HomeMy WebLinkAboutContract 32499 COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary
COUNTY OF TARRANT § Contract NoZ
WHEREAS, GREENWAY-WESTERN CENTER, L.P., hereinafter called
"Developer", desires to make certain improvements to GREENWAY WESTERN
CENTER, an addition to the City of Fort Worth, Texas; and
WHEREAS, the said Developer has requested the City of Fort Worth, a municipal
corporation of Tarrant and Denton Counties, Texas, hereinafter called "City", to do
certain work in connection with said improvements.
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
For and in consideration of the covenants and conditions contained herein, the City and
the Developer do hereby agree as follows:
I. General Requirements
A. The Policy for the Installation of Community Facilities ("Policy")
dated March 2001, approved by the City Council of the City of Fort
Worth, is hereby incorporated into this Community Facilities Contract
as if copy herein verbatim. Developer agrees to comply with all
provisions of said Policy in the performance of its duties and
obligations hereunder.
B. The requirements of the Policy shall govern this Community Facilities
Agreement, provided, however, that any conflict between the terms of
this Community Facilities Agreement and the Policy shall be resolved
in favor of this Agreement.
C. Developer shall provide financial security in conformance with
paragraph 6, Section II, of the Policy.
D. The Developer shall award all contracts for the construction of
community facilities in accordance with Section II, paragraph 7 of the
Policy.
401 J ;lGt,1PIK? c
Greenway Western Center-Newer CFA 4% Jnd Utilities 09 13 05
E. The contracts for the construction of the public infrastructure shall be
administered in conformance with paragraph 8, Section II, of the
Policy.
F. The Developer further covenants and agrees to, and by these presents
does hereby, fully indemnify, hold harmless and defend the City, its
officers, agents and employees from all suits, actions or claims of any
character, whether real or asserted, brought for or on account of any
injuries or damages sustained by any persons (including death) or to
any property, resulting from or in connection with the construction,
design, performance or completion of any work to be performed by
said Developer, his contractors, subcontractors, officers, agents or
employees, or in consequence of any failure to properly safeguard the
work, or on account of any act, intentional or otherwise, neglect or
misconduct of said DEVELOPER, his contractors, sub-contractors,
officers, agents or employees, whether or not such iniuries, death or
damages are caused, in whole or in part, by the alleged negligence of
the City of Fort Worth, its officers, servants, or employees.
G. Developer shall install or adjust all of the required utilities to serve the
development or to construct the improvements required herein.
H. In the event that City participation exceeds $25,000, Developer agrees
that no street construction or storm drainage will begin prior to City
Council approval of this Community Facilities Agreement. (Article
104.100, Ordinance 7234).
I. Developer agrees that no lot shall be occupied under a certificate of
occupancy until the improvements required herein have been
constructed (Article 104.100, Ordinance 7234).
J. Developer hereby releases and agrees to indemnify and hold the City
harmless for any inadequacies in the preliminary plans, specifications
and cost estimates supplied by the Developer for this contract.
K. Developer agrees to provide, at its expense, all necessary rights of
and easements across property owned by Developer re uired. to
Greenway Western Center-Newer CFA 4% and Utilities 09 13 05
construct current and future improvements provided for in this
agreement.
L. Developer agrees to construct proposed improvements as shown on the
exhibits attached hereto. The following exhibits are made a part
hereof: Water (A)None; Sewer (A-1) None; Paving '(B)Attached
Storm Drain (B-1)Attached.
M. City shall not be responsible for any costs that may be incurred by
Developer in the relocation of any utilities that are or may be in
conflict with any of the community facilities to be installed hereunder.
Il. Street and Storm Drain Facilities
A. The Developer(s) agree to install or to cause to have installed, the street,
storm drainage, street lighting, street name sign and other community
facilities improvements shown as "current improvements" on the attached
Exhibits Band B 1.
