HomeMy WebLinkAboutContract 46076-CO2 CITY SECRETARYJ'
FORT WORTH City of Fort Worth CONTRACT `����•�����
Change Order Request
Project Namel Water and Sanitary Sewer Relocation for TRV, Part 7 City Sec No. 46076
Project No.(s) 34014/30100/33002-CO2451-CO3780 DOE No. 7385 City Proj.No. 00969
project Description: Relocation of Sanitary Sewer main M-126,located in direct conflict with the proposed site for gateway valley storage
Contractor: Ark Contracting Services,LLC. Change Order: 0 Date: 9/21/2016
City Project Mgr. Liam Conlon City Inspector: I Paul Gieger
Phone Number: 817-392-6824 Phone Number: 817-392-8371
Dept. Sewer Totals Contract Time
(Calender days)
Original Contract Amount $3,033,273.00 $3,033,273.00 240
Extras to Date $21,090.00 $21,090.00
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $3,054,363.00 $3,054,363.00 240
Amount of Proposed Change Order $663,767.00 $663,767.00 040
Revised Contract Amount $3,718,130.00 $3,718,130.00 280
Original Funds Available for Change Orders $91,000.00 $91,000.00
Remaining Funds Available for this CO $69,910.00 $69,910.00
Additional Funding(if necessary) $593,857.00 $593,857.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 22.58%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+2591o) $3,791,591.25
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No.2 will allow for the pulverization and overlay(requested by the Parks Department)of the
existing parking lot located east of the Fort Woof Dog Park within Gateway Park, in addition to roadway repair
work in Gateway Park for which Ark Contracting is already under contract. This additional work is not the result
f,nor is it necessitated by the Trinity River Vision—Central City Project. However, expanding the scope of the
existing contract to incorporate this additional work results in better coordination in the field an to
he City. The cost for the pulverization and overlay of the existing parking will be paid for b a� h
k
Recreation Department. ppOO�$
a E�
Az�,0
Staff recommends theel=of 40 calendar days for the change order. 0
ser, C' Semi
Itis uncle stood�n e at the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Contractor Signature Date
Ark Contracting Services,LLC. Mike Plunk
Inspector Date Project Manager y Date
Assistant Direct ( ater ept) Date Con truction Supervisor(Water Dept) Date
X C �I �/;—
Assistant City Attorney Date Assistant City Manager Date
tic
a6-�
Council Action(If Required)
M&C Number C-27937 LLf T6, 2 M&C Date Approved 9/20/2016
Ft3R`r WOP,TH City of Fort Worth
Change Order Additions
Project Name Water and Sanitary Sewer Relocation for TRV,Part 7 City Sec No. 46076
Project No.(s) 34014/30100/33002-CO2451-CO3780 DOE No.= City Proj. No. 969
Project Relocation of Sanitary Sewer main M-126,located in direct conflict with the proposed site for gateway valley storage
Description
Contractor Ark Contracting Services,LLC, Change Order: = Date: 9/21!2016
City Project Mgr. Liam Conlon City Inspector r Paul Gieger
ADDITIONS
�,.. �;: ;,DEPT,., 4 U:riif ;: Unit�Cost , Tota(
�, �....
63 3"Removal of excess material Sewer 28900 SY $2.53 $73,117.00
64 8"cement stabilization at 23 lbs/sy Sewer 28900 SY $5.35 $154,615.00
65 3"asphalt pavement type D Sewer 28900 SY $15.00 $433,500.00
66 Stripping of the parking lot Sewer 1.00 Ls $2,535.00 $2,535.00
Sewer $663,767.00
Page 2 of 4 Additions Sub Total $663,767.00
F_ C3 RT C3 RT> 4 City of Fort Worth
Change Order Deletions
Project Name Water and Sanitary Sewer Relocation for TRV, Part 7 City Sec No. 46076
Project No.(s) 34014/30100/33002-CO2451-CO3780 DOE No. 7385 City Proj. No. 969
Project Description Relocation of Sanitary Sewer main M-126,located in direct conflict with the proposed site for gateway valley storage
Contractor Ark Contracting Services,LLC. Change Order: 1 2 1 Date 9/21/2016
City Project Mgr. Liam Conlon City Inspector Paul Gieger
DELETIONS
ITEM,DES,CRIP.T10,N`; ,: DEPT 4ty: . Unit: Unit:Cost " Total
Sewer
Page 3 of 4 Deletions Sub Total
M/WBE Breakdown for this Change Order
MaNBE Sub .. Typeof Servic Arou►at`for this
GO:
Total
Previous Change Orders
Co# DATE AMOUNT .
