AN ORDINANCE APPROVING AND ADOPTING ESTIMATES OF THE COST OF IMPROVE-
MENTS AND OF AMOUNTS TO BE ASSESSED FOR IMPROVEMENTS ON A PORTION OF
AND PORTIONS OF SUNDRY OTHER STREETS, AVENUES AND PUBLIC PLACES IN THE
CITY OF FORT WORTH, TEXAS, FIXING TIME AND PLACE FOR HEARING TO THE
OWNERS OF ABUTTING PROPERTY AND TO ALL OTHERS INTERESTED; DIRECTING
THE CITY SECRETARY TO GIVE NOTICE OF SUCH HEARING; AND DIRECTING THE
CITY SECRETARY TO ENGROSS AND ENROLL THIS ORDINANCE BY COPYING THE
CAPTION OF SAME IN THE MINUTE BOOK OF THE CITY COUNCIL AND BY FILING
THE COMPLETE ORDINANCE IN THE APPROPRIATE ORDINANCE RECORDS OF THE
CITY AND PROVIDING AN EFFECTIVE DATE.
WHEREAS, the City Council of the City of Fort Worth, Texas, has heretofore ordered that each of the
hereinafter described portions of streets, avenues and public places in the City of Fort Worth, Texas, be im-
proved by raising grading and filling same and by constructing thereon the following to-wit
UNIT I RAIDER ROAD From So Pipeline Road to Tube Drive known and desig-
nated as Project No 013-36468 Unit I, a seven-inch
thick reinforced concrete pavement on a six-inch thick
lime stabilized subgrade with seven-inch high super-
imposed concrete curb on a forty-foot roadway six-inch
thick concrete driveways will be constructed where
specified
UNIT II SO PIPELINE ROAD From Highway 183 to Raider Road, known and designated
as Project No 013-36468 Unit II,a seven-inch thick
reinfroced concrete pavement on a six-inch thick lime
stabilized subgrade with seven-inch high superimposed
concrete curb on a forty-foot roadway Six-inch thick
concrete driveways will be constructed where specified
UNIT III BELL DRIVE From So Pipeline Road to Tube Drive known and desig-
nated as Project No 013-36468 Unit III, a seven-inch
thick reinforced concrete pavement on a six-inch thick
lime stabilized subgrade with seven-inch high super-
imposed concrete curb on a forty-foot roadway Six-inch
thick concrete driveways will be constructed where spe-
cified
UNIT IV TUBE DRIVE From Reves Drive to Raider Road, known and designated
as Project No 013-36468 Unit IV, a seven-inch thick
reinforced concrete pavement on a six-inch thick lime
stabilized subgrade with seven-inch high superimposed
concrete curb on a forty-foot roadway
together with concrete curbs gutters driveways and incidentals to such improvements
on proper grade and line where same are not already so constructed together with storm
sewers and drains and other necessary incidentals and appurtenances all of said im-
provements to be «b nstructed as and where shown on the Plans and in strict accordance
with the Plans and Specifications therefor contract therefore has been made acd
entered into with APAC-TEXAS, INC. ,
and
WHEREAS, the City Council of the City of Fort Worth Texas has caused the Public
Works Director to prepare and file estimates of the cost of such improvements and
estimates of the amount per front foot proposed to be assessed against abutting property
and the owners thereof and such estimates have been examined NOW, THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS THAT
I
Such estimates be and they are hereby adopted and approved
II
It is hereby found and determined that the cost of improvements on each portion of
streets avenues and public places hereinafter described, with the amount or amounts
per front foot proposed to be assessed for such improvements against abutting pro-
perty and the owners thereof are as follows to-wit
Unit I Raider Road From So Pipeline Road to Tube Drive, known and de-
signated as Project Na 013-36468, Unit Il
The estimated cost of improvements is $ 176,.506.51 the estimated amount
per front foot to be assessed against abutting property and the owners thereof for superimposed
concrete curb 2111 is $ 1 70 the estimated amount per front foot to
be assessed against abutting property and the owners thereof for pavement is $ 46 52 ,
the estimated amount per front foot to be assessed against abutting property and the
owners thereof for -0- wide concrete sidewalk is $ -0- the estimated
amount per square foot to be assessed against abutting property and the owners thereof for
six-inch thick concrete driveway is $_2.$6 per square foot the total
estimated amount per front foot to be assessed against abutting property and the owners
thereof is $ 1~S_2? plus the cost incurred for concrete driveway construction
where specified
III
A hearing be given and held by and before the City .Council of the City
of Fort Worth Texas to all owning or claiming any property abutting upon said
portions of highways streets avenues and public places as well as to all
owning or claiming any interest in any such property Such hearing shall be
given and held on the 16th day of June 19 81, at 10 00 A ~
in the Council Chamber in the City Hall in the City of Fort Worth Texas and
the City Secretary is hereby directed to give or cause to be given notice ,of the
time and place of such hearing and of other matters and facts in accordance with
the terms and provisions of an Act passed at the First Called Session of the
Fortieth Legislature of the State of Texas and known as Chapter 106 of the Acts
of said Session now being known as Article 1105b of Vernon°s Texas Civil Statutes
as amended by Acts 1967 60th Legislature Page 365 Chapter 176 Section 1,