B. As shown below in the "Summary of Cost for Street and Storm Drain
Facilities", the Developer shall fund its share of "current improvements"
and shall pay to the City for its share of the cost of street, storm drainage,
street lighting, street name signs as shown on the attached Exhibits Band
B 1. The estimated total cost of current improvements and related support
services specified in this agreement, including design, construction and
inspection is estimated to $ 10,967.84.
Greenway Western Center-Newer CFA 4% Rid Utilities 09 13 05
SUMMARY OF
COST
Greenway Western Center
Item Developer City Cost Total Cost
Cost
A. Construction $ -
1. Streets $6,546.00 6,546.00
2. Storm Drainage $4,000.00 4,000.00
3. Street Lights $0.00 $ -
4. Street Name Signs $0.00 $
B. Engineering Design $
C. Construction Engineering
and Management by DOE $ $
4% 421.84 421.84
TOTALS 10,967.84 $ - 10,967.84
Notes:
1. All Preliminary Plats filed after July 2000 will require sidewalks on all streets.
The developer is responsible for installation of sidewalk and a separate financial
guarantee is required in the form of a bond or check for the cost of the sidewalk.
2. Developer's column for Item C represents four percent(4%) cost for construction
inspection fees and materials testing. The City will pay additional inspection fee over
4%.
3. City not preparing plans and specifications.
Greenway Western Center-Newer CFA 4%and Utilities 09 13 05
IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be
executed in quadruplicate in its name and on its behalf by its Assistant City Manager,
attested by its City Secretary, with the corporate seal of the City affixed, by rum said D er
has executed this instrument in triplicate, at Fort Worth, Texas this the I of
,2005.
Approval Recommended:
Transportation and Public Works
Department
Robert Goode, P. E.
Director
ity o Wo
Marc Ott
ENO M&C REJQUIRED Assistant City Manager
ATTEST:
Marty Hendrix
City Secretary
App ed as to Form:
ssis t 9fty Attorney l
ATTEST:
e ':�vV,.UJly U�uti:
d
R VED
Corporate Secretary
S'�C.,o"L51L�d�'.
'n'➢ GL c
Greenway Western Center-Newer CFA 4%end Utilities 09 13 05
DEVELOPER:
Greenway-Western Center, L.P.
A Texas limited partnership
By: Blue M GP, LLC
A Texas limited liability company
General Partner
By:
Name: i/�/�/ J
Title:
Ila n.aV�:UIW9 UISG,
Greenway Western Center-Newer CFA 4% dnd Utilities 09 13 05
PBury Partners Bury&Parma-DFw,Inc.
E N G I N E E R I N G S O L U T I O N S
5310 Harvest H11 Road,Suite 100
Dallas,Texas 75230
Tel 9721991-0011
Fax 972M91-0278
ENGINEER'S PRELIMINARY OPINION OF PROBABLE CONSTRUCTION COST
PROJECT: Sonic Drive-In(Blue Mound) PROJECT NO: 30405-01
CLIENT: Greenway Investment Company DATE: September 12,2005
ESTIMATE PREPARED BY: BA/SMH
Note:Estimate only Includes proposed paving/drainage Improvements fo
a Community Facilities Agreement between the City of Fort Worth and the developer.
PAVING EXHIBIT 8
DESCRIPTION QUANTITY UNIT COSTIUNIT TOTAL COST
*Sawcut Existing Pavement 110 LF 2.00 220
*Remove Existing Pavement 25 SY $ 40.00 $ 1,000
*Dowel to Existing Pavement 100 LF $ 3.00 $ 300
6-inch Reinf.Conc.Pavement 3500 i 80 SY 22.00 1,760
6"Lime Stabilized Sub-grade 801 SY $ 2.25 $ 180
6%Hydrated Lime 1.11 TON 1 $ 105.00 $ 116
6"Integral Concrete Curb 85 LF $ 2.00 $ 170
4'Sidewalk 1501 LF $ 14.00 $ 2,100
Type I Sidewalk Ramp 21 EA 1 $ 350.00 $ 700
'Unk Aim naprmWean CFA Checkbt Paving Subtotal: $ 6,546
STORM DRAIN EXHIBIT B-1
DESCRIPTION QUANTITY UNIT COSTIUNIT TOTAL COST
*Remove EAsting Inlet 1 LS $ 500.00 $ 500
10'Recessed Inlet 1 EA $ 2 200.00 $ 2,200
*Pipe to PiDe Wye Connection 1 EA $ 400.00 $ 400
24"RCP 20 LF 44.00 880
Trench Safety 1 201 LF 1 1.00 20
'UnRP+ICotoprowWow CFA Chodd'st Storm Drain Subtotal: $ 4,000
DESCRIPTION TOTAL COST
Transportation&Public Works P Department
Paving Exhibit B 6,546
Storm Drain Exhibit B-1 $ 4,000
TOTAL ESTIMATED TPW COST TPW Subtotal: I $ 10,546
Notes:
1. The Preliminary Opinion of Probable Construction cost is made by an engineer,not a professional
cost estimator or construction contractor. The accuracy of the estimate is not guaranteed.
