HomeMy WebLinkAboutContract 48969 CITY SECRETARY
CONTRACT NO. 011-1-
Developer and Project Information Cover Sheet:
.......... ...............
I Developer Company Name: Hillwood Alliance Services,LLC
Address, State,Zip Code: 9800 Hillwood Pkwy Suite 300,Fort Worth TX 76177
Phone&, Email: 817-224-6000, Joe.Schneider@hillwood.com
Authorized Signatory,Title- L.Russell Laughlin, Senior Vice President-Properties Division
Project Name: Alliance Town Center North Founders Way&Hillwood Parkway
Brief Description:
Paving& Storm Drain
Project Location: I In Between Golden Triangle Blvd. and Heritage Trace Parkway Just
East of 1-3 5 W
Plat Case Number: <Plat Case Plat Name: <Plat Name>
Mapsco: 21Y Council District: i 7 City Project Number: 100832
CFA Number: 2017-038 DOE Number: <DOE#>
To be completed by staff
Received by:4 Date:
APR 12 2017
TX
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 1 of 11
STANDARD COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary
COUNTY OF TARRANT § Contract No.
WHEREAS, Hillwood Alliances Services LLC A ("Developer"), desires to make certain
specific improvements as described below and on the exhibits attached hereto ("Improvements")
related to a project generally described as Alliance Town Center North - Founders WU &
Hillwood Parkway Paving & Storm Drain ("Project") within the City or the extraterritorial
jurisdiction of Fort Worth, Texas ("City"); and
WHEREAS, the City has no obligation to participate in the cost of the Improvements or
Project; and
WHEREAS, any future City participation in this CFA is subject to the availability of
City funds and approval by the Fort Worth City Council and shall be memorialized as an
amendment to this Agreement; and
WHEREAS, the Developer and the City desire to enter into this Community Facilities
Agreement ("CFA" or "Agreement") in connection with the collective Improvements for the
Project.
NOW, THEREFORE, for and in consideration of the covenants and conditions
contained herein, the City and the Developer do hereby agree as follows:
General Requirements
A. The Policy for the Installation of Community Facilities ("Policy") dated March 2001,
approved by the City Council of the City of Fort Worth, as amended, is hereby
incorporated into this Agreement as if copied herein verbatim. Developer agrees to comply
with all provisions of said Policy in the performance of its duties and obligations hereunder
and to cause all contractors hired by Developer to comply with the Policy in connection
with the work performed by said contractors.
B. Developer shall provide financial security in conformance with paragraph 6, Section II, of
the Policy and recognizes that there shall be no reduction in the collateral until the Project
has been completed and the City has officially accepted the Improvements. Developer
City of Fort Worth, Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 2 of 11
further acknowledges that said acceptance process requires the Developer's contractor(s)
to submit a signed affidavit of bills paid and consent of Surety signed by its surety to
ensure the contractor has paid any sub-contractor(s) and suppliers in full. Additionally,
the contractor will provide in writing that the contractor has been paid in full by
Developer for all the services provided under this contract.
C. Developer agrees to cause the construction of the Improvements contemplated by this
Agreement and that said construction shall be completed in a good and workmanlike
manner and in accordance with all City standards and the City-approved construction
plans, specifications and cost estimates provided for the Project and the exhibits attached
hereto.
D. The following checked exhibits describe the Improvements and are incorporated herein:
Water (A) ❑,, Sewer (A-1) El, Paving (B) 0, Storm Drain (B-1) M, Street Lights &
Signs (C) I4.
E. The Developer shall award all contracts for the construction of the Improvements in
accordance with Section II, paragraph 7 of the Policy and the contracts shall be
administered in conformance with paragraph 8, Section II, of the Policy. Developer shall
ensure its contractor(s)pays the then-current City-established wage rates.
