HomeMy WebLinkAboutContract 46343-CO6 RECEIVED FORT WORTH,u *1Ty,(;FCRMTMV
AM 3 0 2016 °OH I R 1CT N0. 3 �
gyp City Of Fort Worth
Change Order Request
Facility and
Project Terminal Building Renovation Meacham International Airport City Sec No. 46343
Description:
Funding(FID)53902-0550435-5740010-C01527-C08180 City Proj.No. C01527
No.(s)
Contractor: Imperial Construction Change Order#F--6--1 Date: I 7/6/2016
City Project Mgr.Alfonso Meza City Inspector: Mike Miiam
Phone Number 817-392-8274 Phone Number: 817-392-2297
Contract Time
(CD)
Original Contract Amount------—--------------------------------------------------------------------- $15,872,750.00 407
Extras to Date --------------------------------------------------_____-- __ $2,044,838.00 196
Credits to Date— -- ----------------------- -- -- $0.00 0
Pending Change Orders(in M&C Process)------ ---------- ----- $0.00 0
Contract Cost to Date -------------------------------------- $17,917,588.00 603
Amount of Proposed Change Order------------------------------------------------------------ $24,168.00 5
Revised Contract Amount-------------------------------------------------------------------- $17,941,756.00 608
Original Funds Available for Change Orders----------------------------—-------------------------- $0.00
Remaining Funds Available for this CO-------------------------------------------------- $0.00
Additional Funding(if necessary)-------------------------- --- $0.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 12.88%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $19,840,937.50
JUSTIFICATIONfi#COM FOR CHANGE ORDER
Authorize a change in scope to increase the construction contract by$24,168.00 to add steel angles along the second floor deck,deck drains
on 3rd floor balcony,add blocking to accept roof coping,and re-route roof drain piping.
The total amount of change orders 1,2,3,4,5&6 results in an increase of the original contract amount by 13.03%.This change order
includes PC#94,101,102&103.This change order does not include an increase in contract time of 174 days in already approved PC's
through to date.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incindental to the above Change Order.
Gorltrat 's 098MName Contractor t1ame Contractor ,
Imperial Construction
Co 11-11)`5
PMD Date I UNKU bate
$•S•Ilo c� 5 9cl
Date (� � Services Man
Date
I°0/
�G 0000
D Assis 0'70
0 .
M&C Number N/A M&C Date Approved N/A T°o
Q; 1
AtW9ted � woa
OFFICIAL.RECORD
CITY SECRETARY
FT.WORTH,TX Mary ayser, City Secretary
ILPERIALProposed Change
C 0 N S T R U C T10N
Project: Meacham Terminal Building ICI Job Number: 4-0644_]
PC Na: 094 Date: 6(11/2016
Submitted To: Submitted By:
Mike Milam Jennifer Collins
City of Fort Worth-Property Management Imperial Construction,Inc.
401 West 13th Street 4001-20 West Suite 200
Fort Worth,Texas 76102 Weatherford,Texas 76086
Reason; IDesign Modification
Scope/Modification/Description:
Re-Route Roof Drain Piping in Clerestory per RFI-106.
NOTE:This Proposal is based on clouded changes only in the revised contract documents issued and mentioned above along with current
project conditions.All pricing will be reviewed upon approval for differing site conditions at the time of approval and any additional work
required will be submitted under seperate PC
Description Qty UM Other(A) Lab(B) Mat(C) Eq(D) Sub(E) Sub Total
Gardner 1 LS $ 13,754.00 $ 13,754.00
Associated Direct GC Costs 1 LS $ -
$
Sub-Total without GC Markup $ - Is - $ - $ - $ 13,754.00
Add 10%Indirect OH&Fee $ 1,375.40
Subtotal $ 15,129.00
Add P&P Bond 1% $ 151.29
Add insurance 1.5% $ 226.94
Add Sales Tax Exempt
1GRAND TOTAL $ 15,S07.00
The Contract Time will be INCREASED by 5 Calendar Days
By signing below,you agree to pay the amount submitted by either contingency fund transfer or issuance of a formal change order to the contract.tf
approval of this PC is not received within(5)Calendar days from date submitted,it is subject to change.
Submitted Approv
BY: BY.
Imperial stru n,Inc. Ci Fort Worth Date
4001-20 Aev.Store 200.We47herjiin!7'xas 76080
ILPERIALProposed Change
CONSTRUCTION
Project: Meacham Terminal Building ICI Job Number: 140644
PC No: 101 Date: 7/5/2016
Submitted To: Submitted By:
Mike Milam Jennifer Collins
City of Fort Worth-Property Management Imperial Construction,Inc.
401 West 13th Street 400 1-20 West,Suite 200
Fort Worth,Texas 76102 Weatherford,Texas 76086
Reason: IDesign Revision
Scope/Moditkation/Description:
Replace(5) Deck Drains on the 3rd Level SW Balcony with Watts FD-460 Area Drains with Adjustable Top and Hinged Heel Proof Tractor
Grate; No Hub Outlet;Epoxy Coated Cast Iron Finish;Sediment Basket.
