HomeMy WebLinkAboutContract 29998 AMENDMENT NO. 3
STATE OF TEXAS S CITY SECRETARY CONTRACT NO.
(No M&C Needed)
COUN'T'Y OF TARRANT S
WHEREAS, the City of Fort Worth (City) and Carter & Burgess,
Inc. , (Engineer) made and entered into City Secretary Contract No.
28236, (the Contract) which was authorized by the City Council by
M&C C-19346 on the 12th day of November 2002 and subsequently
revised by two previous amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
Engineering contract for the design of Sanitary Sewer
Rehabilitation Contract LXVIII (68) .
WHEREAS, it has become necessary to execute Amendment No. 3
to said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which amends the Contract:
1.
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated April 21, 2004, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $4, 587 .00 .
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $239,205 .75.
I i L RECD""
ORIGINAL
3 .
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of 2004, in Fort
Worth, Tarrant County, Texas.
ATTEST: I1
Contract Authorization
Sy is Glover, Acting City Secretary Date
APPROVAL RECOMMENDED: P OV
A. Douglas Rademaker, P.E. Marc A. Ott
Director, Department of Assista t City Manager
Engineering
Carter & Burgess, Inc.
ENGINEER ZZ,
By:
Name: Steven C. Veal, P.E. _
Principal/Vice-President
777 Main Street
Fort Worth, TX 76101-2058
APPROVED AS TO FORM AND LEGALITY:
Gary Steinberger
Assistant City Attorney
-2-
Carter-Burgess 3,:,, -3
ne: 3'%J35�CCC
April 21, 2004
Mr. Miguel Domenech, P.E.
City of Fort Worth
Engineering Department
900 Monroe Street, Suite 201
Fort Worth, Texas 76102
Reference: Amendment No. 3: M-154 Additional Design Effort
Sanitary Sewer Rehabilitation Contract LXVIII (68)
Water Project No. PS58-070580175800
City Secretary Contract No. 29529 - D.O.E. No. 3766
Carter& Burgess No. 0 11625.010
Dear Mr. Domenech:
At the request of the City of Fort Worth, we are relocating M-154 to the street. This effort requires
additional survey that was provided by A.N.A. Consultants. This redesign and relocation effort is not
part of the original contract agreement. Therefore, we request that you approve this contract
amendment. The following is a breakdown of the compensation for this task:
Engineering Design Fee $3,510.00
Additional Survey Fee $ 600.00
10% Contingency Fee $ 417.00
10% MWBE Administration Fee $ 60.00
Total Amendment 3 Request $4,587.00
This fee will cover our expenses for relocating approximately 307 L.F. of pipe to the street and
relaying approximately 125 L.F. of pipe in the alley to redirect flow to the new alignment. This part of
the contract was originally anticipated and intended to be a pipe burst job. The net change to our
design is to add 432 If of open trench pipe construction and remove 125 If of pipe bursting.
Because of this, survey was limited to locating cleanouts and a topographic survey of existing
alignment. We would appreciate that this amendment request be approved in a timely manner.
The following is a summary of previously approved amendments:
Initial Contract Amount $207,093.00
Amendment# 1 Amount $7,149.00
Amendment# 2 Amount $20,376.75
Amendment# 3 Amount $4,587.00
Total Adjusted Contract Amount $239,205.75
g�, r j
,1 Rice
- 3 -
Mr. Miguel Domenech, P.E.
April 21, 2004
Page 2
If you have any questions regarding this letter, I can be reached at 817-735-6202.
Sincerely,
ir►ti
m. Bart ines, P.E.
Senior Project Manager
W BH/tg
Attachment
T1Job\011625\W P\CORR\01162501.L08.doc
cc: Correspondence
Public Works—JDS
des _� = 3 3ur��cs �rc�.re�r�,?mine=r_. .rc �_. _: .�� -�'=c��,aicc� Inc. _a9. ��riteca _�51n rs,IiAt44 44
=�3 4rc.._cts/=^.ginasr °C =&3 Vevadc '�rc� �\;',ron _� _aira 4rch�tedc,'�nciraers. _ p���'
Mr. Miguel Domenech, P.E.
April 21, 2004
Page 3
CARTER & BURGESS JOB COST ESTIMATE
PROJ MGR: Wm. Bart Hines, P.E. 04/15/04
Relocate M-154 to street, Job# 011625.010 03:56 PM
TOTAL TASK
TASK Project Manager Project Engineer Technioian/CADD COST
art 1 ADDITIONAL DESIGN SURVEY MWBE
Additional Topographic Survey ANA Lump Sum Fee for Surveying $600
Contract Administration 10% $60
SUBTOTALS 0 0 0 $660
Part2ADDITIONAL DESIGN
Design 2 10 24 $3,510
SUBTOTALS 2 10 24 $3,510
10% Contingency Fee $417- 1 1
GRAND TOTALI 2 1 10 24 $4,587.00
TOTAL MAN-HOURS PER DISCIPLINE 2 10 24
AVERAGE HOURLY SALARY RATE PER DISCIPLINE $165.00 $90.00 $95.00
TOTAL JOB COST PER DISCIPLINE $330.00 $900.00 $2,280.00
PERCENT OF TOTAL JOB HOURS PER DISCIPLINE 6% 28% 67%
PERCENT OF TOTAL JOB COST PER DISCIPLINE 7% 20% 50%
TOTAL SALARY COST $4,587.00
TOTAL JOB HOURS 36
MWBE PARTICIPATION 13%
WHOM WE,
off 11CREY"Y
FT. w'011H, TEX.