F. For all Improvements included in this Agreement for which the Developer awards
construction contract(s), Developer agrees to the following:
i. To employ a construction contractor who is approved by the director of the
department having jurisdiction over the infrastructure to be constructed, said
contractor to meet City's requirements for being prequalified, insured, licensed
and bonded to do work in public ways and/or prequalified to perform
water/wastewater construction as the case may be.
ii. To require its contractor to fin-nish to the City a payment and performance bond in
the names of the City and the Developer for one hundred percent (100%) of the
contract price of the infrastructure, and a maintenance bond in the name of the
City for one hundred percent (100%) of the contract price of the infrastructure for
a period of two (2) years from the date of final acceptance insuring the
maintenance and repair of the constructed infrastructure during the term of the
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 3 of 11
maintenance bond. All bonds to be furnished before work is commenced and to
meet the requirements of Chapter 2253, Texas Government Code.
iii. To require the contractor(s) it hires to perform the construction work
contemplated herein to provide insurance equal to or in excess of the amounts
required by the City's standard specifications and contract documents for
developer-awarded infrastructure construction contracts. The City shall be
named as additional insured on all insurance required by said documents and
same will be evidenced on the Certificate of Insurance (ACORD or other state-
approved form) supplied by the contractor's insurance provider and bound in the
construction contract book.
iv. To require its contractor to give 48 hours advance notice of intent to commence
construction to the City's Construction Services Division so that City inspection
personnel will be available; to require the contractor to allow the construction to
be subject to inspection at any and all times by City inspection forces, to not
install or relocate any sanitary sewer, storm drain, or water pipe unless a
responsible City inspector is present and gives his consent to proceed, and to
make such laboratory tests of materials being used as may be required by the City.
V. To require its contractor to have fully executed contract documents submitted to
the City in order to schedule a Pre-Construction Meeting. The submittal should
occur no less than 10 working days prior to the desired date of the meeting. No
construction will commence without a City-issued Notice to Proceed to the
Developer's contractor.
vi. To delay connections of buildings to service lines of sewer and water mains
constructed under this Agreement, if any, until said sewer and water mains and
service lines have been completed to the satisfaction of the Water Department.
G. Developer shall provide at its expense, unless otherwise agreed to by City, all engineering
drawings and documents necessary to construct the improvements under this Agreement.
H. Developer shall cause the installation or adjustment of the required utilities to serve the
development or to construct the Improvements required herein.
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 4 of 11
I. City shall not be responsible for payment of any costs that may be incurred by Developer in
the relocation of any utilities that are or may be in conflict with any of the community
facilities to be installed hereunder.
J. Developer hereby releases and agrees to indemnify, defend and hold the City harmless
for any inadequacies in the preliminary plans, specifications and cost estimates
supplied by the Developer for this Agreement.
K. Developer agrees to provide, at its expense, all necessary rights of way and easements
across property owned by Developer and required for the construction of the current and
future improvements provided for by this Agreement.
L. The Developer further covenants and agrees to, and by these presents does hereby,
fully indemnify, hold harmless and defend the City, its officers, agents and employees
from all suits, actions or claims of any character, whether real or asserted, brought
for or on account of any injuries or damages sustained by any persons (including
death) or to any property, resulting from or in connection with the construction,
design, performance or completion of any work to be performed by said Developer,
its contractors, subcontractors, officers, agents or employees, or in consequence of
any failure to properly safeguard the work, or on account of any act, intentional or
otherwise, neglect or misconduct of said Developer, its contractors, sub-contractors,
officers, agents or employees, whether or not such injuries, death or damages are
caused, in whole or in part, by the alleged negligence of the City of Fort Worth, its
officers, servants, or employees.
M. Developer will further require its contractors to indemnify, defend and hold harmless
the City, its officers, agents and employees from and against any and all claims, suits or
causes of action of any nature whatsoever, whether real or asserted, brought for or on
account of any injuries or damages to persons or property, including death, resulting
from, or in any way connected with, the construction of the infrastructure
contemplated herein, whether or not such injuries, death or damages are caused, in
whole or in part, by the alleged negligence of the City of Fort Worth, its officers,
servants, or employees. Further, Developer will require its contractors to indemnify,
and hold harmless the City for any losses, damages, costs or expenses suffered by the
City or caused as a result of said contractor's failure to complete the work and
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 5 of 11
construct the improvements in a good and workmanlike manner, free from defects, in
conformance with the Policy, and in accordance with all plans and specifications.
