Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
Contract 49086
FORT WORTH Cmr sr:CP.UAW COWMCr NO. C �' PROJECT MANUAL FOR THE CONSTRUCTION OF 2017 WATER LEAD SERVICES REPLACEMENT CONTRACT City Project No. 100889 Betsy Price David Cooke Mayor City Manager John Robert Carman Water Director Prepared for The City of Fort Worth WATER DEPARTMENT i� 2017 10 OFFICIAL RECORD CITY SECRETARY n1j,TX CITY OF FORT WORTH, TEXAS WATER DEPAR TMENT 2017 WATER LEAD SERVICES REPLACEMENT CONTRACT City Project No. 100889 JOHN ROBERT CARMAN DIRECTOR WATER DEPARTMENT 2017 APPROVED Fo,r CHRIS HARDER,P.E.,ASSISA[(A DIRECTOR,WATER DEPARTMENT .APPROVED �O ti Z I TON HOLOLA,P.E.,ENGIN ERINGMANAGER,WATER DEPARTMENT w °� RECON ED DATE FORTWORTH, City of Fort Worth Standard Construction Specification Documents Adopted September 2011 000000-1 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 1 of 4 SECTION 00 00 00 TABLE OF CONTENTS Division 00-General Conditions �. 0005 10 Mayor and Council Communication 0005 15 Addenda 0011 13 Invitation to Bidders 0021 13 Instructions to Bidders 0035 13 Conflict of Interest Affidavit 0041 00 Bid Form 00 42 43 Proposal Form Unit Price 0043 13 Bid Bond 00 43 37 Vendor Compliance to State Law Nonresident Bidder 0045 11 Bidders Prequalifications 0045 12 Prequalification Statement 0045 13 Bidder P.requalification Application 00 45 26 Contractor Compliance with Workers'Compensation Law �- 00 45 40 Minority Business Enterprise Goal 00 52 43 Agreement 0061 13 Performance Bond 0061 14 Payment Bond 0061 19 Maintenance Bond 00 61 25 Certificate of Insurance 00 72 00 General Conditions 00 73 00 Supplementary Conditions Division 01-General Requirements 01 11 00 Summary of Work 01 25 00 Substitution Procedures 01 31 19 Preconstruction Meeting 0132 16 Construction Progress Schedule 01 32 33 Preconstruction Video 0133 00 Submittals -� 0135 13 Special Project Procedures 01 45 23 Testing and Inspection.Services 01 50 00 Temporary Facilities and Controls ., 01 5526 Street Use Permit and Modifications to Traffic Control 01 57 13 Storm Water Pollution Prevention Plan 01 58 13 Temporary Project Signage 01 60 00 Product Requirements 01 66 00 Product Storage and Handling Requirements 01 70 00 Mobilization and Remobilization 01 71 23 Construction Staking and Survey 01 74 23 Cleaning 01 77 19 Closeout Requirements 01 78 23 Operation and Maintenance Data 01 78 39 Project Record Documents CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 2,2016 City Project No.100889 *r 000000-2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 2 of 4 Technical Specifications which have been modified by the Engineer specifically for this Project; hard copies are included in the Project's Contract Documents Division 02-Existing Conditions 0241 14 Utility Removal/Abandonment Division 03-Concrete None Division 26-Electrical None Division 31-Earthwork None Division 32-Exterior Improvements 3201 17 Permanent Asphalt Paving Repair 32 01 29 Concrete Paving Repair 32 17 23 Pavement Markings 3291 19 Topsoil Placement and Finishing of Parkways x 329213, Hydro-Mulching, Seeding,and Sodding Division 33-Utilities 33 1210 Water Services 1-inch to 2-inch 33 1225 Connection to Existing Water Mains Division 34-Transportation 3471 13 Traffic Control Technical Specifications listed below are included for this Project by reference and can be viewed/downloaded from the City's Buzzsaw site at: htps:Hprojectpgint.btimaw.com/client/fortworthgov/Resources/02%20- %20Construction%20Documents/Specifications Division 02-Existing Conditions 0241 15 Paving Removal Division 03-Concrete 03 34 13 Controlled Low Strength Material(CLSM) 03 34 16 Concrete Base Material for Trench Repair Division 26-Electrical None Division 31-Earthwork None Division 32-Exterior Improvements 3212 16 Asphalt Paving CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT "' Revised February 2,2016 City Project No.100889 000000-3 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 3 of 4 --- 32 1273 Asphalt Paving Crack Sealants 32 13 13 Concrete Paving 32 1320 Concrete Sidewalks,Driveways and Barrier Free Ramps 3216 13 Concrete Curb and Gutters and Valley Gutters Division 33-Utilities 33 04 40 Cleaning and Acceptance Testing of Water Mains 3305 10 Utility Trench Excavation,Embedment, and Backfill 33 05 30 Location of Existing Utilities a` 33 1105 Bolts,Nuts,and Gaskets 33 11 10 Ductile Iron Pipe 33 11 11 Ductile Iron Fittings -� 33 11 12 Polyvinyl Chloride(PVC)Pressure Pipe Division 34-Transportation None Appendix GC-4.01 Availability of Lands GC-4.02 Subsurface and Physical Conditions GC-4.04 Underground Facilities GC-4.06 Hazardous Environmental Condition at Site GC-6.06.D Minority and Women Owned Business Enterprise Compliance GC-6.07 Wage Rates GC-6.09 Permits and Utilities GC-6.24 Nondiscrimination GR-01 60 00 Product Requirements END OF SECTION CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 2,2016 City Project No.100889 CERTIFICATE OF INTERESTED PARTIES FORM 1295 loll Complete Nos.1-4 and 6 if there are interested parties. OFFICE USE ONLY Complete Nos.1,2,3.5,and 6 if there are no interested parties. CERTIFICATION OF FILING 1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number: of business. 12017-182598 Tejas Commercial Construction LLC Ft.Worth,TX United States Date Filed: 2 Name of governmental entity or state agency that Is a party to the contract for which the form is 03/2.4/2017 being filed. City of,Fort Worth Date AcknoMedged: 3 Provide the identification number used by the governmental entity or state agency to hack or identify the contract,and provide a description of the services,goods,or other property to be provided under the contract. City Project 41 100889 2017 Water lead services replacement contract 4 Nature of interest Name of Interested Party City,State,Country(place of business) (check applicable) Controlling r Intermediary Aden,Charles Ft.Worth,TX United States X i 5 Check only if there is NO Interested Party. ❑ 6 AFFIDAVIT I swear,or affirm,underenal p ty of perjury,that the above disclosure is true and correct. i r Di Notary Public, State ofMy Commission ExpSEPTEMBER 18, 2SVNWM et awl mbed agent of coe =ft mess enemy AFFIX NOTARY STAMP/SEAL ABOVE SWI subscribed before me,by the said ,this the day of 20„7 r.to certify which,witne my hand and seal of office. Si nature of officer administering oat Printed name of officer administers oath Title of officer adn' i tering oaths Forms provided by Texas Ethics Commission www.ethics.state.tx.us Version V1.0.883 1 Offidal site of the Qty of Fort Worth,Texas CITY COUNCIL AGENDA FflRT'VV4RTH COUNCIL ACTION: Approved on 5/2/2017 - Ordinance No. 22692-05-2017 DATE: 5/2/2017 REFERENCE NO.: **C-28208 LOG NAME: 6017WLEADSVC-TEJASC CODE: C TYPE: CONSENT PUBLIC HEARING: NO SUBJECT: Authorize Execution of a Contract with Tejas Commercial Construction, LLC, in the Amount of$200,000.00 for 2017 Water Lead Services Replacement Contract, Provide for Additional Project Costs for a Total Project Amount of$250,000.00 and Adopt Appropriation Ordinance (ALL COUNCIL DISTRICTS) RECOMMENDATION: It is recommended that the City Council: 1. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water Capital Projects Fund in the amount of$250,000.00 from available funds; and * 2. Authorize the execution of a contract with Tejas Commercial Construction, LLC, in the amount of $200,000.00 for 2017 Water Lead Services Replacement Contract (City Project No. 100889). DISCUSSION: The work to be performed under this contract consists of replacing water services that have been identified as lead water services. This contract is necessary to maintain quality water service by augmenting Water Field Operations efforts in removing lead service lines from the water system in a timely manner. ... The project was advertised for bid on February 23, 2017 and March 2, 2017 in the Fort Worth Star-Telegram and on March 23, 2017, the following bids were received. I Bidder Amount Time of Completion Tejas Commercial Construction, LLC $823,850.00 365 Calendar Days Even though the City only received a sole bid, Staff Ihas reviewed the proposed unit prices and considers them to be fair and reasonable. In addition to the contract amount, $50,000.00 is required for project management, material testing and inspection. The bid documents included a stipulation that the total quantities listed may not reflect actual quantities and that the amount budgeted for the projects is $200,000.00. Final payments will be.made based on actual measured quantities. This project will have no impact on the Water Department's operating budget when completed. ., Construction is expected to start August 2017 and be completed by August of 2018 or when the contract amount is exhausted, whichever occurs last. M/WBE OFFICE: Tejas Commercial Construction, LLC, is in compliance with the City's BDE Ordinance by committing to seven percent MBE participation. The City's MBE goal on this project is seven percent. Additionally, Tejas Commercial Construction, LLC, is a certified M/WBE firm. This project is located in ALL COUNCIL DISTRICTS. FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the current capital budget, as appropriated, of the Water Capital Projects Fund. The Fiscal Year 2017 Water Operating Budget includes appropriations of$21,060,000.00 for the purpose of providing Pay-As-You-Go funding for water capital projects. After this transfer for Fiscal Year 2017, the balance will be $7,680,387.00. Appropriations for 2017 Water Emergency Response Contract as depicted below: F Existing Existing Project ppropriations Appropriations Total* Water Capital $0.00 7$250,000.00 $250,000.00 Projects Fund 56002 Project Total $0.00 (^ $250,000.00 F$250,000.00 m * Numbers rounded for presentation purposes. TO Fund Department Account Project Program Activity Budget Reference# Amount ID ID Year Chartfield 2 FROM Fund Department Account Project Program Activity Budget Reference# Amount {D ID Year Chartfield 2 Submitted for City Manager's Office by: Jay Chapa (5804) Originating Department Head: John Carman (8246) Additional Information Contact: J. Chris Underwood (2629) ATTACHMENTS 6017WLEADSVC,TEJASC 1295 Form.pdf 6017WLEADSVC:TEJASC WATER CAP FUND A017r.docx 000510-1 rw MAYOR AND COUNCIL COMMUNICATION(M&C) Page 1 of 1 1 SECTION 00 05 10 2 MAYOR AND COUNCIL COMMUNICATION(.M&C) 3 4 5 6 7 8 d" 9 10 11 12 13 14 15 16 17 rr 18 19 20 21 22 23 END OF SECTION CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT r Revised July 1,2011 City Project No.100889 000515-1 ADDENDA Page 1 of 1 "* 1 SECTION 00 0515 2 ADDENDA 3 4 5 6 7 8 9 -�- 10 11 12 13 14 15 16 17 an 18 dW 19 20 m 21 22 23 END OF SECTION m to CITP OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT ar Revised July 1,2011 City Project No.100889 001113-1 INVITATION TO BIDDERS Page 1 of 2 1 SECTION 00 11 13 2 INVITATION TO BIDDERS 3 4 RECEIPT OF BIDS 5 Sealed bids for the construction of 2017 WATER LEAD SERVICES REPLACEMENT 6 CONTRACT,City Project No. 100889 will be received by the City of Fort Worth Purchasing 7 Office: 8 9 City of Fort Worth 10 Purchasing Division 11 1000 Throclanorton Street 12 Fort Worth,Texas 76102 13 until 1:30 P.M.CST,Thursday March 23,2017 and bids will be opened publicly and read 14 aloud at 2:00 PM CST in the Council Chambers. 15 16 GENERAL DESCRIPTION OF WORK 17 The major work will consist of the(approximate)following: 18 19 Replacement of 1-inch through 2-inch Lead Water Services. 20 21 TIME PERIOD AND RENEWALS 22 The time period of this Agreement will be for one calendar year or the expiration of the total 23 $200,000.00 funding,whichever occurs last. 24 25 PREQUALIFICATION 26 The improvements included in this project must be performed by a contractor who is pre- 27 qualified by the City at the time of bid opening.The procedures for qualification and pre- 28 qualification are outlined in the Section 00 21 13—INSTRUCTIONS TO BIDDERS. 29 30 DOCUMENT EXAMINATION AND PROCUREMENTS 31 The Bidding and Contract Documents may be examined or obtained on-line by visiting the City 32 of Fort Worth's Purchasing Division website at hft://www.fortworditexas.goy/purchasinlr/and 33 clicking on the Buzzsaw link to the advertised project folders on the City's Buzzsaw site.The 34 Contract Documents may be downloaded,viewed,and printed by interested contractors and/or 35 suppliers. The contractor is required to fill out and notarize the Certificate of Interested 36 Parties Form 1295 and the form must be submitted to the Project Manager before the 37 contract will be presented to the City Council.The form can be obtained at 38 https://www.ethics.state.tx.us/tec/1295-Info.htm 39 40 Copies of the Bidding and Contract Documents may be purchased from 41 J. Chris Underwood 42 Water Department,Design Services 43 927 Taylor Street 44 Fort Worth,Texas 76102 45 46 The cost of Bidding and Contract Documents is:No Cost 47 48 49 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 22,2016 City Project No.100889 00.11 13-2 INVITATION TO BIDDERS Page 2 of 2 1 CITY'S RIGHT TO ACCEPT OR REJECT BIDS 2 City reserves the right to waive irregularities and to accept or reject bids. 3 4 INQUIRIES 5 All inquiries relative to this procurement should be addressed to the following: 6 Attn: J. Chris Underwood,City of Fort Worth 7 Email: john.underwood@fortworthtexas.gov 8 Phone: (817)392-2629 9 Fax: (817)392-2527 10 AND/OR 11 Attn: Jim.Deeter,P.E.,City of Fort Worth Water Department 12 Email: jim.deeter@fortworthtexas.gov W' 13 Phone: (817)392-7803 14 Fax: (817)392-2527 15 16 ADVERTISEMENT DATES 17 February 23,2017 18 March 2,2017 19 20 END OF SECTION - CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 22,2016 City Project No.100889 0021.13-1 INSTRUCTIONS TO BIDDERS Page 1 of 9 1 SECTION 00 2113 am 2 INSTRUCTIONS TO BIDDERS 3 #W 4 1. Defined Terms 5 6 1.1.Terms used in these INSTRUCTIONS TO BIDDERS,which are defined in Section 00 72 7 00-GENERAL CONDITIONS. 8 9 1.2.Certain additional terms used in these INSTRUCTIONS TO BIDDERS have the 10 meanings indicated below which are applicable to both the singular and plural thereof. 1.2 1.2.1. Bidder: Any person,firm,partnership, company,association,or corporation acting 13 directly through a duly authorized representative,submitting a bid for performing 14 the work contemplated under the Contract Documents. 15 16 1.2.2.Nonresident Bidder: Any person,firm,partnership,company,association,or 17 corporation acting directly through a duly authorized representative,submitting a 18 bid for performing the work contemplated under the Contract Documents whose 19 principal place of business is not in the State of Texas. 20 21 1.2.3. Successful Bidder: The lowest responsible and responsive Bidder to whom City 22 (on the basis of City's evaluation as hereinafter provided)makes an award. 23 ow 24 2. Copies of Bidding Documents 25 26 2.1.Neither City nor Engineer shall assume any responsibility for errors or misinterpretations '" 27 resulting from the.Bidders use of incomplete sets of Bidding Documents. 28 29 2.2.City and Engineer in making copies of Bidding Documents available do so only for the *� 30 purpose of obtaining Bids for the Work and do not authorize or confer a license or grant 31 for any other use. 32 33 3. Prequalification of Bidders(Prime Contractors and Subcontractors) 34 35 3.1.All Bidders and their subcontractors are required to be prequalified for the work types 36 requiring prequalification at the time of bidding.Bids received from contractors who are 37 not prequalified(even if inadvertently opened)shall not be considered. Prequalification 38 requirement work types and documentation are as follows: 39 40 3.1.1. Water and Sanitary Sewer—Requirements document located at; 41 https://projeMgint.buzzsaw.com/fortworthgov/Resources/02%20- 42 %20Construction%2ODocuments/Contractor%o2OPr qualification/Water%2Oand%2 ® 43 OSanitarY%20Sewee/o20Contractoe/o20Prequalification%20Program/WSS%20pre 44 qual%20requirements.doc?public 45 46 3.2.Each Bidder unless currently prequalified,must be prepared to submit to City within 47 seven(7)calendar days prior to Bid opening,the documentation identified in Section 00 48 45 11,BIDDERS PREQUALIMCATIONS. 49 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No. 100889 0021 13-2 INSTRUCTIONS TO BIDDERS Page 2 of 9 1 3.2.1. Submission of and/or questions related to prequalification should be addressed to 2 the City contact as provided in Paragraph 6.1. 3 4 5 3.3.The City reserves the right to require any pre-qualified contractor who is the apparent low 6 bidder(s)for a project to submit such additional information as the City, in its sole 7 discretion may require,including but not limited to manpower and equipment records, 8 information about key personnel to be assigned to the project,and construction schedule, 9 to assist the City in evaluating and assessing the ability of the apparent low bidder(s)to 10 deliver a quality product and successfully complete projects for the amount bid within 11 the stipulated time frame.Based upon the City's assessment of the submitted 12 information,a recommendation regarding the award of a contract will be made to the 13 City Council. Failure to submit the additional information,if requested,may be grounds 14 for rejecting the apparent low bidder as non-responsive.Affected contractors will be 15 notified in writing of a recommendation to the City Council. 16 17 3.4.In addition to prequalification,additional requirements for qualification may be required 18 within various sections of the Contract Documents. 19 20 4. Examination of Bidding and Contract Documents,Other Related Data,and Site 21 22 4.1.Before submitting a Bid,each Bidder shall: 23 24 4.1.1.Examine and carefully study the Contract Documents and other related data 25 identified in the Bidding Documents(including"technical data"referred to in 26 Paragraph 4.2. below).No information given by City or any representative of the 27 City other than that contained in the Contract Documents and officially 28 promulgated addenda thereto, shall be binding upon the City. 29 30 4.1.2. Visit the site to become familiar with and satisfy Bidder as to the general, local and 31 site conditions that may affect cost,progress,performance or furnishing of the y� 32 Work. 33 34 4.1.3. Consider federal, state and local Laws and Regulations that may affect cost, 35 progress,performance or furnishing of the Work. 36 37 4.1.4. Not Used. 38 39 4.1.5. Study all: (i)reports of explorations and tests of subsurface conditions at or 40 contiguous to the Site and all drawings of physical conditions relating to existing 41 surface or subsurface structures at the Site(except Underground Facilities)that 42 have been identified in the Contract Documents as containing reliable"technical 43 data"and(ii)reports and drawings of Hazardous Environmental Conditions, if any, 44 at the Site that have been identified in the Contract Documents as containing 45 reliable"technical data." 46 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No.100889 002113-3 INSTRUCTIONS TO BIDDERS Page 3 of 9 1 4.1.6. Be advised that the Contract Documents on file with the City shall constitute all of 2 the information which the City will furnish.All additional information and data 3 which the City will supply after promulgation of the formal Contract Documents 4 shall be issued in the form of written addenda and shall become part of the Contract 5 Documents just as though such addenda were actually written into the original 6 Contract Documents.No information given by the City other than that contained in 7 the Contract Documents and officially promulgated addenda thereto, shall be 8 binding upon the City. 9 10 4.1.7. Perform independent research, investigations,tests,borings,and such other means 11 as may be necessary to gain a complete knowledge of the conditions which will be .. 12 encountered during the construction of the project.On request,City may provide 13 each Bidder access to the site to conduct such examinations,investigations, 14 explorations,tests and studies as each Bidder deems necessary for submission of a 15 Bid. Bidder must fill all holes and clean up and restore the site to its former 16 conditions upon completion of such explorations, investigations,tests and studies. 17 18 4.1.8. Determine the difficulties of the Work and all attending circumstances affecting the 19 cost of doing the Work,time required for its completion,and obtain all information 20 required to make a proposal.Bidders shall rely exclusively and solely upon their 21 own estimates,investigation,research,tests,explorations, and other data which are 22 necessary for full and complete.information upon which the proposal is to be based. 23 It is understood that the submission of a proposal is prima-facie evidence that the 24 Bidder has made the investigation,examinations and tests herein required.Claims 25 for additional compensation due to variations between conditions actually 26 encountered in construction and as indicated in the Contract Documents will not be 27 allowed. 28 29 4.1.9.Promptly notify City of all conflicts,errors,ambiguities or discrepancies in or 30 between the Contract Documents and such other related documents.The Contractor 31 shall not take advantage of any gross error or omission in the Contract Documents, 32 and the City shall be permitted to make such corrections or interpretations as may 33 be deemed necessary for fulfillment of the intent of the Contract.Documents. 34 35 4.2. Reference is made to Section 00 73 00—Supplementary Conditions for identification of: 36 37 4.2.1. those reports of explorations and tests of subsurface conditions at or contiguous to 38 the site which have been utilized by City in preparation of the Contract Documents. 39 The logs of Soil Borings, if any, on the plans are for general information only. 40 Neither the City nor the Engineer guarantee that the data shown is representative of -- 41 conditions which actually exist. 42 43 4.2.2.those drawings of physical conditions in or relating to existing surface and 44 subsurface structures(except Underground Facilities)which are at or contiguous to 45 the site that have been utilized by City in preparation of the Contract Documents. 46 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No.100889 0021 13-4 INSTRUCTIONS TO BIDDERS Page 4 of 9 1 4.2.3. copies of such reports and drawings will be made available by City to any Bidder 2 on request. Those reports and drawings may not be part of the Contract 3 Documents, but the "technical data"contained therein upon which Bidder is entitled 4 to rely as provided in Paragraph 4.02. of the General Conditions has been identified 5 and established in Paragraph SC 4.02 of the Supplementary Conditions. Bidder is 6 responsible for any interpretation or conclusion drawn from any "technical data" or 7 any other data, interpretations,opinions or information. 8 9 4.3.The submission of a Bid will constitute an incontrovertible representation by Bidder(i) 10 that Bidder has complied with every requirement of this Paragraph 4,(ii)that without 1 I exception the Bid is premised upon performing and furnishing the Work required by the 12 Contract Documents and applying the specific means,methods,techniques,sequences or 13 procedures of construction(if any)that may be shown or indicated or expressly required 14 by the Contract Documents,(iii)that Bidder has given City written notice of all 15 conflicts,errors,ambiguities and discrepancies in the Contract Documents and the 16 written resolutions thereof by City are acceptable to Bidder,and when said conflicts, 17 etc.,have not been resolved through the interpretations by City as described in 18 Paragraph 6.,and(iv)that the Contract Documents are generally sufficient to indicate 1.9 and convey understanding of all terms and conditions for performing and furnishing the 20 Work. 21 22 4.4.The provisions of this Paragraph 4,inclusive,do not apply to Asbestos,Polychlorinated 23 biphenyls(PCBs),Petroleum,Hazardous Waste or Radioactive Material covered by 24 Paragraph 4.06.of the General Conditions,unless specifically identified in the Contract 25 Documents. 26 27 5. Availability of Lands for Work,Etc. 28 29 5.1.The lands upon which the Work is to be performed,rights-of-way and easements for 30 access thereto and other lands designated for use by Contractor in performing the Work 31 are identified in the Contract Documents. All additional lands and access thereto , 32 required for temporary construction facilities,construction equipment or storage of 33 materials and equipment to be incorporated in the Work are to be obtained and paid for 34 by Contractor. Easements for permanent structures or permanent changes in existing 35 facilities are to be obtained and paid for by City unless otherwise provided in the 36 Contract Documents. 37 38 5.2.Outstanding right-of-way,easements,and/or permits to be acquired by the City are listed 39 in Paragraph SC 4.01 of the Supplementary Conditions.In the event the necessary right- 40 of-way,easements,and/or permits are not obtained,the City reserves the right to cancel 41 the award of contract at any time before the Bidder begins any construction work on the 42 project. 43 44 5.3. The Bidder shall be prepared to commence construction without all executed right-of- — 45 way, easements,and/or permits,and shall submit a schedule to the City of how 46 construction will proceed in the other areas of the project that do not require permits 47 and/or easements. 48 49 50 CITY OF FORT WORTH 2017 WATER.LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No. 100889 002113-5 INSTRUCTIONS TO BIDDERS Page 5 of 9 1 6. Interpretations and Addenda 2 3 6.1.All questions about the meaning or intent of the Bidding Documents are to be directed to 4 City in writing on or before 2 p.m.,the Monday prior to the Bid opening. Questions 5 received after this day may not be responded to. Interpretations or clarifications 6 considered necessary by City in response to such questions will be issued by Addenda 7 delivered to all parties recorded by City as having received the Bidding Documents. 8 Only questions answered by formal written Addenda will be binding. Oral and other 9 interpretations or clarifications will be without legal effect. 10 I 1 Address questions to: 12 13 City of Fort Worth 14 1000 Throckmorton Street d, 15 Fort Worth,TX 76102 16 Attn: J. Chris Underwood 17 Fax: (817)392-2527 18 Email:john.underwood@fortworthtexas.gov 19 Phone: (817)392-2629 20 21 22 6.2.Addenda may also be issued to modify the Bidding Documents as deemed advisable by 23 City. 24 25 6.3.Addenda or clarifications maybe posted via Buzzsaw at 26 hos://proiegVoint.buzzsaw.com/client[FortWorth og v/lnftastructure%20Projects/10088 27 9%20- 28 %20Water%2OEmergena%2OResponse%2OContract/Bid%2ODocuments%2OPackagg 29 30 6.4.A prebid conference may be held at the time and place indicated in the Advertisement or 31 INVITATION TO BIDDERS. Representatives of City will be present to discuss the 32 Project. Bidders are encouraged to attend and participate in the conference. City will 33 transmit to all prospective Bidders of record such Addenda as City considers necessary 34 in response to questions arising at the conference. Oral statements may not be relied 35 upon and will not be binding or legally effective. 36 37 7. Bid Security ..r 38 39 7.1.Each Bid must be accompanied by Bid.Bond made payable to City in an.amount of five 40 (5)percent of Bidder's maximum Bid price on form attached, issued by a surety meeting 41 the requirements of Paragraphs 5.01 of the General Conditions. 42 43 7.2.The Bid Bond of all Bidders will be retained until the conditions of the Notice of Award 44 have been satisfied. If the Successful Bidder fails to execute and deliver the complete 45 Agreement within 10 days after the Notice of Award,City may consider Bidder to be in 46 default,rescind the Notice of Award,and the Bid Bond of that Bidder will be forfeited. 47 Such forfeiture.shall be City's exclusive remedy if Bidder defaults. The Bid Bond of all 48 other Bidders whom City believes to have a reasonable chance of receiving the award 49 will be retained by City until final contract execution. 50 CITY OF FORT WORTH '2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No. 100889 002113-6 INSTRUCTIONS TO BIDDERS Page 6 of 9 1 8. Contract Times 2 The number of days within which,or the dates by which,Milestones are to be achieved in 3 accordance with the General Requirements and the Work is to be completed and ready for 4 Final Acceptance is set forth in the Agreement or incorporated therein by reference to the 5 attached Bid Form. 6 ®. 7 9. Liquidated Damages 8 Provisions for liquidated damages are set forth in the Agreement. 9 _ 10 10. Substitute and "Or-Equal" Items 11 The Contract,if awarded,will be on the basis of materials and equipment described in the 12 Bidding Documents without consideration of possible substitute or"or-equal"items. �- 13 Whenever it is indicated or specified in the Bidding Documents that a"substitute"or"or- 14 equal" item of material or equipment may be furnished or used by Contractor if acceptable to 15 City,application for such acceptance will not be considered by City until after the Effective 16 Date of the Agreement. The procedure for submission of any such application by Contractor 17 and consideration by City is set forth in Paragraphs 6.05A., 6.05B, and 6.05C.of the General 18 Conditions and is supplemented in Section 0125 00 of the General Requirements. 19 20 11. Subcontractors,Suppliers and Others 21 22 11.1. In accordance with the City's Business Diversity Enterprise Ordinance No.20020- 23 12-2011 (as amended),the City has goals for the participation of minority business 24 and/or small business enterprises in City contracts.A copy of the Ordinance can be 25 obtained from the Office of the City Secretary.The Bidder shall submit the MBE and 26 SBE Utilization Form, Subcontractor/Supplier Utilization Form,Prime Contractor 27 Waiver Form and/or Good Faith Effort Form with documentation and/or Joint 28 Venture Form as appropriate.The Forms including documentation must be received 29 by the City no later than 2:00 P.M. CST,on the second business days after the bid 30 opening date.The Bidder shall obtain a receipt from the City as evidence the 31 documentation was received. Failure to comply shall render the bid as non- 32 responsive. 33 34 11.2. No Contractor shall be required to employ any Subcontractor, Supplier,other person 35 or organization against whom Contractor has reasonable objection. 36 37 12. Bid Form 38 39 12.1. The Bid Form is included with the Bidding Documents; additional copies may be 40 obtained from the City. 41 42 12.2. All blanks on the Bid Form must be completed by printing in ink and the Bid Form 43 signed in ink. Erasures or alterations shall be initialed in ink by the person signing 44 the Bid Form. A Bid price shall be indicated for each Bid item,alternative,and unit 45 price item listed therein. In the case of optional alternatives,the words "No Bid," 46 "No Change,"or"Not Applicable"may be entered.Bidder shall state the prices, 47 written in ink in both words and numerals,for which.the Bidder proposes to do the 48 work contemplated or furnish materials required.All prices shall be written legibly. 49 In case of discrepancy between price in written words and the price in written 50 numerals,the price in written words shall govern. 51 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No.100999 0021 13-7 INSTRUCTIONS TO BIDDERS Page 7 of 9 1 12.3. Bids by corporations shall be executed in the corporate name by the president or a 2 vice-president or other corporate officer accompanied by evidence of authority to 3 sign. The corporate seal shall be affixed. The corporate address and state of 4 incorporation shall be shown below the signature. 5 6 12.4. Bids by partnerships shall be executed in the partnership name and signed by a 7 partner,whose title must appear under the signature accompanied by evidence of 8 authority to sign. The official address of the partnership shall be shown below the 9 signature. 10 11 12.5. Bids by limited liability companies shall be executed in the name of the firm by a M- 12 member and accompanied by evidence of authority to sign. The state of formation of 13 the firm and the official address of the firm shall be shown. 14 15 12.6. Bids by individuals shall show the Bidder`s name and official address. 16 17 12.7. Bids by joint ventures shall be executed by each joint venturer in the manner 18 indicated on the Bid Form. The official address of the joint venture shall be shown. 19 20 12.8. All names shall be typed or printed in ink below the signature. 21 22 12.9. The.Bid shall contain an acknowledgement of receipt of all Addenda,the numbers of 23 which shall be filled in on the Bid Form. 24 ® 25 12.10. Postal and e-mail addresses and telephone number for communications regarding the 26 Bid shall be shown. 27 -� 28 12.11. Evidence of authority to conduct business as a Nonresident Bidder in the state of 29 Texas shall be provided in accordance with Section 00 43 37—Vendor Compliance 30 to State Law Non Resident Bidder. 31 32 13. Submission of Bids 33 Bids shall be submitted on the prescribed Bid Form,provided with the Bidding Documents, 34 at the time and place indicated in the Advertisement or INVITATION TO BIDDERS, 35 addressed to Purchasing Manager of the City,and shall be enclosed in an opaque sealed 36 envelope,marked with the City Project Number,.Project title,the name and address of 37 Bidder,and accompanied by the Bid security and other required documents. If the Bid is sent 38 through the mail or other delivery system,the sealed envelope shall be enclosed in a separate 39 envelope with the notation "BID ENCLOSED" on the face of it. 40 41 14. Modification and Withdrawal of Bids 42 43 14.1. Bids addressed to the Purchasing Manager and filed with the Purchasing Office 44 cannot be withdrawn prior to the time set for bid opening. A request for withdrawal 45 must be made in writing by an appropriate document duly executed in the manner 46 that a Bid must be executed and delivered to the place where Bids are to be submitted 47 at any time prior to the opening of Bids.After all Bids not requested for withdrawal 48 are opened and publicly read aloud,the Bids for which a withdrawal request has been 49 properly filed may,at the option of the City,be returned unopened. 50 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No.100889 0021 13-8 INSTRUCTIONS TO BIDDERS Page 8 of 9 1 14.2. Bidders may modify their Bid by electronic communication at any time prior to the 2 time set for the closing of Bid receipt. 3 4 15. Opening of Bids 5 Bids will be opened and read aloud publicly at the place where Bids are to be submitted. An 6 abstract of the amounts of the base Bids and major alternates(if any)will be made available 7 to Bidders after the opening of Bids. 8 9 16. Bids to Remain Subject to Acceptance 10 All Bids will remain subject to acceptance for the time period specified for Notice of Award 11 and execution and delivery of a complete Agreement by Successful Bidder. City may, at 12 City's sole discretion,release any Bid and nullify the Bid security prior to that date. -- 13 14 17. Evaluation of Bids and Award of Contract 15 16 17.1. City reserves the right to reject any or all Bids, including without limitation the rights 17 to reject any or all nonconforming,nonresponsive,unbalanced or conditional Bids 18 and to reject the Bid of any Bidder if City believes that it would not be in the best 19 interest of the Project to make an award to that Bidder,whether because the Bid is 20 not responsive or the Bidder is unqualified or of doubtful financial ability or fails to 21 meet any other pertinent standard or criteria established by City. City also reserves 22 the right to waive informalities not involving price,contract time or changes in the 23 Work with the Successful Bidder. Discrepancies between the multiplication of units 24 of Work and unit prices will be resolved in favor of the unit prices. Discrepancies 25 between the indicated sum of any column of figures and the correct sum thereof will 26 be resolved in favor of the correct sum. Discrepancies between words and figures 27 will be resolved in favor of the words. .28 29 17.1.1. Any or all bids will be rejected if City has reason to believe that collusion exists 30 among the Bidders,Bidder is an interested party to any litigation against City, 31 City or Bidder may have a claim against the other or be engaged in litigation, 32 Bidder is in arrears on any existing contract or has defaulted on a previous 33 contract,Bidder has performed a prior contract in an unsatisfactory manner,or 34 Bidder has uncompleted work which in the judgment of the City will prevent or 35 hinder the prompt completion of additional work if awarded. 36 37 17.2. City may consider the qualifications and experience of Subcontractors, Suppliers,and 38 other persons and organizations proposed for those portions of the Work as to which 39 the identity of Subcontractors, Suppliers,and other persons and organizations must 40 be submitted as provided in the Contract Documents or upon the request of the City. 41 City also may consider the operating costs,maintenance requirements,performance 42 data and guarantees of major items of materials and equipment proposed for 43 incorporation in the Work when such data is required to be submitted prior to the 44 Notice of Award. 45 46 17.3. City may conduct such investigations as City deems necessary to assist in the 47 evaluation of any Bid and to establish the responsibility,qualifications,and financial _. 48 ability of Bidders,proposed Subcontractors, Suppliers and other persons and 49 organizations to perform and furnish the Work in accordance with the Contract 50 Documents to City's satisfaction within the prescribed time. 51 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No.100889 0021 13-9 do INSTRUCTIONS TO BIDDERS Page 9 of 9 1 17.4. Contractor shall perform with his own organization,work of a value not less than 2 35%of the value embraced on the Contract, unless otherwise approved by the City. 3 4 17.5. If the Contract is to be awarded, it will be awarded to lowest responsible and 5 responsive Bidder whose evaluation by City indicates that the award will be in the 6 best interests of the City. 7 8 17.6. Pursuant to Texas Government Code Chapter 2252.001,the City will not award 9 contract to a Nonresident Bidder unless the Nonresident Bidder's bid is lower than 10 the lowest bid submitted by a responsible Texas Bidder by the same amount that a 11 Texas resident bidder would be required to underbid a Nonresident Bidder to obtain a 'R 12 comparable contract in the state in which the nonresident's principal place of 13 business is located. 14 .. 15 17.7. A contract is not awarded until formal City Council authorization.If the Contract is 16 to be awarded, City will award the Contract within 90 days after the day of the Bid 17 opening unless extended in writing. No other act of City or others will constitute 18 acceptance of a Bid. Upon the contractor award a Notice of Award will be issued by 19 the City. 20 dN 21 17.8. Failure or refusal to comply with the requirements may result in rejection of Bid. 22 23 18. Signing of Agreement 24 When City issues a Notice of Award to the Successful Bidder, it will be accompanied by the 25 required number of unsigned counterparts of the Agreement. Within 14 days thereafter 26 Contractor shall sign and deliver the required number of counterparts of the Agreement to 27 City with the required Bonds, Certificates of Insurance, and all other required documentation. 28 City shall thereafter deliver one fully signed counterpart to Contractor. 29 30 31 32 END OF SECTION dft CITY OF FORT WORTH 2017 WATER LEAD SERVICES +� STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 21,2015 City Project No.100889 ry 0035 •13 BID FORM Page 1 of'I SECTION 00 35 13 CONFLICT OF INTEREST AFFIDAVIT Each bidder, offeror, or respondent (hereinafter also referred to as "you") to a City of Fort Worth (also referred to as "City") procurement are required to complete Conflict of Interest Questionnaire (the attached CIQ Form) and Local Government Officer Conflicts Disclosure Statement (the attached CIS Form) below pursuant to state law. This affidavit will certify that the Bidder has on file with the City Secretary the required documentation and is eligible to bid on City Work. The referenced forms may also be downloaded from the website links provided below. http://www.ethics.state.tx.us/forms/CIQ.pdf http://www.ethics.state.tx.us/forms/CIS.pdf D CIQ Form is on file with City Secretary ❑ CIQ Form is being provided to the City Secretary ❑ CIS Form is on File with City Secretary ❑ CIS Form is being provided to the City Secretary BIDDER: Tejas Commercial Construction, LLC By: Charles D. Allen P.O. Box 10395 Signature: 0 River Oaks, TX 76114 Title: Vice President END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20120327 Bid Package CONFLICT OF INTEREST QUESTIONNAIRE FORM CIQ For vendor or other person doing business with local governmental entity This questionnaire reflects changes made to the law by H.B. 1491, 86th Leg., Regular Session. OFFICEUSEONLY This questionnaire is being filed in accordance with Chapter 176,Local Government Code Dace Received by a person who has a business relationship as defined by Section 176.001(1-a)with a local governmental entity and the person meets requirements under Section 176.006(a). By law this questionnaire must be filed with the records administrator of the local governmental entity not later than the 7th business day after the date the person becomes aware of facts that require the statement to be filed. See Section 176.006,Local Government Code. A person commits an offense if the person knowingly violates Section 176.006, Local Government Code.An offense under this section is a Class C misdemeanor. 1 Name of person who has a business relationship with local governmental entity. 2 ❑ Check this box if you are filing an update to a previousiyfiled questionnaire. (The law requires that you file an updated completed questionnaire with the appropriate filing authority not later than the 7th business day after the date the originally filed questionnaire becomes incomplete or inaccurate.) 3 Name of local government officer with whom filer has employment or business relationship. Name of Officer This section (item 3 including subparts A, B, C & D) must be completed for each officer with whom the filer has an employment.or other business relationship as defined by Section 176.001(1-a), Local Government Code. Attach additional pages to this Form CIQ as necessary. A. Is the local government officer named in this section receiving or likely to receive taxable income,other than investment income, from the filer of the questionnaire? Yes F--] No B. Is the filer of the questionnaire receiving or likely to receive taxable income,other than investment income,from or at the direction of the local government officer named in this section AND the taxable income is not received from the local governmental entity? F] Yes F--1No C. Is the filer of this questionnaire employed by a corporation or other business entity with respect to which the local government officer serves as an officer or director, or holds an ownership of 10 percent or more? Yes F--1 No D. Describe each employment or business relationship with the local government officer named in this section. 4 Signature of person doing business with the governmental entity Date Adopted 06/29/2007 LOCAL GOVERNMENT OFFICER FORM CIS CONFLICTS DISCLOSURE STATEMENT (Instructions for completing and filing this form are provided on the next page.) This questionnaire reflects changes made to the law by H.B. 1491, 80th Leg., Regular Session. OFFICE USE ONLY This is the notice to the appropriate local governmental entity that the following local —"— government officer has become aware of facts that require the officer to file this statement Date Received in accordance with Chapter 176,Local Government Code. 1 Name of Local Government Officer 2 Office Held 3 Name of person described by Sections 176.002(a)and 176.003(a),Local Government Code 4 Description of the nature and extent of employment or other business relationship with person named in item 3 s List gifts accepted by the local government officer and any family member, excluding gifts described by Section 176.003(a-1),if aggregate value of the gifts accepted from person named in item 3 exceed$250 during the 12-month period described by Section 176.003(a)(2)(B) Date Gift Accepted Description of Gift Date Gift Accepted Description of Gift Date GiftAccepted Description of Gift (attach additional forms as necessary) e AFFIDAVIT I swear under penalty of perjury that the above statement is true and correct. I acknowledge that the disclosure applies to a family member(as defined by Section 176.001(2), Local Government Code)of this local government officer, i also acknowledge that this statement covers the 12-month period described by Section 176.003(a),Local Government Code. Signature of Local Government Officer AFFIX NOTARY STAMP r SEAL ABOVE ` Swan to and subscribed before me,by the said this the day Of .20 ,to certify which,witness my hand and seal of office. Signature of officer administering oath Printed name of officer administering oath Title of officer administering oath Adopted 06/29/2007 LOCAL GOVERNMENT OFFICER CONFLICTS DISCLOSURE STATEMENT Section 176.003 of the Local Government Code requires certain local government officers to file this form. A "local government officer" is defined as a member of the governing body of a local governmental entity; a director, superintendent, administrator, president,or other person designated as the executive officer of the local governmental entity; or an employee of a local governmental entity with respect to whom the local governmental entity has, in accordance with Section 176.005,extended the requirements of Sections 176.003 and 176.004. This form is required to be filed with the records administrator of the local governmental entity not later than 5 p.m. on the seventh business day after the date on which the officer becomes aware of the facts that require the filing of this statement. A local government officer commits an offense if the officer knowingly violates Section 176.003, Local Government Code.An offense under this section is a Class C misdemeanor. Please refer to chapter 176 of the Local Government Code for detailed information regarding the requirement to file this form. INSTRUCTIONS FOR COMPLETING THIS FORM The following numbers correspond to the numbered boxes on the other side. 1. Name of Local Government Officer. Enter the name of the local government officer filing this statement. 2. Office Held. Enter the name of the office held by the local government officer filing this statement. 3. Name of person described by Sections 176.002(a)and 176.003(a), Local Government Code. Enter the name of the person described by Section 176.002, Local Government Code with whom the officer has an employment or other business relationship as described by Section 176.003(a), Local Government Code. 4. Description of the nature and extent of employment or business relationship with person named in item 3. Describe the nature and extent of the employment or other business relationship with the person in item 3 as described by Section 176.003(a), Local Government Code. 5. List gifts accepted, excluding gifts described by Section 176.003(a-1), if aggregate value of the gifts accepted from person named in item 3 exceed$250. List gifts accepted during the 12-month period (described by Section 176.003(a),Local Government Code)by the local government officer or family member of the officer, excluding gifts described by Section 176.003(a-1),from the person named in item 3 that in the aggregate exceed$250 in value. 6.Affidavit. Signature of local government officer. W7roqu Adopted 06/29/2007 0041 00 BID FORM Page 1 of 3 SECTION 00 4100 BID FORM TO: The Purchasing Manager c/o:The Purchasing Division 1000 Throckmorton Street City of Fort Worth, Texas 76102 FOR: 2017 WATER LEAD SERVICES REPLACEMENT CONTRACT City Project No.: 100889 Units/Sections: Water Improvements 1. Enter Into Agreement The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with City in the form included in the Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents. 2. BIDDER Acknowledgements and Certification 2.1. In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION TO BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those dealing with the disposition of Bid Bond. 2.2. Bidder is aware of all costs to provide the required insurance, will do so pending contract award, and will provide a valid insurance certificate meeting all requirements within 14 days of notification of award. 2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation. 2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid. 2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding. 2.6. Bidder has not engaged in corrupt,fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph: a. "corrupt practice"means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process. b. "fraudulent practice"means an intentional misrepresentation of facts made(a)to influence the bidding process to the detriment of City(b)to establish Bid prices at artificial non-competitive levels, or(c)to deprive City of the benefits of free and open competition. c. "collusive practice"means a scheme or arrangement between two or more Bidders,with or without the knowledge of City, a purpose of which is to establish Bid prices at artificial, non-competitive levels. d. "coercive practice"means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Form Revised 20150821 City Project No.100889 0041 00 BID FORM Page 2 of 3 3. Prequalification The Bidder acknowledges that the following work types must be performed only by prequalified contractors and subcontractors: a. Water Improvements-Replacement of 1-inch through 2-inch Lead Water Services �.:. r5� C � '... d Lts '�w9 ape}ate o� $ e 4. Time of Completion 4.1. The Work will be complete for Final Acceptance within 365 days after the date when the the Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions. 4.2. Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work(and/or achievement of Milestones)within the times specified in the Agreement. 5. Attached to this Bid The following documents are attached to and made a part of this Bid: a. This Bid Form, Section 00 41 00 b. Required Bid Bond, Section 00 43 13 issued by a surety meeting the requirements of Paragraph 5.01 of the General Conditions. c. Proposal Form, Section 00 42 43 d. Vendor Compliance to State Law Non Resident Bidder, Section 00 43 37 e. MWBE Forms(optional at time of bid) f. Prequalification Statement, Section 00 45 12 g. Conflict of Interest Affidavit, Section 00 35 13 *If necessary, CIQ or CIS forms are to be provided directly to City Secretary h. Any additional documents that may be required by Section 12 of the Instructions to Bidders 6. Total Bid Amount 6.1. Bidder will complete the Work in accordance with the Contract Documents for the following bid amount. In the space provided below, please enter the total bid amount for this project. Only this figure will be read publicly by the City at the bid opening. 6.2. It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is subject to verification and/or modification by multiplying the unit bid prices for each pay item by the respective estimated quantities shown in this proposal and then totaling all of the extended amounts. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Form Revised 20150821 City Project No.100889 0041 00 BID FORM Page 3 of 3 6.3. Total Bid Amount Total Bid $823,850.00 7. Bid Submittal This Bid is submitted on March 23, 2017 by the entity named below. Respectfully submitted, Receipt is acknowledged of the Initial following Addenda: By: �, � � Addendum No. 1: N/A (Signature) Addendum No. 2: N/A Addendum No. 3: N/A Charles D. Allen Addendum No.4: N/A (Printed Name) Title: Vice President Company: Tejas Commercial Construction, LLC Corporate Seal: Address: P.O. Box 10395 River Oaks, TX 76114 ���`�Gcrn> !�!'c ►j ''%, State of Incorporation: Texas M: Email:Email: Callen@teiasconstruction.net — � p•: LID Phone: 817-901-8499 2009 END OF SECTION CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Form Revised 20150821 City Project No.100889 W4243 BID PROPOSAL, Pogo I nr.`. SECTION 00 42 43 PROPOSAL FORM UNIT PRICE BID Bidder's Application Project Item Information Bidders Proposal Pay Item Bid List Item Specification Bid Quantity Unit of Description Unit Price Bid Value No. Section No. Measurement WATER IMPROVEMENTS _ 1 3312.2003 33 12 10 15 EA 1-inch Water Service, 0'-10'Length,No Paving Thirty one hundred Dollars No Cents $3,100.00 $46,500.00 2 3312.2003 33 1210 15 EA 1-inch Water Service, 0'-10'Length,Asphalt Paving Thirty seven hundred Dollars No Cents $3,700.00 $55500.00 3 3312.2003 33 1210 5 EA 1-inch Water Service, 0'-10'Length,Concrete Paving Thirty eight hundred Dollars No Cents $3,800.00 $19,000.00 .. 