HomeMy WebLinkAboutContract 30561 AMENDMENT NO. 4
STATE OF TEXAS S CITY SECRETARY CONTRACT NO.(Q)05161
(No M&C Needed)
COUNTY OF TARRANT $
WHEREAS, the City of Fort Worth (City) and Ned K. Burleson &
Associates, Inc. , (Engineer) made and entered into City Secretary
Contract No. 27585, (the Contract) which was authorized by the City
Council by M&C C-19901 on the 19th day of March 2002, and
subsequently revised by three previous amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
Water and Sanitary Sewer Replacement Contract 2001 WSM-N
WHEREAS, it has became necessary to execute Amendment No. 4 to
said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following
agreement which amends the Contract:
1.
Article I of the Contract is amended to include the additional
engineering services specified in a proposal letter dated August
12, 2004, a copy of which is attached hereto and incorporated
herein. The cost to City for the additional design services to be
performed by Engineer total $8,949.33.
2.
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $144,397.20.
t ORIGINAL
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force
and effect.
EXECUTED on this the k:�L day ofLqpt2
,
2004, in Fort Worth, Tarrant County, Texas.
ATTEST:
P�\A J'-� Contract AuthorizatioA
Marty Hendri
City Secretary
Date
APPROVAL RECOMMENDED: AP D:
A. Douglas Rademaker, P.E. Mar 6 A. Ott
Director, Department of Ass�stant City Manager
Engineering
NED K. BURLESON & ASSOCIATES, INC.
ENGINEER
By:
Name: Ned K. Burleson, P.E. , President
2565 E. Loom 820 N. B1da. 12
Fort Worth. TX 76118
APPROVED AS TO FORM AND LEGALITY:
Gary Steinberger
Assistant City Attorney
-2-
FT.
NED K. BURLESON & ASSOCIATES, INC.
Consulting Engineers
August 12`h,2004
Liam Conlon
Department of Engineering
City of Fort Worth
1000 Throckmorton St.
Fort Worth, Texas 76102-6311
Reference: Amendment No.4, Water and Sanitary Sewer Improvements
Contract 2001 WSM-N (Water and Sewer Improvements) D.O.E. No. 3599
Dear Mr. Conlon:
In response to your request, Ned K. Burleson and Associates is please to present this fourth Amendment
for additional services for design and survey of an additional water line replacement within Lenox Drive
from Virginia Place to Dorothy Lane. The amendment shall include the following additional services:
• Design/Plan Preparation for the replacement of an existing 6-inch water line in Lenox Drive between
Virginia Place and Dorothy Lane with 820 Linear Feet of new 8-inch PVC pipe.
A Summary of the proposed budget for this amendment is as follows:
Additional Design/Plan Fee $ 6,309.33
Additional Design Survey Fee $ 2,400.00
Sub Consultant Fee $ 240.00
TOTAL PROPOSED AMENDMENT No. 4 $ 8,949.33
(Water Cost= $ 8,949.33; Sewer Cost= $ 0.00)
The additional design/plan fee was based upon the T.S.P.E. Curve %X 85%X Estimated Construction
Cost(additional water line only) Utilizing Curve 'A'= (11.0%X 85%X$67,479.50) = $6,309.33
Dal-Tech Engineering,Inc. (M/WBE Firm) will continue services for additional survey work
on this project. The additional survey work comprises 19.24% of the overall amendment price.
2565 E Loop 820 N • Fort Worth, Texas 76118 • 817-590-8800
PROJECT FEE DETAILS
Original Contract $67,505.57
Amendment No.1 $24;792.61
Amendment No.2 $24,620.63
Amendment No.3 $18,529.06
Amendment No.4 $ 8,949.33
TOTAL PROJECT $144,397.20
Water/Sewer Cost for entire project
(Water Cost= $63,527.03; Sewer Cost=$80,870.17)
If you have any questions or require additional information, please give me a call.
Sincerely,
Wade Goodman
Project Manager
2565 E Loop 820 N • Fort Worth, Texas 76118 • 817-590-8800
ENGINEERING, lNf%--.
