HomeMy WebLinkAboutContract 47465-CO1 CITY SECRETARY
FORT WORTH. City of Fort Worth "AMTRIWIr °lZkZC&
Change Order Request Breakdown
Project Namel HMAC 2015-4 Rehab I City Sec# 1 47465
Client Project#(s)l 02551 -39408-0200431-5740010--CO2551-C06283--
Contractor JLB Contracting LLC PM Kristian Sugrim Inspectorl Gary Deyon
Change Order Submittal# 0 Date 6/28/2016
Dept. TPW Contract Time
Totals CD
Original Contract Amount $1,607,630.92 $1,607,630.92 220
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,607,630.92 $1,607,630.92 220
rAm—ount of Proposed Change Order $175,406.14 $175,406.14 35
Revised Contract Amount $1,783,037.06 $1,783,037.06 255
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary) $175,406.14 $175,406.14
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 10.91
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,009,538,65
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order is for the two lane extension of Summer Creek Drive between Rancho Vedrde Parkway and Posada Drive. Subsequently to
complete the project an additional 35 calendar days is needed.
J r, ity Secretm
00 w° QQM-
wo,
OFFICIAL RECORD
� 0000000- CP* CITY SECRETARY
���� FT. WORTH9 TX
FOaT�t City of Fort worth
Change Order Additions
Project Name HMAC 2015-4 Rehab City Sec# 47465
Client Project# 02551-39408-0200431-5740010--CO2551-C06283--
Contractor JLB Contracting LLC PM Kristian Sugr m Inspector Gary Deyon
Change Order Submittal# Date 6/28/2016
ADDITIONS
ITEM DESCRIPTION DEPT City Unit Unit Cost Total
emove Fence TPW LF W7
102 Site Clearing TPW 1.00000000 LS $7,600.06
201 21"RCP,Class III TPW 32.00000000 LF 132.00
202 21"Flared Headwall TPW 2.00000000 EA 1,095.00
301 Unclassified Excavation TPW 60.00000000 CY $24.35
302 Embankment TPW 60.00000000 CY 2.25
303 Hydrated Lime TPW 50.14800000 TN $168.00
304 8"Lime Treatment TPW 2,388.00000000 SY $2.800
305 2"Asphalt Type D TPW 2,220.00000000 SY 12.14
306 4"Asphalt Type B TPW 2,220.00000000 SY 23.70
307 Barbed Wire Fence TPW 259.00000000 LF $26.25
308 Metal Beam Guard Fence TPW 275.00000000 LF $29.25
309 Safety End Treatment TPW 1.00000000 EA $3,450.00
310 Downstream Terminal Anchor TPW 1.00000000 EA $1,065.00
401 4"SLD Pvmt Marking HAS(W) TPW 1,652.00000000 LF 1.25
402 4"SLD Pvmt Marking HAS(Y) TPW 1,466.00000000 LF 1.25
403 24"SLD Pvmt Marking HAE(W) TPW 24.00000000 LF $15.66
404 Furnish&Install Alum Sign Ground Mount TPW 4.00000000 EA $410.0
405 Furnish&Install Type III Barricade TPW 48.00000000 LF 27.05
501 SWPPP=1 acre TPW 1.00000000 LS $3,450.00
502 Seeding,Hydromulch TPW 1,570.00000000 SY $1.45
9999.0096 Paving Construction Allowance TPW 1.00000000 LS 29,137.03
TPW $175,406.14
Sub Total Additions 175,406.14
Change Order Additions Page 1 of 1
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name NMAC 2015-4 Rehab CitySec# 47465
Client Project# 02551-39408-0200431-5740010—CO2551-C06283—
Contractor JLB Contracting LLC PM Kristian Sugrim Inspector Gary Deyon
Change Order Submittal# I Date 6/28/2016
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
T $0.00
Sub Total Deletions
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
MiSBE=Sub ' . . Type of SeNce
Amount for this C0.. ,
ATCO HMAC Haul and Misc. Trucking $5,247.00
JD's Trucking Raw Materials Hauling $6,412.00
Greenscaping Landscaping/Grass $2,100.00
Total $13,759.OD
Previous Change Orders
C9, ",# DATE . AMOUNT w r
Total $ .��
CFW Change Order Approval St-COApp01 Page 1 of 3
Routing
Assigned To: Due Date:
Assigned By: Due Time:
Links 2
fortworthgov/Infrastructure Proiects/02551 - Street Rehabilitation (HMAC 2015-4)/Contractor/Change Orders/HMAC
2015-4 C01 M&C493.Ddf
fortworthgov/Infrastructure Proiects/02551 - Street Rehabilitation (HMAC 2015-4)/Contractor/Change Orders/Copy of
Copy of Copy of summer creek posada connection Change Order Breakdown.xls
Attachments(0)
No Attachments have been added to this form.