4 3312.2003 33 12 10 15 EA 1-inch Water Service, 10.1'-25'Length,No Paving Thirty four hundred Dollars No Cents $3,400.00 $51,000.00 ® 5 3312.2003 3312 10 15 EA 1-inch Water Service, 10.1'-25'Length,Asphalt Paving Forty three hundred Dollars No Cents $4,300.00 $64,500.00 6 3312.2003 33 12 10 5 EA 1-inch Water Service, 10.1'-25'Length,Concrete Paving Forty five hundred Dollars No Cents $4,500.00 $22,500.00 7 3312.2003 33 12 10 15 EA 1-inch Water Service, 25.1-40'Length,Asphalt Paving Fifty four hundred Dollars No Cents $5,400.00 $81,000.00 8 3312.2003 33 12 10 5 EA 1-inch Water Service, 25.1'-40'Length,Concrete Paving Six thousand Dollars No Cents $6.000.00 $30,000.00 9 3312.2103 33 12 10 5 EA 1.5-inch Water Service, 0'-10'Length,No Paving Thrifty five hundred Dollars No Cents $3,500.00 $17500.00 10 3312.2103 33 12 10 5 EA 1.5-inch Water Service, 0'-10'Length,Asphalt Paving Four thousand Dollars No Cents $4,000.00 $20,000.00 CITY OF FORT WORTH 2017 WATER LEAD SFRVICES STANDARD CONSTRUCTION SPECIFICATION DOCUWNTS REPLACEkENT CONTRACT Forth Rc iml 20120120 City Pfood No.100889 00 42 43 BID PROPOSAL Pape 2 nr5 SECTION 00 42 43 PROPOSAL FORM UNIT PRICE BID Bidder's Application Project Item Information Bidder's Proposal dOp Bid List Item Specification Unit of Pay Item No. Section No. Bid Quantity Measurement Description Unit Price Bid Value 11 3312.2103 33 12 10 2 EA 1.5-inch Water Service, 0'-10'Length,Concrete Paving w Forty three hundred Dollars No Cents $4,300.00 $8,600.00 12 3312.2103 33 12 10 5 EA 1.5-inch Water Service, 10.1'-25'Length,No Paving s Thirty eight hundred Dollars No Cents $3,800.00 $19,000.00 13 3312.2103 33 12 10 5 EA 1.5-inch Water Service, MR 10.1'-25'Length,Asphalt Paving Forty eight hundred Dollars No Cents $4,800.00 $24,000.00 14 3312.2103 33 12 10 2 EA 1.5-inch Water Service, �. 10.1'-25'Length,Concrete Paving Five Thousand Dollars No Cents $5,000.00 $10,000.00 15 3312.2103 33 12 10 5 EA 1.5-inch Water Service, 25.1-40'Length,Asphalt Paving Fifty eight hundred Dollars No Cents $5,800.00 $29,000.00 ® 16 3312.2103 33 12 10 2 EA 1.5-inch Water Service, 25.1'-40'Length,Concrete Paving Sixty three hundred Dollars No Cents $6.300.00 $12,600.00 *� 17 3312.2203 33 12 10 5 EA 2-inch Water Service, 0'-10'Length,No Paving Four thousand Dollars No Cents $4,000.00 $20,000.00 18 3312.2203 33 12 10 5 EA 2-inch Water Service, 0'-10'Length,Asphalt Paving Forty two hundred Dollars ear Cents $4,200.00 $21,000.00 19 3312.2203 33 12 10 2 EA 2-inch Water Service, 0'-10'Length,Concrete Paving Forty four hundred Dollars w No Cents $4,400.00 $8,800.00 20 3312.2203 33 12 10 5 EA 2-inch Water Service, 10.1'-25'Length,No Paving Fourtv three hundred Dollars No Cents $4,300.00 $21500.00 M!R ,rel CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Farm Re fined 20120120 City PmieG Na.10088Q 00 42 43 BID PROPOSAL Page 3.1`5 SECTION 00 42 43 PROPOSAL FORM UNIT PRICE BID Bidder's Application Project Item Information Bidders Proposal Pay Item Bid List Item Specification Bid Quantity Unit of Description Unit Price Bid Value No. Section No. Measurement 21 3312.2203 33 12 10 5 EA 2-inch Water Service, 10.1'-25'Length,Asphalt Paving Five thousand Dollars Cents $5,000.00 $25000.00 22 3312.2203 33 12 10 2 EA 2-inch Water Service, 10.1'-25'Length,Concrete Paving Fifty three hundred Dollars No Cents $5,300.00 $10,600.00 23 3312.2203 33 12 10 5 EA 2-inch Water Service, 25.1-40'Length,Asphalt Paving Fifty eight hundred Dollars No Cents $5,800.00 $29,000.00 24 3312.2203 33 12 10 2 EA 2-inch Water Service, 25.1'-40'Length,Concrete Paving Sixty three hundred Dollars No Cents $630000 $12,600.00 25 3311.0161 33 11 12 100 LF 6-inch PVC Water Pipe Fifty Dollars No Cents $50.00 $5,000.00 «� 26 3311.0151 3311 10 100 LF 6-inch DIP Water Sixty five Dollars No Cents $65.00 $6,500.00 27 3311.0261 33 11 12 100 LF 8-inch PVC Water Pipe Fifty five Dollars ® No Cents $55.00 $5,500.00 28 3311.0251 3311 10 100 LF 8-inch DIP Water Eighty five r+ No Cents $85.00 $8,500.00 29 3311.0361 33 11 12 100 LF 10-inch PVC Water Pipe Sixty five Dollars No Cents $65.00 $6,500.00 30 3311.0351 3311 10 100 LF 10-inch DIP Water Ninety Dollars No Cents $90.00 $9,000.00 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUNIEN[S REPLACEIETIT CONTRACT I—R-id 20120120 City Pcojw No.100889 DO 42 43 BID PROPOSAL. Pegs 4 d 5 SECTION 00 42 43 PROPOSALFORM UNIT PRICE BID Bidder's Application Project Item Information Bidder's Proposal Bid List Item Specification Unit of Pay Item No. Section No. Bid Quantity Measurement Description Unit Price Bid Value 31 3311.0461 33 11 12 100 LF 12-inch PVC Water Pipe Ninety Dollars No Cents $90.00 $9,000.00 32 3311.0451 3311 10 100 LF 12-inch DIP Water Ninety Five Dollars No Cents $95.00 $9,500.00 33 33 12 10 100 LF 3/4-inch Private Water Service, Relocation Thirty Dollars No Cents $30.00 $3,000.00 34 3312.2004 33 12 10 100 LF 1-inch Private Water Service, Relocation Forty Dollars No Cents $40.00 $4,000.00 35 3312.2104 33 12 10 20 LF 1.5-inch Private Water Service, Relocation Forty Five Dollars No Cents $45.00 $900.00 36 3312.2204 33 1210 20 LF 2-inch Private Water Service, Relocation Fifty Dollars No Cents $50.00 $1000.00 37 3305.0203 33 05 10 10 CY Imported Embedment/Backfill CLSM One Hundred Dollars �. No Cents $100.00 $1000.00 38 3201.0112 3201 17 300 LF 5-foot Wide Asphalt Pavement Repair,Residential sixty No Cents $60.00 $18,000.00 39 3201.0132 3201 17 150 LF 5-foot Wide Asphalt Pavement Repair,Industrial Sixty Five Dollars ... No Cents $65.00 $9,750.00 40 3201.0614 3201 29 150 Sy Concrete Pavement Repair, Residential Seventy Dollars No Cents $70.00 $10,500.00 m.. CITY OF FORTWORTH Mil WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEN ENT CONTRACT' I—Rmw 20120120 City Prim No.100889 00 42 4; BID PROPOSAL R8e 5 of S SECTION 00 42 43 PROPOSAL FORM UNIT PRICE BID Bidder's Application Project Item Information Bidders Proposal Pay Item Bid List Item Specification Bid Quantity Unit of Description Unit Price Bid Value No. Section No. Measurement 41 3201.0616 3201 29 75 SY Concrete Pavement Repair, Arterial/Industrial Eiahty five Dollars No Cents $85.00 $6,375.00 42 3201.0302 3201 17 250 SY 3-inch Extra Width Asphalt Pavement Repair Thirty Dollars No Cents $30.00 $7,500.00 43 3216.0101 3216 13 50 LF 6-inch Concrete Curb and Gutter, Replacement Forty Five Dollars No Cents $45.00 $2,250.00 44 3213.0301 32 13 20 75 SF 4-inch Concrete Sidewalk, Replacement Ten Dollars No Cents $10.00 $750.00 45 3213.0401 32 13 20 75 SF 6-inch Concrete Driveway, Replacement Fifteen Dollars Cents $15.00 $1125.00 46 3471.0003 3471 13 30 EA Traffic Control,Residential Four Hundred Dollars No Cents $400.00 $12,000.00 47 3471.0003 3471 13 10 EA Traffic Control,Arterial/Industrial One Thousand Dollars No Cents $1.000.00 $10,000.00 48 3471.0003 3471 13 10 EA Traffic Control,Major Arterial/Industrial Twelve Hundred _ _Doliars No Cents $1,200.00 $12,000.00 49 50 EA Street Use Permit One Hundred Dollars No Cents $100.00 $5000.00 Total Bid $823,850.00 END OF SEMON CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT F—Revised 20120120 City Iiojw No.100889 Endurance Endurance American Insurance Company Bid Bond Know all men by these presents: That we, the undersigned Tejas Commercial Construction LLC ,as Principal(hereinafter the"Principal"), and Endurance American Insurance Company 750 Third Avenue,2nd Floor,New York, NY 10017, a Delaware corporation (hereinafter the "Surety"), are held and firmly bound unto City of Fort Worth (hereinafter the"Obligee")in the penal sum of Five Percent or Two Hundred Forty Thousand Max , $ for the payment of which sum the Principal and Surety bind themselves, their heirs, executors, administrators,successors and assigns,jointly and severally,as provided herein. Whereas, the Principal has submitted a bid for • Fort Worth-2017 Water Lead Services Replacement Contract,City project no. 100889 me Now,therefore,if the Obligee shall accept the bid of the Principal and the Principal shall enter into a contract with the.Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or contract documents with good and sufficient surety for the faithful performance of such contract and for the prompt "" payment of labor and materials furnished in prosecution thereof,or in the event of the failure of the Principal to enter into such contract and give such bond or bonds,if the Principal shall pay to the Obligee the difference, not to exceed the penalty hereof between the amount specified in said bid and such larger amount for which the Obligee may reasonably contract with another party to perform the work covered by said bid,then this obligation shall be null and void,otherwise to remain in full force and effect.The liability of the Surety hereunder shall in no event exceed the lesser of:(a)the penalty hereof,or (b) the difference between the amount specified in the Principal's bid and any larger amount for which the Obligee reasonably contracts with another party to perform the work specified in the Principal's bid. Signed and sealed this 7--7 day of A4---i — 29/Z . \� rim* CORP, Principal:Tejas Commercial Construction LLC �' ? 41110 By: ®. rn:C;= Name&Title:Charles Allen,Vice President �. (SEAL) `�"';d• •.� ,-, '7��` ��'�s,�` 2009• ���`��� Surety: Endurraayncee Americ/a'�/nl Insurance Company Name:Chris Holt,Attorney in Fact (Attorney-in-Fact) Endurance American Insurance Comoanv Page 1 of 1 SUR 0205 0716 Policyholder Notice TEXAS-IMPORTANT NOTICE AVISO IMPORTANTE To obtain information or make a complaint: Para obtener informacion o para someter una ® You may call the company's telephone number for queja: information or to make a complaint at: Usted puede Ilamar al numero de telefono de la compania para information o para someter una queja al: 1-877-676-7575 1-877-676-7575 You may write the Company at: Usted tambien puede escribir a: Endurance American Insurance Company Endurance American Insurance Company Attention:Surety Attention:Surety 750 Third Avenue 750 Third Avenue New York,NY 10017 New York, NY 10017 You may contact the Texas Department of Puede communicarse con el Departamento de Insurance to obtain information on companies, Seguros de Texas para obtener informacion acerca coverages, rights or complaints at: de companias,coberturas,derechos o quejas al: 1-800-252-3439 1-800-252-3439 You may write the Puede escribir al Texas Department of Insurance Departamento de Seguros de Texas PO Box 149104 PO Box 149104 Austin,TX 78714-9104 Austin,TX 78714-9104 FAX#(512)490-1007 FAX#(512)475-1771 Web: http://www.tdi.texas.goy Web: http://www.tdi.texas.gov E-mail:Con sumerProtection@tdi.texas.gov E-mail:ConsumerProtection@tdi.texas.gov PREMIUM OR CLAIM DISPUTES: Should you have a DISPUTAS SOBRE PRIMAS O RECLAMOS: Si tiene .� dispute concerning your premium or about a claim una disputa concerniente a su prima o a un you should contact the company first. If the dispute reclamo,debe comunicarse con la compania is not resolved,you may contact the Texas primero. Si no se resuelve la disputa, puede Department of Insurance. entonces comunicarse con el departamento(TDI). ATTACH THIS NOTICE TO YOUR POLICY: This notice UNA ESTE AVISO A SU POLIZA: Este aviso es solo is for information only and does not become a part para proposito de informacion y no se convierte en or condition of the attached document. parte o condicion del documento adjunto. ENDURANCE AMERICAN INSURANCE COMPANY POA1000005456 127 POWER OF ATTORNEY xnow ad9Ken 6't(rese(Present, that ENDURANCE AMERICAN INSURANCE COMPANY,a Delaware corporation(the"Corporabon0,with offices at 750 Third Avenue, New York,NY 10017,has made,constituted and appointed and by these presents,does make,constitute and appoint CHRIS L.HOLT,JOE RODNEY DUCKWORTH its true and lawful Attomey(s)An•fact,at AMARILLO in the State of TX and each of them to have full power to act without the other or others,to make,execute,seal and deliver for and on its behalf bonds,undertakings or obligations in surety or cosurety with others,also to execute and deliver on its behalf renewals,extensions,agreements,waivers,consents or stipulations relating to such aforesaid bonds,undertakings or obligations provided,however,that no single bond or undertaking so made,executed and delivered shall obligate the Corporation for any{lprtiortof the penal sum thereof in excess of the sum of TEN MILLION Dollars($10,000,000). Such bonds and pp�erFalIngs for purposes,when duly executed by said attomey(syin-fad,shall be binding upon the Corporation as fully and to the same extent as if signed by the Presltferi4 of ie W_Pp;itibn ur [i(S corporate seal attested by its Corporate Secretary. This e�OHitrrle >5 made under' by 8uti ity of certain resolutions adopted by the Board of Directors of the Corporation by unanimous written consent on the 21st day of July,2011 a Eppy of coli XPi appears below u r theAking entitled"Certificate". This Power of Attorney is* d and sealed 6yiacsimile under and by authority of the following resolution adopted by the Board of Directors of the Corporation by unanimous written coassiff an the 21st dey Of 1 y,2011 and said resolution has not since been revoked,amended or repealed: RESOLVED,that in granting powels of a1*4 pursuant to certain resolutions adopted by the Board of Directors of the Corporation by unanimous written consent onthe 21st day of �r July,2wt"'Q 9r- e of suchtfi6tlor rdotficers and the seal of the Corporation may be affixed to any such power of attorney or any certificate relating thereto by facsimile and any sudtpower o Otto qr ceitific bearing such facsimile signature or seal shall be valid and binding upon the Corporation in the future with respell to any bond or undertaking to which it attaid This Power of Xftbmey,g Wgexpire and all authority hereunder shall terminate without notice at 12:01 a.m.(Standard Time where said attomey(s)An-fact is authorized to act) December 7,2019 ■m IN WITNESS WHEREOF,the Corporation has caused these presents to be duly signed and its corporate seal to be hereunto affixed and attested this2nd day of November,2016 at New York,New York. (Corporate Seal) ENDURANCE AMERICAN INSURANCE COMPANY ATTESTBy � RICHARD M.APPEL,SENIOR VICE PRESIDENT BRIAN BEGGS,EXECUTIVE VICE PRESIDENT STATE OF NEW YORK ss:MANHATTAN COUNTY OF NEW YORK a On the 2nd day ofVovftber,20J6 before me personally came BRIAN BEGGS to me known,who being by me duly swom,did depose and say that(s)he resides in NEW YORK,NEW YORK that,(s)re is aEXEWC A E Vlf;rPRESIDENT of ENDURANCE AMERICAN INSURANCE COMPANY,the Corporation described in and which executed the above instrument that(s)he�knothe seal of said ration;that the seal affixed to said instrument is such corporate seal;that it was so affixed by order of the Board of Directors of said Corporation, and that(s)Iigrrer "( t°4y like order. rr (Notarial }' -T� f Nicholas James Benena5,Notary Public-My Commission Expires 12/07/2019 ,.r- CERTIFICATE STATE OF OwxdRl('• ' ss:MANHATTAN COUNTY 65*12%T sTE73 f,CHRISTOPHE9 SPARRO the'PRESIDENT of ENDURANCE AMERICAN INSURANCE COMPANY,a Delaware Corporation(the"Corporation!,hereby certify: 1.That the original power of attomey of which the foregoing is a copy was duly executed on behalf of the Corporation and has not since been revoked amended or modified;that the undersigned has compared the foregoing copy thereof with the original power of attorney,and that the same is a true and coned copy of the original power of attorney and of the whole thereof; 2. The following are resolutions which were adopted by the Board of Directors of the Corporation by unanimous written consent on 21st day of July,2011 and said resolutions have not since been revoked,amended or modified: "RESOLVED,that each of the individuals named below is authorized to make,execute,seal and deliver for and on behalf of the Corporation any and all bonds,undertakings or obligations in surety or cosurety with others and to execute and deliver for and on behalf of the Corporation renewals,extensions,agreements,waivers,consents or stipulations relating to such aforesaid bonds,undertakings or obligations: RICHARD M.APPEL,BRIAN BEGGS And be it further RESOLVE// ech d 9Ye mov'duals named above is authorized to appoint attorneys in•fact for the purpose of making,executing,sealing and delivering bonds,undertakings or obliga6dn.W'surety Ar ca:surety for andori.behalf of the Corporation.' 3. The uriderskrhed further certifie0at t' a'iove resolutions are We and correct copies of the resolutions as so recorded and of the whole thereof NR IN 40ESS WHEF0F,I hive hereunto set my hand and affixed the corporate seal this day of 20 ;,. r In w (Corporate Seal) x / L>r CHRISTOPHER SPARRO,PRESIDENT `;,:;;,:t�•` Any reproductions are void. Primary Surety Gaims Submission:suretybonddelms@eWuranceservices.com • Surety Gaims Hotline:877!767575 Mailing Address:Endurance Surety Claims Department,750 Third Avenue—10th Fbor,New York,NY 10017 00 43 37 VENDOR COMPLIANCE TO STATE LAW Page 1 of 1 SECTION 00 43 37 VENDOR COMPLIANCE TO STATE LAW NON RESIDENT BIDDER Texas Government Code Chapter 2252 was adopted for the award of contracts to nonresident bidders. This law provides that, in order to be awarded a contract as low bidder, nonresident bidders (out-of-state contractors whose corporate offices or principal place of business are outside the State of Texas) bid projects for construction, improvements, supplies or services in Texas at an amount lower than the lowest Texas resident bidder by the same amount that a Texas resident bidder would be required to underbid a nonresident bidder in order to obtain a comparable contract in the State which the nonresident's principal place of business is located. The appropriate blanks in Section A must be filled out by all nonresident bidders in order for your bid to meet specifications. The failure of nonresident bidders to do so will automatically disqualify that bidder. Resident bidders must check the box in Section B. A. Nonresident bidders in the State of , our principal place of business, ` are required to be percent lower than resident bidders by State Law. A copy of the statute is attached. Nonresident bidders in the State of , our principal place of business, are not required to underbid resident bidders. B. The principal place of business of our company or our parent company or majority owner is in the State of Texas. P-1 BIDDER: Tejas Commercial Construction, LLC By: Charles D. Allen P.O. Box 10395 0 (Signature) River Oaks, TX 76114 Title: Vice President Date: �i �i 7 END OF SECTION CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Form Revised 20110627 City Project No.100889 i4 004511-1 BIDDERS PREQUALIFICATIONS Page 1 of 3 1 SECTION 00 4511 n 2 BIDDERS PREQUALIFICATIONS 3 4 1. Summary.All contractors are required to be prequalified by the City prior to submitting 5 bids.To be eligible to bid the contractor must submit Section 00 45 12,Prequalification 6 Statement for the work type(s)listed with their Bid.Any contractor or subcontractor who is 7 not prequalified for the work type(s) listed must submit Section 00 45 13,Bidder 8 Prequalification Application in accordance with the requirements below. 9 10 The prequalification process will establish a bid limit based on a technical evaluation and 11 financial analysis of the contractor.The information must be submitted seven(7)days prior 12 to the date of the opening of bids.For example,a contractor wishing to submit bids on 13 projects to be opened on the 7th of April must file the information by the 31st day of March 14 in order to bid on these projects.In order to expedite and facilitate the approval of a Bidder's 15 Prequalification Application,the following must accompany the submission. 16 a. A complete set of audited or reviewed financial statements. 17 (1) Classified Balance Sheet 18 (2) Income Statement 19 (3) Statement of Cash Flows 20 (4) Statement of Retained Earnings 21 (5) Notes to the Financial Statements, if any 22 b. A certified copy of the firm's organizational documents(Corporate Charter,Articles 23 of Incorporation,Articles of Organization,Certificate of Formation,LLC 24 Regulations,Certificate of Limited Partnership Agreement). 25 c. A completed Bidder Prequalification Application. 26 (1) The firm's Texas Taxpayer Identification Number as issued by the Texas 27 Comptroller of Public Accounts.To obtain a Texas Taxpayer Identification 28 number visit the Texas Comptroller of Public Accounts online at the 29 following web address www.window.state.tx.us/taxpermit/and fill out the 30 application to apply for your Texas tax ID. 31 (2) The firm's e-mail address and fax number. 32 (3) The firm's DUNS number as issued by Dun&Bradstreet.This number 33 is used by the City for required reporting on Federal Aid projects. The DUNS 34 number may be obtained at www.dnb.com. 35 d. Resumes reflecting the construction experience of the principles of the firm for firms 36 submitting their initial prequalification.These resumes should include the size and 37 scope of the work performed. 38 e. Other information as requested by the City. 39 40 2. Prequalification Requirements 41 a. Financial Statements.Financial statement submission must be provided in 42. accordance with the following: 43 (1) The City requires that the original Financial Statement or a certified copy 44 be submitted for consideration. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 004511-2 BIDDERS PREQUALIFICATIONS Page 2 of 3 1 (2) To be satisfactory,the financial statements must be audited or reviewed 2 by an independent,certified public accounting firm registered and in 3 good standing in any state.Current Texas statues also require that 4 accounting firms performing audits or reviews on business entities within 5 the State of Texas be properly licensed or registered with the Texas State 6 Board of Public Accountancy. 7 (3) The accounting firm should state in the audit report or review whether 8 the contractor is an individual,corporation,or limited liability company. 9 (4) Financial Statements must be presented in U.S. dollars at the current rate 10 of exchange of the Balance Sheet date. 11 (5) The City will not recognize any certified public accountant as 12 independent who is not,in fact,independent. 13 (6) The accountant's opinion on the financial statements of the contracting 14 company should state that the audit or review has been conducted in 15 accordance with auditing standards generally accepted in the United 16 States of America.This must be stated in the accounting firm's opinion. 17 It should:(1)express an unqualified opinion,or(2)express a qualified 18 opinion on the statements taken as a whole. �.. 19 (7) The City reserves the right to require a new statement at any time. 20 (8) The financial statement must be prepared as of the last day of any month, 21 not more than one year old and must be on file with the City 16 months 22 thereafter,in accordance with Paragraph 1. 23 (9) The City will determine a contractor's bidding capacity for the purposes 24 of awarding contracts.Bidding capacity is determined by multiplying the 25 positive net working capital(working capital=current assets—current 26 liabilities)by a factor of 10.Only those statements reflecting a positive 27 net working capital position will be considered satisfactory for 28 prequalification purposes. 29 (1.0) In the case that a bidding date falls within the time a new financial 30 statement is being prepared,the previous statement shall be updated with 31 proper verification. �- 32 b. Bidder Prequalification Application. A Bidder Prequalification Application must be 33 submitted along with audited or reviewed financial statements by firms wishing to be 34 eligible to bid on all classes of construction and maintenance projects.Incomplete 35 Applications will be rejected. 36 (1) In those schedules where there is nothing to report,the notation of 37 "None"or"N/A"should be inserted. 38 (2) A minimum of five(5)references of related work must be provided. .� 39 (3) Submission of an equipment schedule which indicates equipment under 40 the control of the Contractor and which is related to the type of work for 41 which the Contactor is seeking prequalification. The schedule must 42 include the manufacturer,model and general common description of 43 each piece of equipment.Abbreviations or means of describing 44 equipment other than provided above will not be accepted. 45 46 3. Eligibility to Bid 47 a. The City shall be the sole judge as to a contractor's prequalification. 48 b. The City may reject,suspend,or modify any prequalification for failure by the 49 contractor to demonstrate acceptable financial ability or performance. 50 c. The City will issue a letter as to the status of the prequalification approval. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 004511-3 BIDDERS PREQUALIFICATIONS Page 3 of 3 1 d. If a contractor has a valid prequalification letter,the contractor will be eligible to bid .,r 2 the prequalified work types until the expiration date stated in the letter. 3 4 �. 5 6 7 8 END OF SECTION 9 ws .w 4m OR w CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No. 100889 00 45 12 BID FORM Page 1 of 1 SECTION 00 4512 PREQUALIFICATION STATEMENT Each Bidder for a City procurement is required to complete the information below by identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed. Major Work Type Contractor/Subcontractor Company Name Prequalification Expiration Date Water Improvements- Replacement of 1-inch through Tejas Commercial Construction, LLC 4/30/2017 2-inch Lead Water Services List work type here or space oma p�tam0,Oro_ space f�aie Herer space List work type here or spaceamp�Inr Narrfe Here o spae Date:Here or space List work type here or space r ofnpan' Name Here or,space'' Date=Here s r rec f The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are currently prequalified for the work types listed. BIDDER: Tejas Commercial Construction, LLC By: Charles D. Allen P.O. Box 10395 0 (Signature) River Oaks, TX 76114 Title: Vice President Date: -3 h" ��7 END OF SECTION CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Form Revised 20120120 City Project No.100889 FORTWORTH r SECTION 00 45 13 BIDDER PREQUALIFICATION APPLICATION Date of Balance Sheet Mark only one: Individual Limited Partnership NamGeneral Partnershipe under which you wish to qualify ' Corporation Limited Liability Company Post Office Box City State Zip Code Street Address(required) City State Zip Code Telephone Fax Email Texas Taxpayer Identification No. Federal Employers Identification No. w DUNS No. (if applicable) MAIL THIS QUESTIONAIRE ALONG WITH.FINANCIAL STATEMENTS TO: CITY OF FORT WORTH TEXAS 1000 THROCKMORTON STREET FORT WORTH,TEXAS 76102-6311 AND MARK THE ENVELOPE: "BIDDER PREQUALIFICATION APPLICATION" 004513-2 BIDDER PREQUALIFICATION APPLICATION _ Page 2 of 8 BUSINESS CLASSIFICATION The following should be completed in order that we may properly classify your firm: (Check the block(s)which are applicable—Block 3 is to be left blank if Block 1 and/or Block 2 is checked) Has fewer than 100 employees and/or Has less than$6,000,000.00 in annual gross receipts OR Does not meet the criteria for being designated a small business as provided in Section 2006.001 of the Texas Government Code. The classification of your firm as a small or large business is not a factor in determining eligibility to become prequalified. �- MAJOR WORK CATEGORIES Water Department Augur Boring-24-inch diameter casing and less Augur Boring-Greater than 24-inch diameter casing and greater Tunneling—36-Inches—60—inches,and 350 LF or less Tunneling-36-Inches—60—inches,and greater than 350 LF Tunneling—66"and greater,350 LF and greater Tunneling—66"and greater,350 LF or Less Cathodic Protection Water Distribution,Development, 8-inch diameter and smaller Water Distribution,Urban and Renewal, 8-inch diameter and smaller Water Distribution,Development, 12-inch diameter and smaller Water Distribution,Urban and Renewal, 12-inch diameter and smaller Water Transmission,Development,24-inches and smaller Water Transmission,Urban/Renewal,24-inches and smaller Water Transmission,Development,42-inches and smaller Water Transmission,Urban/Renewal,42-inches and smaller Water Transmission,Development,All Sizes Water Transmission,Urban/Renewal,All Sizes Sewer Bypass Pumping, 18-inches and smaller Sewer Bypass Pumping, l 8-inches—36-inches Sewer Bypass Pumping 42-inches and larger CCTV, 8-inches and smaller CCTV, 12-inches and smaller CCTV, 18-inches and smaller CCTV,24-inches and smaller CCTV,42-inches and smaller CCTV,48-inches and smaller CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,201.2 CityProject No. 100889 0045 13-3 BIDDER PREQUALIFICATION APPLICATION Page 3 of 8 MAJOR WORK CATEGORIES,CONTINUED Sewer CIDP, 12-inches and smaller Sewer CIDP,24-inches and smaller Sewer CIDP,42-inches and smaller Sewer CIDP,All Sizes Sewer Collection System,Development, 8-inches and smaller Sewer Collection System,Urban/Renewal, 8-inches and smaller Sewer Collection System,Development, 12-inches and smaller Sewer Collection System,Urban/Renewal, 12-inches and smaller Sewer Interceptors, Development,24-inches and smaller Sewer Interceptors, Urban/Renewal,24-inches and smaller Sewer Interceptors, Development,42-inches and smaller Sewer Interceptors, Urban/Renewal,42-inches and smaller Sewer Interceptors, Development,48-inches and smaller Sewer Interceptors, Urban/Renewal,48-inches and smaller Sewer Pipe Enlargement 12-inches and smaller Sewer Pipe Enlargement 24-inches and smaller Sewer Pipe Enlargement,All Sizes Sewer Cleaning,24-inches and smaller Sewer Cleaning,42-inches and smaller Sewer Cleaning,All Sizes Sewer Cleaning, 8-inches and smaller Sewer Cleaning, 12-inches and smaller Sewer Siphons 12-inches or less Sewer Siphons 24-inches or less Sewer Siphons 42-inches or less Sewer Siphons All Sizes Transportation Public Works Asphalt Paving Construction/Reconstruction(LESS THAN 15,000 square yards) Asphalt Paving Construction/Reconstruction(15,000 square yards and GREATER) Asphalt Paving Heavy Maintenance(UNDER$1,000,000) Asphalt Paving Heavy Maintenance($1,000,000 and OVER) Concrete Paving Construction/Reconstruction(LESS THAN 15,000 square yards) Concrete Paving Construction/Reconstruction(15,000 square yards and GREATER) Roadway and Pedestrian Lighting CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 004513-4 BIDDER PREQUALIFICATION APPLICATION Page 4 of 8 1. List equipment you do not own but which is available by renting DESCRIPTION OF EQUIPMENT NAME AND DETAILED ADDRESS OF OWNER �- 2. How many years has your organization been in business as a general contractor under your present name? List previous business names: 3. How many years of experience in construction work has your organization had: (a) As a General Contractor: (b)As a Sub-Contractor: 4. *What projects has your organization completed in Texas and elsewhere? CLASS LOCATION NAME AND DETAILED CONTRACT OF DATE CITY-COUNTY- ADDRESS OF OFFICIAL TO AMOUNT WORK COMPLETED STATE WHOM YOU REFER *If requalifying only show work performed since last statement.. 5.Have you ever failed to complete any work awarded to you? If so,where and why? 6.Has any officer or owner of your organization ever been an officer of another organization that failed to complete a contract? If so, state the name of the individual,other organization and reason. e 7.Has any officer or owner of your organization ever failed to complete a contract executed in his/her name? If so,state the name of the individual,name of owner and reason. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT e Revised December 20,2012. City Project No.100889 004513-5 BIDDER PREQUALIFICATION APPLICATION Page 5 of 8 8. In what other lines of business are you financially interested? 9. Have you ever performed any work for the City?. If so,when and to whom do you refer? 10. State names and detailed addresses of all producers from whom you have purchased principal ® materials during the last three years. NAME OF FIRM OR COMPANY DETAILED ADDRESS 11. Give the names of any affiliates or relatives currently debarred by the City. Indicate your relationship to this person or firm. 12. What is the construction experience of the principal individuals in your organization? PRESENT MAGNITUDE POSITION OR YEARS OF AND TYPE OF IN WHAT NAME OFFICE EXPERIENCE WORK CAPACITY 13. If any owner, officer, director,or stockholder of your firm.is an employee of the City,or shares the same household with a City employee,please list the name of the City employee and the relationship.In addition, list any City employee who is the spouse, child,or parent of an owner, officer,stockholder,or director who does not live in the same household but who receives care and assistance from that person as a direct result of a documented medical condition.This includes foster children or those related by i adoption or marriage. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0045 13-6 BIDDER PREQUALIFICATION APPLICATION Page 6 of 8 ^° CORPORATION BLOCK PARTNERSHIP BLOCK If a corporation: If a partnership: Date of Incorporation State of Organization Charter/File No. Date of organization President Is partnership general, limited,or registered limited liability partnership? Vice Presidents File No. (if Limited Partnership) General Partners/Officers Secretary Limited Partners(if applicable) Treasurer LIMITED LIABILITY COMPANY BLOCK If a corporation: State of Incorporation Date of organization File No. Individuals authorized to sign for Partnership Officers or Managers(with titles,if any) Except for limited partners,the individuals listed in the blocks above are presumed to have full signature authority for your firm unless otherwise advised.Should you wish to grant signature authority for additional individuals,please attach a certified copy of the corporate resolution, corporate minutes,partnership agreement,power of attorney or other legal documentation which grants this authority. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 004513-7 BIDDER PREQUALIFICATION APPLICATION Page 7 of 8 14. Equipment $ TOTAL BALANCESHEET ITEM QUANTITY ITEM.DESCRIPTION VALUE » 1 2 3 4 5 6 .� 7 8 9 10 11 12 13 14 15 16 17 18 19 ^� 20 21 22 23 24 25 26 27 28 29 30 Various- TOTAL Similar types of equipment may be lumped together.If your firm has more than 30 types of equipment, you may show these 30 types and show the remainder as "various".The City,by allowing you to show only 30 types of equipment,reserves the right to request a complete,detailed list of all your equipment. The equipment list is a representation of equipment under the control of the firm and which is related to the type of work for which the firm is seeking qualification.In the description include,the manufacturer, model,and general common description of each. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 004513-8 BIDDER PREQUALIFICATION APPLICATION Page 8 of 8 BIDDER PREQUALIFICATION AFFIDAVIT STATE OF COUNTY OF The undersigned hereby declares that the foregoing is a true statement of the financial condition of the entity herein first named, as of the date herein first given; that this statement is for the express purpose of inducing the party to whom it is submitted to award the submitter a contract; and that the accountant who prepared the balance sheet accompanying this report as well as any depository, vendor or any other _ agency herein named is hereby authorized to supply each party with any information,while this statement is in force,necessary to verify said statement. being duly sworn, deposes and says that he/she is the of the entity described in and which executed the foregoing statement that he/she is familiar with the books of the said entity showing its financial condition; that the foregoing financial statement taken from the books of the said entity as of the date thereof and that the answers to the questions of the foregoing Bidder Prequalification Application are correct and true as of the date of this affidavit. Firm Name: Signature: _ Sworn to before me this day of Notary Public A Notary Public must not be an officer,director,or stockholder or relative thereof. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 l 004326-1 Z CONTRACTOR COMPLIANCE WITH WORKER'S C7A&ENSATIONIAW Page i bel:: 1 SECTION 00 45 26 n 2 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW j l 4 Pursuant to Texas Labor Code Section 406.096(a),as amended,Contractor certifies that it 5 provides worker's compensation insurance coverage for all of its employees employed:on City t 6 Project No.100889.Contractor further certifies that,pursuant to Texas Labor Code,Section . . 7 406.096(b);as amended,it will provide to City its subcontractor's certificates of compliance with 8 worker's compensation coverage. 9 10 CONTRACTOR: 11 12 77"4-'a_5 z!�Le By.- 13 y;13 Company (Please Print) 14 Si 15 re4�4 z Y� � 3 �X /��gs � ? 16 Address 17 18 e �— �S� i X 74� Title: Vi c c-- P,-t,cf—4- 19 City/State/Zip (Please Print) 20 21. i 22 THE STATE OF TEXAS § 23 y ' 24 COUNTY OF TARRANT § 25 26 BEFORE ME,the undersigned authority;on this day personally appeared 27 11w k� b. +4�.1 ,known to me to be the person whose name is 28 subscribed to the foregoing instrument and acknowledged to me that he/she executed the same as 29 the act and deed of" rte C ..K, :.„ -r_ 4e-e_ for the purposes and 30 consideration therein expressed and in the capacity therein stated. 31 32 QrYEN UNDER MY HAND AND SEAL OF OFFICE this J,3 _day of 33 20/. 34 35 36 :,qKATHY GREGORY 37 MY COMMISyS�IOyN� EXPIRES Nota, Public ' an for the S. to of xas J*23,20�8 38 39 END OF SECTION A 40 AW c N; CITY OF FORT WORTH 2017 WATER LtAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 Cit. Project No.100889 004540-1 Minority Business Enterprise Specifications Page 1 of 2 1 SECTION 00 45 40 2 Minority Business Enterprise Specifications 3 .. 4 APPLICATION OF POLICY 5 If the total dollar value of the contract is greater than $50,000, then a MBE subcontracting goal is 6 applicable. 7 8 POLICY STATEMENT 9 It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minority 10 Business Enterprises (MBE) in the procurement of all goods and services. All requirements and 11 regulations stated in the City's current Business Diversity Enterprise Ordinance apply to this bid. 12 13 MBE PROJECT GOALS 14 The City's MBE goal on this project is 7% of the total bid value of the contract (Base bid applies to 15 Parks and Community Services). 16 17 Note: If both MBE and SBE subcontracting goals are established for this project, then an Offeror 18 must submit both a MBE Utilization Form and a SBE Utilization Form to be deemed responsive. 19 20 COMPLIANCE TO BID SPECIFICATIONS 21 On City contracts $50,000 or more where a MBE subcontracting goal is applied, Offerors are required to 22 comply with the intent of the City's Business Diversity Enterprise Ordinance by one of the following: 23 1. Meet or exceed the above stated MBE goal through MBE subcontracting participation,or 24 2. Meet or exceed the above stated MBE goal through MBE Joint Venture participation,or 25 3. Good Faith Effort documentation,or; 26 4. Prime Waiver documentation. 27 28 SUBMITTAL OF REQUIRED DOCUMENTATION 29 The applicable documents must be received by the Purchasing Division, within the following times 30 allocated, in order for the entire bid to be considered responsive to the specifications. The Offeror shall 31 deliver BE the Mdocumentation in person to the appropriate employee of the purchasing division and 32 obtain a date/time receipt. Such receipt shall be evidence that the City received the documentation in the 33 time allocated. A faxed and/or emailed copy will not be accepted. 34 1. Subcontractor Utilization Form, if received no later than 2:00 p.m., on the second City business goal is met or exceeded: day after the bid opening date, exclusive of the bid opening date. 2. Good Faith Effort and received no later than 2:00 p.m., on the second City business _ Subcontractor Utilization Form, if day after the bid opening date, exclusive of the bid opening participation is less than statedgoal: date. 3. Good Faith Effort and received no later than 2:00 p.m., on the second City business Subcontractor Utilization Form, if no day after the bid opening date, exclusive of the bid opening MBE participation: date. 4. Prime Contractor Waiver Form, received no later than 2:00 p.m., on the second City business if you will perform all day after the bid opening date, exclusive of the bid opening AW contracting/supplier work: date. 35 CITY OF FORT WORTH 2OI7 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised June 9,2015 City Project No. 100889 004540-2 Minority Business Enterprise Specifications Page 2 of 2 1 _ 5. Joint Venture Form, if goal is met received no later than 2:00 p.m., on the second City business or exceeded. day after the bid opening date, exclusive of the bid opening date. .. 2 FAILURE TO COMPLY WITH THE CITY'S BUSINESS DIVERSITY ENTERPRISE ORDINANCE 3 WILL RESULT IN THE BID BEING CONSIDERED NON-RESONSIVE TO SPECIFICATIONS. 4 FAILURE TO SUBMIT THE REQUIRED MBE DOCUMENTATION WILL RESULT IN THE BID .. BEING CONSIDERED NON-RESPONSIVE.A SECOND FAILURE WILL RESULT IN THE OFFEROR 5 BEING DISQUALIFIED FOR A PERIOD OF ONE YEAR.THREE FAILURES IN A FIVE YEAR PERIOD WILL RESULT IN A DISQUALIFICAITON PERIOD OF THREE YEARS. 6 7 Any Questions,Please Contact The M/WBE Office at(817)212-2674. 8 END OF SECTION 9 10 11 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised June 9,2015 City Project No.100889 w 005243-1 Agreement Page 1 of 5 1 SECTION 00 52 43 2 AGREEMENT 3 4 THIS AGREEMENT, authorized on May 2, 2017is made by and between the City of Forth 5 Worth, a Texas home rule municipality, acting by and through its duly authorized City Manager, 6 ("City"), and Teias Commercial Construction, LLC, authorized to do business in Texas, acting 7 by and through its duly authorized representative, ("Contractor"). 8 City and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as 9 follows: 10 Article 1.WORK 11 Contractor shall complete all Work as specified or indicated in the Contract Documents for the 12 Project identified herein. 13 Article 2.PROJECT 14 The project for which the Work under the Contract Documents may be the whole or only a part is 15 generally described as follows: 16 2017 WATER LEAD SERVICES REPLACEMENT CONTRACT 17 CITY PROJECT NO. 100889 18 Article 3. CONTRACT TIME 19 3.1 Time is of the essence. 20 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract 21 Documents are of the essence to this Contract. 22 3.2 Final Acceptance. 23 The Work will be complete for Final Acceptance within 365 days after the date when the 24 Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions. 25 3.3 Liquidated damages 26 Contractor recognizes that time is of the essence of this Agreement and that City will 27 suffer financial loss if the Work is not completed within the times specified in Paragraph 28 3.2 above, plus any extension thereof allowed in accordance with Article 12 of the 29 General Conditions. The Contractor also recognizes the delays, expense and difficulties 30 involved in proving in a legal proceeding the actual loss suffered by the City if the Work 31 is not completed on time. Accordingly, instead of requiring any such proof, Contractor 32 agrees that as liquidated damages for delay (but not as a penalty), Contractor shall pay 33 City Two Hundred—Ten & 00/100 Dollars($210.00) for each day that expires after the 34 time specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter 35 of Acceptance. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised January 6,2017 City Project No.100889 005243-2 Agreement Page 2 of 5 36 Article 4. CONTRACT PRICE .� 37 City agrees to pay Contractor for performance of the Work in accordance with the Contract 38 Documents an amount in current funds of Two Hundred Thousand & 00/100 Dollars 39 ($200,000.00). 40 Article 5. CONTRACT DOCUMENTS 41 5.1 CONTENTS: 42 A. The Contract Documents which comprise the entire agreement between City and 43 Contractor concerning the Work consist of the following: 44 1. This Agreement. 45 2. Attachments to this Agreement: 46 a. Bid Form 47 1) Proposal Form 48 2) Vendor Compliance to State Law Non-Resident Bidder 49 3) Prequalification Statement 50 4) State and Federal documents(project specific) 51 b. Current Prevailing Wage Rate Table 52 c. Insurance ACORD Form(s) 53 d. Payment Bond 54 e. Performance Bond 55 f. Maintenance Bond 56 g. Power of Attorney for the Bonds 57 h. Worker's Compensation Affidavit 58 i. MBE and/or SBE Commitment Form 59 j. Form 1295 Certification No. 2017-182598 60 3. General Conditions. 61 4. Supplementary Conditions. 62 5. Specifications specifically made a part of the Contract Documents by attachment 63 or, if not attached, as incorporated by reference and described in the Table of 64 Contents of the Project's Contract Documents. 65 6. Drawings. 66 7. Addenda. 67 8. Documentation submitted by Contractor prior to Notice of Award. 68 9. The following which may be delivered or issued after the Effective Date of the 69 Agreement and, if issued, become an incorporated part of the Contract Documents: 70 a. Notice to Proceed. .� 71 b. Field Orders. 72 c. Change Orders. 73 d. Letter of Final Acceptance. 74 75 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised January 6,2017 City Project No.100889 005243-3 Agreement Page 3 of 5 77 Article 6. INDEMNIFICATION 78 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own 79 expense, the city, its officers, servants and employees, from and against any and all 80 claims arising out of, or alleged to arise out of,the work and services to be performed 81 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees 82 under this contract. This indemnification provision is specifically intended to operate 83 and be effective even if it is alleged or proven that all or some of the damages being 84 sought were caused,in whole or in part, by any act,omission or negligence of the city. 85 This indemnity provision is intended to include, without limitation, indemnity for 86 costs,expenses and legal fees incurred by the city in defending against such claims and 87 causes of actions. 88 89 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, 90 the city,its officers,servants and employees,from and against any and all loss,damage 91 or destruction of property of the city,arising out of,or alleged to arise out of,the work 92 and services to be performed by the contractor, its officers, agents, employees, 93 subcontractors, licensees or invitees under this contract. This indemnification 94 provision is specifically intended to operate and be effective even if it is alleged or 95 proven that all or some of the damages being sought were caused,in whole or in part, 96 by any act,omission or negligence of the city. 97 98 Article 7.MISCELLANEOUS 99 7.1 Terms. 100 Terms used in this Agreement which are defined in Article 1 of the General Conditions will 101 have the meanings indicated in the General Conditions. 102 7.2 Assignment of Contract. �- 103 This Agreement, including all of the Contract Documents may not be assigned by the 104 Contractor without the advanced express written consent of the City. 105 7.3 Successors and Assigns. 106 City and Contractor each binds itself, its partners, successors, assigns and legal 107 representatives to the other party hereto, in respect to all covenants, agreements and 108 obligations contained in the Contract Documents. 109 7.4 Severability.. 110 Any provision or part of the Contract Documents held to be unconstitutional, void or 111 unenforceable by a court of competent jurisdiction shall be deemed Stricken, and all 112 remaining provisions shall continue to be valid and binding upon CITY and 113 CONTRACTOR. 114 7.5 Governing Law and Venue. .� 115 This Agreement, including all of the Contract Documents is performable in the State of 116 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the 117 Northern District of Texas,Fort Worth Division. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised January 6,2017 City Project No.100889 005243-4 Agreement Page 4 of 5 118 7.6 Other Provisions. 119 The Contractor agrees to pay at least minimum wage per hour for all labor as the same is 120 classified, promulgated and set out by the City, a copy of which is attached hereto and 121 made a part hereof the same as if it were copied verbatim herein. 122 7.7 Authority to Sign. 123 Contractor shall attach evidence of authority to sign Agreement, if other than duly 124 authorized signatory of the Contractor. 125 126 lift. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised January 6,2017 City Project No.100889 OR 005243-5 Agreement am Page 5 of 5 127 IN WITNESS WHEREOF, City and Contractor have executed this Agreement in multiple *� 128 counterparts. 129 130 This Agreement is effective as of the last date signed by the Parties("Effective Date"). 131 Contractor: City of Fort Worth By: Jesus J. Chapa By:a'����.�% Assistant City Manager N (Signature) tretary Date.�r Attes(Printed Name) A• City S �-�. •.1.Q (Seal) U Title: i✓ c C cz�,•d+ _ Address: Q. o �.�,� !o•7S s' M&C C.- 29020*0 ... . Date: (AM City/State/Zip: Contract Compliance Manager: By signing,.I acknowledge that I am the person responsible for the monitoring and Date administration of this contract,including ensuring all performance and reporting req u- Jim Deeter,P.E. Senior Professional Engineer Approved as to Form and Legality: D uglas W. Black Assistant City Attorney 132 133 134 APPROVAL RECOMMENDED: 135 +�. 136 �+ 137 r 138 John Robert Carman 139 DIRECTOR, .. 140 Water Department 141 _ OFFICIAL RECORD CITY SECRETARY CITY OF FORT WORTH OlA7L'� SLdIG STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT Revised January 6,2017 City Project No.100889 1 ' 006113-1 PERFORMANCE BOND Page 1 of 2 1 SECTION 00 6113 2 PERFORMANCE BOND EAIC127000006 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 8 That we, Tejas Commercial Construction LLC known as j » City of Fort Worth 1 9 Principal herein and a corporate �. 10 surety(sureties,if more than one)duly authorized to do business in the State of Texas,known as 11 "Surety"herein(whether one or more),are hold and firmly bound unto the City of Fort Worth,a 12 municipal corporation created pursuant to the laws of Texas,known as City herein,in the penal. 13 sum of, Two Hundred Thousand Dollars Dollars 14200000.00 ($ , lawful money of the United States,to be paid in Fort Worth, 15 Tarrant County,Texas for the payment of which sum well and truly to be made,we bind 16 ourselves,our heirs,executors,administrators,successors and assigns,jointly and severally, 17 firmly by these presents. 18 WHEREAS,the Principal has entered into a certain written contract with the City 19 awarded the 200 day of VN�� ,2C� -1,which Contract is.hereby referred to and 1 20 made a part hereof for all purposes as if fully set forth herein,to furnish all materials,equipment 4 21 labor and other accessories defined by law,in the prosecution of the Work,including any Change 22 Orders,as provided for in said Contract designated as 2017 Water Lead Services Replacement 23 Contract, City Project No. 100889 24 NOW,THEREFORE,the condition of this obligation issuch that if the said Principal ( 25 shall faithfi111y perform it obligations under the Contract and shall in all respects duly and 1 26 faithfully perform the Work,including Change Orders,under the Contract,according to the plans, " 27 specifications,and contract documents therein referred to,and as well during any period of 28 extension of the Contract that may be granted on the part of the City,then this obligation shall be 29 and become null and void,otherwise to remain in full force and effect. 30 PROVIDED FURTHER,that if any legal action be filed on this Bond,venue shall lie in 31 Tarrant County,Texas or the United States District Court for the Northern District of.Texas,Fort 32 WortkLaVision. . ... i Zr'i 1`Tg]RT WORTH 2017 WATER LEAD SERVICES STAPdti'ieud.�lTtr $ONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT �e1,2011 City Project No.100889 wu 006113-2 PERFORMANCE BOND Ptige 2 of 2 go 1 This bond is made and executed in compliance with the provisions of Chapter 2253 of.the ( 2 Texas Government Code,as amended,and all liabilities on this bond shall be determined in 1 3 accordance with the provisions of said statue. 4 IN WITNESS WHEREOF,the Principal and the Surety have SIGNED and SEALED 5 ' this instrument by duly authorizedagents and officers on this the Z`J 9 day of l6 � 20AI_. 7 PRINCIPAL: u� 9 -�ejas-Gea�rersial• 10 ' 11 BY>C •--�� 12 Signature 13 ATTEST: 14 1 15 Charles Allen,Vice President i 16 _ (Principal)Secretary Name and Title 17 '18 Address: PO Box 10395 19 River Oaks,TX 76114 21 ' 22 Witness as to Principal 23 SURETY: 24 Endurance American Insurance Company 25 26 27 BY: 28 Signature a■i 29 30 Chris Holt,Attorney in Fact 31 Name and Title 32 33 Address: 750 Third Avenue 2nd Floor 34 New York,New York 10017 35 j 36 OU ..___......__ II 37 Witness as to SuretyTelephone Number: 817-261-1101 38 39 oil 40 41 *.Note: If signed by an officer of the Surety Company,there must be on file a certified extract 42 from the by-laws showing that this person has authority to sign such obligation. If ali 43 Surety's physical address is different from its mailing address, both must be provided. 