Change Order Request Breakdown
ProjectNamel CONCRETE RESTORATION(2016-1)AT VARIOUS LOCATIONS City Sec# 1 47922
Client Project#(s)l CPN#100064
Contractorl Cheyenne Construction PM Tariqul Islam Inspector Mike Flute
Change Order Submittal# 0 Date 2/9/2017
Dept. T/PW Contract Time
Totals CD
Original Contract Amount $1,118,470.00 $1,118,470.00 180
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,118,470.00 $1,118,470.00 180
Amount of Proposed Change Order $207,247.50 $207,247.50 72
Revised Contract Amount $1,325,717.50 $1,325,717.50 252
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO
Additional Funding(if necessary) $207,247.50 $207,247.50
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 18.53%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,398,087.50
JUSTIFIG4TIGN (REA +ON's) FQR cHX-NGE ORDER
This change order is needed to add additional funds to the contract to cover the cast of overrns on concrete paving,sidewalk and driveway
installation.Overruns on concrete paving are due to additional pavement replacement due to voids found as concrete was being removed.The
street that required more concrete replacement include Bently Ave.,Big Horn Way,Catlow Valley Rd.,Lake Arrowhead Dr.,Mesa Verde Tr.
and North Park Dr.Weatherford Ave.and Belknap Ave.was also added to the contract due to pavement failures.Driveway overruns are
associated with having to adjust drive approaches due to paving replacement. Overruns on sidewalk quantities are primarily due to upgrades
on wheelchair ramps and eliminating dangerous trip hazards in the sidewalk caused by tree roots.An additional 30 days are being added to the
contract to allow for time to complete the additional work.Additional time is also being added to the contract because the contractor had to stop
work until TXDOT completed their work on the guard rails on the bridge east of our work on Belknap.This is to avoid having multiple lanes
closed and creating traffic delays.Thus,42 days are being added.Additional funds are needed to pay for HMAC installation for the area behind
the curb on the eastbound lane of Weatherford where the curb was adjusted due to street settlement.
AUMstlod by
�aL` �� �•l �. S , C Secretaq
�- •IF OR I-
.o
1.
OFFICIAL RECORD
CITY SECRETARYXAS
FT.WORTH,TX _
� J
FORT WORTH City of Fort worth
Change Order Additions
Project Name I CONCRETE RESTORATION(2016-1)AT VARIOUS LOCATIONS City Sec# 47922
Client Project# I CPN#100064
Contractor Cheyenne Construction PM Tariqul Islam Inspector Mike Flute
Change Order Submittal# F1 Date 2/912017
ADDITIONS
nitni os Total
Remove and Replace Concrete Driveway
Remove oncrete and Replace with oncrete Pavement HE W 5.0 0 0 .7
Remove and Replace 4"Sidewalk T/PW 220.00000000F
7 Flex Base,Type A, / W --57T70-0600
New Install 2 1/2 inches of Asphalt on 3 1/2ex base material at Weatherford T/PW 7 . Y
T/PW $207,247.50
Sub Total Additions --3M-7,7,T7-5U.
Change Order Additions Page 1 of 1
i
FOR' WORTH City Of Fort worth
= Change Order Deletions
Project Name I CONCRETE RESTORATION 2016-1)AT VARIOUS LOCATIONS City Sec# 47922
Client Project# I CPN#100064
Contractor Cheyenne Construction PM Tariqul Islam InspectorF Mike Flute
Change Order Submittal# 0 Date 21912017
DELETIONS
ITEM DEPT Qty
unit unit Cost Total
T/PW $0.00
sub Total Deletions
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
MISBE Sub Type of Service Amount for this CO
na $0.00
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
CFW Change Order Approval St-COApp01 Page 1 of 3
Links 2
fortworthgov/Infrastructure Proiects/100064 - Concrete Restoration (2016-1)/Contractor/Change Orders/Change Order 1
Breakdown.xls
fortworthgov/Infrastructure Projects/100064- Concrete Restoration (2016-1)/Contractor/Change Orders/M&C - Change
Order 1.0f
Attachments(0)
No Attachments have been added to this form.