https://projeetpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&Proces... 12/12/2016
CFW Change Order Approval St-COApp01 Page 2 of 3
ORT WORTHo City of Fort Worth
�-- Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: 1
Change Order No.: St-COApp01 Date Started: .2016-11-30
City Sec. No.: 47465 Date Due: 2017-01-19
Project Name: 'Street Rehabilitation (HMAC 2015-4)
Project Numbers: 02551 :DOE Numbers:
Project 'HMAC Street Rehabilitation; removal and replacement on non-
Description: ';functional or damaged curb & gutter and driveways,
pulverization and stabilization of the existing pavement
followed by a HMAC surface overlay.
Project Manager: Kristian Sugrim City Inspector: 'Gary Deyon
Contractor: JLB Contracting, LLC
COUNCIL ACTION (If Required):
M&C Log Name: 20HMAC STREET REHABILITATION(2015-4) CHANGE ORDER NO 1
M&C Number: C-27804 M&C Date: ,6-28-2016
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
7PW $ 175,406.14:.5740010 35
Total Cost-'$ 175,406.14 Total Requested Days: 35
Approval Status:
https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?SiteId=51500&Proces... 12/12/2016
CFW Change Order Approval St-COApp01 Page 3 of 3
Approved: Yes
Comments:
User: Tara Fishback
Date: 2016-11-30 1:52 PM
Approved: Yes
Comments:
User: Sam Davis
'Date: 2016-11-30 2:56 PM
'Approved: Yes
'Comments:
'User: Kristian Sugrim
Date: 2016-12-01 10:44 AM
Approved: Yes
Comments: Attached M & C approved
User: Najib Fares
°'Date: 2016-12-01 11:02 AM
:Approved: Yes
Comments:
User: Todd Blomstrom
Date: 2016-12-05 9:29 AM
Approved: Yes
.Comments:
User: Doug Wiersig
Date: 2016-12-09 11:54 AM
;Approved: Yes
`Comments:
User: Doug Black
.Date: 2016-12-09 2:22 PM
Approved: Yes
Comments:
User: Jay Chapa
Date: 2016-12-12 9:04 AM
Action Required:
https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?SiteId=51500&Proces... 12/12/2016
M&C Review Page 1 of 2
Official site of the City of Fort Worth,Texas
oR_ _r
CITY COUNCIL AGENDA _
COUNCIL ACTION: Approved on 6/28/2016 -Ordinance No. 22302-06-2016
REFERENCE 20HMAC STREET
DATE: 6/28/2016 NO.: C-27804 LOG NAME: REHABILITATION (2015-4)
CHANGE ORDER NO 1
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Change Order No. 1 to City Secretary Contract No. 47465 with JLB
Contracting, LLC., in the Amount of$175,406.14, Thereby Increasing the Total Contract
Amount to $1,783,037.06 and Adopt Appropriation Ordinance (COUNCIL DISTRICT 6)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt appropriation ordinance increasing estimated receipts and appropriations in the HMAC
Street Rehabilitation 2015-4 Project in the amount of$175,407.00 and reduce reserves in the
Contract Street Maintenance Fund by the same amount; and
2. Authorize the execution of Change Order No. 1 to City Secretary Contract No. 47465 with JLB
Contracting, LLC., in the amount of$175,406.14 for Hot Mix Asphaltic Concrete Street Rehabilitation
(2015-4) (C-02551).
DISCUSSION:
On December 15, 2015 (Mayor and Council Communication (M&C) C-27572), the City Council
authorized the execution of a contract with JLB Contracting, LLC., in the amount of$1,607,630.92 for
Hot Mix Asphaltic Concrete (2015-4), following water and sewer line replacements. The subject
change order in the amount of$175,406.14 will provide for the two-lane extension of Summer Creek
Drive between Rancho Verde Parkway and Posada Drive. The recommended change order will also
add 35 calendar days to the construction contract.