1 44 The date of the bond shall not be prior to the date the Contract is awarded. } 45 Y_4=�PRT WORTH 2O17 WATER LEAD SERVICES $74D CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT _V��Iy 1,201.1 City Proieat No.100889 ON ENDURANCE AMERICAN INSURANCE COMPANY POA1000005459 127 POWER OF ATTORNEY ROW ad`M¢R i6y these Tresent, that ENDURANCE AMERICAN INSURANCE COMPANY,a Delaware oration(the the 7� rp 'Corporation),with offices at 750 Third Avenue, New York.NY 10017,has made.constituted and appointed and by these presents,does make,constitute and appoint CHRIS L.HOLT,JOE RODNEY DUCKWORTH its true and lawful Attomey(s)-in-fact,at AMARILLO in the State of TX and each of them to have full power to act without the other or others,to make,execute,seal and deliver for and on its behalf bonds,undertakings or obligations in surety or co-surety with others.also to execute and deliver on its behalf renewals.extensions,agreements,waivers,consents or stipulations relating to such aforesaid bonds.undertakings or obligations provided,however,that no single bond or undertaking so made.executed and delivered shall obligate the Corporation for any portion;of the penal sum thereof in excess of the sum of TEN MILLION Dollars($10,000,000). Such bonds endtmde t ngs frlr said purposes,when duly executed by said attomey(s�in-fact,shall be binding upon the Corporation as fully and to the same extent as if signed by the Pres"of the Corporation udder its corporate seal attested by its Corporate Secretary. 4,4 This p•,strrlrarxjs made under by authority of certain resolutions adopted b the Board of Directors of the Corporation b unanimous written consent on the 21st da of Ju 2011 _BPpoin �.Y ty P Y m Y Y ty• a copy 6f whr&appears below under the heading entitled"Certificate'. This dower of Atoompyis*tied and sealed by facsimile under and by authority of the following resolution adopted by the Board of Directors of the Corporation by unanimous written corlserdon the 21st dpygf July,2011 and said resolution has not since been revoked,amended or repealed: rNer RE§QLVED,that m g'ranfing powers of atttimep pursuant to certain resolutions adopted by the Board of Directors of the Corporation by unanimous written consent onthe 21st day of July,201t the srrptature of such directors andofficers and the seal of the Corporation may be affixed to any such power of attorney or any certificate relating thereto by facsimile,and any such power of attomay dr certificate bearing such facsimile signature or seal shall be valid and binding upon the Corporation In the future with respect to any bond or undertaking to which it is attadherl. x This Power of Attorney shall exWtte and all authority hereunder shall terminate without notice at 12:01 a.m.(Standard Time where said attomey(s}in-fact is authorized to act.) December 7,2019 IN WITNESS WHEREOF,the Corporation has caused these presents to be duly signed and its corporate seal to be hereunto affixed and attested this 2nd day of November,2016 at New York,New York. (Corporate Seal) ENDURANCE AMERICAN INSURANCE COMPANY ATTEST.._. RICHARD M.APPEL,SENIOR VICE PRESIDENT BRIAN BEGGS.EXECUTIVE VICE PRESIDENT STATE OF NEW YORK ss:MANHATTAN e COUNTY OF NEN YORK On the 2nd day of November.2016 before me personally came BRIAN BEGGS to me known.who being by me duly swom,did depose and say that(s)he resides in NEN YORK,NEW YORK that(s)he a&EXECUTIVE VICE PRESIDENT of ENDURANCE AMERICAN INSURANCE COMPANY.the Corporation described in and which executed the above instrument that(s)he knows the seal of said CCorperation:that the seal affixed to said instrument is such corporate seal;that it was so affixed by order of the Board of Directors of said Corporation, and that(s)tgtslpnedh4;fie0 name thereto by like order. "f ,_;4✓, 7 Nicholas James Benenati,Notary Public-My Commission Expires 1210712019 '• s , . CERTIFICATE STATE OF.0w)(ORK } ss:MANHATTAN COUNTY OFWESTCHESTER` I,CHRISTOPHER SPARRO the PRESIDENT of ENDURANCE AMERICAN INSURANCE COMPANY,a Delaware Corporation(the-Corporation),hereby certify: 1. That the original power of attorney of which the foregoing is a copy was duly executed on behalf of the Corporation and has not since been revoked amended or modified:that the undersigned has compared the foregoing copy thereof with the original power of attomey,and that the same is a true and correct copy of the original power of attorney and of the whole thereof; 2.The following are resolutions which were adopted by the Board of Directors of the Corporation by unanimous written consent on 21st day of July,2011 and said resolutions have not since been revoked,amended or modified: 'RESOLVED,that each of the individuals named below is authorized to make,execute,seal and deliver for and on behalf of the Corporation any and all bonds undertakings or obligations in surety or co-surety with others and to execute and deliver for and on behalf of the Corporation renewals,extensions,agreements,waivers.consents or stipulations relating to such aforesaid bonds,undertakings or obligations: RICHARD M.APPEL,BRIAN BEGGS And be it further . RESOLD,ftf each of the individuals named above is authorized to appoint attomeys•in-fact for the purpose of making,executing,sealing and delivering bonds,undertakings or obligations Wsurety orrcaauNty for and on behalf of the Corporation.' z 3. Tlie undersigned further certifies that tf1 above resolutions are We and correct copies of the resolutions as so recorded and of the whole thereof IN"ESS WHEti q( jhive hereunto set roy hand and affixed the corporate seal this day of 20 (Cciprtite Seal) CHRISTOPHER SPARRO,PRESIDENT s yam. Any reproductions are void. Primary Surety Claims Submission:suretybondclaims@enduranceservices.mm w - Surety Claims Hotline:677{76-7575 Mailing Address:Endurance Surety Claims Department,750 Third Avenue—lith Floor.New York,NY 10017 on Policyholder Notice TEXAS-IMPORTANT NOTICE AVISO IMPORTANTE To obtain information or make a complaint: Para obtener informacion o para someter una You may call the company's telephone number for queja: information or to make a complaint at: Usted puede Ilamar al numero de telefono de la compania para informacion o para someter una queja al: 1-877-676-7575 1-877-676-7575 You may write the Company at: Usted tambien puede escribir a: Endurance American Insurance Company Endurance American Insurance Company Attention:Surety Attention:Surety 750 Third Avenue 750 Third Avenue New York,NY 10017 New York,NY 10017 You may contact the Texas Department of Puede communicarse con el Departamento de Insurance to obtain information on companies, Seguros de Texas para obtener informacion acerca coverages, rights or complaints at: de companias,coberturas,derechos o quejas al: 1-800-252-3439 1-800-252-3439 You may write the Puede escribir al Texas Department of Insurance Departamento de Seguros de Texas PO Box 149104 PO Box 149104 Austin,TX 78714-9104 Austin,TX 78714-9104 FAX#(512)490-1007 FAX#(512)475-1771 Web: http://www.tdi.texas.eov Web: http://www.tdi.texas.gov E-mail:ConsumerProtection@tdi.texas.gov E-mail:ConsumerProtection@tdi.texas.eov PREMIUM OR CLAIM DISPUTES: Should you have a DISPUTAS SOBRE PRIMAS O RECLAMOS: Si tiene dispute concerning your premium or about a claim una disputa concerniente a su prima o a un you should contact the company first. If the dispute reclamo,debe comunicarse con la compania is not resolved,you may contact the Texas primero. Si no se resuelve la disputa, puede Department of Insurance. entonces comunicarse con el departamento(TDI). ATTACH THIS NOTICE TO YOUR POLICY: This notice UNA ESTE AVISO A SU POLIZA: Este aviso es solo is for information only and does not become a part para proposito de informacion y no se convierte en or condition of the attached document. parte o condicion del documento adjunto. f 006114-1 PAYMENT BOND Page 1 of 2 1 SECTION 00 6114 2 PAYMENT BOND EAIC127000006 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § f 7 8 That we, Teias Commercial Construction LLC known as 9 "Principal" herein, and Gity of Fork Worth a 10 corporate surety (sureties), duly authorized to do business in the State of Texas, known as j 11 "Surety"herein (whether one or more), are held and firmly bound unto the City of Fort Worth, a .� 12 municipal corporation created pursuant to the laws of the State of Texas,known as"City"herein, f I 13 in the penal sum Of Two Hundred Thousand Dollars , Dollars 14 200,000.00 � ($ ), lawful money of the United States, to be paid in Fort Worth, IyI 15 Tarrant County,Texas,for the payment of which sum well.and truly be made,we bind ourselves, 16 our heirs, executors, administrators, successors and assigns,jointly and severally, firmly by these i 17 presents: 18 WHEREAS,Principal has entered into a certain written Contract with City, awarded the 19 day of M � , 20,x_, which Contract is hereby referred to and 20 made a part hereof for all purposes as if fully set forth herein,to furnish.all materials,equipment, 21 labor and other accessories as defined by law, in the prosecution of the Work as provided for in 22 said Contract and designated as 2017 Water Lead Services Replacement Contract; Citv 23 Project No. 100889 24 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if 25 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in 26 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under 27 the Contract,then this obligation shall be and became null and void; otherwise to remain in full f 28 force and effect, i i r 29 This bond is made and executed in compliance with the provisions of Chapter 2253 of the 39 Texas Government Code, as amended, and all liabilities on this bond shall be determined in �1 aoc&dance with.the provisions of said statute. � l.,. h :.j. .t-�ORT WORTH 201.7 WATER LEAD SERVICES 1 'S1ri�j`y��XRD CONSTRUCTION SPEC1rICA'tION DOCUMENTS REPLACEMENT CONTRACT I cyfJuly 1,2011 City Proiect No.100889 I dw 006114-2 PAYMENTBOND Page 2 of 2 1 IN WITNESS WHEREOF,the,Principal and Surety have each SIGNED and SEALED 2 this instrument by duly authorized agents and officers on this the �Zday of .r 3 20, lam_. 4 j PRINCIPAL: 1 Tejas Commercial Construction LLC ATTEST: BY: Signature �. Charles Allen,Vice President j (Principal)Secretary Name and Title .w, Address: PO Box 10395 River Oaks,TX 76114 do Witness as to Priaipal 1 SURETY: Endurance American Insurance Company ATTEST: BY: (/;w +r. _ Signature Chris Holt,Attorney in Fact (Surety)Secretary Name and Title Address: 750 Third Avenue 2nd Floor New Yor, New York 10017 Witness as to Surety Telephone Number: 817-261-1101 5 6 Note: If signed by an officer of the Surety, there must be on file a certified extract from the 7 bylaws showing that this person has authority to sign such obligation. If Surety's physical 8 address is different from its mailing address,both must be provided, 9 10 The date of the bond shall not be prior to the date the Contract is awarded. 11 END OF SECTION 12 'C1'1JY1iIMr6RT 4708'ki 2017 WATER LEAD SERVICES 8:NARUItb CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT j ; isr;; July 1,2011. City Project No.100889 ENDURANCE AMERICAN INSURANCE COMPANY POAM00005459 127 POWER OF ATTORNEY Know aff Men 6r these(Present, that ENDURANCE AMERICAN INSURANCE COMPANY,a Delaware corporation(the'Corporahonl,with offices at 750 Third Avenue, New York.NY 10017,has made,constituted and appointed and by these presents,does make,constitute and appoint CHRIS L.HOLT,JOE RODNEY DUCKWORTH its true and lawful Adomey(s)-in-fact,at AMARILLO in the State of TX and each of them to have full power to act without the other or others,to make,execute,seat and deliver for and on its behalf bonds,undertakings or obligations in surety or co-surety with others.also to execute and deliver on its behalf renewals,extensions,agreements.waivers,consents or *� stipulations relating to such aforesaid bonds,undertakings or obligations provided,however,that no single bond or undertaking so made.executed and delivered shall obligate the Corporation for any portiggof the penal sum thereof in excess of the sum of TEN MILLION Dollars($10,000,000). Such bonds and under takings for said purposes,when duty executed by said athmey(s)-in-fact,shall be binding upon the Corporation as fully and to the same extent as if signed by the President of the Corporation under its corporate seal attested by its Corporate Secretary. This .: f appantrnent is made underaitd,by authority of certain resolutions adopted by the Board of Directors of the Corporation by unanimous'written consent on ihe21 st day of July,2011 a copy of whiff appears below under the heading entitled'Certificate'. �ra This Power of Attorrigy is sfgri d and sealed try,facsimile under and by authority of the following resolution adopted by the Board of Directors of the Corporation by unanimous written coruenton the 21st doyQ(J ly,2011 and said resolution has not since been revoked,amended or repealed: RESOLVED,that in granting powers of atlatnay pursuant to certain resolutions adopted by the Board of Directors of the Corporation by unanimous written consent onthe 21st day of July,203f the sgnsture of such directortand officers and the seal of the Corporation may be affixed to any such power of attorney or any certificate relating thereto by facsimile,and any such porter of alloi or certificate bearing such facsimile signature or seal shall be valid and binding upon the Corporation in the future with respect to any bond or undertaking to which it is attached. �^ x b This Power of Attorney shag expire and all authority hereunder shall terminate without notice at 12:01 a.m.(Standard Time where said attomey(srin-fact is authonzed to act) December 7,2019 IN WITNESS WHEREOF,the Corporation has caused these presents to be duly signed and its corporate seal to be hereunto affixed and attested this 2nd day of November,2016 at New York,New York. (Corporate Seat) ENDURANCE AMERICAN INSURANCE COMPANY ATTEST-- BY RICHARD M.APPEL,SENIOR VICE PRESIDENT BRIAN BEGGS,EXECUTIVE VICE PRESIDENT STATE OF NEW YORK ss:MANHATTAN COUNTY OF NEW YORK On the 2nd day of November.20.16 before me personalty came BRIAN BEGGS to me known.who being by me duly sworn,did depose and say that(s)he resides in NEW YORK,NEW YORK that(s)he is aEXECUTiVE VICE PRESIDENT of ENDURANCE AMERICAN INSURANCE COMPANY.the Corporation described in and which executed the above instrument that(s)heknows the seal of said Corporation;that the seal affixed to said instrument is such corporate seal;that it was so affixed by order of the Board of Directors of said Corporation. **r and thtaf(s)tgisigne0il^q dame#Weto by like order. (NofenatS ; 3 i Nicholas James Benenatl,Notary Public-My Commission Expires 12107!2019 ` �.` ,;'� CERTIFICATE STATE OF V ;i0,RK ss:MANHATTAN COUNTY OF WESTCPESTER I,CHRISTOPHER SPARRO the PRESIDENT of ENDURANCE AMERICAN INSURANCE COMPANY,a Delaware Corporation(the'Corporation'),hereby certify: 1. That the original power of attorney of which the foregoing is a copy was duly executed on behalf of the Corporation and has not since been revoked amended or modified;that the undersigned has compared the foregoing copy thereof with the original power of attorney,and that the same is a true and correct copy of the original power of attorney and of the whole thereat; ® 2.The following are resolutions which were adopted by the Board of Directors of the Corporation by unanimous written consent on 21st day of July,2011 and said resolutions have not since been revoked.amended or modified: 'RESOLVED.that each of the individuals named below is authorized to make.execute,seal and deliver for and on behalf of the Corporation any and all bonds,undertakings or obligations in surety or co-surety with others and to execute and deliver for and on behalf of the Corporation renewals,extensions,agreements,waivers,consents or stipulations relating to such aforesaid bonds,undertakings or obligations: RICHARD M.APPEL,BRIAN BEGGS And be it further '$.N RESOLVED;lot sack of 01e mdtviduals named above is authorized to appoint attorneys-in-fact for the purpose of making,executing,sealing and delivering bonds,undertakings or obligagoaiwsuretYarco-aur"for andon behalf of the Corporation," 3. The undersigned further certifieslthat the above resolutions are true and correct copies of the resolutions as so recorded and of the whole thereat IN Iii NESS WHERE# Jlh ve hereunto set my hand and affixed the corporate seal this day of 20 (Cate Seal) # / AW *" CHRISTOPHER SPARRO,PRESIDENT Any reproductions are void. Primary Surety Clams Submission:surerybonddabm@enduranceservices.mm Surety Claims Hotline:877$76-7575 Mailing Address:Endurance Surety Claims Department.750 Third Avenue-10th Floor,New York,NY 10017 a �4 Policyholder Notice TEXAS-IMPORTANT NOTICE AVISO IMPORTANTE To obtain information or make a complaint: Para obtener informacion o para someter una You may call the company's telephone number for queja: information or to make a complaint at: Usted puede Ilamar al numero de telefono de la compania para informacion o para someter una queja al: 1-877-676-7575 1-877-676-7575 You may write the Company at: Usted tambien puede escribir a: Endurance American Insurance Company Endurance American Insurance Company Attention:Surety Attention:Surety 750 Third Avenue 750 Third Avenue New York, NY 10017 New York, NY 10017 You may contact the Texas Department of Puede communicarse con el Departamento de Insurance to obtain information on companies, Seguros de Texas para obtener informacion acerca coverages, rights or complaints at: de companias,coberturas,derechos o quejas al: 1-800-252-3439 1-800-252-3439 You may write the Puede escribir al Texas Department of Insurance Departamento de Seguros de Texas PO Box 149104 PO Box 149104 Austin,TX 78714-9104 Austin,TX 78714-9104 FAX#(512)490-1007 FAX#(512)475-1771 Web: http://www.tdi.texas.aov Web: http://www.tdi.texas.gov E-mail:ConsumerProtection@tdi.texas.aov E-mail:ConsumerProtection@tdi.texas.gov PREMIUM OR CLAIM DISPUTES: Should you have a DISPUTAS SOBRE PRIMAS O RECLAMOS: Si tiene dispute concerning your premium or about a claim una disputa concerniente a su prima o a un you should contact the company first. If the dispute reclamo,debe comunicarse con la compania is not resolved,you may contact the Texas primero. Si no se resuelve la disputa,puede Department of Insurance. entonces comunicarse con el departamento(TDI). ATTACH THIS NOTICE TO YOUR POLICY: This notice UNA ESTE AVISO A SU POLIZA: Este aviso es solo is for information only and does not become a part para proposito de informacion y no se convierte en or condition of the attached document. parte o condicion del documento adjunto. 0061 19-1 . MAINTENANCE BOND ( Page 1 of 3 I 1 SECTION 00 6119 2 MAINTENANCE BOND EAIC127000006 3 4 THE STATE OF TEXAS § {. 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 8 That we Teias Commercial Construction LLC ,known.as 9 "Principal"herein and City of Forth Worth ,a corporate surety I, 10 (sureties,if more than one)duty authorized to do business in the State of Texas,known as 11 "Surety"herein(whether one or more),are held and firmly bound unto the City of Fort Worth,a I ( 12 municipal corporation created pursuant to the laws of the State of Texas,known as"City"herein, 13 In the SUM of Two Hundred Thousand Dollars Dollars 200,000.00 14 ($ ),lawful money of the United States,to be paid in Fort Worth, 15 Tarrant County,Texas,for payment of which sum well and truly be made unto the City and its 16 successors,we bind ourselves,our heirs,executors,administrators,successors and assigns,jointly fi 17 and severally,firmly by these presents, r 18 1.9 WHEREAS,the Principal has entered into a certain written contract with the City awarded " f 20 the 2�h day of �M1 ,20-Q,which Contract is hereby 21 referred to and a made part hereof for all purposes as if fully set forth herein,to furnish all ` 22 materials,equipment labor and.other accessories as defined by law,in the prosecution of the i t 23 Work,.including any Work resulting from a duly authorized Change Order(collectively herein, 24 the"Work")as provided for in said contract and designated as 2017 Water Lead Services 25 Replacement Contract; City Protect No. 100889; and 26 27 WHEREAS,.Principal binds itself to use such materials and to so construct the Work in 28 accordance with the plans,specifications and Contract Documents that the Work is and.will 29 remain free from defects in materials or workmanship for and during the period of two(2)years 30 after the date of Final Acceptance of the Work by the City("Maintenance Period");and 31 32 WHEREAS,Principal binds itself to repair or reconstruct the Work in whole or in part 33 upon receiving notice from the City of the need therefor at any time within the Maintenance - 34cf;iAd; rQ-ITY C�*Oi' T WORTH 2017 WATER LEAD SERVICES S? 3C ONS'1'RUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT .}: �.`. a1l4.e�t�► �1,2011 City Project No.100889 0061 19-3 MAINTENANCE BOND Page 3 of 3 I IN WITNESS WHEREOF,the Principal and the Surety have each SIGNED and SEALED this i2 instrument by duly authorized agents and officers on this the '�`� day of 3 20_AL. I 4 5 PRINCIPAL: — 6 7 � 8 �- 9 BY: 10 Signature 11 ATTEST: 12 I 13 Charles Allen,Vice President I 14 (Principao Secretary Name and Title 15 16 Address: PO Box 10395 17 River 05ks,TX 76114 18 19 C6r ( 20 Witness as to P ' cipal 1 21 SURETY: 22 Endurance American Insurance Company 23 24 25 BY: (- 26 Signature 27 28 Chris Holt,Attorney in Fact 29 ATTEST: Name and Title r 30 I 31 Address: 750 Third Avenue 2nd Floor 32 (Surety)Secretary New—York,New York 33 34 35 Witness as to Surety Telephone Number: 817-261-1101 36 37 *Note: If signed by an officer of the Surety Company,there must be on file a certified extract f 38 from the by-laws showing that this person has authority to sign such obligation. If 39 Surety's physical address is different from its trailing address, both must be provided, 40 The date of the band shall not be prior to the date the Contract is awarded. 41 ; FORT WORTH WATER LEAD SERVICES fiD CONSTRUCTION SPECIFICATION.DOCUMENTS REPLACEMENT CONTRACT " 1"'RPO July 1"2011 City Project No.100889 we ENDURANCE AMERICAN INSURANCE COMPANY POA1000005459 127 POWER OF ATTORNEY Know adwen iy these Present, that ENDURANCE AMERICAN INSURANCE COMPANY,a Delaware corporation(the"Corporation'1,with offices at 750 Third Avenue, New York,NY 10017,has made.constituted and appointed and by these presents,does make,constitute and appoint CHRIS L.HOLT,JOE RODNEY DUCKWORTH its true and lawful Attomey(s}in-fact,at AMARILLO in the State of TX and each of them to have full power to act without the other or others,to make,execute,seal and deliver for and on its behalf bonds,undertakings or obligations in surety or co-surety with others,also to execute and deliver on its behalf renewals,extensions,agreements,waivers,consents or Mi. stipulations relating to such aforesaid bonds,undertakings or obligations provided,however,that no single bond or undertaking so made,executed and delivered shall obligate the Corporation for any poctioAof the penal sum thereof in excess of the sum of TEN MILLION Dollars($10,000,000). Such bonds.t�ti&t�Mg f�"d purposes,when duly executed by said attomey(sHn-fact,shall be binding upon the Corporation as fully and to the same extent as if signed by Pres'the Pre afthe, n dndet,4s corporate seal attested by its Corporate Secretary. ms .. rw♦r This appontmentA made uncre'arrd by 40*1ty of certain resolutions adopted by the Board of Directors of the Corporation by unanimous written consent on the21st day of July,2011 a copy bf whkKappears below u thdjw ding entitled'Certificate". Thi�Pow�er of Attoripils skr#ed and sea"facsimile under and by authority of the following resolution adopted by the Board of Directors of the Corporation by unanimous written col >on the 21st clay j,2011 and sato resolution has not since been revoked,amended or repealed: RESO'ED,that in granting power of atWtney pursuant to certain resolutions adopted by the Board of Directors of the Corporation by unanimous written consent on the 21st day of July,'2flffithe`sotature of such._directors and officers and the seal of the Corporation may be affixed to any such power of attorney or any certificate relating thereto by facsimile,and any such po#er of atto0ey6rcer1jfic*bearing such facsimile signature or seal shall be valid and binding upon the Corporation in the future with respect to any bond or undertaking to which It Is attaint. ; This Power of Attomey sttaA.expire and all authority hereunder shall terminate without notice at 12:01 a.m.(Standard Time where said attomey(s)-in-fact is authorized to act) ® December 7,2019 IN WITNESS WHEREOF,the Corporation has caused these presents to be duly signed and its corporate seal to be hereunto affixed and attested this 2nd day of November,2016 at New York,New York. (Corporate Seal) ENDURANCE AMERICAN INSURANCE COMPANY :..r- . MiF ATTEST wi BY 2 / �*r� RICHARD M.APPEL,SENIOR VICE PRESIDENT BRIAN BEGGS,EXECUTIVE VICE PRESIDENT STATE OF NEW YORK ss:MANHATTAN COUNTY OF NEW YORK On the 2nd day of November,2Q16 before me personally came BRIAN BEGGS to me known,who being by me duly swom,did depose and say that(s)he resides in NEW YORK,NEW YORK that(s)he is,afXk(WTLVE VICE PRESIDENT of ENDURANCE AMERICAN INSURANCE COMPANY,the Corporation described in and which executed the above instrument that(s)he,knoyiq the seal of said 6 pration;that the seal affixed to said instrument is such corporate seal;that it was so affixed by order of the Board of Directors of said Corporation, and t4f'(s)F*stgne*hi§0e4,'ngm6` ,&et6 by like order. (Notanal ao- k'0.141111,VOW( r m m t ESP" Nicholas James Benenati,Notary Public-My Commission Expires 12107/2019 CERTIFICATE STATE OF "ORK- !-k "ss:MANHATTAN COUNTY 6f,w FAST `" we I,CHRISTOPHER SPARRO the�PRESIDENT of ENDURANCE AMERICAN INSURANCE COMPANY,a Delaware Corporation(the"Corporation'1,hereby certify: 1. That the original power of attomey of which the foregoing is a copy was duly executed on behalf of the Corporation and has not since been revoked,amended or modified;that the undersigned has compared the foregoing copy thereof with the original power of attorney,and that the same is a true and correct copy of the original power of attorney and of the whole thereof; Mirk 2. The following are resolutions which were adopted by the Board of Directors of the Corporation by unanimous written consent on 21st day of July,2011 and said resolutions have not since been revoked,amended or modified: "RESOLVED,that each of the individuals named below is authorized to make,execute,seal and deliver for and on behalf of the Corporation any and all bonds,undertakings or obligations in surety or co-surety with others and to execute and deliver for and on behalf of the Corporation renewals,extensions,agreements,waivers,consents or stipulations relating to such aforesaid bonds,undertakings or obligations: RICHARD M.APPEL,BRIAN BEGGS And be it furtlter�`� � "' RESOD 1aC ate indh teamed above is authorized to appoint attorneys in-fact for the purpose of making,executing,sealing and delivering bonds,undertakings or �a u`rftyaehalf of the Corporation." oblig * 3. Wdersigrted further cerGfiet flat ve resolutions are true and correct copies of the resolutions as so recorded and of the whole thereof IN j6ESS WHEve hereunto ray hand and affixed the corporate seal this day of 20 t - (C fe Seal) �� ` CHRISTOPHER SPARRO,PRESIDENT •t, _ Any reproductions are void. Primary Surety Claims Submission:suretybonddaims@enduranceservices.com Surety Claims Hotline:877-676-7575 Mailing Address:Endurance Surety Claims Department,750 Third Avenue-10th Floor,New York,NY 10017 r Policyholder Notice TEXAS-IMPORTANT NOTICE AVISO IMPORTANTE To obtain information or make a complaint: Para obtener informacion o para someter una You may call the company's telephone number for queja: information or to make a complaint at: Usted puede Ilamar al numero de telefono de la compania para informacion o para someter una -� queja al: 1-877-676-7575 1-877-676-7575 You may write the Company at: Usted tambien puede escribir a: Endurance American Insurance Company Endurance American Insurance Company Attention:Surety Attention:Surety 750 Third Avenue 750 Third Avenue New York, NY 10017 New York, NY 10017 You may contact the Texas Department of Puede communicarse con el Departamento de Insurance to obtain information on companies, Seguros de Texas para obtener informacion acerca coverages, rights or complaints at: de companias,coberturas,derechos o quejas al: 1-800-252-3439 1-800-252-3439 You may write the Puede escribir al Texas Department of Insurance Departamento de Seguros de Texas PO Box 149104 PO Box 149104 Austin,TX 78714-9104 Austin,TX 78714-9104 FAX#(512)490-1007 FAX#(512)475-1771 Web: http://www.tdi.texas.gov Web: http://www.tdi.texas.gov E-mail:ConsumerProtection@tdi.texas.gov E-mail:Consumer Protection @td i.texas.gov PREMIUM OR CLAIM DISPUTES: Should you have a DISPUTAS SOBRE PRIMAS O RECLAMOS: Si tiene dispute concerning your premium or about a claim una disputa concerniente a su prima o a un you should contact the company first. If the dispute reclamo,debe comunicarse con la compania is not resolved,you may contact the Texas primero. Si no se resuelve la disputa, puede Department of Insurance. entonces comunicarse con el departamento(TDI). ATTACH THIS NOTICE TO YOUR POLICY: This notice UNA ESTE AVISO A SU POLIZA: Este aviso es solo is for information only and does not become a part para proposito de informacion y no se convierte en or condition of the attached document. parte o condicion del documento adjunto. AC R®® CERTIFICATE OF LIABILITY INSURANCE D ATE / O17Y) i 2 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER,AND THE CERTIFICATE HOLDER. IMPORTANT. If the certificate holder is an ADDITIONAL INSURED, the poiicy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy,certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). PRODUCER CONTACT Karissa Greer CIC ACSR NAME: + + DFB Insurance Group of DEW, LLC PHONE (817)261-1101 FAX te17>z61-llzo C No Ext: AIC No 700 Highlander Blvd. , Ste. 340 E-MAIL ADDRESS:kg reer@dfbinsurance.com INSURERS AFFORDING COVERAGE NAIC N Arlington TX 76015 INSURERA:United Fire 6 Casualt C an 13021 INSURED INSURERB:Texas Mutual Insurance Co 22945 Tejas Commercial Construction, LLC INSURER C: PO BOX 10395 INSURER D: INSURER E River Oaks TX 76114 INSURER F: COVERAGES CERTIFICATE NUMBER:1617 LIAB REVISION NUMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES.LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR �.ADDLSUBR1 POLICY EFF POLICY EXP LTR TYPE OF INSURANCE INsn,wvn POLICY NUMBER MMIDDIYYYY MM DDIYYYY LIMITS X I COMMERCIAL GENERAL LIABILITY EACH OCCURRENCE $ 1,000,000 A CLAIMS-MADE a OCCUR PREMISAMAM TO RENTED 100 000 ES Ea occurrence $ + X X C U Coverage Included 60422917 11/8/2016 11/8/2017 MED EXP(Any one person) $ 5,000 X Contractual Liab Incl. PERSONAL&ADV INJURY $ 1,000,000 GEN'L AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $ 2,000,000 POLICY JEC LOC PRODUCTS-COMP/OPAGG $ 2,000,000 � OTHER: $ fi AUTOMOBILE LIABILITY EOa INED .n SINGLE LIMIT aBc d $ 1,000,000 '.. A X ANY AUTO BODILY INJURY(Per person) $ ALL OWNED SCHEDULED 60422917 11/8/2016 11/8/2017 BODILY INJURY(Per accident) $ AUTOS AUTOS NON-OWNED PROPERTY DAMAGE X HIRED AUTOS X AUTOS Per accident $ PIP-Basic $ 2,500 X UMBRELLA LIAR X OCCUR EACH OCCURRENCE $ 2,000,000 A EXCESS LIAB CLAIMS-MADE AGGREGATE $ 2,000,000 DED X RETENTION$ 10,000 60422917 11/8/2016 11/8/2017 $ WORKERS COMPENSATION X PER H- AND EMPLOYERS'LIABILITY Y I N STATUTE ER ANY PROPRIETOR/PARTNER/EXECUTIVE E.L.EACH ACCIDENT $ 1,000,000 OFFICERIMEMBER EXCLUDED? N/A B ❑y (Mandatory in NH) TSF0001217793 11/8/2016 11/8/2017 E.L.DISEASE-EA EMPLOYE $ 1 000,000 If yes,describe under DESCRIPTION OF OPERATIONS below E.L.DISEASE-POLICY LIMIT $ 1,000,000 A Leased/Rented 60422917 11/8/2016 11/8/2017 400,000 Deductible 1,000 DESCRIPTION OF OPERATIONS I LOCATIONS I VEHICLES (ACORD 101,Additional Remarks Schedule,may be attached if more space is required) Project 100889 The general liability policy includes a blanket automatic additional insured endorsement CG7152 0611 that provides additional insured status to the certificate holder only when there is a written contract between the named insured and the certificate holder that requires such status. The general liability and workers' compensation policy includes a blanket automatic waiver of subrogation endorsement that provides this feature only when there is a written contract between the named insured and the certificate holder that requires it. The general liability policy contains a special endorsement with "PrimaEy It CERTIFICATE HOLDER CANCELLATION SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE CITY OF FORT WORTH THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN 1000 THROCKMORTON ACCORDANCE WITH THE POLICY PROVISIONS. FORT WORTH, TX 76102 AUTHORIZED REPRESENTATIVE Chris Hnit G� ccgolor ©1988-2014 ACORD CORPORATION. All rights reserved. ACORD 25(2014/01) The ACORD name and logo are registered marks of ACORD INS025(201401) COMMENTS/REMARKS wording. Above policies include an endorsement providing that 30 day Notice of Cancellation (or coverage change) will be furnished to the certificate holder. i OFREMARK COPYRIGHT 2000, AMS SERVICES INC. STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT MR dw CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS '� Revision:FdxumyZ2016 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT TABLE OF CONTENTS Page Article 1 —Definitions and Terminology... ................................................................................ .. , ..............1 1.01 Defined Terms. .............................................................................................................................1 1.02 Terminology... .... ........... . , .....,................ ... .. ..... ..................................,,. .......................6 Article2—Preliminary Matters................ .. ............ ........................................................ ...........................7 2.01 Copies of Documents...................................................................,.......,........ .... ..............................7 2.02 Commencement of Contract Time;Notice to Proceed................................................................7 2.03 Starting the Work................................................................... ....... ............................................8 2.04 Before Starting Construction.............................................. .........................................................8 2.05 Preconstruction Conference..... .............................................................................. ...............8 2.06 Public Meeting............................................................................. .............................................8 2.07 Initial Acceptance of Schedules................ . ................................. ............................... ... ......8 Article 3—Contract Documents: Intent,Amending,Reuse............................................................................8 3.01 Intent........................ .....................................................................................................................8 3.02 Reference Standards...................... ....... . .. . .......... ......................... :. ........ ...........................9 3.03 Reporting and Resolving Discrepancies...................................................................................1.1.9 3.04 Amending and Supplementing Contract Documents.................................................................10 3.05 Reuse of Documents............................................................................ ......................................10 �- 3.06 Electronic Data............................. .................... .......................................................... ........ ...11 Article 4—Availability of Lands; Subsurface and Physical Conditions;Hazardous Environmental _ Conditions;Reference Points..................................... ..... ................................... ............... .....11 4.01 Availability of Lands...... ........ ........................ .........................................................................11 4.02 Subsurface and Physical Conditions. ............................................ ................................. .12 4.03 Differing Subsurface or Physical Conditions.............................................................................12 4.04 Underground Facilities.......................................... ...... . .......... .. ........................................13 4.05 Reference Points.........................................................................................................................14 4.06 Hazardous Environmental Condition at Site..............................................................................14 Article 5—Bonds and Insurance.......................... .......... ...... ...... ......................... .,............................16 --o- 5.01 Licensed Sureties and Insurers............................................................................. ........... .16 5.02 Performance,Payment,and Maintenance Bonds...................... ................................................16 5.03 Certificates of Insurance...................................................................................... ..................16 5.04 Contractor's Insurance............................................................................. ................ .................18 5.05 Acceptance of Bonds and Insurance; Option to Replace........... ........ . ..................................19 Article 6—Contractor's Responsibilities............ .................. ............ ........... . ............ ............... .19 6.01 Supervision and Superintendence...............................................................................................19 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnrry 2,20I6 6.02 Labor;Working Hours...........................................................................:. ................................,20 6.03 Services,Materials,and Equipment......................:....................................................................20 6.04 Project Schedule.. ...... ... ... .... .........................................................................................21 6.05 Substitutes and"Or-Equals"...... ...............................................................................................21 6.06 Concerning Subcontractors, Suppliers,and Others. . ......................................................... ....24 6.07 Wage Rates..................................................................................................................................25 ~� 6.08 Patent Fees and Royalties. ....... ....._. .,.. ....... ....... ........ ................................................26 6.09 Permits and Utilities....................................................................................................................27 6.10 Laws and Regulations.....,........ ... ....... ...... .................................................... . ........ . .. ...27 6.11 Taxes...........4... ........................................................................................................................28 6.12 Use of Site and Other Areas.................................... . .. ............ . .... ........ ........................28 ..... . . .... ..... .. 6.13 Record Documents................................................................................................... 29 6.14 Safety and Protection..................................................................... ............................................29 6.15 Safety Representative......................... . .................. , .................. ... ......... .... .............30 6.16 Hazard Communication Programs .............................................................................................30 6.17 Emergencies and/or Rectification............................. 6.18 Submittals....................................................................................................................................31 6.19 Continuing the Work....................................................... ............................ ........................ .32 6.20 Contractor's General Warranty and Guarantee..........................................................................32 6.21 Indemnification..........................................................................................................................33 6.22 Delegation of Professional Design Services........................................................................... ..34 6.23 Right to Audit..............................................................................................................................34 6.24 Nondiscrimination.............. ........ ............ .............................,.. ,..... ................. ....... ..........35 Article 7-Other Work at the Site................................... .. ............... . ..............................................35 7.01 Related Work at Site....................... ....................... ...................................................................35 7.02 Coordination......................................................... .. ...................................... .. .. .............. ...36 Article 8-City's Responsibilities...................................................................................................................36 8.01 Communications to Contractor............................ ..... .. ................................................ .....36 8.02 Furnish Data................................................................. ..............................................................36 8.03 Pay When Due.................................... . ........................................ .. ................................ .36 8.04 Lands and Easements;Reports and Tests...................................................................................36 8.05 Change Orders......................... . ......................... ........... . ............... .. ..................... .. ...36 8.06 Inspections,Tests,and Approvals..............................................................................................36 8.07 Limitations on City's Responsibilities.................................................... . ...............................37 8.08 Undisclosed Hazardous Environmental Condition................ ................................................37 8.09 Compliance with Safety Program...............................................................................................37 Article 9-City's Observation Status During Construction...........................................................................37 9.01 City's Project Manager..................................... . .......................... ......................................37 .� 9.02 Visits to Site................................................................................................................................37 9.03 Authorized Variations in Work....................................................................... .............. ..... . .38 9.04 Rejecting Defective Work................................................................................................. . .....38 �- 9.05 Determinations for Work Performed............... ......... ......................................................... .38 9.06 Decisions on Requirements of Contract Documents and Acceptability of Work.....................38 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febney2,2016 _ Article 10-Changes T��ra��mzk,-.--.~'~~-,~~---...~.'-...^.---'.-..,.-,-...'__^.]@ �m r 10J01Authorized Changes iothe Work...............................................................................................]@ }0{�2 Unauthorized Changes iuthe Wnck.....................................-......._-........................... ~........3g }0.03 Execution of ....~......,..~-.~.--.^^_,,-..^.^,._.-....-_~-,..^^...-.,,..--,......39 -- 10.04 Extra Work,-_�.''.................... ~_._ ........ ..................................................-'-........... ..............3g }0J]5Notification tmSurety_,,.~~~_~,,,,_~^,^,.,,,^^^_^^^,__^_,^^^,^_,^__.^,.,,_,,,^^~^,_~^.,,^,^'.,,..^^.^^,~..]9 40 10.06 (�mu1ractCl�z�mProcess_-._-_--'�-....-._-_.-.-~.-.~.-.-'_.~~.--.-..~-.---^.---'--.' ~~ Article ll -Cost nfthe Work: Unit Price Work;Plans -.-..-.......4} }}J]l Cost mfthe Work.................................................................................. ...................�~,,-~'.~~'4} ~- }}.02 Allowances..................................................................................................................................4] }1.0] Unit Price Work.............................................................................................................-...........44 11.04 Plans Quantity Measurement...,.'-.-..,...'.',,-.-._.'...-~,--..-~-.-....'.'-~'.~..~-........-...'45 ~~ Article 12-Change ofContract Price; Change mfContract Time.................................................................46 12.)} Change ofContract Price............................................................................................................46 12.02 Change of Contract Time........................................... ................................................................47 }2.0] Delays____--.~--'._,_-~.~._^'.-_.,-..~..-..-~._-..-~.-'...-_'.---..',.'.-......~_,----''.-~..4? _ Article }]-TeotOazxd Removal or Acceptance ufDefective Work......................48 13.01 Notice ofDefects .--',.--.----.-.-,'......-.---.~-~.-..--'.,...~--...'.....-.~'.,-.,.-..-..'48 13'02 Access to Work...........................................................................................~.............................48 ~� 13.03 Tests and Inspections-..-'...,-.~,-.-..'~.-..--.-..-.^~--'....-,.-...°_~~'.,..^,..-..^----.,-..^48 }].04 .-.._..'-~-.-'~-.-..-'-.--.,-_,--,~-~,.-....---'.~.-.-'..-,~-.'_'.'49 13.05 City May Stop the Work..............................................................................................................4g m� }].06 Correction orRemoval ufDefective Work................................................................................50 }]'07 Correction Period............ ~ ........... ............................................................................................50 13.08 Acceptance ufDefective Work.............. ..................................................................,..................5l - }].09 City May Correct Defective Work....................................................................................... ^.^.5} Article }4-Payments tnContractor and Completion.................... ...............................................................5Z 14.01 Schedule Schedo}emfValues......................................................................................................................52 14.02 Progress Payments_---'__,_-_-_'.'.-^--'~-~.'__-__-~^-_-~.'--.'~_^-__''_~--.--^^-_-.'-~~'52 14.03 Contractor's Warranty ofTitle...................................................................................................54 }4J)4Partial T}tilimzti0n--~...... ..................................................... ..................................................~55 14]05 Final Inspection.............-..................................................................... ~~.'__~~'-.--~~..~'~.-.'55 ~~ }4j}6 FinalAcceptance-.......................................... ......... ...............................a..................................55 14.07 Final ............. ....................................................................................................... .......56 14.08 Final Completion Delayed and Partial Retainage,Release........................................................56 14.09 Waiver ofClaims...............................................................................................^..................-^`'57 Article }5-Suspension mfWork and Termination........................................................................................57 15.01 City May Suspend Work.............................. .........,..........................^.......................................57 l5 �� City May 58 ' -_� ---' ~'_�'~-.-~---.-_.-..-_^-'~'---,-.--.---'..~~~~~---'----� }5_0] City May Terminate For Convenience.................................................................................... -60 Article16-Dispute Resolution......................................................................................................................6l 16.01 Methods and Procedures.............................................................................................................6} =° CITY opFORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS oevimon:skumy2,20\e in .� Article 17—Miscellaneous......... ........ .................., .......................... . ........ . ..................., ..................62 17.01 Giving Notice....... . ....... .................... .................... . .................................. ...... ..................62 17.02 Computation of Times.................................. . ..................................... ............................62 +.� 17.03 Cumulative Remedies.. ..............................................................................................................62 17.04 Survival of Obligations............. ................... ..... ... ... .. ... ........... .... .. ........ ...................63 17.05 Headings...... .......... ..... . ......... t.. . .......................................................... ........63 A. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS "'"� Revision:FebnimyZ20I6 007200-1 GENERAL CONDITIONS Page I of 63 ARTICLE 1 –DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct,or change the Bidding Requirements or the proposed Contract Documents. 2. Agreement—The written instrument which is evidence of the agreement between City and Contractor covering the Work. 3. Application for Payment—The form acceptable to City which is to be used by Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents. 4. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. S. Award–Authorization by the City Council for the City to enter into an Agreement. 6. Bid-The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed. 7. Bidder—The individual or entity who submits a Bid directly to City. 8. Bidding Documents—The Bidding Requirements and the proposed Contract Documents (including all Addenda). 9. Bidding Requirements—The advertisement or Invitation to Bid, Instructions to Bidders, Bid security of acceptable form,if any, and the Bid Form with any supplements. 10. Business Day –A business day is defined as a day that the City conducts normal business, generally Monday through Friday,except for federal or state holidays observed by the City. 11. Buzzsaw–City's on-line,electronic document management and collaboration system. 12. Calendar Day–A day consisting of 24 hours measured from midnight to the next midnight. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnmry2,2016 007200-1 GENERAL CONDITIONS Page 2 of 63 13. Change Order—A document, which is prepared and approved by the City, which is signed °- by Contractor and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 14. City— The City of Fort Worth, Texas, a home-Wile municipal corporation, authorized and chartered under the Texas State Statutes, acting by its governing body through its City Manager, his designee, or agents authorized under his behalf, each of which is required by Charter to perform specific duties with responsibility for final enforcement of the contracts involving the City of Fort Worth is by Charter vested in the City Manager and is the entity with whom Contractor has entered into the Agreement and for whom the Work is to be performed. 15. City Attorney-The officially appointed City Attorney of the City of Fort Worth, Texas, or his duly authorized representative. 16. City Council - The duly elected and qualified governing body of the City of Fort Worth, Texas. 17. City Manager - The officially appointed and authorized City Manager of the City of Fort Worth, Texas,or his duly authorized representative. - 18. Contract Claim—A demand or assertion by City or Contractor seeking an adjustment of Contract Price or Contract Time, or both, or other relief with respect to the terms of the Contract.A demand for money or services by a third party is not a Contract Claim. 19. Contract—The entire and integrated written document between the City and Contractor concerning the Work. The Contract contains the Agreement and all Contract Documents and supersedes prior negotiations,representations,or agreements,whether written or oral. 20. Contract Documents—Those items so designated in the Agreement. All items listed in the Agreement are Contract Documents. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 21. Contract Price The moneys payable by City to Contractor for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of Paragraph 11.03 in the case of Unit Price Work). 