Total
Page 4 of 4
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 9/20/2016 - Ordinance No. 22431-09-2016
DATE: Tuesday, September 20, 2016 REFERENCE NO.: **C-27937
LOG NAME: 60TRVP7CO2 -ARK
SUBJECT:
Authorize Execution of Change Order No. 2 to City Secretary Contract No. 46076 with Ark Contracting
Services, LLC, in the Amount of$663,767.00 for a Revised Contract Amount of$3,718,130.00 for
Additional Road and Parking Lot Repaving Associated with the Sanitary Sewer Main Relocations for the
Trinity River Vision-Central City Project, and the Trinity Uptown Service Area Phase 2 Bridge, and Channel
Relocations, Part 7, Gateway Site E Sanitary Sewer Relocations, Provide for Materials Testing and
Inspection, and Adopt Appropriation Ordinance (COUNCIL DISTRICTS 4 and 5)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
PACS Gas Lease Capital Projects Fund in the amount of$286,181.00 from available funds; and
2. Authorize execution of Change Order No. 2 to City Secretary Contract No. 46076 with Ark Contracting
Services, LLC, in the amount of$663,767.00 for additional road and parking lot repaving associated with
the Sanitary Sewer Main Relocations for the Trinity River Vision-Central City Project, and the Trinity
Uptown Service Area Phase 2 Bridge, and Channel Relocations, Part 7, Gateway Site E Sanitary Sewer
Relocations, thereby increasing the contract amount to $3,718,130.00.
DISCUSSION:
On September 23, 2014, (M&C C-27017) City Council authorized a contract with Ark Contracting
Services, LLC, in the amount of$3,033,273.00 for Sanitary Sewer Main Relocations for the Trinity River
Vision-Central City Project and the Trinity Uptown Service Area Phase 2 Bridge and Channel Relocations,
Part 7, Gateway Site E Sanitary Sewer Relocations. The contract was subsequently revised by Change
Order No. 1 in the amount of$21,090.00 administratively authorized June 8, 2015.
Change Order No. 2 will allow for the pulverization and overlay (requested by the Park and Recreation
Department) of the existing parking lot located east of the Fort Woof Dog Park within Gateway Park, in
addition to roadway repair work in Gateway Park for which Ark Contracting is already under contract. This
additional work is not the result of, nor is it necessitated by the Trinity River Vision — Central City Project.
However, expanding the scope of the existing contract to incorporate this additional work results in better
coordination in the field and cost savings to the City. The cost for the pulverization and overlay of the
existing parking will be paid by the Parks and Recreation Department.
Staff recommends the approval of 40 calendar days for the change order.
In addition to the change order amount, $20,000.00 is required for material testing and inspection.
Logname: 60TRVP7CO2 -ARK Page 1 of 2
M/WBE OFFICE: A waiver of the goal for MBE/SBE subcontracting requirements was requested by the
Department and approved by the M/WBE Office, in accordance with the BDE Ordinance, because the
purchase of goods or services from source (s) where subcontracting or supplier opportunities are
negligible.
This project is located in COUNCIL DISTRICTS 4 and 5, Mapsco 78 B.
FISCAL INFORMATION /CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in the current capital budget, as appropriated, of
the 2014 Bond Program.
FUND Current Proposed Total
Appropriations Appropriations
2014 Bond Program
Fund 34014 _ $316,953.00 $O.00 $316,953.00
Fun
General Capital $80,633.00 $0.00 $80,633.00
Projects Fund 30100
PACS Gas Leasee
Capital Projects $0.00 $286,181.00 $286,181.00
Fund 33002
Project Total $397,586.00 $286,181.00 $683,767.00
*Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2
FROM
Fund Department Accoun Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: John Carman (8246)
Additional Information Contact: Liam Conlon (6824)
ATTACHMENTS
1. 60TRVP7CO2 -ARK Form 1295.pdf (Public)
2. 60TRVP7CO2 ARK Waiver.pd (CFW Internal)
3. 60TRVP7CO2-ARK A016.docx (Public)
4. 60TRVP7CO2-ARK Fund Identifiers REVISED.pdf (Public)
5. 60TRVP7CO2-ARK MapOl.pdf (Public)
6. SAM Ark Contracting Services.pdf (Public)
Logname: 60TRVP7CO2 -ARK Page 2 of 2
FID TABLE M&C Log Name 60TRVP7CO2-ARK
FUND IDENTIFIERS(FIDS):
TO
Reference
Department Account Project Budget # Amount
Fund ID ID Program Activity year (Chartfield
2)
1)33002 0800450 4800200 UNSGAS 2016 $286,181.00
1)33002 0800450 5740010 CO2451 C03780 2016 $286,181.00
FROM
Reference
Department Account Project Budget # Amount
Fund ID ID Program Activity Year (Chartfield
2)
2)34014 0800450 5740010 CO2451 C03780 2016 $316,953.00
2)30100 0800450 5740010 CO2451 C03780 2016 $80,633.00
2)33002 0800450 5740010 CO2451 C03780 2016 $286,181.00