HomeMy WebLinkAboutContract 46343-CO9 FORT WORTH..
CONTRACT NO.
City Of Fort Worth
Change Order Request
Facility and
Project Terminal Building Renovation Meacham International Airport City Sec No. 46343
Description:
Funding(FID)53902-0550435-5740010-C01527-C08180 City Proj.No. C01527
No.(s)
Contractord Imperial Construction Change order#F--9--] Date: 2/1/2017
City Project Mgr.Alfonso Meza CityInspector: IMikeMilam
Phone Number:817-392-8274 Phone Number: 817-392-2297
Contract Time
(CD)
Original Contract Amount-------------------------------------------- ------- $15,872,750.00 407
Extras to Date--------------------------------------------------------- – — — -- $2,175,093.00 201
Credits to Date------------–-----------– ------------------------ — –— $0.00 0
Pending Change Orders(in M&C Process)-------------------------------------------- $0.00 0
Contract Cost to Date----------------------------------------------------------------- $18,047,843.00 608
Amount of Proposed Change Order-------------------------- — $1,200,000.00 191
Revised Contract Amount---------------------------------------- --------------------- $19,247,843.00 799
Original Funds Available for Change Orders--------------------------------------------- $0.00
Remaining Funds Available for this CO-- ------------------------ $0.00
Additional Funding(if necessary)- -------------------------- $0.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 21.3 %
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $19,840,937.50
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Authorize a change in scope to increase the construction contract by$1,200,000.00 to complete the finish out of the customs suite.Authorize
Change Order No.9 for an increase in the cost of the Customs Office finish-out construction.The previous estimate of$500,000.00 was
appropriated through Change Order No.2 to City Secretary Contract No.46343.The increase in funding required to complete the finish-out is
due to an outdated cost estimate(completed nearly two years ago).The original estimate was based on scaling back the cost of a stand-
alone facility and with very general Customs and Border Patrol requirements.In the almost two years since the estimate was made the cost of
materials and labor have increased and full specifications/requirements for a Customs facility have been incorporated;with the final cost
estimate considerably greater than the original.The Customs facility will serve all airport tenants and increase business opportunities for the
City of Fort Worth.The total amount of change orders 1-9 results in an increase of the original contract amount by 21.3%.An additional 120
days added to the contract are for customs finish out and the remaining 71 days are for additional work authorized by the city through PC's
due to code requirements that were not on the plans and unforseens during construction of the base building.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incindental to the above Change Order.
Contractor's Company Name Contractor Name Contractor ignature Date
Imperial Construction
PMD Ins ct Date ro' c nager Date
Z•6%0 a 5 k620 1
PMD S erintendent Date AAhit ral Services M ager Date
.2 2' t�• t
ject Architect Date toriproperty Manage nt D artmeht Date
( '
Assistant City Att ney Date' Assistant City Manager Dante
Z zo R
ORT.�?i
mber C-28097 M&C Date Approved 1/31/2017
EOFFICIAL _
AdmftdU ' *
FORTWORTH.
H`�1� ROMCE CORRESPONDENCE
City of Fort Worth
Property Management/Architectural Services
February 15, 2017
FROM: BRIAN GLASS, ARCHITECTURAL SERVICES MANAGER
PROJECT: TERMINAL BUILDING RENOVATION AT MEACHAM INTERNATIONAL
AIRPORT - C01527
IMPERIAL CONSTRUCTION
SUBJECT: CHANGE ORDER #9
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
&.OvX4 /�. &&-,'
Brian R. Glass, AIA
Architectural Services Manager
PROPERTY MANAGEMENT DEPARTMENT
FACILITIES DIVISION/ARCHITECTURAL SERVICES
THE CITY OF FORT WORTH*401 WEST 13TH STREET*FORT WORTH,TEXAS 76102
(817)392-2586*FAX(817)392-8488
OftidaI site of the City of FortVloith,Texas
CITY COUNCILAGENDA FORT 11
DATE: 1/31/2017 REFERENCE C-28097 LOG NAME: 55FTW ADMIN BLDG FUNDING 3 -
NO.: CUSTOMS
CODE: C TYPE: NON- PUBLIC NO
CONSENT HEARING:
SUBJECT: Authorize Execution of Change Order No. 9 to City Secretary Contract No. 46343 with
Imperial Construction, Inc., to Increase Funding for the Meacham Administration Building
Renovation Project to Include Finish-out Construction for the Customs Facility, Authorize
Use of Revenue Derived from Mineral Leases on Airport Property in an Amount Up to
$1,200,000.00 to Fund Costs Associated With this Project at Fort Worth Meacham
International Airport for a Revised Total Project Amount of$22,637,882.00 and Adopt
Appropriation Ordinance (COUNCIL DISTRICT 2)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the use of unappropriated revenue derived from mineral leases on City-owned airports in
the amount of$1,200,000.00 to fund project costs associated with the Meacham Administration Building
Renovation Project at Fort Worth Meacham International Airport;
2. Adopt the attached appropriation ordinance increasing the estimated receipts and appropriations in
the Airports Gas Lease Capital Project Fund in the amount of$1,200,000.00 from available funds; and
3. Authorize execution of Change Order No. 9 to City Secretary Contract No. 46343 with Imperial
Construction, Inc., to increase the contract in an amount up to $1,200,000.00 for completion of the U.S.
