HomeMy WebLinkAboutContract 31289 01 -31 -05P02 :46 RCVD COMMUNITY FACILITIES AGREEMENT THE STATE OF TEXAS § City Secretary COUNTY OF TARRANT § Contract No. � WHEREAS, SJ Rainbow Ridge Development, L.P., hereinafter called "Developer", desires to make certain improvements to Rainbow Ridge Addition, Phase 1, an addition to the City of Fort Worth, Texas; and WHEREAS, the said Developer has requested the City of Fort Worth, a municipal corporation of Tarrant and Denton Counties, Texas, hereinafter called "City", to do certain work in connection with said improvements. NOW, THEREFORE, KNOW ALL BY THESE PRESENTS: That said Developer, acting herein by and through SJ Rainbow Ridge Development L.L.C., its duly authorized General Partner, and the City, acting herein by and through Marc Ott, its duly authorized Assistant City Manager, for and in consideration of the covenants and conditions contained herein, do hereby agree as follows: I. General Requirements A. The Policy for the Installation of Community Facilities ("Policy") dated March 2001, approved by the City Council of the City of Fort Worth, is hereby incorporated into this Community Facilities Contract as if copy herein verbatim. Developer agrees to comply with all provisions of said Policy in the performance of its duties and obligations hereunder. B. The requirements of the Policy shall govern this Community Facilities Agreement, provided, however, that any conflict between the terms of this Community Facilities Agreement and the Policy shall be resolved in favor of this Agreement. C. Developer shall provide financial security in conformance with paragraph 6, Section II, of the Policy. D. The Developer shall award all contracts for the construction of community facilities in accordance with Section II,paragraph 7 of the Policy. E. The contracts for the construction of the public infrastructure shall be administered in conformance with paragraph 8, Section II, of t y -----. 200223810 CFA-TPW 03-0811 J WM.doc1 , F. The Developer further covenants and agrees to, and by these presents does hereby, fully indemnify, hold harmless and defend the City, its officers, agents and employees from all suits, actions or claims of any character, whether real or asserted, brought for or on account of any injuries or damages sustained by any persons (including death) or to any property, resulting from or in connection with the construction, design, performance or completion of any work to be performed by said Developer, his contractors, subcontractors, officers, agents or employees, or in consequence of any failure to properly safeguard the work, or on account of any act, intentional or otherwise, neglect or misconduct of said DEVELOPER, his contractors, sub-contractors, officers, agents or employees, whether or not such injuries, death or damages are caused, in whole or in Part, by the alleged negligence of the City of Fort Worth, its officers, servants, or employees. G. Developer shall install or adjust all of the required utilities to serve the development or to construct the improvements required herein. H. In the event that City participation exceeds $25,000, Developer agrees that no street construction or storm drainage will begin prior to City Council approval