HomeMy WebLinkAboutContract 33387 COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary
COUNTY OF TARRANT § Contract No.33::�3
ypWHEREAS, C� , hereinafter called "Developer", desires to
make certain improvements to SENDERA RANCH EAST PHASE VI, SECTION 3, an
addition to the City of Fort Worth, Texas; and
WHEREAS, the said Developer has requested the City of Fort Worth, a municipal
corporation of Tarrant, Denton and Wise Counties, Texas, hereinafter called "City", to do
certain work in connection with said improvements.
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
For and in consideration of the covenants and conditions contained herein, the City and
the Developer do hereby agree as follows:
1. General Requirements
A. The Policy for the Installation of Community Facilities ("Policy")
dated March 2001, approved by the City Council of the City of Fort
Worth and subsequently amended, is hereby incorporated into this
Community Facilities Agreement as if copied herein verbatim.
Developer agrees to comply with all provisions of said Policy in the
performance of its duties and obligations hereunder.
B. The requirements of the Policy shall govern this Community Facilities
Agreement, provided, however, that any conflict between the terms of
this Community Facilities Agreement and the Policy shall be resolved
in favor of this Agreement.
C. Developer shall provide financial security in conformance with
paragraph 6, Section II, of the Policy.
D. Developer acknowledges that there shall be no reduction in the amount
of financial security prior to project completion and acceptance by the
City.
E. The Developer shall award all contracts for the construction of
community facilities in accordance with Section II, paragraph 7 of the
Policy.
03-30-Ob A;`3 : 09 I N
l ��
F. The contracts for the construction of the public infrastructure shall be
administered in conformance with paragraph 8, Section II, of the
Policy.
G. The Developer further covenants and agrees to, and by these presents
does hereby, fully indemnify, hold harmless and defend the City, its
officers, agents and employees from all suits, actions or claims of any
character, whether real or asserted, brought for or on account of any
injuries or damages sustained by any persons (including death) or to
any property, resulting from or in connection with the construction,
design, performance or completion of any work to be performed by
said Developer, his contractors, subcontractors, officers, agents or
employees, or in consequence of any failure to properly safeguard the
work, or on account of any act, intentional or otherwise, neglect or
misconduct of said DEVELOPER, his contractors, sub-contractors,
officers, agents or employees, whether or not such injuries, death or
damages are caused, in whole or in part, by the alleged negligence of
the City of Fort Worth, its officers, semants, or employees.
H. Developer shall install or adjust all of the required utilities to serve the
development or to construct the improvements required herein.
I. In the event that City participation exceeds 525,000, Developer agrees
that no street construction or storm drainage will begin prior to City
Council approval of this Community Facilities Agreement. (Article
104.100, Ordinance 7234).
J. Developer agrees that no lot shall be occupied under a certificate of
occupancy until the improvements required herein have been
constructed (Article 104.100, Ordinance 7234).
K. Developer hereby releases and agrees to indemnify and hold the City
harmless for any inadequacies in the preliminary plans, specifications
and cost estimates supplied by the Developer for this contract.
L. Developer agrees to provide, at its expense, all necessary rights of way
and easements across property owned by Developer required to
2
construct current and future improvements provided for in this
agreement.
M. Developer agrees to construct proposed improvements as shown on the
exhibits attached hereto. The following exhibits are made a part
hereof: Water (A)None; Sewer (A-1) None; Paving (B)Attached
Storm Drain (B-1) Attached; Street Lights and Signs (C) Attached.
N. City shall not be responsible for any costs that may be incurred by
Developer in the relocation of any utilities that are or may be in
conflict with any of the community facilities to be installed hereunder.
II. Street and Storm Drain Facilities
A. The Developer(s) agree to install or to cause to have installed, the street,
storm drainage, street lighting, street name sign and other community
facilities improvements shown as "current improvements" on the attached
Exhibits B, B 1, and C.
