HomeMy WebLinkAboutContract 31811 COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary
COUNTY OF TARRANT § Contract No. l b i
WHEREAS, Kimball Hill Chadwick Farms, L. P., hereinafter called "Developer",
desires to make certain improvements to Chadwick Farm, Section 2, an addition to the
City of Fort Worth, Texas; and
WHEREAS, the said Developer has requested the City of Fort Worth, a municipal
corporation of Tarrant and Denton Counties, Texas, hereinafter called "City", to do
certain work in connection with said improvements.
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
That said Developer, acting herein by and through Kimball Hill Homes Dallas,
LP, its general partner, acting herein by and through Kimball Hill Homes Dallas
Operations, LLC, acting herein by and through Samuel L. Wyse, III, its duly authorized
vice president, and the City, acting herein by and through Marc Ott, its duly authorized
Assistant City Manager, for and in consideration of the covenants and conditions
contained herein, do hereby agree as follows:
I. General Requirements
A. The Policy for the Installation of Community Facilities ("Policy")
dated March 2001, approved by the City Council of the City of Fort Worth, is
hereby incorporated into this Community Facilities Contract as if copy herein
verbatim. Developer agrees to comply with all provisions of said Policy in the
performance of its duties and obligations hereunder.
B. The requirements of the Policy shall govern this Community Facilities
Agreement, provided, however, that any conflict between the terms of this
Community Facilities Agreement and the Policy shall be resolved in favor of this
Agreement.
C. Developer shall provide financial security in conformance with
paragraph 6, Section II, of the Policy.
D. The Developer shall award all contracts for the construction of
community facilities in accordance with Section II, paragraph 7 of the Policy.
COMMUNITY FACILITIES AGREEMENT
CHADWICK FARMS,SECTIONII �., � � ^ g4%meq•p 7��''
Page I of 4"� '��.,1..-', f: V�J�✓
;CVD ,o�
:T: � L�,
E. The contracts for the construction of the public infrastructure shall be
administered in conformance with paragraph 8, Section II, of the Policy.
F. The Developer further covenants and agrees to, and by these presents
does hereby, fully indemnify, hold harmless and defend the City, its officers,
agents and employees from all suits, actions or claims of any character, whether
real or asserted, brought for or on account of any injuries or damages sustained by
any persons (including death) or to any property, resulting from or in connection
with the construction, design, performance or completion of any work to be
performed by said Developer, his contractors, subcontractors, officers, agents or
employees, or in consequence of any failure to properly safeguard the work or on
account of any act, intentional or otherwise, neglect or misconduct of said
DEVELOPER, his contractors, sub-contractors, officers, agents or employees,
whether or not such injuries, death or damages are caused, in whole or in part,
by the alleged negligence of the City of Fort Worth, its officers, servants, or
employees.
G. Developer shall install or adjust all of the required utilities to serve the
development or construct the improvements required herein.
H. In the event that City participation exceeds $25,000, Developer agrees
that no street construction or storm drainage will begin prior to City Council
approval of this Community Facilities Agreement. (Article 104.100, Ordinance
7234).
I. Developer agrees that no lot shall be occupied under a certificate of
occupancy until the improvements required herein have been constructed (Article
104.100, Ordinance 7234).
J. Developer hereby releases and agrees to indemnify and hold the City
harmless for any inadequacies in the preliminary plans, specifications and cost
estimates supplied by Developer for this contract.
K. Developer agrees to provide, at its expense, all necessary rights of way
and easements across property owned by Developer required to construct Current
'fled 1*LIttlrc provided for in this agreement.
COMMUNITY FACILITIES AGREEMENT !• ` �' p^�
CHADWICK FARMS,SECTIONII
Page 2of5
\�)afL
Ue `✓1 i
L. Developer agrees to construct the proposed improvements as shown on
the following exhibits which are attached hereto and incorporated herein for all
intents and purposes:
Exhibit B Paving
Exhibit B-1 Storm Drains
Exhibit C Street Lights and Signs
M. City shall not be responsible for any costs that may be incurred by
Developer in the relocation of any utilities that are or may be in conflict
with any of the community facilities to be installed hereunder.
II. Street and Storm Drain Facilities
A. The Developer(s) agree to install or to cause to have installed, the street,
storm drainage, street lighting, street name sign and other community
facilities improvements shown as "current improvements" on the attached
Exhibits B, B1, and C.
