total of fees paid be in excess of 25%; c. no fee shall be payable on the basis of costs itemized under Paragraphs 11.0l.A.6, and 11.01.B; d. the amount of credit to be allowed by Contractor to City for any change which results in a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in Contractor's fee by an amount equal to five percent (5 0/6) of such net decrease. 12.02 Change of Contract Time A. The Contract Time may only be changed by a Change Order. B. No extension of the Contract Time will be allowed for Extra Work or for claimed delay unless the Extra Work contemplated or claimed delay is shown to be on the critical path of the Project Schedule or Contractor can show by Critical Path Method analysis how the Extra Work or claimed delay adversely affects the critical path. 12.03 Delays A. Where Contractor is reasonably delayed in the performance or completion of any part of the Work within the Contract Time due to delay beyond the control of Contractor,the Contract Time may be extended in an amount equal to the time lost due to such delay if a Contract Claim is made therefor. Delays beyond the control of Contractor shall include, but not be limited to, acts or neglect by City, acts or neglect of utility owners or other contractors performing other work as contemplated by Article 7, fires, floods, epidemics, abnormal weather conditions, or acts of God. Such an adjustment shall be Contractor's sole and exclusive remedy for the delays described in this Paragraph. B. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. C. Contractor shall not be entitled to an adjustment in Contract Price or Contract Time for delays within the control of Contractor. Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of Contractor. D. The Contractor shall receive no compensation for delays or hindrances to the Work, except when direct and unavoidable extra cost to the Contractor is caused by the failure of the City to provide information or material, if any,which is to be furnished by the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De=nber2l,2012 007200-1 General Conditions Page 48 of 63 ARTICLE 13—TESTS AND INSPECTIONS; CORRECTION,REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 13.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected,corrected,or accepted as provided in this Article 13. 13.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor's safety procedures and programs so that they may comply therewith as applicable. 13.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections,which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re-tests, or approvals required for City's acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor's purchase thereof for incorporation in the Work. Such inspections, tests, re-tests, or approvals shall be performed by organizations acceptable to City. D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to perform any inspections or tests ("Testing") for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible,with Contractor; 2. Should any Testing under this Section 13.03 D result in a "fail", "did not pass" or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor's cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanber2l,2012 00 7200-1 General Conditions Page 49 of 63 3. Any amounts owed for any retest under this Section 13.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue Final Payment until the Testing Lab is paid. E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. F. Uncovering Work as provided in Paragraph 13.03.E shall be at Contractor's expense. G. Contractor shall have the right to make a Contract Claim regarding any retest or invoice issued under Section 13.03 D. 13.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City's observation and replaced at Contractor's expense. B. If City considers it necessary or advisable that covered Work be observed by City or inspected or tested by others, Contractor, at City's request, shall uncover, expose, or otherwise make available for observation, inspection, or testing as City may require, that portion of the Work in question, furnishing all necessary labor,material,and equipment. 1. If it is found that the uncovered Work is defective, Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such uncovering, exposure, observation, inspection, and testing, and of satisfactory replacement or reconstruction (including but not limited to all costs of repair or replacement of work of others); or City shall be entitled to accept defective Work in accordance with Paragraph 13.08 in which case Contractor shall still be responsible for all costs associated with exposing,observing,and testing the defective Work. 2. If the uncovered Work is not found to be defective, Contractor shall be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure,observation, inspection,testing,replacement, and reconstruction. f 13.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any �. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dc=nber2l,2012 007200-1 General Conditions Page 50 of 63 Subcontractor, any Supplier, any other individual or entity,or any surety for,or employee or agent of any of them. 13.06 Correction or Removal of Defective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 13.06 or Paragraph 13.07, Contractor shall take no action that would void or otherwise impair City's special warranty and guarantee, if any, on said Work. 13.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor's use by City or permitted by Laws and Regulations as contemplated in Paragraph 6.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City's written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work,to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City's written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others)will be paid by Contractor. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decenber2l,2012 007200-1 General Conditions Page 51 of 63 C. In special circumstances where a particular item of equipment is placed in continuous service before Final Acceptance of all the Work,the correction period for that item may start to run from an earlier date if so provided in the Contract Documents. D. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 13.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor should such additional warranty coverage be required. Contractor may dispute this requirement by filing a Contract Claim,pursuant to Paragraph 10.06. E. Contractor's obligations under this Paragraph 13.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 13.07 shall not be construed as a substitute for, or a waiver of,the provisions of any applicable statute of limitation or repose. 13.08 Acceptance of Defective Work If, instead of requiring correction or removal and replacement of defective Work, City prefers to accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) attributable to City's evaluation of and determination to accept such defective Work and for the diminished value of the Work to the extent not otherwise paid by Contractor. If any such acceptance occurs prior to Final Acceptance, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work so accepted. 13.09 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 13.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven(7)days written notice to Contractor, correct,or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 13.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor's services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants, employees, and City's other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dooernber21,2012 007200-1 General Conditions Page 52 of 63 costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City's rights and remedies under this Paragraph 13.09. ARTICLE 14—PAYMENTS TO CONTRACTOR AND COMPLETION 14.01 Schedule of Values The Schedule of Values for lump sum contracts established as provided in Paragraph 2.07 will serve as the basis for progress payments and will be incorporated into a form of Application for Payment acceptable to City. Progress payments on account of Unit Price Work will be based on the number of units completed. 14.02 Progress Payments A. Applications for Payments: 1. Contractor is responsible for providing all information as required to become a vendor of the City. 2. At least 20 days before the date established in the General Requirements for each progress payment, Contractor shall submit to City for review an Application for Payment filled out and signed by Contractor covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. 3. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice, or other documentation warranting that City has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate insurance or other arrangements to protect City's interest therein, all of which must be satisfactory to City. 4. Beginning with the second Application for Payment, each Application shall include an affidavit of Contractor stating that previous progress payments received on account of the Work have been applied on account to discharge Contractor's legitimate obligations associated with prior Applications for Payment. 5. The amount of retainage with respect to progress payments will be as stipulated in the Contract Documents. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber21,2012 0072 00-1 General Conditions Page 53 of 63 B. Review of Applications: 1. City will, after receipt of each Application for Payment, either indicate in writing a recommendation of payment or return the Application to Contractor indicating reasons for refusing payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application. 2. City's processing of any payment requested in an Application for Payment will be based on City's observations of the executed Work, and on City's review of the Application for Payment and the accompanying data and schedules,that to the best of City's knowledge: a. the Work has progressed to the point indicated; b. the quality of the Work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Final Acceptance, the results of any subsequent tests called for in the Contract Documents, a final determination of quantities and classifications for Work performed under Paragraph 9.05, and any other qualifications stated in the recommendation). 3. Processing any such payment will not thereby be deemed to have represented that: a. inspections made to check the quality or the quantity of the Work as it has been performed have been exhaustive, extended to every aspect of the Work in progress, or involved detailed inspections of the Work beyond the responsibilities specifically assigned to City in the Contract Documents; or b. there may not be other matters or issues between the parties that might entitle Contractor to be paid additionally by City or entitle City to withhold payment to Contractor,or c. Contractor has complied with Laws and Regulations applicable to Contractor's performance of the Work. 4. City may refuse to process the whole or any part of any payment because of subsequently discovered evidence or the results of subsequent inspections or tests, and revise or revoke any such payment previously made, to such extent as may be necessary to protect City from loss because: a. the Work is defective, or the completed Work has been damaged by the Contractor or his subcontractors,requiring correction or replacement; b. discrepancies in quantities contained in previous applications for payment; c. the Contract Price has been reduced by Change Orders; d. City has been required to correct defective Work or complete Work in accordance with Paragraph 13.09;or CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dearnber2l,2012 007200-1 General Conditions Page 54 of 63 e. City has actual knowledge of the occurrence of any of the events enumerated in Paragraph 15.02.A. C. Retainage: 1. For contracts less than $400,000 at the time of execution, retainage shall be ten percent (10%). 2. For contracts greater than $400,000 at the time of execution, retainage shall be five percent (5%). D. Liquidated Damages. For each calendar day that any work shall remain uncompleted after the time specified in the Contract Documents, the sum per day specified in the Agreement, will be deducted from the monies due the Contractor, not as a penalty, but as liquidated damages suffered by the City. E. Payment: Contractor will be paid pursuant to the requirements of this Article 14 and payment will become due in accordance with the Contract Documents. F. Reduction in Payment: 1. City may refuse to make payment of the amount requested because: a. Liens have been filed in connection with the Work, except where Contractor has delivered a specific bond satisfactory to City to secure the satisfaction and discharge of such Liens; b. there are other items entitling City to a set-off against the amount recommended; or c. City has actual knowledge of the occurrence of any of the events enumerated in Paragraphs 14.02.B.4.a through 14.02.B.4.e or Paragraph 15.02.A. 2. If City refuses to make payment of the amount requested, City will give Contractor written notice stating the reasons for such action and pay Contractor any amount remaining after deduction of the amount so withheld. City shall pay Contractor the amount so withheld, or any adjustment thereto agreed to by City and Contractor, when Contractor remedies the reasons for such action. 14.03 Contractor's Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to City no later than the time of payment free and clear of all Liens. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:December2l,2012 007200-1 General Conditions Page 55 of 63 14.04 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor's performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 14.05 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. B. No time charge will be made against the Contractor between said date of notification of the City and the date of Final Inspection. Should the City determine that the Work is not ready for Final Inspection, City will notify the Contractor in writing of the reasons and Contract Time will resume. 14.06 Final Acceptance Upon completion by Contractor to City's satisfaction, of any additional Work identified in the Final Inspection,City will issue to Contractor a letter of Final Acceptance. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De=nber2l,2012 007200-1 General Conditions Page 56 of 63 14.07 Final Payment A. Application for Payment: I. Upon Final Acceptance, and in the opinion of City, Contractor may make an application for final payment following the procedure for progress payments in accordance with the Contract Documents. 2. The final Application for Payment shall be accompanied(except as previously delivered)by: a. all documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; b. consent of the surety, if any,to final payment; c. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and d, affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. B. Payment Becomes Due: 1. After City's acceptance of the Application for Payment and accompanying documentation, requested by Contractor, less previous payments made and any sum City is entitled, including but not limited to liquidated damages, will become due and payable. 2. After all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor's insurance provider for resolution. 3. The making of the final payment by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. 14.08 Final Completion Delayed and Partial Retainage Release A. If final completion of the Work is significantly delayed, and if City so confirms, City may, upon receipt of Contractor's final Application for Payment, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by City for Work not fully completed or corrected is less than the retainage stipulated in Paragraph 14.02.C, and if bonds have been furnished as required in Paragraph 5.02, the written consent of the surety to the payment of the balance due for that CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:December2l,2012 007200-1 General Conditions Page 57 of 63 portion of the Work fully completed and accepted shall be submitted by Contractor to City with the Application for such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of Contract Claims. B. Partial Retainage Release. For a Contract that provides for a separate vegetative establishment and maintenance, and test and performance periods following the completion of all other construction in the Contract Documents for all Work locations, the City may release a portion of the amount retained provided that all other work is completed as determined by the City. Before the release, all submittals and final quantities must be completed and accepted for all other work. An amount sufficient to ensure Contract compliance will be retained. 14.09 Waiver of Claims The acceptance of final payment will constitute a release of the City from all claims or liabilities under the Contract for anything done or furnished or relating to the work under the Contract Documents or any act or neglect of City related to or connected with the Contract. ARTICLE 15—SUSPENSION OF WORK AND TERMINATION 15.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will make no extra payment for stand-by time of construction equipment and/or construction crews. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not available within a reasonable period of time, Contractor may request an extension in Contract Time,directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. D. Contractor may be reimbursed for the cost of moving his equipment off the job and returning the necessary equipment to the job when it is determined by the City that construction may be resumed. Such reimbursement shall be based on actual cost to the Contractor of moving the equipment and no profit will be allowed. Reimbursement may not be allowed if the equipment is moved to another construction project for the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De=nber21,2012 007200-1 General Conditions Page 58 of 63 15.02 City May Terminate for Cause A. The occurrence of any one or more of the following events by way of example, but not of limitation, may justify termination for cause: 1. Contractor's persistent failure to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment, failure to adhere to the Project Schedule established under Paragraph 2.07 as adjusted from time to time pursuant to Paragraph 6.04, or failure to adhere to the City's Business Diversity Enterprise Ordinance #20020-12-2011 established under Paragraph 6.06.D); 2. Contractor's disregard of Laws or Regulations of any public body having jurisdiction; 3. Contractor's repeated disregard of the authority of City; or 4. Contractor's violation in any substantial way of any provisions of the Contract Documents; or 5. Contractor's failure to promptly make good any defect in materials or workmanship, or defects of any nature,the correction of which has been directed in writing by the City; or 6. Substantial indication that the Contractor has made an unauthorized assignment of the Contract or any funds due therefrom for the benefit of any creditor or for any other purpose; or 7. Substantial evidence that the Contractor has become insolvent or bankrupt, or otherwise financially unable to carry on the Work satisfactorily;or 8. Contractor commences legal action in a court of competent jurisdiction against the City. B. If one or more of the events identified in Paragraph 15.02A, occur, City will provide written notice to Contractor and Surety to arrange a conference with Contractor and Surety to address Contractor's failure to perform the Work. Conference shall be held not later than 15 days, after receipt of notice. 1. If the City, the Contractor, and the Surety do not agree to allow the Contractor to proceed to perform the construction Contract, the City may, to the extent permitted by Laws and Regulations, declare a Contractor default and formally terminate the Contractor's right to complete the Contract. Contractor default shall not be declared earlier than 20 days after the Contractor and Surety have received notice of conference to address Contractor's failure to perform the Work. 2. If Contractor's services are terminated, Surety shall be obligated to take over and perform the Work. If Surety does not commence performance thereof within 15 consecutive calendar days after date of an additional written notice demanding Surety's performance of its CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber2l,2012 007200-1 General Conditions Page 59 of 63 obligations, then City, without process or action at law, may take over any portion of the Work and complete it as described below. a. If City completes the Work, City may exclude Contractor and Surety from the site and take possession of the Work, and all materials and equipment incorporated into the Work stored at the Site or for which City has paid Contractor or Surety but which are stored elsewhere, and finish the Work as City may deem expedient. 3. Whether City or Surety completes the Work, Contractor shall not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the Contract Price exceeds all claims, costs, losses and damages sustained by City arising out of or resulting from completing the Work, such excess will be paid to Contractor. If such claims, costs, losses and damages exceed such unpaid balance, Contractor shall pay the difference to City. Such claims, costs, losses and damages incurred by City will be incorporated in a Change Order, provided that when exercising any rights or remedies under this Paragraph, City shall not be required to obtain the lowest price for the Work performed. 4. Neither City, nor any of its respective consultants, agents, officers, directors or employees shall be in any way liable or accountable to Contractor or Surety for the method by which the completion of the said Work, or any portion thereof, may be accomplished or for the price paid therefor. F 5. City, notwithstanding the method used in completing the Contract, shall not forfeit the right to recover damages from Contractor or Surety for Contractor's failure to timely complete the entire Contract. Contractor shall not be entitled to any claim on account of the method used by City in completing the Contract. 6. Maintenance of the Work shall continue to be Contractor's and Surety's responsibilities as provided for in the bond requirements of the Contract Documents or any special guarantees provided for under the Contract Documents or any other obligations otherwise prescribed by law. C. Notwithstanding Paragraphs 15.02.11, Contractor's services will not be terminated if Contractor begins within seven days of receipt of notice of intent to terminate to correct its failure to perform and proceeds diligently to cure such failure within no more than 30 days of receipt of said notice. D. Where Contractor's services have been so terminated by City, the termination will not affect any rights or remedies of City against Contractor then existing or which may thereafter accrue. Any retention or payment of moneys due Contractor by City will not release Contractor from liability. E. If and to the extent that Contractor has provided a performance bond under the provisions of Paragraph 5.02,the termination procedures of that bond shall not supersede the provisions of this Article. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwember2l,2012 007200-1 General Conditions Page 60 of 63 15.03 City May Terminate For Convenience A. City may, without cause and without prejudice to any other right or remedy of City,terminate the Contract. Any termination shall be effected by mailing a notice of the termination to the Contractor specifying the extent to which performance of Work under the contract is terminated, and the date upon which such termination becomes effective. Receipt of the notice shall be deemed conclusively presumed and established when the letter is placed in the United States Postal Service Mail by the City. Further, it shall be deemed conclusively presumed and established that such termination is made with just cause as therein stated; and no proof in any claim,demand or suit shall be required of the City regarding such discretionary action. B. After receipt of a notice of termination, and except as otherwise directed by the City, the Contractor shall: 1. Stop work under the Contract on the date and to the extent specified in the notice of termination; 2. place no further orders or subcontracts for materials, services or facilities except as may be necessary for completion of such portion of the Work under the Contract as is not terminated; 3. terminate all orders and subcontracts to the extent that they relate to the performance of the Work terminated by notice of termination; 4. transfer title to the City and deliver in the manner, at the times, and to the extent, if any, directed by the City: a. the fabricated or unfabricated parts, Work in progress, completed Work, supplies and other material produced as a part of, or acquired in connection with the performance of, the Work terminated by the notice of the termination; and b. the completed, or partially completed plans, drawings, information and other property which, if the Contract had been completed, would have been required to be furnished to the City. 5. complete performance of such Work as shall not have been terminated by the notice of termination; and 6. take such action as may be necessary, or as the City may direct, for the protection and preservation of the property related to its contract which is in the possession of the Contractor and in which the owner has or may acquire the rest. C. At a time not later than 30 days after the termination date specified in the notice of termination, the Contractor may submit to the City a list, certified as to quantity and quality, of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Demnber2l,2012 007200-1 General Conditions Page 61 of 63 D. Not later than 15 days thereafter, the City shall accept title to such items provided, that the list submitted shall be subject to verification by the City upon removal of the items or, if the items are stored, within 45 days from the date of submission of the list, and any necessary adjustments to correct the list as submitted, shall be made prior to final settlement. E. Not later than 60 days after the notice of termination, the Contractor shall submit his termination claim to the City in the form and with the certification prescribed by the City. Unless an extension is made in writing within such 60 day period by the Contractor, and granted by the City,any and all such claims shall be conclusively deemed waived. F. In such case, Contractor shall be paid for(without duplication of any items): 1. completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work; 2. expenses sustained prior to the effective date of termination in performing services and furnishing labor, materials, or equipment as required by the Contract Documents in connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses; and 3. reasonable expenses directly attributable to termination. G. In the event of the failure of the Contractor and City to agree upon the whole amount to be paid to the Contractor by reason of the termination of the Work, the City shall determine, on the basis of information available to it, the amount, if any, due to the Contractor by reason of the termination and shall pay to the Contractor the amounts determined. Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss arising out of or resulting from such termination. ARTICLE 16—DISPUTE RESOLUTION 16.01 Methods and Procedures A. Either City or Contractor may request mediation of any Contract Claim submitted for a decision under Paragraph 10.06 before such decision becomes final and binding. The request for mediation shall be submitted to the other party to the Contract. Timely submission of the request shall stay the effect of Paragraph 10.06.E. B. City and Contractor shall participate in the mediation process in good faith. The process shall be F commenced within 60 days of filing of the request. F C. If the Contract Claim is not resolved by mediation, City's action under Paragraph 10.06.0 or a denial pursuant to Paragraphs 10,06.C.3 or 10.06.D shall become final and binding 30 days after F termination of the mediation unless,within that time period,City or Contractor: CRY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanlw2l,2012 007200-1 General Conditions Page 62 of 63 I. elects in writing to invoke any other dispute resolution process provided for in the Supplementary Conditions; or 2. agrees with the other party to submit the Contract Claim to another dispute resolution process; or 3. gives written notice to the other party of the intent to submit the Contract Claim to a court of competent jurisdiction. ARTICLE 17—MISCELLANEOUS 17.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if. 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended;or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 17.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 17.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwernber21,2012 007200-1 General Conditions Page 63 of 63 17.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 17.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanter 21,2012 007300-1 SUPPLEMENTARY CONDITIONS Pagel of 5 1 SECTION 00 73 00 2 SUPPLEMENTARY CONDITIONS 3 TO 4 GENERAL CONDITIONS 5 6 Supplementary Conditions 7 8 These Supplementary Conditions modify and supplement Section 00 72 00-General Conditions,and other 9 provisions of the Contract Documents as indicated below. All provisions of the General Conditions that are 10 modified or supplemented remain in full force and effect as so modified or supplemented. All provisions 11 of the General Conditions which are not so modified or supplemented remain in full force and effect. 12 13 Defined Terms 14 15 The terms used in these Supplementary Conditions which are defined in the General Conditions have the 16 meaning assigned to them in the General Conditions,unless specifically noted herein. 17 18 Modifications and Supplements 19 20 The following are instructions that modify or supplement specific paragraphs in the General Conditions and 21 other Contract Documents. 22 23 SC-3.03B.2,"Resolving Discrepancies" 24 25 Plans govern over Specifications. 26 27 SC-4.01A 28 29 Easement limits shown on the Drawing are approximate and were provided to establish a basis for bidding. 30 Upon receiving the final easements descriptions,Contractor shall compare them to the lines shown on the 31 Contract Drawings. 32 33 SC-4.01A.1.,"Availability of Lands" 34 35 The following is a list of known outstanding right-of-way,and/or easements to be acquired,if any as of 36 37 38 Outstanding Right-Of-Way,and/or Easements to Be Acquired PARCEL OWNER TARGET DATE NUMBER OF POSSESSION None 39 The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed, 40 and do not bind the City. 41 42 If Contractor considers the final easements provided to differ materially from the representations on the 43 Contract Drawings, Contractor shall within five (5) Business Days and before proceeding with the Work, 44 notify City in writing associated with the differing easement line locations. 45 46 SC-4.01A.2,"Availability of Lands" 47 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 1,20I3 007300-1 SUPPLEMENTARY CONDITIONS Page 1 of 5 1 SECTION 00 73 00 2 SUPPLEMENTARY CONDITIONS 3 TO 4 GENERAL CONDITIONS 5 6 Supplementary Conditions 7 8 These Supplementary Conditions modify and supplement Section 00 72 00-General Conditions,and other 9 provisions of the Contract Documents as indicated below. All provisions of the General Conditions that are 10 modified or supplemented remain in full force and effect as so modified or supplemented. All provisions 11 of the General Conditions which are not so modified or supplemented remain in full force and effect. 12 13 Defined Terms 14 15 The terms used in these Supplementary Conditions which are defined in the General Conditions have the 16 meaning assigned to them in the General Conditions,unless specifically noted herein. 17 18 Modifications and Supplements 19 20 The following are instructions that modify or supplement specific paragraphs in the General Conditions and 21 other Contract Documents. 22 23 SC-3.03B.2,"Resolving Discrepancies" 24 25 Plans govern over Specifications. 26 27 SC-4.01A 28 29 Easement limits shown on the Drawing are approximate and were provided to establish a basis for bidding. 30 Upon receiving the final easements descriptions,Contractor shall compare them to the lines shown on the 31 Contract Drawings. 32 33 SC-4.01A.1.,"Availability of Lands" 34 35 The following is a list of known outstanding right-of-way,and/or easements to be acquired,if any as of 36 37 38 Outstanding Right-Of-Way,and/or Easements to Be Acquired PARCEL OWNER TARGET DATE NUMBER OF POSSESSION None 39 The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed, 40 and do not bind the City. 41 42 If Contractor considers the final easements provided to differ materially from the representations on the 43 Contract Drawings, Contractor shall within five (5) Business Days and before proceeding with the Work, 44 notify City in writing associated with the differing easement line locations. 45 46 SC-4.01A.2,"Availability of Lands" 47 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 1,2013 007300-2 SUPPLEMENTARY CONDITIONS Page 2 of 5 1 Utilities or obstructions to be removed,adjusted,and/or relocated 2 3 The following is list of utilities and/or obstructions that have not been removed,adjusted,and/or relocated 4 as of 5 EXPECTED UTILITY AND LOCATION TARGET DATE OF OWNER ADJUSTMENT None 6 The Contractor understands and agrees that the dates listed above are estimates only,are not guaranteed, 7 and do not bind the City. 8 9 SC-4.02A.,"Subsurface and Physical Conditions" 10 11 The following are reports of explorations and tests of subsurface conditions at the site of the Work: 12 13 A Geotechnical Report No. 22801 ,dated May 22,2014 ,prepared by LML Engineering a sub- 14 consultant of BHB Engineering,a consultant of the City,providing geotechnical study. 15 16 The following are drawings of physical conditions in or relating to existing surface and subsurface 17 structures(except Underground Facilities)which are at or contiguous to the site of the Work: 18 None 19 20 SC-4.06A.,"Hazardous Environmental Conditions at Site" 21 22 The following are reports and drawings of existing hazardous environmental conditions known to the City: 23 None 24 25 SC-5.03A.,"Certificates of Insurance" 26 27 The entities listed below are"additional insureds as their interest may appear" including their respective 28 officers,directors,agents and employees. 29 30 (1) City 31 (2) Consultant: Baird,Hampton&Brown,Inc. 32 (3) Other: None 33 34 SC-5.04A.,"Contractor's Insurance" 35 36 The limits of liability for the insurance required by Paragraph GC-5.04 shall provide the following 37 coverages for not less than the following amounts or greater where required by laws and regulations: 38 39 5.04A.Workers'Compensation,under Paragraph GC-5.04A. 40 41 Statutory limits 42 Employer's liability 43 $100,000 each accident/occurrence 44 $100,000 Disease-each employee 45 $500,000 Disease-policy limit 46 47 SC-5.04B.,"Contractor's Insurance" 48 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 1,2013 007300-3 SUPPLEMENTARY CONDITIONS Page 3 of 5 1 5.04B.Commercial General Liability,under Paragraph GC-5.0413. Contractor's Liability Insurance 2 under Paragraph GC-5.04B.,which shall be on a per project basis covering the Contractor with 3 minimum limits of- 4 5 $1,000,000 each occurrence 6 $2,000,000 aggregate limit 7 8 The policy must have an endorsement(Amendment—Aggregate Limits of Insurance)making the 9 General Aggregate Limits apply separately to each job site. 10 11 The Commercial General Liability Insurance policies shall provide"X","C",and"U"coverage's. 12 Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. 13 14 SC 5.04C.,"Contractor's Insurance" 15 5.04C. Automobile Liability,under Paragraph GC-5.04C. Contractor's Liability Insurance under 16 Paragraph GC-5.04C.,which shall be in an amount not less than the following amounts: 17 18 (1) Automobile Liability-a commercial business policy shall provide coverage on"Any Auto", 19 defined as autos owned,hired and non-owned. 20 21 $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at 22 least: 23 24 $250,000 Bodily Injury per person/ 25 $500,000 Bodily Injury per accident/ 26 $100,000 Property Damage 27 28 SC-5.04D.,"Contractor's Insurance" 29 30 The Contractor's construction activities will require its employees,agents,subcontractors,equipment,and 31 material deliveries to cross railroad properties and tracks: 32 None 33 34 The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, 35 hinder,or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains 36 or other property. Such operations on railroad properties may require that Contractor to execute a"Right of 37 Entry Agreement"with the particular railroad company or companies involved,and to this end the 38 Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute 39 the right-of-entry(if any)required by a railroad company.The requirements specified herein likewise relate 40 to the Contractor's use of private and/or construction access roads crossing said railroad company's 41 properties. 42 43 The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide 44 coverage for not less than the following amounts,issued by companies satisfactory to the City and to the 45 Railroad Company for a term that continues for so long as the Contractor's operations and work cross, 46 occupy,or touch railroad property: 47 48 (1) General Aggregate: $Confirm Limits with Railroad 49 50 (2) Each Occurrence: $Confirm Limits with Railroad 51 52 _Required for this Contract Not required for this Contract 53 <Provide an X"next to the appropriate selection above based on the Contract requirements> 54 55 With respect to the above outlined insurance requirements,the following shall govern: CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 1,2013 007300-4 SUPPLEMENTARY CONDITIONS Page 4 of 5 1 2 1. Where a single railroad company is involved, the Contractor shall provide one insurance policy in 3 the name of the railroad company. However, if more than one grade separation or at-grade 4 crossing is affected by the Project at entirely separate locations on the line or lines of the same 5 railroad company,separate coverage may be required,each in the amount stated above. 6 7 2. Where more than one railroad company is operating on the same right-of-way or where several 8 railroad companies are involved and operated on their own separate rights-of-way, the Contractor 9 may be required to provide separate insurance policies in the name of each railroad company. 10 11 3. If, in addition to a grade separation or an at-grade crossing, other work or activity is proposed on a 12 railroad company's right-of-way at a location entirely separate from the grade separation or at- 13 grade crossing, insurance coverage for this work must be included in the policy covering the grade 14 separation. 15 16 4. If no grade separation is involved but other work is proposed on a railroad company's right-of- 17 way,all such other work may be covered in a single policy for that railroad, even though the work 18 may be at two or more separate locations. 19 20 No work or activities on a railroad company's property to be performed by the Contractor shall be 21 commenced until the Contractor has furnished the City with an original policy or policies of the insurance 22 for each railroad company named,as required above. All such insurance must be approved by the City and 23 each affected Railroad Company prior to the Contractor's beginning work. 24 25 The insurance specified above must be carried until all Work to be performed on the railroad right-of-way 26 has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, 27 insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. 28 Such insurance must name the railroad company as the insured,together with any tenant or lessee of the 29 railroad company operating over tracks involved in the Project. 30 31 SC-6.04.,"Project Schedule" 32 33 Project schedule shall be tier 3 for the project. 34 35 SC-6.07.,"Wage Rates" 36 37 The following is the prevailing wage rate table applicable to this project and is provided in the Appendixes: 38 https://projectpoint.bu=saw.com/_bz_rest/Web/Home/Index?folder=37331#/_bz_rest/Web/Item/Details?id 39 =389755&itemtype=File 40 41 SC-6.09.,"Permits and Utilities" 42 43 SC-6.09A.,"Contractor obtained permits and licenses" 44 The following are known permits and/or licenses required by the Contract to be acquired by the Contractor: 45 1. NOI/NOT from TCEQ 46 2. City of Fort Worth Street Use Permit 47 48 SC-6.09B."City obtained permits and licenses" 49 The following are known permits and/or licenses required by the Contract to be acquired by the City: 50 1. ENVR documents 51 52 SC-6.09C."Outstanding permits and licenses" 53 54 The following is a list of known outstanding permits and/or licenses to be acquired,if any as of 55 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 1,2013 007300-5 SUPPLEMENTARY CONDITIONS Page 5 of 5 1 2 Outstanding Permits and/or Licenses to Be Acquired OWNER PERMIT OR LICENSE AND LOCATION TARGET DATE OF POSSESSION None 3 4 SC-7.02.,"Coordination" 5 6 The individuals or entities listed below have contracts with the City for the performance of other work at 7 the Site: 8 Vendor Scope of Work Coordination Authority None None None 9 10 11 SC-8.01,"Communications to Contractor" 12 13 N/A 14 15 SC-9.01.,"City's Project Representative" 16 17 The following firm is a consultant to the City responsible for construction management of this Project: 18 N/A 19 20 SC-13.03C.,"Tests and Inspections" 21 22 None 23 24 SC-16.01C.1,"Methods and Procedures" 25 26 None 27 28 29 30 END OF SECTION CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised April 1,2013 011100-1 SUMMARY OF WORK Page I of 3 1 SECTION 01 1100 2 SUMMARY OF WORK 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Summary of Work to be performed in accordance with the Contract Documents 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0 -Bidding Requirements, Contract Forms, and Conditions of the Contract 11 2. Division 1 -General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Work Covered by Contract Documents 19 1. Work is to include furnishing all labor,materials, and equipment, and performing 20 all Work necessary for this construction project as detailed in the Drawings and 21 Specifications. 