B. As shown below in the "Summary of Cost for Street and Storm Drain
Facilities", the Developer shall fund its share of "current improvements"
and shall pay to the City for its share of the cost of street, storm drainage,
street lighting, street name signs as shown on the attached Exhibits B, B 1,
and C. The estimated total cost of current improvements and related
support services specified in this agreement, including design,
construction and inspection is estimated to $711,247.16.
3
SUMMARY OF
COST
Sendera Ranch East Phase VI Section 3
Item Developer City Cost Total Cost
Cost
A. Construction $ -
1. Streets $455,776.28 455,776.28
2. Storm Drainage $174,348.40 174,348.40
3. Street Lights $41,600.00 41,600.00
4. Street Name Signs $1,715.00 1,715.00
B. Engineering Design $
C. Construction Engineering
and Management by DOE $ $
4% 25,204.99 25,204.99
D. Materials Testing by DOE $ $
2% 12,602.49 1 12,602.49
TOTALS 711,247.16 $ - 711,247.16
Notes:
1. All Preliminary Plats filed after July 2000 will require sidewalks on all streets.
2. Developer's column for Item C represents four percent (4%) cost for construction
inspection fees. The City will pay additional inspection fee over 4%.
3. City not preparing plans and specifications.
4. Developer's column for Item D represents two percent (2%) of paving and storm drain
costs for materials testing.
4 �
IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be
executed in triplicate in its name and on its behalf by its Assistant City Manager, attested by
its City Secretary, with the corporate seal of the City affixed, and said Dev loper has
executed this instrument in triplicate, at Fort Worth, Texas this the6lday of
12006.
Approval Recommended:
Transportation and Public Wor
Department
Robert Goode, P. E.
Director
IVO M&C It`:(�UIlIZED Cit of Fo W rth
Marc Ott
Assistant City Manager
ATTEST:
Marty Hendrix R E C E I V E D
City Secretary
Approve to Form:
Assistant ity ttorney
DEVELOPER
Two SR, L.P.
A Texas Limited Partnership
By: Centamtar Terras, L.L.C.
A Texas Limited Liability Company
AT EST:
J,i Ail 1kL&4sA1
Corporate Secretary Mehrdad Moayedi, Manager
S V J 7
c� 6
.8 1'�.
ESS :::::.:.::.�::;:::;::.::.�::::::.:::::::::::::::.:,.�.::::::.a:::::..::::.::.::::.
>`<> :
.......:;:
.PHE?NE .'�85:84 ...�rr �Il�trc�:.
SENDERA RANCH
PHASE VI, SECTION 3
19 DECEMBER 2005
PAVING
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 6"LIME STABALIZED SUBGRADE 18,312 S.Y. 1.65 $30,214.80
2 6" R.C. STREET PVMT W/7"CURB 17,738 S.Y. 21.96 $389,526.48
3 HYDRATED LIME 30#/SY 275 TON 85.00 $23,375.00
4 4'SIDEWALK 3,200 S.F. 3.80 $12,160.00
5 STORM WATER MANAGEMENT 1 L.S. 1 500.00 $500.00
TOTAL-PAVING $455,776.28
PAVING - BONDS
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 PAYMENT, PERFORMANCE & MAINT. BOND 1 L.S. 6,950.00 $6,950.00
TOTAL-PAVING BONDS $6,950.00
STREET LIGHTS & SIGNS
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 STREET LIGHTS SINGLE ARM ONLY 16 EA. $2,000.00 $32,000.00
2 STREET LIGHTS CONTINGENCY 10% 1 EA. $3,200.00 $3,200.00
3 STREET SIGNS 7 EA. $100.00 $700.00
OTAL STREET LIGHTSISIGNS $35,90LOOJI
G:UOB\0137271EST\Bonds20050711 �,
:::iii::;j':;:-:•:':':>i;i:::''':::::::vii;:i'::::::::::::::::::::::i::::::�i':�:::::�'::::i':::is':::::i::::::ii':i: :::::::�':-':::::.ii':::::�::'�.''"v i::j{:'::::::::::::::i:yy::::ii�:�::':::':i�:::.':;::::�{:::j�:•.>':}ii�:':::?ii:�:i::::::::•:::::i i�;::::?��:.:i?ii::::;:':'i:;;:'�::::i:i::i::i::i::::::i:i:':�:::::::j::::}:::::i:::