N. Upon completion of all work associated with the construction of the Improvements,
Developer will assign to the City a non-exclusive right to enforce the contracts entered into
by the Developer with its contractor along with an assignment of all warranties given by the
contractor, whether express or implied. Further, Developer agrees that all contracts with
any contractor shall include provisions granting to the City the right to enforce such
contracts as an express intended third party beneficiary of such contracts.
O. Inspection and material testing fees are required as follows:
i. Developer shall pay in cash water and wastewater inspection fees and material
testing fees equal to two percent (2%) for a total of 4% of the developer's share of
the total construction cost as stated in the construction contract.
ii. Developer shall pay in cash paving and storm drain inspection fees equal to four
percent (4%) and material testing fees equal to two percent (2%) for a total of 6%
of the developer's share of the total construction cost as stated in the construction
contract.
iii. Developer shall pay in cash the total cost of streetlights or if the city is not
installing the streetlights, inspection fees equal to four percent (4%) of the
developer's share of the streetlight construction cost as stated in the construction
contract.
iv. Developer shall pay in cash the total cost of street signs.
P. COMPLETION WITHIN 2 YEARS
i. Developer shall complete the Improvements within two (2) years, provided,
however, if construction of the Improvements has started within the two year
period, the developer may request that the CFA be extended for one additional
year.
ii. Nothing contained herein is intended to limit the Developer's obligations
under the Policy, this Agreement, its financial guarantee, its agreement with
its contractor or other related agreements.
iii. The City may utilize the Developer's financial guarantee submitted for this
Agreement to cause the completion of the construction of the Improvements if at
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date:01.03.2017
Page 6 of 11
the end of two (2) years from the date of this Agreement (and any extension
period)the Improvements have not been completed and accepted.
iv. The City may utilize the Developer's financial guarantee to cause the completion
of the construction of the Improvements or to cause the payment of costs for
construction of same before the expiration of two (2) years if the Developer
breaches this Agreement, becomes insolvent or fails to pay costs of construction
and the financial guarantee is not a Completion Agreement. If the financial
guarantee is a Completion Agreement and the Developer's contractors and/or
suppliers are not paid for the costs of supplies and/or construction, the contractors
and/or suppliers may put a lien upon the property which is the subject of the
Completion Agreement.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 7 of 11
Cost Summary Sheet
Project Name: Alliance Town Center North Founders Way&Hillwood Pkwy Paving& Storm Drain
CFA No.: 2017-038 City Project No.: 100832
An Engineer's Estimate of Probable Cost is acceptable. However, the construction contract price
will ultimately determine the amount of CFA fees and financial guarantee. The bid price and
any additional CFA payments will be required prior to scheduling a pre-construction meeting.
An itemized estimate corresponding to each project-specific exhibit is required to support the
following information.
Items Developer's Cost
A. Water and Sewer Construction
1. Water Construction $ -
2.Sewer Construction $ -
Water and Sewer Construction Total $ -
B. TPW Construction
1.Street $ 2,036,735.75
2.Storm Drain $ 560,802.00
3.Street Lights Installed by Developer $ 293,220.00
4. Signals $ -
TPW Construction Cost Total $ 2,890,757.75
Total Construction Cost(excluding the fees): $ 2,890,757.75
Construction Fees:
C. Water/Sewer Inspection Fee(2%) $
D. Water/Sewer Material Testing Fee(2%) $
Sub-Total for Water Construction Fees $ -
E. TPW Inspection Fee(4%) $ 103,901.51
F. TPW Material Testing(2%) $ 51,950.76
G. Street Light Inspsection Cost $ 11,728.80
H. Signals Inspection Cost $ -
H. Street Signs Installation Cost $ -
Sub-Total for TPW Construction Fees $ 167,581.07
Total Construction Fees: $ 167,581.07
Choice
Financial Guarantee Options,choose one Amount Mark one
Bond= 100% $ 2,890,757.75
Completion Agreement= 100%/Holds Plat $ 2,890,757.75
Cash Escrow Water/Sanitary Sewer=125% $ -
Cash Escrow Paving/Storm Drain=125% $ 3,613,447.19
Letter of Credit=125%w/2yr expiration period $ 3,613 447.19 x
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 8 of 11
ACCORDINGLY,the City of Fort Worth and Developer have each caused this instrument to be
executed in quadruplicate in each entity's respective name by its duly authorized signatories effective as
of the date executed by the City's City Manager or his/her designee.
