HomeMy WebLinkAboutOrdinance 22361-08-2016 ORDINANCE NO.22361-08-2016
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE SEWER CAPITAL PROJECTS FUND IN THE
AMOUNT OF $504,800.00,FROM AVAILABLE FUNDS,FOR THE PURPOSE OF
FUNDING SANITARY SEWER REHABILITATION, CONTRACT 84;
PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN
CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2015-2016 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Sewer
Capital Projects Fund in the amount of $504,800.00, from available funds, for the purpose of funding
Sanitary Sewer Rehabilitation,Contract 84.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance No. 21873-09-2015 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas W.Black, �,a J.te ,Sr.Assistant City Attorney ty Sec
ADOPTED AND EFFECTIVE:August 16.2016
Ordinance No.22361-08-2016
Page 1 of 1
MAYOR AND COUNCIL COMMUNICATION MAP
60SSR84-CIRCLEC
T ER T
co
-— Lu
co
71
ag
r
^ p
Z
LL
NE 29TH wp 9 r r
t
1. elk }
'L
dl
,
' SELK AVE, IVEY ST.-
z z, � � .,, r'
co 0 p �� L:
— J
i m '
F�Tl
- . r u o m N ILA
fF
HOLLIS ST J k °I #"�HOLLIS"ST
,
� � � 1
;Z4_3 le r, f
r h 714 1
-j
i. ELMA ST,''
cox
.'
FORTWORTH ,
4 -
I ! �� s �SPRINGDALE RD ,
A
Mill
Fiala#
BNB. k �� �
1111111 FII MINE
Milk
wit
HIS
mill 11 F
' now •
Mawr
„rte
„ •, °µ Will
1i
Motor
., MIS
Colm " "P1 1.011 .
01sw ftllz�fli
�. 111111VAR w
FoRTWORTH
,�� � �
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 8/16/2016 - Ordinance No. 22361-08-2016 & 22312-08-
2016
DATE: Tuesday, August 16, 2016 REFERENCE NO.: C-27876
LOG NAME: 60SSR84-CIRCLEC
SUBJECT:
Authorize Execution of a Contract with William J. Schultz, Inc. d/b/a Circle "C" Construction Company, in
the Amount of$3,534,032.50 for Sanitary Sewer Rehabilitation, Contract 84 in the Carter Riverside
Neighborhood, Provide for Project Costs and Contingencies for a Total Project Amount of$4,108,432.50
and Adopt Appropriation Ordinances (COUNCIL DISTRICT4)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Sewer Capital Projects Fund in the amount of$504,800.00 from available funds;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Clean Water State Revolving Fund in the amount of$2,969,839.00 from available funds; and
3. Authorize the execution of a contract with William J. Schultz, Inc. d/b/a Circle "C" Construction
Company, in the amount of$3,534,032.50 for Sanitary Sewer Rehabilitation, Contract 84.
DISCUSSION:
On March 1, 2011, Mayor and Council Communication (M&C C-24754) the City Council authorized an
Engineering Agreement with RJN Group, Inc., the preparation of plans and specifications for Sanitary
Sewer Rehabilitation, Contract 84.
This Mayor and Council Communication is to authorize a construction contract for the replacement of the
deteriorated sanitary sewer mains located on the following streets and easement locations:
Stree JFrom ITo
U.S. 377 JYucca Avenue North Beach Street
North Beach Street U.S. 377 Springdale Road
Springdale Road INorth Beach Street North Riverside Drive
250 feet west of the 250 feet east of the
Honeysuckle Avenue Honeysuckle Avenue/Brittain Honeysuckle Avenue / Brittain
Street Intersection Street Intersection
Brittain Street ISpringdale Road Selma Street
Selma Street Brittain Street 1500 feet east
Logname: 60SSR84-CIRCLEC Page I of 4
lKearby Street Beryl Street 1200 feet east
Easement between Barbell [Hollis Street
Lane and David Street 1,050 feet north
Easement located 150 feet
south of the N.E. 28th [150 feet west F250 feet west
Street/David Street r
Easement between Fairview
Street and Robinwood Drive Hollis Street ISelk Avenue
Easement between
Robinwood Drive and Brittain Hollis Street Selk Avenue
Street
Easement between Brittain Hollis Street ISelk Avenue
Street and Beryl Street -
From 1,000 feet west of Beach
N.E. 28th Street Street/N.E. 28th Street [600 feet east
Intersection
Elinor Street N.E. 28th Street 11,250 feet north
The project was advertised for bid on February 25, 2016 and March 2, 2016 in the Fort Worth
Star-Telegram and on May 5, 2016, the following bids were received.