22 B. Subsidiary Work 23 1. Any and all Work specifically governed by documentary requirements for the 24 project, such as conditions imposed by the Drawings or Contract Documents in 25 which no specific item for bid has been provided for in the Proposal and the item is 26 not a typical unit bid item included on the standard bid item list,then the item shall 27 be considered as a subsidiary item of Work,the cost of which shall be included in 28 the price bid in the Proposal for various bid items. 29 C. Use of Premises 30 1. Coordinate uses of premises under direction of the City. 31 2. Assume full responsibility for protection and safekeeping of materials and 32 equipment stored on the Site. 33 3. Use and occupy only portions of the public streets and alleys, or other public places 34 or other rights-of-way as provided for in the ordinances of the City, as shown in the 35 Contract Documents, or as may be specifically authorized in writing by the City. 36 a. A reasonable amount of tools, materials, and equipment for construction 37 purposes may be stored in such space, but no more than is necessary to avoid 38 delay in the construction operations. CITY OF FORT WORTH Dry Branch Creek Interinm Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 011100-2 SUMMARY OF WORK Pare 2 of 3 1 b. Excavated and waste materials shall be stored in such a way as not to interfere 2 with the use of spaces that may be designated to be left free and unobstructed 3 and so as not to inconvenience occupants of adjacent property. 4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such 5 manner as not to interfere with the operation of the railroad. 6 1) All Work shall be in accordance with railroad requirements set forth in 7 Division 0 as well as the railroad permit. 8 D. Work within Easements 9 1. Do not enter upon private property for any purpose without having previously 10 obtained permission from the owner of such property. 11 2. Do not store equipment or material on private property unless and until the 12 specified approval of the property owner has been secured in writing by the 13 Contractor and a copy furnished to the City. 14 3. Unless specifically provided otherwise, clear all rights-of-way or easements of 15 obstructions which must be removed to make possible proper prosecution of the 16 Work as a part of the project construction operations. 17 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery,plants, 18 lawns, fences,culverts,curbing, and all other types of structures or improvements, 19 to all water, sewer,and gas lines,to all conduits,overhead pole lines, or 20 appurtenances thereof, including the construction of temporary fences and to all 21 other public or private property adjacent to the Work. 22 5. Notify the proper representatives of the owners or occupants of the public or private 23 lands of interest in lands which might be affected by the Work. 24 a. Such notice shall be made at least 48 hours in advance of the beginning of the 25 Work. 26 b. Notices shall be applicable to both public and private utility companies and any 27 corporation,company, individual, or other, either as owners or occupants, 28 whose land or interest in land might be affected by the Work. 29 c. Be responsible for all damage or injury to property of any character resulting 30 from any act, omission, neglect, or misconduct in the manner or method or 31 execution of the Work, or at any time due to defective work, material,or 32 equipment. 33 6. Fence 34 a. Restore all fences encountered and removed during construction of the Project 35 to the original or a better than original condition. 36 b. Erect temporary fencing in place of the fencing removed whenever the Work is 37 not in progress and when the site is vacated overnight, and/or at all times to 38 provide site security. 39 c. The cost for all fence work within easements, including removal,temporary 40 closures and replacement, shall be subsidiary to the various items bid in the 41 project proposal,unless a bid item is specifically provided in the proposal. CITY OF FORT WORTH Dry Branch Creek Interinm Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 011100-3 SUMMARY OF WORK Page 3 of 3 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION [NOT USED] 11 END OF SECTION 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 CITY OF FORT WORTH Dry Branch Creek Interinm Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 012500-1 SUBSTITUTION PROCEDURES Pagel of 4 1 SECTION 0125 00 2 SUBSTITUTION PROCEDURES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedure for requesting the approval of substitution of a product that is not 7 equivalent to a product which is specified by descriptive or performance criteria or 8 defined by reference to 1 or more of the following: 9 a. Name of manufacturer 10 b. Name of vendor 11 c. Trade name 12 d. Catalog number 13 2. Substitutions are not"or-equals". 14 B. Deviations from this City of Fort Worth Standard Specification 15 1. None. 16 C. Related Specification Sections include,but are not necessarily limited to: 17 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 18 2. Division 1 —General Requirements 19 1.2 PRICE AND PAYMENT PROCEDURES 20 A. Measurement and Payment 21 1. Work associated with this Item is considered subsidiary to the various items bid. 22 No separate payment will be allowed for this Item. 23 1.3 REFERENCES [NOT USED] 24 1.4 ADMINISTRATIVE REQUIREMENTS 25 A. Request for Substitution-General 26 1. Within 30 days after award of Contract(unless noted otherwise),the City will 27 consider formal requests from Contractor for substitution of products in place of 28 those specified. 29 2. Certain types of equipment and kinds of material are described in Specifications by 30 means of references to names of manufacturers and vendors,trade names,or 31 catalog numbers. 32 a. When this method of specifying is used, it is not intended to exclude from 33 consideration other products bearing other manufacturer's or vendor's names, 34 trade names, or catalog numbers,provided said products are"or-equals," as 35 determined by City. 36 3. Other types of equipment and kinds of material may be acceptable substitutions 37 under the following conditions: 38 a. Or-equals are unavailable due to strike, discontinued production of products 39 meeting specified requirements,or other factors beyond control of Contractor; 40 or, CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 2500-2 SUBSTITUTION PROCEDURES Page 2 of 4 1 b. Contractor proposes a cost and/or time reduction incentive to the City. 2 1.5 SUBMITTALS 3 A. See Request for Substitution Form(attached) 4 B. Procedure for Requesting Substitution 5 1. Substitution shall be considered only: 6 a. After award of Contract 7 b. Under the conditions stated herein 8 2. Submit 3 copies of each written request for substitution, including: 9 a. Documentation 10 1) Complete data substantiating compliance of proposed substitution with 11 Contract Documents 12 2) Data relating to changes in construction schedule,when a reduction is 13 proposed 14 3) Data relating to changes in cost 15 b. For products 16 1) Product identification 17 a) Manufacturer's name 18 b) Telephone number and representative contact name 19 c) Specification Section or Drawing reference of originally specified 20 product, including discrete name or tag number assigned to original 21 product in the Contract Documents 22 2) Manufacturer's literature clearly marked to show compliance of proposed 23 product with Contract Documents 24 3) Itemized comparison of original and proposed product addressing product 25 characteristics including,but not necessarily limited to: 26 a) Size 27 b) Composition or materials of construction 28 c) Weight 29 d) Electrical or mechanical requirements 30 4) Product experience 31 a) Location of past projects utilizing product 32 b) Name and telephone number of persons associated with referenced 33 projects knowledgeable concerning proposed product 34 c) Available field data and reports associated with proposed product 35 5) Samples 36 a) Provide at request of City. 37 b) Samples become the property of the City. 38 c. For construction methods: 39 1) Detailed description of proposed method 40 2) Illustration drawings 41 C. Approval or Rejection 42 1. Written approval or rejection of substitution given by the City 43 2. City reserves the right to require proposed product to comply with color and pattern 44 of specified product if necessary to secure design intent. 45 3. In the event the substitution is approved,the resulting cost and/or time reduction 46 will be documented by Change Order in accordance with the General Conditions. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 012500-3 SUBSTITUTION PROCEDURES Page 3 of 4 1 4. No additional contract time will be given for substitution. 2 5. Substitution will be rejected if 3 a. Submittal is not through the Contractor with his stamp of approval 4 b. Request is not made in accordance with this Specification Section 5 c. In the City's opinion,acceptance will require substantial revision of the original 6 design 7 d. In the City's opinion, substitution will not perform adequately the function 8 consistent with the design intent 9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 10 1.7 CLOSEOUT SUBMITTALS [NOT USED] 11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 12 1.9 QUALITY ASSURANCE 13 A. In making request for substitution or in using an approved product,the Contractor 14 represents that the Contractor: 15 1. Has investigated proposed product,and has determined that it is adequate or 16 superior in all respects to that specified,and that it will perform function for which 17 it is intended 18 2. Will provide same guarantee for substitute item as for product specified 19 3. Will coordinate installation of accepted substitution into Work,to include building 20 modifications if necessary,making such changes as may be required for Work to be 21 complete in all respects 22 4. Waives all claims for additional costs related to substitution which subsequently 23 arise 24 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 25 1.11 FIELD [SITE] CONDITIONS [NOT USED] 26 1.12 WARRANTY [NOT USED] 27 PART 2- PRODUCTS [NOT USED] 28 PART 3- EXECUTION [NOT USED] 29 END OF SECTION 30 Revision Log DATE NAME SUMMARY OF CHANGE 31 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 012500-4 SUBSTITUTION PROCEDURES Page 4 of 4 1 EXHIBIT A 2 REQUEST FOR SUBSTITUTION FORM: 3 4 TO: 5 PROJECT: DATE: 6 We hereby submit for your consideration the following product instead of the specified item for 7 the above project: 8 SECTION PARAGRAPH SPECIFIED ITEM 9 10 11 Proposed Substitution: 12 Reason for Substitution: 13 Include complete information on changes to Drawings and/or Specifications which proposed 14 substitution will require for its proper installation. 15 16 Fill in Blanks Below: 17 A. Will the undersigned contractor pay for changes to the building design, including engineering 18 and detailing costs caused by the requested substitution? 19 20 21 B. What effect does substitution have on other trades? 22 23 24 C. Differences between proposed substitution and specified item? 25 26 27 D. Differences in product cost or product delivery time? 28 29 30 E. Manufacturer's guarantees of the proposed and specified items are: 31 32 Equal Better(explain on attachment) 33 The undersigned states that the function, appearance and quality are equivalent or superior to the 34 specified item. 35 Submitted By: For Use by City 36 37 Signature _Recommended _Recommended 38 as noted 39 40 Firm _Not recommended _Received late 41 Address By 42 Date 43 Date Remarks 44 Telephone 45 46 For Use by City: 47 48 Approved Rejected 49 City Date CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 013119-I PRECONSTRUCTION MEETING Page 1 of 3 1 SECTION 01 31 19 2 PRECONSTRUCTION MEETING 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to 7 clarify construction contract administration procedures 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include,but are not necessarily limited to: 11 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 12 2. Division 1 —General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered subsidiary to the various items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS 19 A. Coordination 20 1. Attend preconstruction meeting. 21 2. Representatives of Contractor, subcontractors and suppliers attending meetings 22 shall be qualified and authorized to act on behalf of the entity each represents. 23 3. Meeting administered by City may be tape recorded. 24 a. If recorded,tapes will be used to prepare minutes and retained by City for 25 future reference. 26 B. Preconstruction Meeting 27 1. A preconstruction meeting will be held within 14 days after the execution of the 28 Agreement and before Work is started. 29 a. The meeting will be scheduled and administered by the City. 30 2. The Project Representative will preside at the meeting,prepare the notes of the 31 meeting and distribute copies of same to all participants who so request by fully 32 completing the attendance form to be circulated at the beginning of the meeting. 33 3. Attendance shall include: 34 a. Project Representative 35 b. Contractor's project manager 36 c. Contractor's superintendent 37 d. Any subcontractor or supplier representatives whom the Contractor may desire 38 to invite or the City may request CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised August 17,2012 01 31 19-2 PRECONSTRUCTION MEETING Page 2 of 3 1 e. Other City representatives 2 f. Others as appropriate 3 4. Construction Schedule 4 a. Prepare baseline construction schedule in accordance with Section 01 32 16 and 5 provide at Preconstruction Meeting. 6 b. City will notify Contractor of any schedule changes upon Notice of 7 Preconstruction Meeting. 8 5. Preliminary Agenda may include: 9 a. Introduction of Project Personnel 10 b. General Description of Project 11 c. Status of right-of-way,utility clearances, easements or other pertinent permits 12 d. Contractor's work plan and schedule 13 e. Contract Time 14 f. Notice to Proceed 15 g. Construction Staking 16 h. Progress Payments 17 i. Extra Work and Change Order Procedures 18 j. Field Orders 19 k. Disposal Site Letter for Waste Material 20 1. Insurance Renewals 21 m. Payroll Certification 22 n. Material Certifications and Quality Control Testing 23 o. Public Safety and Convenience 24 p. Documentation of Pre-Construction Conditions 25 q. Weekend Work Notification 26 r. Legal Holidays 27 s. Trench Safety Plans 28 t. Confined Space Entry Standards 29 u. Coordination with the City's representative for operations of existing water 30 systems 31 v. Storm Water Pollution Prevention Plan 32 w. Coordination with other Contractors 33 x. Early Warning System 34 y. Contractor Evaluation 35 z. Special Conditions applicable to the project 36 aa. Damages Claims 37 bb. Submittal Procedures 38 cc. Substitution Procedures 39 dd. Correspondence Routing 40 ee. Record Drawings 41 ff. Temporary construction facilities 42 gg. M/WBE or MBE/SBE procedures 43 hh. Final Acceptance 44 ii. Final Payment 45 J. Questions or Comments CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised August 17,2012 01 31 19-3 PRECONSTRUCTION MEETING Page 3 of 3 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3 - EXECUTION [NOT USED] 11 END OF SECTION 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised August 17,2012 013120-1 PROJECT MEETINGS Pagel of 3 1 SECTION 01 31 20 2 PROJECT MEETINGS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provisions for project meetings throughout the construction period to enable orderly 7 review of the progress of the Work and to provide for systematic discussion of 8 potential problems 9 B. Deviations this City of Fort Worth Standard Specification 10 1. None. 11 C. Related Specification Sections include,but are not necessarily limited to: 12 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 13 2. Division 1 —General Requirements 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Work associated with this Item is considered subsidiary to the various items bid. 17 No separate payment will be allowed for this Item. 18 1.3 REFERENCES [NOT USED] 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Coordination 21 1. Schedule, attend and administer as specified,periodic progress meetings, and 22 specially called meetings throughout progress of the Work. 23 2. Representatives of Contractor, subcontractors and suppliers attending meetings 24 shall be qualified and authorized to act on behalf of the entity each represents. 25 3. Meetings administered by City may be tape recorded. 26 a. If recorded,tapes will be used to prepare minutes and retained by City for 27 future reference. 28 4. Meetings, in addition to those specified in this Section,may be held when requested 29 by the City, Engineer or Contractor. 30 B. Pre-Construction Neighborhood Meeting 31 1. After the execution of the Agreement,but before construction is allowed to begin, 32 attend 1 Public Meeting with affected residents to: 33 a. Present projected schedule,including construction start date 34 b. Answer any construction related questions 35 2. Meeting Location 36 a. Location of meeting to be determined by the City. 37 3. Attendees 38 a. Contractor CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 01 31 20-2 PROJECT MEETINGS Page 2 of 3 1 b. Project Representative 2 c. Other City representatives 3 4. Meeting Schedule 4 a. In general,the neighborhood meeting will occur within the 2 weeks following 5 the pre-construction conference. 6 b. In no case will construction be allowed to begin until this meeting is held. 7 C. Progress Meetings 8 1. Formal project coordination meetings will be held periodically. Meetings will be 9 scheduled and administered by Project Representative. 10 2. Additional progress meetings to discuss specific topics will be conducted on an as- 11 needed basis. Such additional meetings shall include,but not be limited to: 12 a. Coordinating shutdowns 13 b. Installation of piping and equipment 14 c. Coordination between other construction projects 15 d. Resolution of construction issues 16 e. Equipment approval 17 3. The Project Representative will preside at progress meetings, prepare the notes of 18 the meeting and distribute copies of the same to all participants who so request by 19 fully completing the attendance form to be circulated at the beginning of each 20 meeting. 21 4. Attendance shall include: 22 a. Contractor's project manager 23 b. Contractor's superintendent 24 c. Any subcontractor or supplier representatives whom the Contractor may desire 25 to invite or the City may request 26 d. Engineer's representatives 27 e. City's representatives 28 f. Others, as requested by the Project Representative 29 5. Preliminary Agenda may include: 30 a. Review of Work progress since previous meeting 31 b. Field observations,problems, conflicts 32 c. Items which impede construction schedule 33 d. Review of off-site fabrication,delivery schedules 34 e. Review of construction interfacing and sequencing requirements with other 35 construction contracts 36 f. Corrective measures and procedures to regain projected schedule 37 g. Revisions to construction schedule 38 h. Progress, schedule,during succeeding Work period 39 i. Coordination of schedules 40 j. Review submittal schedules 41 k. Maintenance of quality standards 42 1. Pending changes and substitutions 43 m. Review proposed changes for: 44 1) Effect on construction schedule and on completion date 45 2) Effect on other contracts of the Project 46 n. Review Record Documents 47 o. Review monthly pay request 48 p. Review status of Requests for Information CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 01 3120-3 PROJECT MEETINGS Page 3 of 3 1 6. Meeting Schedule 2 a. Progress meetings will be held periodically as determined by the Project 3 Representative. 4 1) Additional meetings may be held at the request of the: 5 a) City 6 b) Engineer 7 c) Contractor 8 7. Meeting Location 9 a. The City will establish a meeting location. 10 1) To the extent practicable,meetings will be held at the Site. 11 1.5 SUBMITTALS [NOT USED] 12 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 13 1.7 CLOSEOUT SUBMITTALS [NOT USED] 14 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 15 1.9 QUALITY ASSURANCE [NOT USED] 16 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 17 1.11 FIELD [SITE] CONDITIONS [NOT USED] 18 1.12 WARRANTY [NOT USED] 19 PART 2- PRODUCTS [NOT USED] 20 PART 3- EXECUTION [NOT USED] 21 END OF SECTION 22 Revision Log DATE NAME SUMMARY OF CHANGE 23 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 32 16-1 CONSTRUCTION PROGRESS SCHEDULE Page I of 5 1 SECTION 0132 16 2 CONSTRUCTION PROGRESS SCHEDULE 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. General requirements for the preparation, submittal,updating, status reporting and 7 management of the Construction Progress Schedule 8 2. Specific requirements are presented in the City of Fort Worth Schedule Guidance 9 Document 10 B. Deviations from this City of Fort Worth Standard Specification 11 1. None. 12 C. Related Specification Sections include, but are not necessarily limited to: 13 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 14 2. Division 1 —General Requirements 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Work associated with this Item is considered subsidiary to the various items bid. 18 No separate payment will be allowed for this Item. 19 1.3 REFERENCES 20 A. Definitions 21 1. Schedule Tiers 22 a. Tier 1 -No schedule submittal required by contract. Small, brief duration 23 proj ects 24 b. Tier 2 -No schedule submittal required by contract,but will require some 25 milestone dates. Small,brief duration projects 26 c. Tier 3 - Schedule submittal required by contract as described in the 27 Specification and herein. Majority of City projects, including all bond program 28 projects 29 d. Tier 4 - Schedule submittal required by contract as described in the 30 Specification and herein. Large and/or complex projects with long durations 31 1) Examples: large water pump station project and associated pipeline with 32 interconnection to another governmental entity 33 e. Tier 5 - Schedule submittal required by contract as described in the 34 Specification and herein. Large and/or very complex projects with long 35 durations, high public visibility 36 1) Examples might include a water or wastewater treatment plant 37 2. Baseline Schedule- Initial schedule submitted before work begins that will serve 38 as the baseline for measuring progress and departures from the schedule. 39 3. Progress Schedule-Monthly submittal of a progress schedule documenting 40 progress on the project and any changes anticipated. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 01 32 16-2 CONSTRUCTION PROGRESS SCHEDULE Page 2 of 5 1 4. Schedule Narrative-Concise narrative of the schedule including schedule 2 changes, expected delays,key schedule issues, critical path items, etc 3 B. Reference Standards 4 1. City of Fort Worth Schedule Guidance Document 5 1.4 ADMINISTRATIVE REQUIREMENTS 6 A. Baseline Schedule 7 1. General 8 a. Prepare a cost-loaded baseline Schedule using approved software and the 9 Critical Path Method(CPM)as required in the City of Fort Worth Schedule 10 Guidance Document. 1 I b. Review the draft cost-loaded baseline Schedule with the City to demonstrate 12 understanding of the work to be performed and known issues and constraints 13 related to the schedule. 14 c. Designate an authorized representative(Project Scheduler)responsible for 15 developing and updating the schedule and preparing reports. 16 B. Progress Schedule 17 1. Update the progress Schedule monthly as required in the City of Fort Worth 18 Schedule Guidance Document. 19 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 20 3. Change Orders 21 a. Incorporate approved change orders, resulting in a change of contract time, in 22 the baseline Schedule in accordance with City of Fort Worth Schedule 23 Guidance Document. 24 C. Responsibility for Schedule Compliance 25 1. Whenever it becomes apparent from the current progress Schedule and CPM Status 26 Report that delays to the critical path have resulted and the Contract completion 27 date will not be met, or when so directed by the City,make some or all of the 28 following actions at no additional cost to the City 29 a. Submit a Recovery Plan to the City for approval revised baseline Schedule 30 outlining: 31 1) A written statement of the steps intended to take to remove or arrest the 32 delay to the critical path in the approved schedule 33 2) Increase construction manpower in such quantities and crafts as will 34 substantially eliminate the backlog of work and return current Schedule to 35 meet projected baseline completion dates 36 3) Increase the number of working hours per shift, shifts per day,working 37 days per week,the amount of construction equipment,or any combination 38 of the foregoing, sufficiently to substantially eliminate the backlog of work 39 4) Reschedule activities to achieve maximum practical concurrency of 40 accomplishment of activities, and comply with the revised schedule 41 2. If no written statement of the steps intended to take is submitted when so requested 42 by the City,the City may direct the Contractor to increase the level of effort in 43 manpower(trades),equipment and work schedule(overtime,weekend and holiday 44 work, etc.)to be employed by the Contractor in order to remove or arrest the delay 45 to the critical path in the approved schedule. 46 a. No additional cost for such work will be considered. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 32 16-3 CONSTRUCTION PROGRESS SCHEDULE Page 3 of 5 1 D. The Contract completion time will be adjusted only for causes specified in this 2 Contract. 3 a. Requests for an extension of any Contract completion date must be 4 supplemented with the following: 5 1) Furnish justification and supporting evidence as the City may deem 6 necessary to determine whether the requested extension of time is entitled 7 under the provisions of this Contract. 8 a) The City will, after receipt of such justification and supporting 9 evidence,make findings of fact and will advise the Contractor, in 10 writing thereof. 11 2) If the City finds that the requested extension of time is entitled,the City's 12 determination as to the total number of days allowed for the extensions 13 shall be based upon the approved total baseline schedule and on all data 14 relevant to the extension. 15 a) Such data shall be included in the next updating of the Progress 16 schedule. 17 b) Actual delays in activities which, according to the Baseline schedule, 18 do not affect any Contract completion date shown by the critical path in 19 the network will not be the basis for a change therein. 20 2. Submit each request for change in Contract completion date to the City within 30 21 days after the beginning of the delay for which a time extension is requested but 22 before the date of final payment under this Contract. 23 a. No time extension will be granted for requests which are not submitted within 24 the foregoing time limit. 25 b. From time to time, it may be necessary for the Contract schedule or completion 26 time to be adjusted by the City to reflect the effects of job conditions,weather, 27 technical difficulties, strikes,unavoidable delays on the part of the City or its 28 representatives, and other unforeseeable conditions which may indicate 29 schedule adjustments or completion time extensions. 30 1) Under such conditions,the City will direct the Contractor to reschedule the 31 work or Contract completion time to reflect the changed conditions and the 32 Contractor shall revise his schedule accordingly. 33 a) No additional compensation will be made to the Contractor for such 34 schedule changes except for unavoidable overall contract time 35 extensions beyond the actual completion of unaffected work, in which 36 case the Contractor shall take all possible action to minimize any time 37 extension and any additional cost to the City. 38 b) Available float time in the Baseline schedule may be used by the City 39 as well as by the Contractor. 40 3. Float or slack time is defined as the amount of time between the earliest start date 41 and the latest start date or between the earliest finish date and the latest finish date 42 of a chain of activities on the Baseline Schedule. 43 a. Float or slack time is not for the exclusive use or benefit of either the 44 Contractor or the City. 45 b. Proceed with work according to early start dates, and the City shall have the 46 right to reserve and apportion float time according to the needs of the project. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 32 16-4 CONSTRUCTION PROGRESS SCHEDULE Page 4 of 5 1 c. Acknowledge and agree that actual delays, affecting paths of activities 2 containing float time,will not have any effect upon contract completion times, 3 providing that the actual delay does not exceed the float time associated with 4 those activities. 5 E. Coordinating Schedule with Other Contract Schedules 6 1. Where work is to be performed under this Contract concurrently with or contingent 7 upon work performed on the same facilities or area under other contracts,the 8 Baseline Schedule shall be coordinated with the schedules of the other contracts. 9 a. Obtain the schedules of the other appropriate contracts from the City for the 10 preparation and updating of Baseline schedule and make the required changes 11 in his schedule when indicated by changes in corresponding schedules. 12 2. In case of interference between the operations of different contractors,the City will 13 determine the work priority of each contractor and the sequence of work necessary 14 to expedite the completion of the entire Project. 15 a. In such cases,the decision of the City shall be accepted as final. 16 b. The temporary delay of any work due to such circumstances shall not be 17 considered as justification for claims for additional compensation. 18 1.5 SUBMITTALS 19 A. Baseline Schedule 20 1. Submit Schedule in native file format and pdf format as required in the City of Fort 21 Worth Schedule Guidance Document. 22 a. Native file format includes: 23 1) Primavera(P6 or Primavera Contractor) 24 2. Submit draft baseline Schedule to City prior to the pre-construction meeting and 25 bring in hard copy to the meeting for review and discussion. 26 B. Progress Schedule 27 1. Submit progress Schedule in native file format and pdf format as required in the 28 City of Fort Worth Schedule Guidance Document. 29 2. Submit progress Schedule monthly no later than the last day of the month. 30 C. Schedule Narrative 31 1. Submit the schedule narrative in pdf format as required in the City of Fort Worth 32 Schedule Guidance Document. 33 2. Submit schedule narrative monthly no later than the last day of the month. 34 D. Submittal Process 35 1. The City administers and manages schedules through Buzzsaw. 36 2. Contractor shall submit documents as required in the City of Fort Worth Schedule 37 Guidance Document. 38 3. Once the project has been completed and Final Acceptance has been issued by the 39 City,no further progress schedules are required. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 32 16-5 CONSTRUCTION PROGRESS SCHEDULE Page 5 of 5 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE 5 A. The person preparing and revising the construction Progress Schedule shall be 6 experienced in the preparation of schedules of similar complexity. 7 B. Schedule and supporting documents addressed in this Specification shall be prepared, 8 updated and revised to accurately reflect the performance of the construction. 9 C. Contractor is responsible for the quality of all submittals in this section meeting the 10 standard of care for the construction industry for similar projects. 11 1.10 DELIVERY, STORAGE,AND HANDLING[NOT USED] 12 1.11 FIELD [SITE] CONDITIONS [NOT USED] 13 1.12 WARRANTY [NOT USED] 14 PART 2 - PRODUCTS [NOT USED] 15 PART 3 - EXECUTION [NOT USED] 16 END OF SECTION 17 Revision Log DATE NAME SUMMARY OF CHANGE 18 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 3233-1 PRECONSTRUCTION VIDEO Pagel of 2 1 SECTION 0132 33 2 PRECONSTRUCTION VIDEO 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Administrative and procedural requirements for: 7 a. Preconstruction Videos 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include,but are not necessarily limited to: 11 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 12 2. Division 1 —General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered subsidiary to the various items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS 19 A. Preconstruction Video 20 1. Produce a preconstruction video of the site/alignment, including all areas in the 21 vicinity of and to be affected by construction. 22 a. Provide digital copy of video upon request by the City. 23 2. Retain a copy of the preconstruction video until the end of the maintenance surety 24 period. 25 1.5 SUBMITTALS [NOT USED] 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE [NOT USED] 30 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 31 1.11 FIELD [SITE] CONDITIONS [NOT USED] 32 1.12 WARRANTY [NOT USED] 33 PART 2 - PRODUCTS [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 013233-2 PRECONSTRUCTION VIDEO Page 2 of 2 1 PART 3- EXECUTION [NOT USED] 2 END OF SECTION 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 013300-1 SUBMITTALS Page 1 of 8 1 SECTION 0133 00 2 SUBMITTALS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. General methods and requirements of submissions applicable to the following 7 Work-related submittals: 8 a. Shop Drawings 9 b. Product Data(including Standard Product List submittals) 10 c. Samples 11 d. Mock Ups 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include,but are not necessarily limited to: 15 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 16 2. Division 1 —General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Coordination 24 1. Notify the City in writing, at the time of submittal, of any deviations in the 25 submittals from the requirements of the Contract Documents. 26 2. Coordination of Submittal Times 27 a. Prepare,prioritize and transmit each submittal sufficiently in advance of 28 performing the related Work or other applicable activities,or within the time 29 specified in the individual Work Sections, of the Specifications. 30 b. Contractor is responsible such that the installation will not be delayed by 31 processing times including,but not limited to: 32 a) Disapproval and resubmittal(if required) 33 b) Coordination with other submittals 34 c) Testing 35 d) Purchasing 36 e) Fabrication 37 f) Delivery 38 g) Similar sequenced activities 39 c. No extension of time will be authorized because of the Contractor's failure to 40 transmit submittals sufficiently in advance of the Work. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013300-2 SUBMITTALS Page 2 of 8 1 d. Make submittals promptly in accordance with approved schedule, and in such 2 sequence as to cause no delay in the Work or in the work of any other 3 contractor. 4 B. Submittal Numbering 5 1. When submitting shop drawings or samples, utilize a 9-character submittal cross- 6 reference identification numbering system in the following manner: 7 a. Use the first 6 digits of the applicable Specification Section Number. 8 b. For the next 2 digits number use numbers 01-99 to sequentially number each 9 initial separate item or drawing submitted under each specific Section number. 10 c. Last use a letter, A-Z, indicating the resubmission of the same drawing(i.e. 11 A=2nd submission, B=3rd submission,C=4th submission, etc.). A typical 12 submittal number would be as follows: 13 14 03 30 00-08-B 15 16 1) 03 30 00 is the Specification Section for Concrete 17 2) 08 is the eighth initial submittal under this Specification Section 18 3) B is the third submission(second resubmission)of that particular shop 19 drawing 20 C. Contractor Certification 21 1. Review shop drawings,product data and samples, including those by 22 subcontractors,prior to submission to determine and verify the following: 23 a. Field measurements 24 b. Field construction criteria 25 c. Catalog numbers and similar data 26 d. Conformance with the Contract Documents 27 2. Provide each shop drawing, sample and product data submitted by the Contractor 28 with a Certification Statement affixed including: 29 a. The Contractor's Company name 30 b. Signature of submittal reviewer 31 c. Certification Statement 32 1) "By this submittal, I hereby represent that I have determined and verified 33 field measurements,field construction criteria,materials,dimensions, 34 catalog numbers and similar data and I have checked and coordinated each 35 item with other applicable approved shop drawings." 36 D. Submittal Format 37 1. Fold shop drawings larger than 8 `/2 inches x 11 inches to 8 `/2 inches x 11 inches. 38 2. Bind shop drawings and product data sheets together. 39 3. Order 40 a. Cover Sheet 41 1) Description of Packet 42 2) Contractor Certification 43 b. List of items/Table of Contents 44 c. Product Data/Shop Drawings/Samples/Calculations 45 E. Submittal Content 46 1. The date of submission and the dates of any previous submissions CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013300-3 SUBMITTALS Page 3 of 8 1 2. The Project title and number 2 3. Contractor identification 3 4. The names of- 4 a. Contractor 5 b. Supplier 6 c. Manufacturer 7 5. Identification of the product,with the Specification Section number,page and 8 paragraph(s) 9 6. Field dimensions, clearly identified as such 10 7. Relation to adjacent or critical features of the Work or materials 11 8. Applicable standards, such as ASTM or Federal Specification numbers 12 9. Identification by highlighting of deviations from Contract Documents 13 10. Identification by highlighting of revisions on resubmittals 14 11. An 8-inch x 3-inch blank space for Contractor and City stamps 15 F. Shop Drawings 16 1. As specified in individual Work Sections includes,but is not necessarily limited to: 17 a. Custom-prepared data such as fabrication and erection/installation(working) 18 drawings 19 b. Scheduled information 20 c. Setting diagrams 21 d. Actual shopwork manufacturing instructions 22 e. Custom templates 23 f. Special wiring diagrams 24 g. Coordination drawings 25 h. Individual system or equipment inspection and test reports including: 26 1) Performance curves and certifications 27 i. As applicable to the Work 28 2. Details 29 a. Relation of the various parts to the main members and lines of the structure 30 b. Where correct fabrication of the Work depends upon field measurements 31 1) Provide such measurements and note on the drawings prior to submitting 32 for approval. 33 G. Product Data 34 1. For submittals of product data for products included on the City's Standard Product 35 List,clearly identify each item selected for use on the Project. 36 2. For submittals of product data for products not included on the City's Standard 37 Product List, submittal data may include,but is not necessarily limited to: 38 a. Standard prepared data for manufactured products(sometimes referred to as 39 catalog data) 40 1) Such as the manufacturer's product specification and installation 41 instructions 42 2) Availability of colors and patterns 43 3) Manufacturer's printed statements of compliances and applicability 44 4) Roughing-in diagrams and templates 45 5) Catalog cuts 46 6) Product photographs CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013300-4 SUBMITTALS Page 4 of 8 1 7) Standard wiring diagrams 2 8) Printed performance curves and operational-range diagrams 3 9) Production or quality control inspection and test reports and certifications 4 10) Mill reports 5 11) Product operating and maintenance instructions and recommended 6 spare-parts listing and printed product warranties 7 12) As applicable to the Work 8 H. Samples 9 1. As specified in individual Sections, include,but are not necessarily limited to: 10 a. Physical examples of the Work such as: 11 1) Sections of manufactured or fabricated Work 12 2) Small cuts or containers of materials 13 3) Complete units of repetitively used products color/texture/pattern swatches 14 and range sets 15 4) Specimens for coordination of visual effect 16 5) Graphic symbols and units of Work to be used by the City for independent 17 inspection and testing, as applicable to the Work 18 I. Do not start Work requiring a shop drawing, sample or product data nor any material to 19 be fabricated or installed prior to the approval or qualified approval of such item. 20 1. Fabrication performed,materials purchased or on-site construction accomplished 21 which does not conform to approved shop drawings and data is at the Contractor's 22 risk. 23 2. The City will not be liable for any expense or delay due to corrections or remedies 24 required to accomplish conformity. 