CITY OF FORT WORTH DEVELOPER
Hillwood Alliance Services,LLC
Jesus J. Chapa
Assistant City Manager
Date: U r /a — '� y Name: L.Russugifin
Title: Senior Vice President-Properties Division
Recommended by:
Date:
( � ATTEST: (Only if required by Developer)
Wendy Chi-Babulal, EMBA, P.E.
Development Engineering Manager
Water Department 406-"
`
LLNSignature a o I
'
ame: LW-1 bxA t
Dougl W. Wiersig,P.E.
Director Contract Compliance Manager:
Transportation&Public Works Department
By signing, I acknowledge that I am the
Approved as to Form &Legality: person responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
requirements.
Richard A. McCracken
Assistant City Attorney
M&C No. N)A- RA no + L1n
Date: 1011 /%-1 Name:
Form 1295: NIA, Title:
ATTEST: �0 0,,y
ATTEST:
' ' O
U ' '
XYlar J. s
City Sec �': ` 'IRY
�XAs feTX
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 9 of 11
Check items associated with the project being undertaken; checked items must be
included as Attachments to this Agreement
Included Attachment
Attachment 1 - Changes to Standard Community Facilities Agreement
Location Map
❑ Exhibit A: Water Improvements
❑' Water Cost Estimate
❑' Exhibit A-1: Sewer Improvements
❑'` Sewer Cost Estimate
Exhibit B: Paving Improvements
Paving Cost Estimate
Exhibit B-1: Storm Drain Improvements
Storm Drain Cost Estimate
Exhibit C: Street Lights and Signs Improvements
Street Lights and Signs Cost Estimate
(Remainder of Page Intentionally Left Blank)
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 10 of 11
ATTACHMENT"1"
Changes to Standard Agreement
Community Facilities Agreement
City Project No. 100832
None
City of Fort Worth,Texas
Standard Community Facilities Agreement-Alliance Town Center North Founders Way&Hillwood Parkway
CFA Official Release Date: 01.03.2017
Page 11 of 11
l
GOLDEN TRIANGLE BLVD
SITELUX
z �
WO U
HILLWOOD >w Q
m
PKWY =o
z
AMADOR0 HERIT E
DR z TRACE P W 377
(0 w
Z
WJ
287
LL
NORJA
OOD BLVD
-----------------------•--------------------••---•---------------------------------...- --------------------------- ............----
ALLIANCE TOWN OWNER/ DEVELOPER: ENGINEER:
411" r 1111
CENTER NORTH HILLWOOD ALLIANCE 1-1 LAND IPEL�OTON
OLUTIONS
NORTH FOUNDERS WAY & SERVICES, L.P.
