HomeMy WebLinkAboutContract 47713-FP2 Department of TP &W Const. Services
CPN# Date
ProRisk n
t Maliag r 'l b ZT WORTH,
F �
Risk Management Caad C'� "-1" ��dS&� if3f�= CR.E&ARa _
D.O.E. Brotherton 4V 'CONTRACT
CFA Westerman/Scanned b
Esteban Perez/Scanned UVT tJ kX 0(>
The Proceeding people have been Contacted
concerning the request for final payment& have 'ATION AND PUBLIC WORKS
released this project for such payment. IF PROJECT COMPLETION
Developer Projects)
Clearance Conducted By Developer
P "City Project Ns: 02745
Cs#y?7/3
Regarding contract 02745 for MORNINGSTAR SECTION 10,PHASE 2 as required by the
TRANSPORTATION&PUBLIC WORKS as approved by City Council on N/A through IVI&C N/A the director
of the TRANSPORTATION&PUBLIC WORKS upon the recommendation of the Assistant Director of the
Transportation&Public Works Department bas accepted die project as complete.
Original Conti-act Price: $133,002.00
Amount of Approved Change Orders: No
Revised Contract Amount:
Total Cost Work Completed: $133,002.00
Recommended for cceptance Date
Asst. Director, PW Infrastructure Design and Construction
AcceptedO Date
Director, TRANSPORTA ON & PUBLIC WORKS
Asst. City Manager Date
i
Comments:
LCp-' jr
Y �L � A��( 1
i
Rev.9/22/16
FORTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name MORNINGSTAR SECTION t0,PHASE 2
Contract Limits
Project Type STORM DRAIN
City Project Numbers 02745
DOE Number 2745
Estimate Number 1 Payment Number 1 For Period Ending 9/27/2016
CD
City Secretary Contract Number Contract Time 7ED
Contract Date Days Charged to Date 193
Project Manager NA Contract is 100.00 Complete
Contractor D T UTILITY CONTRACTORS,INC.
2614 CAUSBIE RD
WEATHERFORD, TX 76087
Inspectors LAYER / HOUSTON
Wednesday,September 28,2016 Page I of 4
i
City Project Numbers 02745 DOE Number 2745
Contract Name MORNINGSTAR SECTION 10,PHASE 2 Estimate Number I
Contract Limits Payment Number I
Project Type STORM DRAIN For Period Ending 9/27/2016
Project Funding
STORM DRAIN
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quauity Total
I TRENCH SAFETY 844 LF $0.50 $422.00 844 $422.00
2 30"RCP CLASS III 628 LF $80.00 $50,240.00 628 $50,240.00
3 24"RCP CLASS 111 216 LF $60.00 $12,960.00 216 $12,960.00
4 20'CURB INLET 8 EA $6,100.00 $48,800.00 8 $48,800.00
5 4'STORM JUNCTION BOX 2 EA $4,000.00 $8,000.00 2 $8,000.00
6 MEDIUM STONE RIPRAP DRY 148 SY $85.00 $12,580.00 148 $12,580.00
Sub-Total of Previous Unit $133,002.00 $133,002.00
I
i
i
i
I
3
i
pE
S
l
t
E
Wednesday,September 28,2016 Page 2 of 4
f[
E
f
City Project Numbers 02745 DOL Number 2745
Contract Name MORNINGSTAR SECTION 10,PHASE 2 Estimate Number I
Contract Limits Payment Number I
Project Type STORM DRAIN For Period Ending 9/27/2016
Project Funding
Contract Information Summaiw
Original Contract Amount $133,002.00
Chanhe Orders
Total Contract Price $133,002.00
Date _2 y I� Total Cost of Work Completed $133,002.00
Coll Less %Retained $0.00
/A Net Earned $133,002.00
Date 4
InsIlectio 17r i Earned This Period $133,002.00
Retainage This Period $0.00
Date/ /�// Less Liquidated Damages
Pr jec n r
Days @ /Day $0.00
Date �' LessPavement Deficiency $0.00
ZsCir1corIPWpp-tufrastructure Design and Construction Less Penalty $0.00
ate I Z Zo% Less Previous Payment $0.00
Directo /Contracting Departnieif Plus Material on Hand Less 15% $0.00
Balance Due This Payment $133,002.00
Wednesday,September 28,2016 Page 3 of 4
City Project Numbers 02745 DOE Number 2745
Contract Name MORNINGSTAR SECTION 10,PHASE 2 Estimate Number I
Contract Limits Payment Number I
Project Type STORM DRAIN For Period Ending 9/27/2016
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors LAYER / HOUSTON Contract Date
Contractor D T UTILITY CONTRACTORS,INC. Contract Time 75 CD
2614 CAUSBIE RD Days Charged to Date 193 CD
WEATHERFORD, TX 76087 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
------------- -- -- -- ---
Total Cost of Work Completed $133,002.00
Less %Retained $0.00
Net Earned $133,002.00
Earned This Period $133,002.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $133,002.00
Wednesday,September 28,2016 Page 4 of
FORTWORTH rev 03/05/07
TRANSPORTATION&PUBLIC WORKS
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO. 1
NAME OF PROJECT: Morningstar Section 10 Phase 2
PROJECT NO.: 02745 CONTRACTOR: DT Utility
DOE NO. 2745
PERIOD FROM 02/16/16 TO: 08/26/16 FINAL INSPECTION DATE: 14-Sep-16
WORK ORDER EFFECTIVE 2/16/2016 CONTRACT TIME 75 O WD OO CD
DAY OF DAYS REASON FOR DAYS DAY OF DAYS REASON FOR DAYS
MONTH CHARGED CREDITED MONTH CHARGED CREDITED
DURING DURING
1. 16.