25 3. Complete project Work,materials,fabrication,and installations in conformance 26 with approved shop drawings, applicable samples,and product data. 27 J. Submittal Distribution 28 1. Electronic Distribution 29 a. Confirm development of Project directory for electronic submittals to be 30 uploaded to City's Buzzsaw site,or another external FTP site approved by the 31 City. 32 b. Shop Drawings 33 1) Upload submittal to designated project directory and notify appropriate 34 City representatives via email of submittal posting. 35 2) Hard Copies 36 a) 3 copies for all submittals 37 b) If Contractor requires more than 1 hard copy of Shop Drawings 38 returned,Contractor shall submit more than the number of copies listed 39 above. 40 c. Product Data 41 1) Upload submittal to designated project directory and notify appropriate 42 City representatives via email of submittal posting. 43 2) Hard Copies 44 a) 3 copies for all submittals 45 d. Samples 46 1) Distributed to the Project Representative 47 2. Hard Copy Distribution(if required in lieu of electronic distribution) CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013300-5 SUBMITTALS Page 5 of 8 1 a. Shop Drawings 2 1) Distributed to the City 3 2) Copies 4 a) 8 copies for mechanical submittals 5 b) 7 copies for all other submittals 6 c) If Contractor requires more than 3 copies of Shop Drawings returned, 7 Contractor shall submit more than the number of copies listed above. 8 b. Product Data 9 1) Distributed to the City 10 2) Copies 11 a) 4 copies 12 c. Samples 13 1) Distributed to the Project Representative 14 2) Copies 15 a) Submit the number stated in the respective Specification Sections. 16 3. Distribute reproductions of approved shop drawings and copies of approved 17 product data and samples,where required,to the job site file and elsewhere as 18 directed by the City. 19 a. Provide number of copies as directed by the City but not exceeding the number 20 previously specified. 21 K. Submittal Review 22 1. The review of shop drawings,data and samples will be for general conformance 23 with the design concept and Contract Documents. This is not to be construed as: 24 a. Permitting any departure from the Contract requirements 25 b. Relieving the Contractor of responsibility for any errors, including details, 26 dimensions, and materials 27 c. Approving departures from details furnished by the City, except as otherwise 28 provided herein 29 2. The review and approval of shop drawings, samples or product data by the City 30 does not relieve the Contractor from his/her responsibility with regard to the 31 fulfillment of the terms of the Contract. 32 a. All risks of error and omission are assumed by the Contractor,and the City will 33 have no responsibility therefore. 34 3. The Contractor remains responsible for details and accuracy, for coordinating the 35 Work with all other associated work and trades, for selecting fabrication processes, 36 for techniques of assembly and for performing Work in a safe manner. 37 4. If the shop drawings,data or samples as submitted describe variations and show a 38 departure from the Contract requirements which City finds to be in the interest of 39 the City and to be so minor as not to involve a change in Contract Price or time for 40 performance,the City may return the reviewed drawings without noting an 41 exception. 42 5. Submittals will be returned to the Contractor under 1 of the following codes: 43 a. Code 1 44 1) "NO EXCEPTIONS TAKEN' is assigned when there are no notations or 45 comments on the submittal. 46 a) When returned under this code the Contractor may release the 47 equipment and/or material for manufacture. 48 b. Code 2 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013300-6 SUBMITTALS Page 6 of 8 1 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of 2 the notations and comments IS NOT required by the Contractor. 3 a) The Contractor may release the equipment or material for manufacture; 4 however, all notations and comments must be incorporated into the 5 final product. 6 c. Code 3 7 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is 8 assigned when notations and comments are extensive enough to require a 9 resubmittal of the package. 10 a) The Contractor may release the equipment or material for manufacture; 11 however, all notations and comments must be incorporated into the 12 final product. 13 b) This resubmittal is to address all comments,omissions and 14 non-conforming items that were noted. 15 c) Resubmittal is to be received by the City within 15 Calendar Days of 16 the date of the City's transmittal requiring the resubmittal. 17 d. Code 4 18 1) "NOT APPROVED" is assigned when the submittal does not meet the 19 intent of the Contract Documents. 20 a) The Contractor must resubmit the entire package revised to bring the 21 submittal into conformance. 22 b) It may be necessary to resubmit using a different manufacturer/vendor 23 to meet the Contract Documents. 24 6. Resubmittals 25 a. Handled in the same manner as first submittals 26 1) Corrections other than requested by the City 27 2) Marked with revision triangle or other similar method 28 a) At Contractor's risk if not marked 29 b. Submittals for each item will be reviewed no more than twice at the City's 30 expense. 31 1) All subsequent reviews will be performed at times convenient to the City 32 and at the Contractor's expense,based on the City's or City 33 Representative's then prevailing rates. 34 2) Provide Contractor reimbursement to the City within 30 Calendar Days for 35 all such fees invoiced by the City. 36 c. The need for more than 1 resubmission or any other delay in obtaining City's 37 review of submittals,will not entitle the Contractor to an extension of Contract 38 Time. 39 7. Partial Submittals 40 a. City reserves the right to not review submittals deemed partial, at the City's 41 discretion. 42 b. Submittals deemed by the City to be not complete will be returned to the 43 Contractor, and will be considered "Not Approved" until resubmitted. 44 c. The City may at its option provide a list or mark the submittal directing the 45 Contractor to the areas that are incomplete. 46 8. If the Contractor considers any correction indicated on the shop drawings to 47 constitute a change to the Contract Documents,then written notice must be 48 provided thereof to the City at least 7 Calendar Days prior to release for 49 manufacture. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013300-7 SUBMITTALS Page 7 of 8 1 9. When the shop drawings have been completed to the satisfaction of the City, the 2 Contractor may carry out the construction in accordance therewith and no further 3 changes therein except upon written instructions from the City. 4 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days 5 following receipt of submittal by the City. 6 L. Mock ups 7 1. Mock Up units as specified in individual Sections, include,but are not necessarily 8 limited to, complete units of the standard of acceptance for that type of Work to be 9 used on the Project. Remove at the completion of the Work or when directed. 10 M. Qualifications 11 1. If specifically required in other Sections of these Specifications, submit a P.E. 12 Certification for each item required. 13 N. Request for Information(RFI) 14 1. Contractor Request for additional information 15 a. Clarification or interpretation of the contract documents 16 b. When the Contractor believes there is a conflict between Contract Documents 17 c. When the Contractor believes there is a conflict between the Drawings and 18 Specifications 19 1) Identify the conflict and request clarification 20 2. Use the Request for Information(RFI) form provided by the City. 21 3. Numbering of RFI 22 a. Prefix with"RFI" followed by series number,"-xxx",beginning with"01"and 23 increasing sequentially with each additional transmittal. 24 4. Sufficient information shall be attached to permit a written response without further 25 information. 26 5. The City will log each request and will review the request. 27 a. If review of the project information request indicates that a change to the 28 Contract Documents is required,the City will issue a Field Order or Change 29 Order, as appropriate. 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 32 1.7 CLOSEOUT SUBMITTALS [NOT USED] 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 34 1.9 QUALITY ASSURANCE [NOT USED] 35 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 36 1.11 FIELD [SITE] CONDITIONS [NOT USED] 37 1.12 WARRANTY [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013300-8 SUBMITTALS Page 8 of 8 I PART 2- PRODUCTS [NOT USED] 2 PART 3 - EXECUTION [NOT USED] 3 END OF SECTION 4 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D.Johnson 1.4.K.8.Working Days modified to Calendar Days 5 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013513-1 SPECIAL PROJECT PROCEDURES Pagel of 8 I SECTION 0135 13 2 SPECIAL PROJECT PROCEDURES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedures for special project circumstances that includes,but is not limited to: 7 a. Coordination with the Texas Department of Transportation 8 b. Work near High Voltage Lines 9 c. Confined Space Entry Program 10 d. Air Pollution Watch Days I I e. Use of Explosives,Drop Weight, Etc. 12 f. Water Department Notification 13 g. Public Notification Prior to Beginning Construction 14 h. Coordination with United States Army Corps of Engineers 15 i. Coordination within Railroad permits areas 16 j. Dust Control 17 k. Employee Parking 18 19 B. Deviations from this City of Fort Worth Standard Specification 20 1. None. 21 C. Related Specification Sections include,but are not necessarily limited to: 22 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 23 2. Division 1 —General Requirements 24 3. Section 33 12 25 —Connection to Existing Water Mains 25 1.2 PRICE AND PAYMENT PROCEDURES 26 A. Measurement and Payment 27 1. Coordination within Railroad permit areas 28 a. Measurement 29 1) Measurement for this Item will be by lump sum. 30 b. Payment 31 1) The work performed and materials furnished in accordance with this Item 32 will be paid for at the lump sum price bid for Railroad Coordination. 33 c. The price bid shall include: 34 1) Mobilization 35 2) Inspection 36 3) Safety training 37 4) Additional Insurance 38 5) Insurance Certificates 39 6) Other requirements associated with general coordination with Railroad, 40 including additional employees required to protect the right-of-way and 41 property of the Railroad from damage arising out of and/or from the 42 construction of the Project. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 35 13-2 SPECIAL PROJECT PROCEDURES Page 2 of 8 1 2. Railroad Flagmen 2 a. Measurement 3 1) Measurement for this Item will be per working day. 4 b. Payment 5 1) The work performed and materials furnished in accordance with this Item 6 will be paid for each working day that Railroad Flagmen are present at the 7 Site. 8 c. The price bid shall include: 9 1) Coordination for scheduling flagmen 10 2) Flagmen 11 3) Other requirements associated with Railroad 12 3. All other items 13 a. Work associated with these Items is considered subsidiary to the various Items 14 bid. No separate payment will be allowed for this Item. 15 1.3 REFERENCES 16 A. Reference Standards 17 1. Reference standards cited in this Specification refer to the current reference 18 standard published at the time of the latest revision date logged at the end of this 19 Specification,unless a date is specifically cited. 20 2. Health and Safety Code,Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 21 High Voltage Overhead Lines. 22 3. North Central Texas Council of Governments (NCTCOG)—Clean Construction 23 Specification 24 1.4 ADMIlVISTRATIVE REQUIREMENTS 25 A. Coordination with the Texas Department of Transportation 26 1. When work in the right-of-way which is under the jurisdiction of the Texas 27 Department of Transportation(TxDOT): 28 a. Notify the Texas Department of Transportation prior to commencing any work 29 therein in accordance with the provisions of the permit 30 b. All work performed in the TxDOT right-of-way shall be performed in 31 compliance with and subject to approval from the Texas Department of 32 Transportation 33 B. Work near High Voltage Lines 34 1. Regulatory Requirements 35 a. All Work near High Voltage Lines(more than 600 volts measured between 36 conductors or between a conductor and the ground) shall be in accordance with 37 Health and Safety Code,Title 9, Subtitle A, Chapter 752. 38 2. Warning sign 39 a. Provide sign of sufficient size meeting all OSHA requirements. 40 3. Equipment operating within 10 feet of high voltage lines will require the following 41 safety features 42 a. Insulating cage-type of guard about the boom or arm 43 b. Insulator links on the lift hook connections for back hoes or dippers 44 c. Equipment must meet the safety requirements as set forth by OSHA and the 45 safety requirements of the owner of the high voltage lines CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 35 13-3 SPECIAL PROJECT PROCEDURES Page 3 of 8 1 4. Work within 6 feet of high voltage electric lines 2 a. Notification shall be given to: 3 1) The power company(example: ONCOR) 4 a) Maintain an accurate log of all such calls to power company and record 5 action taken in each case. 6 b. Coordination with power company 7 1) After notification coordinate with the power company to: 8 a) Erect temporary mechanical barriers,de-energize the lines, or raise or 9 lower the lines 10 c. No personnel may work within 6 feet of a high voltage line before the above 11 requirements have been met. 12 C. Confined Space Entry Program 13 1. Provide and follow approved Confined Space Entry Program in accordance with 14 OSHA requirements. 15 2. Confined Spaces include: 16 a. Manholes 17 b. All other confined spaces in accordance with OSHA's Permit Required for 18 Confined Spaces 19 D. Air Pollution Watch Days 20 1. General 21 a. Observe the following guidelines relating to working on City construction sites 22 on days designated as"AIR POLLUTION WATCH DAYS". 23 b. Typical Ozone Season 24 1) May 1 through October 31. 25 c. Critical Emission Time 26 1) 6:00 a.m. to 10:00 a.m. 27 2. Watch Days 28 a. The Texas Commission on Environmental Quality(TCEQ), in coordination 29 with the National Weather Service,will issue the Air Pollution Watch by 3:00 30 p.m. on the afternoon prior to the WATCH day. 31 b. Requirements 32 1) Begin work after 10:00 a.m. whenever construction phasing requires the 33 use of motorized equipment for periods in excess of 1 hour. 34 2) However,the Contractor may begin work prior to 10:00 a.m. if: 35 a) Use of motorized equipment is less than 1 hour, or 36 b) If equipment is new and certified by EPA as "Low Emitting",or 37 equipment burns Ultra Low Sulfur Diesel (ULSD), diesel emulsions, or 38 alternative fuels such as CNG. 39 E. TCEQ Air Permit 40 1. Obtain TCEQ Air Permit for construction activities per requirements of TCEQ. 41 F. Use of Explosives,Drop Weight,Etc. 42 1. When Contract Documents permit on the project the following will apply: 43 a. Public Notification 44 1) Submit notice to City and proof of adequate insurance coverage, 24 hours 45 prior to commencing. 46 2) Minimum 24 hour public notification in accordance with Section 01 31 13 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 35 13-4 SPECIAL PROJECT PROCEDURES Page 4 of 8 1 G. Water Department Coordination 2 1. During the construction of this project, it will be necessary to deactivate, for a 3 period of time, existing lines. The Contractor shall be required to coordinate with 4 the Water Department to determine the best times for deactivating and activating 5 those lines. 6 2. Coordinate any event that will require connecting to or the operation of an existing 7 City water line system with the City's representative. 8 a. Coordination shall be in accordance with Section 33 12 25. 9 b. If needed, obtain a hydrant water meter from the Water Department for use 10 during the life of named project. 11 c. In the event that a water valve on an existing live system be turned off and on 12 to accommodate the construction of the project is required, coordinate this 13 activity through the appropriate City representative. 14 1) Do not operate water line valves of existing water system. 15 a) Failure to comply will render the Contractor in violation of Texas Penal 16 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor 17 will be prosecuted to the full extent of the law. 18 b) In addition,the Contractor will assume all liabilities and 19 responsibilities as a result of these actions. 20 H. Public Notification Prior to Beginning Construction 21 1. Prior to beginning construction on any block in the project, on a block by block 22 basis,prepare and deliver a notice or flyer of the pending construction to the front 23 door of each residence or business that will be impacted by construction. The notice 24 shall be prepared as follows: 25 a. Post notice or flyer 7 days prior to beginning any construction activity on each 26 block in the project area. 27 1) Prepare flyer on the Contractor's letterhead and include the following 28 information: 29 a) Name of Project 30 b) City Project No(CPN) 31 c) Scope of Project (i.e.type of construction activity) 32 d) Actual construction duration within the block 33 e) Name of the contractor's foreman and phone number 34 f) Name of the City's inspector and phone number 35 g) City's after-hours phone number 36 2) A sample of the `pre-construction notification' flyer is attached as Exhibit 37 A. 38 3) Submit schedule showing the construction start and finish time for each 39 block of the project to the inspector. 40 4) Deliver flyer to the City Inspector for review prior to distribution. 41 b. No construction will be allowed to begin on any block until the flyer is 42 delivered to all residents of the block. 43 I. Public Notification of Temporary Water Service Interruption during Construction 44 1. In the event it becomes necessary to temporarily shut down water service to 45 residents or businesses during construction,prepare and deliver a notice or flyer of 46 the pending interruption to the front door of each affected resident. 47 2. Prepared notice as follows: CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 35 13-5 SPECIAL PROJECT PROCEDURES Page 5 of 8 1 a. The notification or flyer shall be posted 24 hours prior to the temporary 2 interruption. 3 b. Prepare flyer on the contractor's letterhead and include the following 4 information: 5 1) Name of the project 6 2) City Project Number 7 3) Date of the interruption of service 8 4) Period the interruption will take place 9 5) Name of the contractor's foreman and phone number 10 6) Name of the City's inspector and phone number 11 c. A sample of the temporary water service interruption notification is attached as 12 Exhibit B. 13 d. Deliver a copy of the temporary interruption notification to the City inspector 14 for review prior to being distributed. 15 e. No interruption of water service can occur until the flyer has been delivered to 16 all affected residents and businesses. 17 f. Electronic versions of the sample flyers can be obtained from the Project 18 Construction Inspector. 19 J. Coordination with United States Army Corps of Engineers (USACE) 20 1. At locations in the Project where construction activities occur in areas where 21 USACE permits are required,meet all requirements set forth in each designated 22 permit. 23 K. Coordination within Railroad Permit Areas 24 1. At locations in the project where construction activities occur in areas where 25 railroad permits are required,meet all requirements set forth in each designated 26 railroad permit. This includes, but is not limited to,provisions for: 27 a. Flagmen 28 b. Inspectors 29 c. Safety training 30 d. Additional insurance 31 e. Insurance certificates 32 f. Other employees required to protect the right-of-way and property of the 33 Railroad Company from damage arising out of and/or from the construction of 34 the project. Proper utility clearance procedures shall be used in accordance 35 with the permit guidelines. 36 2. Obtain any supplemental information needed to comply with the railroad's 37 requirements. 38 3. Railroad Flagmen 39 a. Submit receipts to City for verification of working days that railroad flagmen 40 were present on Site. 41 L. Dust Control 42 1. Use acceptable measures to control dust at the Site. 43 a. If water is used to control dust, capture and properly dispose of waste water. 44 b. If wet saw cutting is performed,capture and properly dispose of slurry. 45 M. Employee Parking 46 1. Provide parking for employees at locations approved by the City. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 0135 13-6 SPECIAL PROJECT PROCEDURES Page 6 of 8 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3 - EXECUTION [NOT USED] 11 END OF SECTION 12 Revision Log DATE NAME SUMMARY OF CHANGE 1.4.13•-Added requirement of compliance with Health and Safety Code,Title 9. 8/31/2012 D.Johnson Safety,Subtitle A.Public Safety,Chapter 752.High Voltage Overhead Lines. 1.4.E—Added Contractor responsibility for obtaining a TCEQ Air Permit 13 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 35 13-7 SPECIAL PROJECT PROCEDURES Page 7 of 8 1 EXHIBIT A 2 (To be printed on Contractor's Letterhead) 3 4 5 6 Date: 7 8 CPN No.: 9 Project Name: 10 Mapsco Location: 11 Limits of Construction: 12 13 14 15 16 17 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT 18 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR 19 PROPERTY. 20 21 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE 22 OF THIS NOTICE. 23 24 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER 25 ISSUE, PLEASE CALL: 26 27 28 Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.> 29 30 OR 31 32 Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> 33 34 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 35 36 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 37 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 013513-8 SPECIAL PROJECT PROCEDURES Page 8 of 8 1 EXHIBIT B 2 FORT WORTH o� DOE NO.10= Projew i anw. NOTICE OF TEMPORARY WATER SERVICE INTERRUPTION DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR WATER SERVICE WILL BE INTERRUPTED ON BETWEEN THE HOURS OF AND IF YOU HAVE QUESTIONS ABOUT THIS SHUT-OUT,PLEASE CALL: MR. AT (CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER) OR MR. AT (CITY INSPECTOR) (TELEPHONE NUMBER) THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE. THANK YOU, .CONTRACTOR 3 - 4 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 014523-1 TESTING AND INSPECTION SERVICES Page 1 of 2 1 SECTION 0145 23 2 TESTING AND INSPECTION SERVICES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Testing and inspection services procedures and coordination 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 a. Contractor is responsible for performing, coordinating,and payment of all 17 Quality Control testing. 18 b. City is responsible for performing and payment for first set of Quality 19 Assurance testing. 20 1) If the first Quality Assurance test performed by the City fails,the 21 Contractor is responsible for payment of subsequent Quality Assurance 22 testing until a passing test occurs. 23 a) Final acceptance will not be issued by City until all required payments 24 for testing by Contractor have been paid in full. 25 1.3 REFERENCES [NOT USED] 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Testing 28 1. Complete testing in accordance with the Contract Documents. 29 2. Coordination 30 a. When testing is required to be performed by the City,notify City, sufficiently 31 in advance, when testing is needed. 32 b. When testing is required to be completed by the Contractor,notify City, 33 sufficiently in advance,that testing will be performed. 34 3. Distribution of Testing Reports 35 a. Electronic Distribution 36 1) Confirm development of Project directory for electronic submittals to be 37 uploaded to City's Buzzsaw site, or another external FTP site approved by 38 the City. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 014523-2 TESTING AND INSPECTION SERVICES Page 2 of 2 1 2) Upload test reports to designated project directory and notify appropriate 2 City representatives via email of submittal posting. 3 3) Hard Copies 4 a) 1 copy for all submittals submitted to the Project Representative 5 b. Hard Copy Distribution(if required in lieu of electronic distribution) 6 1) Tests performed by City 7 a) Distribute 1 hard copy to the Contractor 8 2) Tests performed by the Contractor 9 a) Distribute 3 hard copies to City's Project Representative 10 4. Provide City's Project Representative with trip tickets for each delivered load of 11 Concrete or Lime material including the following information: 12 a. Name of pit 13 b. Date of delivery 14 c. Material delivered 15 B. Inspection 16 1. Inspection or lack of inspection does not relieve the Contractor from obligation to 17 perform work in accordance with the Contract Documents. 18 1.5 SUBMITTALS [NOT USED] 19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 20 1.7 CLOSEOUT SUBMITTALS [NOT USED] 21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 22 1.9 QUALITY ASSURANCE [NOT USED] 23 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 24 1.11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2 - PRODUCTS [NOT USED] 27 PART 3 - EXECUTION [NOT USED] 28 END OF SECTION 29 Revision Log DATE NAME SUMMARY OF CHANGE 30 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 5000-1 TEMPORARY FACILITIES AND CONTROLS Page] of 4 1 SECTION 0150 00 2 TEMPORARY FACILITIES AND CONTROLS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provide temporary facilities and controls needed for the Work including,but not 7 necessarily limited to: 8 a. Temporary utilities 9 b. Sanitary facilities 10 c. Storage Sheds and Buildings 11 d. Dust control 12 e. Temporary fencing of the construction site 13 B. Deviations from this City of Fort Worth Standard Specification 14 1. None. 15 C. Related Specification Sections include,but are not necessarily limited to: 16 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 17 2. Division 1 —General Requirements 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Work associated with this Item is considered subsidiary to the various Items bid. 21 No separate payment will be allowed for this Item. 22 1.3 REFERENCES [NOT USED] 23 1.4 ADMINISTRATIVE REQUIREMENTS 24 A. Temporary Utilities 25 1. Obtaining Temporary Service 26 a. Make arrangements with utility service companies for temporary services. 27 b. Abide by rules and regulations of utility service companies or authorities 28 having jurisdiction. 29 c. Be responsible for utility service costs until Work is approved for Final 30 Acceptance. 31 1) Included are fuel,power,light,heat and other utility services necessary for 32 execution, completion,testing and initial operation of Work. 33 2. Water 34 a. Contractor to provide water required for and in connection with Work to be 35 performed and for specified tests of piping,equipment,devices or other use as 36 required for the completion of the Work. 37 b. Provide and maintain adequate supply of potable water for domestic 38 consumption by Contractor personnel and City's Project Representatives. 39 c. Coordination 40 1) Contact City 1 week before water for construction is desired CITY OF FORT WORTH Dry Banch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 015000-2 TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 1 d. Contractor Payment for Construction Water 2 1) Obtain construction water meter from City for payment as billed by City's 3 established rates. 4 3. Electricity and Lighting 5 a. Provide and pay for electric powered service as required for Work, including 6 testing of Work. 7 1) Provide power for lighting,operation of equipment,or other use. 8 b. Electric power service includes temporary power service or generator to 9 maintain operations during scheduled shutdown. 10 4. Telephone 11 a. Provide emergency telephone service at Site for use by Contractor personnel 12 and others performing work or furnishing services at Site. 13 5. Temporary Heat and Ventilation 14 a. Provide temporary heat as necessary for protection or completion of Work. 15 b. Provide temporary heat and ventilation to assure safe working conditions. 16 B. Sanitary Facilities 17 1. Provide and maintain sanitary facilities for persons on Site. 18 a. Comply with regulations of State and local departments of health. 19 2. Enforce use of sanitary facilities by construction personnel at job site. 20 a. Enclose and anchor sanitary facilities. 21 b. No discharge will be allowed from these facilities. 22 c. Collect and store sewage and waste so as not to cause nuisance or health 23 problem. 24 d. Haul sewage and waste off-site at no less than weekly intervals and properly 25 dispose in accordance with applicable regulation. 26 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 27 4. Remove facilities at completion of Project 28 C. Storage Sheds and Buildings 29 1. Provide adequately ventilated,watertight,weatherproof storage facilities with floor 30 above ground level for materials and equipment susceptible to weather damage. 31 2. Storage of materials not susceptible to weather damage may be on blocks off 32 ground. 33 3. Store materials in a neat and orderly manner. 34 a. Place materials and equipment to permit easy access for identification, 35 inspection and inventory. 36 4. Equip building with lockable doors and lighting, and provide electrical service for 37 equipment space heaters and heating or ventilation as necessary to provide storage 38 environments acceptable to specified manufacturers. 39 5. Fill and grade site for temporary structures to provide drainage away from 40 temporary and existing buildings. 41 6. Remove building from site prior to Final Acceptance. 42 D. Temporary Fencing 43 1. Provide and maintain for the duration or construction when required in contract 44 documents 45 E. Dust Control CITY OF FORT WORTH Dry Banch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 5000-3 TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 1 1. Contractor is responsible for maintaining dust control through the duration of the 2 project. 3 a. Contractor remains on-call at all times 4 b. Must respond in a timely manner 5 F. Temporary Protection of Construction 6 1. Contractor or subcontractors are responsible for protecting Work from damage due 7 to weather. 8 1.5 SUBMITTALS [NOT USED] 9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 10 1.7 CLOSEOUT SUBMITTALS [NOT USED] 11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 12 1.9 QUALITY ASSURANCE [NOT USED] 13 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 14 1.11 FIELD [SITE] CONDITIONS [NOT USED] 15 1.12 WARRANTY [NOT USED] 16 PART 2- PRODUCTS [NOT USED] 17 PART 3- EXECUTION [NOT USED] 18 3.1 INSTALLERS [NOT USED] 19 3.2 EXAMINATION [NOT USED] 20 3.3 PREPARATION [NOT USED] 21 3.4 INSTALLATION 22 A. Temporary Facilities 23 1. Maintain all temporary facilities for duration of construction activities as needed. 24 3.5 [REPAIR] / [RESTORATION] 25 3.6 RE-INSTALLATION 26 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 27 3.8 SYSTEM STARTUP [NOT USED] 28 3.9 ADJUSTING [NOT USED] 29 3.10 CLEANING [NOT USED] 30 3.11 CLOSEOUT ACTIVITIES 31 A. Temporary Facilities CITY OF FORT WORTH Dry Banch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 5000-4 TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 1 1. Remove all temporary facilities and restore area after completion of the Work,to a 2 condition equal to or better than prior to start of Work. 3 3.12 PROTECTION [NOT USED] 4 3.13 MAINTENANCE [NOT USED] 5 3.14 ATTACHMENTS [NOT USED] 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 8 CITY OF FORT WORTH Dry Banch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 015526-1 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Pagel of 3 1 SECTION 0155 26 2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Administrative procedures for: 7 a. Street Use Permit 8 b. Modification of approved traffic control 9 c. Removal of Street Signs 10 B. Deviations from this City of Fort Worth Standard Specification 11 1. None. 12 C. Related Specification Sections include,but are not necessarily limited to: 13 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 14 2. Division 1 —General Requirements 15 3. Section 34 71 13—Traffic Control 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES 21 A. Reference Standards 22 1. Reference standards cited in this specification refer to the current reference standard 23 published at the time of the latest revision date logged at the end of this 24 specification,unless a date is specifically cited. 25 2. Texas Manual on Uniform Traffic Control Devices(TMUTCD). 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Traffic Control 28 1. General 29 a. When traffic control plans are included in the Drawings,provide Traffic 30 Control in accordance with Drawings and Section 34 71 13. 31 b. When traffic control plans are not included in the Drawings,prepare traffic 32 control plans in accordance with Section 34 71 13 and submit to City for 33 review. 34 1) Allow minimum 10 working days for review of proposed Traffic Control. 35 B. Street Use Permit 36 1. Prior to installation of Traffic Control,a City Street Use Permit is required. 37 a. To obtain Street Use Permit, submit Traffic Control Plans to City 38 Transportation and Public Works Department. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 5526-2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 1 1) Allow a minimum of 5 working days for permit review. 2 2) Contractor's responsibility to coordinate review of Traffic Control plans for 3 Street Use Permit, such that construction is not delayed. 4 C. Modification to Approved Traffic Control 5 1. Prior to installation traffic control: 6 a. Submit revised traffic control plans to City Department Transportation and 7 Public Works Department. 8 1) Revise Traffic Control plans in accordance with Section 34 71 13. 9 2) Allow minimum 5 working days for review of revised Traffic Control. 10 3) It is the Contractor's responsibility to coordinate review of Traffic Control 11 plans for Street Use Permit,such that construction is not delayed. 12 D. Removal of Street Sign 13 1. If it is determined that a street sign must be removed for construction,then contact 14 City Transportation and Public Works Department, Signs and Markings Division to 15 remove the sign. 16 E. Temporary Signage 17 1. In the case of regulatory signs,replace permanent sign with temporary sign meeting 18 requirements of the latest edition of the Texas Manual on Uniform Traffic Control 19 Devices(MUTCD). 20 2. Install temporary sign before the removal of permanent sign. 21 3. When construction is complete,to the extent that the permanent sign can be 22 reinstalled,contact the City Transportation and Public Works Department, Signs 23 and Markings Division,to reinstall the permanent sign. 24 F. Traffic Control Standards 25 1. Traffic Control Standards can be found on the City's Buzzsaw website. 26 1.5 SUBMITTALS [NOT USED] 27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 28 1.7 CLOSEOUT SUBMITTALS [NOT USED] 29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 30 1.9 QUALITY ASSURANCE [NOT USED] 31 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 32 1.11 FIELD [SITE] CONDITIONS [NOT USED] 33 1.12 WARRANTY [NOT USED] 34 PART 2- PRODUCTS [NOT USED] 35 PART 3- F,XECUTION [NOT USED] 36 END OF SECTION CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 5526-3 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 1 Revision Lot DATE NAME SUMMARY OF CHANGE 2 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 57 13-1 STORM WATER POLLUTION PREVENTION Pagel of 3 1 SECTION 0157 13 2 STORM WATER POLLUTION PREVENTION 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Procedures for Storm Water Pollution Prevention Plans 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0— Bidding Requirements,Contract Forms and Conditions of the 11 Contract 12 2. Division 1 —General Requirements 13 3. Section 31 25 00—Erosion and Sediment Control 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Construction Activities resulting in less than 1 acre of disturbance 17 a. Work associated with this Item is considered subsidiary to the various Items 18 bid. No separate payment will be allowed for this Item. 19 2. Construction Activities resulting in greater than 1 acre of disturbance 20 a. Measurement and Payment shall be in accordance with Section 3125 00. 21 1.3 REFERENCES 22 A. Abbreviations and Acronyms 23 1. Notice of Intent:NOI 24 2. Notice of Termination: NOT 25 3. Storm Water Pollution Prevention Plan: SWPPP 26 4. Texas Commission on Environmental Quality: TCEQ 27 5. Notice of Change: NOC 28 A. Reference Standards 29 1. Reference standards cited in this Specification refer to the current reference 30 standard published at the time of the latest revision date logged at the end of this 31 Specification,unless a date is specifically cited. 32 2. Integrated Storm Management(iSWM)Technical Manual for Construction 33 Controls 34 1.4 ADMINISTRATIVE REQUIREMENTS 35 A. General 36 1. Contractor is responsible for resolution and payment of any fines issued associated 37 with compliance to Stormwater Pollution Prevention Plan. CITY OF FORT WORTH Dry Banch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 57 13-2 STORM WATER POLLUTION PREVENTION Page 2 of 3 1 B. Construction Activities resulting in: 2 1. Less than 1 acre of disturbance 3 a. Provide erosion and sediment control in accordance with Section 31 25 00 and 4 Drawings. 5 2. 1 to less than 5 acres of disturbance 6 a. Texas Pollutant Discharge Elimination System(TPDES) General Construction 7 Permit is required 8 b. Complete SWPPP in accordance with TCEQ requirements 9 1) TCEQ Small Construction Site Notice Required under general permit 10 TXR 150000 11 a) Sign and post at job site 12 b) Prior to Preconstruction Meeting, send 1 copy to City Department of 13 Transportation and Public Works, Environmental Division, (817)392- 14 6088. 15 2) Provide erosion and sediment control in accordance with: 16 a) Section 3125 00 17 b) The Drawings 18 c) TXR150000 General Permit 19 d) SWPPP 20 e) TCEQ requirements 21 3. 5 acres or more of Disturbance 22 a. Texas Pollutant Discharge Elimination System(TPDES)General Construction 23 Permit is required 24 b. Complete SWPPP in accordance with TCEQ requirements 25 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee 26 a) Sign and post at job site 27 b) Send copy to City Department of Transportation and Public Works, 28 Environmental Division, (817) 392-6088. 29 2) TCEQ Notice of Change required if making changes or updates to NOI 30 3) Provide erosion and sediment control in accordance with: 31 a) Section 3125 00 32 b) The Drawings 33 c) TXR150000 General Permit 34 d) SWPPP 35 e) TCEQ requirements 36 4) Once the project has been completed and all the closeout requirements of 37 TCEQ have been met a TCEQ Notice of Termination can be submitted. 38 a) Send copy to City Department of Transportation and Public Works, 39 Environmental Division, (817) 392-6088. 40 1.5 SUBMITTALS 41 A. SWPPP 42 1. Submit in accordance with Section 01 33 00,except as stated herein. 43 a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City 44 as follows: 45 1) 1 copy to the City Project Manager 46 a) City Project Manager will forward to the City Department of 47 Transportation and Public Works, Environmental Division for review CITY OF FORT WORTH Dry Banch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 57 13-3 STORM WATER POLLUTION PREVENTION Page 3 of 3 1 B. Modified SWPPP 2 1. If the SWPPP is revised during construction,resubmit modified SWPPP to the City 3 in accordance with Section 01 33 00. 4 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 5 1.7 CLOSEOUT SUBMITTALS [NOT USED] 6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 7 1.9 QUALITY ASSURANCE [NOT USED] 8 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 9 1.11 FIELD [SITE] CONDITIONS [NOT USED] 10 1.12 WARRANTY [NOT USED] 11 PART 2- PRODUCTS [NOT USED] 12 PART 3 - EXECUTION [NOT USED] 13 END OF SECTION 14 Revision Log DATE NAME SUMMARY OF CHANGE 15 CITY OF FORT WORTH Dry Banch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 015813-1 TEMPORARY PROJECT SIGNAGE Page 1 of 3 1 SECTION 0158 13 2 TEMPORARY PROJECT SIGNAGE 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Temporary Project Signage Requirements 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 18 1.5 SUBMITTALS [NOT USED] 19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 20 1.7 CLOSEOUT SUBMITTALS [NOT USED] 21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 22 1.9 QUALITY ASSURANCE [NOT USED] 23 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 24 1.11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2- PRODUCTS 27 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 28 2.2 EQUIPMENT,PRODUCT TYPES,AND MATERIALS 29 A. Design Criteria 30 1. Provide free standing Project Designation Sign in accordance with City's Standard 31 Details for project signs. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 58 13-2 TEMPORARY PROJECT SIGNAGE Page 2 of 3 1 B. Materials 2 1. Sign 3 a. Constructed of 3/-inch fir plywood,grade A-C(exterior) or better 4 2.3 ACCESSORIES [NOT USED] 5 2.4 SOURCE QUALITY CONTROL [NOT USED] 6 PART 3 - EXECUTION 7 3.1 INSTALLERS [NOT USED] 8 3.2 EXAMINATION [NOT USED] 9 3.3 PREPARATION [NOT USED] 10 3.4 INSTALLATION 11 A. General 12 1. Provide vertical installation at extents of project. 