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&ProcessI... 4/20/2017
GFW Cl3ange Order Approval St-COApp01 Page 2 of 3
FORT WORTH. city of Fort Worth
--- Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: St-COSubb01
Change Order No.: St-COApp01 Date Started: 3/30/2017 01
City Sec. No.: 47922 Date Due: 4/8/2017 TMI
Project Name: 100064 - Concrete Restoration (2016-1)
Project Numbers: 100064 DOE Numbers:
Project Concrete Restoration at various locations
Description:
City Project Mgr.: Tariqul Islam City Inspector: Michael Flute
Contractor: Cheyenne Construction
COUNCIL ACTION (If Required):
M&C Log Name: 2000NCRETE RESTORATION 2016-1 CHANGE ORDER 1
M&C Number: C- 28157 M&C Date: 3/28/2017
COST AND DAYS SUMMARY:
Department: Cost($) Fund Account Center: Requested Days:
TPW $ 207,247.50 30100-0200431-5740010-- 72
100064-003380----
Total: $ 207,247.50 Total Requested Days: 72
Approval Status:
https://projectpoint.buzzsaw.com/ bz_web/Forms/FormPrint.aspx?SiteId=51500&Processl... 4/20/2017
GFW Change Order Approval St-COApp01 Page 3 of 3
Approved: Yes
Comments:
User: Jonathan White
Date: 2017-04-03 8:31 AM
Approved: Yes
Comments:
User: Tariqul Islam
Date: 2017-04-03 9:01 AM
Approved: Yes
Comments:
User: Riad Nusrallah
Date: 2017-04-03 4:44 PM
Approved: Yes
Comments:
User: Richard Martinez
Date: 2017-04-13 10:14 AM
Approved: Yes
Comments:
User: Doug Wiersig
Date: 2017-04-13 8:44 PM
Approved: Yes
Comments:
User: Doug Black
Date: 2017-04-14 10:48 AM
Approved: Yes
Comments:
User: Jay Chapa
Date: 2017-04-20 11:10 AM
Action Required:
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessI... 4/20/2017
4
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 3/28/2017
DATE: Tuesday, March 28, 2017 REFERENCE NO.: **C-28157
LOG NAME: 2000NCRETE RESTORATION 2016-1 CHANGE ORDER 1
SUBJECT:
Authorize Execution of Change Order No. 1 to City Secretary Contract No. 47922 with BDD Enterprises
LLC d/b/a Cheyenne Construction Company in the Amount of$207,247.50 for Additional Panel, Driveway
and Sidewalk Replacement on Various Street Segments for a Revised Contract Amount of$1,325,717.50
and Provide for Project Management Costs in the Amount of$130,000.00 for a Revised Project Amount of
$1,455,717.50 (COUNCIL DISTRICTS 4 and 9)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of Change Order No. 1 to City Secretary
Contract No. 47922 with BDD Enterprises LLC d/b/a Cheyenne Construction Company in the amount of
$207,247.50 for additional panel, driveway and sidewalk replacement on various street segments for a
revised contract amount of$1,325,717.50 (City Project No. 100064).
DISCUSSION:
On June 7, 2016, (M&C C-27756)the City Council awarded City Secretary Contract No. 47922 in the
amount of$1,118,470.00 to BDD Enterprises LLC d/b/a Cheyenne Construction Company for Concrete
Street Restoration at Six Locations (City Project No. 100064).
Change Order No. 1 will provide funding of panel replacement for additional failures on East Belknap
Street and East Weatherford Street from North Pecan Street to North Nichols Street. Installation of
asphalt behind the curb, due to change of elevation of East Weatherford Street is included in this change
order. This change order also includes additional panel, driveway and sidewalk replacement on Bentley
Avenue, Big Horn Way, Catlow Valley Road, Lake Arrowhead Drive, Mesa Verde Trail and North Park
Drive.
Project budget is as follows:
Original Contract $1,118,470.00
Change Order No. 1 F$-207,247.50
Revised Contract F$-1,325,717.50
Project Management, Inspection, Material Testing $ 130,000.00
and Contingencies
Project Appropriations $1,455,717.50
The estimated completion date will be extended to May 2017 as a result of the additional work capacity
added by this change order.
Logname: 2000NCRETE RESTORATION 2016-I CHANGE ORDER I Page I of 2
M/WBE OFFICE—Cheyenne Construction Company agrees to maintain its initial MBE commitment of 15
percent that it made on the original contract and extend and maintain that same MBE commitment of 15
percent to this first change order. Therefore, Cheyenne Construction Company remains in compliance
with the City's BDE Ordinance and attests to its commitment by its signature on the Acceptance of
Previous MBE Commitment form executed by an authorized representative of its company.
The project is located in COUNCIL DISTRICTS 4 and 9, Mapsco 35M, 36G, 36K, 36L, 36P, 36R, 36T, 36
V, 62M and 63W.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget, as appropriated, of
the General Capital Projects Fund.
FUND IDENTIFIERS (FIDs):
TO
Fun Department count! Project ProgramAct Budget Reference # moun
�_.__ ID �_ ID ( Year _ _ ._(Chartfield 2
FROM
Fun Department ,Accoun Project Program ctivity Budget Reference # 7 m 06
y ID ID Year ` (Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Douglas Wiersig (7801)
Additional Information Contact: Tariqul Islam (2486)
ATTACHMENTS
1. 100064- Concrete Restoration 2016-1 FID Identifier.xlsx (CFW Internal)
2. APCF CR 2016-1.pdf (CFW Internal)
3. Form 1295 Concrete Restoration 2016-1 CO1.pdf (Public)
4. Map 01 CR 2016-1.pdf (Public)
5. Map 02 CR 2016-1.pdf (Public)
6. Map 03 CR 2016-1.pdf (Public)
7. Map 04 CO CR 2016-1.odf (Public)
Logname: 2000NCRETE RESTORATION 2016-1 CHANGE ORDER I Page 2 of 2
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Tariqul Islam/
Title