HomeMy WebLinkAboutContract 30578-A2 CITY SECRETARY Z
CONTRACT NO.
CSJ#0902-48-558
District#02-Fort Worth
Code Chart 64#15000
Project: Historic Handley Village
Federal Highway Administration
CFDA#20.205
Not Research and Development
STATE OF TEXAS §
COUNTY OF TRAVIS §
ADVANCE FUNDING AGREEMENT
AMENDMENT#2
THIS AMENDMENT is made by and between the State of Texas, acting through the Texas
Department of Transportation, called the State, and the City of Fort Worth, acting by and through its
duly authorized officials, called the Local Government.
WITNESSETH
WHEREAS, the State and the Local Government executed a contract on January 13, of 2011 to
effectuate their agreement to design and construct several on and off system locations within the
Historic Handley Urban Village; and,
WHEREAS, Amendment 1 was executed on April 1, 2011 to add language to Article 10;
WHEREAS, the scope of work from the original contract executed January 13 of 2011 is revised to
delete three off-system locations; and,
WHEREAS, it is necessary to add to the original agreement Green Ribbon Landscaping Planting
Program project funding and responsibilities; and,
WHEREAS, Rider 15 of Senate Bill 1 of the 82nd Legislature, expands the Green Ribbon Project, a
public-private partnership initiative, to include the Green Ribbon Landscaping Planting Program, to
enhance the appearance of public highways by incorporating in the design and improvement of
public highways the planting of trees and shrubs, integrating public art, and highlighting culturab
uniqueness of neighborhoods, and allocates funds for landscaping activities including the planting
and establishment of trees and plants on the state highway to help mitigate the effects of air pollution
in non-attainment and near non-attainment areas; and,
WHEREAS, it has become necessary to amend that contract;
NOW THEREFORE, in consideration of the premises and of the mutual covenants and agreements
of the parties, the State and the Local Government do agree as follows:
AFA-AFA_Amend Page 1 of 3 Revised 04/08111
09-24-12 A
CSJ #0902-48-558
District# 02-Fort Worth
Code Chart 64#15000
Project: Historic Handley Village
Federal Highway Administration
CFDA#20.205
Not Research and Development
THIS AGREEMENT IS EXECUTED by the State and the Local Government in duplicate.
THE LOCAL GOVERNMENT
1110-� 4-41.,
Signature fxRPROVED AS TO
&AAA1Z 6L5FORM AND LEGALITY:
Typed or Printed Name
SS1 �1 Ty 9421ASSISTANT CITY ATTORNEY
Title
�
Dat by p 9,°°°°°°0 �a
°°
000
THE STATE OF TEXAS Mary J. ser, C1 S ° o°p •fid
�e"]y?�V2,0-A' ¢ o �,
° o° d
anice Mullenix J*"'OOO000°° q'
��aatx�A 4��aa
erector of Contract Services Atiao
Tec"12
exassDepartment of Transportation
Date
AFA-AFA_Amend Page 3 of 3 Revised 04/08/11
CSJ #0902-48-558
District#02 - FTW
Code Chart 64# 15000
Project: City of FTW Corridor
Redevelopment Project-Historic
Handley Village
Federal Highway Administration
CFDA#20.205
Not Research and Development
Attachment C-1
Budget Estimate and Source of Funds
Costs will be allocated based on 100% Federal funding for Engineering and Construction (TCSP
funds) and 100% Federal and State funding (Green Ribbon) for Construction until the federal and
state funding reaches the maximum obligated amount. The Local Government will then be
responsible for 100% of the costs.
Description Total Estimated Federal State Local
Cost Participation Participation Participation
% Cost % Cost % Cost
Engineering $78,741 100% $78,741 0% $0 0% $0
1(by Local
Construction $297,099 100% $297,099 0% $0 0% $0
(by Local Government
Construction (by Local $68,000 80% $54,400 20% $13,600 0% $0
Government) Green Ribbon
Subtotal $443,840 $430,240 1 $13,600 $0
Engineering Direct State Casts $4,014 100% $4,0140% $0 0% $0
Construction Direct State Costs $15,146 100% $15,146 0% $0 0% $0
Construction Direct State Costs $3,46780% $2,774 20% $693 0% $0
TOTAL $446,467 0% $452,174 % $14,293
Initial payment by the Local Government to the State: $0
Payment by the Local Government to the State before construction: $0.00
Estimated total payment by the Local Government to the State $0.00
This is an estimate. The final amount of Local Government participation will be based on actual
costs.
Page 1 of 1 Attachment C-1
CSJ #0002-48-558
District#02 - FTW
Code Chart 64 # 15000
Project: City of FTW Corridor
Redevelopment Project-Historic
Handley Village
Federal Highway Administration
CFDA#20.205
Not Research and Development
ATTACHMENT D
Green Ribbon Landscaping Planting Project Responsibilities
Contract Period
The Green Ribbon Landscaping Planting Project between the State and the Local Government
becomes effective upon the date of final execution of this Agreement by the State, and the
maintenance responsibilities by the Local Government shall extend from the completion of the
landscape installation by the Local Government's contractor, and remain in effect for a five year
period. The agreement shall then renew automatically on an annual basis until it is mutually
determined by the Local Government and the State the plant materials are sufficiently established to
survive without additional care or until this Agreement is terminated or modified as stated in the
Master Agreement.