As shown below in the "Summary of Cost for Street and Storm Drain Facilities", the
Developer shall fund its share of"current improvements" and shall pay to
the City kir its share of the cost of street, storm drainage, street lighting,
street name signs as shown on the attached Exhibits B, B 1, and C. The
estimated total cost of current improvements and related support services
specified in this agreement, including design, construction and inspection
is estimated to $800,067.12.
COMMUNITY FACILITIES AGREEMENT �' r� 1N•�'�, �pp�y iI f
CHADWICK FARMS,SECTIONII
Page 3 of 5
SUMMARY OF COST
Chadwick Farms Section 2
Item Developer City Cost Total Cost
Cost
A. Construction
1. Streets $516,597.70 $ 107,973.00 $ 624,570.70
2. Storm Drainage $115,095.20 $ 115,095.20
3. Street Lights $33,500.00 $ 33,500.00
4. Street Name Signs $300.00 $ 300.00
B. Engineering Design $ -
C. Construction Engineering $
and Management by DOE (4%) $ 26,601.22 $ 26,601.22
TOTALS $692,094.12 $ 107,97300j$ 800,067.12
Notes:
1. All Preliminary Plats filed after July 2000 will require sidewalks on all streets.
The developer is responsible for installation of sidewalk and a separate financial
guarantee is required in the form of a bond or check for the cost of the sidewalk.
2. Developer's column for Item C represents four percent (4%) cost for construction
inspection fees and materials testing. The City will pay additional inspection fee over
4%.
3. City not preparing plans and specifications.
COMMUNITY FACILITIES AGREEMENT
CHADWICK FARMS,SECTIONII
Page 4 of 5
r
ONI
h }�
Executed this day of I 1 , 2005.
Approval Recommended: CI O ORT W TH
Robert Go e, P. E., Director Mac A
Transportation and Public Works Assistant City Manager
ATTEST: Approve as to Form and Legality:
���
Marty Hendrix Assistant CTMtorney
City Secretary
Attest: DEVELOPER
Kimball Hill Chadwick Farms LP
A Texas Limited Partnership
b By: Kimball Hill Homes, LP
It's General Partner
'ontract Authoriaatioia��— By: Kimball Hill Homes Dallas
nate Operations, LLC
It's General Partner
tT4
Samuel L.Ivyse, III
Vice President
VED
COMMUNITY FACILITIES AGREEMENT
CHADWICK FARMS,SECTIONII
Page 5of5
ENGINEER'S OPINION OF PROBABLE COST
Date: 3/25/2004 Project: Chadwick Farms, Section 2 Client: Kimball Hill
Homes
Job No: 9933 Location: Fort Worth, Texas Page: 1 of 3
ITEM UNIT TOTAL
No. DESCRIPTION UNIT QUANTITY PRICE COST
Paving Facilities
1. 6" Concrete Pavement S.Y. 4,660 $19.75 $92,035.00
2. 8" Concrete Pavement S.Y. 8,588 $24.00 $206,112.00
3. Lime Stabilized Subgrade S.Y. 14,408 $3.50 $50,428.00
4. 8" Concrete Pavement * S.Y. 3,999 $24.00 $95,976.00
(T/PW Participation)
5. Lime Stabilized Subgrade * S.Y. 3,999 $3.50 $13,996.50
(T/PW Participation)
6. Barrier Free Ramps Ea. 6 $400.00 $2,400.00
7. Barricade& Header L.F. 87 $13.36 $1,162.20
8. 4' Concrete Sidewalk L.F. 3,892 $14.00 $54,488.00
(Thoroughfare and Non-Residential)
Paving Subtotal $516,597.70
* Transportation/Public Works Cost Participation is based up on the annexation agreement
for Chadwick Farms,which stipulates the CFA policy at the time of annexation will be utilized for
said development. Therefore,T/PW Cost Participation for Cleveland-Gibbs Road Improvments
for turn lanes,median breaks, first 7 feet of concrete paving width,and subgrade
totals$108,873 with 10%contingency.
This Engineer's opinion of probable construction cost is made on the basis of the Engineer's experience
and best judgement as a design professional. It must be recognized that any evaluation of work to be
performed to construct this project must by necessity be speculative in nature until completion of its actual
detailed design. In addition the engineer has no control over the cost of labor material or services to be
furnished by others or over market conditions. Accordingly Goodwin & Marshall, Inc. can not guarantee
that actual costs will not vary from the opinions expressed herein.
