HomeMy WebLinkAboutContract 30293 AMENDMENT NO.—4
STATE OF TEXAS $ CITY SECRETARY CONTRACT NO.
(No M&C Needed)
COUNTY OF TARRANT $
WHEREAS, the City of Fort Worth (City) and Kimley-Horn and
Associates, Inc. , (Engineer) made and entered into City Secretary
Contract No. 27675, (the Contract) which was authorized by the City
Council by M&C C-19071 on the 30th day of April, 2002 and
subsequently revised by three previous amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
Water Distribution System Improvements in the Medical
District.
WHEREAS, it has become necessary to execute Amendment No. 4 to
said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following
agreement which amends the Contract:
1.
Article I of the Contract is amended to include the additional
engineering services specified in a proposal letter dated July 9,
2004, a copy of which is attached hereto and incorporated herein.
The cost to City for the additional design services to be performed
by Engineer total $18,625.
2.
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $985,625.
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of , 2004, in Fort
Worth, Tarrant County, Texas.
ATTEST: --'k/0 ��'
Contract Adthorizatiou
Syl ' a Glover
Acting City Secretary Date
APPROVAL RECOb ENDED: APPROVED:
L4 ro��� 1 2��,,
Dale A. Fisseler, P.E. Marc A. Ott
irector, Water Department Assistant City Manager
KIMLZY-HORN AND ASSOCIATES, INC.
ENGINEER
�`''�
J'
Name: Glenn A. Gary, P.E.
Vige -President
801 Cherry Street, Suite 1025
Fort Worth. Tx 76102
APPROVED AS Z7 AND LEGALITY:
f
Gary Steinberger
Assistant City Attorney
-2-
'v
Kimley-Horn
and Associates, Inc.
■
July 9,2004 Suite 1025
801 Cherry Street,Unit 11
Fort Worth,Texas
Mr. Liam Conlon 76102-6803
Project Manager
City of Fort Worth Department of Engineering
1000 Throckmorton Street
Fort Worth,TX 76102
Re: City of Fort Worth-Water Distribution Improvements in the Medical District
Additional Services—Cathodic Protection and Unit Revisions
Contract Amendment No.4
KHA No. 061018017
Dear Liam:
As we have discussed with you,Kimley-Horn has performed several additional
scope items for the design of the Phase 2 plans for this project that were not
included in the original services of this contract. These items include the
following:
1. Project Unit Divisions-Per the request of the M/WBE department,
Kimley-Horn revised the plans to include an additional Unit for the
construction of the project. The revisions include changes to the cover
sheet,plan and profile sheets, sequencing, completing a new bid form
and revising the specifications.
2. Cathodic Protection-During the review of the final design of the
project,Kimley-Horn was directed to add steel pipe as an alternative pipe
material to the contract documents. This pipe material was added to
provide for more competition for 24-inch and larger pipe lines. Because
the project area is an older area of the City,there is a greater potential for
stray current which can adversely effect the design life of steel pipe. The
City instructed Kimley-Horn to evaluate,recommend and include
cathodic protection system plans and specifications for approximately
5,830 linear feet of 24-inch, 30-inch,and 36-inch water transmission
pipeline for this project. This requirement was given with fewer than 30
days to complete and still meet the deadline for the project bid schedule.
This change includes sub consultants for geotechnical services and the
design of the cathodic protection system.
The fees for adding Unit III to the Phase 2 project, and designing the cathodic
protection system are $6,900 and$11,725,respectively. Attached is a fee
breakdown for each of these tasks. Of the total, $18,625, $8,477 is for the
subconsultant expenses. The subconsultants we used were Corrpro Companies,
Inc., CMJ Engineering Inc., and GM Enterprises. The total fee for this. _
Amendment will be added to Task 6 Water Line Design and Bidding. This will
■
TEL 817 335 6511
FAX 817 335 5070
Kimley-Horn Mr.Liam Conlon,July 9,2004,Page 2
and Associates, Inc.
increase the total contract amount for this project to $985,625, as shown in
Table 1.
The following table summarizes our recommended budget revisions and their
distribution among the existing Tasks in the Contract:
Table 1
Task Description Original Amend. Amend. Amend. Amend. Task
Contract No. I No.2 No.3 No.4 Total
1 Data Collection and $ 89,150 $6,500 $5,200 No No $100,850
Field Investigation Changes Changes
2 Mapping $28,600 $7,500 $2,100 No No $38,200
Changes Changes
3 Analysis and $77,700 No No No No $77,700
Evaluation Changes Changes Changes Changes
4 Report and $ 50,150 No $1,600 No No $51,750
Communication Changes Changes Changes
5 Standard Operation $24,400 No $2,700 No No $27,100
Procedures Changes Changes Changes
6 Water Line Design $204,600 No $358,200 No $18,625 $581,425
and Bidding Changes Changes
7 Construction Phase NA NA $83,800 $24,800 No $108,600
Services Changes
Total $474,600 $14,000 $453,600 $24,800 $18,625 $985,625
Kimley-Horn will subcontract part of the geotechnical services for the design of
the cathodic protection system to the following M/WBE subconsultant: GM
Enterprises. The amount we anticipate to subcontract for this amendment is
approximately$1,022. Our revised M/WBE commitment would now be
$177,347. Since our revised contract amount will be $985,625,the revised total
contract M/WBE participation percentage will be 18.0%. The original M/WBE
goal for this project was 19.0%.
We appreciate the opportunity to be of continued service to the City. Please
contact us if we need to provide any further information.
Very truly yours,
KIMLEY-HORN AND ASSOCIATES, �—
.s`--
Glenn A.Gary,P.E.
Vice President
Attachment:
GAG/CTD:ctd
Copy to: Mr.Peter Fu,P.E.,Fort Worth Water Department
r:+oeroie.arym�nm��amvm_[mam,1mma.aoe
ten
City of Fort Worth Medical District Water System Analysis
Fee Breakdown
Amendment 4
Baylor All Saints Distribution System Improvements
PERSONNEL HOURS Labor Hours Total
P7 P6 P4-P5 P1-P3 A2 Labor Fee Subconsultants Fee
Task A3-6-Water Infrastructure Design
Baylor All Saints-Units I,II,and III(Phase 2)
Additional Services
Revise Plans for an additional Unit 4 12 40 6
Also includes the revisions to the Quantity Take Offs,
Bid Form,and Opinion of Probable Construction Cost
Cathodic Protection for Large Diameter Pipe Lines 2 5 12 2
Corrpro Subconsultant $6,275
Geotechnical Subconsuttant $1,180
Geotechnical MWBE Subconsuttant $1,023
10%of Subconsu@ants fees $848
SUBTOTAL 6 0 17 52 8 83
SUBTOTAL DOLLARS $1,000 $0 $2,200 $5,600 $500 $9,300
Task TOTAL $1,000 $0 $2,200 $5,600 $500 $9,300 $9,325 $18,625
PROJECT AMENDMENT TOTAL $9,300 $9,325 $18,625
in,