of this Community Facilities Agreement. (Article 104.100, Ordinance 7234). I. Developer agrees that no lot shall be occupied under a certificate of occupancy until the improvements required herein have been constructed (Article 104.100, Ordinance 7234). J. Developer hereby releases and agrees to indemnify and hold the City harmless for any inadequacies in the preliminary plans, specifications and cost estimates supplied by the Developer for this contract. K. Developer agrees to provide, at its expense, all necessary rights of way and easements across property owned by Developer required to construct current and future improvements provided for in this agreement. L. Developer agrees to construct proposed improvements as shown on the exhibits attached hereto. The following exhibits are made a part hereof: 200223810 CFA-TPW 03-0811 JWM.doc2 Water(A)None; Sewer(A-1)None; Paving (B) attached; Storm Drain (B- 1) attached; Street Lights and Signs (C) attached. 200223810 CFA-TPW 03-0811 JWM.doc3 ! r*'.,1 G' U II. Street and Storm Drain Facilities A. The Developer(s) agree to install or to cause to have installed, the street, storm drainage, street lighting, street name sign and other community facilities improvements shown as "current improvements" on the attached Exhibits B, B 1, and C. B. As shown below in the "Summary of Cost for Street and Storm Drain Facilities", the Developer shall fund its share of "current improvements" and shall pay to the City for its share of the cost of street, storm drainage, street lighting, street name signs as shown on the attached Exhibits B, B 1, and C. The estimated total cost of current improvements and related support services specified in this agreement, including design, construction and inspection is estimated to r C 2011,A�),c,;� Notes: 1. All Preliminary Plats filed after July 2000, will require sidewalks on all streets. Sidewalk cost is included under street cost. The developer is responsible for installation of sidewalk. 2. Developer's column for Item C represents two percent (2%) cost for construction inspection fees and materials testing less 10% for contingency cost. (*) Represents City participation for construction fees based on actual cost. 3. City not preparing plans and specifications. 200223810_CFA-TPW 03-0811 JWM.doc4 SUMMARY OF COST Rainbow Ridge Addition Phase I Item Developer City Cost Total Cost Cost A. Construction $ - 1. Streets $855,968.00 $ - $ 855,968.00 2. Storm Drainage $65,659.00 $ 8,480.00 $ 74,139.00 3. Street Lights $12,500.00 $ 37,500.00 $ 50,000.00 4. Street Name Signs $0.00 $ 1,500.00 $ 1,500.00 B. Engineering Design $ 509.00 $ 509.00 C. Construction Engineering and Management by DOE (2%) 1 $ 18,432.54 18,432.54 TOTALS $ 952,559.54 1 $ 47,989.00 $ 1,000,548.54 CFA CODE: 4 IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be executed in quadruplicate in its name and on its behalf by its Assistant City Manager, attested by its City Secretary, with the corporate seal of the City affixed, and said Developer has executed this instrument in triplicate, at Fort Worth,Texas this the QC^day of , 200)(5 11 Approval Recommended: Transportation and Public Works Department co'n•tracTAU tho izatiox l -" Robe Goode, P. E. Date Director ATTEST: City Of Fort Worth By Marc Ott City Secretary Assistant City Manager Approved as to Form: Assistant I Attorney ATTEST: DEVELOPER SJ Rainbow Ridge Developme BY: SJ Rainbow Ridge D e , L.L.C. General Partner Corporate Secretary By: St e w ins P eside 200223810—CFA-TPW_03-0811 JWM.docS ' 0 BARC LQ4A 'G`P AUCAN CAa DIZ aBOLO - FORT WORTH ALI-AM_ VAkAA �� 00 ^ LYD p y� �vS c�yH BAIIOERRY B� R V d 1� X15 3 �tT E �1 0 ft A AR C N Pa K P� { d 4(5`N M E ARVESTELO L-0 Land OUflG S F i U ' G _ M-14 PANIEC gg WAY OUT P Pwk RZBURO g RO BU OSTE a TF1Y/R5T g dd 0 R TON HRI. may V BE �,V AR M SCU MEADOW AGECOACH U e -�W N �� WR �- apuw s4 cEOR AN - SP Os MEADO (n Z r A B ? PoO qlO - f' OR _ p�U g - fl100 z- LL CO N S _ G> MIS S NO FORK p URS -HaBm F asG N 7} p F (3U S° Rw SYCA stt � 5 scH s sa cHoa -a qh JO AR SP GS Z PdN N SAN &¢� P�EAp Y 4Rf� S v1 M �l LLO i� fRE'- WA LONG EAOOWk q 288i �LCRE Gd4 3 SWEE N 4 z_RID EA CR 4 •, BEE TREE C SYCAMORE 4AR 15P ^ 8T ME y CRFEX Y ICE ,VL F V y AIRPORT 3 T Nt; S O CH STER UN COLNSFRR iJSC C BROdIWAY Oft% iTE (Q �SPRINGS WOOD AU BLE A CUNNINGH S WORTH I SCU EW C T N TON 3 t I �Rlsl ger (n HCR VL Y E URNE N L b AIflFlEID CRO.tCY CITY L.IT CITY z j r INDUSTRIAL TORr � vdnH 6 M5t CROWLEY �aEEK Pap 6,974 IMS tADAVIS �F,P �CCMLY e _L E A SKELLCeneter GLEND E PRAIR E V BI Pen enniat BOVELL E GLENDAp PACIND �iIR C VSTOBOVELL STR CKLAN CE ES ARH NIS E MUSTA > H NI E N SS O CRO Y- 2,D BURL SON PEC MEADOVCRES PE q CROVLEY BURLESON CL m VICINITY MAP U O O CO RA INR 0 W RIDGE ADDITION U 11 DUNAWAY ASSOCIATES, Inc. ENGINEERS — PLANNERS — SURVEYORS C FORT WORTH, TEXAS t� 4 / gi R I R R • n « I q c � a F x A 8 d i g R x R C r e• d d q R a R ill-- —8 — --� 1 Ar� I x R A W 8 a t —'-4—z n o ! I I oToll el) •ul L L x 9'8 :g wo}sno :azlsJ8AO 'Sesao 'INV 89:Et,:60 EOOZ/17Z/90 'NIVHCI VYHO1S Tmwejo 6ulned\ego\00\8EZZOOZ\ZO\udlsaa\:I f = : VV q V A r\ 5 a �W z�6a �i p q g A q E i A A F �ca I q q \ q Y C4q A ai X40 / e � A R ►� �i QZ zt CR SS � q I 8 ... 1JU'lft;U'2 RT 0 •ul L x 9•8 :g wo}snO :azlsJanO 'sesaO Md 0 L:BZ:LO EOOZ/LZ/90 'NI`dad WaOIS TMP'e10 uPP WJOIS\e;0\00\8£ZZOOZ\ZO\u6lsad\:l 14) fit zV, k l �MIij Cry•.._ �.. /- _ h / / 1�.i I.I - -- R �� I a k R R 4 z I I ti En R I ! VSA �jI h A / a It 4 A—�—di� R ' " it S — / a u Iii,jl \ 4 _\� �- gam.'•!! ,o ..�,% �:.. . R k J1 1 L x 9.8 :},wolsno :azlsJanp 'sesaJ:D VW 6 L:OO:O L £OOZ/LZ/90 '1HJIl 133H-LS '5MV210 1011 IaaJIs\edo\00\8EZZOOZ\ZO\u6lsao\:I ENGINEER'S OPINION Community Facilities OF Agreement PROBABLE DEVELOPMENT COST for Rainbow Ridge Addition Phase One 225 Lots 46.397 Acres DAI No.200223810 23-Jun-03 ONSITE CONSTRUCTION COSTS I. WATER $ 324,434.00 ll. SANITARY SEWER $ 379,416.25 III. STORM DRAIN $ 65,659.40 IV. PAVING $ 641,772.20 TOTAL ONSITE CONSTRUCTION COST $ 1,411,281.85 OFFSITE CONSTRUCTION COSTS I. OFFSITE WATER (Installed for Crowley ISD) $ 65,340.00 II. OFFSITE STORM DRAIN (Located Within McCart Street R.O.W.) $ 77,112.00 III. OFFSITE PAVING (McCart Street) $ 150,677.05 IV. OFFSITE PAVING (Connection to Crowley-Cleburne Road) $ 47,524.50 TOTAL OFFSITE CONSTRUCTION COST $ 340,653.55 TOTAL CONSTRUCTION COSTS TOTAL ONSITE CONSTRUCTION COST $ 1,411,281.85 TOTAL OFFSITE CONSTRUCTION COST $ 340,653.55 REIMBURSEMENT COST $ (24,474.00) TOTAL