HomeMy WebLinkAboutContract 47349-CO1 Il'QRT W ORTH City of Fort Worth t YSEGRETARY
Change Order Request Breakdowlfl('14TRACT No. uq
Project Namel N. Beach Street from Fossil Creek to NE Loop 820 City Sec# 47349
Client Project#(s)l 02238
Change Order Submittal# 0 Date 5/17/2016
Dept. T/PW Water Sewer Totals Contract TimeCD
Original Contract Amount $5,675,296.15 $89,335.52 $82,214.26 $5,846,845.93 541
Extras to Date $0.00 $0.00 0
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $5,675,296.15 $89,335.52 $82,214.26 $5,846,845.93 541
Amount of Proposed Change Order $74,930.00 $0.00 $0.00 $74,930.00 7
Revised Contract Amount $5,750,226.15 $89,335.52 $82,214.26 $5,921,775.93 548
Original Funds Available for Change Orders $488,154.00 $6,250.00 $5,750.00 $500,154.00
Remaining Funds Available for this CO $488,154.00 $6,250.00 $5,750.00 $500,154.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 1.28%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+2591o) $7,308,557.41
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change order required to add a pay item for hauling off excavated material and for adjusting existing irrigation lines that will be affected during
construction.
AUesW by:
4y //�� F r-®p
ary J. A� , , ity �oo0,Ofl0000D,p00 %
00
ILo R�®
a
V0 oy
0
o�v�oa®Oaooaa��o 00
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
FORT WOR'H City of Fort worth
Change Order Additions
Project Name N.Beach Street from Fossil Creek to NE Loop 820 City Sec# 47349
Client Project# 02238
Change Order Submittal# 0 Date 5/17/2016
ADDITIONS
Qty Unit Unit Cost I ota
new nc assi ieExcavation- au .
202(new) Adjust Existing Irrigation Systems T/PW 10,000.00 LS 1.00
203(new) Business Signs T PW 20.00 EA 250.00
T/PW $74,930.00
Water $0.00
Sewer $0.00
Sub Total Additions $74,930.00
Change Order Additions Page 1 of 1
FORT'WOR'CH City of Fort Worth
Change Order Deletions
Project Name N.Beach Street from Fossil Creek to NE Loop 820 CitySec# 47349
Client Project# 02238
Change Order Submittal# 01 Date 5/17/2016
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
T/PW $0.00
Water $0.00
Sewer $0.00
Sub Total Deletions
Change Order Deletions Page 1 of 1
M&C Review Page 1 of 4
Official site of the City of Fort Worth, Texas
CITY COUNCIL AGENDA FO11
COUNCIL ACTION: Approved on 12/15/2015 -Ordinance No. 22016-12-2015 & Resolution No.
4558-12-2015
DATE: 12/15/2015 REFERENCE C-27574 LOG NAME: 20N BEACH
NO.: CONSTRUCTION-02238
CODE: C TYPE: NON- PUBLIC NO
CONSENT HEARING:
SUBJECT: Authorize Execution of a Contract with JLB Contracting, LLC, in the Amount of
$5,846,846.00 for the Construction of North Beach Street from Fossil Creek
Boulevard to NE Loop 820 and Provide for Additional Project Management,
Inspections, Testing and Survey Costs and Contingencies in the Amount of
$1,053,154.00 for a Total Project Construction Phase Cost of$6,900,000.00, Adopt
Reimbursement Resolution and Adopt Appropriation Ordinance (2014 BOND
PROGRAM) (COUNCIL DISTRICT 4)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the execution of a contract with JLB Contracting, LLC, in the amount of$5,846,846.00 for
the construction of North Beach Street from Fossil Creek Boulevard to NE Loop 820, CPN 02238;
2. Adopt the attached resolution expressing official Intent to Reimburse expenditures with proceeds of
future debt for the construction of the North Beach Street from Fossil Creek Boulevard to NE Loop 820
Project; and
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water/Sewer Direct Purchase Note Fund in the amount of$183,551.00.
DISCUSSION:
This project provides for the reconstruction of North Beach Street as a six-lane divided arterial street as
provided for in the 2014 Bond Program. Existing 6-inch and 12-inch water mains and a 15-inch sanitary
sewer main will also be replaced as a part of this project. The project was advertised on July 16, 2015 and
July 23, 2015 in the Fort Worth Star-Telegram requesting competitive sealed proposals. Two proposals were
received on August 20, 2015. The proposals were evaluated based on a pre-established criteria provided in
the solicitation. JLB Contracting, LLC, submitted the highest ranking proposal.