?ilii::.•:iiiiiY." :i:itii:::::i:::::i:i::titi::i::,::::iiiif:iii:
. E
tT
RM
SENDERA RANCH
PHASE VI, SECTION 3
19 DECEMBER 2005
STORM DRAIN SYSTEM
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 6'x4'BOX 137 L.F. 217.45 $29,790.65
2 48'RCP 149 L.F. 110.50 $16,464.50
3 33"RCP 537 L.F. 63.00 $33,831.00
4 30"RCP 406 L.F. 54.60 $22,167.60
5 24" RCP 364 L.F. 42.60 $15,506.40
6 21"RCP 110 L.F. 38.00 $4,180.00
7 TRENCH SAFETY STORM DRAIN 1,703 L.F. 0.75 $1,277.25
8 33"RCP SLOPING HEADWALL 1 EA. 2,100.00 $2,100.00
9 30"RCP SLOPING HEADWALL 1 EA. 1,575.00 $1,575.00
10 24"RCP SLOPING HEADWALL 1 EA. 1,250.00 $1,250.00
11 STD 15' CURB INLET 4 EA. 3,040.00 $12,160.00
12 STD 10' CURB INLET 81 EA. 2,525.00 $20,200.00
13 5' SQUARE MANHOLE 1 EA. 4,049.00 $4,049.00
14 ROCK RUBBLE RIP RAP 12"-18" 170 S.Y. 54.70 $9,299.00
15 STORM WATER MANAGEMENT 1 L.S. 498.00 $498.00
TOTAL-STORM DRAINAGE SYSTEM $174,348.40
WATER - BONDS
ITEM# DESCRIPTION QTY UNIT PRICE AMOUNT
1 PAYMENT, PERFORMANCE & MAINT. BOND 1 L.S. 10,565.00 $10,565.00
TOTAL-WATER-BONDS $10,565.00
G:\JOB\013727\EST\Bonds20050711 CITY,
+ - t
RECEIVED
PART B - PROPOSAL
This proposal must not be removed from this book of Contract Documents.
TO: Two SR, L.P.
c/o CARTER&BURGESS
PROPOSAL FOR: STREET IMPROVEMENTS FOR
SENDERA RANCH EAST, PHASE VI, SECTION 3
D.O.E.NO. 4815
FILE NO. W-1637
Includes the furnishing of all materials, except materials specified to be furnished by the City,
equipment and labor for the installation of water and sanitary sewer facilities and all necessary
appurtenances and incidental work to provide a complete and serviceable project designated as:
Sendera Ranch East Phase VI, Section 3
(project name)
Pursuant to the foregoing Notice to Bidders', the undersigned Bidder, having thoroughly
examined the Contract Documents, including plans, special contract documents, and the General
Contract Documents and General Specifications for Water Department Projects, the site of the
project and understanding the amount of work to be done, and the prevailing conditions, hereby
proposes to do all the work, furnish all labor, equipment and material except as specified to be
furnished by the City, which is necessary to fully complete the work as provided in the Plans and
Contract Documents and subject to the inspection and approval of the Director of the City
Engineering Department of the City of Fort Worth, Texas; and binds himself upon acceptance of
this Proposal to execute a contract and fumish an approved Performance Bond, Payment Bond,
Maintenance Bond, and such other bonds, if any, as may be required by the Contract Documents
for the performing and completing of the said work. Contractor proposes to do the work within
the time stated and for the following sums:
N:U0B\013727\Spec\013727,010B.doc B- 1
UNIT I: PAVING IMPROVEMENTS
ITEM APPROX. DESCRIPTION ITEMS WITH UNIT TOTAL
NO. QUANTITY OF BID PRICES WRITTEN IN WORDS PRICE AMOUNT
(Furnish and install, including all appurtenant work, complete in place, the following items)
(D-No. refers to related items in the Part D Special Conditions:)
Item Approx Unit Item Description Unit Price Total
No. Quantity Measure "D" Item reference Amount
ment
1. 18,312 S.Y. 6" Lime Stabilized Subgrade:
Per Square Foot:
One Dollars &
Sixty Five Cents $1.65 $30,214.80
2. 17,738 S.Y. 6" RC Street Pavement with 7"curb,
Per Square Foot:
Twenty One Dollars &
Ninety Six Cents $21.96 $389,526.48
3. 275 TON Lime for subgrade (30#/S.Y.)