22. Contract Time The number of days or the dates stated in the Agreement to: (i) achieve Milestones,if any and(ii)complete the Work so that it is ready for Final Acceptance. 23. Contractor—The individual or entity with whom City has entered into the Agreement. -Y 24. Cost of the Work--See Paragraph 11.01 of these General Conditions for definition. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Feb iny2,2016 0072 00-1 GENERAL CONDITIONS Page 3 of 63 25. Damage Claims — A demand for money or services arising from the Project or Site from a third parry, City or Contractor exclusive of a Contract Claim. �. 26. Day or day—A day,unless otherwise defined, shall mean a Calendar Day. 27. Director of Aviation — The officially appointed Director of the Aviation Department of the City of Fort Worth,Texas,or his duly appointed representative,assistant,or agents. 28. Director of Parks and Community Services— The officially appointed Director of the Parks and Community Services Department of the City of Fort Worth, Texas, or his duly appointed representative, assistant,or agents. 29. Director of Planning and Development— The officially appointed Director of the Planning and Development Department of the City of Fort Worth, Texas, or his duly appointed representative,assistant,or agents. 30.Director of Transportation Public Works — The officially appointed Director of the Transportation Public Works Department of the City of Fort Worth, Texas, or his duly appointed representative,assistant,or agents. 31. Director of Water Department—The officially appointed Director of the Water Department of the City of Fort Worth,Texas,or his duly appointed representative,assistant,or agents. 32. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 33. Effective Date of the Agreement—The date indicated in the Agreement on which it becomes effective,but if no such date is indicated, it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver. 34.Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the City. 35. Extra Work — Additional work made necessary by changes or alterations of the Contract Documents or of quantities or for other reasons for which no prices are provided in the Contract Documents.Extra work shall be part of the Work. 36.Field Order—A written order issued by City which requires changes in the Work but which does not involve a change in the Contract Price, Contract Time, or the intent of the Engineer. Field Orders are paid from Field Order Allowances incorporated into the Contract,by funded work type at the time of award. 37. Final Acceptance -- The written notice given by the City to the Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Februaty2,2016 007200-1 GENERAL CONDITIONS Page 4 of 63 38. Final Inspection — Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 39. General Requirements—Sections of Division 1 of the Contract Documents. 40. Hazardous Environmental Condition—The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, Radioactive Material; or other materials in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto. 41. Hazardous Waste—Hazardous waste is defined as any solid waste listed as hazardous or possesses one or more hazardous characteristics as defined in the federal waste regulations, as amended from time to time. 42. Laws and Regulations Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 43. Liens--Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 44. Major Item—An Item of work included in the Contract Documents that has a total cost equal to or greater than 5%of the original Contract Price or$25,000 whichever is less. 45.Milestone—A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 46. Notice of Award-The written notice by City to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed therein, City will sign and deliver the Agreement. 47. Notice to Proceed—A written notice given by City to Contractor fixing the date on which the Contract Time will commence to run and on which Contractor shall start to perform the Work specified in Contract Documents. ._ 48. PCBs—Polychlorinated biphenyls. 49. Petroleum Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and crude oils. 50. Plans—See definition of Drawings. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febn=yZ 2016 0072 00-1 GENERAL CONDITIONS Page 5 of 63 51.Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor's plan to accomplish the Work within the Contract Time. 52. Project—The Work to be performed under the Contract Documents. 53. Project Manager—The authorized representative of the City who will be assigned to the Site. 54.Public Meeting – An announced meeting conducted by the City to facilitate public participation and to assist the public in gaining an informed view of the Project. 55. Radioactive Material—Source, special nuclear, or byproduct material as defined by the Atomic Energy Act of 1954(42 USC Section 2011 et seq.) as amended from time to time. 56. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday(excluding legal holidays). 57. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. 58. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 59. Schedule of Values—A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment. 60. Site—Lands or areas indicated in the Contract Documents as being furnished by City upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City which are designated for the use of Contractor. 61. Specifications That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 62. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:FdxutayZ2016 007200-1 GENERAL CONDITIONS Page 6 of 63 me 63. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. .. 64. Successful Bidder—The Bidder submitting the lowest and most responsive Bid to whom City makes an Award. �. 65. Superintendent— The representative of the Contractor who is available at all times and able to receive instructions from the City and to act for the Contractor. 66. Supplementary Conditions—That part of the Contract Documents which amends or supplements these General Conditions. 67. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 68. Underground Facilities All underground pipelines, conduits, ducts, cables, wires, manholes, vaults,tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water,wastewater,storm water,other liquids or chemicals,or traffic or other control systems. 69. Unit Price Work—See Paragraph 11.03 of these General Conditions for definition. 70. Weekend Working Hours— Hours beginning at 9:00 a.m, and ending at 5:00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. 71. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Change Order or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction,all as required by the Contract Documents. ,., 72. Working Day—A working day is defined as a day,not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m.and 6 p.m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.B through E are not defined but, when used in the Bidding Requirements or Contract Documents,have the indicated meaning. B. Intent of Certain Terms or Adjectives: CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:FebruaryZ 2016 00 7200-1 GENERAL CONDITIONS Page 7 of 63 1. The Contract Documents include the terms "as allowed," "as approved," as ordered," "as directed" or terms of like effect or import to authorize an exercise of judgment by City. In addition, the adjectives "reasonable," "suitable," "acceptable," "proper," "satisfactory," or adjectives of like effect or import are used to describe an action or determination of City as to the Work. It is intended that such exercise of professional judgment, action, or determination will be solely to evaluate, in general, the Work for compliance with the information in the Contract Documents and with the design concept of the Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). C. Defective: _. 1. The word "defective," when modifying the word "Work," refers to Work that is unsatisfactory,faulty,or deficient in that it: • a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or �. approval referred to in the Contract Documents; or c. has been damaged prior to City's written acceptance. D. Furnish, Install, Perform, Provide: 1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or the word "Supply," or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. E. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. ARTICLE 2—PRELIMINARY MATTERS 2.01 Copies of Documents City shall furnish to Contractor one (1) original executed copy and one (1) electronic copy of the Contract Documents, and four (4) additional copies of the Drawings. Additional copies will be furnished upon request at the cost of reproduction. 2.02 Commencement of Contract Time; Notice to Proceed The Contract Time will commence to ran on the day indicated in the Notice to Proceed. A Notice to Proceed may be given at any time within 14 days after the Effective Date of the Agreement. MR CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febivary2,2016 '"` 007200-1 GENERAL CONDITIONS Page 8 of 63 2.03 Starting the Work Contractor shall start to perform the Work on the date when the Contract Time commences to run. No Work shall be done at the Site prior to the date on which the Contract Time commences to run. 2.04 Before Starting Construction Baseline Schedules: Submit in accordance with the Contract Documents, and prior to starting the Work. 2.05 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.06 Public Meeting .. Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. 2.07 Initial Acceptance of Schedules No progress payment shall be made to Contractor until acceptable schedules are submitted to City in accordance with the Schedule Specification as provided in the Contract Documents. ARTICLE 3—CONTRACT DOCUMENTS. INTENT,AMENDING,REUSE 3.01 Intent A. The Contract Documents are complementary; what is required by one is as binding as if required by all. B. It is the intent of the Contract Documents to describe a functionally complete project (or part thereof) to be constructed in accordance with the Contract Documents. Any labor, documentation, services, materials, or equipment that reasonably may be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the indicated result will be provided whether or not specifically called for, at no additional cost to City. C. Clarifications and interpretations of the Contract Documents shall be issued by City. D. The Specifications may vary in form, format and style. Some Specification sections may be written in varying degrees of streamlined or declarative style and some sections may be relatively narrative by comparison. Omission of such words and phrases as "the Contractor shall," "in conformity with," "as shown," or "as specified" are intentional in streamlined sections. Omitted words and phrases shall be supplied by inference. Similar types of provisions may appear in various parts of a section or articles within a part depending on the format of the CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnoy2,2016 007200-1 GENERAL CONDITIONS Page 9 of 63 section. The Contractor shall not take advantage of any variation of form, format or style in making Contract Claims. . E. The cross referencing of specification sections under the subparagraph heading "Related Sections include but are not necessarily limited to:" and elsewhere within each Specification section is provided as an aid and convenience to the Contractor. The Contractor shall not rely on the cross referencing provided and shall be responsible to coordinate the entire Work under the Contract Documents and provide a complete Project whether or not the cross referencing is � provided in each section or whether or not the cross referencing is complete. 3.02 Reference Standards �. A. Standards, Specifications,Codes,Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations,whether such reference be specific or by implication, shall mean the standard, specification,manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids),except as may be otherwise specifically stated in the Contract Documents. 2. No provision of any such standard, specification, manual, or code, or any instruction of a Supplier, shall be effective to change the duties or responsibilities of City, Contractor, or any of their subcontractors, consultants, agents, or employees, from those set forth in the Contract Documents. No such provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.03 Reporting and Resolving Discrepancies A. Reporting Discrepancies: 1. Contractor's Review of Contract Documents Before Starting Work: Before undertaking each part of the Work, Contractor shall carefully study and compare the Contract Documents and check and verify pertinent figures therein against all applicable field measurements and conditions. Contractor shall promptly report in writing to City any conflict, error, ambiguity, or discrepancy which Contractor discovers, or has actual knowledge of, and shall obtain a written interpretation or clarification from City before proceeding with any Work affected .- thereby. 2. Contractor's Review of Contract Documents During Performance of Work. If, during the ._ performance of the Work, Contractor discovers any conflict, error, ambiguity, or discrepancy within the Contract Documents, or between the Contract Documents and (a) any applicable Law or Regulation , (b) any standard, specification,manual, or code, or (c) any instruction of any Supplier, then Contractor shall promptly report it to City in writing. Contractor shall not proceed with the Work affected thereby (except in an emergency as required by Paragraph CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS e Revision:Febnoy2,2016 007200-1 GENERAL CONDITIONS Page 10 of 63 6.17.A) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in Paragraph 3.04. 3. Contractor shall not be liable to City for failure to report any conflict, error, ambiguity, or discrepancy in the Contract Documents unless Contractor had actual knowledge thereof. B. Resolving Discrepancies: 1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Contract Documents and the provisions of any standard, specification,manual, or the instruction of any Supplier (whether or not specifically incorporated by reference in the Contract Documents). 2. In case of discrepancies, figured dimensions shall govern over scaled dimensions, Plans shall govern over Specifications, Supplementary Conditions shall govern over General Conditions and Specifications, and quantities shown on the Plans shall govern over those shown in the proposal. 3.04 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized,by one or more of the following ways: 1. A Field Order; 2. City's review of a Submittal (subject to the provisions of Paragraph 6.18.C); or 3. City's written interpretation or clarification. 3.05 Reuse of Documents A. Contractor and any Subcontractor or Supplier shall not: 1. have or acquire any title to or ownership rights in any of the Drawings, Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer, including electronic media editions;or 2. reuse any such Drawings, Specifications,other documents, or copies thereof on extensions of the Project or any other project without written consent of City and specific written verification or adaptation by Engineer. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febm 82,2016 00 72 00-1 GENERAL CONDITIONS Page I i of 63 B. The prohibitions of this Paragraph 3.05 will survive final payment, or termination of the Contract. Nothing herein shall preclude Contractor from retaining copies of the Contract Documents for record purposes. 3.06 Electronic Data A. Unless otherwise stated in the Supplementary Conditions, the data furnished by City or Engineer to Contractor, or by Contractor to City or Engineer, that may be relied upon are limited to the printed copies included in the Contract Documents (also known as hard copies) and other Specifications referenced and located on the City's Buzzsaw site. Files in electronic media format of text, data, graphics, or other types are furnished only for the convenience of the receiving party. Any conclusion or information obtained or derived from such electronic files will be at the user's sole risk. If there is a discrepancy between the electronic files and the hard copies,the hard copies govern. B. When transferring documents in electronic media format, the transferring party makes no representations as to long term compatibility, usability, or readability of documents resulting from the use of software application packages, operating systems, or computer hardware differing from those used by the data's creator. ARTICLE 4—AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS 4.01 Availability of Lands A. City shall furnish the Site. City shall notify Contractor of any encumbrances or restrictions not of general application but specifically related to use of the Site with which Contractor must comply in performing the Work. City will obtain in a timely manner and pay for easements for permanent structures or permanent changes in existing facilities. 1. The City has obtained or anticipates acquisition of and/or access to right-of-way, and/or easements. Any outstanding right-of-way and/or easements are anticipated to be acquired in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding right-of-way, and/or easements. 2. The City has or anticipates removing and/or relocating utilities, and obstructions to the Site. Any outstanding removal or relocation of utilities or obstructions is anticipated in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding utilities,or obstructions to be removed,adjusted,and/or relocated by others. B. Upon reasonable written request, City shall fizrnish Contractor with a current statement of record legal title and legal description of the lands upon which the Work is to be performed. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Fdxuary2,201.6 """ 007200-I GENERAL CONDITIONS Page 12 of 63 C. Contractor shall provide for all additional lands and access thereto that may be required for construction facilities or storage of materials and equipment. 4.02 Subsurface and Physical Conditions A. Reports andDrawings: The Supplementary Conditions identify: 1. those reports known to City of explorations and tests of subsurface conditions at or contiguous to the Site; and 2. those drawings known to City of physical conditions relating to existing surface or subsurface structures at the Site(except Underground Facilities). B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Supplementary Conditions, Contractor may not make any Contract Claim against City, or any of their officers, directors,members,partners,employees, agents, consultants, or subcontractors with respect to: 1. the completeness of such reports and drawings for Contractor's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto;or 2. other data, interpretations, opinions, and information contained in such reports or shown or indicated in such drawings;or 3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such other data,interpretations,opinions, or information. 4.03 Differing Subsurface or Physical Conditions A. Notice: If Contractor believes that any subsurface or physical condition that is uncovered or revealed either: 1. is of such a nature as to establish that any "technical data" on which Contractor is entitled to rely as provided in Paragraph 4.02 is materially inaccurate; or 2. is of such a nature as to require a change in the Contract Documents; or 3. differs materially from that shown or indicated in the Contract Documents; or 4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract " Documents; CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnmry2,2016 007200-1 GENERAL CONDITIONS Page 13 of 63 then Contractor shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical conditions or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.17.A),notify City in writing about such condition. B. Possible Price and Time Adjustments Contractor shall not be entitled to any adjustment in the Contract Price or Contract Time if. 1. Contractor knew of the existence of such conditions at the time Contractor made a final commitment to City with respect to Contract Price and Contract Time by the submission of a Bid or becoming bound under a negotiated contract;or 2. the existence of such condition could reasonably have been discovered or revealed as a result of the examination of the Contract Documents or the Site; or 3. Contractor failed to give the written notice as required by Paragraph 4.03.A. 4.04 Underground Facilities A. Shown or Indicated.• The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the Site is based on information and data furnished to City or Engineer by the owners of such Underground Facilities, including City, or by others. Unless it is otherwise expressly provided in the Supplementary Conditions: 1. City and Engineer shall not be responsible for the accuracy or completeness of any such information or data provided by others; and 2. the cost of all of the following will be included in the Contract Price, and Contractor shall have full responsibility for: a. reviewing and checking all such information and data; b. locating all Underground Facilities shown or indicated in the Contract Documents; c. coordination and adjustment of the Work with the owners of such Underground Facilities,including City,during construction; and d. the safety and protection of all such Underground Facilities and repairing any damage thereto resulting from the Work. B. Not Shown or Indicated.- 1. If an Underground Facility which conflicts with the Work is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnny2,2016 „� 007200-1 GENERAL CONDITIONS Page 14 of 63 Work in connection therewith (except in an emergency as required by Paragraph 6.17.A), identify the owner of such Underground Facility and give notice to that owner and to City. City will review the discovered Underground Facility and determine the extent, if any, to which a change may be required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. Contractor shall be responsible for the safety and protection of such discovered Underground Facility. 2. If City concludes that a change in the Contract Documents is required, a Change Order may be issued to reflect and document such consequences. • 3. Verification of existing utilities, structures, and service lines shall include notification of all utility companies a minimum of 48 hours in advance of construction including exploratory excavation if necessary. 4.05 Reference Points A. City shall provide engineering surveys to establish reference points for construction, which in City's judgment are necessary to enable Contractor to proceed with the Work. City will provide construction stakes or other customary method of marking to establish line and grades for roadway and utility construction, centerlines and benchmarks for bridgework. Contractor shall protect and preserve the established reference points and property monuments, and shall make no changes or relocations. Contractor shall report to City whenever any reference point or property monument is lost or destroyed or requires relocation because of necessary changes in grades or locations. The City shall be responsible for the replacement or relocation of reference points or property monuments not carelessly or willfully destroyed by the Contractor. The Contractor shall notify City in advance and with sufficient time to avoid delays. B. Whenever, in the opinion of the City, any reference point or monument has been carelessly or willfully destroyed, disturbed, or removed by the Contractor or any of his employees, the full cost for replacing such points plus 25% will be charged against the Contractor, and the full amount will be deducted from payment due the Contractor. 4.06 Hazardous Environmental Condition at Site A. Reports and Drawings: The Supplementary Conditions identify those reports and drawings known to City relating to Hazardous Environmental Conditions that have been identified at the Site. B. Limited Reliance by Contractor on Technical Data Authorized.• Contractor may rely,upon the accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Supplementary Conditions. Contractor may not make any Contract Claim against City, or any of their officers, directors,members,partners,employees, agents,consultants,or subcontractors with respect to: 1. the completeness of such reports and drawings for Contractor's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of CITY OF FORT WORTH ..� STANDARD CONSTRUCTION SPECIFICATION DOCUN ENTS Revision:Fdm=yZ2016 00 72 00-1 GENERAL CONDITIONS Page 15 of 63 construction to be employed by Contractor and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings; or .. 3. any Contractor interpretation of or conclusion drawn from any "technical data' or any such other data,interpretations,opinions or information. �. C. Contractor shall not be responsible for any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work. Contractor shall be responsible for a Hazardous Environmental Condition created with any materials brought to the Site by Contractor, Subcontractors, Suppliers, or anyone else for whom Contractor is responsible. ,. D. If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone for whom Contractor is responsible creates a Hazardous Environmental Condition, Contractor shall immediately: (i) secure or otherwise isolate such condition; (ii) stop all Work in connection with such condition and in any area affected thereby (except in an emergency as required by Paragraph 6.17.A); and (iii) notify City(and promptly thereafter confirm such notice in writing). City may consider the necessity to retain a qualified expert to evaluate such condition or take corrective action,if any. E. Contractor shall not be required to resume Work in connection with such condition or in any affected area until after City has obtained any required permits related thereto and delivered written notice to Contractor: (i) specifying that such condition and any affected area is or has been rendered suitable for the resumption of Work; or (ii) specifying any special conditions under which such Work may be resumed. F. If after receipt of such written notice Contractor does not agree to resume such Work based on a reasonable belief it is unsafe, or does not agree to resume such Work under such special conditions, then City may order the portion of the Work that is in the area affected by such condition to be deleted from the Work. City may have such deleted portion of the Work performed by City's own forces or others. G. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City,from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court �- or arbitration or other dispute resolution costs) arising out of or relating to a Hazardous Environmental Condition created by Contractor or by anyone for whom Contractor is responsible. Nothing in this Paragraph 4.06.0 shall obligate Contractor to indemnify any .� individual or entity from and against the consequences of that individual's or entity's own negligence. H. The provisions of Paragraphs 4.02, 4.03, and 4.04 do not apply to a Hazardous Environmental Condition uncovered or revealed at the Site. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS ... Revision:Febnkvy2,2016 007200-1 GENERAL CONDITIONS Page 16 of 63 ARTICLE 5--BONDS AND INSURANCE 5.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverages so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 5.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor's obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of"Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury, All bonds signed by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney-in-fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 5.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 5.01 and 5.02.C. 5.03 Certificates of Insurance Contractor shall deliver to City, with copies to each additional insured and loss payee identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by City or any other additional insured)which Contractor is required to purchase and maintain. 1. The certificate of insurance shall document the City, and all identified entities named in the Supplementary Conditions as"Additional Insured"on all liability policies. CITY OF FORT WORTH �., STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febney2,2016 007200-1 GENERAL CONDITIONS Page 17 of 63 2. The Contractor's general liability insurance shall include a, "per project" or "per location', endorsement,which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M.Best Property&Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers' compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required,written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in the Supplementary Conditions 6. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor's obligation to maintain such lines of insurance coverage. 7. If insurance policies are not written for specified coverage limits, an Umbrella or Excess .� Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 8. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If coverage is underwritten on a claims-made basis,the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims-made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 9. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 10. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In CTTY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Fdx uay2,2016 007200-1 GENERAL CONDITIONS Page 18 of 63 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk .. retention groups,must also be approved by City. 11. Any deductible in excess of$5,000.00, for any policy that does not provide coverage on a first-dollar basis,must be acceptable to and approved by the City. 12. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage's and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 13. City shall be entitled, upon written request and without expense,to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to -• conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 14. City shall not be responsible for the direct payment of insurance premium costs for Contractor's insurance. 5.04 Contractor's Insurance A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers' Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers' Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor's performance of the Work and Contractor's other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers' compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor's employees. B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations,personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Fdmmy2,2016 007200-1 .� GENERAL CONDITIONS Page 19 of 63 insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, .®. products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy,unless the City approves such exclusions in writing. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project (if identified in the Supplementary _ Conditions). C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto", defined as autos owned, hired and non-owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the requirements identified in the Supplementary Conditions. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has - been procured.There shall be no time credit for days not worked pursuant to this section. 5.05 Acceptance of Bonds and Insurance; Option to Replace �- If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the City may — reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 6—CONTRACTOR'S RESPONSIBILITIES - 6.01 Supervision and Superintendence A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means,methods,techniques,sequences, and procedures of construction. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febm"2,2016 007200-I GENERAL CONDITIONS Page 20 of 63 B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor's representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 6.02 Labor, Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract.Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City's written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication)to perform Work: �. 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 6.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume fu11 responsibility for all services, materials, equipment, labor, transportation, construction equipment �. and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing,start-up,and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests)as to the source,kind, and quality of materials and equipment. CITY OF FORT WORTH �. STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:.FebnuaryZ 2016 007200-1 GENERAL CONDITIONS Page 21 of 63 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier,except as otherwise may be provided in the Contract Documents. D. All items of standard equipment to be incorporated into the Work shall be the latest model at the time of bid,unless otherwise specified. 6.04 Project Schedule ,. A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.07 and the General Requirements as it may be adjusted from time to time as provided below. _. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.07 and the General Requirements) proposed adjustments in the Project Schedule that will not result in changing the Contract Time. Such adjustments will comply with any provisions of the General Requirements applicable thereto. 2. Contractor shall submit to City a monthly Project Schedule with a monthly progress payment for the duration of the Contract in accordance with the schedule specification 0132 16. 3. Proposed adjustments in the Project Schedule that will change the Contract Time shall be �. submitted in accordance with the requirements of Article 12. Adjustments in Contract Time may only be made by a Change Order. 6.05 Substitutes and "Or-Equals" A. Whenever an item of material or equipment is specified or described in the Contract Documents _ by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or "or-equal" item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. "Or-Equal"Items: If in City's sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an "or-equal" item, in which case review and approval of the proposed item may, in City's sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 6.05.A.1, a proposed item of material or-equipment will be considered functionally equal to an item so named if: a. the City determines that: — 1) it is at least equal in materials of construction, quality, durability, appearance, strength,and design characteristics; CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS . Revision:Fdmm y2,2016 007200-1 GENERAL CONDITIONS Page 22 of 63 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that,if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time;and 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City's sole discretion an item of material or equipment proposed by Contractor does not qualify as an "or-equal" item under Paragraph 6.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 0125 00 and: 1) shall certify that the proposed substitute item will: a) perform adequately the functions and achieve the results called for by the general design; b) be similar in substance to that specified; c) be suited to the same use as that specified;and 2) will state: a) the extent, if any, to which the use of the proposed substitute item will prejudice Contractor's achievement of final completion on time; b) whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Feb umy2,2016 007200-1 �. GENERAL CONDITIONS Page 23 of 63 c) whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: a) all variations of the proposed substitute item from that specified; b) available engineering, sales,maintenance,repair,and replacement services;and 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City's sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 6.05.A.2. C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 6.05.A and 6.05.B. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability.No "or-equal" or substitute will be ordered, installed or utilized until City's review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an"or-equal."City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or .. submitted by Contractor pursuant to Paragraphs 6.05.A.2 and 6.05.B. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents (or in the provisions of any other direct contract with City)resulting from the acceptance of each proposed substitute. F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or "or-equal"at Contractor's expense. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revisions Febnoy2,2016 007200-1 GENERAL CONDITIONS Page 24 of 63 G. City Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Change Order. H. Time Extensions: No additional time will be granted for substitutions. 6.06 Concerning Subcontractors, Suppliers, and Others A. Contractor shall perform with his own organization, work of a value not less than 35% of the value embraced on the Contract,unless otherwise approved by the City. B. Contractor shall not employ any Subcontractor, Supplier, or other individual or entity, whether initially or as a replacement, against whom City may have reasonable objection. Contractor shall not be required to employ any Subcontractor, Supplier, or other individual or entity to furnish or perform any of the Work against whom Contractor has reasonable objection (excluding those acceptable to City as indicated in Paragraph 6.06.C). C. The City may from time to time require the use of certain Subcontractors, Suppliers, or other individuals or entities on the project, and will provide such requirements in the Supplementary Conditions. — D. Minority Business Enterprise Compliance: It is City policy to ensure the full and equitable participation by Minority Business Enterprises (MBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MBE goal, Contractor is required to comply with the intent of the City's MBE Ordinance(as amended)by the following: 1. Contractor shall, upon request by City, provide complete and accurate information regarding actual work performed by a MBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the -� Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, .� records, or files in the possession of the Contractor that will substantiate the actual work performed by an MBE. Material misrepresentation of any nature will be grounds for termination of the Contract in accordance with Paragraph 15.02.A. Any such misrepresentation may be grounds for disqualification of Contractor to bid on future contracts with the City for a period of not less than three years. E. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract Documents: CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Fdxue y2,2016 007200-1 GENERAL CONDITIONS Page 25 of 63 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other �.. individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys �. due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. F. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. G. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. H. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically ... binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the benefit of City. 6.07 Wage Rates A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258,Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its .. administrative costs,pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, .� including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31 st day after the date the City receives the information, as to whether ..� good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City's determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:.Fdxiny2,2016 00 72 00-1 GENERAL CONDITIONS Page 26 of 63 D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act(Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show(i) the name and occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii)the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit,shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258,Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 6.08 Patent Fees and Royalties A. Contractor shall pay all license fees and royalties and assume all costs incident to the use in the ® performance of the Work or the incorporation in the Work of any invention, design, process, product, or device which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product, or device is specified in the Contract Documents for use in the performance of the Work and if, to the actual knowledge of City, its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by City in the Contract Documents. Failure of the City to disclose such information does not relieve the Contractor from its obligations to pay for the use of said fees or royalties to others. B. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City,from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnjmy2,2016 00 7200-1 GENERAL CONDITIONS Page 27 of 63 the incorporation in the Work of any invention, design,process,product, or device not specified in the Contract Documents. -- 6.09 Permits and Utilities A. Contractor obtained permits and licenses. Contractor shall obtain and pay for all construction permits and licenses except those provided for in the Supplementary Conditions or Contract Documents. City shall assist Contractor, when necessary,in obtaining such permits and licenses. Contractor shall pay all governmental charges and inspection fees necessary for the prosecution of the Work which are applicable at the time of opening of Bids, or, if there are no Bids, on the Effective Date of the Agreement, except for permits provided by the City as specified in 6.09.B. City shall pay all charges of utility owners for connections for providing permanent service to the Work. B. City obtained permits and licenses. City will obtain and pay for all permits and licenses as provided for in the Supplementary Conditions or Contract Documents. It will be the Contractor's responsibility to carry out the provisions of the permit. If the Contractor initiates changes to the �- Contract and the City approves the changes, the Contractor is responsible for obtaining clearances and coordinating with the appropriate regulatory agency. The City will not reimburse the Contractor for any cost associated with these requirements of any City acquired permit. The following are permits the City will obtain if required: 1. Texas Department of Transportation Permits 2. U.S.Army Corps of Engineers Permits 3. Texas Commission on Environmental Quality Permits 4. Railroad Company Permits C. Outstanding permits and licenses. The City anticipates acquisition of and/or access to permits and licenses. Any outstanding permits and licenses are anticipated to be acquired in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding permits and licenses. 6.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or .� Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnaay2,2016 007200-1 GENERAL CONDITIONS Page 28 of 63 court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor's responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor's obligations under Paragraph 3.02. C. Changes in Laws or Regulations not known at the time of opening of Bids having an effect on the cost or time of performance of the Work may be the subject of an adjustment in Contract Price or Contract Time. 6.11 Taxes A. On a contract awarded by the City, an organization which qualifies for exemption pursuant to Texas Tax Code, Subchapter H, Sections 151.301-335 (as amended), the Contractor may purchase, rent or lease all materials, supplies and equipment used or consumed in the performance of this contract by issuing to his supplier an exemption certificate in lieu of the tax, said exemption certificate to comply with State Comptroller's Ruling .007. Any such exemption certificate issued to the Contractor in lieu of the tax shall be subject to and shall comply with the provision of State Comptroller's Ruling .011, and any other applicable rulings pertaining to the Texas Tax Code,Subchapter H. B. Texas Tax permits and information may be obtained from: -- 1. Comptroller of Public Accounts Sales Tax Division Capitol Station Austin,TX 78711; or 2. http://www.window.state.tx.us/taxinfo/taxforms/93-fon-ns.html 6.12 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment,the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. CITY OF FORT WORTH. �r STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnoy2,201 b 007200-1 GENERAL CONDITIONS Page 29 of 63 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 6.21, Contractor shall indemnify and hold harmless City,from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and the costs of such direct action, plus 25 % of such costs,shall be deducted from the monies due or to become due to the Contractor. D. Final Site Cleaning.• Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 6.13 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders,Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 6.14 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall ..a CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Felmay2,2016 007200-1 GENERAL CONDITIONS Page 30 of 63 take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage,injury or loss to.- 1. o:1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site;and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal,relocation,or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal,relocation,and replacement of their property. C. Contractor shall comply with the applicable requirements of City's safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any, with which City's employees and representatives must comply while at the Site. E. All damage,injury, or loss to any property referred to in Paragraph 6.14.A.2 or 6.14.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual'or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 6.15 Safety Representative Contractor shall inform City in writing of Contractor's designated safety representative at the Site. 6.16 Hazard Communication Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 6.17 Emergencies and/or Rectification A. In emergencies affecting the safety or protection of persons or the Work or property at the Site or adjacent thereto, Contractor is obligated to act to prevent threatened damage, injury, or loss. Contractor shall give City prompt written notice if Contractor believes that any significant CITY OF FORT WORTH ,® STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:FebnimyZ 2016 007200-1. GENERAL CONDITIONS Page 31 of 63 changes in the Work or variations from the Contract Documents have been caused thereby or are required as a result thereof. If City determines that a change in the Contract Documents is required because of the action taken by Contractor in response to such an emergency, a Change Order may be issued. B. Should the Contractor fail to respond to a request from the City to rectify any discrepancies, omissions, or correction necessary to conform with the requirements of the Contract Documents, the City shall give the Contractor written notice that such work or changes are to be performed. . The written notice shall direct attention to the discrepant condition and request the Contractor to take remedial action to correct the condition. In the event the Contractor does not take positive steps to fulfill this written request, or does not show just cause for not taking the proper action, �. within 24 hours,the City may take such remedial action with City forces or by contract. The City shall deduct an amount equal to the entire costs for such remedial action, plus 25%, from any funds due or become due the Contractor on the Project. -� 6.18 Submittals A. Contractor shall submit required Submittals to City for review and acceptance in accordance with the accepted Schedule of Submittals (as required by Paragraph 2.07). Each submittal will be identified as City may require. �. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 6.18.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. .� 5. For-Information-Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier,pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 6.18.C. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnaay2,2016 007200-1 GENERAL CONDITIONS Page 32 of 63 B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City's review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City's Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City's review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 2. City's review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents)or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City's review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City's review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 6.19 Continuing the Work Except as otherwise provided, Contractor shall carry on the Work and adhere to the Project Schedule during all disputes or disagreements with City. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as City and Contractor may otherwise agree in writing. 6.20 Contractor's General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor's warranty and guarantee. B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse,modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible;or CITY OF FORT WORTH �+ STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnm y2,2016 00 72 00-1 . GENERAL CONDITIONS Page 33 of 63 2. normal wear and tear under normal usage. C. Contractor's obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute.None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor's obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection,test,or approval by others;or 7. any correction of defective Work by City. .. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 5.02.B. The City will give notice of observed defects with reasonable promptness. 6.21 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT AL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART. BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROMS ON IS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febaty2,2016 007200-1 GENERAL CONDITIONS Page 34 of 63 SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED. IN WHOLE OR IN PART. _BY ANY ACT. OMISSION OR NEGLIGENCE OF THE CITY. 6.22 Delegation gfPrgfessional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor's responsibilities for construction means, methods, techniques,sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose °— signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional's written approval when ` submitted to City. C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 6.22, City's review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City's review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 6.18.C. 6.23 Right to Audit A. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents,papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. B. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract,have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnoy2,2016 007200-1 GENERAL CONDITIONS Page 35 of 63 Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give .�. Subcontractor reasonable advance notice of intended audits. C. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 6.24 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit- _ related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. ARTICLE 7—OTHER WORK AT THE SITE _ 7.01 Related Work at Site A. City may perform other work related to the Project at the Site with City's employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work;and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City's employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor's Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor's Work. Contractor's failure to so _ report will constitute an acceptance of such other work as fit and proper for integration with Contractor's Work except for latent defects in the work provided by others. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS , Revision:Febnoy2,2016 007200-1 GENERAL CONDITIONS Page 36 of 63 7.02 Coordination A. If City intends to contract with others for the performance of other work on the Project at the Site,the following will be set forth in Supplementary Conditions: 1. the individual or entity who will have authority and responsibility for coordination of the activities among the various contractors will be identified; i 2. the specific matters to be covered by such authority and responsibility will be itemized; and 3. the extent of such authority and responsibilities will be provided. B. Unless otherwise provided in the Supplementary Conditions, City shall have authority for such coordination. ARTICLE 8—CITY'S RESPONSIBILITIES 8.01 Communications to Contractor Except as otherwise provided in the Supplementary Conditions, City shall issue all communications to Contractor. 8.02 Furnish Data City shall timely furnish the data required under the Contract Documents. 8.03 Pay When Due City shall make payments to Contractor in accordance with Article 14. 