NOT TO SCALE 9800 HILLWOOD PARKWAY,SUITE 300 RK HILLWOOD
,SUITE
HILLWOOD PARKWAY FORT WORTH,TEXAS 76177 PARKWAY,SUITE 76
PHONE: (817) 224-6000 FORT WORTH,TEXAS 76177
DATE:MARCH 2017 PHONE:817-562-3350
GOLDEN TRIANGLE BOULEVARD
/ PRIOADE�
55' B-B /85' ROW
l
t
Q
i ILIto
0
Z ,
o :
PRESTIGE ROAD
r m®
r
o
55' B-B /85' ROW
i
LEGEND
PROPOSED CONCRETE PAVEMENT
SIDEWALK BY DEVELOPER
H.C. RAMPS BY DEVELOPER
Q
EXHIBIT A - PAVING
..................... ---------------------- ----------------------------------- --------------------------------- -------------------
ALLIANCE TOWN OWNER/DEVELOPER: ENGINEER:
0 NORTH 500 CENTER NORTH HILLWOOD ALLIANCE LAND 11111
FOUNDERS WAY & SERVICES, L.P. 9800HILLWOOD
H I LLWOOD PARKWAY 9800 HILLFORTVWORTH,R TEXAS OOD 76U 7E 300 PARKWAY,SUITE 250
PHONE: (817) 224-6000 FORT WORTH,TEXAS 76177
GRAPHIC SCALE DATE:MARCH 2017 PHONE:817-562-3350
GOLDEN TRIANGLE BOULEVARD
EX 24" RCP ' EX 42" RCP
PRIVATE"
/ ROAD EX 42" RCP
/ 21" RCP 24" RCPN
I I -
/ -
/ -
1 W
0
Z�
O
LL
24" RCP
o
21" RCP 21" RCP
PRESTIGE ROAD
i 36" RCP m
21" RCP 36" RCP
I I o
o
I 21" RCP
I 48" RCP I
21" RCP 60" RCP
54" RCP 3� 6'X5' RCB
21" RCP I 8'X5' RCB
E
27" RCP
LEGEND
5'X4' RC
o PROPOSED STORM DRAIN INLET 48" RCP 24" RCP
---�-- EXIST STORM DRAIN INLET
—i— PROPOSED STORM DRAIN MANHOLE 42" RCP !�'fQ 21" RCP
—�
EX 24 PROPOSED STORM DRAIN HEADWALL
21" RCP RCP
6 o0
EXHIBIT A1 — STORM DRAINAGE 0
..------------------------------------ . -- ........... ........................ .........
ALLIANCE TOWN OWNER/ DEVELOPER: ENGINEER:
^PELOTON
0 NORTH 500, CENTER NORTH HILLWOOD ALLIANCE blit LAND SOLUTION!
FOUNDERS WAY & SERVICES, L.P. 9800 HILLWOOD
HILLWOOD PARKWAY 9800 HILLFORTWORTH,OOD R TEXAS PARKWAY, 300 PARKWAY,SUITE 250
PHONE: (817) 224-6000 FORT WORTH,TEXAS 76177
GRAPHIC SCALE DATE:MARCH 2017 PHONE:817-562-3350
GOLDEN TRIANGLE BOULEVARD
e :
PRIVATE"'
D / ROAD
r
/ r
r
r
t
i a
W �
0
j PRESTIGE ROAD
I
LEGEND
0
PROPOSED STREET LIGHTS
O EXIST STREET LIGHTS `
a'
0
O
EXHIBIT B - STREET LIGHTS _'
J
..._..... ................................................................................................................................�
ALLIANCE TOWN OWNER/ DEVELOPER: ENGINEER:
?
NORTH 500' CENTER NORTH HILLWOOD ALLIANCE j^ LAND &OLUTIONS
PELOTON
FOUNDERS WAY & SERVICES, L.P. 9800 HILLWOOD
H I LLWOOD PARKWAY 9800 FORT WORTH,T TEXOD AS 76177E SUITE 300 PARKWAY,SUITE 250
PHONE: (817) 224-6000 FORT WORTH,TEXAS 76177
GRAPHIC SCALE DATE:MARCH 2017 PHONE:817-562-3350
GOLDEN TRIANGLE BOULEVARD
� , c
PRIVATE��`-~
/ ROAD
/ 0 I �
I
I I
Q
w
W
al
ZI
PRESTIGE ROAD
o,.,.�.
