HomeMy WebLinkAboutContract 47001-CO4 FORT WORTH® City of Fort Worth CITY SECRETARY
Change Order Request BreakdownCONTRACT NO-
ProjectNamel Transportation Connections for Pedestrians and Bicycles City Sec# 1 47001
Client Project#(s)l 01734(DOE#7318)
Contractor The Fain Froup PM Clint Symank Inspectorl Scott Nevotti
Change Order Submittal# ® Date 10/6/2016
Dept. Park and Rec Contract Time
Totals CD
Original Contract Amount $1,438,687.96 $1,438,687.96 250
Extras to Date $57,407.82 $57,407.82 28
Credits to Date $0.00
Pending Change Orders(in M&C Process) $0.00
Contract Cost to Date $1,496,095.78 $1,496,095.78 278
Amount of Proposed Change Order $18,345.00 $18,345.00 3
Revised Contract Amount $1,514,440.78 $1,514,440.78 281
Original Funds Available for Change Orders $89,827.00 $89,827.00
Remaining Funds Available for this CO $32,419.18 $32,419.18
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.27%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $1,798,359.95
F"TION(RMOM)FOR CHANGE ORD€R _
Additional rip rap was removed over the scheduled value of 150 SY(value per summary sheet;sheet 27)due to actual field conditions and per
plan quantity of 357 on sheet 55. Additional block sodding was furnished and installed on project in order to repair and cover exposed soil
areas beyond what the scheduled block sodding value of 5,779 SY covered.Additional soil retention blankets were furnished and installed on
project in order to cover exposed soil areas beyond what the scheduled soil retention blankets value of 5,779 SY covered.
A bY' s.o `$O
Mary J. K r ty ��tiry o !11
���Sktb00
w
1XA
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH,TX
FORT WORTH® City of Fort Worth CITY sECRETARY
�V Change Order Request BreakdownCONTRACT No - Y16VI�Q�" --
Project Namel Transportation Connections for Pedestrians and Bicycles City Sec# 1 47001
Client Project#(s)l 01734(DOE#7318)
Contractorl The Fain Froup PM Clint Symank Inspectorl Scott Nevotti
Change Order Submittal# ® Date 10/6/2016
Dept. Park and Rec Contract Time
Totals CD
Original Contract Amount $1,438,687.96 $1,438,687.96 250
Extras to Date $57,407.82 $57,407.82 28
Credits to Date $0.00
Pending Change Orders(in M&C Process) $0.00
Contract Cost to Date $1,496,095.78 $1,496,095.78 278
Amount of Proposed Change Order $18,345.00 $18,345.00 3
Revised Contract Amount $1,514,440.78 $1,514,440.78 281
Original Funds Available for Change Orders $89,827.00 $89,827.00
Remaining Funds Available for this CO $32,419.18 $32,419.18
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.27%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,798,359.95
a
Additional rip rap was removed over the scheduled value of 150 SY(value per summary sheet;sheet 27)due to actual field conditions and per
plan quantity of 357 on sheet 55. Additional block sodding was furnished and installed on project in order to repair and cover exposed soil
areas beyond what the scheduled block sodding value of 5,779 SY covered.Additional soil retention blankets were furnished and installed on
project in order to cover exposed soil areas beyond what the scheduled soil retention blankets value of 5,779 SY covered.