Total Points
Contractor Bid Amount Calendar Price Time MBE Total
Days (0-75) (0-15) (0-10)
JLB Contracting, LLC $5,846,845.93 465 75.0 15.0 6.0 96.0
Jackson Construction, Inc. $6,421,347.50 540 10.0 0.0 6.0 16.0
The budget for the reconstruction of North Beach Street (Fossil Creek Boulevard to NE Loop 820) consists of
the following:
http://www.foilworthgov.org/council_packet/mc_review.asp?ID=21649&c... 12/17/2015
M&C Review Page 2 of 4
PROJECT BUDGET AMOUNT
Design Contract Budget $1,200,000.00
City Project Management, Design $ 50,000.00
Coordination
Total Design $192509000.00
Right-of-Way and Easement $ 200,000.00
Acquisition Coordination
Utility Relocations and Tree Removal $ 50,000.00
Total ROW, Utilities, Tree $ 2509000.00
Removal
Construction Costs as Bid $5,846,846.00
City Project Management, Inspections,
Quality Control/Assurance and $ 738,549.78
Coordination
Construction Project Contingencies $ 498,154.00
Total Construction $71083,549.78
TOTAL PROJECT BUDGET $8,583,549.78
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer
Fund. Available cash within the Water and Sewer portfolio and the City's portfolio along with the
appropriation authority authorized under the Direct Purchase Note Program will be used to provide interim
financing for this project until debt is issued. To the extent resources other than the Water and Sewer
portfolio are used to provide interim financing, the Water and Sewer Fund will be charged interest that is
equivalent to the overall rate of return being earned by the City portfolio (currently approximately one-
percent annually). Should the City's portfolio not support the liquidity needed to provide an interim short-
term financing source, another funding source will be required, which could mean issuance of securities
under the Direct Purchase Note Program or earlier issuance of Water and Sewer revenue bonds than is
currently planned. Once debt associated with this project is sold, bond proceeds will be used to reimburse
the Water and Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement
Resolution.
In accordance with the provisions of the Financial Management Policy Statements, Staff anticipates
presenting revenue-supported debt issuances to the City Council for consideration within the next three
years. The Financial Management Services Department is currently working with all departments to ensure
that multi-year capital improvements plans are in place. Newly developed and already existing plans, such
as the Water Department's current multi-year capital improvement plan, will be presented to City Council for
review and adoption. If the City Council-adopted plan does not include issuance of debt for this specific
project, the project will be funded other financing sources. If the City Council-adopted plan calls for debt
issuance, that debt must be issued within approximately three years to provide reimbursement for these
expenses. If that does not occur, the costs will no longer be reimbursable by issuing tax-exempt debt and
the funding source will have to be made whole through other budgetary methods. Adoption of this
resolution does not obligate the City to sell bonds, but preserves the ability to reimburse the City from tax-
exempt bond proceeds. Funding for the North Beach Street project is as depicted in the following tables.
This capital project will result in the demand for additional operation and maintenance resources within City
departments due to the construction of new public infrastructure assets. The estimated average annual
cost for these additional operation and maintenance resources is summarized in the following table:
ITEMS ESTIMATED I DEPARTMENT/DIVISION
http://www.fortworthgov.org/councilpacket/mc review.asp?ID=21649&c... 12/17/2015
M&C Review Page 3 of 4
INSTALLED WITH ANNUAL
THIS PROJECT OPERATING
IMPACT
16 Streetlights $33,200.00 TPW/Traffic Management
($200.00/streetlight)
3 Traffic Signals
$10,000.00/si nal
8 Inlets ($60.00 per $480.00 TPW/Storm Water
Inlet)
4.1 Lane Miles $15,744.00TPW/Streets
of 11 Inch Division
Concrete
Pavement
($3,840.00 per
Lane
Mile
This construction contract will be funded through the 2014 Bond Program. Available resources within the
General Fund will be used to provide interim financing for these expenses until debt is issued. Once debt
associated with this project is sold, bond proceeds will reimburse the General Fund in accordance with the
statement expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the
bond election (Ordinance No. 21241-05-2014).
Funding sources for this project are as follows:
Project 2014 Bond Water Direct Total Project
Name Program Purchase Note Funding
North
Beach $8,400,000.00 $183,549.78 $815837549.78
Street
Construction is anticipated to commence in January 2016 and be substantially completed by May 2017.
Contract time for substantial completion is 465 calendar days.
M/WBE OFFICE—JLB Contracting, LLC, is in compliance with the City's BDE Ordinance by committing to
22 percent MBE participation on this project. The City's MBE goal on this project is 16 percent.
The Project is located in COUNCIL DISTRICT 4.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are included in the approved budget
to date of the 2014 Bond Program and funds are available in the General Fund to pay expenses which
will be incurred on this contract until reimbursement can occur from the issuance of public securities
and certifies that funds are available as directed by M&C G-18375 in the 2017 Water and Sewer
Revenue Bonds Capital Project Fund for transfer from unspecified funding to the North Beach Street
Project. After transfer of$183,549.78 to this project, the amount of$92,112,722.40 in available
revenue will remain in the 2017 Water and Sewer Revenue Bonds.