ENGINEER'S OPINION OF PROBABLE COST
Date: 3/25/2004 Project: Chadwick Farms, Section 2 Client: Kimball Hill
Homes
Job No: 9933 Location: Fort Worth, Texas Page: 2 of 3
ITEM UNIT TOTAL
No. DESCRIPTION UNIT QUANTITY PRICE COST
Storm Drain Facilities
1. 10'Depressed Curb Inlets Ea. 4 $2,300.00 $9,200.00
2. 15' Depressed Curb Inlets Ea. 1 $2,500.00 $2,500.00
3. 21" R.C.P. L.F. 48 $40.00 $1,920.00
4. 24" R.C.P. L.F. 139 $44.00 $6,116.00
5. 30" R.C.P. L.F. 742 $52.00 $38,584.00
6. 36" R.C.P. L.F. 180 $64.00 $11,520.00
7. 42" R.C.P. L.F. 292 $84.00 $24,528.00
8. 48" R.C.P. L.F. 29 $110.00 $3,190.00
9. 48" Sloped End Headwall Ea. 1 $3,000.00 $3,000.00
10. 4' x 4' Junction Box Ea. 2 $3,000.00 $6,000.00
11. 5' x 4' Junction Box w/M.H. Riser Ea. 1 $5,500.00 $5,500.00
12. Gabion Mattress S.Y. 24 $66.97 $1,607.20
13. Trench Safety L.F. 1,430 $1.00 $1,430.00
Storm Drain Subtotal $115,095.20
This Engineer's opinion of probable construction cost is made on the basis of the Engineer's experience
and best judgement as a design professional. It must be recognized that any evaluation of work to be
performed to construct this project must by necessity be speculative in nature until completion of its actual
detailed design. In addition the engineer has no control over the cost of labor material or services to be
furnished by others or over market conditions. Accordingly Goodwin & Marshall, Inc. can not guarantee
that actual costs will not vary from the opinions expressed herein.
rr1 l O, �N1,
Iq� P1,,f
ENGINEER'S OPINION OF PROBABLE COST
Date: 3/25/2004 Project: Chadwick Farms, Section 2 Client: Kimball Hill
Homes
Job No: 9933 Location: Fort Worth, Texas Page: 3 of 3
ITEM UNIT TOTAL
No. DESCRIPTION UNIT QUANTITY PRICE COST
Miscellaneous
1. Street Lights L.S. 1 $33,500.00 $33,500.00
2. Street Signs L.F. 3 $100.00 $300.00
Miscellaneous Subtotal $33,800.00
This Engineer's opinion of probable construction cost is made on the basis of the Engineer's experience
and best judgement as a design professional. It must be recognized that any evaluation of work to be
performed to construct this project must by necessity be speculative in nature until completion of its actual
detailed design. In addition the engineer has no control over the cost of labor material or services to be
furnished by others or over market conditions. Accordingly Goodwin & Marshall, Inc. can not guarantee
that actual costs will not vary from the opinions expressed herein.
''Ip}(/ rz n-
TAA2y
� 'THY R",
I. STREET LIGHT COST ESTIMATE
QUANTITY UNIT COST TOTAL COST
INTERSECTIONS 1 EA $ 2, 000 $2 , 000 . 00
MID-BLOCK RESIDENTIAL 2 EA $ 2, 000 $4, 000 . 00
CHANGE OF DIRECTION RESIDENTIAL 1 EA $ 2, 000 $2, 000 . 00
MID-BLOCK COLLECTOR 0 EA $ 2, 000 $0 , 000 . 00
MID-BLOCK ARTERIAL PARKWAY 0 EA $ 2, 500 $0, 000 .00
MID-BLOCK ARTERIAL MEDIAN 9 EA $ 2, 500 $22, 500 . 00
RELOCATE EXISTING LIGHT 0 EA $ 1, 500 $0, 000 . 00
Subtotal $30, 500 . 00
City' s Cost $00, 000 . 00
Developer's Subtotal $30, 500 .00
10% Contingencies $3, 500.00
Project Total $33, 500.00
Adjacent Developer' s Cost $0, 000.00
Developer's Cost $33,500 .00
2% Inspection Fee $0, 00.00
DEVELOPER'S COST: $33, 500.00
CHADWICK FARMS, SECTION II
May 19, 2004
Fort Worth, Texas
May 25, 2004
PAGE I OF Exhibit C
II. STREET LIGHTS WORK DESCRIPTION:
1 . The Developer shall provide for the installation of streetlights at
the approximate locations shown in Exhibit "C" , immediately after
final acceptance of the street construction, in accordance with
engineering plans and specifications approved by the Transportation
and Public Works Department .