Per Square Foot:
Eighty Five Dollars &
No Cents $85.00 $23,375.00
4. 3,200 S.F. 4' Sidewalk,
Per Square Foot:
Three Dollars &
Eighty Cents $3.80 $12,160.00
5. 1 L.S. Storm Water Management
Per Square Foot:
Five Hundred Dollars &
No Cents $500.00 $500.00
N:JOB\013727\Spec\O 13727.01OB.doc B-2
6. 1 L.S. Payment, Performance & Maintenance
Bonds
Per Lump Sum:
Six Thousand Nine Hundred
Fifty Dollars &
No Cents $6,950.00 $6,950.00
GRAND TOTAL STREET IMPROVEMENTS $ 462,726.28
N:VOB\013727\Spec\013727.010B.doc B-3 `�,
PART B -PROPOSAL (Cont.)
Within ten (10) days after acceptance of this Proposal, the undersigned will execute the formal
contract and will deliver an approved Surety Bond and such other bonds as required by the
Contract Documents, for the faithful performance of the Contract. The attached bid security in
the amount of 5%is to become the property of the City of Fort Worth, Texas, in the event the
contract and bond or bonds are not executed and delivered within the time above set forth, as
liquidated damages for the delay and additional work caused thereby.
The undersigned bidder certified that he has been furnished at least one set of the General
Contract Documents and General Specifications for Water Department Projects dated January 1,
1978, and that he has read and thoroughly understands all the requirements and conditions of
those General Documents and the specific Contract Documents and appurtenant plans.
The successful bidder shall be required to perform the work in accord with the following
publications, both of which are incorporated herein and made a part hereof for all
purposes:
1. The General Contract Documents and General Specifications for Water
Department Projects dated January 1, 1978,which may be purchased from the
Water Department.
2. The Standard Specifications for Street and Storm Drain Construction which
may be purchased from the Department of Transportation & Public Works.
The undersigned assures that its employees and applicants for employment and those of any
labor organization, subcontractors, or employment agency in either furnishing or referring
employee applicants to the undersigned are not discriminated against as prohibited by the terms
of City Ordinance No. 7278 as amended by City Ordinance No. 7400.
The Bidder agrees to begin construction within Ten 10 calendar days after issue of the work
order, and to complete the contract within Thi 30 working days after beginning construction
as set forth in the written work order to be furnished by the Owner.
(Complete A or B below, as applicable:)
A. The principal place of business of our company is in the State of
Nonresident bidders in the State of , our principal
place of business, are required to be percent lower than resident bidders
by state law. A copy of the statute is attached.
Non resident bidders in the State of , our principal
place of business, are not required to underbid resident bidders.
B. The principal place of business of our company or our parent company or
majority owner is in the State of Texas.
1vf:UOB\013727\Spec\O13727.010B.doc B-4
RECEIVED
I (we) acknowledge receipt of the following addenda to the plans and specifications, all of the
provisions and requirements of which have been taken into consideration on preparation of the
foregoing bid:
Addendum No. 1 (Initials) Addendum No. 3 (Initials)
Addendum No. 2 (Initials) Addendum No. 4 (Initials)
Respectfully submitted,
Mario Sida`c'o'l& Sons Excavatiniz, Inc.