Customs and Border Patrol Office finish-out.
DISCUSSION:
The Customs facility will serve all tenants and users of Meacham Airport, increasing business
opportunities for the City of Fort Worth and grow Meacham Airport's ability to meet its customer's
needs. This facility is being requested by such airport tenants as Texas Jet, American Aero, Richardson
Aviation, XTO Energy and Bell Textron. Many businesses and transient aircraft divert aircraft to other
regional airports to clear customs, prior to their final destination at Meacham Airport, due to lack of
customs availability at Meacham Airport. In addition to the loss of fuel flowage revenue, many
businesses have stated that having a Customs facility is the determining factor in relocating to
Meacham Airport, resulting in a further loss of aircraft operations, land revenue and hangar revenue.
On November 17, 2015, Mayor and Council Communication (M&C C-27536), the City Council
authorized $500,000.00 for project costs associated with the construction of a new U.S. Customs
facility. These funds covered the cost of providing a "shell" space for a customs facility, not full finish-out.
Funds approved in this M& C also covered the modification of tenant space to realize a more efficient
layout, additional finish-out construction to meet an increased demand for tenant suites that were added
to the project after the construction bid, as well as to increase the Owner' s General Contingency
Allowance (Allowance) in the contract with Imperial Construction, Inc. (Imperial Construction). At that
time, funds were programmed into the Aviation Capital Improvement Plan (CIP) to provide for full
customs finish-out in the 2017 fiscal year at $1,200,000.00.
M&C-27536, approved in November of 2015, also provided for the ballistic exterior wall of the suite
dividing it from the other Meacham Administration Building tenants. This portion of the Custom's Facility
could not be delayed. The Aviation Department is now recommending approval of Change Order No. 9
for the Customs Office finish-out construction at a cost of$1,200,000.00. This funding is required for the
Customs suite to complete the space including all requirements identified by the Customs and Border
Patrol during their review and approval of final design plans. The scope of the total finish-out includes
bullet proof wall's with a reinforced steel mesh lining around the entire exterior and interior of the suite,
blast proof glass, specialized IT infrastructure including cabling, networking and computers, security
systems including cameras and access control, two detention cells, interrogation room, closed circuit air
conditioning and electrical. The $1,200,000.00 being appropriated by this M&C for customs finish-out is
on the Aviation Department's CIP for Fiscal Year 2017.
By executing Change Order No. 9 to City Secretary Contract No. 46343 with Imperial Construction, the
$1,200,000.00 will be used to cover the cost of the Customs Office finish-out and bring the Project total
to $22,637,882.00.
Eight change orders have been executed to-date and are summarized in the table below.
NET
AMOUNT DATE CONTRACT DESCRIPTION
AMOUNT
Reconstruction
INITIAL of Meacham
CONTRACT $15,872,750.00 9-Dec-14 $ - Airport
Terminal
Building
Revise glazing
C01 $ 0.00.00 29-Apr-15 $15,872,750.00 spec for all
glass
Increase
CO2 $ 1,800,000.00 17-Nov-15 $17,672,750.00 contingency
allowance
�______ -__-
Increase
CO3 $ 99,988.00 19-Nov-15 $17,772,738.00 contingency
lallowance
_____- _._____ ..__..__..
Additional
fencing,
C04 $ 94,347.00 12-Jul-16 $17,869,085.00 pavement
removal, utility
work, flooring
design
C05 $ 50,503.00 14-Jul-16 ($17,917,588.00 Drainage
improvements
C06 $ 24,168.00 30-Aug-16 $17,941,756.00 Roofing
I
work/drains
Fill, flooring,�-
entrance
C07 $ 69,973.00 12-Sep-16 $18,011,729.00 signage, fire
sprinkler,
fencing
Signage -
008 $ 36,114.00 26-Sep-16 $18,047,843.00 interior/exterior
and associated
installation
Administration Building construction began on March 2, 2015, and was completed December 30, 2016.