emergency effective May 12 1967 Such notice shall be by advertisement inserted
at least three (3) times in a newspaper published in the pity of Fort Worth
Texas, the first publication to be made at least twenty one (21) days before
the date of said hearing Said notice shall comply with and be in accordance with
the terms and provisions of said Act as amended The City Secretary is further
directed to give or cause to be given personal notice of the time and place of
such hearing to all owning or claiming any property abutting on said portions of
highways streets avenues and public places as well as to all owning or claiming
any interest in any such property Such personal notice shall be in writing and
shall be given or caused to be given by the City Secretary by depositing such
written notice in the United States Mail at least fourteen (14) days before the
date of the hearing postage prepaid iri envelopes addressed to all persons
owning or claiming any interest in the respective properties abutting the high-
ways streets avenues and public places or portions thereof to be improved as
the names bf such persons are shown on the current rendered tax rolls of the City
of Fort Worth and at the addresses so shown or if the name of such respective
owners do not appear on such rendered ta•x rolls then address to such owners as
their names are shown on the current unrendered tax rolls of the City of Fort Worth
at the addresses shown thereon In those cases in which an owner of property
abutting a highway street avenue or public place or portion or portions there-
of which is to be improved is listed as "unknown" on the then current City of
Fort Worth tax rolls or the name of an owner is shown on the City of Fort Worth
tax rolls but no address for such owner is shown no notice need be mailed In
those cases where the owner is shown to be an estate the mailed notice may be
addressed to such estate In this connection the City Secretary shall prepare
and file or cause to be prepared and filed with these proceedings a list of the
properties to be assessed the names of those persons owing or claiming any
interest in said properties to whom the notice was mailed together with the last
known addresses determined as aforesaid of the respective owners and those perms
sons owning or claiming any interest in said property
The Cfty Secretary shall certify that. each of the parties in said list whose
address is shown on the then current rendered or. unrendered tax rolls of the City
of Fort Worth was mailed a copy of the notice of hearing and shall further certify
the date or dates on which said notice was mailed A copy of each notice shall be
attached to such certificate The certificate of the City Secretary will be con-
clusive evidence of the facts therein recited
~a
IV
The City Secretary is hereby directed to engross and enroll this ordinance
by copying the caption of carne in the Minute Book of the City Council and by
filing the complete ordinance in the appropriate Ordinance Records of this City
V
This ordinance shall take effect and be in fu11 force and effect from and
after the date of its passage
Passed and approved this__~_day of 19~_
APPROVED AS TO FORM AND LEGALITY
C~~~/ ®-
,ty ttorney
UNIT II SO PIPELINE ROAD From Highway 183 to Raider Road, known and de-
signated as Project No 013-36468, Unit II
The estimated cost of improvements is $ 160,306.87 the estimated amount
per front foot to be assessed against abutting property and the owners thereof for super-
imposed concrete curb ~~~~E~~f~~~~ is $ 1 70 the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 4702
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for -0- _ wide concrete sidewalk is $ -0- the estimated
amount per square foot to be assessed against abutting prcperty and the owners
thereof for 6-inch thick concrete driveway is $ 2 86 per square foot the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $ 48 72 plus the cost incurred for concrete drivewav con
struction where specified
UNIT III BELL DRIVE From $o Pipeline Road to Tube Drive known and de-
signated as Project No 013-36468, Unit III
The estimated cost of improvements is $ 205,310 93_ _ the estimated amount
per front foot to be assessed against abutting property .and the owners thereof for super-
imposed concrete curb t~~~~~~~'~d~~#~6is $ 1 70 the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 50 28
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for -0- wide concrete sidewalk is $_ -0- the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $ 2 86 per square foot the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $ 51 98 plus the cost incurred for concrete driveway con-
struction where specified
UNIT IV TUBE DRIVE From Reyes Drive to Raider Road, known and desig-
nated as Project No 013-36468 Unit IV
The estimated cost of improvements is $.216,908.28 the estimated amount
per front foot to be assessed against abutting property and the owners thereof for super-
imposed concrete curb ~~~'~~ is $ 1 70 _ the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 4$ 08
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for -0- wide concrete sidewalk is $ -0- the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $ 2 86` per .square foot the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $ 49 78 ~ plus the cost incurred for concrete driveway con-