13 2. Relocate sign as needed, upon request of the City. 14 B. Mounting options 15 a. Skids 16 b. Posts 17 c. Barricade 18 3.5 REPAIR/RESTORATION [NOT USED] 19 3.6 RE-INSTALLATION [NOT USED] 20 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING [NOT USED] 24 3.11 CLOSEOUT ACTIVITIES [NOT USED] 25 3.12 PROTECTION [NOT USED] 26 3.13 MAINTENANCE 27 A. General 28 1. Maintenance will include painting and repairs as needed or directed by the City. 29 3.14 ATTACHMENTS [NOT USED] 30 END OF SECTION 31 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 58 13-3 TEMPORARY PROJECT SIGNAGE Page 3 of 3 1 Revision Log DATE NAME SUMMARY OF CHANGE 2 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 6000-1 PRODUCT REQUIREMENTS Page I of 2 1 SECTION 0160 00 2 PRODUCT REQUIREMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. References for Product Requirements and City Standard Products List 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 13 1.3 REFERENCES [NOT USED] 14 1.4 ADMINISTRATIVE REQUIREMENTS 15 A. A list of City approved products for use is located on Buzzsaw as follows: 16 1. Resources\02 -Construction Documents\Standard Products List 17 B. Only products specifically included on City's Standard Product List in these Contract 18 Documents shall be allowed for use on the Project. 19 1. Any subsequently approved products will only be allowed for use upon specific 20 approval by the City. 21 C. Any specific product requirements in the Contract Documents supersede similar 22 products included on the City's Standard Product List. 23 1. The City reserves the right to not allow products to be used for certain projects even 24 though the product is listed on the City's Standard Product List. 25 D. Although a specific product is included on City's Standard Product List,not all 26 products from that manufacturer are approved for use,including but not limited to,that 27 manufacturer's standard product. 28 E. See Section 0133 00 for submittal requirements of Product Data included on City's 29 Standard Product List. 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 32 1.7 CLOSEOUT SUBMITTALS [NOT USED] 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 34 1.9 QUALITY ASSURANCE [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 016000-2 PRODUCT REQUIREMENTS Page 2 of 2 1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2- PRODUCTS [NOT USED] 5 PART 3 - EXECUTION [NOT USED] 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 10/12/12 D.Johnson Modified Location of City's Standard Product List 8 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 6600-1 PRODUCT STORAGE AND HANDLING REQUIREMENTS Pagel of 4 1 SECTION 0166 00 2 PRODUCT STORAGE AND HANDLING REQUIREMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Scheduling of product delivery 7 2. Packaging of products for delivery 8 3. Protection of products against damage from: 9 a. Handling 10 b. Exposure to elements or harsh environments 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. None. 13 C. Related Specification Sections include,but are not necessarily limited to: 14 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 15 2. Division 1 —General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 22 1.5 SUBMITTALS [NOT USED] 23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 24 1.7 CLOSEOUT SUBMITTALS [NOT USED] 25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 26 1.9 QUALITY ASSURANCE [NOT USED] 27 1.10 DELIVERY AND HANDLING 28 A. Delivery Requirements 29 1. Schedule delivery of products or equipment as required to allow timely installation 30 and to avoid prolonged storage. 31 2. Provide appropriate personnel and equipment to receive deliveries. 32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site 33 for personnel or equipment to receive the delivery. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 016600-2 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 1 4. Deliver products or equipment in manufacturer's original unbroken cartons or other 2 containers designed and constructed to protect the contents from physical or 3 environmental damage. 4 5. Clearly and fully mark and identify as to manufacturer, item and installation 5 location. 6 6. Provide manufacturer's instructions for storage and handling. 7 B. Handling Requirements 8 1. Handle products or equipment in accordance with these Contract Documents and 9 manufacturer's recommendations and instructions. 10 C. Storage Requirements 11 1. Store materials in accordance with manufacturer's recommendations and 12 requirements of these Specifications. 13 2. Make necessary provisions for safe storage of materials and equipment. 14 a. Place loose soil materials and materials to be incorporated into Work to prevent 15 damage to any part of Work or existing facilities and to maintain free access at 16 all times to all parts of Work and to utility service company installations in 17 vicinity of Work. 18 3. Keep materials and equipment neatly and compactly stored in locations that will 19 cause minimum inconvenience to other contractors,public travel, adjoining owners, 20 tenants and occupants. 21 a. Arrange storage to provide easy access for inspection. 22 4. Restrict storage to areas available on construction site for storage of material and 23 equipment as shown on Drawings, or approved by City's Project Representative. 24 5. Provide off-site storage and protection when on-site storage is not adequate. 25 a. Provide addresses of and access to off-site storage locations for inspection by 26 City's Project Representative. 27 6. Do not use lawns, grass plots or other private property for storage purposes without 28 written permission of owner or other person in possession or control of premises. 29 7. Store in manufacturers' unopened containers. 30 8. Neatly, safely and compactly stack materials delivered and stored along line of 31 Work to avoid inconvenience and damage to property owners and general public 32 and maintain at least 3 feet from fire hydrant. 33 9. Keep public and private driveways and street crossings open. 34 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to 35 satisfaction of City's Project Representative. 36 a. Total length which materials maybe distributed along route of construction at 37 one time is 1,000 linear feet,unless otherwise approved in writing by City's 38 Project Representative. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 016600-3 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3 - EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 ERECTION [NOT USED] 9 3.5 REPAIR/RESTORATION [NOT USED] 10 3.6 RE-INSTALLATION [NOT USED] 11 3.7 FIELD [OR] SITE QUALITY CONTROL 12 A. Tests and Inspections 13 1. Inspect all products or equipment delivered to the site prior to unloading. 14 B. Non-Conforming Work 15 1. Reject all products or equipment that are damaged,used or in any other way 16 unsatisfactory for use on the project. 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES [NOT USED] 21 3.12 PROTECTION 22 A. Protect all products or equipment in accordance with manufacturer's written directions. 23 B. Store products or equipment in location to avoid physical damage to items while in 24 storage. 25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by 26 the manufacturer. 27 3.13 MAINTENANCE [NOT USED] 28 3.14 ATTACHMENTS [NOT USED] 29 END OF SECTION 30 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 016600-4 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 Revision Log DATE NAME SUMMARY OF CHANGE 1 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 017000-1 MOBILIZATION AND REMOBILIZATION Pagel of 4 1 SECTION 01 70 00 2 MOBILIZATION AND REMOBILIZATION 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Mobilization and Demobilization 7 a. Mobilization 8 1) Transportation of Contractor's personnel,equipment, and operating supplies 9 to the Site 10 2) Establishment of necessary general facilities for the Contractor's operation 11 at the Site 12 3) Premiums paid for performance and payment bonds 13 4) Transportation of Contractor's personnel,equipment,and operating supplies 14 to another location within the designated Site 15 5) Relocation of necessary general facilities for the Contractor's operation 16 from 1 location to another location on the Site. 17 b. Demobilization 18 1) Transportation of Contractor's personnel,equipment,and operating supplies 19 away from the Site including disassembly 20 2) Site Clean-up 21 3) Removal of all buildings and/or other facilities assembled at the Site for this 22 Contract 23 c. Mobilization and Demobilization do not include activities for specific items of 24 work that are for which payment is provided elsewhere in the contract. 25 2. Remobilization 26 a. Remobilization for Suspension of Work specifically required in the Contract 27 Documents or as required by City includes: 28 1) Demobilization 29 a) Transportation of Contractor's personnel,equipment,and operating 30 supplies from the Site including disassembly or temporarily securing 31 equipment,supplies,and other facilities as designated by the Contract 32 Documents necessary to suspend the Work. 33 b) Site Clean-up as designated in the Contract Documents 34 2) Remobilization 35 a) Transportation of Contractor's personnel,equipment,and operating 36 supplies to the Site necessary to resume the Work. 37 b) Establishment of necessary general facilities for the Contractor's 38 operation at the Site necessary to resume the Work. 39 3) No Payments will be made for: 40 a) Mobilization and Demobilization from one location to another on the 41 Site in the normal progress of performing the Work. 42 b) Stand-by or idle time 43 c) Lost profits 44 3. Mobilizations and Demobilization for Miscellaneous Projects 45 a. Mobilization and Demobilization CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 017000-2 MOBILIZATION AND REMOBILIZATION Page 2 of 4 1 1) Mobilization shall consist of the activities and cost on a Work Order basis 2 necessary for: 3 a) Transportation of Contractor's personnel, equipment, and operating 4 supplies to the Site for the issued Work Order. 5 b) Establishment of necessary general facilities for the Contractor's 6 operation at the Site for the issued Work Order 7 2) Demobilization shall consist of the activities and cost necessary for: 8 a) Transportation of Contractor's personnel, equipment, and operating 9 supplies from the Site including disassembly for each issued Work 10 Order 11 b) Site Clean-up for each issued Work Order 12 c) Removal of all buildings or other facilities assembled at the Site for 13 each Work Oder 14 b. Mobilization and Demobilization do not include activities for specific items of 15 work for which payment is provided elsewhere in the contract. 16 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects 17 a. A Mobilization for Miscellaneous Projects when directed by the City and the 18 mobilization occurs within 24 hours of the issuance of the Work Order. 19 B. Deviations from this City of Fort Worth Standard Specification 20 1. None. 21 C. Related Specification Sections include,but are not necessarily limited to: 22 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 23 2. Division 1 —General Requirements 24 1.2 PRICE AND PAYMENT PROCEDURES 25 A. Measurement and Payment 26 1. Mobilization and Demobilization 27 a. Measure 28 1) This Item is considered subsidiary to the various Items bid. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this Item 31 are subsidiary to the various Items bid and no other compensation will be 32 allowed. 33 2. Remobilization for suspension of Work as specifically required in the Contract 34 Documents 35 a. Measurement 36 1) Measurement for this Item shall be per each remobilization performed. 37 b. Payment 38 1) The work performed and materials furnished in accordance with this Item 39 and measured as provided under"Measurement"will be paid for at the unit 40 price per each"Specified Remobilization"in accordance with Contract 41 Documents. 42 c. The price shall include: 43 1) Demobilization as described in Section 1.1.A.2.a.1) 44 2) Remobilization as described in Section 1.1.A.2.a.2) 45 d. No payments will be made for standby, idle time,or lost profits associated this 46 Item. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 7000-3 MOBILIZATION AND REMOBILIZATION Page 3 of 4 1 3. Remobilization for suspension of Work as required by City 2 a. Measurement and Payment 3 1) This shall be submitted as a Contract Claim in accordance with Article 10 4 of Section 00 72 00. 5 2) No payments will be made for standby, idle time, or lost profits associated 6 with this Item. 7 4. Mobilizations and Demobilizations for Miscellaneous Projects 8 a. Measurement 9 1) Measurement for this Item shall be for each Mobilization and 10 Demobilization required by the Contract Documents 11 b. Payment 12 1) The Work performed and materials furnished in accordance with this Item 13 and measured as provided under"Measurement"will be paid for at the unit 14 price per each"Work Order Mobilization" in accordance with Contract 15 Documents. Demobilization shall be considered subsidiary to mobilization 16 and shall not be paid for separately. 17 c. The price shall include: 18 1) Mobilization as described in Section 1.1.A.3.a.1) 19 2) Demobilization as described in Section 1.1.A.3.a.2) 20 d. No payments will be made for standby,idle time, or lost profits associated this 21 Item. 22 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects 23 a. Measurement 24 1) Measurement for this Item shall be for each Mobilization and 25 Demobilization required by the Contract Documents 26 b. Payment 27 1) The Work performed and materials furnished in accordance with this Item 28 and measured as provided under"Measurement"will be paid for at the unit 29 price per each"Work Order Emergency Mobilization"in accordance with 30 Contract Documents. Demobilization shall be considered subsidiary to 31 mobilization and shall not be paid for separately. 32 c. The price shall include 33 1) Mobilization as described in Section 1.1.A.4.a) 34 2) Demobilization as described in Section 1.1.A.3.a.2) 35 d. No payments will be made for standby, idle time, or lost profits associated this 36 Item. 37 1.3 REFERENCES [NOT USED] 38 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 39 1.5 SUBMITTALS [NOT USED] 40 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 41 1.7 CLOSEOUT SUBMITTALS [NOT USED] 42 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 43 1.9 QUALITY ASSURANCE [NOT USED] 44 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 017000-4 MOBILIZATION AND REMOBILIZATION Page 4 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3 - EXECUTION [NOT USED] 5 END OF SECTION 6 Revision Log DATE NAME SUMMARY OF CHANGE 7 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 7123-1 CONSTRUCTION STAKING AND SURVEY Page 1 of 4 1 SECTION 01 71 23 2 CONSTRUCTION STAKING AND SURVEY 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Requirements for construction staking and construction survey 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Construction Staking 15 a. Measurement 16 1) This Item is considered subsidiary to the various Items bid. 17 b. Payment 18 1) The work performed and the materials furnished in accordance with this 19 Item are subsidiary to the various Items bid and no other compensation will 20 be allowed. 21 2. Construction Survey 22 a. Measurement 23 1) This Item is considered subsidiary to the various Items bid. 24 b. Payment 25 1) The work performed and the materials furnished in accordance with this 26 Item are subsidiary to the various Items bid and no other compensation will 27 be allowed. 28 1.3 REFERENCES [NOT USED] 29 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 30 1.5 SUBMITTALS 31 A. Submittals, if required, shall be in accordance with Section 01 33 00. 32 B. All submittals shall be approved by the City prior to delivery. 33 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 34 A. Certificates 35 1. Provide certificate certifying that elevations and locations of improvements are in 36 conformance or non-conformance with requirements of the Contract Documents. 37 a. Certificate must be sealed by a registered professional land surveyor in the 38 State of Texas. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 7123-2 CONSTRUCTION STAKING AND SURVEY Page 2 of 4 1 B. Field Quality Control Submittals 2 1. Documentation verifying accuracy of field engineering work. 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE 6 A. Construction Staking 7 1. Construction staking will be performed by the City. 8 2. Coordination 9 a. Contact City's Project Representative at least 2 weeks in advance for 10 scheduling of Construction Staking. 11 b. It is the Contractor's responsibility to coordinate staking such that construction 12 activities are not delayed or negatively impacted. 13 3. General 14 a. Contractor is responsible for preserving and maintaining stakes furnished by 15 City. 16 b. If in the opinion of the City, a sufficient number of stakes or markings have 17 been lost, destroyed or disturbed,by Contractor's neglect, such that the 18 contracted Work cannot take place,then the Contractor will be required to pay 19 the City for new staking with a 25 percent markup. The cost for staking will be 20 deducted from the payment due to the Contractor for the Project. 21 B. Construction Survey 22 1. Construction Survey will be performed by the City. 23 2. Coordination 24 a. Contractor to verify that control data established in the design survey remains 25 intact. 26 b. Coordinate with the City prior to field investigation to determine which 27 horizontal and vertical control data will be required for construction survey. 28 c. It is the Contractor's responsibility to coordinate Construction Survey such that 29 construction activities are not delayed or negatively impacted. 30 d. Notify City if any control data needs to be restored or replaced due to damage 31 caused during construction operations. 32 1) City shall perform replacements and/or restorations. 33 3. General 34 a. Construction survey will be performed in order to maintain complete and 35 accurate logs of control and survey work as it progresses for Project Records. 36 b. The Contractor will need to ensure coordination is maintained with the City to 37 perform construction survey to obtain construction features, including but not 38 limited to the following: 39 1) All Utility Lines 40 a) Rim and flowline elevations and coordinates for each manhole or 41 junction structure 42 2) Water Lines 43 a) Top of pipe elevations and coordinates for waterlines at the following 44 locations: 45 (1) Every 250 linear feet CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 017123-3 CONSTRUCTION STAKING AND SURVEY Page 3 of 4 1 (2) Horizontal and vertical points of inflection, curvature,etc. (All 2 Fittings) 3 (3) Cathodic protection test stations 4 (4) Sampling stations 5 (5) Meter boxes/vaults (All sizes) 6 (6) Fire lines 7 (7) Fire hydrants 8 (8) Gate valves 9 (9) Plugs, stubouts,dead-end lines 10 (10) Air Release valves (Manhole rim and vent pipe) 11 (11) Blow off valves(Manhole rim and valve lid) 12 (12) Pressure plane valves 13 (13) Cleaning wyes 14 (14) Casing pipe(each end) 15 b) Storm Sewer 16 (1) Top of pipe elevations and coordinates at the following locations: 17 (a) Every 250 linear feet 18 (b) Horizontal and vertical points of inflection, curvature,etc. 19 c) Sanitary Sewer 20 (1) Top of pipe elevations and coordinates for sanitary sewer lines at 21 the following locations: 22 (a) Every 250 linear feet 23 (b) Horizontal and vertical points of inflection, curvature, etc. 24 (c) Cleanouts 25 c. Construction survey will be performed in order to maintain complete and 26 accurate logs of control and survey work associated with meeting or exceeding 27 the line and grade required by these Specifications. 28 d. The Contractor will need to ensure coordination is maintained with the City to 29 perform construction survey and to verify control data, including but not 30 limited to the following: 31 1) Established benchmarks and control points provided for the Contractor's 32 use are accurate 33 2) Benchmarks were used to furnish and maintain all reference lines and 34 grades for tunneling 35 3) Lines and grades were used to establish the location of the pipe 36 4) Submit to the City copies of field notes used to establish all lines and 37 grades and allow the City to check guidance system setup prior to 38 beginning each tunneling drive. 39 5) Provide access for the City to verify the guidance system and the line and 40 grade of the carrier pipe on a daily basis. 41 6) The Contractor remains fully responsible for the accuracy of the work and 42 the correction of it,as required. 43 7) Monitor line and grade continuously during construction. 44 8) Record deviation with respect to design line and grade once at each pipe 45 joint and submit daily records to City. 46 9) If the installation does not meet the specified tolerances, immediately notify 47 the City and correct the installation in accordance with the Contract 48 Documents. 49 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 017123-4 CONSTRUCTION STAKING AND SURVEY Page 4 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 APPLICATION 9 3.5 REPAIR/RESTORATION [NOT USED] 10 3.6 RE-INSTALLATION [NOT USED] 11 3.7 FIELD [OR] SITE QUALITY CONTROL 12 A. It is the Contractor's responsibility to maintain all stakes and control data placed by the 13 City in accordance with this Specification. 14 B. Do not change or relocate stakes or control data without approval from the City. 15 3.8 SYSTEM STARTUP [NOT USED] 16 3.9 ADJUSTING [NOT USED] 17 3.10 CLEANING [NOT USED] 18 3.11 CLOSEOUT ACTIVITIES [NOT USED] 19 3.12 PROTECTION [NOT USED] 20 3.13 MAINTENANCE [NOT USED] 21 3.14 ATTACHMENTS [NOT USED] 22 END OF SECTION 23 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D.Johnson 24 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 74 23-1 CLEANING Page 1 of 4 1 SECTION 0174 23 2 CLEANING 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Intermediate and final cleaning for Work not including special cleaning of closed 7 systems specified elsewhere 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include,but are not necessarily limited to: 11 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 12 2. Division 1 —General Requirements 13 3. Section 32 92 13 —Hydro-Mulching, Seeding and Sodding 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Work associated with this Item is considered subsidiary to the various Items bid. 17 No separate payment will be allowed for this Item. 18 1.3 REFERENCES [NOT USED] 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Scheduling 21 1. Schedule cleaning operations so that dust and other contaminants disturbed by 22 cleaning process will not fall on newly painted surfaces. 23 2. Schedule final cleaning upon completion of Work and immediately prior to final 24 inspection. 25 1.5 SUBMITTALS [NOT USED] 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE [NOT USED] 30 1.10 STORAGE,AND HANDLING 31 A. Storage and Handling Requirements 32 1. Store cleaning products and cleaning wastes in containers specifically designed for 33 those materials. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 7423-2 CLEANING Page 2 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2 - PRODUCTS 4 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 5 2.2 MATERIALS 6 A. Cleaning Agents 7 1. Compatible with surface being cleaned 8 2. New and uncontaminated 9 3. For manufactured surfaces 10 a. Material recommended by manufacturer 11 2.3 ACCESSORIES [NOT USED] 12 2.4 SOURCE QUALITY CONTROL [NOT USED] 13 PART 3- EXECUTION 14 3.1 INSTALLERS [NOT USED] 15 3.2 EXAMINATION [NOT USED] 16 3.3 PREPARATION [NOT USED] 17 3.4 APPLICATION [NOT USED] 18 3.5 REPAIR/RESTORATION [NOT USED] 19 3.6 RE-INSTALLATION [NOT USED] 20 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING 24 A. General 25 1. Prevent accumulation of wastes that create hazardous conditions. 26 2. Conduct cleaning and disposal operations to comply with laws and safety orders of 27 governing authorities. 28 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in 29 storm or sanitary drains or sewers. 30 4. Dispose of degradable debris at an approved solid waste disposal site. 31 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an 32 alternate manner approved by City and regulatory agencies. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 01 7423-3 CLEANING Page 3 of 4 1 6. Handle materials in a controlled manner with as few handlings as possible. 2 7. Thoroughly clean, sweep,wash and polish all Work and equipment associated with 3 this project. 4 8. Remove all signs of temporary construction and activities incidental to construction 5 of required permanent Work. 6 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to 7 have the cleaning completed at the expense of the Contractor. 8 10. Do not burn on-site. 9 B. Intermediate Cleaning during Construction 10 1. Keep Work areas clean so as not to hinder health, safety or convenience of 11 personnel in existing facility operations. 12 2. At maximum weekly intervals, dispose of waste materials,debris and rubbish. 13 3. Confine construction debris daily in strategically located container(s): 14 a. Cover to prevent blowing by wind 15 b. Store debris away from construction or operational activities 16 c. Haul from site at a minimum of once per week 17 4. Vacuum clean interior areas when ready to receive finish painting. 18 a. Continue vacuum cleaning on an as-needed basis,until Final Acceptance. 19 5. Prior to storm events,thoroughly clean site of all loose or unsecured items, which 20 may become airborne or transported by flowing water during the storm. 21 C. Interior Final Cleaning 22 1. Remove grease, mastic,adhesives,dust, dirt, stains, fingerprints, labels and other 23 foreign materials from sight-exposed surfaces. 24 2. Wipe all lighting fixture reflectors, lenses, lamps and trims clean. 25 3. Wash and shine glazing and mirrors. 26 4. Polish glossy surfaces to a clear shine. 27 5. Ventilating systems 28 a. Clean permanent filters and replace disposable filters if units were operated 29 during construction. 30 b. Clean ducts,blowers and coils if units were operated without filters during 31 construction. 32 6. Replace all burned out lamps. 33 7. Broom clean process area floors. 34 8. Mop office and control room floors. 35 D. Exterior(Site or Right of Way)Final Cleaning 36 1. Remove trash and debris containers from site. 37 a. Re-seed areas disturbed by location of trash and debris containers in accordance 38 with Section 32 92 13. 39 2. Sweep roadway to remove all rocks,pieces of asphalt,concrete or any other object 40 that may hinder or disrupt the flow of traffic along the roadway. 41 3. Clean any interior areas including,but not limited to,vaults, manholes, structures, 42 junction boxes and inlets. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July I,2011 01 7423-4 CLEANING Page 4 of 4 1 4. If no longer required for maintenance of erosion facilities,and upon approval by 2 City, remove erosion control from site. 3 5. Clean signs, lights, signals,etc. 4 3.11 CLOSEOUT ACTIVITIES [NOT USED] 5 3.12 PROTECTION [NOT USED] 6 3.13 MAINTENANCE [NOT USED] 7 3.14 ATTACHMENTS [NOT USED] 8 END OF SECTION 9 Revision Log DATE NAME SUMMARY OF CHANGE 10 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 77 19-1 CLOSEOUT REQUIREMENTS Pagel of 3 1 SECTION 0177 19 2 CLOSEOUT REQUIREMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedure for closing out a contract 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Guarantees,Bonds and Affidavits 19 1. No application for final payment will be accepted until all guarantees,bonds, 20 certificates, licenses and affidavits required for Work or equipment as specified are 21 satisfactorily filed with the City. 22 B. Release of Liens or Claims 23 1. No application for final payment will be accepted until satisfactory evidence of 24 release of liens has been submitted to the City. 25 1.5 SUBMITTALS 26 A. Submit all required documentation to City's Project Representative. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 77 19-2 CLOSEOUT REQUIREMENTS Page 2 of 3 1 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 CLOSEOUT PROCEDURE 9 A. Prior to requesting Final Inspection, submit: 10 1. Project Record Documents in accordance with Section 01 78 39 11 2. Operation and Maintenance Data,if required,in accordance with Section 01 78 23 12 B. Prior to requesting Final Inspection,perform final cleaning in accordance with Section 13 01 7423. 14 C. Final Inspection 15 1. After final cleaning,provide notice to the City Project Representative that the Work 16 is completed. 17 a. The City will make an initial Final Inspection with the Contractor present. 18 b. Upon completion of this inspection,the City will notify the Contractor,in 19 writing within 10 business days, of any particulars in which this inspection 20 reveals that the Work is defective or incomplete. 21 2. Upon receiving written notice from the City, immediately undertake the Work 22 required to remedy deficiencies and complete the Work to the satisfaction of the 23 City. 24 3. Upon completion of Work associated with the items listed in the City's written 25 notice, inform the City,that the required Work has been completed. Upon receipt 26 of this notice,the City,in the presence of the Contractor,will make a subsequent 27 Final Inspection of the project. 28 4. Provide all special accessories required to place each item of equipment in full 29 operation. These special accessory items include,but are not limited to: 30 a. Specified spare parts 31 b. Adequate oil and grease as required for the first lubrication of the equipment 32 c. Initial fill up of all chemical tanks and fuel tanks 33 d. Light bulbs 34 e. Fuses 35 f. Vault keys 36 g. Handwheels 37 h. Other expendable items as required for initial start-up and operation of all 38 equipment 39 D. Notice of Project Completion CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 77 19-3 CLOSEOUT REQUIREMENTS Page 3 of 3 1 1. Once the City Project Representative finds the Work subsequent to Final Inspection 2 to be satisfactory,the City will issue a Notice of Project Completion(Green Sheet). 3 E. Supporting Documentation 4 1. Coordinate with the City Project Representative to complete the following 5 additional forms: 6 a. Final Payment Request 7 b. Statement of Contract Time 8 c. Affidavit of Payment and Release of Liens 9 d. Consent of Surety to Final Payment 10 e. Pipe Report(if required) 11 f. Contractor's Evaluation of City 12 g. Performance Evaluation of Contractor 13 F. Letter of Final Acceptance 14 1. Upon review and acceptance of Notice of Project Completion and Supporting 15 Documentation,in accordance with General Conditions, City will issue Letter of 16 Final Acceptance and release the Final Payment Request for payment. 17 3.5 REPAIR/RESTORATION [NOT USED] 18 3.6 RE-INSTALLATION [NOT USED] 19 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 20 3.8 SYSTEM STARTUP [NOT USED] 21 3.9 ADJUSTING [NOT USED] 22 3.10 CLEANING [NOT USED] 23 3.11 CLOSEOUT ACTIVITIES [NOT USED] 24 3.12 PROTECTION [NOT USED] 25 3.13 MAINTENANCE [NOT USED] 26 3.14 ATTACHMENTS [NOT USED] 27 END OF SECTION 28 Revision Log DATE NAME SUMMARY OF CHANGE 29 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 78 23-1 OPERATION AND MAINTENANCE DATA Page 1 of 5 1 SECTION 0178 23 2 OPERATION AND MAINTENANCE DATA 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Product data and related information appropriate for City's maintenance and 7 operation of products furnished under Contract 8 2. Such products may include,but are not limited to: 9 a. Traffic Controllers 10 b. Irrigation Controllers(to be operated by the City) 11 c. Butterfly Valves 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include,but are not necessarily limited to: 15 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 16 2. Division 1 —General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Schedule 24 1. Submit manuals in final form to the City within 30 calendar days of product 25 shipment to the project site. 26 1.5 SUBMITTALS 27 A. Submittals shall be in accordance with Section 01 33 00 . All submittals shall be 28 approved by the City prior to delivery. 29 1.6 INFORMATIONAL SUBMITTALS 30 A. Submittal Form 31 1. Prepare data in form of an instructional manual for use by City personnel. 32 2. Format 33 a. Size: 8 '/2 inches x 11 inches 34 b. Paper 35 1) 40 pound minimum,white, for typed pages 36 2) Holes reinforced with plastic,cloth or metal 37 c. Text: Manufacturer's printed data,or neatly typewritten CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 017823-2 OPERATION AND MAINTENANCE DATA Page 2 of 5 1 d. Drawings 2 1) Provide reinforced punched binder tab,bind in with text 3 2) Reduce larger drawings and fold to size of text pages. 4 e. Provide fly-leaf for each separate product,or each piece of operating 5 equipment. 6 1) Provide typed description of product,and major component parts of 7 equipment. 8 2) Provide indexed tabs. 9 f. Cover 10 1) Identify each volume with typed or printed title"OPERATING AND 11 MAINTENANCE INSTRUCTIONS". 12 2) List: 13 a) Title of Project 14 b) Identity of separate structure as applicable 15 c) Identity of general subject matter covered in the manual 16 3. Binders 17 a. Commercial quality 3-ring binders with durable and cleanable plastic covers 18 b. When multiple binders are used,correlate the data into related consistent 19 groupings. 20 4. If available,provide an electronic form of the O&M Manual. 21 B. Manual Content 22 1. Neatly typewritten table of contents for each volume,arranged in systematic order 23 a. Contractor,name of responsible principal,address and telephone number 24 b. A list of each product required to be included,indexed to content of the volume 25 c. List,with each product: 26 1) The name,address and telephone number of the subcontractor or installer 27 2) A list of each product required to be included,indexed to content of the 28 volume 29 3) Identify area of responsibility of each 30 4) Local source of supply for parts and replacement 31 d. Identify each product by product name and other identifying symbols as set 32 forth in Contract Documents. 33 2. Product Data 34 a. Include only those sheets which are pertinent to the specific product. 35 b. Annotate each sheet to: 36 1) Clearly identify specific product or part installed 37 2) Clearly identify data applicable to installation 38 3) Delete references to inapplicable information 39 3. Drawings 40 a. Supplement product data with drawings as necessary to clearly illustrate: 41 1) Relations of component parts of equipment and systems 42 2) Control and flow diagrams 43 b. Coordinate drawings with information in Project Record Documents to assure 44 correct illustration of completed installation. 45 c. Do not use Project Record Drawings as maintenance drawings. 46 4. Written text,as required to supplement product data for the particular installation: 47 a. Organize in consistent format under separate headings for different procedures. 48 b. Provide logical sequence of instructions of each procedure. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 7823-3 OPERATION AND MAINTENANCE DATA Page 3 of 5 1 5. Copy of each warranty,bond and service contract issued 2 a. Provide information sheet for City personnel giving: 3 1) Proper procedures in event of failure 4 2) Instances which might affect validity of warranties or bonds 5 C. Manual for Materials and Finishes 6 1. Submit 5 copies of complete manual in final form. 7 2. Content, for architectural products, applied materials and finishes: 8 a. Manufacturer's data,giving full information on products 9 1) Catalog number, size,composition 10 2) Color and texture designations 11 3) Information required for reordering special manufactured products 12 b. Instructions for care and maintenance 13 1) Manufacturer's recommendation for types of cleaning agents and methods 14 2) Cautions against cleaning agents and methods which are detrimental to 15 product 16 3) Recommended schedule for cleaning and maintenance 17 3. Content, for moisture protection and weather exposure products: 18 a. Manufacturer's data,giving full information on products 19 1) Applicable standards 20 2) Chemical composition 21 3) Details of installation 22 b. Instructions for inspection,maintenance and repair 23 D. Manual for Equipment and Systems 24 1. Submit 5 copies of complete manual in final form. 25 2. Content, for each unit of equipment and system,as appropriate: 26 a. Description of unit and component parts 27 1) Function, normal operating characteristics and limiting conditions 28 2) Performance curves, engineering data and tests 29 3) Complete nomenclature and commercial number of replaceable parts 30 b. Operating procedures 31 1) Start-up,break-in,routine and normal operating instructions 32 2) Regulation,control, stopping, shut-down and emergency instructions 33 3) Summer and winter operating instructions 34 4) Special operating instructions 35 c. Maintenance procedures 36 1) Routine operations 37 2) Guide to "trouble shooting" 38 3) Disassembly, repair and reassembly 39 4) Alignment,adjusting and checking 40 d. Servicing and lubrication schedule 41 1) List of lubricants required 42 e. Manufacturer's printed operating and maintenance instructions 43 f. Description of sequence of operation by control manufacturer 44 1) Predicted life of parts subject to wear 45 2) Items recommended to be stocked as spare parts 46 g. As installed control diagrams by controls manufacturer 47 h. Each contractor's coordination drawings 48 1) As installed color coded piping diagrams CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 017823-4 OPERATION AND MAINTENANCE DATA Page 4 of 5 1 i. Charts of valve tag numbers,with location and function of each valve 2 j. List of original manufacturer's spare parts,manufacturer's current prices,and 3 recommended quantities to be maintained in storage 4 k. Other data as required under pertinent Sections of Specifications 5 3. Content, for each electric and electronic system,as appropriate: 6 a. Description of system and component parts 7 1) Function,normal operating characteristics,and limiting conditions 8 2) Performance curves,engineering data and tests 9 3) Complete nomenclature and commercial number of replaceable parts 10 b. Circuit directories of panelboards 11 1) Electrical service 12 2) Controls 13 3) Communications 14 c. As installed color coded wiring diagrams 15 d. Operating procedures 16 1) Routine and normal operating instructions 17 2) Sequences required 18 3) Special operating instructions 19 e. Maintenance procedures 20 1) Routine operations 21 2) Guide to "trouble shooting" 22 3) Disassembly,repair and reassembly 23 4) Adjustment and checking 24 f. Manufacturer's printed operating and maintenance instructions 25 g. List of original manufacturer's spare parts,manufacturer's current prices,and 26 recommended quantities to be maintained in storage 27 h. Other data as required under pertinent Sections of Specifications 28 4. Prepare and include additional data when the need for such data becomes apparent 29 during instruction of City's personnel. 30 1.7 CLOSEOUT SUBMITTALS [NOT USED] 31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 32 1.9 QUALITY ASSURANCE 33 A. Provide operation and maintenance data by personnel with the following criteria: 34 1. Trained and experienced in maintenance and operation of described products 35 2. Skilled as technical writer to the extent required to communicate essential data 36 3. Skilled as draftsman competent to prepare required drawings CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 7823-5 OPERATION AND MAINTENANCE DATA Page 5 of 5 1 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2- PRODUCTS [NOT USED] 5 PART 3 - EXECUTION [NOT USED] 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D.Johnson 1.5.A.1—title of section removed 8 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 01 78 39-1 PROJECT RECORD DOCUMENTS Page 1 of 4 1 SECTION 0178 39 2 PROJECT RECORD DOCUMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Work associated with the documenting the project and recording changes to project 7 documents, including: 8 a. Record Drawings 9 b. Water Meter Service Reports 10 c. Sanitary Sewer Service Reports 11 d. Large Water Meter Reports 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include,but are not necessarily limited to: 15 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 16 2. Division 1 —General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 23 1.5 SUBMITTALS 24 A. Prior to submitting a request for Final Inspection,deliver Project Record Documents to 25 City's Project Representative. 26 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE 30 A. Accuracy of Records 31 1. Thoroughly coordinate changes within the Record Documents,making adequate 32 and proper entries on each page of Specifications and each sheet of Drawings and 33 other Documents where such entry is required to show the change properly. 34 2. Accuracy of records shall be such that future search for items shown in the Contract 35 Documents may rely reasonably on information obtained from the approved Project 36 Record Documents. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 7839-2 PROJECT RECORD DOCUMENTS Page 2 of 4 1 3. To facilitate accuracy of records,make entries within 24 hours after receipt of 2 information that the change has occurred. 3 4. Provide factual information regarding all aspects of the Work,both concealed and 4 visible,to enable future modification of the Work to proceed without lengthy and 5 expensive site measurement, investigation and examination. 