2. 17.
3. 18.
4. 19.
5. 20.
6. 21.
7. 22.
8. 23.
9. 24.
10. 25.
11. 26.
12. 27.
13. 28.
14. 29.
15. 30.
31.
SAT,SUN, RAIN,TOO WE, UTILITIES OTHERS* DAYS TOTAL
&HOLIDAYS &TOO COLD RELOCATIONS CHARGED DAYS
THIS 0 0 0 0 193 193
PERIOD
PREVIOUS 0 0 0 0 0 0
PERIOD
TOTALS 0 0 0 0 193 193
TO DATE
*REMARKS:
'e
CONTRACTOR DATE INSPECTO DATE
ENGINEERING DEPARTMENT
! The City of Fort Worth• 1000 Throckmorton Street•Fort Worth,TX 76012-6311
(817)392-7941 •Fax:(817)392-7845
FORTWORTHREV.8/20/16
TRANSPORTATION AND PUBLIC WORKS
PERFORMANCE EVALUATION OF CONTRACTOR
1) CONTRACTOR&PROJECT DATA
Name ojConu-actor Pi•ojectNaine
D.T.Utility Contractors Morningstar Section 10 Phase 2
Inspector City Project Number
Garey Houston 02745
Construction Components Project Manager
❑Water ❑Waste Water 0 Storm Drainage ❑Pavement Pat Buckle
Initial Contract Amount Project Difjlculty
$133,002.00 O Simple OO Routine O Complex
Final ContractAurount Date
$133,002.00 9/14/2016
II)PERFORMANCE EVALUATION
0-Inadequate 1-Deficient 2-Standard 3-Good 4-Excellent
ELEMENT WEIGHT(x) APPLICABLE(Y/N) RATING(0-4) MAX SCORE SCORE
1 Submission of Documents 2 Y 4 8 8
2 Public Notifications 5 Y 4 20 20
3 Plans on Site 5 Y 4 20 20
4 Field Supervision 15 Y 4 60 60
5 Work Performed 15 Y 4 60 60
6 Finished Product 15 Y 4 60 60
7 Job Site Safety 15 Y 4 60 60
8 Traffic Control Maintenance 15 Y 4 60 60
9 Daily Clean Up 5 Y 4 20 20
10 Citizen's Complaint Resolution 5 Y 4 20 20
11 Property Restoration 5 Y 4 20 20
12 After Hours Response 5 Y 4 20 20
13 Project Completion 5 Y 4 20 20
TOTAL ELEMENT SCORE(A) 448
BONUS POINTS(25 Maximum)(B)
TOTAL SCORE(TS) 448
III)CONTRACTOR'S RATING
Maximum Score(MS)=448 or sum of applicable element score maximums which= 448
Rating([TS/MS]*100%) 448 / 448 = 100%
Performance Category Excellent
<20%=Inadequate 20%to<40%=Deficient 40%to<60%=Standard 60%to<80%=Good >_80%=Fxcellent
Inspector's Comments(INCLUDING EXPLANATION OF BONUS POINTS AWARDED)
Inspector SignatureC.4a - ontractor Site
Inspector's Supervisor Signature
CONTRACTOR'S COMMENTS
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth•8851 Camp Bowie West Blvd. •Fort Worth,TX 76116•(817)392-8306
September 13,2016
Garey Houston
City of Fort Worth
8851 Camp Bowie West
Fort Worth,Texas 76116
4
I
f
Re: Morningstar—Section 10,Phase 2
1
Dear Garey,
This letter is to state that no liquidated Damages will be assessed to
any contractors on the above referenced project.
r
Regards,
_ r
Michail Ducote'
Regional Development Manager
z
214-499-2275
fl
1 � 1
' k9
I!