struction where specified
.711 z~~/~~ ~~~1 c~® c~
DATE REFERENCE SUBJECT Contract AWard - ASSeSSmellt PAGE
NUMBER Paving of Streets in .Bell 3
5/19/81 **C-5688 Industrial District lot
City Council action is requested on Project Nos 013-036-468-00 (Engineering)
and 029-036-468-00 (Construction) as described below
Roadway Roadway
Unit Street Limits Width-Feet Width-Feet
I Raider Road S Pipeline Road to 40 50
Tube Drive
II South Pipeline SH 183 to Raider Road 40 50
Road
III Bell Drive S Pipeline Road to 40 60
Tube Drive
IV Tube Drive Reves Street to 40 60
Raider Road
Five parcels of property which abut Unit IT South Pipeline Road on the north
side between SH-183 and Raider Road are within the corporate limits of the
City of Euless On October 26, 1976 the City Council of the City of Euless in
regular session approved the City of Fort Worth's proposal to assessment pave
above segment of South Pipeline Road and to assess abutting City of Euless
property owners in accordance with City of Fort Worth Assessment Paving
Policy The assessment for these five parcels total $51,1$0 53 In accordance
with State law and contingent upon the results of the Benefit Hearing the
City of Fort Worth will forward an ordinance to the City of Euless requesting
the ratification and approval of the assessments levied against the owners of
the five parcels
Origin of Project
This project was initiated by paving petitions signed by the owners of 77 9
percent of the adjacent property and received in the Assessment Paving Office
on July 7 1976 In addition on April 5 1968 (I R 1383) the City Council
approved Community Facilities Contract No 5997 for the development of Lot 9
Block 3 Bell Industrial District with a segment of Bell Drive being a border
street and on January 17 1978 (M&C C-4057) approved Community Facilities
Contract No 9662 for the development of Lot 1 Block 4 Bell Industrial
District with another segment of Bell Drive and 800 feet of Tube Drive being
border streets
DATE REFERENCE SUBJECT COntraGt Award - Assessment PAGE
NUMBER Paving of Streets in Bell 2 3
of
5/19/81 **C-5688 Industrial. Astrct
The project was delayed pending negotiations between the Cities of Euless and
Fort Worth to provide water and sewer services to this area in an orderly
manner The contract between the two (2) cities Was approved on August 18 1980
by M&C C-5223 Construction of water and sower Iacltes is now complete on
streets in this project
Improvements
All four units of this project will be
pavement with concrete curb and drvewa
storm drain pipe and appurtenances
Receipt of Bids
improved with industrial grade concrete
y approaches Also included are required
The project was advertised for bids on March 19 and 26, 1981 and the following
bids were received on April 23 1981 with 75 working days allotted to
complete the project
Bidder Amount
APAC - Texas Inc $ 716,068 49
J L Bertram Construction and Engineering, Inq 723,580 46
Uvalde Construction Company 727,317 60
Austin Paving Company 734,318 49
L H Lacy Company 743 02'2 57
Southwestern Contracting Company 803,185 00
Project Cost and Financing
Based on the low bid and Standard Assessment Paying Policy, approximately
$475,331 55 is proposed to be assessed against the adjacent properties,
including the five (5) parcels within the corpprate limits of the City of
Euless Funding of the property owners' share of construction cost will be
provided for by a bond fund transfer from the "Revol,ving Fund Unspecified"
Cost to the City for construction is approximately $240,736 94 and $42,964 10
for engineering, plus approximately $10 000 for construction and drainage
easements Sufficient funds are available in tie project account for the
engineering costs however, a bond fund transfeF from the "Assessment Paving
Unspecified" account in the amount of $245,000 is required for the City's
construction cost
DATE REFERENCE SUBJECT Contract Award - Assessment PAGE
NUMBER Paving of Streets in Bell 3 of 3
5/19/81 **C-5688 Industrial Di r'
Recommendation
It is recommended that
1 The following bond fund transfers be approved
From To Amount Reason
094-009-901-00 094-036-468-00 $475,331 55 To provide funds far
Revolving Fund Streets in Bell property owners' share
Unspecified Industrial District of construction coat
029-024-901-00 029-036-468-00 $245,000 00 To provide funds for
Assessment Pav- Streets in Bell City's construction
ing Unspecified Industrial District cost
2 An ordinance be adopted r~~~~~ ~~~~'~~~~~~ N~ ~3~~
a Declaring the necessity for and ordering the improvements
b Making provisions for levying assessments
c Directing the Public Works Department to prepare estimates of costs
and amounts to be assessed
d Awarding the contract to APAC-Texas Inc in the amount of
$716 068 49 based on their low bid,
e Making appropriations to cover the indebtedness thereby incurred for
improvements of the project named above and
3 An ordinance be adopted ADOP~E~ ~~ ~>~eq~~~ ~~ ~~~~
a Approving the estimates of costs and amounts proposed to be assessed
and
b Setting June 16 1981 as the date for the Benefit Hearing
GG ph
Attachment
pppROVED~C~t
ciTY cap
~~~ ~.
,~
~f ~,
SUBMITTED FOR THE ~ _ DISPOSITION BY COUNCIL: PROCESSED BY
CITY MANAGER'S ^ APPROVED
OFFICE BY
^ OTHER (DESCRIBE)
ORIGINATING
DEPARTMENT HEAD: Gar L. Sariterre CITY SECRETARY
FOR ADDITIONAL INFORMATION
CONTACT Odell H. SC mi DATE