8.04 Lands and Easements,Reports and Tests +� City's duties with respect to providing lands and easements and providing engineering surveys to establish reference points are set forth in Paragraphs 4.01 and 4.05. Paragraph 4.02 refers to City's identifying and making available to Contractor copies of reports of explorations and tests of subsurface conditions and drawings of physical conditions relating to existing surface or subsurface structures at or contiguous to the Site that have been utilized by City in preparing the Contract Documents. 8.05 Change Orders •• City shall execute Change Orders in accordance with Paragraph 10.03. 8.06 Inspections, Tests, and Approvals City's responsibility with respect to certain inspections,tests, and approvals is set forth in Paragraph 13.03. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febauary2,2016 007200-I GENERAL CONDITIONS Page 37 of 63 8.07 Limitations on City's Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor's failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 6.14. 8.08 Undisclosed Hazardous Environmental Condition City's responsibility with respect to an undisclosed Hazardous Environmental Condition is set forth in Paragraph 4.06. 8.09 Compliance with Safety Program While at the Site, City's employees and representatives shall comply with the specific applicable requirements of Contractor's safety programs of which City has been informed pursuant to Paragraph 6.14. ARTICLE 9—CITY'S OBSERVATION STATUS DURING CONSTRUCTION 9.01 City's Project Manager City will provide one or more Project Manager(s) during the construction period. The duties and responsibilities and the limitations of authority of City's Project Manager during construction are set forth in the Contract Documents. The City's Project Manager for this Contract is <insert name here >, or his/her successor pursuant to written notification from the Director of < insert managing department here>. 9.02 Visits to Site A. City's Project Manager will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor's executed Work. Based on information obtained during such visits and observations, City's Project Manager will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City's Project Manager will not be required to make exhaustive or continuous inspections on.the Site to check the quality or quantity of the Work. City's Project Manager's efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City's Project Manager's visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents including those set forth in Paragraph 8.07. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Felxuay2,2016 007200-1 GENERAL CONDITIONS Page 38 of 63 9.03 Authorized Variations in Work City's Project Manager may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City and also on Contractor,who shall perform the Work involved promptly. 9.04 Rejecting Defective Work City will have authority to reject Work which City's Project Manager believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 13, whether or not the Work is fabricated, installed, or completed. 9.05 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City's Project � Manager will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City's written decision will be final (except as modified to reflect changed factual conditions or more accurate data). 9.06 Decisions on Requirements of Contract Documents and Acceptability of Work A. City will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. B. City will render a written decision on any issue referred. C. City's written decision on the issue referred will be final and binding on the Contractor, subject to the provisions of Paragraph 10.06. ARTICLE 10—CHANGES IN THE WORK; CLAIMS;EXTRA WORK 10.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price, a Field Order may be issued by the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnay2,2016 007200-1 GENERAL CONDITIONS Page 39 of 63 10.02 Unauthorized Changes in the Work Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Time with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented as provided in Paragraph 3.04, except in the case of an .. emergency as provided in Paragraph 6.17. 10.03 Execution of Change Orders A. City and Contractor shall.execute appropriate Change Orders covering: 1. changes in the Work which are: (i) ordered by City pursuant to Paragraph 10.01.A, (ii) required because of acceptance of defective Work under Paragraph 13.08 or City's correction of defective Work under Paragraph 13.09,or(iii)agreed to by the parties; 2. changes in the Contract Price or Contract Time which are agreed to by the parties, including any undisputed sum or amount of time for Work actually performed. 10.04 Extra Work A. Should a difference arise as to what does or does not constitute Extra Work, or as to the payment thereof, and the City insists upon its performance, the Contractor shall proceed with the work after making written request for written orders and shall keep accurate account of the actual reasonable cost thereof. Contract Claims regarding Extra Work shall be made pursuant to Paragraph 10.06. B. The Contractor shall furnish the City such installation records of all deviations from the original Contract Documents as may be necessary to enable the City to prepare for permanent record a corrected set of plans showing the actual installation. C. The compensation agreed upon for Extra Work whether or not initiated by a Change Order shall be a full, complete and final payment for all costs Contractor incurs as a result or relating to the �. change or Extra Work, whether said costs are known, unknown, foreseen or unforeseen at that time, including without limitation, any costs for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged work as a result of the change or Extra Work. 10.05 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor's responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision.Febnoy2,201.6 007200-I GENERAL CONDITIONS Page 40 of 63 10.06 Contract Claims Process A. City's Decision Required. All Contract Claims, except those waived pursuant to Paragraph 14.09, shall be referred to the City for decision. A decision by City shall be required as a .. condition precedent to any exercise by Contractor of any rights or remedies he may otherwise have under the Contract Documents or by Laws and Regulations in respect of such Contract Claims. B. Notice: 1. Written notice stating the general nature of each Contract Claim shall be delivered by the Contractor to City no later than 15 days after the start of the event giving rise thereto. The responsibility to substantiate a Contract Claim shall rest with the parry making the Contract �. Claim. 2. Notice of the amount or extent of the Contract Claim, with supporting data shall be delivered to the City on or before 45 days from the start of the event giving rise thereto (unless the City allows additional time for Contractor to submit additional or more accurate data in support of such Contract Claim). 3. A Contract Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of Paragraph 12.01. 4. A Contract Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of Paragraph 12.02. 5. Each Contract Claim shall be accompanied by Contractor's written statement that the adjustment claimed is the entire adjustment to which the Contractor believes it is entitled as a result of said event. 6. The City shall submit any response to the Contractor within 30 days after receipt of the ., claimant's last submittal (unless Contract allows additional time). C. City's Action: City will review each Contract Claim and,within 30 days after receipt of the last submittal of the Contractor,if any,take one of the following actions in writing: 1. deny the Contract Claim in whole or in part; 2. approve the Contract Claim; or 3. notify the Contractor that the City is unable to resolve the Contract Claim if, in the City's .. sole discretion, it would be inappropriate for the City to do so. For purposes of further resolution of the Contract Claim,such notice shall be deemed a denial. CITY OF FORT WORTH .� STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:FebnmyZ2016 00 72 00-1 GENERAL CONDITIONS Page 41 of 63 D. City's written action under Paragraph 10.06.0 will be final and binding, unless City or Contractor invoke the dispute resolution procedure set forth in Article 16 within 30 days of such action or denial. E. No Contract Claim for an adjustment in Contract Price or Contract Time will be valid if not submitted in accordance with this Paragraph 10.06. ARTICLE 11—COST OF THE WORK;ALLOWANCES; UNIT PRICE WORK; PLANS QUANTITY MEASUREMENT 11.01 Cost of the Work A. Costs Include& The term Cost of the Work means the sum of all costs, except those excluded in Paragraph 11.01.B, necessarily incurred and paid by Contractor in the proper performance of the Work. When the value of any Work covered by a Change Order, the costs to be reimbursed to Contractor will be only those additional or incremental costs required because of the change in the Work. Such costs shall not include any of the costs itemized in Paragraph 11.0 LB, and shall include but not be limited to the following items: 1. Payroll costs for employees in the direct employ of Contractor in the performance of the Work under schedules of job classifications agreed upon by City and Contractor. Such employees shall include, without limitation, superintendents, foremen, and other personnel employed full time on the Work. Payroll costs for employees not employed full time on the Work shall be apportioned on the basis of their time spent on the Work. Payroll costs shall include; a. salaries with a SS%markup, or b. salaries and wages plus the cost of fringe benefits, which shall include social security contributions, unemployment, excise, and payroll taxes, workers' compensation, health and retirement benefits, bonuses, sick leave, vacation and holiday pay applicable thereto. The expenses of performing Work outside of Regular Working Hours, Weekend Working Hours, or legal holidays, shall be included in the above to the extent authorized by City. 2. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers' field services required in connection therewith. 3. Rentals of all construction equipment and machinery, and the parts thereof whether rented from Contractor or others in accordance with rental agreements approved by City, and the costs of transportation, loading, unloading, assembly, dismantling, and removal thereof. All such costs shall be in accordance with the terms of said rental agreements. The rental of any such equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the Work. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febmmy2,2016 '"` 007200-1 GENERAL•CONDITIONS Page 42 of 63 4. Payments made by Contractor to Subcontractors for Work performed by Subcontractors. If required by City, Contractor shall obtain competitive bids from subcontractors acceptable to City and Contractor and shall deliver such bids to City, who will then determine, which bids, if any, will be acceptable. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work and fee shall be determined in the same manner as Contractor's Cost of the Work and fee as provided in this Paragraph 11.01. 5. Costs of special consultants (including but not limited to engineers, architects, testing laboratories, surveyors, attorneys, and accountants) employed for services specifically related to the Work. 6. Supplemental costs including the following: r a. The proportion of necessary transportation, travel, and subsistence expenses of Contractor's employees incurred in discharge of duties connected with the Work. b. Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, office, and temporary facilities at the Site, and hand tools not owned by the workers, which are consumed in the performance of the Work, and cost, less market value, of such items used but not consumed which remain the property of Contractor. c. Sales, consumer, use, and other similar taxes related to the Work, and for which Contractor is liable not covered under Paragraph 6.11, as imposed by Laws and Regulations. d. Deposits lost for causes other than negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable,and royalty payments and fees for permits and licenses. e. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by Contractor in connection with the performance of the Work, provided such losses and damages have resulted from causes other than the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and approval of City. No such losses, damages, and expenses shall be included in the Cost of the Work for the purpose of determining Contractor's fee. f. The cost of utilities,fuel, and sanitary facilities at the Site. g. Minor expenses such as telegrams, long distance telephone calls, telephone and communication services at the Site, express and courier services, and similar petty cash items in connection with the Work. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Fdxumy2,2016 007200-1 GENERAL CONDITIONS Page 43 of 63 h. The costs of premiums for all bonds and insurance Contractor is required by the Contract Documents to purchase and maintain. B. Costs Excluded: The term Cost of the Work shall not include any of the following items: 1. Payroll costs and other compensation of Contractor's officers, executives, principals (of partnerships and sole proprietorships), general managers, safety managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, expediters, timekeepers, clerks, and other personnel employed by Contractor, whether at the Site or in Contractor's principal or branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in Paragraph 11.0l.A.1 or specifically covered by Paragraph 11.01.A.4, all of which are to be considered administrative costs covered by the Contractor's fee. 2. Expenses of Contractor's principal and branch offices other than Contractor's office at the Site. 3. Any part of Contractor's capital expenses, including interest on Contractor's capital �. employed for the Work and charges against Contractor for delinquent payments. 4. Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to, the correction of defective Work, disposal of materials or equipment wrongly supplied, and making good any damage to property. 5. Other overhead or general expense costs of any kind. C. Contractor's Fee: When all the Work is performed on the basis of cost-plus, Contractor's fee shall be determined as set forth in the Agreement. When the value of any Work covered by a Change Order for an adjustment in Contract Price is determined on the basis of Cost of the Work, Contractor's fee shall be determined as set forth in Paragraph 12.01.C. D. Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to Paragraphs 11.01.A and 11.0l.B, Contractor will establish and maintain records thereof in accordance with generally accepted accounting practices and submit in a form acceptable to City an itemized cost breakdown together with supporting data. 11.02 Allowances A. Specified Allowance: It is understood that Contractor has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be performed for such sums and by such persons or entities as may be acceptable to City. �. B. Pre-bid Allowances: 1. Contractor agrees that: CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnwy2,20I6 007200-I GENERAL CONDITIONS Page 44 of 63 a. the pre-bid allowances include the cost to Contractor of materials and equipment required by the allowances to be delivered at the Site, and all applicable taxes;and b. Contractor's costs for unloading and handling on the Site, labor, installation, overhead, profit, and other expenses contemplated for the pre-bid allowances have been included in the allowances, and no demand for additional payment on account of any of the foregoing will be valid. C. Contingency Allowance: Contractor agrees that a contingency allowance, if any, is for the sole use of City. D. Prior to final payment, an appropriate Change Order will be issued to reflect actual amounts due Contractor on account of Work covered by allowances, and the Contract Price shall be correspondingly adjusted. 11.03 Unit Price Work A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the unit price for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement. B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by Contractor will be made by �- City subject to the provisions of Paragraph 9.05. C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to -- cover Contractor's overhead and profit for each separately identified item. Work described in the Contract Documents, or reasonably inferred as required for a functionally complete installation, but not identified in the listing of unit price items shall be considered incidental to unit price work listed and the cost of incidental work-included as part of the unit price. D. City may make an adjustment in the Contract Price in accordance with Paragraph 12.01 if. 1. the quantity of any item of Unit Price Work performed by Contractor differs materially and significantly from the estimated quantity of such item indicated in the Agreement;and 2. there is no corresponding adjustment with respect to any other item of Work. E. Increased or Decreased Quantities: The City reserves the right to order Extra Work in accordance with Paragraph 10.01. 1. If the changes in quantities or the alterations do not significantly change the character of work under the Contract Documents, the altered work will be paid for at the Contract unit price. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febfmy2,2016 00n00-1 GENERAL CONDITIONS Page 45 of 63 2. If the changes in quantities or alterations significantly change the character of work, the Contract will be amended by a Change Order. 3. If no unit prices exist, this will be considered Extra Work and the Contract will be amended by a Change Order in accordance with Article 12. 4. A significant change in the character of work occurs when: a. the character of work for any Item as altered differs materially in kind or nature from that in the Contract or b. a Major Item of work varies by more than 25%from the original Contract quantity. 5. When the quantity of work to be done under any Major Item of the Contract is more than 125% of the original quantity stated in the Contract, then either party to the Contract may request an adjustment to the unit price on the portion of the work that is above 125%. 6. When the quantity of work to be done under any Major Item of the Contract is less than 75% of the original quantity stated in the Contract, then either party to the Contract may request an adjustment to the unit price. 11.04 Plans Quantity Measurement A. Plans quantities may or may not represent the exact quantity of work performed or material moved, handled, or placed during the execution of the Contract. The estimated bid quantities are designated as final payment quantities, unless revised by the governing Section or this Article. B. If the quantity measured as outlined under"Price and Payment Procedures" varies by more than 25% (or as stipulated under "Price and Payment Procedures" for specific Items) from the total estimated quantity for an individual Item originally shown in the Contract Documents, an adjustment may be made to the quantity of authorized work done for payment purposes. The party to the Contract requesting the adjustment will provide field measurements and calculations showing the final quantity for which payment will be made. Payment for revised quantity will be made at the unit price bid for that Item,except as provided for in Article 10. C. When quantities are revised by a change in design approved by the City, by Change Order, or to correct an error, or to correct an error on the plans, the plans quantity will be increased or decreased by the amount involved in the change, and the 25% variance will apply to the new plans quantity. D. If the total Contract quantity multiplied by the unit price bid for an individual Item is less than $250 and the Item is not originally a plans quantity Item, then the Item may be paid as a plans quantity Item if the City and Contractor agree in writing to fix the final quantity as a plans quantity. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febimy 2,2016 007200-1 GENERAL CONDITIONS Page 46 of 63 E. For callout work or non-site specific Contracts,the plans quantity measurement requirements are not applicable. ARTICLE 12—CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 12.01 Change of Contract Price _. A. The Contract Price may only be changed by a Change Order. B. The value of any Work covered by a Change Order will be deternuned as follows: 1. where the Work involved is covered by unit prices contained in the Contract Documents, by application of such unit prices to the quantities of the items involved (subject to the provisions of Paragraph 11.03); or 2. where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed lump sum or unit price (which may include an allowance for overhead and profit not necessarily in accordance with Paragraph 12.0l.C.2), and shall include the cost of any secondary impacts that are foreseeable at the time of pricing the cost of Extra Work; -_ or 3. where the Work involved is not covered by unit prices contained in the Contract Documents �. and agreement to a lump sum or unit price is not reached under Paragraph 12.013.2, on the basis of the Cost of the Work (determined as provided in Paragraph 11.01) plus a Contractor's fee for overhead and profit(determined as provided in Paragraph 12.01.C). C. Contractor's Fee: The Contractor's additional fee for overhead and profit shall be determined as follows: 1. a mutually acceptable fixed fee;or 2. if a fixed fee is not agreed upon,then a fee based on the following percentages of the various portions of the Cost of the Work: a. for costs incurred under Paragraphs 11.0l.A.1, 11.0l.A.2. and 11.0l.A.3, the Contractor's additional fee shall be 15 percent except for: 1) rental fees for Contractor's own equipment using standard rental rates; 2) bonds and insurance; b. for costs incurred under Paragraph 11.01.A.4 and 11.01.A.5,the Contractor's fee shall be five percent(5%); 1) where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of Paragraphs 12.0l.C.2.a and 12.0l.C.2.b is that the Subcontractor who actually performs the Work, at whatever CITY OF FORT WORTH "~ STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:FebnayZ 2016 007200-1 GENERAL CONDITIONS Page 47 of 63 tier,will be paid a fee of 15 percent of the costs incurred by such Subcontractor under Paragraphs 11.01.A.1 and 11.0l.A.2 and that any higher tier Subcontractor and Contractor will each be paid a fee of five percent(5%) of the amount paid to the next lower tier Subcontractor,however in no case shall the cumulative total of fees paid be in excess of 25%; c. no fee shall be payable on the basis of costs itemized under Paragraphs 11.01.A.6, and 11.O1.B; d. the amount of credit to be allowed by Contractor to City for any change which results in a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in Contractor's fee by an amount equal to five percent (5%) of such net A decrease. 12.02 Change of Contract Time A. The Contract Time may only be changed by a Change Order. B. No extension of the Contract Time will be allowed for Extra Work or for claimed delay unless the Extra Work contemplated or claimed delay is shown to be on the critical path of the Project Schedule or Contractor can show by Critical Path Method analysis how the Extra Work or claimed delay adversely affects the critical path. 12.03 Delays A A. Where Contractor is reasonably delayed in the performance or completion of any part of the Work within the Contract Time due to delay beyond the control of Contractor,the Contract Time may be extended in an amount equal to the time lost due to such delay if a Contract Claim is made therefor. Delays beyond the control of Contractor shall include, but not be limited to, acts or neglect by City, acts or neglect of utility owners or other contractors performing other work as contemplated by Article 7, fires, floods, epidemics, abnormal weather conditions, or acts of God. Such an adjustment shall be Contractor's sole and exclusive remedy for the delays described in this Paragraph. B. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration. or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. C. Contractor shall not be entitled to an adjustment in Contract Price or Contract Time for delays within the control of Contractor. Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of Contractor. D. The Contractor shall receive no compensation for delays or hindrances to the Work, except when direct and unavoidable extra cost to the Contractor is caused by the failure of the City to provide information or material,if any,which is to be furnished by the City. CITYOF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Feb►umy 2,2016 007200-1 GENERAL CONDITIONS Page 48 of 63 ARTICLE 13—TESTS AND INSPECTIONS; CORRECTION,REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 13.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected,or accepted as provided in this Article 13. 13.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor's safety procedures and programs so that they may comply therewith as applicable. 13.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections,which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re-tests, or approvals required for City's acceptance of materials or *" equipment to be incorporated in the Work; or acceptance of materials,mix designs, or equipment submitted for approval prior to Contractor's purchase thereof for incorporation in the Work. Such inspections, tests, re-tests, or approvals shall be performed by organizations acceptable to City. D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to perform any inspections or tests ("Testing") for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible,with Contractor; 2. Should any Testing under this Section 13.03 D result in a "fail", "did not pass" or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor's cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. CITY OF FORT WORTH MW STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:FebawyZ 2016 007200-1 GENERAL CONDITIONS Page 49 of 63 3. Any amounts owed for any retest under this Section 13.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue Final Payment until the Testing Lab is paid. E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. F. Uncovering Work as provided in Paragraph 13.03.E shall be at Contractor's expense. G. Contractor shall have the right to make a Contract Claim regarding any retest or invoice issued under Section 13.03 D. 13.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City's observation and replaced at Contractor's expense. B. If City considers it necessary or advisable that covered Work be observed by City or inspected or tested by others, Contractor, at City's request, shall uncover, expose, or otherwise make available for observation, inspection, or testing as City may require, that portion of the Work in question, furnishing all necessary labor,material,and equipment. 1. If it is found that the uncovered Work is defective, Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such uncovering, exposure, observation, inspection, and testing, and of satisfactory replacement or reconstruction (including but not limited to all costs of repair or replacement of work of others); or City shall be entitled to accept defective Work in accordance with Paragraph 13.08 in which case Contractor shall still be responsible for all costs associated with exposing,observing, and testing the defective Work. 2. If the uncovered Work is not found to be defective, Contractor shall be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure, observation,inspection,testing,replacement, and reconstruction. 13.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS . Revision:Febmay 2,2016 007200-1 GENERAL CONDITIONS Page 50 of 63 Subcontractor, any Supplier,any other individual or entity,or any surety for, or employee or agent of any of them. 13.06 Correction or Removal ofDefective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 13.06 or Paragraph 13.07, Contractor shall take no action that would void or otherwise impair City's special warranty and guarantee, if any, on said Work. 13.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor's use by City or permitted by Laws and Regulations as contemplated in Paragraph 6.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City's written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective,and 4. satisfactorily correct or repair or remove and replace any damage to other Work,to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City's written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement(including but not limited to all costs of repair or replacement of work of others)will be paid by Contractor. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Fdxumy2,2016 007200-1 GENERAL CONDITIONS Page 51 of 63 C. In special circumstances where a particular item of equipment is placed in continuous service before Final Acceptance of all the Work,the correction period for that item may start to run from an earlier date if so provided in the Contract Documents. D. Where defective Work(and damage to other Work resulting therefrom) has been. corrected or removed and replaced under this Paragraph 13.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor should such additional warranty coverage be required. Contractor may dispute this recquirement by filing a Contract Claim,pursuant to Paragraph 10.06. E. Contractor's obligations under this Paragraph 13.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 13.07 shall not be construed as a substitute for, or a waiver of,the provisions of any applicable statute of limitation or repose. 13.08 Acceptance of Defective Work If, instead of requiring correction or removal and replacement of defective Work, City prefers to accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) attributable to City's evaluation of and determination to accept such defective Work and for the diminished value of the Work to the extent not otherwise paid by Contractor. If any such acceptance occurs prior to Final Acceptance, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work so accepted. 13.09 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 13.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven(7)days written notice to Contractor, correct,or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 13.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor's services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants, -� employees, and City's other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnoy2,2016 007200-1 GENERAL CONDITIONS Paae 52 of 63 costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City's rights and remedies under this Paragraph 13.09. ARTICLE 14—PAYMENTS TO CONTRACTOR AND COMPLETION 14.01 Schedule of Values The Schedule of Values for lump sum contracts established as provided in Paragraph 2.07 will serve as the basis for progress payments and will be incorporated into a form of Application for Payment acceptable to City. Progress payments on account of Unit Price Work will be based on the number of units completed. 14.02 Progress Payments A. Applications for Payments: 1. Contractor is responsible for providing all information as required to become a vendor of the City. 2. At least 20 days before the date established in the General Requirements for each progress payment, Contractor shall submit to City for review an Application for Payment filled out and signed by Contractor covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. 3. If payment is requested on the basis of materials and equipment not incorporated in the Work -• but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice, or other documentation warranting that City has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate insurance or other arrangements to protect City's interest therein, all of which must be satisfactory to City. 4. Beginning with the second Application for Payment, each Application shall include an affidavit of Contractor stating that previous progress payments received on account of the Work have been applied on account to discharge Contractor's legitimate obligations associated with prior Applications for Payment. 5. The amount of retainage with respect to progress payments will be as stipulated in the Contract Documents. CITY OF FORT WOR'T`H STANDARD CONSTRUCTION SPECIFICATION.DOCUMENTS Revision:Fdxumy2,2016 007200-1 GENERAL CONDITIONS Page 53 of 63 B. Review ofApplications: 1. City will, after receipt of each Application for Payment, either indicate in writing a recommendation of payment or return the Application to Contractor indicating reasons for refusing payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application. 2. City's processing of any payment requested in an Application for Payment will be based on City's observations of the executed Work, and on City's review of the Application for Payment and the accompanying data and schedules,that to the best of City's knowledge: a. the Work has progressed to the point indicated; b. the quality of the Work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Final Acceptance,, the results of any subsequent tests called for in the Contract Documents, a final determination of quantities and classifications for Work performed under Paragraph 9.05, _ and any other qualifications stated in the recommendation). 3. Processing any such payment will not thereby be deemed to have represented that: W a, inspections made to check the quality or the quantity of the Work as it has been performed have been exhaustive, extended to every aspect of the Work in progress, or involved detailed inspections of the Work beyond the responsibilities specifically assigned to City in the Contract Documents; or b. there may not be other matters or issues between the parties that might entitle Contractor to be paid additionally by City or entitle City to withhold payment to Contractor, or c. Contractor has complied with Laws and Regulations applicable to Contractor's performance of the Work. 4. City may refuse to process the whole or any part of any payment because of subsequently discovered evidence or the results of subsequent inspections or tests, and revise or revoke any such payment previously made, to such extent as may be necessary to protect City from loss because: a. the Work is defective, or the completed Work has been damaged by the Contractor or his subcontractors,requiring correction or replacement; b. discrepancies in quantities contained in previous applications for payment; c. the Contract Price has been reduced by Change Orders; d. City has been required to correct defective Work or complete Work in accordance with Paragraph 13.09; or CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnoy2,2016 0072 00-1 GENERAL CONDITIONS Page 54 of 63 d% e. City has actual knowledge of the occurrence of any of the events enumerated in Paragraph 15.02.A. C. Retainage: 1. For contracts less than $400,000 at the time of execution, retainage shall be ten percent (10%). 2. For contracts greater than $400,000 at the time of execution, retainage shall be five percent (5%). D. Liquidated Damages. For each calendar day that any work shall remain uncompleted after the time specified in the Contract Documents, the sum per day specified in the Agreement, will be +� deducted from the monies due the Contractor, not as a penalty, but as liquidated damages suffered by the City. E. Payment. Contractor will be paid pursuant to the requirements of this Article 14 and payment will become due in accordance with the Contract Documents. F. Reduction in Payment.- 1. ayment:1. City may refuse to make payment of the amount requested because: a. Liens have been filed in connection with the Work, except where Contractor has delivered a specific bond satisfactory to City to secure the satisfaction and discharge of such Liens; b. there are other items entitling City to a set-off against the amount recommended; or c. City has actual knowledge of the occurrence of any of the events enumerated in Paragraphs 14.02.B.4.a through 14.02.B.4.e or Paragraph 15.02.A. 2. If City refuses to make payment of the amount requested, City will give Contractor written notice stating the reasons for such action and pay Contractor any amount remaining after deduction of the amount so withheld. City shall pay Contractor the amount so withheld, or any adjustment thereto agreed to by City and Contractor, when Contractor remedies the reasons for such action. 14.03 Contractor's Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to City no later than the time of payment free and clear of all Liens. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febn=yZ2016 007200-1 GENERAL CONDITIONS Page 55 of 63 14.04 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor's performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of , the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 14.05 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: 1. within 10 days,City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. B. No time charge will be made against the Contractor between said date of notification of the City and the date of Final Inspection. Should the City determine that the Work is not ready for Final Inspection, City will notify the Contractor in writing of the reasons and Contract Time will resume. 14.06 Final Acceptance Upon completion by Contractor to City's satisfaction, of any additional Work identified in the Final Inspection,City will issue to Contractor a letter of Final Acceptance. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOMAENTS Revision:Febuty2,2016 007200-1 GENERAL CONDITIONS Page 56 of 63 14.07 Final Payment A. Application for Payment: 1. Upon Final Acceptance, and in the opinion of City, Contractor may make an application for final payment following the procedure for progress payments in accordance with the Contract Documents. 2. The final Application for Payment shall be accompanied(except as previously delivered)by: a. all documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; b. consent of the surety,if any,to final payment; c. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and d. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. B. Payment Becomes Due: 1. After City's acceptance of the Application for Payment and accompanying documentation, requested by Contractor, less previous payments made and any sum City is entitled, including but not limited to liquidated damages,will become due and payable. 2. After all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor's insurance provider for resolution. 3. The making of the final payment by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. 14.08 Final Completion Delayed and Partial Retainage Release A. If final completion of the Work is significantly delayed, and if City so confirms, City may, upon receipt of Contractor's final Application for Payment, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by City for Work not fully completed or corrected is less than the retainage stipulated in Paragraph 14.02.C, and if bonds have been furnished as required in Paragraph 5.02, the written consent of the surety to the payment of the balance due for that CITY OF.FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:FebnwryZ 2016 00 72 00-1 GENERAL CONDITIONS Page 57 of 63 portion of the Work fully completed and accepted shall be submitted by Contractor to City with the Application for such payment. Such payment shall be made under the terms and conditions _ governing final payment,except that it shall not constitute a waiver of Contract Claims. B. Partial Retainage Release. For a Contract that provides for a separate vegetative establishment and maintenance, and test and performance periods following the completion of all other construction in the Contract Documents for all Work locations, the City may release a portion of the amount retained provided that all other work is completed as determined by the City. Before the release, all submittals and final quantities must be completed and accepted for all other work. An amount sufficient to ensure Contract compliance will be retained. 14.09 Waiver of Claims The acceptance of final payment will constitute a release of the City from all claims or liabilities �. under the Contract for anything done or furnished or relating to the work under the Contract Documents or any act or neglect of City related to or connected with the Contract. ARTICLE 15—SUSPENSION OF WORK AND TERMINATION 15.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will make no extra payment for stand-by time of construction equipment and/or construction crews. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not available within a reasonable period of time, Contractor may request an extension in Contract Time,directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period,the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. D. Contractor may be reimbursed for the cost of moving his equipment off the job and returning the necessary equipment to the job when it is determined by the City that construction may be resumed. Such reimbursement shall be based on actual cost to the Contractor of moving the equipment and no profit will be allowed. Reimbursement may not be allowed if the equipment is moved to another construction project for the City. .- CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnimy2,2016 007200-I GENERAL CONDITIONS Page 58 of 63 15.02 City May Terminate for Cause A. The occurrence of any one or more of the following events by way of example, but not of limitation,may justify termination for cause: 1. Contractor's persistent failure to perform the Werk in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment, failure to adhere to the Project Schedule established under Paragraph 2.07 as adjusted from time to time pursuant to Paragraph 6.04, or failure to adhere to the City's Business Diversity Enterprise Ordinance #20020-12-2011 established under Paragraph 6.06.D); 2. Contractor's disregard of Laws or Regulations of any public body having jurisdiction; 3. Contractor's repeated disregard of the authority of City; or �. 4. Contractor's violation in any substantial way of any provisions of the Contract Documents; or �. 5. Contractor's failure to promptly make good any defect in materials or workmanship, or defects of any nature,the correction of which has been directed in writing by the City;or 6. Substantial indication that the Contractor has made an unauthorized assignment of the Contract or any funds due therefrom for the benefit of any creditor or for any other purpose; or 7. Substantial evidence that the Contractor has become insolvent or bankrupt, or otherwise financially unable to carry on the Work satisfactorily; or 8. Contractor commences legal action in a court of competent jurisdiction against the City. B. If one or more of the events identified in Paragraph 15.02A. occur, City will provide written notice to Contractor and Surety to arrange a conference with Contractor and Surety to address Contractor's failure to perform the Work. Conference shall be held not later than 15 days, after receipt of notice. 1. If the City, the Contractor, and the Surety do not agree to allow the Contractor to proceed to ®„ perform the construction Contract, the City may, to the extent permitted by Laws and Regulations, declare a Contractor default and formally terminate the Contractor's right to complete the Contract. Contractor default shall not be declared earlier than 20 days after the Contractor and Surety have received notice of conference to address Contractor's failure to perform the Work. .. 2. If Contractor's services are terminated, Surety shall be obligated to take over and perform the Work. If Surety does not commence performance thereof within 15 consecutive calendar days after date of an additional written notice demanding Surety's performance of its CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnoy2,20I6 007200-I GENERAL CONDITIONS Page 59 of 63 obligations, then City, without process or action at law, may take over any portion of the Work and complete it as described below. a. If City completes the Work, City may exclude Contractor and Surety from the site and take possession of the Work, and all materials and equipment incorporated into the Work _ stored at the Site or for which City has paid Contractor or Surety but which are stored elsewhere,and finisli the Work as City may deem expedient. 3. Whether City or Surety completes the Work, Contractor shall not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the Contract Price exceeds all claims, costs, losses and damages sustained by City arising out of or resulting from completing the Work, such excess will be paid to Contractor. If such claims, costs, losses and damages exceed such unpaid balance, Contractor shall pay the difference to City. Such claims, costs, losses and damages incurred by City will be incorporated in a Change �. Order, provided that when exercising any rights or remedies under this Paragraph, City shall not be required to obtain the lowest price for the Work performed. 4. Neither City, nor any of its respective consultants, agents, officers, directors or employees _ shall be in any way liable or accountable to Contractor or Surety for the method by which the completion of the said Work, or any portion thereof, may be accomplished or for the price paid therefor. 5. City, notwithstanding the method used in completing the Contract, shall not forfeit the right to recover damages from Contractor or Surety for Contractor's failure to timely complete the entire Contract. Contractor shall not be entitled to any claim on account of the method used by City in completing the Contract. 6. Maintenance of the Work shall continue to be Contractor's and Surety's responsibilities as provided for in the bond requirements of the Contract Documents or any special guarantees .� provided for under the Contract Documents or any other obligations otherwise prescribed by law. C. Notwithstanding Paragraphs 15.02.13, Contractor's services will not be terminated if Contractor begins within seven days of receipt of notice of intent to terminate to correct its failure to perform and proceeds diligently to cure such failure within no more than 30 days of receipt of said notice. D. Where Contractor's services have been so terminated by City, the termination will not affect any _ rights or remedies of City against Contractor then existing or which may thereafter accrue. Any retention or payment of moneys due Contractor by City will not release Contractor from liability. E. If and to the extent that Contractor has provided a performance bond under the provisions of Paragraph 5.02,the termination procedures of that bond shall not supersede the provisions of this Article. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:FebnmyZ 2016 007200-1 GENERAL CONDITIONS Page 60 of 63 15.03 City May Terminate For Convenience A. City may, without cause and without prejudice to any other right or remedy of City,terminate the Contract. Any termination shall be effected by mailing a notice of the termination to the Contractor specifying the extent to which performance of Work under the contract is terminated, and the date upon which such termination becomes effective. Receipt of the notice shall be deemed conclusively presumed and established when the letter is placed in the United States Postal Service Mail by the City. Further, it shall be deemed conclusively presumed and established that such termination is made with just cause as therein stated; and no proof in any claim,demand or suit shall be required of the City regarding such discretionary action. B. After receipt of a notice of termination, and except as otherwise directed by the City, the Contractor shall: 1. Stop work under the Contract on the date and to the extent specified in the notice of termination; 2. place no further orders or subcontracts for materials, services or facilities except as may be necessary for completion of such portion of the Work under the Contract as is not terminated; 3. terminate all orders and subcontracts to the extent that they relate to the performance of the Work terminated by notice of termination; 4, transfer title to the City and deliver in the manner, at the tunes, and to the extent, if any, directed by the City: a. the fabricated or unfabricated parts, Work in progress, completed Work, supplies and other material produced as a part of, or acquired in connection with the performance of, the Work terminated by the notice of the termination;and b. the completed, or partially completed plans, drawings, information and other property which, if the Contract had been completed, would have been required to be furnished to the City. 5. complete performance of such Work as shall not have been terminated by the notice of termination; and 6. take such action as may be necessary, or as the City may direct, for the protection and preservation of the property related to its contract which is in the possession of the Contractor and in which the owner has or may acquire the rest. C. At a time not later than 30 days after the termination date specified in the notice of termination, the Contractor may submit to the City a list, certified as to quantity and quality, of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febntmy2,2016 007200-1 GENERAL CONDITIONS Page 61 of 63 D. Not later than 15 days thereafter, the City shall accept title to such items provided, that the list submitted shall be subject to verification by the City upon removal of the items or, if the items are stored, within 45 days from the date of submission of the list, and any necessary adjustments to correct the list as submitted, shall be made prior to final settlement. E. Not later than 60 days after the notice of termination, the Contractor shall submit his termination claim to the City in the form and with the certification prescribed by the City. Unless an extension is made in writing within such 60 day period by the Contractor, and granted by the City,any and all such claims shall be conclusively deemed waived. F. In such case, Contractor shall be paid for(without duplication of any items): 1. completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work; 2. expenses sustained prior to the effective date of termination in performing services and fiunishing labor, materials, or equipment as required by the Contract Documents in connection with uncompleted Work,plus fair and reasonable sums for overhead and profit on such expenses; and 3. reasonable expenses directly attributable to termination. G. In the event of the failure of the Contractor and City to agree upon the whole amount to be paid to the Contractor by reason of the termination of the Work,the City shall determine, on the basis of information available to it, the amount, if any, due to the Contractor by reason of the termination and shall pay to the Contractor the amounts determined. Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss arising out of or resulting from such termination. ARTICLE 16—DISPUTE RESOLUTION 16.01 Methods and Procedures A. Either City or Contractor may request mediation of any Contract Claim submitted for a decision under Paragraph 10.06 before such decision becomes final and binding. The request for mediation shall be submitted to the other party to the Contract. Timely submission of the request shall stay the effect of Paragraph 10.06.E. B. City and Contractor shall participate in the mediation process in good faith. The process shall be commenced within 60 days of filing of the request. C. If the Contract Claim is not resolved by mediation, City's action under Paragraph 10.06.0 or a denial pursuant to Paragraphs 10.06.C.3 or 10.06.D shall become final and binding 30 days after termination of the mediation unless,within that time period, City or Contractor: CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febnmry2,2016 007200-I GENERAL CONDITIONS Page 62 of 63 1. elects in writing to invoke any other dispute resolution process provided for in the Supplementary Conditions;or 2, agrees with the other party to submit the Contract Claim to another dispute resolution process;or 3. gives written notice to the other party of the intent to submit the Contract Claim to a court of competent jurisdiction. ARTICLE 17—MISCELLANEOUS 17.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if. 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 17.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. if the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 17.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. CITY OF FORT WORTH �. STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febmary2,2016 007200-1 GENERAL CONDITIONS Page 63 of 63 1.7.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 17.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revision:Febuuy2,2016 w 007300-1 SUPPLEMENTARY CONDITIONS Page 1 of 5 .. 