Bidder Amount Time of
Completion
William J. Schultz, Inc. d/b/a Circle " C" Construction F$3,534,032.501400 Calendar Days
Company
Ark Contracting $6,086,035.00
Thane Construction Company $6,563,137.75
This project will have no impact on the Water Department's operating budget when completed.
Construction is expected to start October of 2016 and be completed by November of 2017.
M/WBE OFFICE: William J. Schultz, Inc. d/b/a Circle "C" Construction Company is in compliance with the
City's BDE Ordinance by documenting good faith effort. The City's MBE goal on this project is 10 percent.
Most State Revolving Loans are granted for construction contracts only. Additional appropriations
of $399,600.00 (Sewer: $355,000.00; TPW: $44,600.00) is required for project management, material
testing and Inspection; $174,800.00 (Sewer: $149,800.00; TPW: $25,000.00) is provided for project
contingencies.
Construction for the Sanitary Sewer Rehabilitation, Contract 84 Project, is one component of the overall
project that includes project management, easement, acquisition, utility coordination, material testing,
inspection, construction and contingencies. The overall project budget is $4,427,991.00. This project is
part of the Water Department's Sanitary Sewer Overflow Initiative Program.
The project is located in COUNCIL DISTRICT 4, Mapsco 63H, 64E and 64J.
Logname: 60SSR84-CIRCLEC Page 2 of 4
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance funds will be available in the current capital budget, as appropriated, of
the Sewer Capital Projects Fund, the Street Rehabilitation Fund and the Clean Water State Revolving
Fund 2007. The Fiscal Year 2016 Sewer Operating Budget includes appropriations of$26,300,046.00 for
the purpose of providing Pay-As-You-Go funding for sewer capital projects. After this transfer for Fiscal
Year 2016, the balance will be $9,564,338.00. Appropriations for Sanitary Sewer Rehabilitation, Contract
84 project will consist of the following:
FUND Existing Additional Future Project
Appropriations Appropriations Appropriations Total*
Street
Rehabilitation $0.00 $608,794.00 $0.00 $608,794.00
Fund 39408
Clean Water
SRF 59602 $0.00 $2,969,794.00 $0.00 $2,969,794.00
Sewer Operating $344,603.00 $504,800.00 $0.00 $849,403.00
59607 1 F
Project Total i $344,603.001 $4,083,388.001 $0.00 1$4,427,991 .00
* Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department Account Project Program Activity Budget Reference # Amount
ID ID Year Chartfield 2
1 59607 0700430 4956001 C01503 C017ZZ 2016 $504,800.00
1 59607 0700430 5740010 C01503 C01783 2016 $149,800.00
1)596071 0700430 5110101 C01503 C01780 2016 $62,900.00
1)596071 0700430 5310350 C01503 C01784 2016 $94,400.0
1)596071 0700430 5330500 C01503 C01784 2016 $9,000.00
1 59607 0700430 5110101 C01503 C01785 2016 $188,700.00
59602 0700430 4905420 C01503 C01783 2016 2,969,794.00
59602 0700430 5740010 C01503 C01783 2016 2,969,794.00
FROM
Fund Department Account Project Program Activity Budget Reference # Amount
ID ID Year Chartfield 2
N 59602 0700430 5740010 C01503 C01783 2016 2,969,838.50
3 39408 0200431 5740010 C01503 C01783 2016 $564,194.00
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: John Carman (8246)
Additional Information Contact: Robert C. Sauceda (2387)
Logname: 60SSR84-CIRCLEC Page 3 of 4
Lognaine: 60SSR84-CIRCLEC Page 4 of 4