2. Paving and Storm Drain unit prices are based on City participating CFA unit prices.
3. Based on Preliminary Civil Plans dated August 30,2005.
Page t of 1
i
r
-----------------------------------
m_
ti NflN LANE t gag
TUR4 LANE
....�_ * 0 A a
� � � ve
FTW WATER MAP 2043-432W • •"
OWU ITY FACILITIES/ FULL DEPTH SAWCUT AND REMOVE EX a°m-
AGREEMENT (CFA) \ CONC CURB & GUTTER AND INLET.
z Deno I
IMPROVEMENTS PROPOSED CONST 40' CONC DRIVE APPROACH PER
-----------------_ _ DRIVEWAY CITY OF FORT WORTH STD
PROPOSED 35 LF SPEC aTI _NU OR CONSTRUCT_ION. Z a
OF 4' SIDEWALK
MATCH EXISTING E�VATfONS:— _—'—
Z n •O 7
.n
100' WESTERN CENTER BOULEVARD
EX CONC arm
- r
__
PROPOSED 115 LF rn
PROPOSED "TYPE 1" B Q
SIDEWALK RAMP OF 4 SIDEWALK UNOERDH /� ~W
(I�ELECTR�C (�W Z O
'MARKER �./ Ld 13:).:
Z I_—'—¢—¢wz
>m low0
F Q=Ula
f IZX Ooz
F Lj N>-2
I-
F U¢
LEGEND
CITY OF FT. WORTH STANDARD PAVEMENT:
SCALE: 1"-30'
CONCRETE PAVEMENT PER FORT WORTH STD
SPECIFICATIONS DRAWN: BPI
SIDEWALK & FLATWORK: DATE: 09/12/05
4" REINFORCED CONCRETE SIDEWALK SHEET N0.
FLATWORK (3.500 PSI AT 28 DAYS) W/q3
BARS ® 24" O.C.EW ON 4" AGGREGATE BASE
COURSE COMPACTED TO 90% STD PROCTOR. OF 1
--–––––––––––––––—––––––––––-
y4 TURN LANE —16"W
FTW WATER MAP 2048-432W A
STA
0
CONNE CT TO �X 24- SO
INSTALL 1-24 x45!x@EkD
————JNSTALLJ= COM Y FACILITIES
FL 679.38± ArREEMENZF*)—.--.--.---. z 0
MATCH EX FL
IMPROVEMENTS 00
Y WESTERN CENTER BOULEVARD 0 A
REMOVE EX CURB INLET
EX CQNC wpm
UOT
AM91.1)ISBELI "I
LLINE A' 8
24"SD z
- F-X
ON 0.88% ELEC CTRI < ir Ld
Z 0
0 M 1
GA
STA 0+19,24 LN 'A' fMASRKER uj
INSTALL 10' C.I.
PER DETAIL C5.3.4 I ———— — -- — —————-- L—
005
TIC 684.05
FL 679.55 Ca
tr=O0
Ox cn>--K
t ir
Ucc
SCALE: 1'-30'
DRAWN: BPI
DATE: 09/12/05
SHEET NO.
OF 1