hael cola
Tit
Vice President
Address
10950 Research Road
��sco, TX 75034
Telephone: 214-387-3900
(Seal)
Date: January 5, 2006
NAJOB\013727\Spec\013727.O1OB.doc B-5
01�`
2�
UNIT III: STORM DRAIN
(Furnish and install, including all appurtenant work, complete in place, the following items)
Item Approx Unit Item Description Unit Price Total
No. Quantity Measurement "D" Item reference Amount
1. 137 L.F. 6' X 4' Box,
Per Linear Foot:
Two Hundred Seventeen Dollars &
Forty Five Cents
$ 217.45 $29,790.65
2. 149 L.F. 48" Class III R.C. Pipe, Including
Trench Excavation and Backfill,
Per Linear Foot:
One Hundred Ten Dollars &
Fifty Cents $110.50 $16,464.50
3. 537 L.F. 33" Class III R.C. Pipe, Including
Trench Excavation and Backfill,
Per Linear Foot:
Sixty Three Dollars &
No Cents $63.00 $33,831.00
4. 406 L.F. 30" Class III R.C. Pipe, Including
Trench Excavation and Backfill,
Per Linear Foot:
Fifty Four Dollars &
Sixty Cents $54.60 $22,167.60
5. 364 L.F. 24" Class III R.C. Pipe, Including
Trench Excavation and Backfill,
Per Linear Foot:
Forty Two Dollars &
Sixty Cents $42.60 $15,506.40
N:UOB\013727\Spec\013727.01 OA.doc B-8
Item Approx Unit Item Description Unit Price Total
No. Quantity Measurement "D" Item reference Amount
6. 110 L.F. 21" Class III R.C. Pipe, Including
Trench Excavation and Backfill,
Per Linear Foot:
Thirty Eight Dollars &
No Cents $38.00 $4,180.00
7. 1 Ea. 33" Sloping Headwall,
Per Each:
Two Thousand
One Hundred Dollars &
No Cents $2,100.00 $2,100.00
8. 1 Ea. 30" Sloping Headwall,
Per Each:
One Thousand Five Hundred
Seventy Five Dollars &
No Cents $1,575.00 $1,575.00
9. 1 Ea. 24" Sloping Headwall,
Per Each:
One Thousand Two Hundred
Fifty Dollars &
No Cents $1,250.00 $1,250.00
10. 1,703 L.F. Trench Safety, (Storm Drain)
Per Linear Foot:
No Dollars &
Seventy Five Cents $0.75 $1,277.25
N:JOB\013727\Spec\013727.010A.doc B-9
11. 4 Ea. STD 15' Standard Curb Inlet,
Per Each:
Three Thousand
Forty Dollars &
No Cents $3,040.00 $12,160.00
12. 8 Ea. STD 10' Standard Curb Inlet,
Per Each:
Two Thousand Five Hundred
Twenty Five Dollars &
No Cents
$2,525.00 $20,200.00
13. 1 Ea. 5' Square Manhole,
Per Each:
Four Thousand
Forty Nine Dollars $
No Cents $4,049.00 $4,049.00
14. 170 S.Y. Rock Rubble Rip Rap ( 12" X 18"
Dia.),
Per Square Yard:
Fifty Four Dollars &
Seventy Cents $54.70 $9,299.00
15. 1 L.S. Storm Water Management,
Per Lump Sum:
Four Hundred Ninety Eight Dollars &
No Cents $498.00 $498.00
TOTAL AMOUNT BID STORM DRAIN $ 174,348.40
L'
N:\JOB\013727\Spec\013727.010A.doc BA O U
I. STREET LIGHT COST ESTIMATE
QUANTITY UNIT COST TOTAL COST
INTERSECTIONS 4 EA $ 2, 600 $10, 400. 00
MID-BLOCK RESIDENTIAL 5 EA $ 2, 600 $13, 000 . 00
CHANGE OF DIRECTION RESIDENTIAL 7 EA $ 2, 600 $18, 200 . 00
MID-BLOCK COLLECTOR 0 EA $ 2, 600 $00, 000 . 00
MID-BLOCK ARTERIAL 0 EA $ 3, 000 $00, 000 . 00
MID-BLOCK ARTERIAL MEDIAN 0 EA $ 3, 000 $00, 000 . 00
RELOCATE EXISTING LIGHT 0 EA $ 1, 650 $00, 000 . 00
Subtotal $41, 600 . 00
City' s Cost $00, 000 . 00
Developer' s Subtotal $41, 600 . 00
4% Inspection fee $00,000 .00
Project Total $41, 600 . 00
Adjacent Developer' s Cost $00 . 000 . 00
Developer' s Cost $41,600 .00
CFA CODE #2006011
DEVELOPERS COST: $41,600.00
SENDERA RANCH, PHASE VI-III
February 20, 2006
Fort Worth, Texas February 20, 2006
PAGE I OF EXHIBIT "C"
II STREET LIGHTS WORK DESCRIPTION:
1. The Developer shall provide for the installation of street lights at the
approximate locations shown in exhibit "C", immediately after final
acceptance of the street construction, in accordance with engineering plans
and specifications approved by the Transportation and Public Works
Department.
