City Of Fort Worth
Change Order Request
Facility and
Project North Service Center,Phase 1&2 City Sec No. 46976
Description:
Funding(FID)39007-0200431-5740010--CO2105-C00780,39007-0230424-
No.(s)5740010--CO2105-CO0780,304014-0200431-5740010--CO2105- City Proj.No. 02105
C00780-2015-14060199
Contractor:Ridgemont Commercial Construction Change order#F-3-1 Date: 10/25!2016
City Project Mgr.Ronnie Clements City Inspector: Mike Milam
Phone Number:(817)392-8014 Phone Number: (817)392-2297
Contract Time
(CD)
Original ContractAmount-------- -- — — — —------ --- $25,462,398.00 660
Extras to Date--------------------- — —— ------- -- $27,392.00 0
Credits to Date — — ---- -- -- —--------------— -- — --— $0.00 0
Pending Change Orders(in M&C Process)-------- -------- -- — $0.00 0
Contract Cost to Date------ — — — — -- ——-- $25,489,790.00 660
Amount of Proposed Change Order---------- ----— -- ---- -- $51,620.00 0
Revised Contract Amount---------- ----— -- ----- $25,541,410.00 660
Original Funds Available for Change Orders--- -- — ------------ $0.00
Remaining Funds Available for this CO-------- — — ——------- $0.00
Additional Funding(if necessary)-- --- — — -- $0.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.3
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $31,827,997.50
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Authorize a change in scope to increase the construction contract by$51,620.00 to add locating of 3 Devon gas lines and relocation of 1
existing Devon gas line that is in conflict with the proposed masonary screen wall along the north property tine.The total of change orders 1,2,
&3 results in an increase to the original contract amount by.3%.This change order' #27.
�0 �,
O
OFFICIAL RECORD
by: ox
a
Ronald P. Gonzales, st City S ,!-EX `} s
It is understood and agreed that the acceptance of this Change Order by the contractor consitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incindental to the above Change Order.
Contractor's Company Name Contractor Name Contractor Signaate
Ridgemont Commercial Construction
14lin
PMD Insp for Date Project Manager Date
r1,7,4 G�4
PMD Syperintendent Date Architecural Services Manager D A
b //-7/& 1$-Vi N/-7/
Date it ctc, roperty Manqgqnent partment Date
Assistant City Attorney Date Assist tCi Manager Da e
le I Itt
M&C Number M&C Date Approved
Proposed Change Order Request
Ridgemont Commercial Construction
1520 W Walnut Hill Lane R I D G E M O N T
Irving,TX 75038
Phone:214-492-8900 commercial construction
Owner: Cityof FortWorth Project: 1500609- / Fort Worth North Service Center
401 W 13th Street 301 Hillshire Drive
Fort Worth,TX 76102 Fort Worth,TX 76052
Change Order Request#: 27 Relocating Devon Gas Line-Payment Only
Relocate existing gas line on the property by abandoning the existing line and laying a new line on adjoining property(hereafter the
"work").All of this work to be performed by Devon Energy Production Company, LP. Contractor not responsible for the coordination,
supervision or installation of the gas line.This work is being added by change order to the contract sum as an accommodation to the
Owner and is in the nature of a pass-thru expense. Contractor will issue payment in the amount of$32,424 to Devon Energy Productic
Company, LP to accomplish this work. None of the work will be performed on the site of the Project. Owner acknowledges that
Contractor is only responsible to issue payment to Devon Energy to accomplish this work. Under no circumstances shall Contractor b(
responsible for the means and methods of this work,the timing of performance of the work or the final product.This work shall not be
subject to any warranty obligations of Contractor specified by the Contract. In the event of any dispute concerning this work, Owner st
look solely to Devon Energy Production Company LP for resolution and hold Contractor harmless from any claims which may arise oL
the work.To the extent of any conflict between the terms herein as it applies to the work and any other Contract Document,this chane
order shall prevail.
Item Phase Description Estimated
Cost
Relocating Devon Gas Line-Payment Only 22-70- Off-Site Gas 32,424.00
Overhead 4.00% 1,297.00
Bond 1.00% 324.00
Insurance 1.00% 324.00
Fee 4.00% 1,297.00
Requested Total For Item 35,666.00
Attourney Fees-Budget 01-05- Legal Fees 1,020.00
Overhead 4.00% 41.00
Bond 1.00% 10.00
Insurance 1.00% 10.00
Fee 4.00% 41.00
Requested Total For Item 1,122.00
Total For Change Order $36.788.00
Submitted By: Ridgemont Commercial Construction Approved By: City of Fort Worth
Signed: =
Signed:
Date: /,�,Azs�£
Date:
Reviewed By: Quorum Architects, Inc
Signed:
Date:
Proposed Change Order Request
Ridgemont Commercial Construction
1520 W Walnut Hill Lane R I D G E M O N T
Irving,TX 75038
Phone:214-492-8900 commercial construction
Owner: City of Fort Worth Project: 1500609- / Fort Worth North Service Center
401 W 13th Street 301 Hillshire Drive
Fort Worth,TX 76102 Fort Worth,TX 76052
Change Order Request#: 21 Locating Devon Gas Line
Item Phase Description Estimated
Cost
Locating Devon Gas Line 01-71- Licensed Survey 850.00
Surrey Property Lines
02-30- Subsurface Investigation 12,634.00
Pot Hole All Gas Lines
Overhead 4.00% 539.00
Bond 1.000/0 135.00
Insurance 1.000/0 135.00
Fee 4.00% 539.00
Requested Total For Item 14,832.00
Owner Contingency Adjustment 00-91- Owner's Contingency -13,484.00
Overhead 4.001/6 -539.00
Bond 1 M% -135.00
Insurance 1.00% -135.00
Fee 4.00% -539.00
Requested Total For Item -14,832.00
Total For Change Order $0.00
Submitted By: Ridgemont Commercial Construction Approved By: City of Fort Worth
Signed:
Date: Signed
Date:
Reviewed By: quorum Architects, Inc