LEGEND
0
O PROPOSED STREET NAME SIGNS0
a
0 EXIST STREET NAME SIGNS o
O
EXHIBIT B1 - STREET NAME SIGNS
___ ________________ _ _
------------------------------------- -------------ENGINEER: ----
°� ALLIANCE TOWN I
OWNER/ DEVELOPER: ,
0 NORTH 500 CENTER NORTH HILLWOOD ALLIANCE ^ LAND PEL�OTON
FOUNDERS WAY & SERVICES, L.P. 9800HILLWOOD
H I LLWOO D PARKWAY 9800 HILLWOOD FORT WORTH,T EXAS 6177E 300 T PARKWAY,H SUITE 250
PHONE: (81� 224-6000 FORT WORTH,TEXAS 76177
GRAPHIC SCALE DATE:MARCH 2017 PHONE:817-562-3350
SECTION 00 42 43
PROPOSALFORM
UNIT PRICE BID Bidder's Application
ATCN Founders Way&Hillwood Parkway-Paving,Drainage,&Street Lights
EARTHYORKIMPROVEMENTS
Project Item Information Bidder's Proposal
Bidlist Description on Section Unit of Bid Unit Price Bid Value
Item No. NoMeasure Quantity
1 3110.0101 Site Clearing 311000 LS 1 $10,500.00 $10,500.00
2 3123.0103 Borrow by Plan 312316 CY 3,298 $4.50 $14,841.00
3 3123.0101 Unclassified Excavation by Plan 312316 CY 52,672 $3.25 $171,184.00
4 3125.0101 SWPPP a 1 acre 312500 LS 1 $18,500.00 $18,500.00
Total Earthwork Improvements $215,025.00
Page 2 of 10
PAVING IMPROVEMENTS
Project Item Information Bidder's Proposal
Bidlist Specificati Unit of Bid
Item No. Description on Section Measure Quantity Unit Price Bid Value
5 0241.0500 Remove Fence 024113 LF 1,234 $4.00 $4,936.00
6 0241.1100 Remove Asphalt Pvmt 024115 SY 2,299 $8.00 $18,392.00
7 0241.1000 Remove Cone Pvmt 024115 SY 310 $1200 $3320.00
8 0241.0100 Remove Sidewalk 024113 SF 1.091 $2.00 $2,182.00
9 3305.0107 Manhole Adjustment,Minor 330514 EA 13 $750.00 $9,750.00
10 3305.0108 Miscellaneous Structure Adjustment 330514 EA 2 $1,500.00 $3,000.00
11 3305.0111 Valve Box Adjustment 330514 EA 26 $150.00 $3,900.00
12 3213.0103 8"Cone Pvmt 321313 SY 20,967 $42.00 $880,614.00
13 9999.0011 8"Colored Cone Pvmt(Autumn Beige Color) 00 00 00 SY 260 $92.00 $23,920.00
14 3211.0502 8"Lime Treatment 321129 SY 22,812 $3.25 $74,139.00
15 3211.0400 Hydrated Lime 321129 TN 511 $175.00 $89,425.00
16 3212.0503 6"Asphalt Base Type B 311216 SY 416 $34.00 $14,144.00
17 3211.0502 8"Lime Treatment 321129 SY 485 $3.25 $1,576.25
18 3211.0400 Hydrated Lime 321129 TN 11 $175.00 $1,925.00
19 9999.0000 Brick Pavers 00 00 00 SY 1,251 $92.00 $115,092.00
20 9999.0002 Connect to Existing Header 00 00 00 LF 54 $30.00 $1,620.00
21 3213.0301 4"Cone Sidewalk 321320 SF 45,710 $3.25 $148,557.50
22 3213.0504 Barrier Free Ramp,Type M•2 321320 EA 6 $1,$00.00 $10,800.00
23 3213.0510 Barrier Free Ramp,Type C-3 321320 EA 3 $1,500.00 $4,500.00
24 3213.0506 Barrier Free Ramp,Type P-1 331320 EA 6 $1,500.00 $9,000.00
25 9999.0000 Bike Ramp 00 00 00 EA 3 $1,200.00 $3,600.00