2. Streetlights on residential and/or collector streets can be installed using
overhead or underground conductors with the approval of the director of
transportation and Public Works.
3. The City of Fort Worth will install all the street lights that use overhead
or underground conductors on residential, and collector streets. The
developer agrees to pay the City of Fort Worth the amount shown below prior
to the City starting its design efforts, at the option of the developer and
at their expense they may purchase the poles, fixtures, and mast arms from
the City in order to assure compliance with city material standards
4 . Street lights on arterial streets shall be installed with underground
conductors
5. The developer agrees to dedicate all easements required for the
installation and maintenance of the street lights and to provide for the
installation of any electrical transformers required for the proper
operations of the street light system
6. The estimated cost of this street light installation is detailed on page
(1) of exhibit "C" and is summarized below. The street lights will remain
the property of, and will be maintained by the City of Fort Worth
February 20, 2006
DEVELOPERS COST: $41, 600.00
SENDERA RANCH, PHASE V-I
CFA CODE #2006011
PAGE II OF EXHIBIT "C"
III
"STREET LIGHTS"
INTERSECTIONS
RIO BRAVO DR & ZAVALA TRL 1
SANTA ROSA DR & SAN MIGUEL TRL 1
SANTA ROSA DR & BAY MARE WAY 1
ZAVALA TRL & PONCHO IN 1
MID - BLOCK
SANTA ROSA DR 1
SAN MIGUEL TRL 1
RIO BRAVO DR 2
SAN CHRISTOVAL PASS 1
CHANGE OF DIRECTIONS
SAN CHRISTOVAL PASS 3
SAN MIGUEL TRL 1
SANTA ROSA DR 1
BAY MARE WAY 1
ZAVALA TRL 1
SENDERA RANCH, PHASE VI-III
PAGE III OF EXHIBIT "C"
IV
STREET NAME SIGNS
1. The City of Fort Worth will install the street name signs upon final
approval of the street construction. The street name signs will remain
the property of, and will be maintained by, the City of Fort Worth.
2. The Developer will pay for the street name sign installations required
for this development to the extent of$245.00 per intersection. This
unit cost will be revised annually by the Department of Transportation
and Public Works to reflect prevailing costs of materials and labor.