1 SECTION 00 73 00 2 SUPPLEMENTARY CONDITIONS 3 TO 4 GENERAL CONDITIONS 5 6 Supplementary Conditions 7 8 These Supplementary Conditions modify and supplement Section 00 72 00-General Conditions,and other 9 provisions of the Contract Documents as indicated below. All provisions of the General Conditions that are 10 modified or supplemented remain in full force and effect as so modified or supplemented. All provisions 11 of the General Conditions which are not so modified or supplemented remain in full force and effect. 12 13 Defined Terms 14 15 The terms used in these Supplementary Conditions which are defined in the General Conditions have the 16 meaning assigned to them in the General Conditions,unless specifically noted herein. 17 do 18 Modifications and Supplements 19 20 The following are instructions that modify or supplement specific paragraphs in the General Conditions and 21 other Contract Documents. 22 23 SC-3.03B.2,"Resolving Discrepancies" 24 25 Plans govern over Specifications. 26 27 SC-4.01A 28 29 Easement limits shown on the Drawing are approximate and were provided to establish a basis for bidding. 30 Upon receiving the final easements descriptions,Contractor shall compare them to the lines shown on the 31 Contract Drawings. 32 33 SC-4.01A.1.,"Availability of Lands" 34 35 The following is a list of known outstanding right-of-way,and/or easements to be acquired,if any as of 36 February 13,2017: 37 38 Outstanding Right-Of-Way,and/or Easements to Be Acquired PARCEL OWNER TARGET DATE NUMBER OF POSSESSION None 39 The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed, 40 and do not bind the City. 41 42 If Contractor considers the final easements provided to differ materially from the representations on the 43 Contract Drawings, Contractor shall within five(5)Business Days and before proceeding with the Work, 44 notify City in writing associated with the differing easement line locations. 45 46 �* 47 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised January 22,2016 City Project No.100889 sn 0073 00 2 SUPPLEMENTARY CONDITIONS Page 2 of 5 On I SC-4.01A.2,"Availability of Lands" 2 No 3 Utilities or obstructions to be removed,adjusted,and/or relocated 4 5 The following is list of utilities and/or obstructions that have not been removed,adjusted;and/or relocated 6 as of February 13,2017 7 EXPECTED UTILITY AND LOCATION TARGET DATE OF OWNER ADJUSTMENT None 8 The Contractor understands and agrees that the dates listed above are estimates only,are not guaranteed, 9 and do not bind the City. 1.0 , 11 SC-4.02A.,"Subsurface and Physical Conditions" 12 13 The following are reports of explorations and tests of subsurface conditions at the site of the Work: 14 None 15 16 The following are drawings of physical conditions in or relating to existing surface and subsurface 17 structures(except Underground Facilities)which are at or contiguous to the site of the Work: 18 None 19 20 SC-4.06A.,"Hazardous Environmental Conditions at Site" 21 22 The following are reports and drawings of existing hazardous environmental conditions known to the City: 23 None 24 25 SC-5.03A.,"Certificates of Insurance" 26 27 The entities listed below are"additional insureds as their interest may appear"including their respective 28 officers,directors,agents and employees. 29 30 (1) City 31 (2) Consultant: None 32 (3) Other: None 33 34 SC-5.04A.,`Contractor's Insurance" 35 .. 36 The limits of liability for the insurance required by Paragraph GC-5.04 shall provide the following 37 coverages for not less than the following amounts or greater where required by laws and regulations: 38 39 5.04A.Workers'Compensation,under Paragraph GC-5.04A. 40 41 Statutory limits 42 Employer's liability ow 43 $100,000 each accident/occurrence 44 $100,000 Disease-each employee 45 $500,000 Disease-policy limit ON 46 47 48 49 ,.., CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised January 22,2016 City Project No.100889 007300-5 SUPPLEMENTARY CONDITIONS Page 5 of 5 1 SC-6.09C."Outstanding permits and licenses" 2 3 The following is a list of known outstanding permits and/or licenses to be acquired,if any as of February 4 13,2017: 5 6 Outstanding Permits and/or Licenses to Be Acquired OWNER PERMIT OR LICENSE AND LOCATION TARGET DATE OF POSSESSION None 7 8 SC-7.02.,"Coordination" 9 10 The individuals or entities listed below have contracts with the City for the performance of other work at 11 the Site: 12 Vendor Scope of Work Coordination Authority Ono None 13 14 re. 15 SC-8.01,"Communications to Contractor" 16 None 17 ON 18 SC-9.01.,"City's Project Manager" 19 20 The City's Project Manager for this Contract is J.Chris Underwood or his/her successor pursuant to 21 written notification from the Director of Water Department an 22 23 SC-13.03C.,"Tests and Inspections" 24 None 25 26 SC-16.01C.1,-Methods and Procedures" 27 None 28 29 30 END OF SECTION �w Revision Log DATE NAME SUMMARY OF CHANGE 1/22/2016 F.Griffin SC-9.01.,"City's Project Representative"wording changed to City's Projekt Manager. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised January 22,2016 City Project No.100889 011100-1 SUMMARY OF WORK Page 1 of 6 -- 1 SECTION 01 11 00 2 SUMMARY OF WORK 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Summary of Work to be performed in accordance with the Contract Documents 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Bid Quantities-Bid quantities of the various items in the proposal are for 9 comparison only and may not reflect the actual quantities.There is no limit to 10 which a bid item can be increased or decreased. I 1 Contractor shall not be entitled to renegotiation of unit prices regardless of the 12 final measured quantities.To the extent that General Conditions(00-72-00) 13 Article 11 conflicts with this provision,this provision controls.No claim will be 14 considered for lost or anticipated profits based upon differences in estimated 15 quantities versus actual quantities. 16 Total quantities given in the bid proposal may not reflect actual quantities; 17 however,they are given for the purpose of bidding and awarding the contract. 18 A contract in the amount of$200,000.00 shall be awarded with final payment 19 based on actual measured quantities and the unit price in this proposal. 20 Moreover,there is to be no limit on the variation between the estimated 21 quantities shown and the actual quantities performed. 22 It is understood and agreed that the scope of work contemplated in this 23 contract is that which is designated by the City but will in no case exceed 24 $200,000.00 25 2. Non-Exclusive Contract-This contract is non-exclusive.During the term of 26 this contract or any renewal hereof,the City reserves the right to advertise 27 and award another contract for like or similar work.If a second contract is 28 awarded,the City further reserves the right to issue work orders under either 29 contract as it deems in its best interest,without recourse. 30 3. Scope of Work The work covered by these Specifications consists of the 31 replacement of existing 1-inch,1.5-inch and 2-inch lead water services. 32 Included in this work will be all necessary appurtenances required for a 33 complete new water service and surface restoration as itemized in the 34 appropriate water service bid item and specified in"Water Services 1-inch to 35 2-inch"(33-12-10). 36 The process for replacing the lead water services will be as follows: 37 a) The City of Fort Worth Water Field Operations Valve Crew will shut 38 down the water main prior to replacement. 39 b) The existing lead service line will be removed from main to meter 40 including the removal of the existing corporation at the main.The 41 lead service lines shall be delivered to the City of Fort Worth Water 42 Department Field Operations Division for disposal. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 01 1100-2 SUMMARY OF WORK Page 2 of 6 1 c) The appropriate tap saddle will be installed over the existing hole left 2 by the removal of the existing corporation.If the existing water main 3 is compromised by the removal of the corporation and as directed by 4 the engineer,a portion of the water main may be replaced,as 5 necessary.This portion will be paid for at the price per foot of the 6 appropriate bid item for water pipe(PVC or DIP).There will be no 7 additional payment as specified in these documents for"Connection 8 to Existing Water Mains"(33-12-25). 9 d) After the service line has been replaced,the City of Fort Worth Field 10 Operations Valve Crew will re-open the valves to load the water main. 11 The service line shall be flushed a minimum of thirty(30)minutes 12 before reconnecting to meter. 13 e) The water main and service shall be operational prior to the end of 14 the day and/or moving off of jobsite. 15 The Engineer shall determine and designate to the Contractor the location of 16 the service installation by a Work Order together with a sketch and/or map 17 for each such service installation,giving the appropriate bid item required for 18 installation and providing the amount of time to complete the work.The 19 Engineer will notify the Contractor that a Work Order is ready and fax 20 and/or e-mail the Contractor a copy of the Work Order notification.The 21 Contractor is to provide his fax number and e-mail address to the Engineer at 22 the pre-construction conference.Single or several Work Orders may be issued 23 at one time.The Contractor shall initiate work on an installation within seven 24 (7)working days of the date the Work Order is sent to the Contractor,and 25 continue work on the Work Order until it has been completed,not including 26 paving. 27 4. Contractor's Responsibility-Contractor covenants and agrees to fully - 28 perform or cause to be performed,with good faith and due diligence,and in 29 accordance with standards common to the industry and herein set forth in 30 these Contract Documents which is hereby incorporated and made a part of 31 this contract.The City may designate water services to be installed by 32 furnishing to the contractor a marked drawing,or street addresses contained 33 in a written order or by marking in the field by painted stake or other means, 34 or by any or all combinations of said methods of designation.The contractor 35 agrees that no work will be performed without written authorization from the 36 individual designated in writing by the Director of the Water Department. -, 37 5. Contract Time-It is contemplated that Work Orders will be issued to the 38 Contractor for work to be performed under this Contract for not to exceed 39 three hundred sixty-five(365)calendar days following the date of the Contract. 40 nor to exceed the limit of the award amount,whichever should occur first.The 41 Contractor shall be required to complete any work covered by a Work Order 42 issued prior to that date of termination but will not be required to accept any 43 Work Order for execution dated after that date of termination.If the cost of 44 the work performed under this Contract is less than the limit of the contract 45 award at the end of the three hundred sixty-five(365)calendar day period,at 46 the City's option and the Contractor's concurrence,the Contract Time may 47 be extended to the limit of the contract award amount. 48 A calendar day is any day of the week or month, Sundays or legal holidays as 49 defined in General Conditions(00-72-00)Article 1. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 1 City Project No.100889 011100-3 SUMMARY OF WORK Page 3 of 6 1 6. Required Crew Personnel&Equipment-The Contractor shall furnish and -^ 2 supply sufficient equipment and personnel to complete the Work Order in the 3 amount of time provided for in the Work Order.Should the Contractor fail to 4 start any Work Order within the time specified,he shall add the necessary 5 work crews and equipment to prosecute the work to complete the Work Order 6 or Work Orders in the time provided. 7 7. Liquidated Damaees-The Contractor shall pay liquidated damages of two 8 hundred ten dollars($210.00)per day per Work Order,for Failure to begin a 9 Work Order within the seven(7)working days of the date the Work Order is 10 faxed and/or e-mailed to the Contractor.Failure to complete the work within 11 the stipulated construction time on the Work Order will require the 12 Contractor to pay liquidated damages in the amount stipulated in these 13 contract documents. 14 15 8. Payment-Because of the unique nature of this contract,General Conditions 16 (00-72-00)Article 14 shall not apply and shall be superseded by the following: 17 Whenever the improvements prescribed by an individual Work Order have 18 been completed,the contractor shall notify the engineer.The engineer or other 19 appropriate official of the owner will,within a reasonable time,perform the ... 20 inspections.If such inspection reveals that the improvements are in an 21 acceptable condition and have been completed in accordance with the terms of 22 the Contract Documents and all approved modifications thereof,the engineer 23 will recommend acceptance of the work under that particular Work Order 24 and recommend payment therefore. 25 If the engineer finds that the work has not been completed as required,he 26 shall so advise the contractor in writing,furnishing him an itemized list of all 27 known items which have not been completed or which are not in acceptable 28 condition.When the contractor has corrected all such items,he shall again 29 notify the engineer that the improvements are ready for inspection,and the 30 engineer shall proceed as outlined above. 31 Whenever the improvements prescribed by the individual Work Order have 32 been completed and all the requirements of the Contract Documents have 33 been fulfilled on the part of the contractor,an estimate showing the value of 34 the work will be prepared by the engineer as the necessary measurements, 35 computations and checks can be made. .� 36 The amount of the estimate will be paid to the contractor after acceptance by 37 the Water Department Director,provided the contractor has furnished to the 38 owner satisfactory evidence of payment as follows:Prior to submission of the 39 estimate for payment,the contractor shall execute an affidavit,as furnished by 40 the City,certifying that all persons,firms,associations,corporations or other 41 organizations furnishing labor and/or materials under that Work Order have -- 42 been paid in full,that the wage scale established by the City Council in the 43 City of Fort Worth has been paid,and that there are no claims pending for 44 personal injury and/or property damages. CITY OF FORT WORTH 2017 WATER LEAD SERVICES -- STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 011100-4 SUMMARY OF WORK Page 4 of 6 1 The acceptance by the contractor of the individual payment as aforesaid shall 2 operate as and shall release the owner from all claims or liabilities under the 3 Contract for anything done or furnished or relating to the work under that 4 Work Order or any act or neglect of said City relating to or connected with 5 the Contract. 6 The making of the payment by the owner shall not relieve the contractor of any 7 guarantees or other requirements of the Contract Documents which specifically 8 continue thereafter. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0-Bidding Requirements,Contract Forms,and Conditions of the Contract 11 2. Division 1 -General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Work Covered by Contract Documents 19 1. Work is to include furnishing all labor,materials,and equipment,and performing 20 all Work necessary for this construction project as detailed in the Drawings and 21 Specifications. 22 B. Subsidiary Work 23 1. Any and all Work specifically governed by documentary requirements for the 24 project,such as conditions imposed by the Drawings or Contract Documents in 25 which no specific item for bid has been provided for in the Proposal and the item.is 26 not a typical unit bid item included on the standard bid item list,then the item shall 27 be considered as a subsidiary item of Work,the cost of which shall be included in 28 the price bid in the Proposal for various bid items. 29 C. Use of Premises 30 1. Coordinate uses of premises under direction of the City. 31 2. Assume full responsibility for protection and safekeeping of materials and • 32 equipment stored on the Site. 33 3. Use and occupy only portions of the public streets and alleys, or other public places 34 or other rights-of-way as provided for in the ordinances of the City,as shown in the 35 Contract Documents,or as may be specifically authorized in writing by the City. 36 a. A reasonable amount of tools,materials,and equipment for construction 37 purposes may be stored in such space,but no more than is necessary to avoid 38 delay in the construction operations. 39 b. Excavated and waste materials shaII be stored in such a way as not to interfere 40 with the use of spaces that may be designated to be left free and unobstructed 41 and so as not to inconvenience occupants of adjacent property. 42 c. If the street is occupied by railroad tracks,the Work shall be carried on in such 43 manner as not to interfere with the operation of the railroad. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 01 1100-5 ® SUMMARY OF WORK Page 5 of 6 1 1) All Work shall be in accordance with railroad requirements set forth in 2 Division 0 as well as the railroad permit. 3 D. Work within Easements 4 1. Do not enter upon private property for any purpose without having previously 5 obtained permission from the owner of such property. 6 2. Do not store equipment or material on private property unless and until the 7 specified approval of the property owner has been secured in writing by the 8 Contractor and a copy furnished to the City. 9 3. Unless specifically provided otherwise,clear all rights-of-way or easements of 10 obstructions which must be removed to make possible proper prosecution of the I 1 Work as a part of the project construction operations. 12 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery,plants, 13 lawns,fences,culverts,curbing,and all other types of structures or improvements, 14 to all water, sewer,and gas lines,to all conduits,overhead pole lines,or 15 appurtenances thereof,including the construction of temporary fences and to all 16 other public or private property adjacent to the Work. 17 5. Notify the proper representatives of the owners or occupants of the public or private 18 lands of interest in lands which might be affected by the Work. 19 a. Such notice shall be made at least 48 hours in advance of the beginning of the 20 Work. 21 b. Notices shall be applicable to both public and private utility companies and any 22 corporation,company, individual,or other,either as owners or occupants, 23 whose land or interest in land might be affected by the Work. 24 c. Be responsible for all damage or injury to property of any character resulting 25 from any act,omission,neglect, or misconduct in the manner or method or 26 execution of the Work, or at any time due to defective work,material,or 27 equipment. 28 6. Fence 29 a. Restore all fences encountered and removed during construction of the Project 30 to the original or a better than original condition. 31 b. Erect temporary fencing in place of the fencing removed whenever the Work is •. 32 not in progress and when the site is vacated overnight, and/or at all times to 33 provide site security. 34 c. The cost for all fence work within easements,including removal,temporary 35 closures and replacement, shall be subsidiary to the various items bid in the 36 project proposal,unless a bid item is specifically provided in the proposal. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 011100-6 SUMMARY OF WORK Page 6 of 6 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION [NOT USED] 11 END OF SECTION 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 012500-1 SUBSTITUTION PROCEDURES Page 1 of 4 1 SECTION 0125 00 2 SUBSTITUTION PROCEDURES 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedure for requesting the approval of substitution of a product that is not 7 equivalent to a product which is specified by descriptive or performance criteria or 8 defined by reference to 1 or more of the following: 9 a. Name of manufacturer 10 b. Name of vendor 11 c. Trade name 12 d. Catalog number 13 2. Substitutions are not"or-equals". 14 B. Deviations from this City of Fort Worth Standard Specification 15 1. None. 16 C. Related Specification Sections include,but are not necessarily limited to: 17 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 18 2. Division 1—General Requirements 19 1.2 PRICE AND PAYMENT PROCEDURES 20 A. Measurement and Payment 21 1. Work associated with this Item is considered subsidiary to the various items bid. 22 No separate payment will be allowed for this Item. 23 1.3 REFERENCES [NOT USED] 24 1.4 ADMINISTRATIVE REQUIREMENTS 25 A. Request for Substitution-General 26 1. Within 30 days after award of Contract(unless noted otherwise),the City will 27 consider formal requests from Contractor for substitution of products in place of 28 those specified. 29 2. Certain types of equipment and kinds of material are described in Specifications by 30 means of references to names of manufacturers and vendors,trade names,or 31 catalog numbers. 32 a. When this method of specifying is used,it is not intended to exclude from 33 consideration other products bearing other manufacturer's or vendor's names, 34 trade names,or catalog numbers,provided said products are "or-equals,"as 35 determined by City. 36 3. Other types of equipment and kinds of material may be acceptable substitutions 37 under the following conditions: 38 a. Or-equals are unavailable due to strike, discontinued production of products 39 meeting specified requirements,or other factors beyond control of Contractor; 40 or, CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 0125 00-2 SUBSTITUTION PROCEDURES Page 2 of 4 1 b. Contractor proposes a cost and/or time reduction incentive to the City. 2 1.5 SUBMITTALS 3 A. See Request for Substitution Form(attached) 4 B. Procedure for Requesting Substitution 5 1. Substitution shall be considered only: 6 a. After award of Contract 7 b. Under the conditions stated herein 8 2. Submit 3 copies of each written request for substitution,including: 9 a. Documentation 10 1) Complete data substantiating compliance of proposed substitution with 11 Contract Documents 12 2) Data relating to changes in construction schedule,when a reduction is 13 proposed 14 3) Data relating to changes in cost 15 b. For products 16 1) Product identification 17 a) Manufacturer's name 18 b) Telephone number and representative contact name 19 c) Specification Section or Drawing reference of originally specified 20 product,including discrete name or tag number assigned to original 21 product in the Contract Documents 22 2) Manufacturer's literature clearly marked to show compliance of proposed 23 product with Contract Documents 24 3) Itemized comparison of original and proposed product addressing product 25 characteristics including,but not necessarily limited to: 26 a) Size 27 b) Composition or materials of construction 28 c) Weight 29 d) Electrical or mechanical requirements 30 4) Product experience 31 a) Location of past projects utilizing product 32 b) Name and telephone number of persons associated with referenced 33 projects knowledgeable concerning proposed product 34 c) Available field data and reports associated with proposed product 35 5) Samples 36 a) Provide at request of City. 37 b) Samples become the property of the City. 38 c. For construction methods: 39 1) Detailed description of proposed method 40 2) Illustration drawings 41 C. Approval or Rejection -® 42 1. Written approval or rejection of substitution given by the City 43 2. City reserves the right to require proposed product to comply with color and pattern 44 of specified product if necessary to secure design intent. 45 3. In the event the substitution is approved,the resulting cost and/or time reduction 46 will be documented by Change Order in accordance with the General Conditions. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT �.. Revised July 1,2011 City Project No.100889 012500-3 SUBSTITUTION PROCEDURES Page 3 of 4 1 4. No additional contract time will be given for substitution. 2 5. Substitution will be rejected if-. 3 a. Submittal is not through the Contractor with his stamp of approval 4 b. Request is not made in accordance with this Specification Section ^- 5 c. In the City's opinion,acceptance will require substantial revision of the original 6 design 7 d. In the City's opinion, substitution will not perform adequately the function 8 consistent with the design intent 9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 10 1.7 CLOSEOUT SUBMITTALS [NOT USED] 11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 12 1.9 QUALITY ASSURANCE 13 A. In making request for substitution or in using an approved product,the Contractor 14 represents that the Contractor: 15 1. Has investigated proposed product,and has determined that it is adequate or 16 superior in all respects to that specified,and that it will perform function for which 17 it is intended 18 2. Will provide same guarantee for substitute item as for product specified 19 3. Will coordinate installation of accepted substitution into Work,to include building 20 modifications if necessary,making such changes as may be required for Work to be 21 complete in all respects 22 4. Waives all claims for additional costs related to substitution which subsequently 23 arise 24 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 25 1.11 FIELD [SITE] CONDITIONS [NOT USED] 26 1.12 WARRANTY [NOT USED] 27 PART 2- PRODUCTS [NOT USED] 28 PART 3- EXECUTION [NOT USED] 29 END OF SECTION 30 Revision Log DATE NAME SUMMARY OF CHANGE 31 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 012500-4 SUBSTITUTION PROCEDURES Page 4 of 4 1 EXHIBIT A 2 REQUEST FOR SUBSTITUTION FORM: ■*+ 3 4 TO: 5 PROJECT: DATE: .. 6 We hereby submit for your consideration the following product instead of the specified item for 7 the above project: 8 SECTION PARAGRAPH SPECIFIED ITEM 9 10 11 Proposed Substitution: 12 Reason for Substitution: 13 Include complete information on changes to Drawings and/or Specifications which proposed 14 substitution will require for its proper installation. 15 16 Fill in Blanks Below: 17 A. Will the undersigned contractor pay for changes to the building design, including engineering 18 and detailing costs caused by the requested substitution? 19 20 �. 21 B. What effect does substitution have on other trades? 22 23 24 C. Differences between proposed substitution and specified item? *r 25 26 27 D. Differences in product cost or product delivery time? 28 29 30 E. Manufacturer's guarantees of the proposed and specified items are: 31 �. 32 Equal Better(explain on attachment) 33 The undersigned states that the function, appearance and quality are equivalent or superior to the 34 specified item. 35 Submitted By: For Use by City 36 37 Signature _Recommended ,Recommended 38 as noted 39 40 Firm _Not recommended Received late 41 Address By 42 Date 43 Date Remarks 44 Telephone 45 46 For Use by City: 47 48 Approved Rejected 49 City Date CITY OF FORT WORTH. 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT wr Revised July 1,2011 City Project No. 100889 013119-1 PRECONSTRUCTION MEETING Page 1 of 3 1 SECTION 013119 2 PRECONSTRUCTION MEETING 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to 7 clarify construction contract administration procedures 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include, but are not necessarily limited to: 11 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 12 2. Division I —General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered subsidiary to the various items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS 19 A. Coordination 20 1. Attend preconstruction meeting. 21 2. Representatives of Contractor, subcontractors and suppliers attending meetings 22 shall be qualified and authorized to act on behalf of the entity each represents. 23 3. Meeting administered by City may be tape recorded. 24 a. If recorded,tapes will be used to prepare minutes and retained by City for 25 future reference. 26 B. Preconstruction Meeting 27 1. A preconstruction meeting will be held within 14 days after the execution of the 28 Agreement and before Work is started. 29 a. The meeting will be scheduled and administered by the City. 30 2. The Project Representative will preside at the meeting,prepare the notes of the 31 meeting and distribute copies of same to all participants who so request by fully 32 completing the attendance form to be circulated at the beginning of the meeting. 33 3. Attendance shall include: 34 a. Project Representative 35 b. Contractor's project manager 36 c. Contractor's superintendent 37 d. Any subcontractor or supplier representatives whom the Contractor may desire 38 to invite or the City may request CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August:17,2012 City Project No.100889 013119-2 PRECONSTRUCTION MEETING Page 2 of 3 1 e. Other City representatives 2 f.. Others as appropriate 3 4. Construction Schedule 4 a. Prepare baseline construction schedule in accordance with Section 0132 16 and 5 provide at Preconstruction Meeting. 6 b. City will notify Contractor of any schedule changes upon Notice of 7 Preconstruction Meeting. 8 5. Preliminary Agenda may include: 9 a. Introduction of Project Personnel 10 b. General Description of Project 11 c. Status of right-of-way,utility clearances,easements or other pertinent permits 12 d. Contractor's work plan and schedule 13 e. Contract Time 14 f. Notice to Proceed 15 g. Construction Staking 16 h. Progress Payments 17 i. Extra Work and Change Order Procedures 18 j. Field Orders 19 k. Disposal Site Letter for Waste Material 20 1. Insurance Renewals 21 in. Payroll Certification 22 n. Material Certifications and Quality Control Testing 23 o. Public Safety and Convenience 24 p. Documentation of Pre-Construction Conditions 25 q. Weekend Work Notification 26 r. Legal Holidays 27 s. Trench Safety Plans 28 t. Confined Space Entry Standards 29 u. Coordination with the City's representative for operations of existing water 30 systems 31 v. Storm Water Pollution Prevention Plan 32 w. Coordination with other Contractors 33 x. Early Warning System 34 y. Contractor Evaluation 35 z. Special Conditions applicable to the project 36 aa. Damages Claims 37 bb. Submittal Procedures 38 cc. Substitution Procedures 39 dd. Correspondence Routing 40 ee. Record Drawings 41 ff. Temporary construction facilities 42 gg. M/WBE or MBE/SBE procedures 43 hh. Final Acceptance 44 ii. Final Payment 45 jj. Questions or Comments CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 17,2012 City Project No.100889 013119-3 PRECONSTRUCTION MEETING Page 3 of 3 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY[NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION[NOT USED] 11 END OF SECTION 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 CITY OF FORT WORTH 2017 WATER LEAD SERVICES -- STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised August 17,2012 City Project No.100889 013216-1 CONSTRUCTION PROGRESS SCHEDULE Page 1 of 5 1 SECTION 0132 16 2 CONSTRUCTION PROGRESS SCHEDULE 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. General requirements for the preparation, submittal,updating, status reporting and 7 management of the Construction Progress Schedule 8 2. Specific requirements are presented in the City of Fort Worth Schedule Guidance 9 Document 10 B. Deviations from this City of Fort Worth Standard Specification 11 1. None. -� 12 C. Related Specification Sections include,but are not necessarily limited to: 13 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 14 2. Division I —General Requirements 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Work associated with this Item is considered subsidiary to the various items bid. 18 No separate payment will be allowed for this Item. ., 19 1.3 REFERENCES 20 A. Definitions 21 1. Schedule Tiers 22 a. Tier 1 -No schedule submittal required by contract. Small,brief duration 23 projects 24 b. Tier 2-No schedule submittal required by contract,but will require some 25 milestone dates. Small,brief duration projects 26 c. Tier 3-Schedule submittal required by contract as described in the 27 Specification and herein.Majority of City projects,including all bond program 28 projects 29 d. Tier 4-Schedule submittal required by contract as described in the 30 Specification and herein.Large and/or complex projects with long durations - 31 1) Examples:large water pump station project and associated pipeline with 32 interconnection to another governmental entity 33 e. Tier 5-Schedule submittal required by contract as described in the 34 Specification and herein.Large and/or very complex projects with long 35 durations,high public visibility 36 1) Examples might include a water or wastewater treatment plant 37 2. Baseline Schedule-Initial schedule submitted before work begins that will serve 38 as the baseline for measuring progress and departures from the schedule. 39 3. Progress Schedule-Monthly submittal of a progress schedule documenting 40 progress on the project and any changes anticipated. CITY OF FORT WORTH 2017 WATER LEAD SERVICES �. STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 013216-2 CONSTRUCTION PROGRESS SCHEDULE Page 2 of 5 1 4. Schedule Narrative-Concise narrative of the schedule including schedule 2 changes,expected delays,key schedule issues,critical path items,etc 3 B. Reference Standards 4 1. City of Fort Worth Schedule Guidance Document 5 1.4 ADMMSTRATIVE REQUIREMENTS 6 A. Baseline Schedule 7 1. General 8 a. Prepare a cost-loaded baseline Schedule using approved software and the 9 Critical Path Method(CPM)as required in the City of Fort Worth Schedule 10 Guidance Document. .- 11 b. Review the draft cost-loaded baseline Schedule with the City to demonstrate 12 understanding of the work to be performed and known issues and constraints 13 related to the schedule. 14 c. Designate an authorized representative(.Project Scheduler)responsible for 15 developing and updating the schedule and preparing reports. 16 B. Progress Schedule 17 1. Update the progress Schedule monthly as required in the City of Fort Worth 18 Schedule Guidance Document. 19 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 20 3. Change Orders 21 a. Incorporate approved change orders,resulting in a change of contract time, in 22 the baseline Schedule in accordance with City of Fort Worth Schedule 23 Guidance Document. 24 C. Responsibility for Schedule Compliance 25 1. Whenever it becomes apparent from the current progress Schedule and CPM Status 26 Report that delays to the critical path have resulted and the Contract completion 27 date will not be met,or when so directed by the City,make some or all of the 28 following actions at no additional cost to the City 29 a. Submit a Recovery Plan to the City for approval revised baseline Schedule 30 outlining: 31 1) A written statement of the steps intended to take to remove or arrest the 32 delay to the critical path in the approved schedule 33 2) .Increase construction manpower in such quantities and crafts as will 34 substantially eliminate the backlog of work and return current Schedule to 35 meet projected baseline completion dates 36 3) Increase the number of working hours per shift, shifts per day,working 37 days per week,the amount of construction equipment,or any combination 38 of the foregoing, sufficiently to substantially eliminate the backlog of work 39 4) Reschedule activities to achieve maximum practical concurrency of 40 accomplishment of activitiesi and comply with the revised schedule '~ 41 2. If no written statement of the steps intended to take is submitted when so requested 42 by the City,the City may direct the Contractor to increase the level of effort in 43 manpower(trades),equipment and work schedule(overtime,weekend and holiday " 44 work,etc.)to be employed by the Contractor in order to remove or arrest the delay 45 to the critical path in the approved schedule. 46 a. No additional cost for such work will be considered. �- CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 013216-3 CONSTRUCTION PROGRESS SCHEDULE Page 3 of 5 1 D. The Contract completion time will be adjusted only for causes specified in this 2 Contract. 3 a. Requests for an extension of any Contract completion date must be 4 supplemented with the following: 5 1) Furnish justification and supporting evidence as the City may deem 6 necessary to determine whether the requested extension of time is entitled 7 under the provisions of this Contract. 8 a) The City will,after receipt of such justification and supporting 9 evidence,make findings of fact and will advise the Contractor,in 10 writing thereof. 11 2) If the City finds that the requested extension of time is entitled,the City's 12 determination as to the total number of days allowed for the extensions 13 shall be based upon the approved total baseline schedule and on all data 14 relevant to the extension. 15 a) Such data shall be included in the next updating of the Progress 16 schedule. 17 b) Actual delays in activities which,according to the Baseline schedule, 18 do not affect any Contract completion date shown by the critical path in 19 the network will not be the basis for a change therein. 20 2. Submit each request for change in.Contract completion date to the City within 30 21 days after the beginning of the delay for which a time extension is requested but 22 before the date of final payment under this Contract. 23 a. No time extension will be granted for requests which are not submitted within , 24 the foregoing time limit. 25 b. From time to time,it may be necessary for the Contract schedule or completion 26 time to be adjusted by the City to reflect the effects of job conditions,weather, 27 technical difficulties,strikes,unavoidable delays on the part of the City or its 28 representatives,and other unforeseeable conditions which may indicate 29 schedule adjustments or completion time extensions. 30 1) Under such conditions,the City will direct the Contractor to reschedule the 31 work or Contract completion time to reflect the changed conditions and the 32 Contractor shall revise his schedule accordingly. 33 a) No additional compensation will be made to the Contractor for such 34 schedule changes except for unavoidable overall contract time 35 extensions beyond the actual completion of unaffected work, in which 36 case the Contractor shall take all possible action to minimize any time �. 37 extension and any additional cost to the City. 38 b) Available float time in the Baseline schedule may be used by the City 39 as well as by the Contractor. 40 3. Float or slack time is defined as the amount of time between the earliest start date 41 and the latest start date or between the earliest finish date and the latest finish date 42 of a chain of activities on the Baseline Schedule. 43 a. Float or slack time is not for the exclusive use or benefit of either the 44 Contractor or the City. 45 b. Proceed with work according to early start dates,and the City shall have the 46 right to reserve and apportion float time according to the needs of the project. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 013216-4 CONSTRUCTION PROGRESS SCHEDULE Page 4 of 5 1 c. Acknowledge and agree that actual delays,affecting paths of activities 2 containing float time,will not have any effect upon contract completion times, 3 providing that the actual delay does not exceed the float time associated with 4 those activities. 5 E. Coordinating Schedule with Other Contract Schedules 6 1. Where work is to be performed under this Contract concurrently with or contingent 7 upon work performed on the same facilities or area under other contracts,the 8 Baseline Schedule shall be coordinated with the schedules of the other contracts. 9 a. Obtain the schedules of the other appropriate contracts from the City for the 10 preparation and updating of Baseline schedule and make the required changes 11 in his schedule when indicated by changes in corresponding schedules. 12 2. In case of interference between the operations of different contractors,the City will 13 determine the work priority of each contractor and the sequence of work necessary 14 to expedite the completion of the entire Project. 15 a. In such cases,the decision of the City shall be accepted as final. 16 b. The temporary delay of any work due to such circumstances shall not be 17 considered as justification for claims for additional compensation. �. 18 1.5 SUBMITTALS 19 A. Baseline Schedule ®. 20 1. Submit Schedule in native file format and pdf format as required in the City of Fort 21 Worth Schedule Guidance Document. 22 a. Native file format includes: 23 1) Primavera(P6 or Primavera Contractor) 24 2. Submit draft baseline Schedule to City prior to the pre-construction meeting and 25 bring in hard copy to the meeting for review and discussion. -. 26 B. Progress Schedule 27 1. Submit progress Schedule in native file format and pdf format as required in the 28 City of Fort Worth Schedule Guidance Document. 29 2. Submit progress Schedule monthly no later than the last day of the month. 30 C. Schedule Narrative -. 31 1. Submit the schedule narrative in pdf format as required in.the City of Fort Worth 32 Schedule Guidance Document. 33 2. Submit schedule narrative monthly no later than the last day of the month. 34 D. Submittal Process 35 1, The City administers and manages schedules through Buzzsaw. 36 2. Contractor shall submit documents as required in the City of Fort Worth Schedule 37 Guidance Document. 38 3. Once the project has been completed and Final Acceptance has been issued by the 39 City,no further progress schedules are required. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT �. Revised July 1,2011 City Project No.100889 013216-5 CONSTRUCTION PROGRESS SCHEDULE Page 5 of 5 1 1.6 ACTION SUBMITTALSANFORMATIONA.L SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE 5 A. The person preparing and revising the construction Progress Schedule shall be 6 experienced in the preparation of schedules of similar complexity. 7 B. Schedule and supporting documents addressed in this Specification shall be prepared, 8 updated and revised to accurately reflect the performance of the construction. 9 C. Contractor is responsible for the quality of all submittals in this section meeting the 10 standard of care for the construction industry for similar projects. 11 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 12 1.11 FIELD [SITE] CONDITIONS [NOT USED] 13 1.12 WARRANTY[NOT USED] 14 PART 2- PRODUCTS [NOT USED] 15 PART 3- EXECUTION [NOT USED] 16 END OF SECTION 17 Revision Log DATE NAME SUMMARY OF CHANGE 18 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 01 32 33-1 PRECONSTRUCTION VIDEO Page 1 of 2 1 SECTION 0132 33 2 PRECONSTRUCTION VIDEO 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Administrative and procedural requirements for: 7 a. Preconstruction Videos 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. Pre-construction Videos-Given the brief nature of the Work Orders in this 10 contract,pre-construction videos will only be required as requested by the 11 inspector or directed by the Engineer. 12 C. Related Specification Sections include,but are not necessarily limited to: 13 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 14 2. Division 1 —General Requirements 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment �- 17 1. Work associated with this Item is considered subsidiary to the various items bid. 18 No separate payment will be allowed for this Item. 19 1.3 REFERENCES [NOT USED] 20 1.4 ADMINISTRATIVE REQUIREMENTS 21 A. Preconstruction Video Am 22 1. Produce a preconstruction video of the site/alignment,including all areas in the 23 vicinity of and to be affected by construction. 24 a. Provide digital copy of video upon request by the City. 25 2. Retain a copy of the preconstruction video until the end of the maintenance surety 26 period. 27 1.5 SUBMITTALS [NOT USED] 28 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 29 1.7 CLOSEOUT SUBMITTALS [NOT USED] 30 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 31 1.9 QUALITY ASSURANCE[NOT USED] 32 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 33 1.11 FIELD [SITE] CONDITIONS [NOT USED] 34 1.12 WARRANTY[NOT USED] CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised duly 1,2011 City Project No.100889 013233-2 PRECONSTRUCTION VIDEO Page 2 of 2 I PART 2- PRODUCTS [NOT USED] i 2 PART 3- EXECUTION [NOT USED] 3 END OF SECTION 4 Revision Log DATE NAME SUMMARY OF CHANGE 5 i i i IYB ■IPI CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July I;2011 City Project No.100889 013300-1 SUBMITTALS Page 1 of 8 1 SECTION 0133 00 2 SUBMITTALS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. General methods and requirements of submissions applicable to the following 7 Work-related submittals: 8 a. Shop Drawings 9 b. Product Data(including Standard Product List submittals) 10 c. Samples it d. Mock Ups 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include,but are not necessarily limited to: 15 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 16 2. Division 1 —General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Coordination �. 24 1. Notify the City in writing, at the time of submittal, of any deviations in the 25 submittals from the requirements of the Contract Documents. 26 2. Coordination of Submittal Times 27 a. Prepare,prioritize and transmit each submittal sufficiently in advance of 28 performing the related Work or other applicable activities, or within the time 29 specified in the individual Work Sections,of the Specifications. 30 b. Contractor is responsible such that the installation will not be delayed by 31 processing times including,but not limited to: 32 a) Disapproval and resubmittal(if required) 33 b) Coordination with other submittals 34 c) Testing 35 d) Purchasing 36 e) Fabrication 37 f) Delivery 38 g) Similar sequenced activities 39 c. No extension of time will be authorized because of the Contractor's failure to 40 transmit submittals sufficiently in advance of the Work. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 013300-2 SUBMITTALS Page 2 of 8 1 d. Make submittals promptly in accordance with approved schedule,and in such 2 sequence as to cause no delay in the Work or in the work of any other _ 3 contractor. 4 B. Submittal Numbering 5 1. When submitting shop drawings or samples,utilize a 9-character submittal cross- 6 reference identification numbering system in the following manner: 7 a. Use the first 6 digits of the applicable Specification Section.Number. 8 b. For the next 2 digits number use numbers 01-99 to sequentially number each ^w` 9 initial separate item or drawing submitted under each specific Section number. 10 c. Last use a letter,A-Z, indicating the resubmission of the same drawing(i.e. 11 A=2nd submission,B=3rd submission,C=4th submission,etc.). A typical — 12 submittal number would be as follows: 13 14 03 30 00-08-B 15 16 1) 03 30 00 is the Specification Section for Concrete 17 2) 08 is the eighth initial submittal under this Specification Section 18 3) B is the third submission(second resubmission)of that particular shop 19 drawing 20 C. Contractor Certification 21 1. Review shop drawings,product data and samples, including those by 22 subcontractors,prior to submission to determine and verify the following: 23 a. Field measurements 24 b. Field construction criteria 25 c. Catalog numbers and similar data 26 d. Conformance with the Contract Documents 27 2. Provide each shop drawing,sample and product data submitted by the Contractor 28 with a Certification Statement affixed including: 29 a. The Contractor's Company name 30 b. Signature of submittal reviewer 31 c. Certification Statement 32 1) `By this submittal,I hereby represent that I have determined and verified 33 field measurements,field construction criteria,materials,dimensions, " 34 catalog numbers and similar data and I have checked and coordinated each 35 item with other applicable approved shop drawings." 36 D. Submittal Format 37 1. Fold shop drawings larger than 8 %2 inches x 11 inches to 8 %2 inches x 11 inches. 38 2. Bind shop drawings and product data sheets together. 39 3. Order 40 a. Cover Sheet 41 1) Description of Packet _ 42 2) Contractor Certification 43 b. List of items/Table of Contents 44 c. Product Data/Shop Drawings/Samples/Calculations 45 E. Submittal Content 46 1. The date of submission and the dates of any previous submissions CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No. 100889 013300-3 SUBMITTALS Page 3 of 8 1 2. The Project title and number °— 2 3. Contractor identification 3 4. The names of: 4 a. Contractor 5 b. Supplier 6 c. Manufacturer 7 5. Identification of the product,with the Specification Section number,page and. 8 paragraph(s) 9 6. Field dimensions,clearly identified as such 10 7. Relation to adjacent or critical features of the Work or materials 11 8. Applicable standards,such as ASTM or Federal Specification numbers 12 9. Identification by highlighting of deviations from Contract Documents 13 10. Identification by highlighting of revisions on resubmittals 14 11. An 8-inch x 3-inch blank space for Contractor and City stamps 15 F. Shop Drawings 16 1. As specified in individual Work Sections includes, but is not necessarily limited to: 17 a. Custom-prepared data such as fabrication and erection/installation(working) 18 drawings 19 b. Scheduled information 20 c. Setting diagrams 21 d. Actual shopwork manufacturing instructions 22 e. Custom templates 23 f. Special wiring diagrams 24 g. Coordination drawings 25 h. Individual system or equipment inspection and test reports including: 26 1) Performance curves and certifications 27 i. As applicable to the Work 28 2. Details 29 a. Relation of the various parts to the main members and lines of the structure 30 b. Where correct fabrication of the Work depends upon field measurements m— 31 1) Provide such measurements and note on the drawings prior to submitting 32 for approval. 33 G. Product Data 34 1. For submittals of product data for products included on the City's Standard Product 35 List,clearly identify each item selected for use on the Project. 36 2. For submittals of product data for products not included on the City's Standard 37 Product List,submittal data may include,but is not necessarily limited to: 38 a. Standard prepared data for manufactured products(sometimes referred to as 39 catalog data) 40 1) Such as the manufacturer's product specification and installation 41 instructions 42 2) Availability of colors and patterns 43 3) Manufacturer's printed statements of compliances and applicability 44 4) Roughing-in diagrams and templates 45 5) Catalog cuts 46 6) Product photographs CITY OF FORT WORTH 2017 WATER LEAD SERVICES .. STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 013300-4 SUBMITTALS Page 4 of 8 1 7) Standard wiring diagrams 2 8) Printed performance curves and operational-range diagrams 3 9) Production or quality control inspection and test reports and certifications 4 10) Mill reports 5 11) Product operating and maintenance instructions and recommended , 6 spare-parts listing and printed product warranties 7 12) As applicable to the Work 8 H. Samples -- 9 1. As specified in individual Sections,include,but are not necessarily limited to: 10 a. Physical examples of the Work such as: 11 1) Sections of manufactured or fabricated Work 12 2) Small cuts or containers of materials 13 3) Complete units of repetitively used products color/texture/pattern swatches 14 and range sets 15 4) Specimens for coordination of visual effect 16 5) Graphic symbols and units of Work to be used by the City for independent 17 inspection and testing,as applicable to the Work _ 18 I. Do not start Work requiring a shop drawing,sample or product data nor any material to 19 be fabricated or installed prior to the approval or qualified approval of such item. 20 1. Fabrication performed,materials purchased or on-site construction accomplished 21 which does not conform to approved shop drawings and data is at the Contractor's 22 risk. 23 2. The City will not be liable for any expense or delay due to corrections or remedies 24 required to accomplish conformity. 25 3. Complete project Work,materials,fabrication,and installations in conformance 26 with approved shop drawings,applicable samples, and product data. 27 J. Submittal Distribution 28 1. Electronic Distribution 29 a. Confirm development of Project directory for electronic submittals to be 30 uploaded to City's Buzzsaw site, or another external FTP site approved by the 31 City. 32 b. Shop Drawings 33 1) Upload submittal to designated project directory and notify appropriate 34 City representatives via email of submittal posting. 35 2) Hard Copies 36 a) 3 copies for all submittals 37 b) If Contractor requires more than 1 hard copy of Shop Drawings 38 returned, Contractor shall submit more than the number of copies listed 39 above. 40 c. Product Data 41 1) Upload submittal to designated project directory and notify appropriate 42 City representatives via email of submittal posting. 