Vo0°R?-
Avas)qd by:
Mars,J. K ty Semtary 4
4
t�000000
ex-
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FoRTWORTH City of Fort worth
Change Order Additions
Project Name I Transportation Connections for Pedestrians and Bicycles City Sec# 47001
Client Project# 1 01734 #7318
Contract The Fain Froup PM Clint Symank Inspecto Scotl Nevotti
Change Order Submittal# 0 Date 10/6/2016
ADDITIONS
Unit nit Cost Total
emove concrete Riprap Park and Rec
162-2002 Block ing a and Rec Y
Soil Retention Blanket CL—1 TY A Park and ec
— 2,216.00000000
Park and Rec $18,345.00
Sub otal Additions
Change Order Additions Page 2 of 4
FORT WORT City of Fort worth
Change Order Deletions
Project Name I Transportation Connections for Pedestrians and Bicycles City Sec# 47001
Client Project# I 01734 #7318
The Fain Froup PM Clint Synumk Inspecto Scott Newtti
Charge Order Submittal# 0 Date 1016/2016
DELETIONS
Qty Unit Unit Cost Total
Park and Rec $0.00
u otal Delebons
Change Order Deletions Page 3 of 4
�Y
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
Buyers Barricades Barricades
Cowtown Redi-Mix Concrete $0.00
Striping Technology Striping
Total Highway Maintenance LLC Paving markings
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
1 1/1212016 $400.00
2 1/27/2016 $0.00
3 5/31/2016 $0.00
4 10/6/2016 $0.00
Total $400.00
CFW Change Order Approval Pa- COApp04 Page 2 of 3
FORT WORTH, City of Fort Worth
---.•� Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: 4
Change Order No.: Pa - COApp04 Date Started: 2016-10-07
City Sec. No.: 47001 Date Due: 2016-10-15
Project Name: 01734 - Transportation Connections for Bicycles & Pedestrians
Project Numbers: 01734 DOE Numbers:
7318
Project Sidewalk infills, striping, signage, and trails
Description:
Project Manager: Clarence Bryant City Inspector: Scott Nevotti
Contractor: Clint Symank - The Fain Group
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number: M&C Date:
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
PARD $ 18,345.00 39801-0800450-5740010--C01734 3
Total Cost: $ 18,345.00 Total Requested Days: 3
Approval Status:
https://projectpoint.buzzsaw.com/_bz_web/Forms/FormPrint.aspx?Siteld=51500&Proces... 10/31/2016
CFW Change Order Approval Pa - COApp04 Page 3 of 3
Approved: Yes
Comments:
User: Nannette Long
Date: 2016-10-07 10:17 AM
Approved: Yes
Comments:
User: Perla Banda
Date: 2016-10-13 7:30 AM
Approved: Yes
Comments:
User: Clarence Bryant
Date: 2016-10-13 8:06 AM
Approved: Yes
Comments:
User: Joel McElhany
Date: 2016-10-21 3:22 PM
Approved: Yes
Comments:
User: Richard Zavala
Date: 2016-10-21 5:20 PM
Approved: Yes
Comments:
User: Doug Black
Date: 2016-10-26 11:10 AM
Approved: Yes
Comments:
User: Susan Alanis
Date: 2016-10-31 2:04 PM
Action Required: Verify funding
https://projectpoint.buzzsaw.com/_bz_web/Forms/FormPrint.aspx?Siteld=51500&Proces... 10/31/2016
CFW Change Order Approval Pa - COApp04 Page 1 of 3
Routing
Assigned To: Due Date:
Assigned By: Due Time:
Links '1
fortworthgov/PACS/01734 - Transportation Connections for Bicycles &Pedestrians/Part I/Contractor/Change Orders/CO-
4/01734-Change Order Breakdown-4.xls
Attachments(0)
No Attachments have been added to this form,
https://projectpoint.buzzsaw.com/ bz_web/Forms/ForrnPrint.aspx?Site1d=51500&Proces... 10/31/2016
E 0
September 21,2016 FAIN
Constnmft Futures
Clarence Bryant Jr P.O.Box 750
Landscape Architect/Project Manager F�927-4WOO88 7s1o1
P J $ an-ss7-asaa
City of Fort Worth 917-927-4389 Fax
Parks and Recreation Department www.thsfaineompemr.com
4200 South Freeway, St. 2200
Fort Worth,TX 76115
RE: Transportation Connections for Pedestrians and Bicycles Project
Reconciliation Change order
Mr. Bryant,
This is the formal change request to reconcile overages in existing pay items. We will
require three days added to the contract time for this work.
DESCRIPTION EST.QTY UOM UNIT PRICE AMOUNT
104-2009 REMOVE CONCRETE RIPRAP 207.00 SY $53.00 $10,971.00
162-2002 BLOCK SODDING 121.00 SY $6.00 $726.00
169-2001 SOIL RETENTION BLANKET 2,216.00 SY $3.00 $6,648.00
CLI TYA
TOTAL $18,345.00
If you have any questions,please feel free to contact me at 817-9274388.
Sincerely,
- lr-�
Clint Symank
CC:File