It is anticipated that the Customs finish-out will begin spring of 2017 and be completed by summer
2017.
Subject to approval of this M&C, appropriations for this project will consist of the following:
Design $ 1,920,186 50
((Design Administration $ 80,345 00
Design Total $ 2,00 0,531.50
f
(Construction (Including General Contingency Allowance) $18,872,750.00
Materials Testing, Utilities, ITS, FF&E, Art, Contingency $ 1,764,600 50
Construction Total $20,637,350 50
PROJECT TOTAL $22,637,882.00
F
This Project is funded from the Airports Gas Lease Project Fund. The Customs Office finish-out is
included in the Aviation Department Capital Improvement Plan for Fiscal Year 2017.
Below is the total cost of ownership for the Administration Building at Fort Worth Meacham International
Airport:
Design and Construction $22,637,882.00
_------__ __.__.__._.._-___-
$13,236,750.00
Maintenance Reserves j $ 7,936,125.00
(System Upgrades $ 6,348,900 00
Total Cost of Ownership $50,159,657.00
M/WBE OFFICE — Imperial Construction, Inc., is in compliance with the City's BDE Ordinance by
committing to an additional 10 percent MBE participation on this Change Order No. 9.
This project is located in COUNCIL DISTRICT 2 at Fort Worth Meacham International Airport but will
serve Fort Worth residents of ALL COUNCIL DISTRICTS.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinances, funds will be available in the current capital budget, as appropriated,
of the Airports Gas Lease Capital Project Fund. The Airports Gas Lease Capital Project Fund has
unappropriated receipts in the amount of$6,064,143.23. After appropriations for this Project, remaining
unappropriated receipts will be $4,864,143.23 in the current capital budget, as appropriated, of the
Airports Gas Lease Capital Project Fund and that prior to an expense being incurred, the Department
has the responsibility to validate the availability of funds.
TO
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID ( Year I (Chartfield 2)
FROM
Fund Department Account Project Program Activity Budget Reference# Amount
ID__. _ L. Year Chartfield 2
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: Bill Welstead (5402)
Additional Information Contact: Julie Hostak (5407)
ATTACHMENTS
55FTW ADMIN BLDG FUNDING 3 -CUSTOMS.docx
ADMIN BLDG MAP2.pdf
Form 1295 C09.pdf
- - C
CERTIFICATE OF INTERESTED PARTIES FORM 1295
loll
Complete Nos.1-4 and 6 if there are interested parties. OFFICE USE ONLY
Complete Nos.1,2,3,5,and 6 if there are no interested parties. CERTIFICATION OF FILING
1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number:
of business. 2016-149107
Imperial Construction, Inc.
WEATHERFORD,TX United States Date Filed:
2 Name of governmental entity or state agency that is a party to the contract for which the form is 12/27/2016
being filed.
City of Fort Worth Date Ackn wledged:
()
3 Provide the identification number used by the governmental entity or state agency to track or identity the contract,and provide a
description of the services,goods,or other property to be provided under the contract.
01527 Meacham Administration
General Contracting of Administration Building Renovation
Nature of interest
4
Name of Interested Party City,State,Country(place of business) (check applicable)
Controlling Intermediary
I
5 Check only if there is NO Interested Party. ❑ f
X
6 AFFIDAVIT I swear,or affirm,under penalty of perjury,that the above disclosure is true and correct.
1
HOLLY DONALDSON 7
Notary Public,State of Texas
`mac My Commission Expires r
March 23,
20
Signature of authorized agent of contracting business entity
1
AFFIX NOTARY STAMP/SEAL ABOVE
Sworn to and subscribed before me,by the said I`(' , - � n S this the 2J day of 'C C/,-x (�
20 ,to certify which,witness my hand and seal of office.
Signature ofkifficer administering oath Printed name o officer administering oath Title of officer administering oath j
i
I
Forms provided by Texas Ethics Commission www.ethics.state.tx.us Version V1.0.277