CONSTRUCTION COSTS $ 1,727,461.40 Irk "CITY3R-1VV1ff •nen pn ksVl:Clfili� U�G�� 200223810_CFA_OPDC-03-0623_JWM.xls Page 1 of 1 ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ITEM DESCRIPTION QTY/UNIT I PRICE AMOUNT I. WATER 1 10-inch water line 2,502 LF $ 21.50 $ 53,793.00 2 8-inch water line 6,284 LF $ 18.00 $ 113,112.00 3 6-inch water line 51 LF $ 17.00 $ 867.00 4 10-inch gate valve & box 4 EA $ 850.00 $ 3,400.00 5 8-inch gate valve & box 18 EA $ 650.00 $ 11,700.00 6 6-inch gate valve & box 7 EA $ 550.00 $ 3,850.00 7 fire hydrant 7 EA $ 1,250.00 $ 8,750.00 8 Cast iron fittings 7.00 TN $ 3,000.00 $ 21,000.00 9 1-inch water service 235 TN $ 350.00 $ 82,250.00 10 Type "A" meter box 225 EA $ 75.00 $ 16,875.00 11 Trench backfill density testing 8,837 LF $ 1.00 $ 8,837.00 SUBTOTAL $ 324,434.00 II. SANITARY SEWER 1 8-inch sewer line all depths) sdr-35) 7,645 LF $ 26.00 $ 198,770.00 2 8-inch sewer line all depths) sdr-26) 400 LF $ 28.00 $ 11,200.00 3 4-foot dia ssmh 31 EA $ 1,300.00 $ 40,300.00 4 4"sewer service w/dbl cleanout 235 EA $ 400.00 $ 94,000.00 5 Addition depth ssmh 75 VF $ 120.00 $ 9,000.00 6 Trench backfill density testing 8,045 LF $ 1.00 $ 8,045.00 7 Trench safety 8,045 LF $ 1.00 $ 8,045.00 8 JTV inspection 8,045 LF $ 1.25 $ 10,056.25 SUBTOTAL $ 379,416.25 III. STORM DRAIN 1 27-inch Class III RCP 56 LF $ 40.00 $ 2,240.00 2 30-inch Class III RCP 28 LF $ 50.00 $ 1,400.00 3 33-inch Class III RCP 165 LF $ 56.00 $ 9,240.00 4 36-inch Class III RCP 96 LF $ 60.00 $ 5,759.40 5 39-inch Class III RCP 165 LF $ 80.00 $ 13,200.00 6 10-foot curb inlet 6 EA $ 2,000.00 $ 12,000.00 7 33-inch sloped Type "A"headwall 2 EA $ 1,650.00 $ 3,300.00 8 39-inch sloped Type "A"headwall 1 EA $ 1,850.00 $ 1,850.00 9 36-inch Type "B"headwall 1 EA $ 2,300.00 $ 2,300.00 10 12"- 18" grouted rock rubble rip-rap 267 SY $ 50.00 $ 13,350.00 11 Trench backfill density testing 510 LF $ 1.00 $ 510.00 12 Trench safety 510 LF $ 1.00 $ 510.00 SUBTOTAL $ 65,659.40 IV. PAVING 1 6-Inch lime stabilized sub rade 27,246 SY $ 1.70 $ 46,318.20 2 Lime @ 30 lbs/sy 409 TN $ 98.00 $ 40,082.00 3 6-inch concrete pavement(complete in place with 26,384 SY $ 20.50 $ 540,872.00 silicone joint sealing and 7-inch curb) 4 Street li ht ole bases 24 EA $ 500.00 $ 12,000.00 5 Dead-end barricades 5 EA $ 500.00 $ 2,500.00 SUBTOTAL $ 641,772.20 v i1 CEJ20Du J� ,t,•iir{C, tU ?, 1 .K J1 U Ill f �LGO 200223810 CFA OPDC-03-0623 JWM.xIs Page 1 of 1 ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ITEM DESCRIPTION QTY/UNIT PRICE AMOUNT 1. OFFSITE WATER (Installed for Crowley ISD) 1 10-inch water line 2,420 LF $ 21.50 $ 52,030.00 2 8-inch water line 30 LF $ 18.00 $ 540.00 3 10-inch ate valve & box 3 EA $ 850.00 $ 2,550.00 4 6-inch gate valve & box 1 EA $ 550.00 $ 550.00 5 fire hydrant 1 EA $ 1,250.00 $ 1,250.00 6 Cast ironfittings s 2.00 TN $ 3,000.00 $ 6,000.00 7 Trench backfill density testing 2,420 LF $ 1.00 1 $ 2,420.00 SUBTOTAL $ 65,340.00 11. OFFSITE STORM DRAIN (Located Within McCart Street R.O.W.) 1 52 LF— 4'x2' Box Culvert(w/1 parallel wings & 1 flared 1 LS $ 12,000.00 $ 12,000.00 wings) 2 54 LF— (2) 6'x5' Box Culvert(w/1 parallel wings'& 1 1 LS $ 29,000.00 $ 29,000.00 flared wings) 3 10-foot curb inlet 2 EA $ 2,000.00 $ 4,000.00 4 12"- 18" grouted