6 1.10 STORAGE AND HANDLING 7 A. Storage and Handling Requirements 8 1. Maintain the job set of Record Documents completely protected from deterioration 9 and from loss and damage until completion of the Work and transfer of all recorded 10 data to the final Project Record Documents. 11 2. In the event of loss of recorded data,use means necessary to again secure the data 12 to the City's approval. 13 a. In such case,provide replacements to the standards originally required by the 14 Contract Documents. 15 1.11 FIELD [SITE] CONDITIONS [NOT USED] 16 1.12 WARRANTY [NOT USED] 17 PART 2- PRODUCTS 18 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 19 2.2 RECORD DOCUMENTS 20 A. Job set 21 1. Promptly following receipt of the Notice to Proceed, secure from the City,at no 22 charge to the Contractor, 1 complete set of all Documents comprising the Contract. 23 B. Final Record Documents 24 1. At a time nearing the completion of the Work and prior to Final Inspection,provide 25 the City 1 complete set of all Final Record Drawings in the Contract. 26 2.3 ACCESSORIES [NOT USED] 27 2.4 SOURCE QUALITY CONTROL [NOT USED] 28 PART 3 - EXECUTION 29 3.1 INSTALLERS [NOT USED] 30 3.2 EXAMINATION [NOT USED] 31 3.3 PREPARATION [NOT USED] 32 3.4 MAINTENANCE DOCUMENTS 33 A. Maintenance of Job Set 34 1. Immediately upon receipt of the job set, identify each of the Documents with the 35 title, "RECORD DOCUMENTS -JOB SET". CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 01 7839-3 PROJECT RECORD DOCUMENTS Page 3 of 4 1 2. Preservation 2 a. Considering the Contract completion time,the probable number of occasions 3 upon which the job set must be taken out for new entries and for examination, 4 and the conditions under which these activities will be performed, devise a 5 suitable method for protecting the job set. 6 b. Do not use the job set for any purpose except entry of new data and for review 7 by the City,until start of transfer of data to final Project Record Documents. 8 c. Maintain the job set at the site of work. 9 3. Coordination with Construction Survey 10 a. At a minimum, in accordance with the intervals set forth in Section 0171 23, 11 clearly mark any deviations from Contract Documents associated with 12 installation of the infrastructure. 13 4. Making entries on Drawings 14 a. Record any deviations from Contract Documents. 15 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the 16 change by graphic line and note as required. 17 c. Date all entries. 18 d. Call attention to the entry by a "cloud" drawn around the area or areas affected. 19 e. In the event of overlapping changes,use different colors for the overlapping 20 changes. 21 5. Conversion of schematic layouts 22 a. In some cases on the Drawings,arrangements of conduits,circuits,piping, 23 ducts, and similar items,are shown schematically and are not intended to 24 portray precise physical layout. 25 1) Final physical arrangement is determined by the Contractor, subject to the 26 City's approval. 27 2) However,design of future modifications of the facility may require 28 accurate information as to the final physical layout of items which are 29 shown only schematically on the Drawings. 30 b. Show on the job set of Record Drawings,by dimension accurate to within 1 31 inch,the centerline of each run of items. 32 1) Final physical arrangement is determined by the Contractor, subject to the 33 City's approval. 34 2) Show,by symbol or note,the vertical location of the Item("under slab", "in 35 ceiling plenum", "exposed",and the like). 36 3) Make all identification sufficiently descriptive that it may be related 37 reliably to the Specifications. 38 c. The City may waive the requirements for conversion of schematic layouts 39 where, in the City's judgment,conversion serves no useful purpose. However, 40 do not rely upon waivers being issued except as specifically issued in writing 41 by the City. 42 B. Final Project Record Documents 43 1. Transfer of data to Drawings 44 a. Carefully transfer change data shown on the job set of Record Drawings to the 45 corresponding final documents,coordinating the changes as required. 46 b. Clearly indicate at each affected detail and other Drawing a full description of 47 changes made during construction,and the actual location of items. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 017839-4 PROJECT RECORD DOCUMENTS Page 4 of 4 1 c. Call attention to each entry by drawing a"cloud" around the area or areas 2 affected. 3 d. Make changes neatly,consistently and with the proper media to assure 4 longevity and clear reproduction. 5 2. Transfer of data to other Documents 6 a. If the Documents,other than Drawings,have been kept clean during progress of 7 the Work,and if entries thereon have been orderly to the approval of the City, 8 the job set of those Documents,other than Drawings,will be accepted as final 9 Record Documents. 10 b. If any such Document is not so approved by the City, secure a new copy of that 11 Document from the City at the City's usual charge for reproduction and 12 handling,and carefully transfer the change data to the new copy to the approval 13 of the City. 14 3.5 REPAIR/RESTORATION [NOT USED] 15 3.6 RE-INSTALLATION [NOT USED] 16 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES [NOT USED] 21 3.12 PROTECTION [NOT USED] 22 3.13 MAINTENANCE [NOT USED] 23 3.14 ATTACHMENTS [NOT USED] 24 END OF SECTION 25 Revision Log DATE NAME SUMMARY OF CHANGE 26 CITY OF FORT WORTH Dry Branch Creek Interim Rcional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 0241 13-1 SELECTIVE SITE DEMOLITION Page 1 of 3 1 SECTION 02 41 13 2 SELECTIVE SITE DEMOLITION 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Removing fences 7 2. Removing rip rap 8 3. Removing miscellaneous concrete structures including porches and foundations 9 4. Disposal of removed materials 10 B. Deviations this from City of Fort Worth Standard Specification 11 1. Some portions removed which were not applicable to this project. Additional 12 specifications added for this project. 13 C. Related Specification Sections include,but are not necessarily limited to: 14 1. Division 0—Bidding Requirements,Contract Forms,and Conditions of the 15 Contract 16 2. Division 1 —General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Measurement 20 a. Remove Fence: measure by the linear foot. 21 b. Remove Rip Rap: measure by the square foot. 22 c. Remove Miscellaneous Concrete Structure: measure by the lump sum. 23 2. Payment 24 a. Remove Fence: full compensation for removal, hauling,disposal,tools, 25 equipment, labor and incidentals needed to remove fence.For utility projects, 26 this Item shall be considered subsidiary to the trench and no other 27 compensation will be allowed. 28 b. Remove Rip Rap: full compensation for saw cutting,removal, hauling, 29 disposal, tools, equipment, labor and incidentals needed to execute work. For 30 utility projects,this Item shall be considered subsidiary to the trench and no 31 other compensation will be allowed. 32 c. Remove Miscellaneous Concrete Structure: full compensation for saw cutting, 33 removal, hauling, disposal,tools, equipment, labor and incidentals needed to 34 execute work. For utility projects,this Item shall be considered subsidiary to 35 the trench and no other compensation will be allowed. 36 1.3 REFERENCES 37 A. Definitions 38 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 39 1.5 SUBMITTALS [NOT USED] 40 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 0241 13-2 SELECTIVE SITE DEMOLITION Page 2 of 3 1 1.7 CLOSEOUT SUBMITTALS [NOT USED] 2 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 3 1.9 QUALITY ASSURANCE [NOT USED] 4 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 5 1.11 FIELD [SITE] CONDITIONS [NOT USED] 6 1.12 WARRANTY [NOT USED] 7 PART 2- PRODUCTS 8 2.1 OWNER-FURNISHED PRODUCTS [NOT USED] 9 2.2 MATERIALS 10 A. Fill Material: See Section 31 23 23. 11 2.3 ACCESSORIES [NOT USED] 12 2.4 SOURCE QUALITY CONTROL [NOT USED] 13 PART 3- EXECUTION 14 3.1 INSTALLERS [NOT USED] 15 3.2 EXAMINATION [NOT USED] 16 3.3 PREPARATION [NOT USED] 17 3.4 REMOVAL 18 A. Remove Fence 19 1. Remove all fence components above and below ground and backfill with acceptable 20 fill material. 21 2. Use caution in removing and salvaging fence materials. 22 3. Salvaged materials may be used to reconstruct fence as approved by City or as 23 shown on Drawings. 24 4. Contractor responsible for keeping animals(livestock,pets, etc.) within the fenced 25 areas during construction operation and while removing fences. 26 B. Remove Rip Rap 27 1. Remove rip rap to nearest existing dummy, expansion or construction joint. 28 2. Sawcut when removing to nearest joint is not practical. See 3A.K. 29 C. Remove Miscellaneous Concrete Structure 30 1. Remove portions of miscellaneous concrete structures including foundations and 31 slabs. 32 2. Backfill and compact as necessary to achieve proposed grade elevation. 33 D. Sawcut 34 1. Sawing Equipment 35 a. Power-driven 36 b. Manufactured for the purpose of sawing pavement CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 0241 13-3 SELECTIVE SITE DEMOLITION Page 3 of 3 1 c. In good operating condition 2 d. Shall not spall or fracture the pavement to the removal area 3 2. Sawcut perpendicular to the surface completely through existing pavement. 4 3.5 REPAIR [NOT USED] 5 3.6 RE-INSTALLATION [NOT USED] 6 3.7 SITE QUALITY CONTROL [NOT USED] 7 3.8 SYSTEM STARTUP [NOT USED] 8 3.9 ADJUSTING [NOT USED] 9 3.10 CLEANING [NOT USED] 10 3.11 CLOSEOUT ACTIVITIES [NOT USED] 11 3.12 PROTECTION [NOT USED] 12 3.13 MAINTENANCE [NOT USED] 13 3.14 ATTACHMENTS [NOT USED] 14 END OF SECTION 15 Revision Log DATE NAME SUMMARY OF CHANGE- 12/20/2012 D.Johnson 1.2.A.2.Modified Payment-Items will be subsidiary to trench on utility projects 16 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 0241 14-1 UTILITY REMOVAUABANDONMENT Pagel of 5 1 OSECTION 02 41 14 2 UTILITY REMOVAL/ABANDONMENT 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Direction for the removal, abandonment or salvaging of the following utilities: 7 a. Storm Sewer Lines 8 b. Headwalls and Safety End Treatments 9 B. Deviations from this City of Fort Worth Standard Specification 10 1. Some portions removed which were not applicable to this project. 11 C. Related Specification Sections include,but are not necessarily limited to: 12 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 13 2. Division 1 —General Requirements 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Utility Lines 16 1. Utility Line Removal, Same Trench 17 a. Measurement 18 1) This Item is considered subsidiary the proposed utility line being installed. 19 b. Payment 20 1) The work performed and materials furnished in accordance with this Item 21 are subsidiary to the installation of proposed utility pipe and shall be 22 subsidiary to the unit price bid per linear foot of pipe complete in place,and 23 no other compensation will be allowed. 24 B. Storm Sewer Lines and Appurtenances 25 1. Abandonment of Storm Sewer Line by Cut and installation of Abandonment Plug 26 a. Measurement 27 1) Measurement for this Item shall be per each cut and abandonment plug to 28 be installed. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this Item 31 and measured as provided under"Measurement" shall be paid for at the 32 unit price bid for each"Storm Abandonment Plug"installed for: 33 a) Various sizes 34 c. The price bid shall include: 35 1) Furnishing and installing abandonment plug 36 2) Pavement removal 37 3) Excavation 38 4) Hauling 39 5) CLSM 40 6) Disposal of excess material 41 7) Furnishing,placement and compaction of backfill CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Projet No.00485 Revised December 20,2012 024114-1 UTILITY REMOVAUABANDONMENT Pagel of 5 1 OSECTION 02 41 14 2 UTILITY REMOVAL/ABANDONMENT 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Direction for the removal,abandonment or salvaging of the following utilities: 7 a. Storm Sewer Lines 8 b. Headwalls and Safety End Treatments 9 B. Deviations from this City of Fort Worth Standard Specification 10 1. Some portions removed which were not applicable to this project. 11 C. Related Specification Sections include,but are not necessarily limited to: 12 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 13 2. Division 1 —General Requirements 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Utility Lines 16 1. Utility Line Removal, Same Trench 17 a. Measurement 18 1) This Item is considered subsidiary the proposed utility line being installed. 19 b. Payment 20 1) The work performed and materials furnished in accordance with this Item 21 are subsidiary to the installation of proposed utility pipe and shall be 22 subsidiary to the unit price bid per linear foot of pipe complete in place,and 23 no other compensation will be allowed. 24 B. Storm Sewer Lines and Appurtenances 25 1. Abandonment of Storm Sewer Line by Cut and installation of Abandonment Plug 26 a. Measurement 27 1) Measurement for this Item shall be per each cut and abandonment plug to 28 be installed. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this Item 31 and measured as provided under"Measurement"shall be paid for at the 32 unit price bid for each"Storm Abandonment Plug"installed for: 33 a) Various sizes 34 c. The price bid shall include: 35 1) Furnishing and installing abandonment plug 36 2) Pavement removal 37 3) Excavation 38 4) Hauling 39 5) CLSM 40 6) Disposal of excess material 41 7) Furnishing,placement and compaction of backfill CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Projet No.00485 Revised December 20,2012 0241 14-2 UTILITY REMOVAIJABANDONMENT Page 2 of 5 1 8) Clean-up 2 2. Headwall/SET Removal 3 a. Measurement 4 1) Measurement for this Item will be per each headwall or safety end 5 treatment(SET) to be removed. 6 b. Payment 7 1) The work performed and materials furnished in accordance with this Item 8 and measured as provided under"Measurement" shall be paid for at the 9 unit price bid per each"Remove Headwall/SET". 10 c. The price bid shall include: 11 1) Removal and disposal of Headwall/SET 12 2) Pavement removal 13 3) Excavation 14 4) Hauling 15 5) Disposal of excess materials 16 6) Furnishing,placement and compaction of backfill 17 7) Clean-up 18 1.3 REFERENCES [NOT USED] 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Coordination 21 1. Contact Inspector and the Water Department Field Operation Storage Yard for 22 coordination of salvage material return. 23 1.5 SUBMITTALS [NOT USED] 24 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 25 1.7 CLOSEOUT SUBMITTALS [NOT USED] 26 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 27 1.9 QUALITY ASSURANCE [NOT USED] 28 1.10 DELIVERY,STORAGE,AND HANDLING 29 A. Storage and Handling Requirements 30 1. Protect and salvage all materials such that no damage occurs during delivery to the 31 City. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Projet No.00485 Revised December 20,2012 0241 14-3 UTILITY REMOVAUABANDONMENT Page 3 of 5 1 1.111 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART2- PRODUCTS 4 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 5 2.2 MATERIALS 6 2.3 ACCESSORIES [NOT USED] 7 2.4 SOURCE QUALITY CONTROL [NOT USED] 8 PART 3 - EXECUTION 9 3.1 INSTALLERS [NOT USED] 10 3.2 EXAMINATION [NOT USED] 11 3.3 PREPARATION [NOT USED] 12 3.4 REMOVAL, SALVAGE, AND ABANDONMENT 13 A. General 14 1. Manhole Abandonment 15 a. Excavate and backfill in accordance with Section 33 05 10. 16 b. Backfill manhole void in accordance with City Standard Details. 17 B. Storm Sewer Lines and Appurtenances 18 1. Storm Sewer Line Removal 19 a. Excavate and backfill in accordance with Section 33 05 10. 20 b. Remove existing pipe line and properly dispose as approved by City. 21 2. Headwall/SET Removal 22 a. Excavate and backfill in accordance with Section 33 05 10. 23 b. Demolish and remove entire concrete inlet. 24 c. Cut and plug storm sewer lines to be abandoned. 25 3.5 REPAIR/RESTORATION [NOT USED] 26 3.6 RE-INSTALLATION [NOT USED] 27 3.7 FIELD [OR] SITE QUALITY CONTROL 28 3.8 SYSTEM STARTUP [NOT USED] 29 3.9 ADJUSTING [NOT USED] 30 3.10 CLEANING [NOT USED] 31 3.11 CLOSEOUT ACTIVITIES [NOT USED] 32 3.12 PROTECTION [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Projet No.00485 Revised December 20,2012 0241 14-4 UTILITY REMOVAL/ABANDONMENT Page 4 of 5 1 3.13 MAINTENANCE [NOT USED] 2 3.14 ATTACHMENTS [NOT USED] 3 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Projet No.00485 Revised December 20,2012 0241 14-5 UTILITY REMOVAUABANDONMENT Page 5 of 5 1 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 1.2.C.3.c.—Include Frame and Cover in Payment description 12/20/12 D.Johnson Throughout—added abandonment of storm and sewer manholes when requested and/or approved by City 2 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Projet No.00485 Revised December 20,2012 311000-1 SITE CLEARING Page 1 of 5 1 SECTION 31 10 00 2 SITE CLEARING 3 PART ] - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Preparation of right-of-way and other designated areas for construction operations 7 by removing and disposing of all obstructions including clearing and grubbing and 8 trees,when removal of such obstructions is not specifically shown on the Drawings 9 to be paid by other Sections. The City of Fort Worth's Urban Forestry Ordinance 10 governs all tree removals. 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. Some portions removed which were not applicable to this project. 13 C. Related Specification Sections include but are not necessarily limited to 14 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 15 2. Division 1 —General Requirements 16 3. Section 02 41 13 —Selective Site Demolition 17 4. Section 02 41 14—Utility Removal/Abandonment 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Site Clearing 21 a. Measurement 22 1) Measurement for this Item shall be by lump sum. 23 b. Payment 24 1) The work performed and the materials furnished in accordance with this 25 Item shall be paid for at the lump sum price bid for"Site Clearing". 26 c. The price bid shall include: 27 1) Pruning of designated trees and shrubs 28 2) Removal and disposal of structures and obstructions 29 3) Backfilling of holes 30 4) Clean-up 31 2. Tree Removal 32 a. Measurement 33 1) Measurement for this Item shall be lump sum. 34 b. Payment 35 1) The work performed and the materials furnished in accordance with this 36 Item shall be paid for at the unit price bid per each"Tree Removal"for: 37 a) Various caliper ranges 38 c. The price bid shall include: 39 1) Pruning of designated trees and shrubs 40 2) Removal and disposal of structures and obstructions 41 3) Grading and backfilling of holes CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 31 1000-2 SITE CLEARING Page 2 of 5 1 4) Excavation 2 5) Fertilization 3 6) Clean-up 4 1.3 REFERENCES [NOT USED] 5 1.4 ADMINSTRATIVE REQUIREMENTS 6 A. Permits 7 1. Contractor shall obtain Tree Removal Permits and Urban Forestry Permits as 8 required by the City's Tree Ordinance. (www.FortWorthTexas.gov) 9 B. Preinstallation Meetings 10 1. Hold a preliminary site clearing meeting and include the Contractor, City Arborist, 11 City Inspector, and the Project Manager for the purpose of reviewing the 12 Contractor's tree removal plan. Clearly mark all trees to remain on the project site 13 prior to the meeting. 14 2. The Contractor will provide the City with a Disposal Letter in accordance to 15 Division 01. 16 1.5 SUBMITTALS [NOT USED] 17 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 18 1.7 CLOSEOUT SUBMITTALS [NOT USED] 19 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 20 1.9 QUALITY ASSURANCE [NOT USED] 21 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 22 1.11 FIELD CONDITIONS [NOT USED] 23 1.12 WARRANTY [NOT USED] 24 PART 2- PRODUCTS [NOT USED] 25 PART 3 - EXECUTION 26 3.1 INSTALLERS [NOT USED] 27 3.2 EXAMINATION [NOT USED] 28 3.3 PREPARATION 29 A. All trees identified to be protected and/or preserved should be clearly flagged with 30 survey tape. 31 B. Following taping and prior to any removals or site clearing,the Contractor shall meet 32 with the City, the Engineer and the Landowner, if necessary,to confirm trees to be 33 saved. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 31 1000-3 SITE CLEARING Page 3 of 5 1 3.4 INSTALLATION 2 A. Protection of Trees 3 1. Protect designated trees and prune trees and shrubs as shown on the Drawings. 4 Refer to the Drawings for tree protection details. 5 2. If the Drawings do not provide tree protection details,protected trees shall be 6 fenced by placing 6-foot tall metal T-posts in a square around the tree trunk with 7 the corners located on the canopy drip line,unless instructed otherwise. 8 3. When site conditions do not allow for the T-posts to be installed at the drip line,the 9 T-posts may be installed no less than 8 feet from the tree trunk. 4-foot high 12 '/2 10 gauge stock fencing or orange plastic snow fence shall be attached to the T-posts to 11 form the enclosure. 12 4. Do not park equipment, service equipment, store materials, or disturb the root area 13 under the branches of trees designated for preservation. 14 5. When shown on the Drawings,treat cuts on trees with an approved tree wound 15 dressing within 20 minutes of making a pruning cut or otherwise causing damage to 16 the tree. 17 6. Trees and brush shall be mulched on-site. 18 a. Burning as a method of disposal is not allowed. 19 B. Hazardous Materials 20 1. The Contractor will notify the Engineer immediately if any hazardous or 21 questionable materials not shown on the Drawings are encountered. This includes; 22 but not limited to: 23 a. Floor tiles 24 b. Roof tiles 25 c. Shingles 26 d. Siding 27 e. Utility piping 28 2. The testing, removal, and disposal of hazardous materials will be in accordance 29 with Division 1. 30 C. Site Clearing 31 1. Clear areas shown on the Drawings of all obstructions, except those landscape 32 features that are to be preserved. Such obstructions include,but are not limited to: 33 a. Remains of buildings and other structures 34 b. Foundations 35 c. Floor slabs 36 d. Concrete 37 e. Brick 38 f. Lumber 39 g. Plaster 40 h. Septic tank drain fields 41 i. Abandoned utility pipes or conduits 42 j. Equipment 43 k. Trees 44 1. Fences 45 m. Retaining walls 46 n. Other items as specified on the Drawings CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 31 1000-4 SITE CLEARING Page 4 of 5 1 2. Remove vegetation and other landscape features not designated for preservation, 2 whether above or below ground, including,but not limited to: 3 a. Curb and gutter 4 b. Driveways 5 c. Paved parking areas 6 d. Miscellaneous stone 7 e. Sidewalks 8 f. Drainage structures 9 g. Manholes 10 h. Inlets 11 i. Abandoned railroad tracks 12 j. Scrap iron 13 k. Other debris 14 3. Remove culverts, storm sewers,manholes,and inlets in proper sequence to 15 maintain traffic and drainage in accordance with Section 02 41 14. 16 4. In areas receiving embankment, remove obstructions not designated for 17 preservation to 2 feet below natural ground. 18 5. In areas to be excavated, remove obstructions to 2 feet below the excavation level. 19 6. In all other areas, remove obstructions to l foot below natural ground. 20 7. When allowed by the Drawings or directed by the Engineer,cut trees and stumps 21 off to ground level. 22 a. Removal of existing structures shall be as per Section 02 41 13. 23 D. Disposal 24 1. Dispose of all trees within 24 hours of removal. 25 2. All materials and debris removed becomes the property of the Contractor,unless 26 otherwise stated on the Drawings. 27 3. The Contractor will dispose of material and debris off-site in accordance with local, 28 state, and federal laws and regulations. 29 3.5 REPAIR [NOT USED] 30 3.6 RE-INSTALLATION [NOT USED] 31 3.7 FIELD QUALITY CONTROL [NOT USED] 32 3.8 SYSTEM STARTUP [NOT USED] 33 3.9 ADJUSTING [NOT USED] 34 3.10 CLEANING [NOT USED] 35 3.11 CLOSEOUT ACTIVITIES [NOT USED] 36 3.12 PROTECTION [NOT USED] 37 3.13 MAINTENANCE [NOT USED] 38 3.14 ATTACHMENTS [NOT USED] 39 END OF SECTION CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 31 1000-5 SITE CLEARING Page 5 of 5 1 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D.Johnson 1.4.A Permits: Removed ordinance number and added City's website address 2 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 31 23 16-1 UNCLASSIFIED EXCAVATION Page 1 of 5 1 SECTION 3123 16 2 UNCLASSIFIED EXCAVATION 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Excavate areas as shown on the Drawings or as directed. Removal of materials 7 encountered to the lines, grades,and typical sections shown on the Drawings and 8 removal from site. Excavations may include construction of 9 a. Roadways 10 b. Drainage Channels 11 c. Site Excavation 12 d. Excavation for Structures 13 e. Or any other operation involving the excavation of on-site materials 14 B. Deviations from this City of Fort Worth Standard Specification 15 1. Some portions removed which were not applicable to this project. Additional 16 Specifications added for this project. 17 C. Related Specification Sections include,but are not necessarily limited to: 18 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 19 2. Division 1 —General Requirements 20 3. Section 3124 00—Embankments 21 1.2 PRICE AND PAYMENT PROCEDURES 22 A. Measurement and Payment 23 1. Excavation by Plan Quantity 24 a. Measurement 25 1) Measurement for this Item shall be by the cubic yard in its final position 26 using the average end area method. Limits of measurement are shown on 27 the Drawings. 28 2) When measured by the cubic yard in its final position,this is a plans 29 quantity measurement Item. The quantity to be paid is the quantity shown 30 in the proposal,unless modified by Article 11.04 of the General 31 Conditions. Additional measurements or calculations will be made if 32 adjustments of quantities are required. 33 3) Quantity was developed using Autodesk Civil 3d to compare the 34 existing topographic contours to the proposed contours. Civil 3d then 35 generates the volumetric difference between these two surfaces.4" 36 depth of top soil was added to this volume to obtain the total 37 unclassified excavation volume. 38 4) Contractor may reuse existing Top Soil or haul in new. 39 b. Payment CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised January 28,2013 31 23 16-2 UNCLASSIFIED EXCAVATION Page 2 of 5 1 1) The work performed and materials furnished in accordance with this Item 2 and measured as provided under"Measurement"will be paid for at the unit 3 price bid per cubic yard of"Unclassified Excavation by Plan". No 4 additional compensation will be allowed for rock or shrinkage/swell 5 factors, as these are the Contractor's responsibility. 6 c. The price bid shall include: 7 1) Excavation 8 2) Excavation Safety 9 3) Drying 10 4) Dust Control 11 5) Reworking or replacing the over excavated material in rock cuts 12 6) Hauling 13 7) Disposal of excess material not used elsewhere onsite 14 8) Scarification 15 9) Clean-up 16 1.3 REFERENCES [NOT USED] 17 A. Definitions 18 1. Unclassified Excavation—Without regard to materials, all excavations shall be 19 considered unclassified and shall include all materials excavated. Any reference to 20 Rock or other materials on the Drawings or in the specifications is solely for the 21 City and the Contractor's information and is not to be taken as a classification of 22 the excavation. 23 1.4 ADMINSTRATIVE REQUIREMENTS 24 A. The Contractor will provide the City with a Disposal Letter in accordance to Division 25 01. 26 1.5 SUBMITTALS [NOT USED] 27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 28 1.7 CLOSEOUT SUBMITTALS [NOT USED] 29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 30 1.9 QUALITY ASSURANCE 31 A. Excavation Safety 32 1. The Contractor shall be solely responsible for making all excavations in a safe 33 manner. 34 2. All excavation and related sheeting and bracing shall comply with the requirements 35 of OSHA excavation safety standards 29 CFR part 1926 and state requirements. 36 1.10 DELIVERY, STORAGE,AND HANDLING 37 A. Storage 38 1. Within Existing Rights-of-Way(ROW) 39 a. Soil may be stored within existing ROW, easements or temporary construction 40 easements,unless specifically disallowed in the Contract Documents. 41 b. Do not block drainage ways, inlets or driveways. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised January 28,2013 31 23 16-3 UNCLASSIFIED EXCAVATION Page 3 of 5 1 c. Provide erosion control in accordance with Section 3125 00. 2 d. When the Work is performed in active traffic areas, store materials only in 3 areas barricaded as provided in the traffic control plans. 4 e. In non-paved areas,do not store material on the root zone of any trees or in 5 landscaped areas. 6 2. Designated Storage Areas 7 a. If the Contract Documcnts do not allow the storage of spoils within the ROW, 8 easement or temporary construction easement,then secure and maintain an 9 adequate storage location. 10 b. Provide an affidavit that rights have been secured to store the materials on 11 private property. 12 c. Provide erosion control in accordance with Section 3125 00. 13 d. Do not block drainage ways. 14 1.11 FIELD CONDITIONS 15 A. Existing Conditions 16 1. Any data which has been or may be provided on subsurface conditions is not 17 intended as a representation or warranty of accuracy or continuity between soils. It 18 is expressly understood that neither the City nor the Engineer will be responsible 19 for interpretations or conclusions drawn there from by the Contractor. 20 2. Data is made available for the convenience of the Contractor. 21 1.12 WARRANTY [NOT USED] 22 PART 2- PRODUCTS [NOT USED] 23 2.1 OWNER-FURNISHED [NOT USED] 24 2.2 PRODUCT TYPES AND MATERIALS 25 A. Materials 26 1. Unacceptable Fill Material 27 a. In-situ soils classified as ML,MH,PT, OL or OH in accordance with ASTM 28 D2487 29 PART 3- EXECUTION 30 3.1 INSTALLERS [NOT USED] 31 3.2 EXAMINATION [NOT USED] 32 3.3 PREPARATION [NOT USED] 33 3.4 CONSTRUCTION 34 A. Accept ownership of unsuitable or excess material and dispose of material off-site 35 accordance with local, state, and federal regulations at locations. 36 B. Excavations shall be performed in the dry, and kept free from water, snow and ice 37 during construction with eh exception of water that is applied for dust control. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised January 28,2013 31 23 16-4 UNCLASSIFIED EXCAVATION Page 4 of 5 1 C. Separate Unacceptable Fill Material from other materials,remove from the Site and 2 properly dispose according to disposal plan. 3 D. Maintain drainage in the excavated area to avoid damage to the roadway sections and 4 proposed or existing structures. 5 E. Correct any damage to the subgrade caused by weather,at no additional cost to the 6 City. 7 F. Shape slopes to avoid loosening material below or outside the proposed grades. 8 Remove and dispose of slides as directed. 9 G. Rock Cuts 10 1. Excavate to finish grades. 11 2. In the event of over excavation due to contractor error below the lines and grades 12 established in the Drawings,use approved embankment material compacted in 13 accordance with Section 3124 00 to replace the over excavated at no additional 14 cost to City. 15 H. Earth Cuts 16 1. Excavate to finish subgrade 17 2. In the event of over excavation due to contractor error below the lines and grades 18 established in the Drawings,use approved embankment material compacted in 19 accordance with Section 3124 00 to replace the over excavated at no additional 20 cost to City. 21 3. Manipulate and compact subgrade in accordance with Section 3124 00. 22 3.5 REPAIR [NOT USED] 23 3.6 RE-INSTALLATION [NOT USED] 24 3.7 FIELD QUALITY CONTROL 25 A. Subgrade Tolerances 26 1. Excavate to within 0.1 foot in all directions. 27 2. In areas of over excavation,Contractor provides fill material approved by the City 28 at no expense to the City. 29 3.8 SYSTEM STARTUP [NOT USED] 30 3.9 ADJUSTING [NOT USED] 31 3.10 CLEANING [NOT USED] 32 3.11 CLOSEOUT ACTIVITIES [NOT USED] 33 3.12 PROTECTION [NOT USED] 34 3.13 MAINTENANCE [NOT USED] 35 3.14 ATTACHMENTS [NOT USED] 36 END OF SECTION Revision Log CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised January 28,2013 31 23 16-5 UNCLASSIFIED EXCAVATION Page 5 of 5 DATE NAME SUMMARY OF CHANGE 12/20/2012 D.Johnson 1.2-Measurement and Payment Section modified;Blue Text added for clarification 1/28/13 D.Johnson 1.2—Modified Bid Item names in payment section to differentiate between Payment Methods on bid list. 1 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised January 28,2013 312500-I EROSION AND SEDIMENT CONTROL Page 1 of 9 1 SECTION 3125 00 2 EROSION AND SEDIMENT CONTROL 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Implementation of the project's Storm Water Pollution Prevention Plan(SWPPP) 7 and installation, maintenance and removal of erosion and sediment control devices 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. Some portions removed which were not applicable to this project. 10 C. Related Specification Sections include, but are not necessarily limited to: 11 1. Division 0–Bidding Requirements,Contract Forms and Conditions of the Contract 12 2. Division 1 –General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Storm Water Pollution Prevention Plan>_ 1 acre 16 a. Measurement for this Item shall be by lump sum. 17 b. Payment 18 1) The work performed and the materials furnished in accordance with this 19 Item shall be paid for at the lump sum price bid for"SWPPP >_ 1 acre". 20 c. The price bid shall include: 21 1) Preparation of SWPPP 22 2) Implementation 23 3) Permitting fees 24 4) Installation 25 5) Maintenance 26 6) Removal 27 1.3 REFERENCES 28 A. Reference Standards 29 1. Reference standards cited in this Specification refer to the current reference 30 standard published at the time of the latest revision date logged at the end of this 31 Specification,unless a date is specifically cited. 32 2. ASTM Standard: 33 a. ASTM D3786, Standard Test Method for Bursting Strength of Textile 34 Fabrics—Diaphragm Bursting Strength Tester Method 35 b. ASTM D4632, Standard Test Method for Grab Breaking Load and Elongation 36 of Geotextiles 37 c. ASTM D4751, Standard Test Method for Determining Apparent Opening Size 38 of a Geotextile 39 d. ASTM D4833, Standard Test Method for Index Puncture Resistance of 40 Geomembranes and Related Products CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 312500-2 EROSION AND SEDIMENT CONTROL Page 2 of 9 1 3. Texas Commission on Environmental Quality(TCEQ)TPDES General Permit No. 2 TXR150000 3 4. TxDOT Departmental Material Specifications(DMS) 4 a. DMS-6230 "Temporary Sediment Control Fence Fabric" 5 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 6 1.5 SUBMITTALS 7 A. Storm Water Pollution Prevention Plan(SWPPP) 8 B. TCEQ Notice of Intent(NOI) for Storm Water Discharges Associated with 9 Construction Activity under the TPDES General Permit 10 C. Construction Site Notice 11 D. TCEQ Notice of Termination(NOT) for Storm Water Discharges Associated with 12 Construction Activity under the TPDES General Permit 13 E. Notice of Change(if applicable) 14 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 15 1.7 CLOSEOUT SUBMITTALS [NOT USED] 16 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 17 1.9 QUALITY ASSURANCE [NOT USED] 18 1.10 DELIVERY, STORAGE AND HANDLING [NOT USED] 19 1.11 FIELD [SITE] CONDITIONS [NOT USED] 20 1.12 WARRANTY [NOT USED] 21 PART 2 - PRODUCTS 22 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 23 2.2 PRODUCT TYPES AND MATERIALS 24 A. Rock Filter Dams 25 1. Aggregate 26 a. Furnish aggregate with hardness, durability, cleanliness and resistance to 27 crumbling, flaking and eroding acceptable to the Engineer. 28 b. Provide the following: 29 1) Types 1, 2 and 4 Rock Filter Dams 30 a) Use 3 to 6 inch aggregate. 31 2) Type 3 Rock Filter Dams 32 a) Use 4 to 8 inch aggregate. 33 2. Wire 34 a. Provide minimum 20 gauge galvanized wire for the steel wire mesh and tie 35 wires for Types 2 and 3 rock filter dams 36 b. Type 4 dams require: CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 312500-3 EROSION AND SEDIMENT CONTROL Page 3 of 9 1 1) Double-twisted, hexagonal weave with a nominal mesh opening of 21/2 2 inches x 3 '/ inches 3 2) Minimum 0.0866 inch steel wire for netting 4 3) Minimum 0.1063 inch steel wire for selvages and corners 5 4) Minimum 0.0866 inch for binding or tie wire 6 B. Geotextile Fabric 7 1. Place the aggregate over geotextile fabric meeting the following criteria: 8 a. Tensile Strength of 250 pounds,per ASTM D4632 9 b. Puncture Strength of 135 pounds,per ASTM D4833 10 c. Mullen Burst Rate of 420 psi,per ASTM D3786 11 d. Apparent Opening Size of No. 20(max),per ASTM D4751 12 C. Sandbag Material 13 1. Furnish sandbags meeting Section 2.5 except that any gradation of aggregate may 14 be used to fill the sandbags. 15 D. Stabilized Construction Entrances 16 1. Provide materials that meet the details shown on the Drawings and this Section. 17 a. Provide crushed aggregate for long and short-term construction exits. 18 b. Furnish aggregates that are clean,hard, durable and free from adherent coatings 19 such as salt, alkali, dirt, clay, loam, shale, soft or flaky materials and organic 20 and injurious matter. 21 c. Use 3 to 5 inch coarse aggregate with a minimum thickness of 12 inches. 22 d. The aggregate shall be placed over a geotextile fabric meeting the following; 23 criteria: 24 1) Tensile Strength of 300 pounds,per ASTM D4632 25 2) Puncture Strength of 120 pounds,per ASTM D4833 26 3) Mullen Burst Rate of 600 psi,per ASTM D3786 27 4) Apparent Opening Size of No. 40 (max),per ASTM D4751 28 E. Embankment for Erosion Control 29 1. Provide rock,loam,clay,topsoil or other earth materials that will form a stable 30 embankment to meet the intended use. 31 F. Sandbags 32 1. Provide sandbag material of polypropylene,polyethylene or polyamide woven 33 fabric with a minimum unit weight of 4 ounces per square yard,a Mullen burst 34 strength exceeding 300 psi,and an ultraviolet stability exceeding 70 percent. 35 2. Use natural coarse sand or manufactured sand meeting the gradation given in Table 36 1 to fill sandbags. 37 3. Filled sandbags must be 24 to 30 inches long, 16 to 18 inches wide, and 6 to 8 38 inches thick. 39 Table 1 40 Sand Gradation Sieve# Maximum Retained % by Weight) 4 3 percent 100 80 percent 200 95 percent 41 G. Temporary Sediment Control Fence CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 312500-4 EROSION AND SEDIMENT CONTROL Page 4 of 9 1 1. Provide a net-reinforced fence using woven geo-textile fabric. 2 2. Logos visible to the traveling public will not be allowed. 3 a. Fabric 4 1) Provide fabric materials in accordance with DMS-6230,"Temporary 5 Sediment Control Fence Fabric." 6 b. Posts 7 1) Provide essentially straight wood or steel posts with a minimum length of 8 48 inches,unless otherwise shown on the Drawings. 9 2) Soft wood posts must be at least 3 inches in diameter or nominal 2 x 4 inch 10 3) Hardwood posts must have a minimum cross-section of 1-1/2 x 1-1/2 inch 11 4) T-or L-shaped steel posts must have a minimum weight of 1.3 pounds per 12 foot. 13 c. Net Reinforcement 14 1) Provide net reinforcement of at least 12-1/2 gauge galvanized welded wire 15 mesh, with a maximum opening size of 2 x 4 inch, at least 24 inches wide, 16 unless otherwise shown on the Drawings. 17 d. Staples 18 1) Provide staples with a crown at least 3/4 inch wide and legs 1/2 inch long. 19 2.3 ACCESSORIES [NOT USED] 20 2.4 SOURCE QUALITY CONTROL [NOT USED] 21 PART 3- EXECUTION 22 3.1 INSTALLERS [NOT USED] 23 3.2 EXAMINATION [NOT USED] 24 3.3 PREPARATION [NOT USED] 25 3.4 INSTALLATION 26 A. Storm Water Pollution Prevention Plan 27 1. Develop and implement the project's Storm Water Pollution Prevention Plan 28 (SWPPP)in accordance with the TPDF.S Construction General Permit TXR150000 29 requirements. Prevent water pollution from storm water runoff by using and 30 maintaining appropriate structural and nonstructural BMPs to reduce pollutants 31 discharges to the MS4 from the construction site. 32 B. Control Measures 33 1. Implement control measures in the area to be disturbed before beginning 34 construction, or as directed. Limit the disturbance to the area shown on the 35 Drawings or as directed. 36 2. Control site waste such as discarded building materials,concrete truck washout 37 water, chemicals,litter and sanitary waste at the construction site. 38 3. If, in the opinion of the Engineer,the Contractor cannot control soil erosion and 39 sedimentation resulting from construction operations,the Engineer will limit the 40 disturbed area to that which the Contractor is able to control. Minimize disturbance 41 to vegetation. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 312500-5 EROSION AND SEDIMENT CONTROL Page 5 of 9 1 4. Immediately correct ineffective control measures. Implement additional controls as 2 directed. Remove excavated material within the time requirements specified in the 3 applicable storm water permit. 4 5. Upon acceptance of vegetative cover by the City,remove and dispose of all 5 temporary control measures,temporary embankments,bridges,matting, falsework, 6 piling, debris,or other obstructions placed during construction that are not a part of 7 the finished work, or as directed. 8 C. Do not locate disposal areas, stockpiles,or haul roads in any wetland,water body,or 9 streambed. 10 D. Do not install temporary construction crossings in or across any water body without the 11 prior approval of the appropriate resource agency and the Engineer. 12 E. Provide protected storage area for paints,chemicals, solvents,and fertilizers at an 13 approved location. Keep paints, chemicals,solvents,and fertilizers off bare ground and 14 provide shelter for stored chemicals. 