HomeMy WebLinkAboutContract 46469-CO2 CITY SECRE-TARY�
coNTPACT NO
FORT WORTH., City of Fort Worth
Change Order Request Breakdown
Project Namel Chisholm Trail Community Park-Ph 1 City Sec# 1 46469
Client Project#(s)l 02439
Contractor Fain Group PM Tom Alves I Inspector Thomas Miller
Change Order Submittal# Date 7/19/2016
Dept. PACS Contract Time
Totals (CD)
Original Contract Amount $3,400,000.00 $3,400,000.00
Extras to Date $103,326.42 $103,326.42
Credits to Date $28,474.90 $28,474.90
Pending Change Orders(in M&C Process)
Contract Cost to Date $3,474,851.52 $3,474,851.52
Amount of Proposed Change Order $44,267.30 $44,267.30
Revised Contract Amount $3,519,118.82 $3,519,118.82
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary) $44,267.30 $44,267.30
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.507A
MAXALL OWABLE CONTRA C TAMOUNT(ORIGINAL CONTRA CT COST+25%) $4,250,000.00
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Elements within the project that have been added or deducted from the project due to overall need of the City and efficiencies for the overall
project operation and facility improvement. The items that are part of this Change Order#2 are as follows: 1,)windmill relocation,2.)NW
property reconstruction including grading and seeding,3.)picnic tables,4.)light pole relocation,5.)culvert trail crossing, 6.)roundabout
boulders and decomposed granite,7.)lighting at windmill,8.)additional topsoil,9.)pedestrian gate at north end of soccer fields, 10.)NE trail
connection to neighborhood association open space lot, 11.)north parking lot wheel stops, 12.)ADA revisions at Skatepark and 13.)four trees.
The deleltions include: 1.)northside trail drainage and 2.)sod charge reversal.
A
ary J. s r, ty Sem -_.._
0
° o
0
°° [)
_{
��OGaiDiDGUb��d1p
IV
Vqy .
lT- OFFICIAL RECORD
CITY SECRETARY
FT,WORTH,TX
FORT�TIH City of Fort worth
Change Order Additions
Project Name Chisholm Trail Community Park-Ph 1 City Sec# 46469
ClientProjecl# 02439
Contractor Fain Group PM Tom Alves Inspector Thomas Miller
Change Order Submittal# Dale 7/19/2016
AUDI I IUNS
Unit Unit os o a
W—M-111 Relocation
Property Reconstruction 5
# Picnic tables 7, 7.
Light Pole Relocation
Culvert Crossing 5,5 7.
5 RoundaboutQC&DG5, 5
—PUD-92V 3 Fixtures at Windmill
opsei 7
Pedestrian Gate at Soccer Field
Trail Connection
North ar ing Lot Wheel Stops
70-434—ADA Revisions at Skatepark77
PGO#35 Additional ee ing
ee epacement 1.00000000 ILS $3,267.45
PACS $127,011.76
u1 otal Additions $127,011.7-9
Change Order Additions Page 3 of 9
FORt WORTH City of Fort Worth
—' - — Change Order Deletions
Project Name Chisholm Trail Community Park-Ph 1 CitySec# 46469
Client Project# 02439
Contracto Fain Group PM Tom Alves Inspecto ThomasMiller
Change Order Submittal# Date 7/19/2016
ULLL I TUNS
Unit Unit os o a
o si a rT ramage
Sod arge Reversal
PACS 62,744.46
u ota a ehons
Change Order Deletions Page 4 of 9
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
EI Cala Concrete $12,610.00
Total $12,610.00
Previous Change Orders
Co# DATE AMOUNT
1 2/1/2016 $23,138.40
Total $23,138.40
DOE PROJECT 02439 BID NUMBER
FORT WC)R'FH (Please check one)
— - ---
MinorityMomen Business Enterprise Office
LETTER OF INTENT TO PERFORM AS A MBE SUBCONTRACTORISUBCONSULTANT
FOR CONTRACT ADMENDMENTSiCHANGE ORDERS OR EXTRA WORK
[NOTE: Pursuant to the City of Fort Worth Business Diversity Enterprise Ordinance,MBE firms participating under the Ordinance must be certified
prior to recommendation of award in order to be counted towards subcontracting partidpation.if the City of Fort Worth determines that a proposed
MBE Is not certified accordingly to the Ordinance requirements,the firm shouldimmediately submit a completed certification application to the North
Central Texas Regional Certification Agency(NCTRCA),624 Six Flags Drive,Suite 106,Arlington,TX 76011.]
1. Name of Project Chisholm Trail Parkl-Phase 1
2. Name of Offeror/Prime contractor The Fain Group.inc,
3. The undersigned is prepared to perform the following described work and/or supply the material listed in connection with the
above project(where applicable specify"supply'or•install'or both)
Concrete Work
at an additional price of$12,610.00 added to the MBE firm's current subcontract amount
EI Gala Construction Inc.
