HomeMy WebLinkAboutResolution 3544-10-2007A Resolution
NO 3544-10-2007
STATEMENT EXPRESSING OFFICIAL INTENT
TO REIMBURSE COSTS OF THE SURGICAL CLINIC ADDITION TO THE
ANIMAL CARE AND CONTROL CENTER
WHEREAS, the City of Fort Worth, Texas (the "City") is a home-rule
municipality and political subdivision of the State of Texas,
WHEREAS, the City expects to pay expenditures in connection with the design,
planning, acquisition and construction for the project described on Exhibit "A"
hereto (collectively, the "Project") prior to the issuance of obligations by the City in
connection with the financing of the Project from available funds,
WHEREAS, the City finds, considers, and declares that the reimbursement of
the City for the payment of such expenditures will be appropriated and consistent
with the lawful objectives of the City and, as such, chooses to declare its intention , in
accordance with the provisions of Section 1 150 2 of the Treasury Regulations, to
reimburse itself for such payments at such time as it issues obligations to finance the
Project,
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FOR WORTH, TEXAS
Section 1 The City reasonably expects it will incur debt, as one or more series
of obligations, with an aggregate maximum principal amount not to exceed $498,000
for the purpose of paying the aggregate costs for the Project
Section 2 All costs to be reimbursed pursuant hereto will be capital
expenditures No tax-exempt obligations will be issued by the City in furtherance for
this Statement after the date which is later than 18 months after the later of (1) the
date the expenditures are paid of (2) the date on which the property, with respect to
which such expenditures were made, is placed in service.
Section 3 The foregoing notwithstanding, no tax exempt obligation will be
issued pursuant to the Statement more than three years after the date any
expenditure which is to be reimbursed is paid
RESOLUTION NO 3544 10 2007
Adopted this 16th day of October 2007
ATTEST ~'~?~ ~~"~ .-~rr~
'~ APPROVED
~'~~ ~_~~..~~~~~"l CITY C
,~ ~ ,~" ~ ~ ~ OUNClL
~~ ~ ~ ,~
~ ~' s ~ µ' ~CY ~ s 2~~7
~,
.r
B .. "
y - ~; _ .~
-- ~ ~ Y~n~
~ ~ r .?., ft ~ 4 .
1V][arty Hendrix, city.~s~ec.retary City Secretary of the
'f ""~`~"' ~- ~` Cit of Fort Worth Texas
err ~ , ..~ Y
f~fr~'rr
-. ;
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION Approved on 10/16/2007 Res. No.# 3544-10-2007 Ord No.# 17841 10-
2007 & 17842 10-2007
DATE Tuesday October 16 2007
LOG NAME 20SPAY&NPRIME REFERENCE NO C 22454
SUBJECT
Authorize Execution of a Construction Contract with Prime Construction Company for the Spay and
Neuter Surgical Clinic Addition to the Animal Care and Control Center Adopt Reimbursement
Resolution and Adopt Appropriation Ordinances
RECOMMENDATION
It is recommended that the City Council
1 Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Specially Funded Capital Projects Fund by $498 000 from available funds
2. Authorize the transfer of $498 000 from the Specially Funded Capital Projects Fund to the Animal Shelter
Fund
3 Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Animal
Shelter Fund by $498 000 from available funds,
4 Adopt the attached Reimbursement Resolution noting that the City expects to issue Certificates of
Obligation for the purpose of paying the increase in costs of this project; and
5 Authorize the City Manager to execute a construction contract with Prime Construction Company in the
amount not-to-exceed $887 000 for the Spay and Neuter Surgical Clinic addition to the Animal Care and
Control Center located at 4900 Martin Street.