rock rubble rip-rap 638 SY $ 50.00 $ 31,900.00 5 Trench backfill density testing 106 LF $ 1.00 $ 106.00 6 Trench safe 106 LF $ 1.00 $ 106.00 SUBTOTAL -$ 77,112.00 Ill, OFFSITE PAVING (McCart Street) 1 6-inch lime stabilized sub rade 5 784 SY $ 1.70 $ 9,832.80 2 Lime g 30 lbs/s87 TN $ 98.00 $ 8,526.00 3 7-inch concrete paving (complete in place with silicone 4,935 SY $ 21.85 $ 107,829.75 joint sealing and 7-inch curb) 4 Unclassified street excavation 3,2901 CY $ 1.65 $ 5,428.50 5 Street light pole bases 4 EA $ 500.00 $ 2,000.00 6 4-foot wide sidewalks 690 SY $ 24.00 $ 16 560.00 7 Dead-end barricades 1 EA $ 500.00 $ 500.00 SUBTOTAL $ 150,677.05 IV. OFFSITE PAVING (Connection to Crowley-Cleburne Road) 1 8-inch lime stabilized sub rade 2 062 SY $ 2.00 $ 4,124.00 2 Lime 30 lbs/s31 TN $ 98.00 $ 3,038.00 3 6-inch hot mix asphalt 746 TN $ 50.00 $ 37 300.00 4 Street light pole bases 2 EA $ 500.00 $ 1,000.00 5 Unclassified street excavation 1,250,CY $ 1.65 $ 2,062.501 SUBTOTAL $ 47,524.50 200223810_CFA_0PDC-03-0623_JWM.xIs Page 1 of 1 REIMBURSEMENT COSTS ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ITEM DESCRIPTION QTY/UNIT r PRICE AMOUNT I. OFFSITE SD REIMBURSEMENT 1 Cost participation for storm drain culvert over 60"in 1 LS $ 8,480.00 $ 8,480.00 diameter(25% of culvert cost&6% engineering costs) SUBTOTAL $ 8,480.00 II. OFFSITE PAVING REIMBURSEMENT 100% of 27'wide paving of McCart Street(200 LF of 1 city property frontage from existing McCart street south 1 LS $ 15,994.00 $ 15,994.00 towards Phase 1A and 6% engineering costs) SUBTOTAL $ 15,994.00 200223810 CFA OPDC-03-0623 JWM.xIs Page 1 of 1 III. STREET LIGHTS: 1. `STREET LIGHT COST ESTIMATE QUANTITY UNIT .COST TOTAL COST INTERSECTIONS 15 EA $ 2, 000 $30, 000 . 00 MID-BLOCK RESIDENTIAL 9 EA $ 2, 000 $18, 000 . 00 CHANGE OF DIRECTION RESIDENTIAL 1 EA $ 2, 000 $2, 000 . 00 MID-BLOCK COLLECTOR 0 EA $ 2, 000 $0, 000 .00 MID-BLOCK ARTERIAL PARKWAY 0 EA $ 2, 200 $0, 000 .00 MID-BLOCK ARTERIAL MEDIAN 0 EA $ 2,200 $0, 000 .00 RELOCATE EXISTING LIGHT 0 EA $ 1, 500 $0, 000 .00 Subtotal $50, 000 .00 City' s Cost $37, 500 .00 Developer' s Subtotal $0, 000 .00 10% Contingencies $0, 000 .00 Project Total $50, 000 .00 Adjacent Developer' s Cost $0, 000 .00 Developer's Cost $0, 000 .00 2% Inspection Fee $0, 00 . 00 Developer' s Responsibility See PG III-1, "Line 7" RAINBOW RIDGE ADDITION July 9, 2003 Fort Worth, Texas July 10, 2003 PAGE 1 OF Exhibit C 2 . STREET LIGHTS WORK DESCRIPTION: 1 . The Developer shall provide for the installation of streetlights at the approximate locations shown in Exhibit "C" , immediately after final acceptance of the street construction, in accordance with engineering plans and specifications approved by the Transportation and Public Works Department . 2 . Streetlights on residential and /or collector streets can be installed using overhead or underground conductors with the approval of the Director of Transportation and Public Works . 3 . Streetlights on arterial streets shall be installed with underground conduit and conductors . 4 . The Developer shall provide for the installation of a 2-inch schedule 40 PVC conduit at a depth not less than 30 inches and at least 18-inch behind the curb, "clear from all other utilities" . S . The Developer shall provide for the installation of a 2-inch schedule 40 PVC conduit between streetlights proposed for installation and the power source to become operational . 