2 . Streetlights on residential and /or collector streets can be
installed using overhead or underground conductors with the approval
of the Director of Transportation and Public Works .
3 . The City will install all the streetlights that use overhead or
underground conductors on residential, and collector streets, the
developer agrees to pay the city the amount shown below prior to the
City starting it' s design efforts.
4 . Streetlights on arterial streets shall be installed with underground
conduit and conductors .
5 . The Developer agrees to dedicate all easements required for the
installation and maintenance of the street lights and to provide for
the installation of any electrical transformers required for the
proper operation of the street lights
6 . The estimated cost of this street light installation is detailed on
page 1 of exhibit C and is summarized below, the street lights will
remain the property of, and will be maintained by the City of Fort
Worth.
DEVELOPER'S COST: $33,500.00
CHADWICK FARMS, SECTION II
May 19, 2004
FORT WORTH, TEXAS
Page II of Exhibit C
III.
"STREETLIGHTS"
INTERSECTIONS
SWEETPINE LN & YARDBERRY DR 1
MID-BLOCK
SWETTPINE LN 1
YARDBERRY DR 1
CHANGE OF DIRECTIONS
YARDBERRY DR 1
MID-BLOCK MEDIAN
CLEVELAND GIBBS RD_ 9
CHADWICK FARMS, SECTION II
Page III of Exhibit C
IV
STREET NAME SIGNS
1 . The City of Fort Worth will install the street name signs upon
final approval of the street construction. The street name signs
will remain the property of, and will be maintained by, the City
of Fort Worth.
2 . The Developer will pay for the street name sign installations
required for this development to the extent of $100 . 00 per
intersection. This unit cost will be revised annually by the
Department of Transportation and Public Works to reflect
prevailing costs of materials and labor.
3 . This development creates the following three (3) intersections at
a cost to the Developer of $300 .00 :
Cleveland Gibbs Rd & Sweetpine Lane (NB)
Cleveland Gibbs Rd & Sweetpine Lane (SB)
Yarberry Dr & Sweetpine Lane
Chadwick Farms Section 2
CFA code: 2004053 Date : May 7, 2004
L
'v'e
F
NORTHLAKE CITY LIMIT
5
Gee
114
�
1p
N/
N
f
5W ~
f
NORTHLAKF E.T.J.
CITY OF
FORT WORTH
H
o SITE Y /
3 LOCATION Izo
Cemetery
0
� o
O r
u
L�
�O 02
O
x ti�
u�
r I
Glee*
LITSEY ROAD e�
VDC=Y MAP
NTS
0
0
N
M C=TADWHC1T1'7\\.. FARMS
N
9
N
SECTHON DD
c
0 p �/-v
11 OCATED E
Y
3
C HTY (OF DORY WORTH9 =XAS
0
L
U
NOWNEDIDEVELA)PED BY:
o PREPARED BY:
GOODVRNI
0 MAI SHA.]L 9
N
Kimball Hill Homes CML ENGINEERS-PLANNERS-SURVEYORS
0
OW1& es IdStreet,Sults 100,Fort Worth Texas 78172
d Dallas Division Meft(817)429-4373
M
1422 W. Main Street, #1206
M Lewisville, Texas �H9
a' Phone (972 ) 353-434-434 5MAR2004
m
Fox; (214 ) 222-4466
w
0 o p
N tO w O
N
O
w ss
W W i
S99zn
N 44
2 n o Ja 4J o
= N
Q u
p®af v
0
L
� u
o i
.N
C
O
It
i
a V
O
N
`r a C
H
O
w • a
PO
a PO
^ w
w * _
8
Q Y _ i &
&UV7 ffu} IsBfnS o
-- a
a
v
d ^ m d 8
U / C
8
• R
N/d r d •y �
0
U) (n
w w Q N M
z z a =
Q Q
F��] Q N'Ti N?i• •��
.�Y^r��A1•I ® Li(qQt QZ o}O
Z
cr3a m
CrQa
m0LL, D0
ml
Cr —aZ-
w
a$
a\w a\IL,
a
iiW+Sj CM�v ao3v m3va
NLOz M, z M, Za
opo wo wo}
(n 3. Dov �ov� :
. N
U
o Q_ N(D ohm a c
W a p w o w
W
0 O t `
O
O p
N �
N
.v O
W ~y
J W¢ e
2 U
o8e
3 a '
co
Uro
\X, o %
\r u\, �✓ t
Qc
a w w
d Z w
z
1 � �
i _ U U)
= o o o
a z
:w ww
wCL d
CL d
U
�N
0 o V
o O
H
N
I
a , g
ggN
LI1 `L an L7
a 2 O
N � g�
!m
,w. o 'Laod, N
cc 8�q z
(S U
O
L
V
N
\ O
V
N
O
O
_ o N
ry c
n o
g M
fl $ Ol
ry « ry ^ /
N y� W
� o
ry
rt
e
auv7 autd;cams a
m ry a
a
T--
4
-F-T--F-
^ ry • ^ ry 1
1�
a
'd
4 d
� ry
z
ID a ry
PY, � N ❑ ® V
w
U d
o ry
1-1 w
Y y� o ry, a .