M&C C-27572 provided funding for the work proposed under Change Order No. 1 with funding from
the Council District 6 Undesignated Fund. Subsequent to the approval of M&C C-27572 it was
determined that the amount of the change order was mistakenly deducted from the total amount of
funding that should have been appropriated from the Contract Street Maintenance Fund for this
project. The recommended appropriation ordinance included with this M&C will correct this funding
deficit.
This change order for the HMAC Street Rehabilitation 2015-4 Project is one component of the overall
project that includes design, construction, project management, construction staking, inspection and
material testing. The overall budget is $2,056,334.32.
M/WBE OFFICE: JLB Contracting, LLC., agrees to maintain its initial MBE commitment of 15 percent
that it made on the original contract and extend and maintain that same commitment of 15 percent to
all prior change orders up to and inclusive of this Change Order No.1. Therefore, JLB Contracting,
LLC., remains in compliance with the City's BDE Ordinance and attests to its commitment by its
signature on the Acceptance of Previous MBE Commitment Form executed by an authorized
representative of its company.
http://apps.cfwnet.org/council_packet/mc review.asp?ID=22461&councildate=6/28/2016 11/16/2016
M&C Review Page 2 of 2
The project is located in COUNCIL DISTRICT 6, Mapsco 116D.
i
FISCAL INFORMATIONXERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of
the attached appropriation ordinance, funds will be available in the current capital budget, as
appropriated of the Street Rehabilitation Fund. Total current funds available in the Street
Rehabilitation Fund reserves are$1,489,631.63.
Description Appropriations to Pending Remaining
Date Encumbrances and Balance
Expenditures
HMAC Street Rehab $2,179,637.06 $745,299.24 $1,434,337.82
2015-4 Fund: 39408
TO
Fund Department Account Project Program Activity Budget Reference# Amount
ID I I ID I Year Chartfield 2)
1 394081 0200431 4905100 CO2551 C06283 I $175,406.14
1 394081 200431 1 CO2551 C06283 1 $175.406.14
FROM
Fund Department Account Project Program Activity I Budget Reference# Amount
ID I I ID I Year Chartfield 2
394081 0200431 1 5740010 1 CO2551 I I C06283 I 1 1 $175,406.14
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Douglas Wiersig (7801)
Additional Information Contact: Kristian Sugrim (8902)
ATTACHMENTS
20HMAC STREET REHAB H2O15-4 C01 (Map).pdf
20HMAC STREET REHABILITATION (2015-4) CHANGE ORDER NO 1 39408 A016
(Rev6.09.16).docx
JLB CONTRACTING LLC H2O15-4 HB1295.pdf
http://apps.cfwnet.org/council_packet/mc review.asp?ID=22461&councildate=6/28/2016 11/16/2016
CERTIFICATE OF INTERESTED PARTIES
FORM 3.295
lofl
Complete Nos.1.4 and 6 if there are interested parties, OFFICE USE ONLY
Complete Nos,1,2,3,5,and 6 if there are no interested parties. CERTIFICATION OF FILING
1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number:
of business. 12016-62485
JLB Contracting, LLC
Fort Worth,TX United States Date Filed:
2 Name of governmental entity or state agency that is a party to the contract for which the form is 05/26/2016
being filed.
City of Fort Worth Date Acknowledged:
3 Provide the identification number used by the governmental entity or state agency to track or identify the contract,and provide a
description of the services,goods,or other property to be provided under the contract.
02551
HMAC Street Rehabilitation 2015-4-Change Order 1
Nature of interest
4 Name of Interested Party Ci ty,State,Country(Place of business) (check applicable)
Controlling I Intermediary
Humphrey,Jim Fort Worth,TX United States X
Davis,Sam Fort Worth,TX United States X
5 Check only if there is NO Interested Party. ❑
6 AFFIDAVIT I swear,or affirm,under penalty of perjury,that the above disclosure is true and correct.
�Tr'�
A Y.,�1, JAMIE GREENWAY
40 �.r°:Notary Public,State of Texas
My Commission Expires
September 25, 2016 �^
d+nmV�`
Signature of authorized agent of contracting business entity
AFFIX NOTARY STAMP/SEAL ABOVE
_ —,
Sworn to and subscribed before me,by the said c.�'�-� I.d"Fty t s ,this the �tt� day of
20J,to cer' which,witness my hand and seal of office.
Sig alure o officer administerin oath Printed name of officer administering oath Title of officer a ministering oath
Fo m rovided by Texas Ethics Commission www.ethics.state,tx.us Version V1.0.1021