f
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me,the undersigned authority,a notary public in the state
and county aforesaid, on this day personally appeared Lori Tollett,Vice
President Of D.T. Utility Contractors Inc.,known to me to be a credible
person, who being by me duly sworn,upon his oath deposed and said;
i
That all persons, firms,associations,corporations, or other
organizations furnishing labor and/or materials have been paid in fall;
That the wage scale established by the City Council in the City of j
Fort Worth has been paid in full; E
That there are no claims pending for personal injury and/or `
property damages;
On Contract described as;
Morningstar Section 10 Phase 2
BY �g-z
(ter; w u v.fi Name or Title
Subscribed and sworn before me on this date 13 of September,2016.
r
C7 � � RY TANYA DAVIS
a*.-.e
o, �a Notary Public
No ary Public *► '* STATE OF TEXAS r
Parker County of Texas a'�.y M �,�,m. �p.0 „2s-2017
t
CONSENT OF SURETY COMPANY FOR: ❑Prog ess Pa)snentfs)
XI Final Payment
11 Reduction in Retention
O Release ofRefention
Date: September.14,2016
TO: Wilbow-ivfornirigstar Development Corp.
4131 N,Central Expressway,Suite 990 Dallas,TJX 75204
CONTRACTOR: D.T. Utility Contractors Inc.
OBLIGEE: Wilbow-Morningstar Development Corp. !
PROJECT: Morningstar-Section 10, Phase 2, City of Forth Worth(FM 3325 and Old Weatherford Road)Project No.
CONTRACT AMOUNT: $323,806.00
I
CONTRACT DATE: 12123/2015 j
BOND NUMBER: 5001-2609
i
In accordance with the provisions of the Contract between Contractor and the Obligee as indicated below; (here insert
name and address ofSta-etv Companj)
Allied World Specialty Insurance Company SURETY COMPANY,
30 S. 17th St Ste 1600 Philadelphia, PA 19103
on the bond of(here insert name and address gfCohtraeta)
s
3
D.T. Utility Contractors Inc. ,CONTRACTOR,
2614 Causbie Road Weatherford,TX76087
i
hereby approves of the payment to the Contractor,and agrees that payment to the Contractor shall not relieve the Surety
Company of any of its obligations to the obligee as set forth in the said Surety Company's bond.
i
Surety Company further agrees that the final penal amount of Surety Company's bond issued on behalf of Contractor shall F
be$ $323,806.00 reflecting the final amount,adjusted'for change orders.of the Contract_between
Contractor and Obligee.
IN WITNESS WHEREOF,
The Surety Company has hereunto set its hand this 14th day of September 2016 (Year).
Allied World Specialty Insurance Company
Surety Company
Attest _::�F
Lucricia Delgado,Attestee
Signature
(Seal):
David Mahler k
Name of Attorney-In-Pact
If
I;
G
b U- k, 4s'P,rsM Ba l
1065 E.Hillsdale Blvd.,H230
Foster City,California 94404
www.directsurety.com d
i
t
E
L
FoRTWORTHREV:02122107
TRANSPORTATION AND PUBLIC WORKS
CONTRACTOR'S EVALUATION OF CITY
1)PROJECT INFORMATION Date: 9/14/2016
Nance of Contractor Project Name
DT Utility Contractors Morningstar Development Section 10 Phase 2
DOEInspector Project Manager
Garey Houston Pat Buckley
DOEN:mtber Project Difficulty Type of Contract
O Simple OO Routine O Complex D water D waste water (A Storm Drainage,D Pavement
Initial Contract Amount Final Contract Amount
$133,002.00 $133,002.00
11)PERFORMANCE EVALUATION
0-Inadequate 1-Deficient 2-Standard 3-Good 4-Excellent
ELEMENT RATING ELEMENT RATING
(0-4) (0-4)
INSPECTION EVALUATION PLANS&SPECIFICATIONS
1 Availability of Inspector 1 Accuracy of Plans to Existing Conditions 14-
2 Knowledge of Inspector 14 2 Clarity&Sufficiency of Details
3 Accuracy of Measured Quantities 3 Applicability of Specifications C/
4 Display Of Professionalism 4 Accuracy of Plan Quantities C(
5 Citizen Complaint Resolution PROJECT MANAGER EVALUATION
6 Performance-Setting up Valve Crews,Labs 1 Knowledge And/Or Problem Resolution L�
ADMINISTRATION 2 Availability of Project Manager L�
1 Change Order Processing Time f.( 3 Communication Y
2 Timliness of Contractor Payments 14 Resolution of Utility Conflicts [�
3 Bid Opening to Pre-Con Meeting Timeframe
III)COMMENTS&SIGNATURES
COMMENTS
Signature Contractor
Signature DOE Inspector
Signature DOE Inspector's Supervisor
INSPECTOR'S COMMENTS
TRANSPORTATION AND PUBLIC WORKS
+, f The City of Fort Worth•1000 Throckmorton Street•Fort Worth,TX 76012-6311
0
(817)392-7941 •Fax:(817)392-7845