z /
z
w � '
� ao
m V u O
W - V
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 3/8/2005
DATE: Tuesday, March 08, 2005
LOG NAME: 20CHADWICK I&II REFERENCE NO.: C-20563
SUBJECT:
Approval of Community Facilities Agreements with Kimball Hill Chadwick Farms, L.P., for the
Installation of Community Facilities to Serve Chadwick Farms, Sections I and II
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute one Community Facilities
Agreement (CFA) with Kimball Hill Chadwick Farms, L.P., for the installation of community facilities to serve
Chadwick Farms, Section I and a separate CFA with the same developer for the installation of community
facitilities to serve Chadwick Farms, Section Il.
DISCUSSION:
Kimball Hill Chadwick Farms, L.P., the developer of Chadwick Farms, Sections I and II, has executed two
proposed contracts for the installation, in two phases, of community facilities to serve a single family (783
lot) development located in north Fort Worth, bounded on the south by Litsey Road, (See Attachment).
The proposed Community Facility Agreements for Sections I and II reflect the Annexation Service
Agreement corresponding to Ordinance No. 14387, (attached), approved by City Council on November 14,
2000 (M&C PZ-2243). That service agreement specifies that the City will reimburse the developer for
pavement oversizing of the north/south thoroughfare from Litsey Road to S.H. 114 and for construction of
drainage facilities as required according to the "Installation Policy of Community Facilities" in effect in
November 2000.
The estimated costs of all community facilities for Chadwick Farms, Section I are as follows:
Infrastructure Category Developer Citi[ Total
Paving $1,203,120.33 $116,129.75 $1,319,250.08
Storm Drain $490,101.70 $0.00 $490,101.70
Street Lights $79,200.00 $0.00 $79,200.00
Street Name Signs $1,900.00 $0.00 $1,900.00
Inspection $67,385.74 $0.00 $67,385.74
Total $1,841,707.77 $116,129.75 $1,957,837.52
Execution of this CFA would entail the allocation of City funds in the amount of $116,129.75 from the 2004
Bond Program Standard CFA Obligation funds. This CFA includes $190,000 in developer funds for future
drainage and paving improvements to Litsey Road, which is in agreement with the requirements of the
Annexation ordinance.
Logname: 20CHADWICK III Paee I of 2
The estimated costs of all community facilities for Chadwick Farms, Section II are as follows:
Infrastructure Category Developer CRY Total
Paving $516,597.70 $107,973.00 $624,570.70
Storm Drain $115,095.20 $0.00 $115,095.20
Street Lights $33,500.00 $0.00 $33,500.00
Street Name Signs $300.00 $0.00 $300.00
Inspection $26,601.22 $0.00 $26,601.22
Total $692,094.12 $107,973.00 $800,067.12
Execution of this CFA would entail the allocation of City funds in the amount of$107,973.00 from the 2004
Bond Program Standard CFA Obligation funds.
This development is located in COUNCIL DISTRICT 2.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budget, as appropriated, of the
Street Improvement Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
C202 541200 20 2 76 00208 83 $224,102.75
Submitted for City Manager's Office bv: Marc Ott (6191)
Originating Department Head: Robert Goode (7804)
Additional Information Contact: Katherine Mehl (7918)
Logname: 20CHADWICK III Page 2 of 2