26 3292.0400 Seeding,Hydromulch 329213 SY 51,312 $2.00 $102,624.00
27 9999.0003 12"CONOT PVC C905 00 00 00 LF 148 $60.00 $8,880.00
28 9999.0003 8"CONOT PVC C905 00 00 00 LF 1 210 $54.00 $11,340.00
Page 3 of 10
29 9999.0003 6"CONOT PVC C905 00 00 00 LF 210 $42.00 $8,820.00
30 9999.0005 6"CONOT PVC SCH 40(T) 00 00 00 LF 2,272 $30.00 $68,160.00
31 9999.0004 4"CONOT PVC SCH 40(T) 00 00 00 LF 2,272 $20.00 $45,440.00
32 9999.0004 2"CONOT PVC SCH 40(T) 00 00 00 LF 1,136 $14.00 $15,304.00
33 3471.0001 Traffic Control 347113 MO 3 $1,500.00 $4,500.00
Total Paving Improvements $1,690,460.75
Page 4 of 10
STOFIM BRAIN IMPROVEMENTS
Project Item Information Bidder's Proposal
Bidlist Description on Section Unit of Bid Unit Price Bid Value
Item No. Measure Quantity
34 0241.3014 Remove 21"Storm Line 024114 LF 19 $15.00 $285.00
35 0241.3015 Remove 24"Storm Line 024114 LF 24 $18.00 $432.00
36 0241.3017 Remove 30"Storm Line 024114 LF 258 $20.00 $5,160.00
37 0241.4001 Remove 10'Curb Inlet 024114 EA 1 $1,000.00 $1,000.00
38 0241.4201 Remove 4'Drop Inlet 024114 EA 1 $1,000.00 $1,000.00
39 0241.4401 Remove HeadwaIIISET 024114 EA 1 $1,000.00 $1,000.00
40 9999.0000 6"PVC Landscape Drain 00 00 00 LF 68 $50.00 $3,400.00
41 3341.020121"RCP,Class III 334110 LF 742 $50.00 $37,100.00
42 3341.0205 24"RCP,Class III 334110 LF 328 $55.00 $18,040.00
43 3341.0208 27"RCP,Class III 334110 LF 48 $60.00 $2,880.00
44 3341.0309 36"RCP,Class III 334110 LF 729 $95.00 $69,255.00
45 3341.0402 42"RCP,Class 111 334110 LF 36 $110.00 $3,960.00
46 3341.0409 48"RCP,Class III 334110 LF 323 $125.00 $40,375.00
47 3341.0502 54"RCP,Class III 334110 LF 73 $170.00 $12,410.00
48 3341.0602 60"RCP,Class 111 334110 LF 876 $210.00 $183,960.00
49 3341.1202 50 Box Culvert 334110 LF 88 $215.00 $18,920.00
50 3341.1304 6x5 Box Culvert 334110 LF 21 $285.00 $5,985.00
51 3341.1502 80 Box Culvert 334110 LF 66 $385.00 $25,410.00
52 3349.0001 4'Storm Junction Box 334910 EA 2 $4,000.00 $8,000.00
53 3349.0002 5'Storm Junction Box 344910 EA 2 $5,000.00 $10,000.00
54 3349.0003 6'Storm Junction Box 334910 EA 2 $6,000.00 $12,000.00
55 3349.7002 5'Drop Inlet 33 49 20 EA 1 $5,000.00 $5,000.00
56 3349.7003 6'Drop Inlet 33 49 20 EA 1 $6,000.00 $6,000.00
57 9999.0000 5'x7'Junction Box 00 00 00 EA 1 $8,500.00 $8,500.00
Page 5 of 10
58 9999.0000 Const 8'x5'X 5'x4'Concrete Collar 00 00 00 EA 1 $1,500.00 $1,500.00
59 9999.0000 TxOOT Std Concrete Headwall(CH•FW0) 00 00 00 EA 1 $3,500.00 $3,500.00
60 9999.0000 TxOOT Std Concrete Headwall(FW-0) 00 00 00 EA 1 $11,500.00 $11,500.00
61 3349.5001 10'Curb Inlet 33 49 20 EA 12 $2,800.00 $33,600.00
62 9999.0000 6"Perforated PVC French Drain 00 00 00 LF 66 $50.00 $3,300.00