3. This development creates the following seven (7) intersections at a
cost to the Developer of$1,715.00:
Santa Rosa Dr & San Miguel Tr
Santa Rosa Dr & Bay Mare Way
Santa Rosa Dr & Zavala Tr
Rio Bravo Dr & Zavala Tr
Pancho Lane & Zavala Tr
San Christoval Pass & Diamondback Lane
San Christoval Pass & Rosario Lane
Sendera Ranch, Phase VI, Section 3
CFA code: 2006011 August 27, 2005
N
o w
R CcIV D 16 oCL
Z r
N
V1 �
W
O
L s
d = z
L y�
U
w ZU�A w
V 5
"om a
I w
J
V
z �
0
Z
Tbd' , MSEHI a
Y Ng MSFHI
l W43
cn
oyd � y
AVO
'ob N 3Sf10
3Nf1 A1Nf10° SYH /�
95i Yid
6 �
® 0 D Z
o JS
IX67 � 0li O
a
3NI I AlN J 31VWWIX0&,JJ l O w �
g1Za
°" ► szvs e
Ix a4 a u
a Q ci e
a
W�
p 9 I
� u ,
c
O
v
0
_u
h
N
r
U
N
O
O
P
in
OC, V
o
5° d
LLJ
Lu
= o
uj
J� J W W
O O �O 3� O a
C13 m1= WJ WW m
O— D a. a. 7►
In m N Co N J LL
W W0
N>- Ln>- Q7- Q>
Q Q O W N '
� � = O h-
a.0 0-0 a. a-
0<
.OQ OQ Occ O(n /
a: a'
O O mfD =fD —
m a.1= a._, a._. J o
h
x �
A �
_ � �v'•-� � V, 1,
a � g
f
M 1
V }
h � I
e c
N F
N
r
S
O
O
� N
r'] r
n
11 0
o
O
W
a a
v �
G L
p
on t
40
rn xz
n V ,.4 d
m �cn " CY
z N
LZ F—
LU LU "' n
W ^�
a W m Q s
H = w m Z
W A
^Om�
c/]
0
h � •,
h ,
W 1
P
I
I
0 I
Z
LAJ
C)
LTJ
J� JW
O m� �O r.:= O
WJ WW ct
O— Oa. CL
m0 mco —:3 —O
In to 000 N J L+-
Oi� W I W O
N� Q Qm Q>
=
.� m . .O F
IL D _
oa app or or 2
y 0
p r u 0
] a
cl:
` �J��'J U ✓ W I N
161
moe
rz o z
= W > 'F' '°R_�
X 16 c z-�u
�♦ O W W a �i;�a
\� I ♦ � — W iC�/� V C7 2 m a
` / a
��� I \ � Y ✓ PMo
IIS\
hS
W �
r)
W a
LU
z
w J w=a
a •
w z Z ~ u
J - Q U
O 3 0
W S O O ti
O J z Q W
� o
OO O O `� o
cr cr � � x -
0-
a- 0-
W J O
Z
M
0
O by z o m
W 0� W
z � m
` W16Z N
W 0 DO ,� n
F c
CJ m g I
16
u
O WDO w W ~ ^o
ro a
J
N
S
400f
d
I
I\
n 1
n
W z W Z Z a
v
,W d
v Z U
w Z — H
J a a v
� J p 7 f
W J
O
�- O 3 a ti
W 2 O O N
O _I Z a lA- n
�- Z a w N O
N
a a a a N �-
0 0 0, o
� m x —
d d a a W J
0
0
cn N o
xz � o0
T U L v o a
1 , Z
N
r
W GO ti n
J J ii W
u m 1 i
m 2 Z
= w5 deo
A' i u
ui X Gq� W
w l^ Va--d
op
dop
0'.
le
J#
J* x�Y' 1.
� w
A
` 0'l ice ► �J ,\
�_ _ - _ ®• err � � � ' ���
w
1
sw
r
• O
1
N
� S W 1
C7CLrLl's
I
~ LLI W V
M W WHH Z ^
Z W S—H Z 0 E N
w cr H3Q 0 — U r
(n — N W
C7 N WN N
w W LLIJZ H' O
JOU H W a
J (7a— W W a. P.
Z N W cr n
Z —J S H LL-
-
n
N V1Wa H N O
W O to c
F-H V]
a HNVI
N a N
a XOZ S X �
i
WRQ a W J
Z '
M H n o
xz
U O
Z (J f^ a
LZ V W W N
N
N
J J F— GO
0
U m ` 9
LL J
do d
m =
o
ac w W O
N wee
a
40
.'4
/ W
1 I
/• 11 1 I
1 1�
1
1
1
1
1
• O � d '
1
1
�- z w 1
2 Ows 1 c
(7 —a'0 O
J NS 0
F- U
F W 2 Q
D w WF-f-- z N
Z cr—�- z o F- I`
W N — Ln W ;
N WN N
W J Z 1 O
W W J O 0 f- w (r-
J UCL- w w a N
J U z N W m
Z —J 2 F- LL-
(A
L/1 W a N O o
to W O (A
a N N t!1 a V�
C) O
cr XOz cr X x
CL W—< CL W J .
0