CCNSULTiNS CML ENGINEERS/SURVEYCPS
GMTRUCTICN MANASERS
August 11, 2004
VIA FACSIMILE 817-590-889
Mr. Wade Goodman
Ned K. Burleson & Associates, Inc.
2565 East Loop 820 North
Fort Wor-b. Texas 76118
RE: Sanitary Sewer/Nater Replacement,Fee.Proposal,Additional Services
Fort R'orth, Texas
DAL-TECH Job 4 0206
Dear Mr. Goodman:
DAL-TECH Engineering, Inc. is very pleased to submit a fee proposal to perforiii
additional sun•eving services for the above refererced project in Fort Worth, Texas. As
requested in your Uxe.d letter dated August 11. 2004 we will perfonn a design survey of the area
within the right-of-way of Lenon:Drive between Virginia Place and Dorothy Lane, a distance of
approximately 820 linear feet. We will also measure the depths of any associated manlholes if
we are able to open-them.
This survey will also show all topographic features and grade breaks located within the
above-described areas. An electronic AutoCAD drawing will be provided containing contours at
1-foot intervals. A .dat, An, and ASCII points file will also be provided along with the Survey.
DAL-TECH recommends a lurrip sum budget of$2,400,00 to complete these surveying
services. If you are in agreement with this fee proposal, please sign in the space provided below
and return this acknowledgement to our office. We will deliver the survey within 15 working
days of your authorization to proceed. This will serve as our authorization to proceed and our
right to enter the property for surveying purposes.
Sincerely,
Alan Moore, R.P.L.S.
Chief Surveyor
Ned K. Burleson & Associates, Inc.
'r- Z_-k �y
Sign• , re Date
972.250-2727 / FAX 972-250-4774
222 W. EXCHANGE I FT. WORTH, TX 76106 / 817-626-8717 / FAX 617-626-5777
wy,wtal-tech.ccrr
CFW DOE#3599 (WSM-N) UNIT 2
OPINION OF PROBABLE COST(AUG 2004)
WATER REPLACEMENT- LENOX DRIVE
PAY
ITEM QTY. UNITS DESCRIPTION OF PAY ITEMS UNIT COST TOTAL
15 LF 6" PVC Water Line $24.00 $360.00
805 LF 8" PVC Water Line $28.00 $22,540.00
2 EA. Plug and Abandon Exist. 6"Water Line $200.00 $400.00
2 EA. 8"Gate Valve with C.I. Box and Lid $600.00 $1,200.00
24 EA. Furnish and Set Class A Meter Boxes $80.00 $1,920.00
0 EA. Furnish and Set Class B Meter Boxes $175.00 $0.00
0 EA. Furnish and Set Class C Meter Boxes $200.00 $0.00
675 LF 1"Copper Water Service Line Replacement from Meter to Main $15.00 $10,125.00
0 LF 1 1/2"Copper Water Service Line Replacement from Meter to Main $20.00 $0.00
0 LF 2"Copper Water Service Line Replacement from Meter to Main $22.00 $0.00
24 EA. 1"Water Service Tap, Saddle,Stop& Fittings from Service to Main $250.00 $6,000.00
1 1/2"Water Service Tap, Saddle, Stop& Fittings from Service to
0 EA. Main $350.00 $0.00
0 EA. 2"Water Service Tap,Saddle,Stop&Fittings from Service to Main $500.00 $0.00
3/4" Copper Water Service Line Replacement from Meter to Property
240 LF Line $10.00 $2,400.00
Lump Fumish and Lay 2" Pipe and Fittings for Temp. Water Service
1 Sum Connections $5,000.00 $5,000.00
0.5 Tons C.I./D.I. Fittings $3,000.00 $1,500.00
750 LF 2" Hot Mix with 6" Flex Base $7.00 $5,250.00
75 LF Conc. Curb and Gutter Replacement $30.00 $2,250.00
200 LF Grass Sodding $12.00 $2,400.00
Subtotal-Water $61,345.00
$6,134.50
$67,479.50