DISCUSSION
On August 16 2005 M&C C-20904 authorized the execution of a professional services agreement with JRH
Architects Inc. in the amount of $58 800 for the design and construction administration services for the Spay
and Neuter Surgical Clinic addition to the City's existing Animal Care and Control Center
On January 18 2007 M&C C-15582 authorized the rejection of all bids received for the Spay and Neuter
Surgical Clinic addition to the City's existing Animal Care and Control Center and authorized the project be
redesigned and re-advertised for bid
The project was re-advertised on July 19 and 26 2007 in the Fort Worth Star Telegram On August 23 2007
Prime Construction Company was the only bidder and was one of the three bidders in the first
advertisement. Prime Construction Company constructed Fire Station No 38 which opened in February 2007
and is the contractor for Fire Station No 41 which is under construction
Logname 20SPAYNPRIME Page 1 of 3
The bid is as follows.
Base Bid and Alternate Nos. 2 through 4
Alternate No 1 Outdoor Fencing
$887 000 00
$13 000 00 Funded by Public Art; not included in contract
Alternate No 2 Consultation Room $96 000 00
Alternate No 3 Field Offices $112,000 00
Alternate No 4 Wainscot $19 000 00
Alternate No 1 was not part of the original scope and will be funded by Public Art. This will be constructed by
the artist and is not included as part of this construction budget.
Alternate No 2 was part of the original scope of the facility This was re-advertised as an additive alternate
Alternate No 3 was not part of the original scope but was added due to the impending expiration of the
temporary extension of the Certificate of Occupancy for the temporary facility for the field offices (484 SF)
Alternate No 4 was part of the original scope of the facility This was re-advertised as an additive alternate
The estimated overall cost of this project without the art component is
Design
Construction
FF&E
Contingency Geotech ITS Staff
Total
$73 500 00
$887 000 00
$65 000 00
$122.500.00
$1 148 000 00
This project is part of the 2004 Capital Improvement Program with an approved budget of $650 000 for the
project and $15 000 for the public art for this project. An additional $498 000 will be required to award the
construction contract. The overall project cost amount has additional contingencies and ITS costs.
During December 2006 staff identified $150 M in Critical Capital Needs, and Council authorized the sale of
Certificates of Obligation in each of the next four years to meet those needs This summer $43 5 M was sold
for projects identified in the first year of the Critical Capital Program Also during December staff advised
Council that due to inflation some cost overruns were anticipated from projects funded in the 2004 Bond
Program and that $10 M in unspecified debt capacity was reserved for this purpose Further staff advised
that these projects would be presented for Council consideration on an as-needed basis for inclusion in future
Certificate of Obligation sales of the Critical Capital needs. In the interim to avoid further construction delays
staff recommends these costs be funded by a loan from the Specially Funded Capital Projects Fund on a
temporary basis Subsequently in order to allow reimbursement of this fund staff recommends inclusion of
this amount in the next CO sale anticipated sometime in Spring 08 and the use of those proceeds to
reimburse this fund A reimbursement resolution is attached for this purpose
Prime Construction Company is in compliance with the City's M/WBE Ordinance by committing to 25 percent
M/WBE participation The City's goal for this project is 25 percent MNVBE participation
The project is physically located in COUNCIL DISTRICT 5 but will serve Fort Worth residents in ALL
COUNCIL DISTRICTS
FISCAL INFORMATION/CERTIFICATION
Logname 20SPAYNPRIME Page 2 of 3
The Finance Director certifies that funds upon approval of the above recommendations and adoption of the
appropriation ordinances, funds will be available in the current capital budget, as appropriated of the Animal
Shelter Fund
TO Fund/Account/Centers
1~C291 538070 174770080640 $498,000.00
3~C225 472001 201970014680 $498,000.00
~C225 541200 201970014680 $498,000.00
~C291 446100 174770080640 $498,000.00
FROM Fund/Account/Centers
2) C291 538070 174770080640
5)C225 541200 201970014680
$498.000.00
$887,000.00
Submitted for City Manager's Office ~ Marc A. Ott (8476)
Originating Department Head. Robert Goode (7804)
Additional Information Contact: Dalton Murayama (8088)
Logname 20SPAYNPRIME
Page 3 of 3