63 3137.0102 Large Stone Riprap,dry 313700 SY 320 $75.00 $24,000.00
64 3305.0109 Trench Safety 330510 LF 3,330 $1.00 $3,330.00
Total Storm Drain Improvements $560,802.00
Page 6 of 10
PAVEMENT MAR INQ StS D AGE IMPROVEMENTS
Project Item Information Bidder's Proposal
Bidlist Description Specificati Unit of Bid Unit Price Bid Value
Item No. on Section Measure Quantic
65 3217.4301 Remove 4"Pvmt Marking 321723 LF 526 1 $526.00
66 3217.00014"SLD Pvmt Marking HAS(W) 321723 LF 5773 $2.00 $11,546.00
67 3217.0002 4"SLD Pvmt Marking HAS(Y) 321723 LF 5628 $2.00 $11,256.00
68 3217.0003 4"BRK Pvmt Marking HAS(W) 321723 LF 5873 $2.00 $11,746.00
69 3217.02018"SLD Pvmt Marking HAS(W) 321723 LF 105 $4.00 $420.00
70 3217.0202 8"SLD Pvmt Marking HAS(Y) 321723 LF 291 $4.00 $1,164.00
71 9999.0000 Crosswalk 24"White,4"Black Contrast Marking 321723 LF 320 $22.00 $7,040.00
72 9999.0000 2'Line,2'Gap WiContrast Black Outline 18"White,4"Bia 00 00 00 LF 142 $30.00 $4,260.00
73 3217.1003 Lane Legend DBL Arrow 321723 EA 1 $500.00 $500.00
74 3217.1006 Lane Legend Bike 321723 EA 20 $350.00 $7,000.00
75 3217.2102 REFL Raised Marker TY 1-C 321723 EA 147 $4.00 $588.00
76 3217.2103 REFL Raised Marker TY II-A-A 321723 EA 151 $4.00 $604.00
77 9999.0000 Install Alum Sign Ground Mount-ATC Standard 00 00 00 EA 46 $1,400.00 $64,400.00
78 9999.0000 Install Alum Sign to Street Light Pole-ATC Standard 00 00 00 EA 10 $800.00 $8,000.00
79 9999.0000 Install'End of Roadway'Type III Barricade 00 00 00 LF 88 $25.00 $2,200.00
Total Pavement Markings&Signage Improvements !131,250.00
Page 7 of 10
STREET LIGHT IMPROVEMENTS
Project Item Information Bidder's Proposal
Bidlist Description Specificati Unit of Bid Unit Price Bid Value
Item No. on Section Measure Quantic
80 3441.3502 Relocate Street Light Pole 344120 EA 1 4500 $4,500.00
81 2605.3015 2"CONDT PVC SCH 80(T) 26 05 33 LF 6,985 $12.00 $83,820.00
82 2605.3016 2"CONOT PVC SCH 80(B) 26 05 33 LF 100 $28.00 $2,800.00
83 3441.1503 Ground Box,Large,wl Lid Apron 344110 EA 8 $850.00 $6,800.00
84 3441.3201 LED Lighting Fixture 354110 EA 38 $700.00 $26,600.00
85 3441.3002 Rdwy Ilium Assmbly TY 8,11,0.25,and D-30 364110 EA 4 $2,250.00 $9,000.00
86 9999.0000 Rdwy Ilium Assembiy Beacon Product 00 00 00 EA 31 $3,500.00 $108,500.00
87 3441.3303 Rdwy Ilium Foundation TY 7 344120 EA 31 $1,200.00 $37,200.00
88 9999.0000 Rdwy Ilium Foundation(Hillwood) 00 00 00 EA 4 $3,500.00 $14,000.00
Total Street Light Improvements $293,220-00
Old Summaro
Earthwork Improvements $215,025.00
Paving Improvements $1,690,460.75
Storm Drain Improvements $560,802.00
Pavement Marking&Signage Improvements $131,250.00
Street Light Improvements $293,220.00
Total Bid $2,890.757-75
Page 8 of 10