43 2) Hard Copies 44 a) 3 copies for all submittals 45 d. Samples 46 1) Distributed to the Project Representative 47 2. Hard Copy Distribution(if required in lieu of electronic distribution) CITY OF FORT WORTH 201.7 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT , Revised December 20,2012 City Project No.100889 013300-5 SUBMITTALS Page 5 of 8 1 a. Shop Drawings 2 1) Distributed to the City 3 2) Copies 4 a) 8 copies for mechanical submittals 5 b) 7 copies for all other submittals 6 c) If Contractor requires more than 3 copies of Shop Drawings returned, 7 Contractor shall submit more than the number of copies listed above. 8 b. Product Data 9 1) Distributed to the City 10 2) Copies 11 a) 4 copies 12 c. Samples 13 1) Distributed to the Project Representative 14 2) Copies 15 a) Submit the number stated in the respective Specification Sections. 16 3. Distribute reproductions of approved shop drawings and copies of approved 17 product data and samples,where required,to the job site file and elsewhere as 18 directed by the City. 19 a. Provide number of copies as directed by the City but not exceeding the number 20 previously specified. 21 K. Submittal.Review 22 1. The review of shop drawings,data and samples will be for general conformance 23 with the design concept and Contract Documents. This is not to be construed as: 24 a. Permitting any departure from the Contract requirements 25 b. Relieving the Contractor of responsibility for any errors,including details, 26 dimensions,and materials 27 c. Approving departures from details furnished by the City, except as otherwise 28 provided herein 29 2. The review and approval of shop drawings, samples or product data by the City 30 does not relieve the Contractor from his/her responsibility with regard to the 31 fulfillment of the terms of the Contract. 32 a. All risks of error and.omission are assumed by the Contractor,and the City will 33 have no responsibility therefore. 34 3. The Contractor remains responsible for details and accuracy,for coordinating the 35 Work with all other associated work and trades, for selecting fabrication processes, -- 36 for techniques of assembly and for performing Work in a safe manner. 37 4. If the shop drawings,data or samples as submitted describe variations and show a 38 departure from the Contract requirements which City finds to be in the interest of -� 39 the City and to be so minor as not to involve a change in Contract Price or time for 40 performance,the City may return the reviewed drawings without noting an 41 exception. 42 5. Submittals will be returned to the Contractor under 1 of the following codes: 43 a. Code 1 44 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or 45 comments on the submittal. 46 a) When returned under this code the Contractor may release the 47 equipment and/or material for manufacture. 48 b. Code 2 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No. 100889 013300-6 SUBMITTALS Page 6 of 8 1 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of 2 the notations and comments IS NOT required by the Contractor. 3 a) The Contractor may release the equipment or material for manufacture; 4 however,all notations and comments must be incorporated into the 5 final product. 6 c. Code 3 7 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is 8 assigned when notations and comments are extensive enough to require a 9 resubmittal of the package. 10 a) The Contractor may release the equipment or material for manufacture; 11 however,all notations and comments must be incorporated into the 12 final product. 13 b) This resubmittal is to address all comments, omissions and 14 non-conforming items that were noted. 15 c) Resubmittal is to be received by the City within 15 Calendar Days of 16 the date of the City's transmittal requiring the resubmittal. 17 d. Code 4 18 1) "NOT APPROVED" is assigned when the submittal does not meet the _ 19 intent of the Contract Documents. 20 a) The Contractor must resubmit the entire package revised to bring the 21 submittal into conformance. 22 b) It may be necessary to resubmit using a different manufacturer/vendor 23 to meet the Contract Documents. 24 6. Resubmittals 25 a. Handled in the same manner as first submittals 26 1) Corrections other than requested by the City 27 2) Marked with revision triangle or other similar method 28 a) At Contractor's risk if not marked 29 b. Submittals for each item will be reviewed no more than twice at the City's 30 expense. 31 1) All subsequent reviews will be performed at times convenient to the City 32 and at the Contractor's expense,based on the City's or City 33 Representative's then prevailing rates. 34 2) Provide Contractor reimbursement to the City within 30 Calendar Days for 35 all such fees invoiced by the City. 36 c. The need for more than 1 resubmission or any other delay in obtaining City's 37 review of submittals,will not entitle the Contractor to an extension of Contract ,. 38 Time. 39 7. Partial Submittals 40 a. City reserves the right to not review submittals deemed partial, at the City's 41 discretion. 42 b. Submittals deemed by the City to be not complete will be returned to the 43 Contractor,and will be considered "Not Approved"until resubmitted. 44 c. The City may at its option provide a list or mark the submittal directing the 45 Contractor to the areas that are incomplete. 46 8. If the Contractor considers any correction indicated on the shop drawings to 47 constitute a change to the Contract Documents,then written notice must be 48 provided thereof to the City at least 7 Calendar Days prior to release for 49 manufacture. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 013300-7 SUBMITTALS Page 7 of 8 1 9. When the shop drawings have been completed to the satisfaction of the City,the 2 Contractor may carry out the construction in accordance therewith and no further 3 changes therein except upon written instructions from the City. 4 10. Each submittal,appropriately coded,will be returned within 30 Calendar Days 5 following receipt of submittal by the City. 6 L. Mock ups 7 1. Mock Up units as specified in individual.Sections, include,but are not necessarily 8 limited to,complete units of the standard of acceptance for that type of Work to be 9 used on the Project. Remove at the completion of the Work or when directed. 10 M. Qualifications 11 1. If specifically required in other Sections of these Specifications,submit a P.E. 12 Certification for each item required. 13 N. Request for Information(RFI) 14 1. Contractor Request for additional information 15 a. Clarification or interpretation of the contract documents 16 b. When the Contractor believes there is a conflict between Contract Documents 17 c. When the Contractor believes there is a conflict between the Drawings and 18 Specifications 19 1) Identify the conflict and request clarification 20 2. Use the Request for Information(RFI)form provided by the City. 21 3. Numbering of RFI 22 a. Prefix with"RFP' followed by series number,"-xxx",beginning with"01"and 23 increasing sequentially with each additional transmittal. 24 4. Sufficient information shall be attached to permit a written response without further 25 information. 26 5. The City will log each request and will review the request. 27 a. If review of the project information request indicates that a change to the 28 Contract Documents is required,the City will issue a Field Order or Change 29 Order,as appropriate. 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 32 1.7 CLOSEOUT SUBMITTALS [NOT USED] 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 34 1.9 QUALITY ASSURANCE [NOT USED] 35 1.10 DELIVERY,STORAGE,AND HANDLING[NOT USED] 36 1.11 FIELD [SITE] CONDITIONS [NOT USED] 37 1.12 WARRANTY [NOT USED] CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.I00889 r® 013300-8 SUBMITTALS Page 8 of 8 PM I PART 2- PRODUCTS [NOT USED] MR 2 PART 3- EXECUTION [NOT USED] ow 3 END OF SECTION 4 A Revision Log DATE NAME SUMMARY OF CHANGE r.. 12/20/2012 D.Johnson 1.4.K.8.Working Days modified to Calendar Days 5 w sn CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No. 100889 '� 013513-1 SPECIAL PROJECT PROCEDURES Page 1.of 8 1 SECTION 0135 13 2 SPECIAL PROJECT PROCEDURES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedures for special project circumstances that includes,but is not limited to: 7 a. Coordination with the Texas Department of Transportation 8 b. Work near High Voltage Lines 9 c. Confined Space Entry Program 10 d. Air Pollution Watch Days 11 e. Use of Explosives,.Drop Weight,Etc. 12 f. Water Department Notification 13 g. Public Notification Prior to Beginning Construction 14 h. Coordination with United States Army Corps of Engineers 15 i. Coordination within Railroad permits areas 1.6 j. Dust Control 17 k. Employee Parking 18 19 B. Deviations from this City of Fort Worth Standard Specification 20 1. None. 21 C. Related Specification Sections include,but are not necessarily limited to: 22 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 23 2. Division 1 —General Requirements 24 3. Section 33 12 25—Connection to Existing Water Mains 25 1.2 PRICE AND PAYMENT PROCEDURES 26 A. Measurement and Payment 27 1. Coordination within Railroad permit areas 28 a. Measurement ,,- 29 1) Measurement for this Item will be by lump sum. 30 b. Payment 31 1) The work performed and materials furnished in accordance with this Item 32 will be paid for at the lump sum price bid for Railroad Coordination. 33 c. The price bid shall include: 34 1) Mobilization 35 2) Inspection 36 3) Safety training 37 4) Additional Insurance 38 5) Insurance Certificates 39 6) Other requirements associated with general coordination with Railroad, 40 including additional employees required to protect the right-of-way and 41 property of the Railroad from damage arising out of and/or from the 42 construction of the Project. CITY OF FORT WORTH 2017 WATER LEAD SERVICES .., STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 013513-2 SPECIAL PROJECT PROCEDURES Page 2 of 8 1 2. Railroad Flagmen 2 a. Measurement 3 1) Measurement for this Item will be per working day. 4 b. Payment 5 1) The work performed and materials furnished in accordance with this Item 6 will be paid for each working day that Railroad Flagmen are present at the 7 Site. 8 c. The price bid shall include: 9 1) Coordination for scheduling flagmen 10 2) Flagmen 11 3) Other requirements associated with Railroad 12 3. All other items 13 a. Work associated with these Items is considered subsidiary to the various Items 14 bid. No separate payment will be allowed for this Item. 15 1.3 REFERENCES 16 A. Reference Standards 17 1. Reference standards cited in this Specification refer to the current reference 18 standard published at the time of the latest revision date logged at the end of this 19 Specification,unless a date is specifically cited. 20 2. Health and Safety Code,Title 9. Safety, Subtitle A.Public Safety,Chapter 752. 21 High Voltage Overhead Lines. 22 3. North Central Texas Council of Governments(NCTCOG)—Clean Construction 23 Specification 24 1.4 ADMINISTRATIVE REQUIREMENTS 25 A. Coordination with the Texas Department of Transportation 26 1. When work in the right-of-way which is under the jurisdiction of the Texas 27 Department of Transportation(TxDOT): 28 a. Notify the Texas Department of Transportation prior to commencing any work 29 therein in accordance with the provisions of the permit 30 b. All work performed in the TxDOT right-of-way shall be performed in 31 compliance with and subject to approval from the Texas Department of 32 Transportation 33 B. Work near High Voltage Lines 34 1. Regulatory Requirements 35 a. All Work near High Voltage Lines(more than 600 volts measured between 36 conductors or between a conductor and the ground)shall be in accordance with 37 Health and Safety Code,Title 9, Subtitle A,Chapter 752. 38 2. Warning sign 39 a. Provide sign of sufficient size meeting all OSHA requirements. 40 3. Equipment operating within 10 feet of high voltage lines will require the following 41 safety features 42 a. Insulating cage-type of guard about the boom or arm 43 b. Insulator links on the lift hook connections for back hoes or dippers 44 c. Equipment must meet the safety requirements as set forth by OSHA and the 45 safety requirements of the owner of the high voltage lines CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0135 13-3 SPECIAL PROJECT PROCEDURES Page 3 of 8 1 4. Work within 6 feet of high voltage electric lines �,. 2 a. Notification shall be given to: 3 1) The power company(example: ONCOR) 4 a) Maintain an accurate log of all such calls to power company and record 5 action taken in each case. 6 b. Coordination with power company 7 1) After notification coordinate with the power company to: 8 a) Erect temporary mechanical barriers,de-energize the lines,or raise or 9 lower the lines 10 c. No personnel may work within 6 feet of a high voltage line before the above 11 requirements have been met. 12 C. Confined Space Entry Program 13 1. Provide and follow approved Confined Space Entry Program in accordance with 14 OSHA requirements. 15 2. Confined Spaces include: 16 a. Manholes 17 b. All other confined spaces in accordance with OSHA's Permit Required for 18 Confined Spaces 19 D. Air Pollution Watch Days 20 1. General 21 a. Observe the following guidelines relating to working on City construction sites 22 on days designated as"AIR POLLUTION WATCH DAYS". — 23 b. Typical Ozone Season 24 1) May 1 through October 31. 25 c. Critical Emission Time 26 1) 6:00 a.m.to 10:00 a.m. 27 2. Watch Days 28 a. The Texas Commission on Environmental Quality(TCEQ),in coordination 29 with the National Weather Service,will issue the Air Pollution Watch by 3:00 30 p.m,on the afternoon prior to the WATCH day. 31 b. Requirements 32 1) Begin work after 10:00 a.m.whenever construction phasing requires the 33 use of motorized equipment for periods in excess of 1 hour. 34 2) However,the Contractor may begin work prior to 10:00 a.m. if- 35 f35 a) Use of motorized equipment is less than 1 hour, or .� 36 b) If equipment is new and certified by EPA as "Low Emitting",or .37 equipment burns Ultra Low Sulfur Diesel(ULSD),diesel emulsions,or 38 alternative fuels such as CNG. 39 E. TCEQ Air Permit 40 1. Obtain TCEQ Air Permit for construction activities per requirements of TCEQ. 41 F. Use of Explosives,Drop Weight,Etc. 42 1. When Contract Documents permit on the project the following will apply: 43 a. Public Notification 44 1) Submit notice to City and proof of adequate insurance coverage,24 hours 45 prior to commencing. 46 2) Minimum 24 hour public notification in accordance with Section 0131 13 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 CityProject No.100889 013513-4 SPECIAL PROJECT PROCEDURES Page 4 of 8 ..� 1 G. Water Department Coordination 2 1. During the construction of this project,it will be necessary to deactivate,for a s-* 3 period of time,existing lines. The Contractor shall be required to coordinate with 4 the Water Department to determine the best times for deactivating and activating 5 those lines. 6 2. Coordinate any event that will require connecting to or the operation of an existing 7 City water line system with the City's representative. 8 a. Coordination shall be in accordance with Section 33 12 25. 9 b. If needed,obtain a hydrant water meter from the Water Department for use 10 during the life of named project. 11 c. In the event that a water valve on an existing live system be turned off and on 12 to accommodate the construction of the project is required,coordinate this 13 activity through the appropriate City representative. 14 1) Do not operate water line valves of existing water system. 15 a) Failure to comply will render the Contractor in violation of Texas Penal 16 Code Title 7,Chapter 28.03 (Criminal Mischief)and the Contractor 17 will be prosecuted to the full extent of the law. 18 b) In addition,the Contractor will assume all liabilities and 19 responsibilities as a result of these actions. 20 H. Public Notification Prior to Beginning Construction i 21 1. Prior to beginning construction on any block in the project, on a block by block 22 basis,prepare and deliver a notice or flyer of the pending construction to the front 23 door of each residence or business that will be impacted by construction.The notice 24 shall be prepared as follows: 25 a. Post notice or flyer 7 days prior to beginning any construction activity on each 26 block in the project area. 27 1) Prepare flyer on the Contractor's letterhead and include the following 28 information: 29 a) Name of Project 30 b) City Project No(CPN) "® 31 c) Scope of Project(i.e.type of construction activity) 32 d) Actual construction duration within the block 33 e) Name of the contractor's foreman and phone number 34 f) Name of the City's inspector and phone number 35 g) City's after-hours phone number 36 2) A sample of the `pre-construction notification' flyer is attached as Exhibit 37 A. 38 3) Submit schedule showing the construction start and finish time for each 39 block of the project to the inspector. 40 4) Deliver flyer to the City Inspector for review prior to distribution. 41 b. No construction will be allowed to begin on any block until the flyer is 42 delivered to all residents of the block. 43 I. Public Notification of Temporary Water Service Interruption during Construction 44 1.. In the event it becomes necessary to temporarily shut down water service to 45 residents or businesses during construction,prepare and deliver a notice or flyer of �.. 46 the pending interruption to the front door of each affected resident. 47 2. Prepared notice as follows: CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0135 13-5 SPECIAL PROJECT PROCEDURES Page 5 of 8 1 a. The notification or flyer shall be posted 24 hours prior to the temporary ,. 2 interruption. 3 b. Prepare flyer on the contractor's letterhead and include the following 4 information: 5 1) Name of the project 6 2) City Project Number 7 3) Date of the interruption of service 8 4) Period the interruption will take place 9 5) Name of the contractor's foreman and phone number 10 6) Name of the City's inspector and phone number I 1 c. A sample of the temporary water service interruption notification is attached as 12 Exhibit B. 13 d. Deliver a copy of the temporary interruption notification to the City inspector 14 for review prior to being distributed. 15 e. No interruption of water service can occur until the flyer has been delivered to 16 all affected residents and businesses. 17 f. Electronic versions of the sample flyers can be obtained from the Project 18 Construction Inspector. 19 J. Coordination with United States Army Corps of Engineers(USACE) 20 1. At locations in the Project where construction activities occur in areas where 21 USACE permits are required,meet all requirements set forth in each designated 22 permit. 23 K. Coordination within Railroad Permit Areas 24 1. At locations in the project where construction activities occur in areas where 25 railroad permits are required,meet all requirements set forth in each designated 26 railroad permit. This includes, but is not limited to, provisions for: 27 a. Flagmen 28 b. Inspectors 29 c. Safety training 30 d. Additional insurance 31 e. Insurance certificates 32 f. Other employees required to protect the right-of-way and property of the 33 Railroad Company from damage arising out of and/or from the construction of 34 the project. Proper utility clearance procedures shall be used in accordance 35 with the permit guidelines. 36 2. Obtain any supplemental information needed to comply with the railroad's 37 requirements. 38 3. Railroad Flagmen 39 a. Submit receipts to City for verification of working days that railroad flagmen 40 were present on Site. 41 L. Dust Control 42 1. Use acceptable measures to control dust at the Site. 43 a. If water is used to control dust,capture and properly dispose of waste water. 44 b. If wet saw cutting is performed,capture and properly dispose of slurry. 45 M. Employee Parking 46 1. Provide parking for employees at locations approved by the City. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 013513-6 SPECIAL PROJECT PROCEDURES Page 6 of 8 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY,STORAGE,AND HANDLING[NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY[NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION [NOT USED] m. I1 END OF SECTION 12 Revision Log _. DATE NAME SUMMARY OF CHANGE I AB—Added requirement of compliance with Health and Safety Code,Title 9. 8/31/2012 D.Johnson Safety,Subtitle A.Public Safety,Chapter 752.High Voltage Overhead Lines. I.4.E—Added Contractor responsibility for obtaining a TCEQ Air Permit 13 4 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 013513-7 SPECIAL PROJECT PROCEDURES Page 7 of 8 1 EX HBTT A 2 (To be printed on Contractor's Letterhead) 3 4 5 6 Date: 7 8 CPN No.: 9 Project Name: 10 Mapsco Location: 11 Limits of Construction: 12 13 Ah AM 14 15 16 17 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT 18 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR 1.9 PROPERTY. 20 21 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE 22 OF THIS NOTICE. �- 23 24 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER 25 ISSUE, PLEASE CALL: 26 27 28 Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.> 29 30 OR 31 32 Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> 33 34 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 35 36 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 37 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 013513-8 SPECIAL PROJECT PROCEDURES Page 8 of 8 1 EXHIBIT B 2 FORT WORTH Doe: Do>s HO.xxxx Prn1w Ilan. NOTICE OF TEMPORARY WATER SERVICE INTERRUPTION DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR WATER SERVICE WILL BE INTERRUPTED ON BETWEEN THE HOURS OF AND IF YOU HAVE QUESTIONS ABOUT THIS SHUT-OUT,PLEASE CALL: MR. AT (CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER) OR MR. AT (CITY INSPECTOR) (TELEPHONE NUMBER) THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE. THANK YOU, CONTRACTOR 3 4 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 014523-1 TESTING AND INSPECTION SERVICES Page I of 2 1 SECTION 0145 23 2 TESTING AND INSPECTION SERVICES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Testing and inspection services procedures and coordination 7 B. Deviations from this City of Fort Worth Standard Specification. 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division I —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 a. Contractor is responsible for performing,coordinating,and payment of all 17 Quality Control testing. 1.8 b. City is responsible for performing and payment for first set of Quality 19 Assurance testing. .,. 20 1) If the first Quality Assurance test performed by the City fails,the 21 Contractor is responsible for payment of subsequent Quality Assurance 22 testing until a passing test occurs. 23 a) Final acceptance will not be issued by City until all required payments 24 for testing by Contractor have been paid in full. 25 1.3 REFERENCES [NOT USED] 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Testing 28 1. Complete testing in accordance with.the Contract Documents. 29 2. Coordination 30 a. When testing is required to be performed by the City,notify City,sufficiently 31 in advance,when testing is needed. 32 b. When testing is required to be completed by the Contractor,notify City, 33 sufficiently in advance,that testing will be performed. 34 3. Distribution of Testing Reports 35 a. Electronic Distribution 36 1) Confirm development of Project directory for electronic submittals to be 37 uploaded to City's.Buzzsaw site,or another external FTP site approved by 38 the City. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No. 100889 014523-2 TESTING AND INSPECTION SERVICES Page 2 of 2 1 2) Upload test reports to designated project directory and notify appropriate 2 City representatives via email of submittal posting. 3 3) Hard Copies 4 a) I copy for all submittals submitted to the Project Representative 5 b. Hard Copy Distribution(if required in lieu of electronic distribution) 6 1) Tests performed by City 7 a) Distribute 1 hard copy to the Contractor 8 2) Tests performed by the Contractor 9 a) Distribute 3 hard copies to City's Project Representative 10 4. Provide City's Project Representative with trip tickets for each delivered load of 11 Concrete or Lime material including the,following information: 12 a. Name of pit 13 b. Date of delivery 14 c. Material delivered 15 B. Inspection 16 1. Inspection or lack of inspection does not relieve the Contractor from obligation to 17 perforin work in accordance with the Contract Documents. �. 18 1.5 SUBMITTALS [NOT USED] 19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 20 1.7 CLOSEOUT SUBMITTALS [NOT USED] 21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 22 1.9 QUALITY ASSURANCE [NOT USED] 23 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 24 1,11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2- PRODUCTS [NOT USED] 27 PART 3- EXECUTION [NOT USED] 28 END OF SECTION 29 Revision Log DATE NAME SUMMARY OF CHANGE 30 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July I,2011 City Project No.100889 015000-1 TEMPORARY FACILITIES AND CONTROLS Page 1 of 4 1 SECTION 0150 00 2 TEMPORARY FACILITIES AND CONTROLS "-' 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provide temporary facilities and controls needed for the Work including, but not .. 7 necessarily limited to: 8 a. Temporary utilities 9 b. Sanitary facilities 10 c. Storage Sheds and Buildings 11 d. Dust control 12 e. Temporary fencing of the construction site -. 13 B. Deviations from this City of Fort Worth Standard Specification 14 1. None. 15 C. Related Specification Sections include,but are not necessarily limited to: 16 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 17 2. Division 1 —General Requirements 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment .� 20 1. Work associated with this Item is considered subsidiary to the various Items bid. 21 No separate payment will be allowed for this Item, 22 1.3 REFERENCES [NOT USED] 23 1.4 ADMINISTRATIVE REQUIREMENTS 24 A. Temporary Utilities 25 1. Obtaining Temporary Service 26 a. Make arrangements with utility service companies for temporary services. 27 b. Abide by rules and regulations of utility service companies or authorities 28 having jurisdiction. 29 c. Be responsible for utility service costs until Work is approved for Final 30 Acceptance. Mft 31. 1) Included are fuel,power, light,heat and other utility services necessary for 32 execution,completion,testing and initial operation of Work. 33 2. Water 34 a. Contractor to provide water required for and in connection with Work to be 35 performed and for specified tests of piping,equipment,devices or other use as 36 required for the completion of the Work. ^- 37 b. Provide and maintain adequate supply of potable water for domestic 38 consumption by Contractor personnel and City's Project Representatives. 39 c. Coordination ,. 40 1) Contact City I week before water for construction is desired CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 01.5000-2 TEMPORARY FACILITIES AND CONTROLS Page 2 of 1 d. Contractor Payment for Construction Water 2 1) Obtain construction water meter from City for payment as billed by City's 3 established rates. 4 3. Electricity and Lighting 5 a. Provide and pay for electric powered service as required for Work,including 6 testing of Work. 7 1) Provide power for lighting,operation of equipment,or other use. 8 b. Electric power service includes temporary power service or generator to 9 maintain operations during scheduled shutdown. 10 4. Telephone 11 a. Provide emergency telephone service at Site for use by Contractor personnel 12 and others performing work or furnishing services at Site. 13 5. Temporary Heat and Ventilation 14 a. Provide temporary heat as necessary for protection or completion of Work. 15 b. Provide temporary heat and ventilation to assure safe working conditions. 16 B. Sanitary Facilities 17 1. Provide and maintain sanitary facilities for persons on Site. 18 a. Comply with regulations of State and local departments of health. 19 2. Enforce use of sanitary facilities by construction personnel at job site. 20 a. Enclose and anchor sanitary facilities. 21 b. No discharge will be allowed from these facilities. 22 c. Collect and store sewage and waste so as not to cause nuisance or health 23 problem. �.. 24 d. Haul sewage and waste off-site at no less than weekly intervals and properly 25 dispose in accordance with applicable regulation. 26 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 27 4. Remove facilities at completion of Project 28 C. Storage Sheds and Buildings 29 1. Provide adequately ventilated,watertight,weatherproof storage facilities with floor 30 above ground level for materials and equipment susceptible to weather damage. 31 2. Storage of materials not susceptible to weather damage may be on blocks off 32 ground. 33 3. Store materials in a neat and orderly manner. 34 a. Place materials and equipment to permit easy access for identification, 35 inspection and inventory. 36 4. Equip building with lockable doors and lighting,and provide electrical service for 37 equipment space heaters and heating or ventilation as necessary to provide storage 38 environments acceptable to specified manufacturers. 39 5. Fill and grade site for temporary structures to provide drainage away from 40 temporary and existing buildings. 41 6. Remove building from site prior to Final Acceptance. 42 D. Temporary Fencing 43 1. Provide and maintain for the duration or construction when required in contract 44 documents 45 E. Dust Control CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 015000-3 TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 1 1. Contractor is responsible for maintaining dust control through the duration of the 2 project. 3 a. Contractor remains on-call at all times 4 b. Must respond in a timely manner 5 F. Temporary Protection of Construction 6 1. Contractor or subcontractors are responsible for protecting Work from damage due 7 to weather. 8 1.5 SUBMITTALS [NOT USED] 9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 10 1.7 CLOSEOUT SUBMITTALS [NOT USED] 11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 12 1.9 QUALITY ASSURANCE [NOT USED] 13 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 14 1.11 FIELD [SITE] CONDITIONS [NOT USED] 15 1.12 WARRANTY [NOT USED] 16 PART 2- PRODUCTS [NOT USED] 17 PART 3- EXECUTION[NOT USED] 18 3.1 INSTALLERS [NOT USED] 19 3.2 EXAMINATION [NOT USED] 20 3.3 PREPARATION [NOT USED] 21 3.4 INSTALLATION 22 A. Temporary Facilities 23 1. Maintain all temporary facilities for duration of construction activities as needed. 24 3.5 [REPAIR]I[RESTORATION] 25 3.6 RE-INSTALLATION 26 3.7 FIELD [OR] SITE QUALITY CONTROL[NOT USED] 27 3.8 SYSTEM STARTUP [NOT USED] 28 3.9 ADJUSTING[NOT USED] 29 3.10 CLEANING [NOT USED] 30 3.11 CLOSEOUT ACTIVITIES 31 A. Temporary Facilities CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No. 100889 015000-4 TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 1 1. Remove all temporary facilities and restore area after completion of the Work,to a 2 condition equal to or better than prior to start of Work. 3 3.12 PROTECTION [NOT USED] 4 3.13 MAINTENANCE [NOT USED] 5 3.14 ATTACHMENTS [NOT USED] 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 8 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 015526-1 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 -. 1 SECTION 0155 26 2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Administrative procedures for: 7 a. Street Use Permit 8 b. Modification of approved traffic control 9 c. Removal of Street Signs 10 B. Deviations from this City of Fort Worth Standard Specification 11 1. 1.2 PRICE AND PAYMENT PROCEDURES— 12 Given the nature of this contract Street Use Permits will be paid for at the pre- 13 bid price of$100.00 each on an as needed basis.Additionally,Traffic Control 14 Plans will be categorized as Residential,Arterial/Industrial and Major 15 Arterial/Industrial due to the varying degrees of Traffic Control required in 16 these different road types. 17 C. Related Specification Sections include,but are not necessarily limited to: 18 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 19 2. Division 1—General Requirements 20 3. Section 34 71 13—Traffic Control 21 1.2 PRICE AND PAYMENT PROCEDURES 22 A. Measurement and Payment 23 1. Work associated with this Item is considered subsidiary to the various Items bid. 24 No separate payment will be allowed for this Item. 25 1.3 REFERENCES 26 A. Reference Standards 27 1. Reference standards cited in this specification refer to the current reference standard 28 published at the time of the latest revision date logged at the end of this 29 specification, unless a date is specifically cited. 30 2. Texas Manual on Uniform Traffic Control Devices(TMUTCD). 31 1.4 ADMINISTRATIVE REQUIREMENTS 32 A. Traffic Control 33 1. General 34 a. When traffic control plans are included in the Drawings,provide Traffic 35 Control in accordance with Drawings and Section 34 71 13. 36 b. When traffic control plans are not included in the Drawings,prepare traffic 37 control plans in accordance with Section 34 71 13 and submit to City for 38 review. 39 1) Allow minimum 10 working days for review of proposed Traffic Control. CITY OF FORT WORTH 2017 WATER LEAD SERVICES �. STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 015526-2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 �. 1 B. Street Use Permit 2 1. Prior to installation of Traffic Control,a City Street Use Permit is required. 3 a. To obtain.Street Use Permit,submit Traffic Control Plans to City 4 Transportation and Public Works Department. 5 1) Allow a minimum of 5 working days for permit review. 6 2) Contractor's responsibility to coordinate review of Traffic Control plans for 7 Street Use Permit, such that construction is not delayed. 8 C. Modification to Approved Traffic Control 9 1. Prior to installation traffic control: 10 a. Submit revised traffic control plans to City Department Transportation and 11 Public Works Department. 12 1) Revise Traffic Control plans in accordance with Section 34 71 13. 13 2) Allow minimum 5 working days for review of revised Traffic Control. 14 3) It is the Contractor's responsibility to coordinate review of Traffic Control 15 plans for Street Use Permit,such that construction is not delayed. 16 D. Removal of Street Sign 17 1. If it is determined that a street sign must be removed for construction,then contact 18 City Transportation and Public Works Department, Signs and Markings Division to 19 remove the sign. 20 E. Temporary Signage 21 1. In the case of regulatory signs,replace permanent sign with temporary sign meeting 22 requirements of the latest edition of the Texas Manual on Uniform Traffic Control 23 Devices(MUTCD). 24 2. Install temporary sign before the removal of permanent sign. 25 3. When construction is complete,to the extent that the permanent sign can be 26 reinstalled,contact the City Transportation.and Public Works Department, Signs 27 and Markings Division,to reinstall the permanent sign. 28 F. Traffic Control Standards 29 1. Traffic Control Standards can be found on the City's Buzzsaw website. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT i Revised July 1,2011 City Project No.100889 015526-3 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 7 1,11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION[NOT USED] 11 END OF SECTION 12 Revision hog DATE NAME SUMMARY OF CHANGE 13 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 015713-1 STORM WATER POLLUTION PREVENTION Page 1 of 3 1 SECTION 015713 2 STORM WATER POLLUTION PREVENTION 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Procedures for Storm Water Pollution Prevention Plans 7 B. Deviations from this City of Fort Worth Standard.Specification 8 1. None. 9 C. .Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0— Bidding Requirements,Contract Forms and Conditions of the 11 Contract 12 2. Division l—General Requirements 13 3. Section 3125 00—Erosion and Sediment Control 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Construction Activities resulting in less than 1 acre of disturbance 17 a. Work associated with this Item is considered subsidiary to the various Items 18 bid. No separate payment will be allowed for this Item. 19 2. Construction Activities resulting in greater than 1 acre of disturbance 20 a. Measurement and Payment shall be in accordance with Section 3125 00. 21 1.3 REFERENCES 22 A. Abbreviations and Acronyms 23 1. Notice of Intent:NOI 24 2. Notice of Termination:NOT 25 3. Storm Water Pollution Prevention Plan: SWPPP 26 4. Texas Commission on Environmental Quality:TCEQ 27 5. Notice of Change:NOC 28 A. Reference Standards 29 1. Reference standards cited in this Specification refer to the current reference 30 standard published at the time of the latest revision date logged at the end of this 31 Specification,unless a date is specifically cited. 32 2. Integrated Storm Management(iSWM)Technical Manual for Construction 33 Controls 34 1.4 ADMINISTRATIVE REQUIREMENTS 35 A. General 36 1. Contractor is responsible for resolution and payment of any fines issued associated 37 with compliance to Stormwater Pollution Prevention Plan. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100989 015713-2 STORM WATER POLLUTION PREVENTION Page 2 of 3 �- 1 B. Construction Activities resulting in: 2 1. Less than 1 acre of disturbance - 3 a. Provide erosion and sediment control in accordance with Section 3125 00 and 4 Drawings. 5 2. 1 to less than 5 acres of disturbance 6 a. Texas Pollutant Discharge Elimination System(TPDES)General Construction 7 Permit is required 8 b. Complete SWPPP in accordance with TCEQ requirements 9 1) TCEQ Small Construction Site Notice Required under general permit 10 TXR150000 I l a) Sign and post at job site 12 b) Prior to Preconstruction Meeting,send 1 copy to City Department of 13 Transportation and Public Works, Environmental Division, (817)392- 14 6088. 15 2) Provide erosion and sediment control in accordance with: 16 a) Section 3125 00 17 b) The Drawings 18 c) TXR150000 General Permit .. 19 d) SWPPP 20 e) TCEQ requirements 21 3. 5 acres or more of Disturbance 22 a. Texas Pollutant Discharge Elimination System(TPDES)General Construction 23 Permit is required 24 b. Complete SWPPP in accordance with TCEQ requirements 25 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee 26 a) Sign and post at job site 27 b) Send copy to City Department of Transportation and Public Works, 28 Environmental Division,(817)392-6088. 29 2) TCEQ Notice of Change required if making changes or updates to NOI 30 3) Provide erosion and sediment control in accordance with: 31 a) Section 3125 00 32 b) The Drawings 33 c) TXR150000 General.Permit 34 d) SWPPP — 35 e) TCEQ requirements 36 4) Once the project has been completed and all the closeout requirements of 37 TCEQ have been met a TCEQ Notice of Termination can be submitted. �.. 38 a) Send copy to City Department of Transportation and Public Works, 39 Environmental Division,(817)392-6088. 40 1.5 SUBMITTALS "- 41 A. SWPPP 42 1. Submit in accordance with Section 0133 00,except as stated herein. 43 a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City 44 as follows: 45 1) 1 copy to the City Project Manager 46 a) City Project Manager will forward to the City Department of 47 Transportation and Public Works,Environmental Division for review CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 �- 015713-3 STORM WATER POLLUTION PREVENTION Page 3 of 3 1 B. Modified SWPPP 2 1. If the SWPPP is revised during.construction,resubmit modified SWPPP to the City 3 in accordance with Section 013 3 00. 4 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 5 1.7 CLOSEOUT SUBMITTALS [NOT USED] 6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 7 1.9 QUALITY ASSURANCE [NOT USED] 8 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 9 1.11 FIELD [SITE] CONDITIONS [NOT USED] 10 1.12 WARRANTY [NOT USED] 11 PART 2- PRODUCTS [NOT USED] 12 PART 3- EXECUTION [NOT USED] 13 END OF SECTION 14 Revision Log DATE NAME SUMMARY OF CHANGE 15 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 015813-1 TEMPORARY PROJECT SIGNAGE Page 1 of 3 1 SECTION 015813 2 TEMPORARY PROJECT SIGNAGE 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Temporary Project Signage Requirements 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. �. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 18 1.5 SUBMITTALS [NOT USED] 19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 20 1.7 CLOSEOUT SUBMITTALS [NOT USED] 21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 22 1.9 QUALITY ASSURANCE [NOT USED] 23 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] -' 24 1.11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2- PRODUCTS 27 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 28 2.2 EQUIPMENT,PRODUCT TYPES,AND MATERIALS 29 A. Design Criteria 30 l.. Provide free standing Project Designation Sign in accordance with City's Standard 31 Details for project signs. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No. 100889 015813-2 TEMPORARY PROJECT SIGNAGE Page 2 of 3 1 B. Materials 2 1. Sign 3 a. Constructed of Y4-inch fir plywood,grade A-C(exterior)or better 4 2.3 ACCESSORIES [NOT USED] 5 2.4 SOURCE QUALITY CONTROL [NOT USED] 6 PART 3- EXECUTION 7 3.1 INSTALLERS [NOT USED] 8 3.2 EXAMINATION [NOT USED] 9 3.3 PREPARATION [NOT USED] 10 3.4 INSTALLATION 11 A. General 12 1. Provide vertical installation at extents of project. 13 2. Relocate sign as needed,upon request of the City. 14 B. Mounting options 15 a. Skids 16 b. Posts 17 c. Barricade 18 3.5 REPAIR/RESTORATION [NOT USED] 19 3.6 RE-INSTALLATION[NOT USED] 20 3.7 FIELD [ozz] SITE QUALITY CONTROL [NOT USED] 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING [NOT USED] 24 3.11 CLOSEOUT ACTIVITIES [NOT USED] 25 3.12 PROTECTION [NOT USED] 26 3.13 MAINTENANCE 27 A. General 28 1. Maintenance will include painting and repairs as needed or directed by the City. 29 3.14 ATTACHMENTS [NOT USED] 30 END OF SECTION 31 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1.201 l City Project No.100889 015813-3 TEMPORARY PROJECT SIGNAGE Page 3 of 3 Revision Log DATE NAME SUMMARY OF CHANGE 2 Q CITY OF FORT WORTH 2017 WATER LEAD SERVICES r,er STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 016000-1 PRODUCT REQUIREMENTS Page I of 2 1 SECTION 0160 00 2 PRODUCT REQUIREMENTS 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. References for Product Requirements and City Standard Products List 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division. 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 13 1.3 REFERENCES [NOT USED] 14 1.4 ADMINISTRATIVE REQUIREMENTS 1.5 A. A list of City approved products for use is located on Buzzsaw as follows: 16 1. Resources\02-Construction Documents\Standard Products List 17 B. Only products specifically included on City's Standard Product List in these Contract 18 Documents shall be allowed for use on the Project. 19 1. Any subsequently approved products will only be allowed for use upon specific 20 approval by the City. 21 C. Any specific product requirements in the Contract Documents supersede similar 22 products included on the City's Standard Product List. 23 1. The City reserves the right to not allow products to be used for certain projects even 24 though the product is listed on the City's Standard Product List. 25 D. Although a specific product is included on City's Standard Product List,not all 26 products from that manufacturer are approved for use,including but not limited to,that 27 manufacturer's standard product. 28 E. See Section 0133 00 for submittal requirements of Product Data included on City's 29 Standard Product List. 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 32 1.7 CLOSEOUT SUBMITTALS [NOT USED] 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 34 1.9 QUALITY ASSURANCE [NOT USED] CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 016000-2 PRODUCT REQUIREMENTS Page 2 of 2 1 1.10 DELIVERY,STORAGE,AND HANDLING[NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2- PRODUCTS [NOT USED] 5 PART 3- EXECUTION[NOT USED] 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 10/12/12 D.Johnson Modified Location of City's Standard Product List 8 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 "' 016600-1 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 1 of 4 1 SECTION 0166 00 2 PRODUCT STORAGE AND HANDLING REQUIREMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Scheduling of product delivery 7 2. Packaging of products for delivery 8 3. Protection of products against damage from: 9 a. Handling 10 b. Exposure to elements or harsh environments 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. None. 13 C. Related Specification Sections include,but are not necessarily limited to: 14 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 15 2. Division 1 —General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 22 1.5 SUBMITTALS [NOT USED] 23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 24 1.7 CLOSEOUT SUBMITTALS [NOT USED] 25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 26 1.9 QUALITY ASSURANCE [NOT USED] 27 1.10 DELIVERY AND HANDLING 28 A. Delivery Requirements 29 1. Schedule delivery of products or equipment as required to allow timely installation •— 30 and to avoid prolonged storage. 31 2. Provide appropriate personnel and equipment to receive deliveries. 32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site 33 for personnel or equipment to receive the delivery. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 016600-2 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 1 4. Deliver products or equipment in manufacturer's original unbroken cartons or other 2 containers designed and constructed to protect the contents from physical or , 3 environmental damage. 4 5. Clearly and fully mark and identify as to manufacturer,item and installation 5 location. 6 6. Provide manufacturer's instructions for storage and handling. 7 B. Handling Requirements 8 1. Handle products or equipment in accordance with these Contract Documents and 9 manufacturer's recommendations and instructions. 10 C. Storage Requirements 11 1. Store materials in accordance with manufacturer's recommendations and 12 requirements of these Specifications. 13 2. Make necessary provisions for safe storage of materials and equipment. -- 14 a. Place loose soil materials and materials to be incorporated into Work to prevent 15 damage to any part of Work or existing facilities and to maintain free access at 16 all times to all parts of Work and to utility service company installations in 17 vicinity of Work. 1.8 3. Keep materials and equipment neatly and compactly stored in locations that will 19 cause minimum inconvenience to other contractors,public travel,adjoining owners, 20 tenants and occupants. 21 a. Arrange storage to provide easy access for inspection. 22 4. Restrict storage to areas available on construction site for storage of material and _. 23 equipment as shown on Drawings, or approved by City's Project Representative. 24 5. Provide off-site storage and protection when on-site storage is not adequate. 25 a. Provide addresses of and access to off-site storage locations for inspection by 26 City's Project Representative. 27 6. Do not use lawns,grass plots or other private property for storage purposes without 28 written permission of owner or other person in possession or control of premises. — 29 7. Store in manufacturers' unopened containers. 30 8. Neatly, safely and compactly stack materials delivered and stored along line of 31 Work to avoid inconvenience and damage to property owners and general public 32 and maintain at least 3 feet from fire hydrant. 33 9. Keep public and private driveways and street crossings open. 34 10. Repair or replace damaged lawns,sidewalks, streets or other improvements to 35 satisfaction of City's Project Representative. 36 a. Total length which materials may be distributed along route of construction at 37 one time is 1,000 linear feet, unless otherwise approved in writing by City's 38 Project Representative. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 �° 016600-3 PRODUCT STORAGE AND HANDLING REQUIREMENTS ' Page 3 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION[NOT USED] 8 3.4 ERECTION [NOT USED] 9 3.5 REPAIR/RESTORATION [NOT USED] 10 3.6 RE-INSTALLATION [NOT USED] 11 3.7 FIELD [OR] SITE QUALITY CONTROL 12 A. Tests and Inspections 13 1. Inspect all products or equipment delivered to the site prior to unloading. 14 B. Non-Conforming Work 15 1. Reject all products or equipment that are damaged, used or in any other way 16 unsatisfactory for use on the project. 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES [NOT USED] 21 3.12 PROTECTION 22 A. Protect all products or equipment in accordance withmanufacturer's written directions. 23 B. Store products or equipment in location to avoid physical damage to items while in 24 storage. 25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by 26 the manufacturer. 27 3.13 MAINTENANCE [NOT USED] 28 3.14 ATTACHMENTS [NOT USED] 29 END OF SECTION 30 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT "" Revised July 1,2011 City Project No. 100889 016600-4 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 i Revision Log DATE NAME SUMMARY OF CHANGE 1 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 '� 017000-1 MOBILIZATION AND REMOBILIZATION Page 1 of 4 1 SECTION 0170 00 2 MOBILIZATION AND REMOBILIZATION 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Mobilization and Demobilization r. 7 a. Mobilization 8 1) Transportation of Contractor's personnel,equipment, and operating supplies 9 to the Site 10 2) Establishment of necessary general facilities for the Contractor's operation I 1 at the Site 12 3).Premiums paid for performance and payment bonds 13 4) Transportation of Contractor's personnel,equipment,and operating supplies 14 to another location within the designated Site 15 5) Relocation of necessary general facilities for the Contractor's operation 16 from 1 location to another location on the Site. 17 b. Demobilization 18 1) Transportation of Contractor's personnel,equipment,and operating supplies 19 away from the Site including disassembly 20 2) Site Clean-up 21 3) Removal of all buildings and/or other facilities assembled at the Site for this 22 Contract 23 c. Mobilization and Demobilization do not include activities for specific items of 24 work that are for which payment is provided elsewhere in the contract. 25 2. Remobilization 26 a. Remobilization for Suspension of Work specifically required in the Contract 27 Documents or as required by City includes: 28 1) Demobilization 29 a) Transportation of Contractor's personnel,equipment, and operating 30 supplies from the Site including disassembly or temporarily securing 31 equipment, supplies,and other facilities as designated by the Contract 32 Documents necessary to suspend the Work. 33 b) Site Clean-up as designated in the Contract Documents 34 2) Remobilization 35 a) Transportation of Contractor's personnel,equipment,and operating 36 supplies to the Site necessary to resume the Work. 37 b) Establishment of necessary general facilities for the Contractor's 38 operation at the Site necessary to resume the Work. 39 3) No Payments will be made for: 40 a) Mobilization and Demobilization from one location to another on the 41 Site in the normal progress of performing the Work. 42 b) Stand-by or idle time 43 c) Lost profits 44 3. Mobilizations and Demobilization for Miscellaneous Projects ,.� 45 a. Mobilization and Demobilization CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 017000-2 MOBILIZATION AND REMOBILIZATION Page 2 of 4 1 1) Mobilization shall consist of the activities and cost on a Work Order basis 2 necessary for: 3 a) Transportation of Contractor's personnel,equipment,and operating 4 supplies to the Site for the issued Work Order. 5 b) Establishment of necessary general facilities for the Contractor's 6 operation at the Site for the issued Work Order 7 2) Demobilization shall consist of the activities and cost necessary for: 8 a) Transportation of Contractor's personnel,equipment,and operating 9 supplies from the Site including disassembly for each issued Work 10 Order 11 b) Site Clean-up for each issued Work Order 12 c) Removal of all buildings or other facilities assembled at the Site for -� 13 each Work Oder 14 b. Mobilization and Demobilization do not include activities for specific items of 15 work for which payment is provided elsewhere in the contract. 16 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects 17 a. A Mobilization for Miscellaneous Projects when directed by the City and the 18 mobilization occurs within 24 hours of the issuance of the Work Order. ..., 19 B. Deviations from this City of Fort Worth Standard Specification 20 1. 1.2-A-4 Mobilization and Demobilization for Miscellaneous Proiects— 21 1.2-A-5 Emergency Mobilization and Demobilization for Miscellaneous 22 Proiects—Although this contract is considered a miscellaneous type contract, 23 all mobilizations and demobilizations will be considered subsidiary to the work 24 to be performed. 