Local Government's Responsibilities
The Local Government shall install landscaping and irrigation in accordance with the plans and
specifications set forth in the Project. The State, having had the opportunity to review the plans, may
provide input to the Engineer regarding the installation of the plant material and irrigation system
under the contract.
Following the completed installation of the landscape items as shown in the plans, the Local
Government shall assume maintenance of the Project in accordance with State standards. The Local
Government shall:
For the work of plant maintenance, provide all reasonable means to preserve the plants
existing within the project limits in a healthy and vigorous growing condition. This maintenance
activity shall include but not be limited to the following:
(1) Water plants and vegetation
(2) Plant bed and basin maintenance including shaping, weed control, and mulching/mulch
layering
(3) Plant replacement after the original plant maintenance period
(4) Insect, Disease, and Animal Control
(5) Fertilizing
(6) Mowing and Trimming
(7) Re-staking, re-guying, re-bracing and, when applicable, removal of staking, guying and
bracing
(8) Pruning
(9) Litter pickup
Page 1 of 2 Attachment D
0902-48-558
CSJ #
District# 02 - FTW
Code Chart 64# 15000
Project: City of FTW Corridor
Redevelopment Prosect-Historic
Handley Village
Federal Highway Administration
CFDA#20.205
Not Research and Development
Irrigation System Operation and Maintenance
Permanent irrigation system operation and maintenance shall include, but not be limited to,
watering, monitoring, adjustment, repairing, and proper operation of the existing irrigation
system as required, to ensure adequate moisture to the plant material existing on the site. It
shall also include adjusting the system to keep water off hardscapes. All replacement parts
shall be of the same type and manufacturer as originally installed. Substitute parts may be
allowed with the approval of the State prior to replacement.
Page 2 of 2 Attachment D
M&C Review Pagel of 2
Official situ of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FORT 111
COUNCIL ACTION: Approved on 9/18/2012 - Ordinance No. 20386-09-2012
DATE: 9/18/2012 REFERENCE NO.: **G-17663 LOG NAME: 06HANDLEYGR
CODE: G TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorization to Accept and Execute an Agreement with Texas Department of
Transportation for a Green Ribbon Landscaping Planting Program Grant in the Amount of
$68,000.00 for Landscaping Improvements, an Irrigation System and Landscape
Maintenance Costs in the Historic Handley Urban Village Streetscape Project and Adopt
Appropriation Ordinance (COUNCIL DISTRICT 5)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the acceptance a Green Ribbon Landscaping Planting Program grant in the amount of
$68,000.00 from the Texas Department of Transportation to fund landscaping improvements, an
irrigation system and landscape maintenance costs in the Historic Handley Urban Village streetscape
project;
2. Authorize the City Manager to execute a Grant Agreement with Texas Department of
Transportation to fund the improvements listed above; and
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in
the Grants Fund in the amount of$68,000.00, upon receipt of the grant.
DISCUSSION:
In response to the Texas Department of Transportation's (TxDOT) call for projects under its Green
Ribbon Landscaping Planting Program, Staff requested and was awarded a grant in the amount of
$68,000.00 to fund new landscape improvements, an irrigation system, and landscape maintenance
costs for one-year in the Historic Handley Urban Village.
The Green Ribbon Landscaping Planting Program allocates funds for landscaping activities including
the planting and establishment of native and adapted trees and plants on state highways to help
mitigate the effects of air pollution in non-attainment and near non-attainment areas. Eligible projects
must be located on a state highway within the right-of-way and be under contract in TxDOT's 2013
fiscal year(September 1, 2012 to August 31, 2013).
The Historic Handley Urban Village streetscape project, which is funded by a Federal Highway
Administration Transportation, Community, and System Preservation (TCSP) grant in the amount of
$395,000.00 (M&C G-14062), is located on State Highway 180 (East Lancaster Avenue), a TxDOT on-
system highway. The streetscape project is currently under design and includes new landscaping in
rain gardens and planter pots, reconstruction of a substandard sidewalk adjacent to the Handley
historic storefronts, and installation of a new sidewalk and pedestrian lights across the street from the
storefronts. Additional project funding from the TxDOT Green Ribbon Landscaping Planting Program
was sought to augment the $395,000.00 TCSP grant. The TxDOT award of$68,000.00 will help
ensure adequate funding is available to construct the fully designed streetscape project and will save
the City one-year of landscape maintenance costs associated with the project.
The TxDOT Green Ribbon Landscaping Planting grant does not require a local match.
The project is located in COUNCIL DISTRICT 5.
http://apps.cfwnet.org/council_packet/mc review.asp?ID=17301&councildate=9/18/2012 10/16/2012
M&C-Review Page 2 of 2
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that upon approval of the above
recommendations, receipt of the grant, and adoption of the attached appropriation ordinance, funds
will be available in the current budget, as appropriated in the Grants Fund.
TO Fu nd/Accou nt/C enters FROM Fund/Account/Centers
GR76 451942 022302591000 $68,000.00
GR76 5 $68,000.00
(VARIOUS) 022302591 XXX
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: Randle Harwood (6101)
Additional Information Contact: Patrina Newton (8068)
ATTACHMENTS
06HANDLEYGR A012.doc
HandleyGR M&C Map.pdf
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=17301&councildate=9/18/2012 10/16/2012