15 F. Installation and Maintenance 16 1. Perform work in accordance with the TPDES Construction General Permit 17 TXR150000. 18 2. When approved, sediments may be disposed of within embankments, or in areas 19 where the material will not contribute to further siltation. 20 3. Dispose of removed material in accordance with federal, state,and local 21 regulations. 22 4. Remove devices upon approval or when directed. 23 a. Upon removal,finish-grade and dress the area. 24 b. Stabilize disturbed areas in accordance with the permit,and as shown on the 25 Drawings or directed. 26 5. The Contractor retains ownership of stockpiled material and must remove it from 27 the project when new installations or replacements are no longer required. 28 G. Rock Filter Dams for Erosion Control 29 1. Remove trees,brush, stumps and other objectionable material that may interfere 30 with the construction of rock filter dams. 31 2. Place sandbags as a foundation when required or at the Contractor's option. 32 3. For Types 1,2, 3,and 5,place the aggregate to the lines,height,and slopes 33 specified,without undue voids. 34 4. For Types 2 and 3,place the aggregate on the mesh and then fold the mesh at the 35 upstream side over the aggregate and secure it to itself on the downstream side with 36 wire ties, or hog rings,or as directed. 37 5. Place rock filter dams perpendicular to the flow of the stream or channel unless 38 otherwise directed. 39 6. Construct filter dams according to the following criteria,unless otherwise shown on 40 the Drawings: 41 a. Type 1 (Non-reinforced) 42 1) Height-At least 18 inches measured vertically from existing ground to top 43 of filter dam 44 2) Top Width-At least 2 feet 45 3) Slopes -At most 2:1 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 312500-6 EROSION AND SEDIMENT CONTROL Page 6 of 9 1 b. Type 2 (Reinforced) 2 1) Height-At least 18 inches measured vertically from existing ground to top 3 of filter dam 4 2) Top Width-At least 2 feet 5 3) Slopes-At most 2:1 6 c. Type 3 (Reinforced) 7 1) Height -At least 36 inches measured vertically from existing ground to top 8 of filter dam 9 2) Top Width-At least 2 feet 10 3) Slopes -At most 2:1 11 d. Type 4(Sack Gabions) 12 1) Unfold sack gabions and smooth out kinks and bends. 13 2) For vertical filling,connect the sides by lacing in a single loop—double loop 14 pattern on 4-to 5-inches spacing. At 1 end,pull the end lacing rod until 15 tight, wrap around the end,and twist 4 times. At the filling end, fill with 16 stone,pull the rod tight, cut the wire with approximately 6 inches 17 remaining,and twist wires 4 times. 18 3) For horizontal filling,place sack flat in a filling trough, fill with stone,and 19 connect sides and secure ends as described above. 20 4) Lift and place without damaging the gabion. 21 5) Shape sack gabions to existing contours. 22 e. Type 5 23 1) Provide rock filter dams as shown on the Drawings. 24 H. Construction Entrances 25 1. When tracking conditions exist,prevent traffic from crossing or exiting the 26 construction site or moving directly onto a public roadway, alley, sidewalk,parking 27 area,or other right of way areas other than at the location of construction entrances. 28 2. Place the exit over a foundation course,if necessary. 29 a. Grade the foundation course or compacted subgrade to direct runoff from the 30 construction exits to a sediment trap as shown on the Drawings or as directed. 31 3. At drive approaches,make sure the construction entrance is the full width of the 32 drive and meets the length shown on the Drawings. 33 a. The width shall beat least 14 feet for 1-way and 24 feet for 2-way traffic for all 34 other points of ingress or egress or as directed by the Engineer. 35 I. Earthwork for Erosion Control 36 1. Perform excavation and embankment operations to minimize erosion and to remove 37 collected sediments from other erosion control devices. 38 a. Excavation and Embankment for Erosion Control Measures 39 1) Place earth dikes, swales or combinations of both along the low crown of 40 daily lift placement,or as directed,to prevent runoff spillover. 41 2) Place swales and dikes at other locations as shown on the Drawings or as 42 directed to prevent runoff spillover or to divert runoff. 43 3) Construct cuts with the low end blocked with undisturbed earth to prevent 44 erosion of hillsides. 45 4) Construct sediment traps at drainage structures in conjunction with other 46 erosion control measures as shown on the Drawings or as directed. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 312500-7 EROSION AND SEDIMENT CONTROL Page 7 of 9 1 5) Where required,create a sediment basin providing 3,600 cubic feet of 2 storage per acre drained,or equivalent control measures for drainage 3 locations that serve an area with 10 or more disturbed acres at 1 time,not 4 including offsite areas. 5 b. Excavation of Sediment and Debris 6 1) Remove sediment and debris when accumulation affects the performance of 7 the devices,after a rain,and when directed. 8 J. Sandbags for Erosion Control 9 1. Construct a berm or dam of sandbags that will intercept sediment-laden storm water 10 runoff from disturbed areas,create a retention pond, detain sediment and release 11 water in sheet flow. 12 2. Fill each bag with sand so that at least the top 6 inches of the bag is unfilled to 13 allow for proper tying of the open end. 14 3. Place the sandbags with their tied ends in the same direction. 15 4. Offset subsequent rows of sandbags 1/2 the length of the preceding row. 16 5. Place a single layer of sandbags downstream as a secondary debris trap. 17 6. Place additional sandbags as necessary or as directed for supplementary support to 18 berms or dams of sandbags or earth. 19 K. Temporary Sediment-Control Fence 20 1. Provide temporary sediment-control fence near the downstream perimeter of a 21 disturbed area to intercept sediment from sheet flow. 22 2. Incorporate the fence into erosion-control measures used to control sediment in 23 areas of higher flow.Install the fence as shown on the Drawings,as specified in this 24 Section,or as directed. 25 a. Post Installation 26 1) Embed posts at least 18 inches deep,or adequately anchor, if in rock,with a 27 spacing of 6 to 8 feet and install on a slight angle toward the run-off source. 28 b. Fabric Anchoring 29 1) Dig trenches along the uphill side of the fence to anchor 6 to 8 inches of 30 fabric. 31 2) Provide a minimum trench cross-section of 6 x 6 inches 32 3) Place the fabric against the side of the trench and align approximately 2 33 inches of fabric along the bottom in the upstream direction. 34 4) Backfill the trench,then hand-tamp. 35 c. Fabric and Net Reinforcement Attachment 36 1) Unless otherwise shown under the Drawings, attach the reinforcement to 37 wooden posts with staples,or to steel posts with T-clips, in at least 4 places 38 equally spaced. 39 2) Sewn vertical pockets may be used to attach reinforcement to end posts. 40 3) Fasten the fabric to the top strand of reinforcement by hog rings or cord 41 every 15 inches or less. 42 d. Fabric and Net Splices 43 1) Locate splices at a fence post with a minimum lap of 6 inches attached in at 44 least 6 places equally spaced,unless otherwise shown under the Drawings. 45 a) Do not locate splices in concentrated flow areas. 46 2) Requirements for installation of used temporary sediment-control fence 47 include the following: CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 312500-8 EROSION AND SEDIMENT CONTROL Page 8 of 9 1 a) Fabric with minimal or no visible signs of biodegradation(weak fibers) 2 b) Fabric without excessive patching(more than 1 patch every 15 to 20 3 feet) 4 c) Posts without bends 5 d) Backing without holes 6 3.5 REPAIRIRESTORATION [NOT USED] 7 3.6 RE-INSTALLATION [NOT USED] 8 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 9 3.8 SYSTEM STARTUP [NOT USED] 10 3.9 ADJUSTING [NOT USED] 11 3.10 CLEANING 12 A. Waste Management 13 1. Remove sediment, debris and litter as needed. 14 3.11 CLOSEOUT ACTIVITIES 15 A. Erosion control measures remain in place and are maintained until all soil disturbing 16 activities at the project site have been completed. 17 B. Establish a uniform vegetative cover with a density of 70 percent on all unpaved areas, 18 on areas not covered by permanent structures,or in areas where permanent erosion 19 control measures(i.e. riprap, gabions,or geotextiles)have been employed. 20 3.12 PROTECTION [NOT USED] 21 3.13 MAINTENANCE 22 A. Install and maintain the integrity of temporary erosion and sedimentation control 23 devices to accumulate silt and debris until earthwork construction and permanent 24 erosion control features are in place or the disturbed area has been adequately stabilized 25 as determined by the Engineer. 26 B. If a device ceases to function as intended,repair or replace the device or portions 27 thereof as necessary. 28 C. Perform inspections of the construction site as prescribed in the Construction General 29 Permit TXR150000. 30 D. Records of inspections and modifications based on the results of inspections must be 31 maintained and available in accordance with the permit. 32 3.14 ATTACHMENTS [NOT USED] 33 END OF SECTION 34 Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 312500-9 EROSION AND SEDIMENT CONTROL Page 9 of 9 1 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 313700-1 RIPRAP Page 1 of 10 1 SECTION 3137 00 2 RIPRAP 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Furnishing and installing concrete,stone, cement-stabilized, or special riprap. 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Some portions removed which were not applicable to this project. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 3. Section 03 30 00—Cast-In-Place Concrete 13 4. Section 3125 00—Erosion and Sediment Control 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Measurement 17 a. Measurement for this Item shall be by the face square yard to the depth 18 specified of material complete in place.Volume will be computed on the basis 19 of the measured area and type,verified by field measurements. 20 2. Payment 21 a. The work performed and materials furnished in accordance with this Item and 22 measured as provided under"Measurement"will be paid for at the unit price 23 bid per square yard of"Riprap"installed for: 24 1) Various types 25 2) Various thicknesses 26 3) Various void-filling techniques 27 3. The price bid shall include: 28 a. Furnishing,hauling,and placing riprap 29 b. Filter fabric 30 c. Expansion joint material 31 d. Concrete and reinforcing steel 32 e. Excavation of toe wall trenches,as applicable 33 f. Excavation below natural ground or bottom of excavated channel,as applicable 34 g. Shaping of slopes,as applicable 35 h. Bedding 36 i. Grout and mortar 37 j. Scales 38 k. Test weights 39 1. Clean-up 40 1.3 REFERENCES 41 A. Reference Standards CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 313700-2 RIPRAP Page 2 of 10 1 1. Reference standards cited in this Specification refer to the current reference 2 standard published at the time of the latest revision date logged at the end of this 3 Specification,unless a date is specifically cited. 4 2. ASTM Standards 5 a. ASTM C136-06, Standard Test Method for Sieve Analysis of Fine and Coarse 6 Aggregates 7 b. ASTM D7370-09, Standard Test Method for Determination of Relative Density 8 and Absorption of Fine, Coarse,and Blended Aggregate Using Combined 9 Vacuum Saturation and Rapid Submersion 10 c. ASTM C5240-04, Standard Test Method for,Testing Rock Slabs to Evaluate 11 the Soundness of Riprap by Use of Sodium Sulfate or Magnesium Sulfate 12 d. ASTM D4632-08, Standard Test Method for Grab Breaking Load and 13 Elongation of Geotextiles 14 e. ASTM D4533-04, Standard Test Method for Trapezoid Tearing Strength of 15 Geotextiles 16 f. ASTM D751-06, Standard Test Methods for Coated Fabrics 17 g. ASTM D4751-04, Standard Test Method for Determining Apparent Opening 18 Size of a Geotextile 19 h. ASTM D4491-99a, Standard Test Methods for Water Permeability of 20 Geotextiles by Permittivity 21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 22 1.5 SUBMITTALS [NOT USED] 23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 24 1.7 CLOSEOUT SUBMITTALS [NOT USED] 25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 26 1.9 QUALITY ASSURANCE [NOT USED] 27 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 28 1.11 FIELD CONDITIONS [NOT USED] 29 1.12 WARRANTY [NOT USED] 30 PART 2- PRODUCTS 31 2.1 OWNER-FURNISHED [NOT USED] 32 2.2 PRODUCT TYPES AND MATERIALS 33 A. Concrete Riprap 34 1. Use concrete with a compressive strength of 4,000 psi at 28-days,according to 35 Section 03 30 00,unless otherwise shown on the Drawings. 36 B. Stone Riprap 37 1. Unless otherwise shown on the Drawings,use durable natural stone with a 38 minimum bulk specific gravity of 2. Provide stone that has a maximum weight loss 39 of 18 percent after 5 cycles of magnesium sulfate solution and 14 percent after 5 40 cycles of sodium sulfate solution. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 313700-3 RIPRAP Page 3 of 10 1 2. For all types of stone riprap perform a size verification test on the first 5,000 square 2 yards of finished riprap stone at a location determined by the Engineer. Weigh each 3 stone in a square test area with the length of each side of the square equal to 3 times 4 the specified riprap thickness.The weight of the stones, excluding spalls, should be 5 as specified below. Additional tests may be required. Do not place additional riprap 6 until the initial 5,0OO square yards of riprap has been approved. 7 3. When specified,provide grout and mortar as defined as 1 part Portland cement to 3 8 parts sand and mixed with water until it achieves a consistency that will flow into 9 and completely fill all voids. 10 4. Provide filter fabric in accordance with Section 3125 00. For slab riprap,provide 11 the filter fabric type shown on the Drawings 12 a. Large 13 1) Use stones between 50 and 250 pounds with a minimum of 50 percent of 14 the stones heavier than 100 pounds 15 b. Medium 16 1) Use stones between 50 and 250 pounds with a minimum of 40 percent of 17 the stones heavier than 100 pounds Use stones with at least 1 broad flat 18 surface. 19 c. Block 20 1) Use stones between 50 and 250 pounds. Use stones that are at least 3 inches 21 in their least dimension. Use stones that are at least twice as wide as they 22 are thick. When shown on the Drawings or approved,material may consist 23 of broken concrete removed under the Contract or from other approved 24 sources. Before placement of each piece of broken concrete, cut exposed 25 reinforcement flush with all surfaces. 26 d. Slab 27 1) Use boulders or quarried rock that meets the gradation requirements of 28 Table 1. Both the width and the thickness of each piece of riprap must be a 29 least 1/3 of the length. When shown on the Drawings or as approved, 30 material may consist of broken concrete removed under the Contract or 31 from other approved sources. Before placement of each piece of broken 32 concrete, cut exposed reinforcement flush with all surfaces. 33 2) Provide bedding stone that in-place meets the gradation requirements 34 shown in Table 2 or as otherwise shown on the Drawings. 35 Table 1 36 Ri ra Gradation Re uirements Thickness Maximum Size 90 percent Size' 50& Size' 8 percent Size, lb. lb. lb. Minimum lb. 12 in. 200 80-180 30-75 3 15in. 320 170-300 60-165 20 18i:.. 530 290-475 105-220 22 21 in. 800 460-720 175-300 25 24in. 1,000 550-850 200-325 30 30in. 2,600 1,150-2.50 400-900 40 37 38 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 313700-4 RIPRAP Page 4 of 10 1 Table 2 2 Bedding Stone Gradation Sieve Size(Square Mesh Percent by Weight Passing 3 inches 100 1-1/2 inches 50-80 3/4 inches 20-60 No. 4 0-15 No. 10 0-5 3 C. Special Riprap 4 1. Furnish materials for special riprap according to the Drawings. 5 2.3 ASSEMBLY OR FABRICATION TOLERANCES [NOT USED] 6 2.4 ACCESSORIES [NOT USED] 7 2.5 SOURCE QUALITY CONTROL [NOT USED] 8 PART 3- EXECUTION 9 3.1 INSTALLERS [NOT USED] 10 3.2 EXAMINATION [NOT USED] 11 3.3 PREPARATION [NOT USED] 12 3.4 INSTALLATION 13 A. Dress slopes and protected areas to the line and grade shown on the Drawings before 14 the placement of riprap. Place riprap and toe walls according to details and dimensions 15 shown on the Drawings or as directed by the Engineer. 16 B. Concrete Riprap 17 1. Reinforce concrete riprap with No. 3 reinforcing bars spaced at a maximum of 18 18 inches in each direction unless otherwise shown.Provide a minimum 6-inch lap at 19 all splices. At the edge of the riprap,provide a minimum horizontal cover of 1 inch 20 and a maximum cover of 3 inches. Place the first parallel bar at most 6 inches from 21 the edge of concrete.Use approved supports to hold the reinforcement 22 approximately equidistant from the top and bottom surface of the slab. Adjust 23 reinforcement during concrete placement to maintain correct position. 24 2. As directed, sprinkle or sprinkle and consolidate the subgrade before the concrete is 25 placed. All surfaces must be moist when concrete is placed. 26 3. Compact each layer to a minimum of 95 percent standard proctor density with a 27 moisture content not to exceed+4 percent or-2 percent of optimum moisture or as 28 indicated on the Drawings. 29 4. After placing the concrete,compact and shape it to conform to the dimensions 30 shown on Drawings. After it has set sufficiently to avoid slumping, finish the 31 surface with a wood float to secure a smooth surface or broom finish as approved. 32 5. Immediately after the finishing operation,cure the riprap according to Section 03 33 3000. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 313700-5 RIPRAP Page 5 of 10 1 C. Stone Riprap 2 1. Provide the following types of stone riprap when shown on the Drawings. 3 a. Dry Riprap 4 1) Dry riprap is stone riprap with voids filled with only spalls or small stones. 5 b. Grouted Riprap 6 1) Grouted riprap is Type Large,Medium,or Block stone riprap with voids 7 grouted after all the stones are in place. 8 c. Mortared Riprap 9 1) Mortared riprap is Medium stone riprap laid and mortared as each stone is 10 placed. 11 2. Use spalls and small stones lighter than 25 pounds to fill open joints and voids in 12 stone riprap, and place to a tight fit. 13 3. Do not place mortar or grout when the air temperature is below 35 degrees 14 Fahrenheit. 15 4. Protect work from rapid drying for at least 3 days after placement.Unless otherwise 16 approved,place filter fabric with the length running up and down the slope. Ensure 17 fabric has a minimum overlap of 2 feet. 18 5. Secure fabric with nails or pins.Use nails at least 2 inches long with washers or U- 19 shaped pins with legs at least 9 inches long. Space nails or pins at a maximum of 10 20 feet in each direction and 5 feet along the seams. Alternative anchorage and spacing 21 may be used when approved. 22 6. Large 23 a. Construct riprap as shown in Figure 1 and as shown on the Drawings. Place 24 stones in a single layer with close joints so that most of their weight is carried 25 by the earth and not by the adjacent stones. 26 b. Place the upright axis of the stones at an angle of approximately 90 degrees to 27 the embankment slope. 28 c. Place each course from the bottom of the embankment upward with the larger 29 stones in the lower courses. 30 d. Fill open joints between stones with spalls. 31 e. Place stones to create a uniform finished top surface.Do not exceed a 6-inch 32 variation between the tops of adjacent stones. Replace, embed deeper, or chip 33 away stones that project more than the allowable amount above the finished 34 surface. 35 f. When the Drawings require Large stone riprap to be grouted,prevent earth, 36 sand, or foreign material from filling the spaces between the stones. After the 37 stones are in place,thoroughly wet the stones, fill the spaces between the stones 38 with grout, and pack. Sweep the surface of the riprap with a stiff broom after 39 grouting. 40 7. Medium 41 a. Dry Placement 42 1) Construct riprap as shown in Figure 2. Set the flat surface on a prepared 43 horizontal earth bed,and overlap the underlying course to secure a lapped 44 surface. 45 2) Place the large stones first,roughly arranged in close contact. Fill the 46 spaces between the large stones with suitably sized stones placed to leave 47 the surface evenly stepped and conforming to the contour required. 48 3) Place stone to drain water down the face of the slope. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 313700-6 RIPRAP Page 6 of 10 1 b. Grouting 2 1) Construct riprap as shown in Figure 3. Size, shape,and lay large flat- 3 surfaced stones to produce an even surface with minimal voids. 4 2) Place stones with the flat surface facing upward parallel to the slope. Place 5 the largest stones near the base of the slope. 6 3) Fill spaces between the larger stones with stones of suitable size, leaving 7 the surface smooth,tight, and conforming to the contour required. 8 4) Place the stones to create a plane surface with a maximum variation of 6 9 inches in 10 feet from true plane. Provide the same degree of accuracy for 10 warped and curved surfaces. 11 5) Prevent earth, sand or foreign material from filling the spaces between the 12 stones. After the stones are in place,thoroughly wet them, fill the spaces 13 between them with grout,and pack. Sweep the surface with a stiff broom 14 after grouting. 15 c. Mortaring 16 1) Construct riprap as shown in Figure 2. Lap courses as described for dry 17 placement. Before placing mortar,wet the stones thoroughly. 18 2) As the larger stones are placed,bed them in fresh mortar and shove 19 adjacent stones into contact with one another. 20 3) After completing the work, spread all excess mortar forced out during 21 placement of the stones uniformly over them to fill all voids completely. 22 Point up all joints roughly either with flush joints or with shallow, smooth- 23 raked joints as directed. 24 D. Block 25 1. Construct riprap as shown in Figure 4. Place stones on a bed excavated for the base 26 course. Bed the base course of stone well into the ground with the edges in contact. 27 Bed and place each succeeding course in even contact with the preceding course. 28 2. Use spalls and small stones to fill any open joints and voids in the riprap. Ensure 29 the finished surface presents an even,tight surface,true to the line and grades of the 30 typical sections. 31 3. When the Drawings require grouting Block stone riprap,prevent earth, sand,or 32 foreign material from filling the spaces between the stones. After the stones are in 33 place,wet them thoroughly, fill the spaces between them with grout,and pack. 34 Sweep the surface with a stiff broom after grouting. 35 E. Slab 36 1. Construct riprap as shown in Figure 5. Place riprap stone on the slopes within the 37 limits shown on the Drawings. Place stone for riprap on the bedding material to 38 produce a reasonably well-graded mass of riprap with the minimum practicable 39 percentage of voids. 40 2. Construct the riprap to the lines and grades shown on the Drawings or staked in the 41 field. A tolerance of+6 inches and-0 inch from the slope line and grades shown on 42 the Drawings is allowed in the finished surface of the riprap. 43 3. Place riprap to its full thickness in a single operation.Avoid displacing the bedding 44 material. Ensure that the entire mass of stones in their final position is free from 45 objectionable pockets of small stones and clusters of larger stones. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 313700-7 RIPRAP Page 7 of 10 1 4. Do not place riprap in layers,and do not place it by dumping it into chutes, 2 dumping it from the top of the slope,pushing it from the top of the slope, or any 3 method likely to cause segregation of the various sizes. 4 5. Obtain the desired distribution of the various sizes of stones throughout the mass by 5 selective loading of material at the quarry or other source or by other methods of 6 placement that will produce the specified results. 7 6. Rearrange individual stones by mechanical equipment or by hand if necessary to 8 obtain a reasonably well-graded distribution of stone sizes. 9 F. Special Riprap 10 1. Construct special riprap according to the Drawings. 11 3.5 REPAIR [NOT USED] 12 3.6 RE-INSTALLATION [NOT USED] 13 3.7 FIELD QUALITY CONTROL [NOT USED] 14 3.8 SYSTEM STARTUP [NOT USED] 15 3.9 ADJUSTING [NOT USED] 16 3.10 CLEANING [NOT USED] 17 3.11 CLOSEOUT ACTIVITIES [NOT USED] 18 3.12 PROTECTION [NOT USED] 19 3.13 MAINTENANCE [NOT USED] 20 3.14 ATTACHMENTS 21 _ V 22 23 24 25 Grout when es specified 26 ?� w 27 9" min- 28 Slope of embankment 29 Upright axes of stone 30 s perpendicular to slope i 1'4" min 31 32 33 Figure 1 -Large stone riprap, dry or grouted. 34 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 313700-8 RIPRAP Page 8 of 10 1 2 3 4 Grout when specified 5 Flat side up 7� 6 9" min 7 Slope of embankment 8 9 s c 10 E T-6" min 11 12 Figure 2 -Medium stone riprap, dry or grouted. 13 14 15 16 17 Mortar when 18 specified �. 19 r►� N 20 Slope of 21 embankment 22 23 24 a 1'-6" min 25 26 27 Figure 3 -Medium stone riprap,mortared. 28 29 30 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 31 3700-9 RIPRAP Page 9 of 10 Grout when specified Multiple layers (more than one rock depth) g. few M min Slope of embankment E V-6" min r 1 2 Figure 4-Block stone riprap, dry or grouted. 3 f� a� Slope of M 'e esibankment memo Filter fabric ze ft.w Y t } 2 tinges thickness min 4 - - 5 Figure 5-Slab stone riprap 6 7 END OF SECTION CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 31 3700-10 RIPRAP Page 10 of 10 1 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D. Johnson 3A.B.—defined compaction requirements beneath concrete rip rap 2 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3231 13-1 CHAIN LINK FENCE AND GATES Page I of 7 1 SECTION 32 31 13 2 CHAIN LINK FENCE AND GATES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Galvanized coated chain link(non-security) fencing and accessories in accordance 7 with the City's Zoning Ordinance. 8 2. Wrought iron fencing and accessories 9 3. Steel tube fencing and accessories 10 4. On utility projects: 11 a. When existing fence is within the project Site(i.e. parallel to the utility trench 12 and/or within utility easement)and is directly disturbed by construction 13 activities, fencing will be paid for as listed in Article 1.2 below. 14 b. When existing fence is crossing the proposed utility trench,the work performed 15 and materials furnished in accordance with fence replacement will be 16 considered subsidiary to the trench and no other compensation will be allowed. 17 c. When existing fence is outside of the limits of the project Site or is identified as 18 protected on the Drawings and is disturbed and/or by construction activities, 19 replacement will be at the expense of the Contractor and no other compensation 20 will be allowed. 21 B. Deviations from this City of Fort Worth Standard Specification 22 1. Some portions removed which were not applicable to this project. 23 C. Related Specification Sections include,but are not necessarily limited to: 24 1. Division 0-Bidding Requirements,Contract Forms,and Conditions of the Contract 25 2. Division 1 -General Requirements 26 1.2 PRICE AND PAYMENT PROCEDURES 27 A. Measurement and Payment 28 1. Chain Link Fence 29 a. Measurement 30 1) Measurement for this Item shall be by the linear foot of Chain Link Fence 31 installed. 32 b. Payment 33 1) The work performed and materials furnished in accordance with this Item 34 and measured as provided under"Measurement"will be paid for at the unit 35 price bid per linear foot of Chain Link Fence installed for various: 36 a) Heights 37 b) Fabric materials 38 c. The price bid shall include: 39 1) Furnishing and installing all fence and gate materials 40 2) Mow strip, if shown in Drawings 41 3) Cleanup 42 4) Hauling 43 2. Wrought Iron Fence CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3231 13-2 CHAIN LINK FENCE AND GATES Page 2 of 7 1 a. Measurement 2 1) Measurement for this Item shall be by the linear foot of Wrought Iron 3 Fence installed. 4 b. Payment 5 1) The work performed and materials furnished in accordance with this Item 6 and measured as provided under"Measurement"will be paid for at the unit 7 price bid per linear foot of Wrought Iron Fence installed for various 8 heights. 9 c. The price bid shall include: 10 1) Furnishing and installing all fence and gate materials 11 2) Mow strip, if shown in Drawings 12 3) Cleanup 13 4) Hauling 14 3. Steel Tube Fence 15 a. Measurement 16 1) Measurement for this Item shall be by the linear foot of Steel Tube Fence 17 installed. 18 b. Payment 19 1) The work performed and materials furnished in accordance with this Item 20 and measured as provided under"Measurement"will be paid for at the unit 21 price bid per linear foot of Steel Tube Fence installed for various heights. 22 c. The price bid shall include: 23 1) Furnishing and installing all fence and gate materials 24 2) Mow strip, if shown in Drawings 25 3) Cleanup 26 4) Hauling 27 1.3 REFERENCES 28 A. Reference Standards 29 1. Reference standards cited in this specification refer to the current reference standard 30 published at the time of the latest revision date logged at the end of this 31 specification,unless a date is specifically cited. 32 2. American Society for Testing and Materials(ASTM): 33 a. A 36, Standard Specification for Carbon Structural Steel 34 b. A 123, Standard Specification for Zinc(Hot-Dip Galvanized)Coatings on Iron 35 and Steel Products 36 c. A 392, Standard Specification for Zinc-Coated Steel Chain-Link Fence Fabric 37 d. A 500, Standard Specification for Cold-Formed Welded and Seamless Carbon 38 Steel Structural Tubing in Rounds and Shapes 39 e. F 626, Standard Specification for Fence Fittings 40 f. F 1043, Standard Specification for Strength and Protective Coatings on Steel 41 Industrial Chain Link Fence Framework 42 g. F 1083, Standard Specification for Pipe, Steel,Hot-Dipped Zinc-Coated 43 (Galvanized) Welded, for Fence Structures 44 h. F 1183, Specification for Aluminum Alloy Chain Link Fence Fabric 45 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 46 1.5 ACTION SUBMITTALS 47 A. Shop drawings CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3231 13-3 CHAIN LINK FENCE AND GATES Page 3 of 7 1 1. Layout of fences and gates with dimensions,details,and finishes of components, 2 accessories and post foundations if requested by the City. 3 B. Product data 4 1. Manufacturer's catalog cuts indicating material compliance and specified options. 5 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 6 1.7 CLOSEOUT SUBMITTALS [NOT USED] 7 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 8 1.9 QUALITY ASSURANCE [NOT USED] 9 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 10 1.11 FIELD [SITE] CONDITIONS [NOT USED] 11 1.12 WARRANTY [NOT USED] 12 PART 2 - PRODUCTS 13 2.1 OWNER-FURNISHED [NOT USED] 14 2.2 MANUFACTURED UNITS/MATERIALS 15 A. Manufacturer 16 1. Minimum of 5 years of experience manufacturing galvanized coated chain link 17 fencing. 18 2. Approved Manufacturer or equal: 19 a. Allied Fence, Inc. 20 b. American Fence Corp. 21 c. Anchor Fence, Inc. 22 d. Master Halco,Inc. 23 B. Materials 24 1. Chain Link Fence 25 a. General 26 1) Posts,gate frames,braces,rails, stretcher bars,truss rods and tension wire 27 shall be of steel. 28 2) Gate hinges,post caps,barbed wire supporting arms, stretcher bar bands 29 and other parts shall be of steel,malleable iron,ductile iron or equal 30 3) Post tops,rail end,ties and clips may be of aluminum. 31 4) Use only new material,or salvaged/existing material if approved by City or 32 noted on Drawings. 33 b. Steel Fabric 34 1) Fabric 35 a) No. 9 gauge 36 b) 2-inch mesh 37 (1) Commercial: both top and bottom selvages twisted and barged 38 Residential: match existing or both top and bottom selvages knuckled 39 (2) Furnish 1-piece fabric widths. 40 2) Fabric Finish: Galvanized,ASTM A 392, Class I,with not less than 1.2 oz. 41 zinc per square foot of surface. 42 c. Aluminum Fabric CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3231 13-4 CHAIN LINK FENCE AND GATES Page 4 of 7 1 1) Fabric 2 a) ASTM F 1183 3 b) No. 9 gauge 4 c) 2-inch mesh,with both top and bottom selvages twisted and barged. 5 d) Furnish 1-piece fabric widths. 6 d. Steel Framing 7 1) Steel pipe-Type I 8 a) ASTM F 1083 9 b) Standard weight schedule 40 10 c) Minimum yield strength: 30,000 psi 11 d) Sizes as indicated 12 e) Hot-dipped galvanized with minimum average 1.8 Oz/ftz of coated 13 surface area 14 2) Steel pipe-Type 11 15 a) ASTM F 1043, Group IC 16 b) Minimum yield strength: 50,000 psi 17 c) Sizes as indicated on Drawings 18 d) Protective coating per ASTM F 1043 19 (1) External coating Type B 20 (a) Zinc with organic overcoat 21 (b) 0.9 oz/ftz minimum zinc coating with chromate conversion 22 coating and verifiable polymer film 23 (2) Internal coating Type B 24 (a) Minimum 0.9 Oz/ftz zinc or Type D,zinc pigmented, 81 percent 25 nominal coating,minimum 3 mils 26 3) Formed steel ("C") sections: 27 a) Roll formed steel shapes complying with ASTM F 1043, Group 11 28 b) Minimum yield strength: 45,000 psi (310 MPa) 29 c) Sizes as indicated on Drawings 30 d) External coating per ASTM F 1043,Type A 31 (1) Minimum average 2.0 oz/ftz of zinc per ASTM A 123 32 4) Steel square sections 33 a) ASTM A 500, Grade B 34 b) Minimum yield strength: 40,000 psi 35 c) Sizes as indicated on Drawings 36 d) Hot-dipped galvanized with minimum 1.8 oz/ftz of coated surface area 37 e. Accessories 38 1) Chain link fence accessories 39 a) ASTM F 626 40 b) Provide items required to complete fence system. 41 c) Galvanize each ferrous metal item and finish to match framing. 42 2) Post caps 43 a) Formed steel or cast malleable iron weather tight closure cap for 44 tubular posts. 45 b) Provide 1 cap for each post. 46 c) Cap to have provision for barbed wire when necessary. 47 d) "C"shaped line post without top rail or barbed wire supporting arms do 48 not require post caps. 49 e) Where top rail is used,provide tops to permit passage of top rail. 50 3) Top rail and rail ends CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 323113-5 CHAIN LINK FENCE AND GATES Page 5 of 7 1 a) 1 5/8 inch diameter galvanized round pipe for horizontal railing 2 b) Pressed steel per ASTM F626 3 c) For connection of rail and brace to terminal posts 4 4) Top rail sleeves 5 a) 7-inch expansion sleeve with a minimum 0.137 inch wire diameter and 6 1.80 inch length spring, allowing for expansion and contraction of top 7 rail 8 5) Wire ties 9 a) 9 gauge galvanized steel wire for attachment of fabric to line posts 10 b) Double wrap 13 gauge for rails and braces. 11 c) Hog ring ties of 12-1/2 gauge for attachment 12 6) Brace and tension(stretcher bar)bands 13 a) Pressed steel 14 b) Minimum 300 degree profile curvature for secure fence post attachment 15 c) At square post provide tension bar clips. 16 7) Tension(stretcher)bars: 17 a) 1 piece lengths equal to 2 inches less than full height of fabric 18 b) Minimum cross-section of 3/16 inch x 3/4 inch 19 c) Provide tension(stretcher)bars where chain link fabric meets terminal 20 posts. 21 8) Tension wire 22 a) Galvanized coated steel wire, 6 gauge, [0.192 inch] diameter wire 23 b) Tensile strength: 75,000 psi 24 9) Truss rods&tightener 25 a) Steel rods with minimum diameter of 5/16 inch 26 b) Capable of withstanding a tension of minimum 2,000 pounds 27 10) Nuts and bolts are galvanized. 28 2. Wrought Iron Fence: specified per Drawings. 29 3. Steel Tube Fence: specified per Drawings. 30 4. Setting Materials 31 a. Concrete 32 1) Minimum 28 day compressive strength of 3,000 psi 33 2) Bagged concrete allowed. 34 b. Drive Anchors 35 1) Galvanized angles 36 2) ASTM A 36 steel 37 3) 1 inch x 1 inch x 30 inch galvanized shoe clamps to secure angles to posts. 38 2.3 ACCESSORIES [NOT USED] 39 2.4 SOURCE QUALITY CONTROL [NOT USED] 40 PART 3- EXECUTION 41 3.1 INSTALLERS [NOT USED] 42 3.2 EXAMINATION 43 A. Verification of Conditions 44 1. Verify areas to receive fencing are completed to final grades and elevations. 45 2. Ensure property lines and legal boundaries of work are clearly established CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3231 13-6 CHAIN LINK FENCE AND GATES Page 6 of 7 1 3.3 PREPARATION [NOT USED] 2 3.4 INSTALLATION 3 A. Chain Link Fence Framing 4 1. Locate terminal post at each fence termination and change in horizontal or vertical 5 direction of 30 degrees or more. 6 2. Space line posts uniformly at 10 feet on center. 7 3. Set all posts in concrete 8 a. Drill holes in firm, undisturbed or compacted soil. 9 b. Drill hole diameter 4 times greater than outside dimension of post. 10 c. Set post bottom 24 inches below surface when in firm, undisturbed soil. 11 d. Excavate deeper as required for adequate support in soft and loose soils,and for 12 posts with heavy lateral loads. 13 e. Place concrete around posts in a continuous pour. Trowel finish around post. 14 Slope to direct water away from posts. 15 4. Check each post for vertical and top alignment, and maintain in position during 16 placement and finishing operations. 17 5. Bracing 18 a. Install horizontal pipe brace at mid-height for fences 6 feet and taller,on each 19 side of terminal posts. 20 b. Firmly attach with fittings. 21 c. Install diagonal truss rods at these points. 22 d. Adjust truss rod, ensuring posts remain plumb. 23 6. Tension wire 24 a. Provide tension wire at bottom of fabric and at top, if top rail is not specified. 25 b. Install tension wire before stretching fabric and attach to each post with ties. 26 c. Secure tension wire to fabric with 12-1/2 gauge hog rings 24 inches on center. 27 7. Top rail 28 a. Install lengths, 21 feet 29 b. Connect joints with sleeves for rigid connections for expansion/contraction. 30 8. Center Rails for fabric height 12 feet and taller. 31 a. Install mid rails between posts with fittings and accessories. 32 9. Bottom Rails: Install bottom rails between posts with fittings and accessories. 33 B. Chain Link Fabric Installation 34 1. Fabric 35 a. Install fabric on security side and attach so that fabric remains in tension after 36 pulling force is released. 37 b. Leave approximately 2 inches between finish grade and bottom selvage. 38 c. Attach fabric with wire ties to line posts at 15 inches on center and to rails, 39 braces, and tension wire at 24 inches on center. 40 2. Tension(stretcher)bars 41 a. Pull fabric taut. 42 b. Thread tension bar through fabric and attach to terminal posts with bands or 43 clips spaced maximum of 15 inches on center. 44 3. Accessories 45 a. Tie wires: Bend ends of wire to minimize hazard to persons and clothing. 46 b. Fasteners: Install nuts on side of fence opposite fabric side for added security. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3231 13-7 CHAIN LINK FENCE AND GATES Page 7 of 7 1 c. Slats: Install slats in accordance with manufacturer's instructions. 2 C. Wrought Iron Installation: install per Drawings 3 D. Steel Tube Fence: install per Drawings 4 3.5 REPAIR/RESTORATION [NOT USED] 5 3.6 RE-INSTALLATION [NOT USED] 6 3.7 FIELD QUALITY CONTROL [NOT USED] 7 3.8 SYSTEM STARTUP [NOT USED] 8 3.9 ADJUSTING [NOT USED] 9 3.10 CLEANING [NOT USED] 10 3.11 CLOSEOUT ACTIVITIES [NOT USED] 11 3.12 PROTECTION [NOT USED] 12 3.13 MAINTENANCE [NOT USED] 13 3.14 ATTACHMENTS [NOT USED] 14 END OF SECTION 15 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D.Johnson 1.1.A.modified to describe when City would pay for fence replacement on utility projects 16 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project:No.00485 Revised December 20,2012 3231 26-1 WIRE FENCE AND GATES Pagel of 5 1 SECTION 32 3126 2 WIRE FENCE AND GATES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Furnish and construct fence of barbed or smooth wire. 7 2. On utility projects: 8 a. When existing fence is within the project Site(i.e.parallel to the utility trench 9 and/or within utility easement) and is directly disturbed by construction 10 activities, fencing will be paid for as listed in Article 1.2 below. 11 b. When existing fence is crossing the proposed utility trench, the work performed 12 and materials furnished in accordance with fence replacement will be 13 considered subsidiary to the trench and no other compensation will be allowed. 14 c. When existing fence is outside of the limits of the project Site or is identified as 15 protected on the Drawings and is disturbed and/or by construction activities, 16 replacement will be at the expense of the Contractor and no other compensation 17 will be allowed. 18 B. Deviations from this City of Fort Worth Standard Specification 19 1. Some portions removed which were not applicable to this project. 20 C. Related Specification Sections include, but are not necessarily limited to: 21 1. Division 0 - Bidding Requirements,Contract Forms, and Conditions of the Contract 22 2. Division 1 -General Requirements 23 1.2 PRICE AND PAYMENT PROCEDURES 24 A. Measurement and Payment 25 1. Wire Fence 26 a. Measurement 27 1) Measurement for this Item shall be by the linear foot of Wire Fence, 28 excluding gates. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this Item 31 and measured as provided under"Measurement"will be paid for at the unit 32 price bid per linear foot of Wire fence installed for various: 33 a) Post types 34 b) Wire types 35 c) Number of Strands as specified in the Drawings 36 c. The price bid shall include: 37 1) Removal of existing fence and/or,unless specifically defined as a separate 38 pay item on Drawings 39 2) Furnishing,preparing, hauling, and installing Wire Fence 40 3) Excavation,backfilling, and disposal of surplus material 41 4) Removal and trimming of brush and tree limbs 42 2. Steel Gates 43 a. Measurement CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3231 26-2 WIRE FENCE AND GATES Page 2 of 5 1 1) Measurement for this Item shall be per each Steel Fence. 