(Name of MBE Firm) (Date)
rn 1 s
Circle one Owner uthorized Agent of MBE firm)Type or Print Name (Signature of Omer or Authorized Agent of MBE firm)
(Email Address to appWon Listings provided by the MWBE Office) Vffice Phone Number)
AFFIDAVIT OF Offeror/Prime CONTRACTOR
I HEREBY DECLARE AND AFFIRM that 1, Larry Frazier am the duly authorized representative of
Circe one(Owner/Authodzed Agent)
The Fain Group.Inc. Name of Prime Contractor and that I have personaily reviewed the material and
facts set forth in this Intent to Perform form. To the best of my knowledge,information and belief the facts and representation
contained in this form are true,and no material facts have been omitted,
Pursuant to City of Fort Worth Business Diversity Enterprise Ordinance, any person[entity]who makes a false or fraudulent
statement in connection with participation of a SBE in any City of Fort Worth contract will be referred for debarment procedures
under the City of Fort Worth Business Diversity Enterprise Ordinance.
I do solemnly swear or affirm that the signatures contained herein and the information provided by the Prime Contractor are true
and correct,and that I an authorized on behalf of the Prime Contractor to make the affidavit.
/71-arry Frazier The Fain Group,Inc.
Circl e(Ommed Authorized Agent)Type or Print Name (Name of Prime Contractor-Print or Type)
80%
{ nature f r or Authorized Agent) (Date)
81 27-4388 817-9274389
(office Phone Number) (Fax Number)
6/1/2012
12/13/2016 Page 2 of 4
FORT WORTH® city of Fort worth
Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: COSub02
Change Order No.: Pa - COApp02 Date Started: 8/24/2016 TMI
City Sec. No.: 46469 Date Due: 9/10/2016 1
Project Name: C-02439 Chisholm Trail Community Park - Phase I
C-02439 DOE Numbers:
Project Numbers:
DOE No.7509
Project Chisholm Trail Community Park - Phase I - Design Build project
Description: Items that are part of this Change Order No. 2 are as follows:
Windmill relocation
NW Property reconstruction / grading / seeding
Picnic Tables
Light Pole relocation
Culvert crossing
Roundabout boulders and decomposed granite
Lighting at Windmill
Additional Topsoil
Pedestrian Gate at north end soccer fields
NE Trail Connection to NA Open space lot
North Parking Lot wheel stops
ADA revisions at skatepark
Additional seeding
Tree replacement
The deletions include:
Northside trail drainage
Sod Charge reversal
City Project Mgr.: Thomas Alves City Inspector: Thomas Miller
Contractor: The Fain Group Inc.
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number: M&C Date:
COST AND DAYS SUMMARY:
Department: Cost($) Fund Account Center: Requested Days:
PARK $ 44,267.30 34014-0800450-5740010-CO24 0
https://projectpoint.buzzsaw.com/ bz_web/Forms/FormPrint.aspx?SiteId=51500&ProcessId=2313&R...
12/13/2016 Page 3 of 4
Total: $ 44,267.30 Total Requested Days: 0
Approval Status:
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&Processld=2313&R...
12/13/2016 Page 1 of 4
Links 1
fortworthgov/PACS/02439 - Chisholm Trail Community Park- Phase I/Contractor/Chancre Orders/Change Order#2
Breakdown R.xls
Attachments(1)
Name Author �KB) Type Modified
Thomas Alves 1351680 Microsoft Excel 8/24/2016 5:56:51
�CopyofChangeOrder#26reakdownR.xls Spreadsheet PM
https://projeetpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Site1d=51500&Processld=2313&R...
12/13/2016 Page 4 of 4
Approved: Yes
Comments: Funds verified
User: Debra Rose
Date: 2016-08-25 4:55 PM
Approved: Yes
Comments:
User: Larry Frazier
Date: 2016-08-26 7:03 AM
Approved: Yes
Comments: Funds verified
User: Debra Rose
Date: 2016-08-30 10:48 AM
Approved: Yes
Comments:
User: Larry Frazier
Date: 2016-08-30 10:55 AM
Approved: Yes
Comments:
User: Thomas Alves
Date: 2016-08-30 11:03 AM
Approved: Yes
Comments:
User: Joel McElhany
Date: 2016-08-31 10:53 AM
Approved: Yes
Comments:
User: Richard Zavala
Date: 2016-08-31 1:29 PM
Approved: Yes
Comments:
User: Doug Black
Date: 2016-09-01 2:00 PM
Approved: Yes
Comments:
User: Susan Alanis
Date: 2016-09-01 2:10 PM
Action Required: approve
https://projeetpoint.buzzsaw.com/ bz_web/Forms/FormPrint.aspx?Siteld=51500&Processld=2313&R...