Funding Appropriations Pending Remaining
Source to Date Expenditures/ Balance
Encumbrances
2014
http://www.fortworthgov.org/council_packet/mc review.asp?ID=21649&c... 12/17/2015
M&C Review Page 4 of 4
Bond
Program $8,867,000.00$6,974,168.13$1 ,882,841 .87
Water
Direct $
Purchase 0.00 0.00183 649.78
Note
To _
Fund Department Project Program Activity Budget Reference## Amount
Account
I_ ID I ID I Year Chartfield 2
E
56005 0600430 4956010CO2238 C00170 2016 $95,336.00
56005 �_ 0700430 1 4956 10 CO2238 C00170 2016 $88,215.00
t
FROM _
Fund Department Account Project Program Activity Budget Reference## Amount
1_ ID I , ID I I_ Year (Chartfield 2)
34014 0200431 5740010 CO2238 CO2380 2016 14010199 $5,663,296.22
56005 0700430 5740010) CO2238 C00170 2016 �� $88214.26
56005 0600430 5740010 CO2238 C00170 2016 $95,335.52
Submitted for City Manager's office by: Jay Chapa (5804)
Originating Department Head: Douglas Wiersig (6157)
Additional Information Contact: Mike Weiss (8485)
ATTACHMENTS
20N BEACH CONSTRUCTION MAP 02238.pdf
20N BEACH CONSTRUCTION-02238.docx
20N BEACH CONSTRUCTION 02238 REIMB RESOLUTION Version 1 .doc
http://www.fortwoithgov.org/couneil_packet/mc_review.asp?ID=21649&c... 12/17/2015
MAYOR AM COUHUL COMMUNIGAA0VA MAP
200 VI REACH CONSTRUCTION 02238
,S I Z 7 „ ' s HERITAGE
r: i I /./�/ ;`� '_ `.-i l \ l_1 - ',Y J I L1 t�
,� � _TRACE _
I r _ Il--'�' 1- - —�� y' 2 - .ol-
_ f WE$l ERN 'Yj — Z l I J LTJ KROGER
CENTER ' Cly ` O U I —
a it _, BLVD z __ Z
p W - - �~ COSTA L
RID
81 -C ��J
TARRANT
MARMON
t _t; lU
+ - { q ♦ j '- �� 1 T I ����, Y .00 T o PSON
f. O SUMMERFIELDS ry ( CCC`till a ; ' SIDEWALKS EXTEND NORTH TO
4
. .Yrr f';'?'y WESTERN CENTER BOULEVARD
ryt. ;iiSILVERi`i IRC
- SAGE.•
ail
A- -r--
- -
/ "3 �l° BASSWOOD 1�� ps
A.
1 _
gy •.,� ; •A.h' W Z 1, FyESTERN
CENTER Il 4 y
r
i— ` J
SAN
SOM
)2O�- --
—Qui-IU
SAND SAND HE
P %LOOP
� 2
\-. =�_A I IH 80
`
S} -IH•820:
Z'
uDRUM 1` MCLEAN
,:N ��• sl j ".��. i ” r_ _BNSFt� (0� I I - i A
j " BNSFp:. 9y� B(/,� I-1 J. - "'''�.��� - M HAM Y --MEACHAM uP , --
i) f FOSSIL r. s' 1:0 - ----
- — -
- ^ ' --1; VISTA`` t FSR_ IRA —37
c I t• -;�,y �D R� ..• I. ` +li��'Av.` _ I �,.'s� r E- `^ �
N DI E
J I. I l � �}•'I I _��� ' '` 'Zp't�u DOWNING ) - �. -` ,i
�TERMINAO a; E I' G I
Ilk BROADWAY =<a
SA HA
rt DRI
,
�`=d 1 q t r ' I �!i LOOP _y •J
d
Biu P ✓� - W BR _ SI f
J ) J
2111 Lu.
0 250 500
183, al. —28TH .183—
i 0 1500 3000 6000
NORTHBEACHSTREET - s `� " _I JQQ HO S O —gO 1 t t Ft
(IH020 TO FOSSIL CREEK BLVUj
D)Copyright 2015 City of Fort Wonh.Unauthorized reproduction Is a violation of applicable lays. CITY PROJECT#02238
This product is for informational purposes and may not have been prepared for or be suitable for legal,engineering,or surveying
purposes.It does not represent an on-the-ground survey and represents only the approximate relative location of property boundaries.
The City of Fort Worth assumes no responsibility for the accuracy of said data.