2 b. Payment 3 1) The work performed and materials furnished in accordance with this Item 4 and measured as provided under"Measurement"will be paid for at the unit 5 price bid per each Steel Gate by height. 6 c. The price bid shall include: 7 1) Removal of existing fence and/or gates, unless specifically defined as a 8 separate pay item on Drawings 9 2) Furnishing,preparing,hauling, and installing Steel Gates 10 3) Excavation, backfilling, and disposal of surplus material 11 4) Removal and trimming of brush and tree limbs 12 1.3 REFERENCES 13 A. Reference Standards 14 1. Reference standards cited in this specification refer to the current reference standard 15 published at the time of the latest revision date logged at the end of this 16 specification, unless a date is specifically cited. 17 2. American Society for Testing and Materials (ASTM): 18 a. A 702, Standard Specification for Steel Fence Posts and Assemblies, Hot 19 Wrought 20 b. A 121, Standard Specification for Metallic-Coated, Carbon Steel Barbed Wire 21 c. A 116, Standard Specification for Metallic-Coated, Steel Woven Wire Fence 22 Fabric 23 d. F 1083, Standard Specification for Pipe, Steel, Hot-Dipped Zinc-Coated 24 (Galvanized)Welded, for Fence Structures 25 3. American Wood Protection Association(AWPA) 26 a. P8/P9, Standard for Oil-Borne Preservatives 27 b. C5, Fence Posts -Preservative Treatment by Pressure Processes 28 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 29 1.5 ACTION SUBMITTALS [NOT USED] 30 1.6 ACTION SUBMITTALSIINFORMATIONAL SUBMITTALS [NOT USED] 31 1.7 CLOSEOUT SUBMITTALS [NOT USED] 32 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 33 1.9 QUALITY ASSURANCE [NOT USED] 34 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 35 1.11 FIELD [SITE] CONDITIONS [NOT USED] 36 1.12 WARRANTY [NOT USED] 37 PART 2 - PRODUCTS 38 2.1 OWNER-FURNISHED PRODUCTS [NOT USED] 39 2.2 MATERIALS 40 A. Furnish materials in accordance with details shown on the Drawings and with the 41 following requirements. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 323126-3 WIRE FENCE AND GATES Page 3 of 5 1 B. Metal Posts and Braces 2 1. Steel Pipe: ASTM F 1083 3 2. T posts: ASTM A 702 4 3. Use only new steel. Do not use rerolled or open-seam material. 5 4. Furnish galvanized steel sections in ASTM F 1083. 6 5. Painting 7 a. Use an approved anticorrosive coating. 8 b. After installation of painted posts and braces, spot-coat damaged areas with the 9 same paint color. 10 c. Use paint with at least the same anticorrosive properties as the original paint. 11 6. Use the size, weight, and area of posts, braces, and anchor plates shown on the 12 Drawings. 13 C. Wood Posts and Braces 14 1. Untreated Wood: cedar or juniper timber 15 2. Treated Wood 16 a. AWPA standards govern materials and methods of treatments including 17 seasoning,preservatives,and inspection for treatment. 18 b. Each piece or bundle of other treated-timber products must have: 19 1) Legible brand mark or tag indicating the name of the treater 20 2) Date of treatment or lot number 21 3) AWPA treatment specification symbol 22 c. Provide the level of preservative indicated in Table 1. 23 Table 1 24 Minimum Retention of Preservative Penta- Product chlorophenol AWPA (16./cu.ft.) Standard AWPA for Preservative (P8/P9) Treatment Standard Wire fence posts 0.4 C5 round ' 25 1.Retention determined by assay(0 to 1.0-inch zone). 26 3. Use sound timber that is free from decay, shakes, splits, or other defects that would 27 weaken the posts or braces or otherwise make them structurally unsuitable for the 28 purposes intended. 29 4. Knots that are sound,tight,trimmed flush, and not in clusters will be allowed, 30 provided they do not exceed 1/3 of the small diameter or the least dimension of the 31 posts and braces. 32 5. Remove spurs and splinters,cutting the ends square. 33 D. Gates and Gateposts: Furnish materials to the required dimensions. 34 E. Barbed and Smooth Wire: ASTM A 121, Class 1 35 1. Use wire consisting of 2 strand, 12 1/2 gauge,twisted wire 36 2. Barbed Wire: 2-point 14 gauge barbs spaced no more than 5 inches apart 37 F. Wire Mesh: ASTM A 116,Class 1 38 1. Top and bottom wires: at least 10 gauge wire CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 32 31 26-4 WIRE FENCE AND GATES Page 4 of 5 1 2. Intermediate wires and vertical stays: 12 1/2 gauge wire 2 G. Miscellaneous 3 1. Furnish galvanized bolts,nuts, washers, braces, straps, and suitable devices for 4 holding barbed wire and wire mesh firmly to metal posts. 5 2. Use material of good commercial quality and design. 6 3. Provide galvanized staples, at least 1 1/2 inch long. 7 H. Concrete 8 1. Minimum 28 day compressive strength of 3,000 psi 9 2. Bagged concrete allowed. 10 2.3 ACCESSORIES [NOT USED] 11 2.4 SOURCE QUALITY CONTROL [NOT USED] 12 PART 3 - EXECUTION 13 3.1 INSTALLERS [NOT USED] 14 3.2 EXAMINATION [NOT USED] 15 3.3 PREPARATION [NOT USED] 16 3.4 INSTALLATION 17 A. Space fence posts as shown on the Drawings or to match existing. 18 B. Set fence posts plumb and firm at the intervals, depth,and grade shown on the 19 Drawings or to match existing. 20 C. Brace corner and pull posts in 2 directions. 21 D. Brace end posts and gateposts in 1 direction. 22 E. Install a corner post where the alignment changes 30 degrees or more. 23 F. At alignment angles between 15 and 30 degrees,brace the angle post to the adjacent 24 line posts with diagonal tension wires. 25 G. At grade depressions where stresses tend to pull posts out of the ground, snub or guy 26 the fencing at the critical point with a double 9 gauge galvanized wire. 27 H. Connect the wire to the top horizontal line of the barbed wire or to the top and bottom 28 wire or wire mesh fabric, and to a deadman weighing at least 100 pounds. 29 I. Stretch the fence before guying and snubbing. 30 J. Install number stands at spacing shown in Drawings. 31 K. Install corner, end, or angle post assembly before stretching the wire between posts. 32 L. Connect existing cross fences to the new fences and corner posts at junctions with 33 existing fences. 34 M. While drawing barbed wire and wire fabric taut, fasten to posts using galvanized ties or 35 staples, or as shown on the Drawings. 36 N. Install pull post assemblies at 500 feet intervals for steel posts and at 1,000 feet 37 intervals for wood posts. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 323126-5 WIRE FENCE AND GATES Page 5 of 5 1 O. Drive metal line posts provided driving does not damage the posts. 2 P. Set metal corners, ends,pull posts,and braces in concrete footings a minimum of 24 3 inches and crowned at the top to shed water. 4 Q. Thoroughly tamp backfill in 4 inch layers. 5 R. Notch timber posts. 6 3.5 REPAIR/RESTORATION [NOT USED] 7 3.6 RE-INSTALLATION [NOT USED] 8 3.7 FIELD QUALITY CONTROL [NOT USED] 9 3.8 SYSTEM STARTUP [NOT USED] 10 3.9 ADJUSTING [NOT USED] 11 3.10 CLEANING [NOT USED] 12 3.11 CLOSEOUT ACTIVITIES [NOT USED] 13 3.12 PROTECTION [NOT USED] 14 3.13 MAINTENANCE [NOT USED] 15 3.14 ATTACHMENTS [NOT USED] 16 17 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D.Johnson 1.I.A.modified to describe when City would pay for fence replacement on utility projects 18 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 323129-1 WOOD FENCE AND GATES Page 1 of 5 1 SECTION 32 3129 2 WOOD FENCE AND GATES 3 PART1 - GENERAL 4 1.1 SUMI<.ARY 5 A. Section Includes 6 1. Construction of wood fences and gates along boundaries, property lines in 7 accordance with the City's Zoning Ordinance. 8 2. On utility projects: 9 a. When existing fence is within the project Site(i.e. parallel to the utility trench 10 and/or within utility easement)and is directly disturbed by construction 11 activities, fencing will be paid for as listed in Article 1.2 below. 12 b. When existing fence is crossing the proposed utility trench, the work performed 13 and materials furnished in accordance with fence replacement will be 14 considered subsidiary to the trench and no other compensation will be allowed. 15 c. When existing fence is outside of the limits of the project Site or is identified as 16 protected on the Drawings and is disturbed and/or by construction activities, 17 replacement will be at the expense of the Contractor and no other compensation 18 will be allowed. 19 B. Deviations from this City of Fort Worth Standard Specification 20 1. Some portions removed which were not applicable to this project. 21 C. Related Specification Sections include, but are not necessarily limited to: 22 1. Division 0-Bidding Requirements, Contract Forms, and Conditions of the Contract 23 2. Division 1 -General Requirements 24 1.2 PRICE AND PAYMENT PROCEDURES 25 A. Measurement and Payment 26 1. Measurement 27 a. Measurement for this Item shall be by the linear foot of Wood Fence installed, 28 including gates. 29 2. Payment 30 a. The work performed and materials furnished in accordance with this Item and 31 measured as provided under"Measurement"will be paid for at the unit price 32 bid per linear foot of Wood Fence installed for by height. 33 3. The price bid shall include: 34 a. Furnishing all materials for fence and gates 35 b. All preparation, erection and installation of materials 36 1.3 REFERENCES 37 A. Reference Standards 38 1. Reference standards cited in this specification refer to the current reference standard 39 published at the time of the latest revision date logged at the end of this 40 specification, unless a date is specifically cited. 41 2. American Society for Testing and Materials (ASTM): CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 323129-2 WOOD FENCE AND GATES Page 2 of 5 1 a. A 123, Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron 2 and Steel Products 3 b. A 500, Standard Specification for Cold-Formed Welded and Seamless Carbon 4 Steel Structural Tubing in Rounds and Shapes 5 c. F 1043, Standard Specification for Strength and Protective Coatings on Steel 6 Industrial Chain Link Fence Framework 7 d. F 1083, Standard Specification for Pipe, Steel, Hot-Dipped Zinc-Coated 8 (Galvanized) Welded, for Fence Structures 9 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 10 1.5 SUBMITTALS 11 A. Shop drawings: Layout offences and gates with dimensions, details, and finishes of 12 components, accessories and post foundations 13 B. Product data: Manufacturer's catalog cuts indicating material compliance and specified 14 options 15 C. Building Permit: All fences over 6 feet 16 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 17 1.7 CLOSEOUT SUBMITTALS [NOT USED] 18 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 19 1.9 QUALITY ASSURANCE [NOT USED] 20 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 21 1.11 FIELD [SITE] CONDITIONS [NOT USED] 22 1.12 WARRANTY [NOT USED] 23 PART 2- PRODUCTS 24 2.1 OWNER-FURNISHED PRODUCTS [NOT USED] 25 2.2 MATERIALS 26 A. General 27 1. Gate hinges and post caps shall be of steel, malleable iron, ductile iron or equal. 28 2. Post tops may be of aluminum. 29 B. Slats: Redwood or cedar free from all major decay or defects which would weaken or 30 otherwise cause them to be unsuitable for fence slats. 31 C. Bottom and Top Rail: Minimum 2-inch x 4-inch x 8-foot cedar stud or match existing. 32 D. Corner, Gate, End, or Line Posts 33 1. Wood Posts 34 a. Minimum size: 4-inch x 4-inch cedar wood post or match existing 35 b. Free from all decay, splits,multiple cracks, or any other defect which would 36 weaken the posts or otherwise cause them to be structurally unsuitable for the 37 purpose intended 38 2. Steel Posts 39 a. Steel pipe-Type I CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 323129-3 WOOD FENCE AND GATES Page 3 of 5 1 1) ASTM F 1083 2 2) Standard weight schedule 40 3 3) Minimum yield strength: 30,000 psi 4 4) Sizes as indicated on Drawings 5 5) Hot-dipped galvanized with minimum average 1.8 oz/ftz of coated surface 6 area. 7 b. Steel pipe-Type 11 8 1) ASTM F 1043, Group IC 9 2) Minimum yield strength: 50,000 psi 10 3) Sizes as indicated on Drawings 11 4) Protective coating per ASTM F 1043 12 5) External coating Type B 13 a) Zinc with organic overcoat 14 b) 0.9 oz/ftz minimum zinc coating with chromate conversion coating and 15 verifiable polymer film 16 6) Internal coating Type B 17 a) Minimum 0.9 oz/ftz zinc or Type D, zinc pigmented, 81 percent 18 nominal coating,minimum 3 mils 19 c. Formed steel ("C") sections 20 1) Roll formed steel shapes complying with ASTM F 1043, Group II 21 2) Minimum yield strength: 45,000 psi (3 10 MPa) 22 3) Sizes as indicated on Drawings 23 4) External coating per ASTM F 1043,Type A 24 a) Minimum average 2.0 oz/ft' of zinc per ASTM A 123 25 d. Steel square sections 26 1) ASTM A 500,Grade B 27 2) Minimum yield strength: 40,000 psi 28 3) Sizes as indicated 29 4) Hot-dipped galvanized with minimum 1.8 oz/ftz of coated surface area 30 3. Accessories 31 a. Post caps 32 1) Formed steel or cast malleable iron weather tight closure cap for tubular 33 posts. 34 2) Provide one cap for each post. 35 3) Cap to have provision for barbed wire when necessary. 36 4) "C"shaped line post without top rail or barbed wire supporting arms do not 37 require post caps. 38 5) Where top rail is used,provide tops to permit passage of top rail. 39 4. Setting Materials 40 a. Concrete 41 1) Minimum 28 day compressive strength of 3,000 psi 42 2) Bagged concrete allowed. 43 2.3 ACCESSORIES [NOT USED] 44 2.4 SOURCE QUALITY CONTROL [NOT USED] 45 PART 3 - EXECUTION 46 3.1 INSTALLERS [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 323129-4 WOOD FENCE AND GATES Page 4 of 5 1 3.2 EXAMINATION 2 A. Verification of Conditions 3 1. Verify areas to receive fencing are completed to final grades and elevations. 4 2. Ensure property lines and legal boundaries of work are clearly established. 5 3.3 PREPARATION [NOT USED] 6 3.4 INSTALLATION 7 A. Wood Fence Framing 8 1. Steel Posts are required for all required screening fences. 9 2. Locate terminal post at each fence termination and change in horizontal or vertical 10 direction of 30 degrees or more. 11 3. Space line posts uniformly at 10 feet on center. 12 4. Set all posts in concrete. 13 a. Drill holes in firm, undisturbed or compacted soil. 14 b. Drill hole diameter 4 times greater than outside dimension of post (minimum 15 12 inches). 16 c. Set post bottom 24 inches below surface when in firm,undisturbed soil. 17 d. Excavate deeper as required for adequate support in soft and loose soils,and 18 for posts with heavy lateral loads. 19 e. Place concrete around posts in a continuous pour. 20 f. Trowel finish around post. Slope to direct water away from posts. 21 5. Check each post for vertical and top alignment, and maintain in position during 22 placement and finishing operations. 23 B. Slats 24 1. Place slats approximately 1 inch above the ground, and on a straight grade between 25 posts by excavating high points of the ground. 26 2. Fasten slats to top and bottom railings with 2 galvanized screws designed for wood 27 fence construction at both the top and bottom rail. 28 3.5 REPAIR/RESTORATION [NOT USED] 29 3.6 RE-INSTALLATION [NOT USED] 30 3.7 FIELD QUALITY CONTROL [NOT USED] 31 3.8 SYSTEM STARTUP [NOT USED] 32 3.9 ADJUSTING [NOT USED] 33 3.10 CLEANING [NOT USED] 34 3.11 CLOSEOUT ACTIVITIES [NOT USED] 35 3.12 PROTECTION [NOT USED] 36 3.13 MAINTENANCE [NOT USED] 37 3.14 ATTACHMENTS [NOT USED] 38 END OF SECTION 39 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 323129-5 WOOD FENCE AND GATES Page 5 of 5 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D.Johnson 1.l.A.modified to describe when City would pay for fence replacement on utility projects 1 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3291 19- 1 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page 1 of 3 1 SECTION 32 91 19 2 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Furnish and place topsoil to the depths and on the areas shown on the Drawings. 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Some portions removed which were not applicable to this project.Additional 9 Specifications added for this project. 10 C. Related Specification Sections include but are not necessarily limited to 11 1. Division 0 -Bidding Requirements, Contract Forms, and Conditions of the Contract 12 2. Division 1 -General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Measurement 16 a. Measurement for this Item shall be by cubic yard of Topsoil in place. 17 2. Payment 18 a. The work performed and materials furnished in accordance with this Item and 19 measured as provided under"Measurement"will be paid for at the unit price 20 bid per cubic yard of Topsoil. 21 b. All excavation required by this Item in cut sections shall be measured in 22 accordance with provisions for the various excavation items involved with the 23 provision that excavation will be measured and paid for once, regardless of the 24 manipulations involved. 25 c. Contractor may reuse existing Top Soil or haul in new. 26 d. Top Soil may be banked onsite. 27 3. The price bid shall include: 28 a. Furnishing Topsoil if new 29 b. Excavating if reused 30 c. Loading 31 d. Hauling 32 e. Placing 33 1.3 REFERENCES [NOT USED] 34 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 35 1.5 ACTION SUBMITTALS [NOT USED] 36 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 37 1.7 CLOSEOUT SUBMITTALS [NOT USED] 38 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 39 1.9 QUALITY ASSURANCE [NOT USED] CITY OF FORT WORTH Dry Branch Creek Interim Regional Detetnion Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3291 19-2 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page 2 of 3 1 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2 - PRODUCTS 5 2.1 OWNER-FURNISHED loR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 6 2.2 MATERIALS 7 A. Topsoil 8 1. Use easily cultivated, fertile topsoil that: 9 a. Is free from objectionable material including subsoil,weeds, clay lumps, non- 10 soil materials, roots, stumps or stones larger than 1.5 inches 11 b. Has a high resistance to erosion 12 c. Is able to support plant growth 13 2. Secure topsoil from approved sources. 14 3. Topsoil is subject to testing by the City. 15 4. pH: 5.5 to 8.5. 16 5. Liquid Limit: 50 or less 17 6. Plasticity Index: 20 or less 18 7. Gradation: maximum of 10 percent passing No. 200 sieve 19 B. Water: Clean and free of industrial wastes and other substances harmful to the growth 20 of vegetation 21 2.3 ACCESSORIES [NOT USED] 22 2.4 SOURCE QUALITY CONTROL [NOT USED] 23 PART 3 - EXECUTION 24 3.1 INSTALLERS [NOT USED] 25 3.2 EXAMINATION [NOT USED] 26 3.3 PREPARATION [NOT USED] 27 3.4 INSTALLATION 28 A. Finishing of Parkways 29 1. Smoothly shape parkways, shoulders, slopes, and ditches. 30 2. Cut parkways to finish grade prior to the placing of any improvements in or 31 adjacent to the roadway. 32 3. In the event that unsuitable material for parkways is encountered, extend the depth 33 of excavation in the parkways 6 inches and backfill with top soil. 34 4. Make standard parkway grade perpendicular to and draining to the curb line. 35 a. Minimum: 1/4 inch per foot 36 b. Maximum: 4:1 37 c. City may approve variations from these requirements in special cases. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detetnion Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3291 19-3 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page 3 of 3 1 5. Whenever the adjacent property is lower than the design curb grade and runoff 2 drains away from the street,the parkway grade must be set level with the top of the 3 curb. 4 6. The design grade from the parkway extends to the back of the walk line. 5 7. From that point (behind the walk),the grade may slope up or down at maximum 6 slope of 4:1. 7 B. Placing of Topsoil 8 1. Spread the topsoil to a uniform loose cover at the thickness specified. 9 2. Place and shape the topsoil as directed. 10 3. Hand rake finish a minimum of 5 feet from all flatwork. 11 4. Tamp the topsoil with a light roller or other suitable equipment. 12 3.5 REPAIR/RESTORATION] [NOT USED] 13 3.6 RE-INSTALLATION [NOT USED] 14 3.7 FIELD QUALITY CONTROL [NOT USED] 15 3.8 SYSTEM STARTUP [NOT USED] 16 3.9 ADJUSTING [NOT USED] 17 3.10 CLEANING [NOT USED] 18 3.11 CLOSEOUT ACTIVITIES [NOT USED] 19 3.12 PROTECTION [NOT USED] 20 3.13 MAINTENANCE [NOT USED] 21 3.14 ATTACHMENTS [NOT USED] 22 END OF SECTION 23 Revision Log DATE NAME SUMMARY OF CHANGE i 24 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detetnion Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 329213-1 HYDROMULCHING,SEEDING AND SODDING Page 1 of 5 1 SECTION 32 92 13 2 HYDROMULCHING, SEEDING AND SODDING 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Furnishing and installing grass sod and permanent seeding as shown on Drawings, 7 or as directed. 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. Some portions removed which were not applicable to this project.Additional 10 specifications added for this project. I 1 C. Related Specification Sections include, but are not necessarily limited to: 12 1. Division 0 -Bidding Requirements, Contract Forms, and Conditions of the Contract 13 2. Division 1 -General Requirements 14 3. Section 32 91 19—Topsoil Placement and Finishing of Parkways 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Seeding 18 a. Measurement 19 1) Measurement for this Item shall be by the square yard of Seed spread. 20 b. Payment 21 1) The work performed and materials furnished in accordance with this Item 22 and measured as provided under"Measurement"will be paid for at the unit 23 price bid per square yard of Seed placed for various installation methods. 24 c. The price bid shall include: 25 1) Furnishing and placing all Seed 26 2) Furnishing and applying water for seed fertilizer 27 3) Slurry and hydraulic mulching 28 4) Fertilizer 29 5) Watering and mowing(until established) 30 6) Disposal of surplus materials 31 1.3 REFERENCES [NOT USED] 32 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 33 1.5 ACTION SUBMITTALS [NOT USED] 34 1.6 INFORMATIONAL SUBMITTALS 35 A. Seed 36 1. Vendors' certification that seeds meet Texas State seed law including: 37 a. Testing and labeling for pure live seed(PLS) 38 b. Name and type of seed 39 2. All seed shall be tested in a laboratory with certified results presented to the City in 40 writing,prior to planting. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3292 13-2 HYDROMULCHING,SEEDING AND SODDING Page 2 of 5 1 3. All seed to be of the previous season's crop and the date on the container shall be 2 within 12 months of the seeding date. 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY, STORAGE,AND HANDLING 7 A. Seed 8 1. Each species of seed shall be supplied in a separate, labeled container for 9 acceptance by the City. 10 B. Fertilizer 11 1. Provide fertilizer labeled with the analysis. 12 2. Conform to Texas fertilizer law. 13 1.11 FIELD [SITE] CONDITIONS [NOT USED] 14 1.12 WARRANTY [NOT USED] 15 PART 2 - PRODUCTS [NOT USED] 16 2.1 OWNER-FURNISHED PRODUCTS [NOT USED] 17 2.2 MATERIALS AND EQUIPMENT 18 A. Materials 19 1. Seed 20 a. Seed shall be Scorched Earth Recovery Mix spread at a rate of 9 lbs. per 21 acre, by Native American Seed,located in Junction,Texas, or approved 22 equal. 23 2. Mulch 24 a. For use with conventional mechanical or hydraulic planting of seed. 25 b. Wood cellulose fiber produced from virgin wood or recycled paper-by-products 26 (waste products from paper mills or recycled newspaper). 27 c. No growth or germination inhibiting factors. 28 d. No more than ten percent moisture,air dry weight basis. 29 e. Additives: binder in powder form. 30 f. Form a strong moisture retaining mat. 31 3. Fertilizer 32 a. Acceptable condition for distribution 33 b. Applied uniformly over the planted area 34 c. Analysis 35 1) 16-20-0 36 2) 16-8-8 37 d. Fertilizer rate: 38 1) Not required for wildflower seeding 39 2) Newly established seeding areas- 100 pounds of nitrogen per acre 40 3) Established seeding areas - 150 pounds of nitrogen per acre 41 4. Topsoil: See Section 32 91 19. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 329213-3 HYDROMULCHING,SEEDING AND SODDING Page 3 of 5 1 5. Water: clean and free of industrial wastes or other substances harmful to the 2 germination of the seed or to the growth of the vegetation. 3 6. Soil Retention Blanket 4 a. "Curlex P' from American Excelsior, 900 Ave. H East,Post Office Box 5624, 5 Arlington,Texas 76001, 1-800-777-SOIL or approved equal. 6 7 2.3 ACCESSORIES [NOT USED] 8 2.4 SOURCE QUALITY CONTROL [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 3.1 INSTALLERS [NOT USED] 11 3.2 EXAMINATION [NOT USED] 12 3.3 PREPARATION 13 A. Surface Preparation: clear surface of all material including: 14 1. Stumps, stones,and other objects larger than one inch. 15 2. Roots,brush,wire, stakes, etc. 16 3. Any objects that may interfere with seeding or maintenance. 17 B. Tilling 18 1. Compacted areas: till 1 inch deep 19 2. Areas sloped greater than 3:1: run a tractor parallel to slope to provide less 20 seed/water run-off 21 3. Areas near trees: Do not till deeper than 1/2 inch inside "drip line" of trees. 22 3.4 INSTALLATION 23 A. Seeding 24 1. General 25 a. Seed only those areas indicated on the Drawings and areas disturbed by 26 construction. 27 b. Mark each area to be seeded in the field prior to seeding for City approval. 28 2. Broadcast Seeding 29 a. Broadcast seed in 2 directions at right angles to each other. 30 b. Harrow or rake lightly to cover seed. 31 c. Never cover seed with more soil than twice its diameter. 32 d. For wildflower plantings: 33 1) Scalp existing grasses to 1 inch 34 2) Remove grass clippings, so seed can make contact with the soil. 35 3. Mechanically Seeding(Drilling): 36 a. Uniformly distribute seed over the areas shown on the Drawings or as directed. 37 b. All varieties of seed and fertilizer may be distributed at the same time provided 38 that each component is uniformly applied at the specified rate. 39 c. Drill seed at a depth of 1/4 inch to 3/8 inch utilizing a pasture or rangeland type 40 drill. 41 d. Drill on the contour of slopes CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 329213-4 HYDROMULCHING,SEEDING AND SODDING Page 4 of 5 1 e. After planting roll with a roller integral to the seed drill, or a corrugated roller 2 of the "Cultipacker" type. 3 f. Roll slope areas on the contour. 4 4. Hydromulching 5 a. Mixing: Seed, mulch, fertilizer and water may be mixed provided that: 6 1) Mixture is uniformly suspended to form a homogenous slurry. 7 2) Mixture forms a blotter-like ground cover impregnated uniformly with 8 grass seed. 9 3) Mixture is applied within 30 minutes after placed in the equipment. 10 b. Placing 11 1) Uniformly distribute in the quantity specified over the areas shown on the 12 Drawings or as directed. 13 5. Fertilizing: uniformly apply fertilizer over seeded area. 14 6. Watering 15 a. Furnish water by means of temporary metering/irrigation, water truck or by 16 any other method necessary to achieve an acceptable stand of turf as defined in 17 3.13.B. 18 b. Water soil to a minimum depth of 4 inches within 48 hours of seeding. 19 c. Water as direct by the City at least twice daily for 14 days after seeding in such 20 a manner as to prevent washing of the slopes or dislodgement of the seed. 21 d. Water until final acceptance. 22 e. Generally, an amount of water that is equal to the average amount of rainfall 23 plus 1/2 inch per week should be applied until accepted. 24 3.5 REPAIR/RESTORATION [NOT USED] 25 3.6 RE-INSTALLATION [NOT USED] 26 3.7 FIELD QUALITY CONTROL [NOT USED] 27 3.8 SYSTEM STARTUP [NOT USED] 28 3.9 ADJUSTING [NOT USED] 29 3.10 CLEANING [NOT USED] 30 3.11 CLOSEOUT ACTIVITIES 31 3.12 PROTECTION [NOT USED] 32 3.13 MAINTENANCE 33 A. Seeding 34 1. Water and mow sod until completion and final acceptance of the Project or as 35 directed by the City. 36 2. Maintain the seeded area until each of the following is achieved: 37 a. Vegetation is evenly distributed 38 b. Vegetation is free from bare areas 39 3. Turf will be accepted once fully established. 40 a. Seeded area must have 100 percent growth to a height of 3 inches prior to 41 consideration of acceptance by the City. 42 B. Rejection 43 1. City may reject block sod or seeded area on the basis of weed populations. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 3292 13-5 HYDROMULCHING,SEEDING AND SODDING Page 5 of 5 1 3.14 ATTACHMENTS [NOT USED] 2 END OF SECTION 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised December 20,2012 334940-1 STORM DRAIN HEADWALLS,WINGWALLS AND SAFETY END TREATMENTS Page 1 of 5 1 SECTION 33 49 40 2 STORM DRAIN HEADWALLS AND WINGWALLS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Storm drain headwalls, wingwalls, and safety end treatments 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Some portions removed which were not applicable to this project. 9 2. Related Specification Sections include,but are not necessarily limited to: 10 3. Division 0—Bidding Requirements, Contract Forms, and Conditions of the 11 Contract 12 4. Division 1 —General Requirements 13 5. Section 02 41 13 —Selective Site Demolition 14 6. Section 03 30 00—Cast-In-Place Concrete 15 7. Section 31 37 00—Riprap 16 8. Section 33 05 10—Utility Trench Excavation, Embedment and Backfill 17 9. Section 33 41 10—Reinforced Concrete Storm Sewer Pipe/Culverts 18 C. Standard Details 19 1. Concrete Headwall -Refer to TXDOT Fort Worth District Details 20 2. Concrete Wingwall -Refer to TXDOT Fort Worth District Details 21 1.2 PRICE AND PAYMENT PROCEDURES 22 A. Measurement and Payment 23 1. Concrete Headwall 24 a. Measurement 25 1) Measurement for this Item shall be per each"Headwall" satisfactorily 26 completed as specified on the Drawings. 27 b. Payment 28 1) The work performed and materials furnished in accordance with this Item 29 will be paid for at the unit price bid per each"Headwall"installed for: 30 a) Various pipe sizes 31 b) Various types 32 c) Various number of pipes 33 c. The price bid shall include: 34 1) Constructing, furnishing, transporting and installing the Concrete Headwall 35 2) Connecting to the existing structure 36 3) Breaking back, removing and disposing of portions of the existing structure 37 4) Replacing portions of the existing structure to make connections 38 5) Excavation 39 6) Hauling 40 7) Disposal of excess material CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 334940-2 STORM DRAIN HEADWALLS,WINGWALLS AND SAFETY END TREATMENTS Page 2 of 5 1 8) Furnishing,placing and compaction of backfill 2 9) Concrete,as required by Drawings 3 10) Reinforcing Steel, if required by Drawings 4 11) Corrugated metal pipe, if required by Drawings 5 12) Reinforced concrete pipe, if required by Drawings 6 13) Clean-up 7 1.3 REFERENCES 8 A. Definitions 9 1. Headwalls -all walls, including wings, at the ends of single-barrel and multiple- 10 barrel pipe culvert structures 11 2. Wingwalls -all walls at the ends of single-barrel or multiple-barrel box culvert 12 structures 13 B. Reference Standards 14 1. Reference standards cited in this Specification refer to the current reference 15 standard published at the time of the latest revision date logged at the end of this 16 Specification,unless a date is specifically cited. 17 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 18 1.5 SUBMITTALS 19 1. Refer to Section 03 30 00. 20 1.6 ACTION SUBMITTALS/INFORMATION SUBMITTALS [NOT USED] 21 1.7 CLOSEOUT SUBMITTALS [NOT USED] 22 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 23 1.9 QUALITY ASSURANCE [NOT USED] 24 1.10 DELIVERY, STORAGE,AND HANDLING 25 A. Delivery and Acceptance Requirements 26 1. Marking 27 a. Before shipment from the casting or fabrication yard, clearly mark the 28 following on each precast unit: 29 1) Date of manufacture 30 2) Name or trademark of the manufacturer 31 3) Type and size designation 32 2. Causes for Rejection 33 a. Precast units may be rejected for not meeting any one of the Specification 34 requirements. 35 b. Individual units may also be rejected for fractures or cracks passing through the 36 wall or surface defects indicating honeycombed or open texture surfaces. 37 c. Remove rejected units from the project, and replace them with acceptable units 38 meeting the requirements of this Section. 39 B. Storage and Handling Requirements 40 1. Secure and maintain a location to store the material in accordance with Section 01 41 6600. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 334940-3 STORM DRAIN HEADWALLS,WINGWALLS AND SAFETY END TREATMENTS Page 3 of 5 1 2. Store precast units on a level surface. 2 3. Do not place any loads on precast concrete units until design strength is reached. 3 4. Do not ship units until design strength requirements have been met. 4 1.11 FIELD [SITE] CONDITIONS [NOT USED] 5 1.12 WARRANTY [NOT USED] 6 PART 2- PRODUCTS 7 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 8 2.2 EQUIPMENT,PRODUCT TYPES AND MATERIALS 9 A. Materials 10 1. Concrete 11 a. Furnish concrete that conforms to the provisions of Section 03 30 00. 12 2. Reinforcing Steel 13 a. Furnish reinforcing steel that conforms to the requirements of Section 03 30 00. 14 B. Fabrication 15 1. Fabricate cast-in-place concrete units and precast units in accordance with 16 Section 03 30 00. 17 1) Safety End Treatment will be precast for 30-inch and smaller diameters and 18 cast in place for greater than 30-inch diameters. 19 2. Fabrication Tolerances 20 a. Lifting Holes 21 1) For precast units,provide no more than 4 lifting holes in each section. 22 2) Lifting holes may be cast,cut into fresh concrete after form removal or 23 drilled. 24 3) Provide lifting holes large enough for adequate lifting devices based on the 25 size and weight of the section. 26 a) The maximum hole diameter is 3 inches at the inside surface of the wall 27 and 4 inches at the outside surface. 28 b) Do not cut more than 1 longitudinal wire or 2 circumferential wires per 29 layer of reinforcing steel when locating lift holes. 30 2.3 ACCESSORIES [NOT USED] 31 2.4 SOURCE QUALITY CONTROL [NOT USED] 32 PART 3 - EXECUTION 33 3.1 INSTALLERS [NOT USED] 34 3.2 EXAMINATION [NOT USED] 35 3.3 PREPARATION 36 A. Removal 37 1. Remove all or portions of existing structures in accordance with Section 02 41 13. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 334940-4 STORM DRAIN HEADWALLS,WINGWALLS AND SAFETY END TREATMENTS Page 4 of 5 1 2. Drill, dowel and grout in accordance with Section 03 30 00. 2 3.4 INSTALLATION 3 A. Interface with Other Work 4 1. Make connections to new or existing structures in accordance with the details 5 shown on the Drawings. 6 2. Furnish jointing material in accordance with Section 33 41 10, or as shown on the 7 Drawings. 8 B. Excavation, Shaping, Bedding and Backfill 9 a. Excavate, shape,bed and backfill in accordance with Section 33 05 10. 10 b. Take special precautions in placing and compacting the backfill to avoid any 11 movement or damage to the units. 12 c. Bed precast units on foundations of firm and stable material accurately shaped 13 to conform to the bases of the units. 14 C. Placement of Precast Units 15 a. Provide adequate means to lift and place the precast units. 16 1) Utilize sufficient number of lifting holes to ensure that the units are not 17 damaged during lifting. 18 b. Fill lifting holes with mortar or concrete and cure. 19 1) Precast concrete or mortar plugs may be used. 20 3.5 REPAIR 21 A. Occasional imperfections in manufacture or accidental damage sustained during 22 handling may be repaired. 23 1. The repaired units will be acceptable if they conform to the requirements of this 24 Section and the repairs are sound,properly finished and cured in conformance with 25 pertinent Specifications. 26 B. Repair spalled areas around lifting holes. 27 3.6 RE-INSTALLATION [NOT USED] 28 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 29 3.8 SYSTEM STARTUP [NOT USED] 30 3.9 ADJUSTING [NOT USED] 31 3.10 CLEANING [NOT USED] 32 3.11 CLOSEOUT ACTIVITIES [NOT USED] 33 3.12 PROTECTION [NOT USED] 34 3.13 MAINTENANCE [NOT USED] 35 3.14 ATTACHMENTS [NOT USED] 36 END OF SECTION 37 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 334940-5 STORM DRAIN HEADWALLS,WINGWALLS AND SAFETY END TREATMENTS Page 5 of 5 Revision Loe DATE NAME SUMMARY OF CHANGE 1 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised July 1,2011 3471 13-1 TRAFFIC CONTROL Page 1 of 5 1 SECTION 34 71 13 2 TRAFFIC CONTROL 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Installation of Traffic Control Devices and preparation of Traffic Control Plans 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Some portions removed which were not applicable to this project. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Installation of Traffic Control Devices 15 a. Measurement 16 1) Measurement for Traffic Control Devices shall be per month for the Project 17 duration. 18 a) A month is defined as 30 calendar days. 19 b. Payment 20 1) The work performed and materials furnished in accordance with this Item 21 and measured as provided under"Measurement" shall be paid for at the 22 unit price bid for"Traffic Control". 23 c. The price bid shall include: 24 1) Traffic Control implementation 25 2) Installation 26 3) Maintenance 27 4) Adjustments 28 5) Replacements 29 6) Removal 30 7) Police assistance during peak hours 31 2. Portable Message Signs 32 a. Measurement 33 1) Measurement for this Item shall be per week for the duration of use. 34 b. Payment 35 1) The work performed and materials furnished in accordance to this Item and 36 measured as provided under"Measurement"shall be paid for at the unit 37 price bid per week for"Portable Message Sign"rental. 38 c. The price bid shall include: 39 1) Delivery of Portable Message Sign to Site 40 2) Message updating 41 3) Sign movement throughout construction 42 4) Return of the Portable Message Sign post-construction CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised November 22,2013 347113-2 TRAFFIC CONTROL Page 2 of 5 1 3. Preparation of Traffic Control Plan Details 2 a. Measurement 3 1) Measurement for this Item be per each Traffic Control Detail prepared. 4 b. Payment 5 1) The work performed and materials furnished in accordance with this Item 6 shall be paid for at the unit price bid per each"Traffic Control Detail" 7 prepared. 8 c. The price bid shall include: 9 1) Preparing the Traffic Control Plan Details for closures of 24 hours or 10 longer 11 2) Adherence to City and Texas Manual on Uniform Traffic Control Devices 12 (TMUTCD) 13 3) Obtaining the signature and seal of a licensed Texas Professional Engineer 14 4) Incorporation of City comments 15 1.3 REFERENCES 16 A. Reference Standards 17 1. Reference standards cited in this Specification refer to the current reference 18 standard published at the time of the latest revision date logged at the end of this 19 Specification,unless a date is specifically cited. 20 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 21 3. Item 502,Barricades, Signs, and Traffic Handling of the Texas Department of 22 Transportation, Standard Specifications for Construction and Maintenance of 23 Highways, Streets, and Bridges. 24 1.4 ADMINISTRATIVE REQUIREMENTS 25 A. Coordination 26 1. Contact Traffic Services Division(817-392-7738) a minimum of 48 hours prior to 27 implementing Traffic Control within 500 feet of a traffic signal. 28 B. Sequencing 29 1. Any deviations to the Traffic Control Plan included in the Drawings must be first 30 approved by the City and design Engineer before implementation. 31 1.5 SUBMITTALS 32 A. Provide the City with a current list of qualified flaggers before beginning flagging 33 activities. Use only flaggers on the qualified list. 34 B. Obtain a Street Use Permit from the Street Management Section of the Traffic 35 Engineering Division, 311 W. 10" Street. The Traffic Control Plan(TCP) for the 36 Project shall be as detailed on the Traffic Control Plan Detail sheets of the Drawing set. 37 A copy of this Traffic Control Plan shall be submitted with the Street Use Permit. 38 C. Traffic Control Plans shall be signed and sealed by a licensed Texas Professional 39 Engineer. 40 D. Contractor shall prepare Traffic Control Plans if required by the Drawings or 41 Specifications. The Contractor will be responsible for having a licensed Texas 42 Professional Engineer sign and seal the Traffic Control Plan sheets. 43 E. Lane closures 24 hours or longer shall require a site-specific traffic control plan. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised November 22,2013 3471 13-3 TRAFFIC CONTROL Page 3 of 5 1 F. Contractor responsible for having a licensed Texas Professional Engineer sign and seal 2 changes to the Traffic Control Plan(s)developed by the Design Engineer. 3 G. Design Engineer will furnish standard details for Traffic Control. 4 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 5 1.7 CLOSEOUT SUBMITTALS [NOT USED] 6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 7 1.9 QUALITY ASSURANCE [NOT USED] 8 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 9 1.11 FIELD [SITE] CONDITIONS [NOT USED] 10 1.12 WARRANTY [NOT USED] 11 PART 2 - PRODUCTS 12 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 13 2.2 ASSEMBLIES AND MATERIALS 14 A. Description 15 1. Regulatory Requirements 16 a. Provide Traffic Control Devices that conform to details shown on the 17 Drawings, the TMUTCD, and TxDOT's Compliant Work Zone Traffic Control 18 Device List (CWZTCDL). 19 2. Materials 20 a. Traffic Control Devices must meet all reflectivity requirements included in the 21 TMUTCD and TxDOT Specifications—Item 502 at all times during 22 construction. 23 b. Electronic message boards shall be provided in accordance with the TMUTCD. 