6 . A 3-inch schedule 80 PVC conduit is required when crossing streets at a depth not less than 30 inches, unless indicated otherwise on the plans concrete pull boxes shall be provided at the crossing points . 7 . Street light conduit and footings shall be installed by the developer's contractor as part of and at the time of street construction. The city will obtain electric service and complete the street light construction in accordance with approved plans . 8 . The developer or their contractor shall contact City' s street light division 48 hours prior to starting any installation of conduit and/or streetlights at (817) 871-8100 to insure proper inspection of work. 9 .The procedure for installing conduit and footings will be with the inspector on the job site or you can request a copy by calling 817- 871-6596. RAINBOW RIDGE ADDITION July 9, 2003 Page 2 of Exhibit C "STREET LIGHTS" INTERSECTIONS ST. MARTIN RD & ARABA LN 1 ST. BERTS RD & ARABA LN 1 ST. KITTS RD & ARABA LN 1 ST. LUCIA RD & ARABA LN 1 MCCART AVE & ARABA LN 1 CAYNMAN DR & ARABA LN 1 ST. LUCIA RD & CAYMAN DR 1 ST. BURTS RD & CAYMAN DR 1 ST. KITTS RD & CAYMAN DR 1 MCCART AVE & CAYMAN DR 1 ST. MARTIN RD & TOBAGO RD 1 ST. MARTIN RD & ST.VINCENT RD_ 1 ST. LUCIA RD & ST.VINCENT RD_ 1 MARTINIQUE LN & TOBAGO RD 1 ST.VINCENT RD & BERMUDA CT 1 MID - BLOCK ST. MARTIN RD 2 ST. LUCIA RD 1 ST. BERTS RD 2 ST. KITTS RD 2 ST. VINCENT RD 1 CAYMAN DR 1 CHANGE OF DIRECTIONS CAYMAN DR 1 RAINBOW RIDGE ADDITION !Q Page 3 of Exhibit C IV STREET NAME SIGNS 1. The City will install the street name signs upon final approval of the street construction. The street name signs will remain the property of, and will be maintained by, the City. 2 . The City will pay for the street name sign installations required for this development to the extent of $100 . 00 per intersection. This unit cost will be revised annually by the Department of Transportation and Public Works to reflect prevailing costs of materials and labor. 3 . This development creates the following fifteen (15) intersections at a cost to the City of $1500 ,00 : Aruba Lane and McCart Avenue Aruba Lane and St . Barts Road Aruba Lane and St . Kitts Road Aruba Lane and St . Lucia Road Aruba Lane and Cayman Drive Aruba Lane and St . Martin Road Cayman Drive and St . Barts Road Cayman Drive and McCart Avenue Cayman Drive and St . Kitts Road Cayman Drive and St. Lucia Road St . Vincent Road and St. Lucia Road St . Vincent Road and Bermuda Court St . Vincent Road and St. Martin Road St . Martin Road and Tobego Road Tobego Road and Martinique Lane Rainbow Ridge Addition Fort Worth, Texas Date: July 2, 2003 j IV-1 % City of Fort Worth, Texas Mayor and Council Communication COUNCIL ACTION: Approved on 12/14/2004 DATE: Tuesday, December 14, 2004 LOG NAME: 20RAINBOW RIDGE REFERENCE NO.: C-20444 SUBJECT: Authorize Execution of Community Facilities Agreement with Rainbow Ridge Development, L.P., for the Installation of Community Facilities for Rainbow Ridge Addition RECOMMENDATION: It is recommended that the City Council authorize the City Manager