NOTE:This Proposal is based on clouded changes only in the revised contract documents issued and mentioned above along with current
project conditions.All pricing will be reviewed upon approval for differing site conditions at the time of approval and any additional work
required will be submitted under seperate PC.
Description Qty UM Other(A) Lab(B) Mat(C) Eq(D) Sub(E) Sub-Total
Gardner 1 LS $ 4,251.00 $ 4,251.00
Associated Direct GC Costs 1 LS $ -
$ -
Sub-Total without GC Markup $ - Is - $ - $ - $ 4,251.00
Add 10%Indirect OH&Fee $ 425.10
Subtotal $ 4,676.00
Add P&P Bond 1% $ 46.76
Add Insurance 1.5% $ 70.14
Add Sales Tax Exempt
GRAND TOTAL $ 4,793.00
The Contract Time will be UNCHANGED by 0 Calendar Days
By signing below,you agree to pay the amount submitted by either contingency fund transfer or issuance of a formal change order to the contract.If
approval of this PC is not received within(5)Calendar days from date submitted,It is subject to change.
;Submi Approved
Y.
BY: - ,,,-
BY: LQU�
Impe a Const1tr ion,Inc. Ci o Fort Worth Date
1001-20 West,Suite 200,Weatherford,Texas 76086
livj ��—IAL Proposed Change
CONSTRUCTION
Project: Meacham Terminal Buliding ICI Job Number: 14-0644
PC No: 102 Date: 7/5/2016
Submitted To: Submitted By:
Mike Milam Jennifer Collins
City of Fort Worth-Property Management Imperial Construction,Inc.
401 West 13th Street 4001-20 West,Suite 200
Fort Worth,Texas 76102 Weatherford,Texas 76086
Reason: IMaterial Conflict
Scope/Mocflification/Description:
Add Blocking to accept Roof Coping on the NE Canopy(East FBO Entrance)per RFI-116
[NOTE. This Proposal is based on clouded changes only in the revised contract documents issued and mentioned above along with current
oject conditions.All pricing will be reviewed upon approval for differing site conditions at the time of approval and any additional work
quired will be submitted under seperate PC.
Description Ctty LIM Other(A) Lab(B) Mat(C) Eq(D) Sub(E) Sub-Total
SWCI 1 LS $ 1,380.00 $ 1,380.00
S -
$ -
S -
Associated Direct GC Costs 1 LS $
Sub-Total without GC Markup $ - $ - $ - $ - $ 1,380.00
Add 30%Indirect OH&Fee $ 138.00
Subtotal $ 1,518.00
Add P&P Bond 1% $ 15.18
Add Insurance 1.5% $ 22.77
Add Sales Tax Exempt
IGRAND TOTAL $ 1,556.00
The Contract Time will be UNCHANGED by 0 Calendar Days
By signing below,you agree to pay the amount submitted by either contingency fund transfer or issuance of a formal change order to the contract.If
approval of this PC is not received within(5)Calendar days from date submitted,it is subject to change.
Sub mi d Approved /
BY: BY: �G'r�
Imper ors ction,Inc. City 1f ort Worth Date
400 1-10 West,Suite 100•Weatherford,Texas 76086
lu" PEFSAL Proposed Change
CONSTRUCTION
. ,oject: Meacham Terminal Building ICI Job Number: 14-0644
PC No: 103 Date: 7/5/2016
Submitted To: Submitted By:
Mike Milam Jennifer Collins
City of Fort Worth-Property Management Imperial Construction,Inc.
401 West 13th Street 4001-20 West,Suite 200
Fort Worth,Texas 76102 Weatherford,Texas 76086
Reason: Steel Modification
Scope/MuMcatfon/Description:
Add Steel Angles anchored into existinting Concrete on 2nd Floor Deck Edge surrounding FBO Lease Space.Sawcut and Chip Existing
Concrete to adjust recess in(2)Vestibules.
/VOTE:This Proposal is based on clouded changes only in the revised contract documents issued and mentioned above along with current
project conditions.All pricing will be reviewed upon approval for differing site conditions at the time of approval and any additional work
required will be submitted under seperate PC.
Description C}ty UM Other(A) Lab(B) Mat(C) Eq(D) Sub(E) Sub-Total
Plyler 1 LS $ 1,052.00 $ 1,052.00
,on/S&S 1 LS $ 1,000.00 $ 1,000.00
5 -
$ -
Associated Direct GC Costs 1 LS $
Sub-Total without GC Markup $ - $ - $ 1,052.00 $ - $ 2,052.00
Add 10%Indirect OH&Fee $ 205.20
Subtotal $ 2,257.00
Add P&P Bond 1% $ 22.57
Add Insurance 1.5% $ 33.86
Add Sales Tax Exempt
GRAND TOTAL $ 2,313.00
The Contract Time will be UNCHANGED by 0 Calendar Days
By signing below,you agree to pay the amount submitted by either contingency fund transfer or issuance of o formal change order to the contract.If
approval of this PC is not received within(5)Calendar days from date submitted,it is subject to change.
Submitted Approved
imperi Cons ction,Inc. Ci Fort Worth Date
4001-20 West,Suite 200,4t�ealherford,Texas 76086