HomeMy WebLinkAboutContract 47371-CO2 CITY SE
FORT WORTH City of Fort Worth CMTMCT
Change Order Request
Project Name:I Water and Sewer Replacement Contract 2015 WSM-C,Part 2 City Sec No.: 47371
Project No.(s): P253-608170243487/P258-608170243487 DOE No. 7476 City Proj.No.: 02434
Project Description: Water-Sewer Replacement Ave H,Ave. I,Wilkinson,Purrington,Meadowbrook,N.Ayers,Canyon and Jamacia
Contractor: Woody Contractors, Inc. Change Order# Date: 9/1/2016
City Project Mgr. Liam Conlon City Inspector: I Carlos Vasquez
Phone Number: 817-392-6824 Phone Number: 817-392-8306
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $1,516,450.00 $1,516,450.00 190
Extras to Date $22,730.00 $22,730.00 030
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,539,180.00 $1,539,180.00 220
Amount of Proposed Change Order $57,810.00 $57,810.00 060
Revised Contract Amount $1,596,990.00 $1,596,990.00 280
Original Funds Available for Change Orders $80,000.00 $80,000.00
Remaining Funds Available for this CO $57,270.00 $57,270.00
Additional Funding(if necessary) $540.00 $540.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.31%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,895,562.50
JUSTIFICATION (REASONS)FOR CHANGE ORDER
Change Order No. 2 will provide for the following:
• Extra width HMAC pavement repair beyond trench width due to actual conditions that were
encountered during construction.
• 8-inch water line lowering to clear conflict with existing storm drain line.
• Additional costs incurred by the contractor due to not be able to shut down an existing 36-inc ter
main on Beach Street(on schedule)to connect a project 24-in water main.
,,k
Staff concurs with the contractors request for 60 additional calendar days for the cha 'Order.
Q
tit b . �a o�
0
0000
ty Secret�.ry ��.17
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name C ntractor Signature Date
Woody Contractors, Inc. Troy Woody _ -
lnspecWq Date Project Maniager Date
Assistant Dire6erater Date CoostrUGtion Supervisor(TPW Dept) Date
Aostan Aft omDate Assistant City Manager Date
f
Council Action(If Required) ®FFICIAI.REGUI
M&C Number N/A M&C Date Approved N.
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Water and Sewer Replacement Contract 2015 WSM-C, Part 2 City Sec No.: 1 47371
Project No.(s): P253-608170243487/P258-608170243487 DOE No. 7476 City Proj.No.: 02434
Project Water-Sewer Replacement Ave H,Ave. I,Wilkinson,Purrington,Meadowbrook,N.Ayers,Canyon and Jamacia
Description
Contractor Woody Contractors, Inc. Change Order:= Date: 9/1/2016
City Project Mgr. Liam Conlon City Inspector Carlos Vasquez
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
43 Extra Width HMAC Repair/Residential Water 750.00 SY $59.00 $44,250.00
44 8"Water Line Lowering to Clear Storm Drain Water 1.00 LS $4,300,00 $4,300.00
45 Mobilzation due to not able to shut down 36"in Beach St. Water 1.00 LS $2,500.00 $2,500.00
46 Move 24"Water Line From Yard to Job Site Water 1.00 LS $5,000.00 $5,000.00
47 Truck Rental to Move 24"Water Line to Site Water 1.00 LS $1,760.00 $1,760.00
Water $57,810.00
Sewer
Page 2 of 4 Additions Sub Total $57,810.00
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Water and Sewer Replacement Contract 2015 WSM-C, Part 2 City Sec No.: 47371
Project No.(s): P253-608170243487/P258-608170243487 DOE No. 7476 City Proj. No.: 02434
Project Description Water-Sewer Replacement Ave H,Ave. I,Wil kin son,Purrington,Meadowbrook,N.Ayers,Canyon and Jamacia
Contractor Woody Contractors, Inc. Change Order: ® Date 9/1/2016
City Project Mgr. Liam Conlon City Inspector: FCarlos Vasquez
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
--- -- - — -- ------ — -- Water �----
Sewer
Page 3 of 4 Deletions Sub Total
MMBE Breakdown for this Change Order
MINBE Sub Ty 'of Service Amourit,fo this C0
Total $0:00
Previous Change Orders
Co# DATE AMOUNT.
Total
Page 4 of 4
WOODY
CONTRACTORS
WOODY CONTRACTORS INC.
650 TOWER RD
KENNEDALE TX 76060
PHONE- 817-483-4767
FAX 8'17-483-2048
Job: CONTRACT 2015 WSM C PART 2 -fie I- 1)14N wood y
Date June 30, 2016 i n ct P born-e
Time CHANGE ORDER 2
Item Description Quantity Unit Price Total Price
1 8"WATER LINE LOWERING 1 EA $ 4300.00 $ 4 300.QQ
2 MOBILIZATION 1 LS $ $ F4_99-&O
3 MOVE 24"WATER PIPE 1 LS $ 5,000.00 $ 5,000.00
4 TRUCK RENTAL 1 DAY $ 1,760.00 $ 1,760.00
5 EXTRA WIDTH ASP. / RESIDENTIAL 750 SY $ 59.00 $ 44,250.00
Total for Sheet $ 482,344-.80
,/%) Os
%`
Total For Job $ 6 ,
ADD 60 CALENDAR DAYS