to execute a community facilities agreement with Rainbow Ridge Development, L.P., for the installation of community facilities for Rainbow Ridge Addition. DISCUSSION: On April 22, 2003 (M&C G-13956), the City Council approved funds in the amount of $3.28 million to be moved from the Special Assessments Fund to supplement the 1998 Capital Improvement Program new development funds. This project was included in the list of the 83 projects submitted to the City prior to July 29, 2003, when the City Council placed a moratorium on City participation in community facilities agreements for street, storm drainage, street lights and street name sign facilities. Rainbow Ridge Development, L.P., the developer of Rainbow Ridge, has executed a proposed contract for community facilities to serve a 209 lot single-family development located in southwest Fort Worth, south of Loop 820 and west of 1-35W (see attached map). This development has eight (8) interior streets and is adjacent to McCart Avenue. The developer is responsible for the installation of sidewalks along the entire development. There is no City participation for street improvements. The City's participation is for over- sized storm drain improvements. There will be twenty five (25) street lights installed. The developer is responsible for installation of bases and underground conduit. The City is responsible for street light poles, fixtures, and wiring to complete the system. Fifteen (15) street name signs will be installed at total cost to the City. This Community Facilities Agreement is in compliance with the City's Policy for the Installation of Community Facilities. Logname: 20RAINBOW RIDGE Page 1 of 2 The estimated cost of the community facilities is as follows and subject to the actual bid price: ESTIMATED DEVELOPER CITY TOTAL Street Improvments $855,968.00 $0.00 $855,968.00 Design Engineering N/A $0.00 $0.00 Construction Insp. Fee $17,119.00 $0.00 $17,119.00 Storm Drain Improvement $65,659.00 $8,480.00 $74,139.00 Design Engineering N/A $509.00 $509.00 Construction Insp. Fee $1,313.00 M $1,313.00 Street Lights $12,500.00 $37,500.00 $50,000.00 Street Name Signs $0.00 $1,500.00 $1,500.00 Total Estimated Cost $952,559.00 $47,989.00 $1,000,548.00 (*) The City's portion of construction inspection fees are calculated based on actual street and storm drain construction cost over the 2% paid by developer, as per the Community Facilities Agreement policy in effect at the time of this project. PLAN COMMISSION APPROVAL- On August 28,2002, Plan Commission approved the preliminary plat (PP002-011). The final plat (FP 003-020) was filed for record on July 30, 2004. This development is located in COUNCIL DISTRICT 6. FISCAL INFORMATION/CERTIFICATION: The Finance Director certifies that funds are available in the current capital budget, as appropriated , of the Street Improvement Fund. TO Fund/Account/Centers FROM Fund/Account/Centers C115 541200 020115136801 $37,500.00 C115 541200 020115136802 $1,500.00 C115 541200 020115136419 $8,480.00 C115 541200 020115136419 $509.00 Submitted for City Manager's Office by: Marc Ott (8476) Originating Department Head: Robert Goode (7804) Additional Information Contact: Christa Sharpe (8009) Logname: 20RAINBOW RIDGE Page 2 of 2