24 2.3 ACCESSORIES [NOT USED] 25 2.4 SOURCE QUALITY CONTROL [NOT USED] 26 PART 3- EXECUTION 27 3.1 EXAMINATION [NOT USED] 28 3.2 PREPARATION 29 A. Protection of In-Place Conditions 30 1. Protect existing traffic signal equipment. 31 3.3 INSTALLATION 32 A. Follow the Traffic Control Plan(TCP)and install Traffic Control Devices as shown on 33 the Drawings and as directed. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised November 22,2013 3471 13-4 TRAFFIC CONTROL Page 4 of 5 1 B. Install Traffic Control Devices straight and plumb. 2 C. Do not make changes to the location of any device or implement any other changes to 3 the Traffic Control Plan without the approval of the Engineer. 4 1. Minor adjustments to meet field constructability and visibility are allowed. 5 D. Maintain Traffic Control Devices by taking corrective action as soon as possible. 6 1. Corrective action includes but is not limited to cleaning, replacing, straightening, 7 covering, or removing Devices. 8 2. Maintain the Devices such that they are properly positioned, spaced, and legible, 9 and that retroreflective characteristics meet requirements during darkness and rain. 10 E. If the Inspector discovers that the Contractor has failed to comply with applicable federal 11 and state laws(by failing to furnish the necessary flagmen,warning devices,barricades, 12 lights,signs,or other precautionary measures for the protection of persons or property),the 13 Inspector may order such additional precautionary measures be taken to protect persons 14 and property. 15 F. Subject to the approval of the Inspector,portions of this Project,which are not affected by 16 or in conflict with the proposed method of handling traffic or utility adjustments,can be 17 constructed during any phase. 18 G. Barricades and signs shall be placed in such a manner as to not interfere with the sight 19 distance of drivers entering the highway from driveways or side streets. 20 H. To facilitate shifting,barricades and signs used in lane closures or traffic staging may 21 be erected and mounted on portable supports. 22 1. The support design is subject to the approval of the Engineer. 23 I. Lane closures shall be in accordance with the approved Traffic Control Plans. 24 J. If at any time the existing traffic signals become inoperable as a result of construction 25 operations,the Contractor shall provide portable stop signs with 2 orange flags,as 26 approved by the Engineer,to be used for Traffic Control. 27 K. Contractor shall make arrangements for police assistance to direct traffic if traffic signal 28 turn-ons,street light pole installation,or other construction will be done during peak traffic 29 times(AM: 7 am—9 am,PM: 4 pm-6 pm). 30 L. Flaggers 31 1. Provide a Contractor representative who has been certified as a flagging instructor 32 through courses offered by the Texas Engineering Extension Service,the American 33 Traffic Safety Services Association,the National Safety Council, or other approved 34 organizations. 35 a. Provide the certificate indicating course completion when requested. 36 b. This representative is responsible for training and assuring that all flaggers are 37 qualified to perform flagging duties. 38 2. A qualified flagger must be independently certified by 1 of the organizations listed 39 above or trained by the Contractor's certified flagging instructor. 40 3. Flaggers must be courteous and able to effectively communicate with the public. 41 4. When directing traffic, flaggers must use standard attire, flags, signs, and signals 42 and follow the flagging procedures set forth in the TMUTCD. CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised November 22,2013 3471 13-5 TRAFFIC CONTROL Page 5 of 5 1 5. Provide and maintain flaggers at such points and for such periods of time as may be 2 required to provide for the safety and convenience of public travel and Contractor's 3 personnel, and as shown on the Drawings or as directed by the Engineer. 4 a. These flaggers shall be located at each end of the lane closure. 5 M. Removal 6 1. Upon completion of Work,remove from the Site all barricades, signs,cones, lights 7 and other Traffic Control Devices used for work-zone traffic handling in a timely 8 manner, unless otherwise shown on the Drawings. 9 3.4 REPAIR/RESTORATION [NOT USED] 10 3.5 RE-INSTALLATION [NOT USED] 11 3.6 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 12 3.7 SYSTEM STARTUP [NOT USED] 13 3.8 ADJUSTING [NOT USED] 14 3.9 CLEANING [NOT USED] 15 3.10 CLOSEOUT ACTIVITIES [NOT USED] 16 3.11 PROTECTION [NOT USED] 17 3.12 MAINTENANCE [NOT USED] 18 3.13 ATTACHMENTS [NOT USED] 19 END OF SECTION 20 Revision Log DATE NAME SUMMARY OF CHANGE 11/22/13 S.Arnold Added police assistance,requirement for when a site specific TCP is required 21 CITY OF FORT WORTH Dry Branch Creek Interim Regional Detention Basin STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.00485 Revised November 22,2013 DRY BRANCH CREEK Parcel TROE-2 Doe#5425 2301 N CHANDLER DR W BLOCk 3 LOT 13 SPRINGDALE ADDITION CITY OF FORT WORTH TEMPORARY RIGHT OF ENTRY }STATE OF TEXAS § § KNOW ALL BY THESE PRESENTS COUNTY OF TARRANT § That the undersigned, hereinafter referred to as "Grantor", does by these presents grant and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a temporary right of entry onto property described as Block 3, Lot 13, Springdale. Addition and as shown on the recorded deed in D214195776 Tarrant County deed records a/k/a, 2301 N CHANDLER DR W, Fort Worth, Tarrant County, Texas, hereinafter referred to as the "Property", for the purpose of installation of a new chain- , link fence on property line which includes but not limited to any such activities related to the installation of the new fence (post digging,mounting and securing etc.) The existing fence, which is currently located on City of Fort Worth property, will be removed once installation of new fence is completed. Upon execution of this agreement, Grantor will grant Grantee and its contractor's access to the Property for the purpose stated herein, until such time as the project is completed and approved by the ' Grantee, at which time the above described temporary right of entry becomes void. This Right of Entry shall include the right of Grantee and its employees, agents, representatives,or contractors to accbss the aforementioned property. TO HAVE AND TO HOLD the above described right of entry, together with all and singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee, is successors and assigns,for the purposes set forth above. , Grantee shall restore the Property to the condition it was in immediately prior to accessing the Property under this Right of Entry. EXECUTED this the day of _ 02 2015. GRANTOR: �y Emilio Madrigal Owner (Signature) Ana M.Madrigal An a M .M ,, is A'I Owner (Signature) TEMPORARY RIGHT OF ENTRY ' I Rev. 62007 i DRY BRANCH CREEK Parcel TROE-3 Doe#5425 2225 N CHANDLER DR W BLOCK 3 LOT 14 SPRINGDALE ADDITION CITY OF FORT WORTH TEMPORARY RIGHT OF ENTRY STATE OF TEXAS § § KNOW ALL BY THESE PRESENTS COUNTY OF TARRANT § That the undersigned, hereinafter referred to as "Grantor", does by these presents grant and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a temporary right of entry onto property described as Block 3, Lot 14, Springdale Addition and as shown on the recorded deed in D186555392 Tarrant County deed records a/k/a, 2225 N CHANDLER DR W, Fort Worth, Tarrant County, Texas, hereinafter referred to as the"Property", for the purpose of installation of a new chain- link fence on property line which includes but not limited to any such activities related to the installation of the new fence(post digging,mounting and securing etc.) Upon execution of this agreement, Grantor will grant Grantee and its contractor's access to the Property for the purpose stated herein, until such time as the project is completed and approved by the Grantee, at which time the above described temporary right of entry becomes void. This Right of Entry shall include the right of Grantee and its employees, agents, representatives,or contractors to access the aforementioned property. TO HAVE AND TO HOLD the above described right of entry, together with all and singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee, is successors and assigns, for the purposes set forth above. Grantee shall restore the Property to the condition it was in immediately prior to accessing the Property under this Right of Entry. EXECUTED this the Z3 day of jkk& V - —,2015. GRANTOR: James Hinton Owner ignature) Norma Hinton Owner (Signature) TEMPORARY RIGHT OF ENTRY Rev. 6/2007 DRY BRANCH CREEK Parcel TROE-4 Doe#5425 2221 N CHANDLER DR W BLOCK 3 LOT 15 SPRINGDALE ADDITION CITY OF FORT WORTH TEMPORARY RIGHT OF ENTRY STATE OF TEXAS § § KNOW ALL BY THESE PRESENTS COUNTY OF TARRANT § That the undersigned, hereinafter referred to as "Grantor", does by these presents grant and convey to the City of Fort Worth, TX, herein after refer-red to as "Grantee" a temporary right of entry onto property described as Block 3, Lot 15, Springdale Addition and as shown on the recorded deed in D204221584 Tarrant County deed records a/k/a, 2221 N CHANDLER DR W, Fort Worth, Tarrant County, Texas, hereinafter referred to as the "Property", for the purpose of installation of a new chain- link fence on property line which includes but not limited to any such activities related to the installation of the new fence(post digging, mounting and securing etc.) Upon execution of this agreement, Grantor will grant Grantee and its contractor's access to the Property for the purpose stated herein, until such time as the project is completed and approved by the Grantee, at which time the above described temporary right of entry becomes void. This Right of Entry shall include the right of Grantee and its employees, agents, representatives,or contractors to access the aforementioned property. TO HAVE AND TO HOLD the above described right of entry, together with all and singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee, is successors and assigns, for the purposes set forth above. Grantee shall restore the Property to the condition it was in immediately prior to accessing the Property under this Right of Entry. EXECUTED this the day of Cc�o� ,2015. GRANTOR: Donald Gene Hall_Jr. Owner (Signature) PLL-e C- (49 Z L Z &�O�e Acre-SS , 00 PqD MgpoRARY RIGHT OF ENTRY D " Rev. 6'2007 517- 72 L/-7 / �S-o/� F17 -�3 � �9 � Page 1 of 6 D216049291 311012016 2:24 PM PGS 6 Fee: $36.00 Submitter: XEROX COMMERCIAL SOLUTIONS Electronically Recorded by Tarrant County Clerk in Official Public Records Mary Louise Garcia Project dame(CPN 00485) DOE 4 5425; Parcel #12 2720 NE 286 .St Lot-2, Block-2, Ioma Martin Subdivision CITY OF FORT WORTH TEMPORARY CONSTRUCTION EASEMENT DATE: 1-7-0.2016 GRANTOR: Piyush &Jyotsna Naik, L.L.P. DBA Saljal Properties GRANTOR'S MAILING ADDRESS (including County): P.O. Box 55278 HURST, TEXAS 76054-5278 GRANTEE: CITY OF FORT WORTH GRANTEE'S MAILING ADDRESS (including County): 1000 THROCKMORTON ST. FORT WORTH, TARRANT COUNTY, TX 76102 CONSIDERATION: Ten Dollars ($10.00) and other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged. PROPERTY: Being a parcel of land situated in the J.B.York Survey, Abstract Number 1764, City of Fort Worth,Tarrant County,Texas, being a portion of Lot 2,Block 2, toma Martin Subdivision, an addition to the City of Fort Worth, as recorded in Cabinet B,Slide 2109, Plat Records,Tarrant County,Texas,and as conveyed to Piyush and Jyotsna Nalk, LLP.by Deed recorded in Volume 14460, Page 192, Deed Records,Tarrant County,Texas,and being more particularly described in attached exhibits"A" and "B" " containing 0.067 acres(2,913 sf) Grantor, for the consideration paid to Grantor, hereby grant, bargain and convey unto Grantee, its successors and assigns, the use and passage in, over, and across, below and along the easement situated in Tarrant County, Texas, in accordance with the legal description hereto attached as Exhibit "A", and ingress and egress over Grantor's property to the easement as shown on Exhibit "B". It is further agreed and understood that Grantee will be permitted the use of said easement for the purpose of Drainage Channel Improvements Upon completion of improvements and its acceptance by Grantee, all rights granted within the described Temporary Construction Easement shall cease. TO HAVE AND TO HOLD the above described easement, together with, all and singular, the rights and appurtenances thereto in anyway belonging unto Grantee, and Grantee's successors and assigns until the completion of construction and acceptance by Grantee. Grantor hereby bind themselves. their heirs, successors, and assigns, to warrant and defend, all and singular, said easement unto Grantee, its successors and assigns, against every person whomsoever lawfully claiming or to claim the same, or any part thereof. [SIGNATURES APPEAR ON THE FOLLOWING PAGE] Temporary Carudruclinn F.i4+er"�:r 01109.'200' s Page 2 of 6 GRANTOR: GRANTEE: City of Fort Worth Piyush & Jyotsna Naik, LLP DBA Saijal Prope 'es Piyush Naik Jesus J. Chapa ' Assistant City Manager l Jyotsna Naik APPROVED AS TO FORM AND LEGALITY Assistant ity Atto y i ACKNOWLEDGEMENT STATE OF TEXAS § COUNTY OF TARRANT § BEFORE ME, the undersigned authority, a Notary Public in and for the State of Texas, on this day personally appearedwj+Usk IVr known to me to be the same person whose name is sub cri d to the foregoing instrument, and acknowledged to me that the same was the act of _ 1,4 a 5 h roo" 14' and that he/she executed the same as the act of said 0-k u'j� ly �►t<. for the purposes I and consideration therein expressed and in the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this day of "f , 2016, i� Notgb�pbbin and for thd State of Texas of s � TcnWrare C;on mwwn Eascmcat OI ID9,1007 Page 3 of 6 ACKNOWLEDGEMENT STATE OF TEXAS § COUNTY OF TARRANT § BEFORE ME, the undersigned authority, a Notary Public in and for the State of Texas, on this day personally appeared J , known to me to be the same person whose name is subscribed to the foregoing instrument, and acknowledged to me that the same was the act of unA•SPJA Wtk;%', and that he/she executed the same as the act of said �k�D}-SOA N&.t- for the purposes and consideration therein expressed and in the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this day of r 2016. eJz,��tlfµiNJJJJ/�� Glwl ' Not P blic in d for S to of as CA B Off ` qy 1 { i i j Temporuy Consnctioq Egsemaa m,vQ;uo� E Page 4 of 6 ACKNOWLEDGEMENT STATE OF TEXAS § COUNTY OF TARRANT § BEFORE ME, the undersigned authority, a Notary Public in and for the State of Texas, on this day personally appeared Jesus J. Chapa, Assistant City Manager of the City of Fort Worth, known to me to be the same person whose name is subscribed to the foregoing instrument, and acknowledged to me that the same was the act of the City of Fort Worth and that he/she executed the same as the act of the City of Fort Worth for the purposes and consideration therein expressed and in the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this day of , 2016. Notary Public in and for the St a of Texas ,aeek •'��kR PVO "'� ttreUq n!. H1RR F-rRf;C F+N�fl9 E" �e a�r Je"3$ Y!D i2d)dd)d.e, Torilxna:y Cmut:ucteai F�na:l i 01+09:2007 's Page 5 of 6 DRY BKMCI-3 CREEK D_RY BXANCH CR_EEIK DOE 4 54215:P-a-_-17= TCE-2 NIPOR ON EME IT 1E, A-RY Ct NSTRUCTION EASE '.� ACQUISITION FOR WORTH,TFKAS. TCE-2 J.2,YOPT"".SJR-e EY, A-1 7_54 4 C "D:. YCF BE:yr: A _DARC=,:, OF LA1,:0 ARST:,�ACT OU`,Mz­ __ ?5 T WORTF, TARR.AN-_ CZ--u-N71', TZN�5, _REING P. PI-1-MON CIF AN PCZ-.11,)y =S _tJ Cp _B7',jET E, SLT01 PLAT RECORDS, TA�?,A,'.-T COUNT'f, 7_En= , Ay"ED AS TO 7 YU.S jj RND �YOTSMa NA.K, LLE-.,D/P/A 5 zJj:-1_1 BY DEED R-ECCRDED !F PAIG 1921 EJEFS TARi;ANT_ CGUNT., 34EirG _,-%'CRZ ?AK 7 CU_'LZ_R:,Y ET-SCR-73ED B'_; VE-7ES TN:) SOWDS AS FOLLOWS: CoMaINCIN-c- AT A 1-112 INC"; 1RCM ROD FOUND FOR THE SCUTE3A3T COR',\'E� OF _10�1 -1, iiLOCK 2, 0 T SAID IOMA MA.TTN I TP7_ !';iS- R:C:F7-0 F-W'A.y -Tj-jZ CF I - -4 AVZFI:JE (VARTP-BLE WIDTH RICHT_-)F-IWAYI AND THE NCRTE R2G3T 0-7 WAY LIVE OF 1VEY STREFT -VA31A3LE WIDTH TJ-Hq- op'-WAY TH=NCEE NCRi'H GO DEGREES 42 tdT_LVU'_:ES 09 SECONDS WSE!, i39.68 F-E-ET WITB THE EAST LINE OF SA.11) LOT 3, TO THE SOUTHEAST C-C-RMU, 07 SAIL 1,07' 2, T'N THE WEST LINE OF SAID 3LAND111 AVEMM AN�) THE POINT OF BEGINN1211C,; THMVCE MR-H 77 DEGREES 21 1,11NUTES SECONDS :'EST, 116-37 FEET- TO '11FE SOUTHWEST CORNER OF SATED LOT 2, AND THE SOCT:j ';'ZT COXINER OF LOT 1-P. OF SAID BLOCF 2; T'j✓ITC"Er NCRTH 01 1)�G�ZES 1� MINUTES 07 SECCNDS WEST, 25.715 FTET WITH THE COMIMCP LINE 02 SAID LOT 2, AND SAID I0,7 1-R; ' TIMINCE SOUTH 77 DEEGREES 21 MINUTES 4 SECONDS EAST, 116.E3 -TEET TO THE EAST LINE OF SAID SOT 2, 4 SOU-TH 00 DZG - RZES 9.1 MINUTES 09 SECCNDS EAST, .2E.69 FEE-- TO TEE POINT OF BEGINNING AAD CONTA-INING 2,913 34UI-R2 FEET CR. 0.067 ACRE CF LAND MORE OR LESS. Note: SUV.7eyed 011 the ground Se-ptembe!: 2014. Note: 3ea--incs are relative tc True North cbtained frcm Global Pcsitioning Satellite S,iste-m (GPS) Observations, North American Da-win 1963 (111.zD '83) , Texas State Plane Coordinate System, North Central Zone. IL40te: Tn acccrdance wizh the Texas Bca-d of Professional Land Su::weying General Rules of Proced"ITez and Practices, 663.19(9) , this "Rerlcr_­ corsists of the Real Prcperty Des�_riotion includer-4 "-e-rein and the Map of, Survey attacted hezewlth. SDSVARG X L 4; 9-1 S R\j A.N-A.COMLItants,L.L.C. Page I of I 5000 Thompson Terrace Colleyyflle,TX 76034 REVISION: 11-04-15 Page 6 of 6 3roject; 0607ZB try Erzn= Wash M W Oaata wa,cha& Rajw=ts LO Ta r T=--7 �-A DeSCAPOWS.. WSIZIPOS-7 Lot Men. faquwa zamj : 2512.5 Lot Was (Ac=ss) COES57 ict 3swOmetaz: VS.& Mant Arms Squaw Fee=) : 0.01, Cicsing DOWNS: SHIC2,240-J CIMMAS Distance: 5.006 Co--3:2 Dana; T�~01;ch :Za�iUs 3oi-::::S L,-Tet)-I--d' --------------------------------------------------- ---------------------- Acwthing Easting rizeption Distance Begin S9720S1.153391 WK144.047417 S7712VIVE MAU 690533.721475 233037.0100 SOOKIONZ 23.692 5SKMAMIS 2335253.10507 AMMAN 16.372 6374035.EC2472 2335144-610333 WOOVIGOW 2E.754 S06 EA7400.25024 Err=x of closure Dapaxtura in Y (Yarthlry) : Bepwtoxa in M (RaStAgIl Ei Page 1 of 5 D215272609 12/712015 8:21 AM PGS 5 Fee: $32.00 Submitter:XEROX COMMERCIAL SOLUTIONS Electronically Recorded by Tarrant County Clerk in Official Public Records f �r ►� a+c�.t� Mary Louise Garcia Project Name(CPN 00485) DOE#5425; Parcel#3 2300 Blandin Street Lot-1,Block- 1,J.B.York Addition CITY OF FORT WORTH TEMPORARY CONSTRUCTION EASEMENT DATE: j 1 -i '7 -ZOiS- GRANTOR: DONALD J. KLICK GRANTOR'S MAILING ADDRESS (including County): P.O. BOX 7592 FORT WORTH, TX 76111-0592 GRANTEE: CITY OF FORT WORTH GRANTEE'S MAILING ADDRESS (including County): 1000 THROCKMORTON ST. FORT WORTH, TARRANT COUNTY, TX 76102 CONSIDERATION: Ten Dollars ($10.00) and other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged. PROPERTY: Being a parcel of land situated In the J.B.York Survey,Abstract Number 1754,City of Fort Worth,Tarrant County,Texas,being a portion of Lot 1,Block 1,J. B.York Addition, an addition to the City of Fort Worth, as recorded in Volume 388-186, Page 66, Plat Records,Tarrant County,Texas,as conveyed by deed to Donald J.Mick, recorded in Volume 15421, Page 27, Deed Records,Tarrant County,Texas, and being more particularly described in attached exhibits"A" and"B" containing 0.037 acres(1,592 sf) Grantor, for the consideration paid to Grantor, hereby grant, bargain and convey unto Grantee, its successors and assigns, the use and passage in, over, and across, below and along the easement situated in Tarrant County, Texas, in accordance with the legal description hereto attached as Exhibit "A", and ingress and egress over Grantor's property to the easement as shown on Exhibit"B". I� It is further agreed and understood that Grantee will be permitted the use of said easement for the purpose of Drainage Channel Improvements Upon completion of improvements and its acceptance by Grantee, all rights granted within the described Temporary Construction Easement shall cease. TO HAVE AND TO HOLD the above described easement, together with, all and singular, the rights and appurtenances thereto in anyway belonging unto Grantee, and Grantee's successors and assigns until the completion of construction and acceptance by Grantee. Grantor hereby bind themselves, their heirs, successors, and assigns, to warrant and defend, all and singular, said easement unto Grantee, its successors and assigns, against every person whomsoever lawfully claiming or to claim the same, or any part thereof. [SIGNATURES APPEAR ON THE FOLLOWING PAGE] TMVMuy CWS"4=6MMCM 0l/09/ZOO7 I Page 2 of 5 GRANTOR: GRANTEE: City of Fort Worth Donald J. Klick Jesus J. Chapa Assistant City Manager APPROVED AS O FORM AND LEGALITY Assists City Aftchey S7 i G �nSSvzr,� ACKNOWLEDGEMENT STATE OF TEXAS § COUNTY OF TARRANT § BEFORE ME, the undersi authority, a Notary Public in and for the State of Texas, on this day personally appeared I -T In-1: c-h , known to me to be the same person whose name is subscribed to the foregoing instrument, and acknowledged to me that the same was the act of U; L IL _ and that he/she executed the same as the act of said for the purposes and consideration therein expressed and in the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this 17'"— day of 2015. � � Notary Public in and for the ttate of Texas STATE OF CK my tonm t"P,jdv Temporary ConshK lion Ememad o1109nom Page 3 of 5 ACKNOWLEDGEMENT STATE OF TEXAS § COUNTY OF TARRANT § BEFORE ME, the undersigned authority, a Notary Public in and for the State of Texas, on this day personally appeared Jesus J. Chava, Assistant City Manager of the City of Fort Worth, known to me to be the same person whose name is subscribed to the foregoing instrument, and acknowledged to me that the same was the act of the City of Fort Worth and that he/she executed the same as the act of the City of Fort Worth for the purposes and consideration therein expressed and in the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this day of , 2015. Apctp- I U U �1 Notary Public in and for the State Texas 11.11. LINDA M.MMU.%ER My XPIn ISSfON�yp��Fs FskafYA 201$ Temporary Construction Easement O V092007 - - Page-4-of-6 -6-- - DRY BRANCH CREEK DRY BRANCH CREEK DOE#_5425;Parcel# TCE-3 TEMPORARY CONSTRUCTION EASEMENT 2300 BLANDIN ST. ACQUISITION FORT WORTH,TEXAS. TCE-3 I.B.YORK SURVEY,A-1754 EXHIBIT ^A" REAL PROPERTY DESCRIPTION OF A 10 FOOT WIDE TEMPORARY CONSTRUCTION EASEMENT BEING A PARCEL OF LAND SITUATED IN J.B. YORK SURVEY, ABSTRACT NUMBER 1754, CITY OF FORT WORTH, TARRANT COUNTY, TEXAS, BEING A PORTION OF LOT 1, BLOCK 1, J.B. YORK ADDITION, AN ADDITION TO CITY OF FORT WORTH, AS RECORDED IN VOLUE 388-186, PAGE 66, PLAT RECORDS, TARRANT COUNTY, TEXAS, AS CONVEYED BY DEED TO DONALD J. KLICK, RECORDED IN VOLUME 15421 PAGE 27, DEED RECORDS, TARRANT COUNTY, TEXAS, AND BEING MORE PARTICULARLY DESCRIBED BY METES AND BOUNDS AS FOLLOWS: BEGINNING AT A 5/8 INCH IRON ROD FOUND FOR THE SOUTHEAST CORNER OF SAID LOT 1, BLOCK 1, AND THE NORTHEAST CORNER OF LOT 1, BLOCK 2, SPRINGDALE ADDITION, RECORDED IN VOLUME 1191, PAGE 1, OF SAID PLAT RECORDS; THENCE SOUTH 89 DEGREES 36 MINUTES 50 SECONDS WEST, 172.21 FEET WITH THE COMMON LINE OF SAID LOT 1, J.B. YORK ADDITION AND SAID LOT 1, BLOCK 2; r THENCE NORTH 03 DEGREES 47 MINUTES 50 SECONDS EAST, 10.03 FEET; THENCE NORTH 89 DEGREES 36 MINUTES 50 SECONDS EAST, 138.17 FEET TO THE NORTH LINE OF SAID LOT 1, J.B. YORK ADDITION; THENCE SOUTH 77 DEGREES 32 MINUTES 54 SECONDS EAST, 34.21 FEET WITH THE NORTH LINE OF SAID LOT 1, J.B. YORK ADDITION TO A 5/8 INCH IRON ROD FOUND FOR THE NORTHEAST CORNER OF SAID LOT 1, J.B. YORK ADDITION; THENCE SOUTH 00 DEGREES 30 MINUTES 49 SECONDS WEST, 2.40 FEET WITH THE EAST LINE OF SAID LOT 1, J.B. YORK ADDITION, TO THE POINT OF BEGINNING AND CONTAINING 1,592 SQUARE FEET OR 0.037 ACRES OF LAND MORE OR LESS. Note: Surveyed on the ground September 2014. Note: Bearings are relative to True North obtained from Global Positioning Satellite System (GPS) Observations, North American Datum 1983 (NAD '83) , Texas State Plane Coordinate System, North Central Zone. i Note: In accordance with the Texas Board of Professional Land Surveying General Rules of Procedures and Practices, 663.19(9), this "Report" consists of the Real Property Description included herein and the Map of Survey attached herewith. F. T �p 4 STEq�,F� EDWAR0K.KHALiL ---------------------V.. 5951 r= C9 y°yE�S�N��4 ti0 SUR%Ay A.N.A.Consultants,L.L.C. Page 1 of I 5000 Thompson Terrace Colieyville,TX 76034 REVISION:09-01-15 I I I Page 6 of 5.-- LOT 21,BLOCK 3 LOT 23,BLOCK 3 SPRINGDALE ADDITION SPRINGDALE ADDITION VOLUME 368-I42,PAGE 71 VOLUME 388-159,PAGE 81 P.R.T.C.T. N Apparent Owner. City of Fort Worth D212036282 D.R.T.C.TX. Ui C! Apparent Owner. ICIty of Fort Worth Dr 'n ,Branch Creek R.O.W. Z8 'I. Scale 10 60' Z5 3: D.R.VIP-840 W 10 FOOT WIDE z-j mo TEMPORARY CONSTRUCTION s EASEMENT .......... ................ 1,592 SO.FT.+/- 34.21' 111� S77.32'54"E I� o C!lu N, j , Apparent Owner: R'sb-'\ Donald J Klk* -\G' Vol.16421,Pg.27 N89*36'50'E 138.1 r 2.40' IR %7" SOO*3(r49W D.R-T.C.TX S89036'50V 17221' pos 10.03 dt� p aomf Forot Wo NO3,4rso"E ' R M D212CM82 D.P.T.C.TX. LOT BLK 2 APPerent Owner. Rodrigo&Petra L Mahnino D20409MIT LOT2 D.R.T.C.TX OF if C711 'STE S T E LOT EXHIBIT "B" + * SHOW I NG EDWARD K. KHALI A 10 FOOT W I DE TEMPORARY s sio CONSTRUCTION EASEMENT OUT OF LOT 1 . BLOCK 1, J. B. YORK ADDITION, S i grveds CITY OF FORT WORTH. Dater TARRANT COUNTY, TEXAS Mote,J—_ DPJNMN Bye AL A.N.A.CONSULTANTS,L.L.C. DATEs 04-28-15 smi;Lon, mqw Tarom Dm% ms=700-TCE-INT-3 CO $76034 Of LIT (817)335-9900 APPRDVM Bye EK Foe (817)335-"55 SW.?NaD. I OF I ism 09-01-15 FJLN0.10090800 Page 1 of 6 D216004097 1181201611:22 AM PGS 6 Fee: $36.00 Submitter:XEROX COMMERCIAL SOLUTIONS Electronically Recorded by Tarrant County Clerk in Official Public Records � PwQ�Y�a+�•.:. Mary Louise Garcia Project Name (CPN 00485} DOE #5425; Parcel# 4 2232 Blandin Street Lot-2,Block-2, Springdale Addition CITY OF FORT WORTH TEMPORARY CONSTRUCTION EASEMENT DATE: GRANTOR: RODRIGO & PETRA L. MATURING GRANTOR'S MAILING ADDRESS (including County): 2232 BLANDIN STREET FORT WORTH, TX 76111-2905 GRANTEE: CITY OF FORT WORTH GRANTEE'S MAILING ADDRESS (including County): 1000 THROCKMORTON ST. FORT WORTH, TARRANT COUNTY, TX 76102 CONSIDERATION: Ten Dollars (S10.00) and other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged. PROPERTY: Being a parcel of land situated in the J.S.York Survey, Abstract Number 1754,City of Fort Worth,Tarrant County,Texas, being a portion of Lot 2,Block 2, Springdale Addition,an addition to the City of Fort Worth,as recorded in Volume 1191, Page 1, Plat Records,Tarrant County,Texas,as conveyed by deed to Rodrigo and Petra L. Maturino, recorded in Instrument Number D204098417, Deed Records,Tarrant County,Texas, and being more particularly described in attached exhibits"A" and "B" containing 0.040 acres (1,756 sf) Grantor, for the consideration paid to Grantor, hereby grant, bargain and convey unto Grantee, its successors and assigns, the use and passage in, over, and across, below and along the easement situated in Tarrant County, Texas, in accordance with the legal description hereto attached as Exhibit "A', and ingress and egress over Grantor's property to the easement as shown on Exhibit "B". It is further agreed and understood that Grantee will be permitted the use of said easement for the purpose of Drainage Channel Improvements Upon completion of improvements and its acceptance by Grantee, all rights granted within the described Temporary Construction Easement shall cease. TO HAVE AND TO HOLD the above described easement; together with, all and singular, the rights and appurtenances thereto in anyway belonging unto Grantee, and Grantee's successors and assigns until the completion of construction and acceptance by Grantee. Grantor hereby bind themselves, their heirs, successors, and assigns, to warrant and defend, all and singular, said easement unto Grantee, its successors and assigns, against every person whomsoever lawfully claiming or to claim the same, or any part thereof. [SIGNATURES APPEAR ON THE FOLLOWING PAGE] Temporu}Construction Eum.ent 01'09 2007 Page 2of6 GRANTOR: GRANTEE: City of Fort Worth odrigo Ae wrino Jp6us J. Chaps Assistant City Manager .r Petra L Maturino APPROVED AS FORM AND LEGALITY Assists o r - yS ACKNOWLEDGEMENT STATE OF TEXAS COUNTY OF TARRANT § BEFORE ME, the undersigned authority, a N-o Public in and for the State of Texas, on this day pemonaAy appeared(YAQ-W o? known to me to be the same person whose name is subscibed to the faremoing Instrument. and acbww edged to me that the same was the act of i ► '6 and that h&%he executed the same as the act of said v i for the purposes and aorwideretion therein expnmed and In the capacity rein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this day of I 2015. � III JAY Ww� "•'W Notary Public in and for the State of Texas RIA L.UISA GANDARA NOT ARY PU6UC XAS STATE OF TE Comm. UP,9/7116 x r�osnotrr�vomo" 0 Page 3 of 6 ACKNOWLEDGEMENT STATE OF TEXAS § i COUNTY OF TARRANT BEFORE ME, the undersignd authority, a Noy Public in and for the State of Texas, on this day personally appeared Ivw m to me to be the same person whose name is sub4cribed Vv foregoing instrurrient, and acknowledged to me OW the same was the act of t. �'�`+ and that he/she executed the same as the act of said ti for the purposes Said consideration therein expressed and In the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this - day of 0L_CQ4,V001Y- i r l°Y , 2015. Notary Public in and for the State of Texas s �,. MARIA WISA WIDARt NOTARY PUBLIC STATE OF TEDAS MY COMM.fXP 91711 S i F-- t T=WmWyC0mmUW=S"mam OU09f200T Page 4 of 6 3 ACKNOWLEDO"EMENT STATE OF TEXAS E COUNTY OF TARRANT $ r BEFORE ME, the undersigned authority a ;votary Public In and for the State of Texas, on this day personally appeared Manager of the City of Fort Worth, known to me to be the same person whose name is subscribed to the foregoing instrument, and adamowledged to me that the same was the act of the City of Fort Worth and VW he/she executed the same as the act of the City of Fort Worth for the purposes and conskkwation therein expressed and in the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this day of s ' 2015. i s N is in and for the State of 13was mom LeLitP&�4 tA Ilia 1AY M'5 r E i 's t E r i i 3 i ovoor�oor . t i E . E Page 5 of 6 DRY BRANCH CREEK DRY BRANCH CREEK DOE# 5425;Parcel# TCE4 TEMPORARY CONSTRUCTION EASEMENT 2232 BLAVDLti ST. ACQUISITION FORT WORTH,TEXAS. TCE-4 1.8.YORK SURVEY,A-1 1154 EXHIBIT "A" REAL PROPERTY DESCRIPTION OF A 10 FCOT WIDE TEMPORARY CONSTRUCTION EASEMENT BEING A PARCEL OF LAND SIT_UAT ,D IN J.B. YORK SURVEY, ABSTRACT NUMBER 1754, CITY OF FORT WORTH, TARRAIIT COUNTY, TEXAS, BEING A PORTION OF LOT 2, BI-CCK 2, SPRINGDALE ADDITICN, AN ADDITION TO CITY OF FORT WORTH, AS RECORDED IN VCLUME 1'91, PAGE 1, PLAT RECORDS, TARRAN'T COUNTY, TEXAS, AS CONVEYED BY DEED TO RODRIGO AND PETRA L. MATURINO, RECORDED IN INSTRUMENT NUMBER D204098417, DEED RECORDS, T.ARRANT COUNTY, TEXAS, AND BEING MORE PARTICULARLY DESCRIBED BY 2,ETES AND BOUNDS AS FOLLCWS: COMMENCING AT A 1/2 INCH IRON ROD FOUND FOR THE NORTHWEST CORNER OF SAID LOT 2, AND THE SOUTHWEST CORNER OF LOT 1, OF SAID BLOCK 2, IN THE EAST RIGHT-OF-WAY LINE OF BLA.NDIN AVENUE (VARIABLE WIDTH RIGHT-OF-WAY) ; THENCE NOR"- 89 DEGREES 36 MINUTES 50 SECONDS EAST, 123.85 FEET °EDITH THE COMMON LINE OF SAID LOT 1, AND SAID LOT 2, BLOCK 2, TO THE POINT. OF BEGINN_NG; THENCE NORTH 69 DEGREES 36 MINUTES 50 SECONDS EAST, 175.69 FEET WITH THE COMMON LINE OF SAID LOT 1, P-ND SAID LOT 2, BLOCK 2, TO THE NORTHEAST CORNER OF SP_T_D LOT 2; THENCE SOUTH 00 DEGREES 08 MINUTES 59 SECONDS WEST, 10.00 FEET WITH THE EAST LIVE OF SAID LOT 2, OF SAID BLOCK 2; THENCE SOUTH 89 DEGREES 36 MINUTES 50 SECONDS WEST, 175.60 FEET; THENCE NORTH 00 DEGREES 23 MINUTES 10 SECONDS WEST, 10.00 FEET TO THE POINT OF BEGINNING AND CONTAINING 1,756 SQUARE FEET OR 0.040 ACRE OF LAND MORE OF LESS. Note: Surveyed on the ground September 2014. Note: Bearings are relative to True North obtained from Global Positioninc Satellite System (GPS) Observations, North American Datum 1963 (NAD '63) , Texas State Plane Coordinate System, North Central Zone. Note: In accordance with the Texas Board of Professional Land Surveying General Rules of Procedures and Practices, 663.19(9), this "Report" consists of the Real Property . Description included herein and the Map of Survey attached 'herewith. 0 F TF EDWARD K.KHALL =.4 5951 � tiQ SURD A.N.A.Consultants,L.L.C. Page i of 1 5000 Thompson Terrace Colleyville,TX 76034 REVISION; 11-04-15 Page 6 of 6 i ( I Apparent Caner. CEty o Fort YVcrth N L1412036232 i I r.PIT.C.?X. i Apparent Owner: City of Fort`PJcnh Vol.4479,Pg.840 0,R r. Tk i 1 Fw� E PPG Apparent Crvn Scale 1" Donald J,{tick Vr1.15421,Pj v�1�Q D.R.T.C.TX. I LOT 1 FOOT WIDE 3 Apparent Comer LL City of Fort Wcrth POE TEMPORARYCCSTR UCTIONjt,'+� �t ' 111 O 0212036262 EASEMENT I+ ( D.R.T.C.TX. 8!00'23'10"1M1/ 1,756 SQ.FT.+/- ' Q 10.00' , j I I S00°08'59"VJ _Z ;j°IRF 123.85 j N89-36'50:'E / 175.69' J r 10.00' { Q� N99°3o8u"'E i ! i !i _ZZ.I 3 { FOC OOH C01� 17c-.60' S89'36150"141i I I t t5] c Q�• �1, Apparent Omer. + r. Rodngo&Petra L Maturino D22*04098417 , z gP)o�,vrpQ" LOT 2 D.FLT.C.T,C # S89'36150"W I J 25.00' Apparent Owner. 8LK + � I Paut O MBnisavan LOT 3 012D802s3'21 2 14 I D.R.T.C.TX. I i!! Apparent Owner. J LOT 4 Juvenet Rccidguez i D208403398 � D.R.T.C.TX EXHIBIT 17$17 1 EDWARD x.KHALIL• SHOWING J(, "'•".` 595".."1 A 10 FOOT WIDE TEMPORARY 595" �q`'•°..�fs51,°.rr0� CONSTRUCTION EASEMENT sug1j OUT OF LOT 2, 91-OCK 2- SPRINGDALE ADDITION, Signeef�-- CITY OF FORT WORTH, Date:If-r_ t TARRANT COUNTY. TEXAS DRAYIN BY: JV Ak A.N.A. CONSULTANTS,L.L.C. DATE: C4-28-15 00N. N0.:060T00-TCE-!NT-4 500G T'wmpsan Temce I enKS��rwars.L.:_c. Collcy,41c,Thus 7t>34 + i APPROVED BY: Ex Office.- (817)335-4900 Fm (t+Y7)335-9955 ISHT.W., t CF I tzJ11u3Q --REVISED: 11-04-15 F.R VQ.10090800 , i ATTACHMENT 1A Page 1 of 4 FORT WORTH City of Fort Worth Minority Business Enterprise MBE Subcontractors/Suppliers Utilization Form OFFEROR COMPANY NAME: Check applicable block to describe Offeror PROJECT NAME: MAN/DBE NON-MNWDBE BID DATE DAY 16R- City's 44BE Project Goal: Offeror's MBE Project Commitment: PROJECT NUMBER /r% 5-*-'/. O b Identify all subcontractors/suppliers you will use on this project Failure to complete this form, in its entirety with requested documentation, and received by the Purchasing Division no later than 2:00 p.m. on the second City business day after bid opening, exclusive of bid opening date, will result in the bid being considered non-responsive to bid specifications. The undersigned Offeror agrees to enter into a formal agreement with the MBE firm(s) listed in this utilization schedule, conditioned upon execution of a contract with the City of Fort Worth. The intentional and/or knowing misrepresentation of facts is grounds for consideration of disqualification and will result in the bid being 1considered non-responsive to bid specifications. MBEs listed toward meeting the project goal must be located in the six (6) county marketplace at the time of bid or the business has a Significant Business Presence in the Marketplace. Marketplace is the geographic area of Tarrant, Dallas, Denton, Johnson, Parker, and Wise counties. Prime contractors must identify by tier level of all subcontractors/suppliers. Tier: means the level of subcontracting below the prime contractor/consultant i.e. a direct payment from the prime contractor to a subcontractor is considered 15'tier, a payment by a subcontractor to its supplier is considered 2nd tier. The prime contractor is responsible to provide proof of payment of all tiered subcontractors identified as a MBE and counting those dollars towards meeting the contract committed goal. ALL MBEs MUST BE CERTIFIED BEFORE CONTRACT AWARD. Certification means those firms, located within the Marketplace, that have been determined to be a bondafide minority business enterprise by the North Central Texas Regional Certification Agency(NCTRCA) or other certifying agencies that the City may deem appropriate and accepted by the City of Fort Worth. If hauling services are utilized, the Offeror will be given credit as long as the MBE listed owns and operates at least one fully licensed and operational truck to be used on the contract. The MBE may lease trucks from another MBE firm, including MBE owner-operated, and receive full MBE credit. The MBE may lease trucks from non-MBEs, including owner-operated, but will only receive credit for the fees and commissions earned by the MBE as outlined in the lease agreement. Rev.2/10/15 FURT`ORTH ATTACHMENT IA Page 3 of 4 Offerors are required to identify ALL subcontractors/suppliers, regardless of status; i.e., Minority and non-MBEs. MBE firms are to be listed first, use additional sheets if necessary. Please note that only certified MBEs will be counted to meet an MBE goal. NCTRCA N SUBCONTRACTOR/SUPPLIER ° Company Name T n Detail Detail Address i Subcontracting Supplies Dollar Amount Telephone/Fax ' B B B Work Purchased Email E E Contact Person E N kfl 7-AuckN5 adA s�v►NS ,Tjc.7So61 ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ Rev.2/10/15 FOR ATTACHMENT 1A i Page 4 of 4 Total Dollar Amount of MBE Subcontractors/Suppliers $ Total Dollar Amount of Non-MBE Subcontractors/Suppliers $ ID [ 73 TOTAL DOLLAR AMOUNT OF ALL SUBCONTRACTORS/SUPPLIERS $ D 3 7 3 The Offeror will not make additions, deletions, or substitutions to this certified list without the prior approval of the Minority and Women Business Enterprise Office through the submittal of a Request for Approval of Change/Addition form. Any unjustified change or deletion shall be a material breach of contract and may result in debarment in accord with the procedures outlined in the ordinance. The Offeror shall submit a detailed explanation of how the requested change/addition or deletion will affect the committed MBE goal. If the detail explanation is not submitted, it will affect the final compliance determination. By affixing a signature to this form, the Offeror further agrees to provide, directly to the City upon request, complete and accurate information regarding actual work performed by all subcontractors, including MBE(s) and any special arrangements with MBEs. The Offeror also agrees to allow an audit and/or examination of any books, records and files held by their company. The Offeror agrees to allow the transmission of interviews with owners, principals, officers, employees and applicable subcontractors/suppliers participating on the contract that will substantiate the actual work performed by the MBE(s) on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment from City work for a period of not less than three (3) years and for initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this ordinance creates a material breach of the contract and may result in a determination of an irresponsible Offeror and debarment from participating in City work for a period of time not less than one (1) year. ���./G� ZloWe- /✓ kt k! , Authorized sigg(nature Printed Signature / A Title /n� / __// , Contac NamefTitle(if d ent) op A 1" (�t57`�'dy!`id✓1� L X21 -,239 -qv-2- Company Name Telephone and/or Fax A&✓5evt r���y Address E-mail AddrwA City/State2lp Date Rev.2/10/15 2013 PREVAILING WAGE RATES (Commercial Construction Projects) CLASSIFICATION DESCRIPTION Wage Rate AC Mechanic $ 25.24 AC Mechanic Helper $ 13.67 Acoustical Ceiling Installer $ 16.83 Acoustical Ceiling Installer Helper $ 12.70 Bricklayer/Stone Mason $ 19.45 Bricklayer/Stone Mason Trainee $ 13.31 Bricklayer/Stone Mason Helper $ 10.91 Carpenter $ 17.75 Carpenter Helper $ 14.32 Concrete Cutter/Sawer $ 17.00 Concrete Cutter/Sawer Helper $ 11.00 Concrete Finisher $ 15.77 Concrete Finisher Helper $ 11.00 Concrete Form Builder $ 15.27 Concrete Form Builder Helper $ 11.00 Drywall Mechanic $ 15.36 Drywall Helper $ 12.54 Drywall Taper $ 15.00 Drywall Taper Helper $ 11.50 Electrician (Journeyman) $ 19.63 Electrician Apprentice(Helper) $ 15.64 Electronic Technician $ 20.00 Floor Layer $ 18.00 Floor Layer Helper $ 10.00 Glazier $ 21.03 Glazier Helper $ 12.81 Insulator $ 16.59 Insulator Helper $ 11.21 Laborer Common $ 10.89 Laborer Skilled $ 14.15 Lather $ 12.99 Metal Building Assembler $ 16.00 Metal Building Assembler Helper $ 12.00 Metal Installer(Miscellaneous) $ 13.00 Metal Installer Helper(Miscellaneous) $ 11.00 Metal Stud Framer $ 16.12 Metal Stud Framer Helper $ 12.54 Painter $ 16.44 Painter Helper $ 9.95 Pipefitter $ 21.22 Pipefitter Helper $ 15.39 Plasterer $ 16.17 Plasterer Helper $ 12.85 Plumber $ 21.98 Plumber Helper $ 15.85 Reinforcing Steel Setter $ 12'..87 Page 1 of 2 Reinforcing Steel Setter Helper $ 11.08 Roofer $ 16.90 Roofer Helper $ 11.15 Sheet Metal Worker $ 16.35 Sheet Metal Worker Helper $ 13.11 Sprinkler System Installer $ 19.17 Sprinkler System Installer Helper $ 14.15 Steel Worker Structural $ 17.00 Steel Worker Structural Helper $ 13.74 Waterproofer $ 15.00 Equipment Operators Concrete Pump $ 18.50 Crane, Clamsheel, Backhoe, Derrick, D'Line Shovel $ 19.31 Forklift $ 16.45 Foundation Drill Operator $ 22.50 Front End Loader $ 16.97 Truck Driver $ 16.77 Welder $ 19.96 Welder Helper $ 13.00 The prevailing wage rates shown for Commercial construction projects were based on a salary survey conducted and published by the North Texas Construction Industry(Fall 2012) Independently compiled by the Lane Gorman Trubitt,PLLC Construction Group. The descriptions for the classifications listed are provided on the TEXO's(The Construction Association)website. www.texoassociation.org/Chapter/wagerates.asp Page 2 of 2