25 C. Related Specification Sections include, but are not necessarily limited to: 26 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 27 2. Division 1—General Requirements 28 1.2 PRICE AND PAYMENT PROCEDURES 29 A. Measurement and Payment 30 1. Mobilization and Demobilization 31 a. Measure 32 1) This Item is considered subsidiary to the various Items bid. 33 b. Payment 34 1) The work performed and materials furnished in accordance with this Item 35 are subsidiary to the various Items bid and no other compensation will be 36 allowed. 37 2. Remobilization for suspension of Work as specifically required in the Contract 38 Documents 39 a. Measurement 40 1.) Measurement for this Item shall be per each remobilization performed. 41 b. Payment 42 1) The work performed and materials furnished in accordance with this Item 43 and measured as provided under"Measurement"will be paid for at the unit _ 44 price per each"Specified Remobilization"in accordance with Contract 45 Documents. 46 c. The price shall include: CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 017000-3 MOBILIZATION AND REMOBILIZATION Page 3 of 4 1 1) Demobilization as described in Section 1.1.A.2.a.1) 2 2) Remobilization as described in Section. 1.I.A.2.a.2) 3 d. No payments will be made for standby,idle time, or lost profits associated this 4 Item. 5 3. Remobilization for suspension of Work as required by City 6 a. Measurement and Payment 7 1) This shall be submitted as a Contract Claim in accordance with Article 10 8 of Section 00 72 00. 9 2) No payments will be made for standby, idle time, or lost profits associated 10 with this Item. 11 4. Mobilizations and Demobilizations for Miscellaneous Projects 12 a. Measurement 13 1) Measurement for this Item shall be for each Mobilization and 14 Demobilization required by the Contract Documents 1.5 b. Payment 16 1) The Work performed and materials furnished in accordance with this Item 17 and measured as provided under"Measurement"will be paid for at the unit 18 price per each"Work Order Mobilization"in accordance with Contract 19 Documents. Demobilization shall be considered subsidiary to mobilization 20 and shall not be paid for separately. 21 c. The price shall include: 22 1) Mobilization as described in Section 1.1.A.3.a.1) 23 2) Demobilization as described in Section 1.1.A.3.a.2) 24 d. No payments will be made for standby, idle time, or lost profits associated this 25 Item. 26 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects 27 a. Measurement 28 1) Measurement for this Item shall be for each Mobilization and 29 Demobilization required by the Contract Documents 30 b. Payment 31 1) The Work performed and materials furnished in accordance with this Item 32 and measured as provided under"Measurement"will be paid for at the unit 33 price per each"Work Order Emergency Mobilization"in accordance with 34 Contract Documents. Demobilization shall be considered subsidiary to 35 mobilization and shall not be paid for separately. 36 c. The price shall include 37 1) Mobilization as described in Section LLAA.a) 38 2) Demobilization as described in Section 1.LA.3.a.2) 39 d. No payments will be made for standby, idle time,or lost profits associated this 40 Item. 41 1.3 REFERENCES [NOT USED] 42 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 43 1.5 SUBMITTALS [NOT USED] 44 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 45 1.7 CLOSEOUT SUBMITTALS [NOT USED] CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 017000-4 MOBILIZATION AND REMOBILIZATION Page 4 of 4 1 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 2 1.9 QUALITY ASSURANCE [NOT USED] 3 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 4 1.11 FIELD [SITE] CONDITIONS [NOT USED] 5 1.12 WARRANTY [NOT USED] 6 PART 2- PRODUCTS [NOT USED] 7 PART 3- EXECUTION [NOT USED] 8 END OF SECTION 9 Revision Log DATE NAME SUMMARY OF CHANGE 10 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,201.2 CityProject No.100889 ^ 017123-1 CONSTRUCTION STAKING AND SURVEY Page 1 of 4 1 SECTION 017123 2 CONSTRUCTION STAKING AND SURVEY 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Requirements for construction staking and construction survey - 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1—General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. .Measurement and Payment 14 1. Construction Staking 15 a. Measurement 16 1) This Item is considered subsidiary to the various Items bid. 17 b. Payment 18 1) The work performed and the materials furnished in accordance with this 19 Item are subsidiary to the various Items bid and no other compensation will 20 be allowed. 21 2. Construction Survey 22 a. Measurement 23 1) This Item is considered subsidiary to the various Items bid. 24 b. Payment 25 1) The work performed and the materials furnished in accordance with this 26 Item are subsidiary to the various Items bid and no other compensation will 27 be allowed. 28 1.3 REFERENCES [NOT USED] 29 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 30 1.5 SUBMITTALS 31 A. Submittals, if required,shall be in accordance with Section 0133 00. 32 B. All submittals shall be approved by the City prior to delivery. 33 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 34 A. Certificates 35 1. Provide certificate certifying that elevations and locations of improvements are in 36 conformance or non-conformance with requirements of the Contract Documents. 37 a. Certificate must be sealed by a registered professional land surveyor in the 38 State of Texas. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 017123-2 CONSTRUCTION STAKING AND SURVEY Page 2 of 4 *� 1 B. Field Quality Control Submittals 2 1. Documentation verifying accuracy of field engineering work. 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE 6 A. Construction Staking 7 1. Construction staking will be performed by the City. 8 2. Coordination 9 a. Contact City's Project Representative at least 2 weeks in advance for 10 scheduling of Construction Staking. 11 b. It is the Contractor's responsibility to coordinate staking such that construction 12 activities are not delayed or negatively impacted. 13 3. General 14 a. Contractor is responsible for preserving and maintaining stakes furnished by 15 City. 16 b. If in the opinion of the City,a sufficient number of stakes or markings have 17 been lost, destroyed or disturbed,by Contractor's neglect,such that the 18 contracted Work cannot take place,then the Contractor will be required to pay .. 19 the City for new staking with a 25 percent markup. The cost for staking will be 20 deducted from the payment due to the Contractor for the Project. 21 B. Construction Survey �- 22 1. Construction Survey will be performed by the City. 23 2. Coordination 24 a. Contractor to verify that control data established in the design survey remains 25 intact. 26 b. Coordinate with the City prior to field investigation to determine which 27 horizontal and vertical control data will be required for construction survey. 28 c. It is the Contractor's responsibility to coordinate Construction Survey such that 29 construction activities are not delayed or negatively impacted. 30 d. Notify City if any control data needs to be restored or replaced due to damage 31 caused during construction operations. 32 1) City shall perform replacements and/or restorations. 33 3. General — 34 a. Construction survey will be performed in order to maintain complete and 35 accurate logs of control and survey work as it progresses for Project Records. 36 b. The Contractor will need to ensure coordination is maintained with the City to 37 perform construction survey to obtain construction features, including but not 38 limited to the following: 39 1) All Utility Lines — 40 a) Rim and flowline elevations and coordinates for each manhole or 41 junction structure 42 2) Water Lines 43 a) Top of pipe elevations and coordinates for waterlines at the following 44 locations: 45 (1) Every 250 linear feet CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 °" 017123-3 CONSTRUCTION STAKING AND SURVEY .� Page 3 of 4 1 (2) Horizontal and vertical points of inflection,curvature,etc.(All 2 Fittings) 3 (3) Cathodic protection test stations 4 (4) Sampling stations 5 (5) Meter boxes/vaults(All sizes) 6 (6) Fire lines 7 (7) Fire hydrants 8 (8) Gate valves 9 (9) Plugs,stubouts, dead-end lines 10 (10) Air Release valves(Manhole rim and vent pipe) 11 (11) Blow off valves(Manhole rim and valve lid) AN 12 (12) Pressure plane valves 13 (13) Cleaning wyes 14 (14) Casing pipe(each end) 15 b) Storm Sewer 16 (1) Top of pipe elevations and coordinates at the following locations: 17 (a) Every 256 linear feet 18 (b) Horizontal and vertical points of inflection,curvature,etc. 19 c) Sanitary Sewer 20 (1) Top of pipe elevations and coordinates for sanitary sewer lines at 21 the following locations: 22 (a) Every 250 linear feet 23 (b) Horizontal and vertical points of inflection,curvature,etc. 24 (c) Cleanouts �- 25 c. Construction survey will be performed in order to maintain complete and 26 accurate logs of control and survey work associated with meeting or exceeding 27 the line and grade required by these Specifications. 28 d. The Contractor will need to ensure coordination is maintained with the City to 29 perform construction survey and to verify control data,including but not 30 limited to the following: 31 1) Established benchmarks and control points provided for the Contractor's 32 use are accurate 33 2) Benchmarks were used to furnish and maintain all reference lines and 34 grades for tunneling 35 3) Lines and grades were used to establish the location of the pipe 36 4) Submit to the City copies of field notes used to establish all lines and 37 grades and allow the City to check guidance system setup prior to 38 beginning each tunneling drive. 39 5) Provide access for the City to verify the guidance system and the line and 40 grade of the carrier pipe on a daily basis. 41 6) The Contractor remains fully responsible for the accuracy of the work and 42 the correction of it,as required. 43 7) Monitor line and grade continuously during construction. 44 8) Record deviation with respect to design line and grade once at each pipe 45 joint and submit daily records to City. 46 9) If the installation does not meet the specified tolerances, immediately notify 47 the City and correct the installation in accordance with the Contract .. 48 Documents. 49 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 CityProject No.100889 017123-4 CONSTRUCTION STAKING AND SURVEY Page 4 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3 - EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 APPLICATION 9 3.5 REPAIR/RESTORATION[NOT USED] 10 3.6 RE-INSTALLATION[NOT USED] '^ 11 3.7 FIELD [oR] SITE QUALITY CONTROL 12 A. It is the Contractor's responsibility to maintain all stakes and control data placed by the 13 City in accordance with this Specification. 14 B. Do not change or relocate stakes or control data without approval from the City. 15 3.8 SYSTEM STARTUP [NOT USED] 16 3.9 ADJUSTING [NOT USED] 17 3.10 CLEANING [NOT USED] 18 3.11 CLOSEOUT ACTIVITIES [NOT USED] ... 19 3.12 PROTECTION [NOT USED] 20 3.13 MAINTENANCE [NOT USED] 21 3.14 ATTACHMENTS [NOT USED] 22 END OF SECTION 23 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D.Johnson 24 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 017423-1 CLEANING Page I of 4 1 SECTION 0174 23 2 CLEANING 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Intermediate and final cleaning for Work not including special cleaning of closed 7 systems specified elsewhere 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include,but are not necessarily limited to: 11 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 12 2. Division 1 —General Requirements 13 3. Section 32 92 13—Hydro-Mulching, Seeding and Sodding 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and.Payment 16 1. Work associated with this Item is considered subsidiary to the various Items bid. 17 No separate payment will be allowed for this Item. 18 1.3 REFERENCES [NOT USED] 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Scheduling -"' 21 1. Schedule cleaning operations so that dust and other contaminants disturbed by 22 cleaning process will not fall on newly painted surfaces. 23 2. Schedule final cleaning upon completion of Work and immediately prior to final 24 inspection. 25 1.5 SUBMITTALS [NOT USED] 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE [NOT USED] 30 1.10 STORAGE,AND HANDLING 31 A. Storage and Handling Requirements 32 1. Store cleaning products and cleaning wastes in containers specifically designed for 33 those materials. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 017423-2 CLEANING Page 2 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS — 4 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 5 2.2 MATERIALS 6 A. Cleaning Agents 7 1. Compatible with surface being cleaned 8 2. New and uncontaminated 9 3. For manufactured surfaces 10 a. Material recommended by manufacturer 11 2.3 ACCESSORIES [NOT USED] 12 2.4 SOURCE QUALITY CONTROL[NOT USED] 13 PART 3- EXECUTION 14 3.1 INSTALLERS [NOT USED] 15 3.2 EXANIINATION [NOT USED] 16 3.3 PREPARATION [NOT USED] 17 3.4 APPLICATION [NOT USED] 18 3.5 REPAIR/RESTORATION [NOT USED] 19 3.6 RE-INSTALLATION [NOT USED] 20 3.7 FIELD [OR] SITE QUALITY CONTROL[NOT USED] 21 3.8 SYSTEM STARTUP[NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING 24 A. General �. 25 1. Prevent accumulation of wastes that create hazardous conditions. 26 2. Conduct cleaning and disposal operations to comply with laws and safety orders of 27 governing authorities. 28 3. Do not dispose of volatile wastes such as mineral spirits,oil or paint thinner in 29 storm or sanitary drains or sewers. 30 4. Dispose of degradable debris at an approved solid waste disposal site. - 31 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an 32 alternate manner approved by City and regulatory agencies. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 017423-3 CLEANING Page 3 of 4 1 6. Handle materials in a controlled manner with as few handlings as possible. -� 2 7. Thoroughly clean,sweep,wash and polish all Work and equipment associated with 3 this project. 4 8. Remove all signs of temporary construction and activities incidental to construction 5 of required permanent Work. 6 9. If project is not cleaned to the satisfaction of the City,the City reserves the right to 7 have the cleaning completed at the expense of the Contractor. 8 10. Do not burn on-site. 9 B. Intermediate Cleaning during Construction 10 1. Keep Work areas clean so as not to hinder health,safety or convenience of 11 personnel in existing facility operations. 12 2. At maximum weekly intervals, dispose of waste materials,debris and rubbish. 13 3. Confine construction debris daily in strategically located container(s): 14 a. Cover to prevent blowing by wind 15 b. Store debris away from construction or operational activities 16 c. Haul from site at a minimum of once per week 17 4. Vacuum clean interior areas when ready to receive finish painting. 18 a. Continue vacuum cleaning on an as-needed basis,until Final Acceptance. 19 5. Prior to storm events,thoroughly clean site of all loose or unsecured items,which 20 may become airborne or transported by flowing water during the storm. 21 C. Interior Final Cleaning 22 1, Remove grease,mastic,adhesives,dust,dirt,stains,fingerprints,labels and other 23 foreign materials from sight-exposed surfaces. 24 2. Wipe all lighting fixture reflectors,lenses, lamps and trims clean. 25 3. Wash and shine glazing and mirrors. 26 4. Polish glossy surfaces to a clear shine. 27 5. Ventilating systems 28 a. Clean permanent filters and replace disposable filters if units were operated 29 during construction. -- 30 b. Clean ducts,blowers and coils if units were operated without filters during 31 construction. 32 6. Replace all burned out lamps. 33 7. Broom clean process area floors. 34 8. Mop office and control room floors. 35 D. Exterior(Site or Right of Way)Final Cleaning 36 1. Remove trash and debris containers from site. 37 a. Re-seed areas disturbed by location of trash and debris containers in accordance 38 with Section 32 92 13. 39 2. Sweep roadway to remove all rocks,pieces of asphalt,concrete or any other object 40 that may hinder or disrupt the flow of traffic along the roadway. 41 3. Clean any interior areas including,but not limited to,vaults,manholes,structures, 42 junction boxes and inlets. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 017423-4 CLEANING Page 4 of 4 1 4. If no longer required for maintenance of erosion facilities,and upon approval by 2 City,remove erosion control from site. 3 5. Clean signs,lights,signals,etc. 4 3.11 CLOSEOUT ACTIVITIES [NOT USED] 5 3.12 PROTECTION [NOT USED] 6 3.13 MAINTENANCE [NOT USED] 7 3.14 ATTACHMENTS [NOT USED] 8 END OF SECTION 9 Revision Log DATE NAME SUMMARY OF CHANGE 10 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1.201 t City Project No.I00889 01 7719-1 CLOSEOUT REQUIREMENTS Page I of 3 1 SECTION 0177 19 2 CLOSEOUT REQUIREMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedure for closing out a contract 7 B. Deviations from.this City of Fort Worth Standard.Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1—General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Guarantees,Bonds and Affidavits 19 1. No application for final payment will be accepted until all guarantees, bonds, 20 certificates,licenses and affidavits required for Work or equipment as specified are 21 satisfactorily filed with the City. 22 B. Release of Liens or Claims 23 1. No application for final payment will be accepted until satisfactory evidence of 24 release of liens has been submitted to the City. 25 1.5 SUBMITTALS 26 A. Submit all required documentation to City's Project Representative. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No. 100889 017719-2 CLOSEOUT REQUIREMENTS Page 2 of 3 1 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 PART 2- PRODUCTS [NOT USED] �. 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION[NOT USED] 8 3.4 CLOSEOUT PROCEDURE 9 A. Prior to requesting Final.Inspection, submit: 10 1. Project Record Documents in accordance with Section 0178 39 11 2. Operation and Maintenance Data, if required, in accordance with Section 0178 23 12 B. Prior to requesting Final Inspection,perform final cleaning in accordance with Section �. 13 01 7423. 14 C. Final Inspection 15 1. After final cleaning, provide notice to the City Project Representative that the Work 1.6 is completed. 17 a. The City will make an initial Final Inspection with the Contractor present. 18 b. Upon completion of this inspection,the City will notify the Contractor,in 19 writing within 10 business days, of any particulars in which this inspection 20 reveals that the Work is defective or incomplete. 21 2. Upon receiving written notice from the City, immediately undertake the Work 22 required to remedy deficiencies and complete the Work to the satisfaction of the 23 City. 24 3. Upon completion of Work associated with the items listed in the City's written 25 notice,inform the City,that the required Work has been completed. Upon receipt 26 of this notice,the City, in the presence of the Contractor,will make a subsequent 27 Final Inspection of the project. _ 28 4. Provide all special accessories required to place each item of equipment in full 29 operation. These special accessory items include,but are not limited to: 30 a. Specified spare parts 31 b. Adequate oil and grease as required for the first lubrication of the equipment 32 c. Initial fill up of all chemical tanks and fuel tanks 33 d. Light bulbs _ 34 e. Fuses 35 f. Vault keys 36 g. Handwheels 37 h. Other expendable items as required for initial start-up and operation of all 38 equipment 39 D. Notice of Project Completion _y CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 017719-3 CLOSEOUT REQUIREMENTS Page 3 of 3 1 1. Once the City Project Representative finds the Work subsequent to Final Inspection 2 to be satisfactory,the City will issue a Notice of Project Completion(Green Sheet). 3 E. Supporting Documentation 4 1. Coordinate with the City Project Representative to complete the following 5 additional forms: 6 a. Final Payment Request 7 b. Statement of Contract Time 8 c. Affidavit of Payment and Release of Liens 9 d. Consent of Surety to Final Payment 10 e. Pipe Report(if required) 11 £ Contractor's Evaluation of City 12 g. Performance Evaluation of Contractor 13 F. Letter of Final Acceptance 14 1. Upon review and acceptance of Notice of Project Completion and Supporting 15 Documentation,in accordance with General Conditions,City will issue Letter of W 16 Final Acceptance and release the Final Payment Request for payment. 17 3.5 REPAIR I RESTORATION [NOT USED] 18 3.6 RE-INSTALLATION [NOT USED] 19 3.7 FIELD [ox] SITE QUALITY CONTROL [NOT USED] 20 3.8 SYSTEM STARTUP [NOT USED] 21 3.9 ADJUSTING [NOT USED] 22 3.10 CLEANING [NOT USED] 23 3.11 CLOSEOUT ACTIVITIES [NOT USED] 24 3.12 PROTECTION[NOT USED] 25 3.13 MAINTENANCE [NOT USED] 26 3.14 ATTACHMENTS [NOT USED] 27 END OF SECTION 28 Revision Log DATE NAME SUMMARY OF CHANGE 29 CITY OF FORT WORTH 2017 WATER LEAD SERVICES *� STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1.,2011 City Project No.100889 01 7823-1 OPERATION AND MAINTENANCE DATA Page 1 of 5 1 SECTION 0178 23 2 OPERATION AND MAINTENANCE DATA 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Product data and related information appropriate for City's maintenance and 7 operation.of products furnished under Contract 8 2. Such products may include,but are not limited to: 9 a. Traffic Controllers 10 b. Irrigation Controllers(to be operated by the City) 11 c. Butterfly Valves 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include,but are not necessarily limited to: 15 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 16 2. Division 1 —General Requirements ,. 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Schedule 24 1. Submit manuals in final form to the City within 30 calendar days of product 25 shipment to the project site. 26 1.5 SUBMITTALS 27 A. Submittals shall be in accordance with Section 0133 00 . All submittals shall be 28 approved by the City prior to delivery. 29 1.6 INFORMATIONAL SUBMITTALS 30 A. Submittal Form 31 1. Prepare data in form of an instructional manual for use by City personnel. 32 2. Format 33 a. Size: 8 '/2 inches x 11 inches 34 b. Paper 35 1) 40 pound minimum,white,for typed pages 36 2) Holes reinforced with plastic,cloth or metal —• 37 c. Text: Manufacturer's printed data,or neatly typewritten CITY OF FORT WORTH 2017 WATER LEAD SERVICES �- STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 017823-2 OPERATION AND MAINTENANCE DATA Page 2 of 5 1 d. Drawings 2 1) Provide reinforced punched binder tab,bind in with text 3 2) .Reduce larger drawings and fold to size of text pages. 4 e. Provide fly-leaf for each separate product,or each piece of operating 5 equipment. �. 6 1) Provide typed description of product,and major component parts of 7 equipment. 8 2) .Provide indexed tabs. 9 f. Cover 10 1) Identify each volume with typed or printed title"OPERATING AND 11 MAINTENANCE INSTRUCTIONS". 12 2) List: 13 a) Title of Project 14 b) Identity of separate structure as applicable 15 c) Identity of general subject matter covered in the manual 16 3. Binders 17 a. Commercial quality 3-ring binders with durable and cleanable plastic covers 18 b. When multiple binders are used,correlate the data into related consistent 19 groupings. 20 4. If available,provide an electronic form of the O&M Manual. 21 B. Manual Content 22 1. Neatly typewritten table of contents for each volume,arranged in systematic order 23 a. Contractor,name of responsible principal,address and telephone number = 24 b. A list of each product required to be included,indexed to content of the volume 25 c. List,with each product: 26 1) The name,address and telephone number of the subcontractor or installer _ 27 2) A list of each product required to be included,indexed to content of the 28 volume 29 3) Identify area of responsibility of each 30 4) Local source of supply for parts and replacement = 31 d. Identify each product by product name and other identifying symbols as set 32 forth in Contract Documents. 33 2. Product Data 34 a. Include only those sheets which are pertinent to the specific product. 35 b. Annotate each sheet to: 36 1) Clearly identify specific product or part installed = 37 2) Clearly identify data applicable to installation 38 3) Delete references to inapplicable information 39 3. Drawings 40 a. Supplement product data with drawings as necessary to clearly illustrate: 41 1) Relations of component parts of equipment and systems 42 2) Control and flow diagrams — 43 b. Coordinate drawings with information in Project Record Documents to assure 44 correct illustration of completed installation. 45 c. Do not use Project Record Drawings as maintenance drawings. 46 4. Written text,as required to supplement product data for the particular installation: 47 a. Organize in consistent format under separate headings for different procedures. 48 b. Provide logical sequence of instructions of each procedure. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No. 100889 017823-3 OPERATION AND MAINTENANCE DATA Page 3 of 5 1 5. Copy of each warranty,bond and service contract issued 2 a. Provide information sheet for City personnel giving: 3 1) Proper procedures in event of failure 4 2) Instances which might affect validity of warranties or bonds 5 C. Manual for Materials and Finishes 6 1. Submit 5 copies of complete manual in final form. 7 2. Content, for architectural products,applied materials and finishes: 8 a. Manufacturer's data,giving full information on products 9 1) Catalog number, size,composition 10 2) Color and texture designations 11 3) Information required for reordering special manufactured products 12 b. Instructions for care and maintenance 13 1) Manufacturer's recommendation for types of cleaning agents and methods 14 2) Cautions against cleaning agents and methods which are detrimental to 15 product 16 3) Recommended schedule for cleaning and maintenance 17 3. Content,for moisture protection and weather exposure products: 18 a. Manufacturer's data,giving full information on products 19 1) Applicable standards 20 2) Chemical composition 21 3) Details of installation 22 b. Instructions for inspection,maintenance and repair 23 D. Manual for Equipment and Systems 24 1. Submit 5 copies of complete manual in final form. 25 2. Content,for each unit of equipment and system,as appropriate: 26 a. Description of unit and component parts 27 1) .Function,normal operating characteristics and limiting conditions 28 2) Performance curves,engineering data and tests 29 3) Complete nomenclature and commercial number of replaceable parts 30 b. Operating procedures 31 1) Start-up,break-in,routine and normal operating instructions .- 32 2) Regulation,control,stopping, shut-down and emergency instructions 33 3) Summer and winter operating instructions 34 4) Special operating instructions 35 c. Maintenance procedures 36 1) Routine operations 37 2) Guide to"trouble shooting" 38 3) Disassembly,repair and reassembly 39 4) Alignment,adjusting and checking 40 d. Servicing and lubrication schedule 41 1) List of lubricants required 42 e. Manufacturer's printed operating and maintenance.instructions 43 f. Description of sequence of operation by control manufacturer 44 1) Predicted life of parts subject to wear 45 2) Items recommended to be stocked as spare parts 46 g. As installed control diagrams by controls manufacturer 47 h. Each contractor's coordination drawings 48 1) As installed color coded piping diagrams CITY OF FORT WORTH 2OI7 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 017823-4 OPERATION AND MAINTENANCE DATA Page 4 of 5 1 i, Charts of valve tag numbers, with location and function of each valve 2 j. List of original manufacturer's spare parts,manufacturer's current prices,and 3 recommended quantities to be maintained in storage 4 k. Other data as required under pertinent Sections of Specifications 5 3. Content,for each electric and electronic system,as appropriate: , 6 a. Description of system and component parts 7 1) Function,normal operating characteristics,and limiting conditions 8 2) Performance curves,engineering data and tests 9 3) Complete nomenclature and commercial number of replaceable parts 10 b. Circuit directories of panelboards 11 1) Electrical service 12 2) Controls 13 3) Communications 14 c. As installed color coded wiring diagrams 15 d. Operating procedures 16 1) Routine and normal operating instructions 17 2) Sequences required 18 3) Special operating instructions 19 e. Maintenance procedures 20 1) Routine operations 21 2) Guide to"trouble shooting" 22 3) Disassembly,repair and reassembly 23 4) Adjustment and checking 24 f. Manufacturer's printed operating and maintenance instructions 25 g. List of original manufacturer's spare parts,manufacturer's current prices,and 26 recommended quantities to be maintained in storage 27 h. Other data as required under pertinent Sections of Specifications 28 4. Prepare and include additional data when the need for such data becomes apparent 29 during instruction of City's personnel. 30 1.7 CLOSEOUT SUBMITTALS [NOT USED] 31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 32 1.9 QUALITY ASSURANCE 33 A. Provide operation and maintenance data by personnel with the following criteria: 34 1. Trained and experienced in maintenance and operation of described products 35 2. Skilled as technical writer to the extent required to communicate essential data 36 3. Skilled as draftsman competent to prepare required drawings CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 017823-5 OPERATION AND MAR'4TENANCE DATA Page 5 of 5 1 1.10 DELIVERY,STORAGE,AND HANDLING[NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] mm 3 1.12 WARRANTY [NOT USED] 4 PART 2- PRODUCTS [NOT USED] 5 PART 3- EXECUTION[NOT USED] 6 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D.Johnson 1.5.A.1.—title of section removed 8 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No. 100889 01 78 39-1 PROJECT RECORD DOCUMENTS Page I of 4 1 SECTION 0178 39 2 PROJECT RECORD DOCUMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Work associated with the documenting the project and recording changes to project '"• 7 documents, including: 8 a. Record Drawings 9 b. Water Meter Service Reports 10 c. Sanitary Sewer Service Reports 11 d. Large Water Meter Reports 12 B. Deviations from this City of Fort Worth Standard Specification i 13 1. None. 14 C. Related Specification Sections include,but are not necessarily limited to: -. 15 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 16 2. Division 1 —General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 23 1.5 SUBMITTALS 24 A. Prior to submitting a request for Final Inspection,deliver Project Record Documents to 25 City's Project Representative. µ, 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE 30 A. Accuracy of Records 31 1. Thoroughly coordinate changes within the Record Documents,making adequate 32 and proper entries on each page of Specifications and each sheet of Drawings and 33 other Documents where such entry is required to show the change properly. 34 2. Accuracy of records shall be such that future search for items shown in the Contract 35 Documents may rely reasonably on information obtained from the approved Project 36 Record Documents. CITY OF FORT WORTH 2017 WATER LEAD SERVICES �.. STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 017839-2 PROJECT RECORD DOCUMENTS Page 2 of 4 1 3. To facilitate accuracy of records,make entries within 24 hours after receipt of 2 information that the change has occurred. 3 4. Provide factual information regarding all aspects of the Work,both concealed and 4 visible,to enable future modification of the Work to proceed without lengthy and 5 expensive site measurement,investigation and examination. 6 1.10 STORAGE AND HANDLING 7 A. Storage and Handling Requirements 8 1. Maintain the job set of Record Documents completely protected from deterioration 9 and from loss and damage until completion of the Work and transfer of all recorded 10 data to the final Project Record Documents. 11 2. In the event of loss of recorded data,use means necessary to again secure the data 12 to the City's approval. 13 a. In such case,provide replacements to the standards originally required by the 14 Contract Documents. 15 1.11 FIELD [SITE] CONDITIONS [NOT USED] 16 1.12 WARRANTY [NOT USED] 17 PART 2- PRODUCTS 18 2.1 OWNER-FURNISHED [oR] OWNER-SUPPLIED PRODUCTS [NOT USED] 19 2.2 RECORD DOCUMENTS 20 A. Job set 21 1. Promptly following receipt of the Notice to Proceed,secure from the City,at no 22 charge to the Contractor, 1 complete set of all Documents comprising the Contract. 23 B. Final Record Documents 24 1. At a time nearing the completion of the Work and prior to Final Inspection,provide 25 the City 1 complete set of all Final Record Drawings in the Contract. 26 2.3 ACCESSORIES [NOT USED] 27 2.4 SOURCE QUALITY CONTROL [NOT USED] 28 PART 3- EXECUTION 29 3.1. INSTALLERS [NOT USED] 30 3.2 EXAMINATION [NOT USED] 31 3.3 PREPARATION [NOT USED] 32 3.4 MAINTENANCE DOCUMENTS 33 A. Maintenance of Job Set .� 34 1. Immediately upon receipt of the job set,identify each of the Documents with the 35 title, "RECORD DOCUMENTS-JOB SET". CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT .� Revised July 1,2011 City Project No.100889 017839-3 PROJECT RECORD DOCUMENTS Page 3 of 4 1 2. Preservation 2 a. Considering the Contract completion time,the probable number of occasions 3 upon which the job set must be taken out for new entries and for examination, 4 and the conditions under which these activities will be performed, devise a 5 suitable method for protecting the job set. 6 b. Do not use the job set for any purpose except entry of new data and for review 7 by the City, until start of transfer of data to final Project Record Documents. 8 c. Maintain the job set at the site of work. 9 3. Coordination with Construction Survey 10 a. At a minimum,in accordance with the intervals set forth in Section 01 71 23, 11 clearly mark any deviations from Contract Documents associated with 12 installation of the infrastructure. 13 4. Making entries on Drawings 14 a. Record any deviations from Contract Documents. 15 b. Use an erasable colored pencil(not ink or indelible pencil),clearly describe the 16 change by graphic line and note as required. 17 c. Date all entries. 18 d. Call attention to the entry by a"cloud"drawn around the area or areas affected. 19 e. In the event of overlapping changes,use different colors for the overlapping 20 changes. 21 5. Conversion of schematic layouts 22 a. In some cases on the Drawings, arrangements of conduits,circuits,piping, 23 ducts,and similar items,are shown schematically and are not intended to 24 portray precise physical layout. 25 1) Final physical arrangement is determined by the Contractor,subject to the 26 City's approval. �- 27 2) However,design of future modifications of the facility may require 28 accurate information as to the final physical layout of items which are 29 shown only schematically on the Drawings. ,e. 30 b. Show on the job set of Record Drawings,by dimension accurate to within 1 31 inch,the centerline of each run of items. 32 1) Final physical arrangement is determined by the Contractor,subject to the 33 City's approval. 34 2) Show,by symbol or note,the vertical location of the Item("under slab", "in 35 ceiling plenum", "exposed",and the like). 36 3) Make all identification sufficiently descriptive that it may be related 37 reliably to the Specifications. 38 c. The City may waive the requirements for conversion of schematic layouts 39 where,in the City's judgment, conversion serves no useful purpose. However, 40 do not rely upon waivers being issued except as specifically issued in writing 41 by the City. 42 B. Final Project Record Documents 43 1. Transfer of data to Drawings 44 a. Carefully transfer change data shown on the job set of Record Drawings to the 45 corresponding final documents,coordinating the changes as required. 46 b. Clearly indicate at each affected detail and other Drawing a full description of 47 changes made during construction,and the actual location of items. CITY OF FORT WORTH 2017 WATER LEAD SERVICES .� STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City.Project No.100889 017839-4 PROJECT RECORD DOCUMENTS Page 4 of 4 1 c. Call attention to each entry by drawing a"cloud"around the area or areas 2 affected. 3 d. Make changes neatly,consistently and with the proper media to assure 4 longevity and clear reproduction. 5 2. Transfer of data to other Documents 6 a. If the Documents,other than Drawings,have been kept clean.during progress of 7 the Work,and if entries thereon have been orderly to the approval of the City, 8 the job set of those Documents,other than Drawings,will be accepted as fmal , 9 Record Documents. 10 b. If any such Document is not so approved by the City,secure a new copy of that 11 Document from the City at the City's usual charge for reproduction and 12 handling,and carefully transfer the change data to the new copy to the approval 13 of the City. 14 3.5 REPAIR I RESTORATION [NOT USED] .� 15 3.6 RE-INSTALLATION [NOT USED] 16 3.7 FIELD [oR] SITE QUALITY CONTROL[NOT USED] " 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES [NOT USED] 21 3.12 PROTECTION [NOT USED] 22 3.13 MAINTENANCE [NOT USED] 23 3.14 ATTACHMENTS [NOT USED] 24 END OF SECTION 25 Revision Log DATE NAME SUMMARY OF CHANGE 26 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 0241 14-1 UTILITY REMOVAVABANDONMENT Page 1 of 17 1 OSECTION 02 4114 2 UTILITY REMOVAL/ABANDONMENT 3 PART 1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Direction for the removal,abandonment or salvaging of the following utilities: 7 a. Cathodic Protection Test Stations 8 b. Water Lines 9 c. Gate Valves .— 10 d. Water Valves 11 e. Fire Hydrants 12 f. Water Meters and Meter Box 13 g. Water Sampling Station 14 h. Concrete Water Vaults 15 i. Sanitary Sewer Lines 16 j. Sanitary Sewer Manholes 17 k. Sanitary Sewer Junction Boxes 18 1. Storm Sewer Lines 19 in. Storm Sewer Manhole Risers 20 n. Storm Sewer Junction Boxes 21 o. Storm Sewer Inlets 22 p. Box Culverts 23 q. Headwalls and Safety End Treatments 24 r. Trench Drains 25 B. Deviations from this City of Fort Worth Standard Specification 26 1. Removal of Existing Lead Services—The work for removal and disposal of the 27 existing lead water services to be replaced shall be considered subsidiary to the 28 bid price for the appropriate water service as specified in"Summary of Work" 29 (01 1100)and"Water Services 1-inch to 2-inch"(33 12 10). 30 C. Related Specification Sections include,but are not necessarily limited to: 31 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 32 2. Division 1—General Requirements 33 3. Section 03 34 13—Controlled Low Strength Material(CLSM) 34 4. Section 33 05 10—Utility Trench Excavation,Embedment and Backfill 35 5. Section 33 05 24—Installation of Carrier Pipe in Casing or Tunnel Liner Plate 36 6. Section 33 11 11 —Ductile Iron Fittings 37 7. Section 33 11 13—Concrete Pressure Pipe,Bar-wrapped, Steel Cylinder Type 38 8. Section 33 11 14—Buried Steel Pipe and Fittings 39 9. Section 33 12 25—Connection to Existing Water Mains 40 1.2 PRICE AND PAYMENT PROCEDURES 41 A. Utility Lines CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-2 UTILITY REMOVAL/ABANDONMENT Page 2 of 17 1 1. Abandonment of Utility Line by Grouting 2 a. Measurement 3 1) Measurement for this Item shall be per cubic yard of existing utility line to 4 be grouted.Measure by tickets showing cubic yards of grout applied. 5 b. Payment . 6 1) The work performed and materials furnished in accordance with this Item 7 and measured as provided under"Measurement"shall be paid for at the 8 unit price per cubic yard of"Line Grouting"for: 9 a) Various types of utility line 10 c. The price bid shall include: 11 1) Low density cellular grout or CLSM 12 2) Water 13 3) Pavement removal 14 4) Excavation 15 5) Hauling 16 6) Disposal of excess materials 17 7) Furnishing,placement and compaction of backfill 18 8) Clean-up » 19 2. Utility Line Removal, Separate Trench 20 a. Measurement 21 1) Measurement for this Item shall be per linear foot of existing utility line to 22 be removed. 23 b. Payment 24 1) The work performed and materials furnished in accordance with this Item 25 and measured as provided under"Measurement"shall be paid for at the 26 unit price bid per linear foot of"Remove Line"for: 27 a) Various types of existing utility line „ 28 b) Various sizes 29 c. The price bid shall include: 30 1) Removal and disposal of existing utility pipe 31 2) Pavement removal 32 3) Excavation 33 4) Hauling 34 5) Disposal of excess materials 35 6) Furnishing,placement and compaction of backfill 36 7) Clean-up 37 3. Utility Line Removal,Same Trench — 38 a. Measurement 39 1) This Item is considered subsidiary the proposed utility line being installed. 40 b. Payment - 41 1) The work performed and materials furnished in accordance with this Item 42 are subsidiary to the installation of proposed utility pipe and shall be 43 subsidiary to the unit price bid per linear foot of pipe complete in place,and 44 no other compensation will be allowed. 45 4. Manhole Abandonment 46 a. Measurement 47 1) Measurement for this Item will be per each manhole to be abandoned. 48 b. Payment CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-3 UTILITY REMOVAUABANDONMENT Page 3 of 17 1 1) The work performed and materials furnished in accordance with this Item 2 and measured as provided under"Measurement"shall be paid for at the 3 unit price bid per each"Abandon Manhole"for: 4 a) Various diameters 5 b) Various types 6 c. The price bid shall include: 7 1) Removal and disposal of manhole cone 8 2) Removal, salvage and delivery of frame and cover to City,if applicable 9 3) Cutting and plugging of existing sewer lines 10 4) Concrete 11 5) Acceptable material for backfilling manhole void 12 6) Pavement removal 13 7) Excavation 14 8) Hauling 15 9) Disposal of excess materials 16 10)Furnishing,placement and compaction of backfill 17 11) Surface restoration 18 12) Clean-up 19 5. Cathodic Test Station Abandonment 20 a. Measurement 21 1) Measurement for this Item will be per each cathodic test station to be 22 abandoned. 23 b. Payment 24 1) The work performed and materials furnished in accordance with this Item 25 and measured as provided under"Measurement"shall be paid for at the 26 unit price bid per each"Abandon Cathodic Test Station". 27 c. The price bid shall include: 28 1) Abandon cathodic test station 29 2) CLSM 30 3) Pavement removal 31 4) Excavation 32 5) Hauling 33 6) Disposal of excess materials 34 7) Furnishing,placement and compaction of backfill 35 8) Clean-up 36 B. Water Lines and Appurtenances 37 1. Installation of a Water Line Pressure Plug 38 a. Measurement 39 1) Measurement for this Item shall be per each pressure plug to be installed. 40 b. Payment 41 1) The work performed and materials furnished in accordance with this Item 42 and measured as provided under"Measurement"shall be paid for at the 43 unit price bid for each"Pressure Plug"installed for: 44 a) Various sizes 45 c. The price bid shall include: 46 1) Furnishing and installing pressure plug 47 2) Pavement removal 48 3) Excavation 49 4) Hauling CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-4 UTILITY REMOVAUABANDONMENT Page 4 of 1.7 1 5) Disposal of excess material 2 6) Gaskets 3 7) Bolts and Nuts 4 8) Furnishing,placement and compaction of embedment 5 9) Furnishing,placement and compaction of backfill 6 10)Disinfection 7 1.1)Testing 8 12) Clean-up 9 2. Abandonment of Water Line by Cut and installation of Abandonment Plug 10 a. Measurement 11 1) Measurement for this Item shall be per each cut and abandonment plug 12 installed. 13 b. Payment 14 1) The work performed and materials furnished in accordance with this Item 15 and measured as provided under"Measurement"shall be paid for at the 16 unit price bid for each"Water Abandonment Plug"installed for: 17 a) Various sizes 18 c. The price bid shall include: 19 1) Furnishing and installing abandonment plug 20 2) Pavement removal 21 3) Excavation 22 4) Hauling 23 5) CLSM 24 6) Disposal of excess material ., 25 7) Furnishing,placement and compaction of backfill 26 8) Clean-up 27 3. Water Valve Removal » 28 a. Measurement 29 1) Measurement for this Item will be per each water valve to be removed. 30 b. Payment 31 1) The work performed and materials furnished in accordance with this Item 32 and measured as provided under"Measurement"shall be paid for at the 33 unit price bid per each"Remove Water Valve"for: 34 a) Various sizes 35 c. The price bid shall include: 36 1) Removal and disposal of valve 37 2) CLSM 38 3) Pavement removal 39 4) Excavation 40 5) Hauling 41 6) Disposal of excess materials 42 7) Furnishing,placement and compaction of backfill 43 8) Clean-up . 44 4. Water Valve Removal and Salvage 45 a. Measurement 46 1) Measurement for this Item will be per each water valve to be removed and 47 salvaged. 48 b. Payment CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-5 UTILITY REMOVAIJABANDONMENT Page 5 of 17 1 1) The work performed and materials furnished in accordance with this Item 2 and measured as provided under"Measurement"shall be paid for at the 3 unit price bid per each"Salvage Water Valve"for: 4 a) Various sizes 5 c. The price bid shall include: 6 1) Removal and Salvage of valve 7 2) CLSM 8 3) Delivery to City 9 4) Pavement removal 10 5) Excavation 11 6) Hauling 12 7) Disposal of excess materials 13 8) Furnishing,placement and compaction of backfill 14 9) Clean-up 15 5. Water Valve Abandonment 16 a. Measurement 17 1) Measurement for this Item will be per each water valve to be abandoned. 18 b. Payment 19 1) The work performed and materials furnished in accordance with this Item 20 and measured as provided under"Measurement"shall be paid for at the 21 unit price bid per each"Abandon Water Valve"for: 22 a) Various Sizes 23 c. The price bid shall include: ., 24 1) Abandonment of valve 25 2) CLSM 26 3) Pavement removal 27 4) Excavation 28 5) Hauling 29 6) Disposal of excess materials 30 7) Furnishing,placement and compaction of backfill 31 8) Clean-up 32 6. Fire Hydrant Removal and Salvage 33 a. Measurement 34 1) Measurement for this Item will be per each fire hydrant to be removed. 35 b. Payment 36 1) The work performed and materials furnished in accordance with this Item 37 and measured as provided under"Measurement"shall be paid for at the 38 unit price bid per each"Salvage Fire Hydrant". 39 c. The price bid shall include: 40 1) Removal and salvage of fire hydrant 41 2) Delivery to City 42 3) Pavement removal 43 4) Excavation 44 5) Hauling 45 6) Disposal of excess materials 46 7) Furnishing,placement and compaction of backfill 47 8) Clean-up 48 7. Water Meter Removal and Salvage 49 a. Measurement CITY OF FORT WORTH 2017 WATER LEAD SERVICES .a STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-6 UTILITY REMOVAL/ABANDONMENT Page 6 of 17 1 1) Measurement for this Item will be per each water meter to be removed and 2 salvaged. ^- 3 b. Payment 4 1) The work performed and materials furnished in accordance with this Item 5 and measured as provided.under"Measurement"shall be paid for at the 6 unit price bid per each"Salvage Water Meter"for: 7 a) Various sizes 8 2) If a"Water Meter Service Relocate"is performed in accordance with 9 Section 33 12 10,removal and salvage or disposal of the existing(2-inch or 10 smaller)water meter shall be subsidiary to the cost of the"Water Meter 11 Service Relocate",no other compensation will be allowed. 12 c. The price bid shall include: "- 13 1) Removal and salvage of water meter 14 2) Delivery to City 15 3) Pavement removal 16 4) Excavation 17 5) Hauling 18 6) Disposal of excess materials �- 19 7) Furnishing,placement and compaction of backfill 20 8) Clean-up 21 8. Water Sampling Station Removal and Salvage 22 a. Measurement 23 1) Measurement for this Item will be per each water sampling station to be 24 removed. .�. 25 b. Payment 26 1) The work performed and materials furnished in accordance with this Item 27 and measured as provided under"Measurement"shall be paid for at the 28 unit price bid per each"Salvage Water Sampling Station". 29 c. The price bid shall include: 30 1) Removal and salvage of water sampling station 31 2) Delivery to City 32 3) Pavement removal 33 4) Excavation 34 5) Hauling 35 6) Disposal of excess materials 36 7) Furnishing,placement and compaction of backfill 37 8) Clean-up 38 9. Concrete Water Vault Removal 39 a. Measurement 40 1) Measurement for this Item will be per each concrete water vault to be 41 removed. 42 b. Payment 43 1) The work performed and materials furnished in accordance with this Item w- 44 and measured as provided under"Measurement"shall be paid for at the 45 unit price bid per each"Remove Concrete Water Vault". 46 c. The price bid shall include: 47 1) Removal and disposal of concrete water vault 48 2) Removal,salvage and delivery of frame and cover to City,if applicable 49 3) Removal, salvage and delivery of any valves to City,if applicable CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT -.- Revised December 20,2012 City Project No.100889 0241 14-7 UTILITY REMOVALIABANDONMENT Page 7 of 17 1 4) Removal, salvage and delivery of any water meters to City, if applicable 2 5) Pavement removal 3 6) Excavation 4 7) Hauling �. 5 8) Disposal of excess materials 6 9) Furnishing,placement and compaction of backfill 7 10)Clean-up 8 C. Sanitary Sewer Lines and Appurtenances 9 1. Abandonment of Sanitary Sewer Line by Cut and installation of Abandonment Plug 10 a. Measurement 11 1) Measurement for this Item shall be per each cut and abandonment plug 12 installed. 13 b. Payment 14 1) The work performed and materials furnished in accordance with this Item 15 and measured as provided under"Measurement"shall be paid for at the 16 unit price bidfor each"Sewer Abandonment Plug"for: 17 a) Various sizes 18 c. The price bid shall include: 19 1) Furnishing and installing abandonment plug 20 2) Pavement removal 21 3) Excavation 22 4) Hauling 23• 5) CLSM 24 6) Disposal of excess material 25 7) Furnishing,placement and compaction of backfill 26 8) Clean-up 27 2. Sanitary Sewer Manhole Removal 28 a. Measurement 29 1) Measurement for this Item will be per each sanitary sewer manhole to be 30 removed. 31 b. Payment 32 1) The work performed and materials furnished in accordance with this Item 33 and measured as provided under"Measurement" shall be paid for at the 34 unit price bid per each"Remove Sewer Manhole"for: 35 a) Various diameters .. 36 c. The price bid shall include: 37 1) Removal and disposal of manhole 38 2) Removal, salvage and.delivery of frame and cover to City, if applicable 39 3) Cutting and plugging of existing sewer lines 40 4) Pavement removal 41 5) Excavation 42 6) Hauling 43 7) Disposal of excess materials 44 8) Furnishing,placement and compaction of backfill 45 9) Clean-up 46 3. Sanitary Sewer Junction Structure Removal 47 a. Measurement 48 1) Measurement for this Item will be per each sanitary sewer junction 49 structure being removed. CITY OF PORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-8 UTILITY REMOVAL/ABANDONMENT Page 8 of 17 1 b. Payment 2 1) The work performed and materials furnished in accordance with this Item 3 and measured as provided under"Measurement"shall be paid for at the 4 lump sum bid per each"Remove Sewer Junction Box"location. 5 c. The price bid shall include: *�* 6 1) Removal and disposal of junction box 7 2) Removal,salvage and delivery of frame and cover to City. 8 3) Pavement removal 9 4) Excavation 10 5) Hauling 11 6) Disposal of excess materials 12 7) Furnishing, placement and compaction of backfill 13 8) Clean-up 14 D. Storm Sewer Lines and Appurtenances 15 1. Abandonment of Storm Sewer Line by Cut and installation of Abandonment Plug 16 a. Measurement 17 1) Measurement for this Item shall be per each cut and abandonment plug to 18 be installed. 19 b. Payment 20 1) The work performed and materials furnished in accordance with this Item 21 and measured as provided under"Measurement"shall be paid for at the 22 unit price bid for each"Storm Abandonment Plug"installed for: 23 a) Various sizes 24 c. The price bid shall include: 25 l) Furnishing and installing abandonment plug 26 2) Pavement removal 27 3) Excavation 28 4) Hauling 29 5) CLSM 30 6) Disposal of excess material i4 31 7) Furnishing,placement and compaction of backfill 32 8) Clean-up 33 2. Storm Sewer Manhole Removal -- 34 a. Measurement 35 1) Measurement for this Item will be per each storm sewer manhole to be 36 removed. �. 37 b. Payment 38 1) The work performed and materials furnished in accordance with this Item 39 and measured as provided under"Measurement"shall be paid for at the 40 unit price bid per each"Remove Manhole Riser"for: 41 a) Various sizes 42 c. The price bid shall include: 43 1) Removal and disposal of manhole 44 2) Removal, salvage and delivery of frame and cover to City,if applicable 45 3) Pavement removal 46 4) Excavation y` 47 5) Hauling 48 6) Disposal of excess materials 49 7) Furnishing,placement and compaction of backfill -� CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-9 UTILITY REMOVALIABANDONMENT Page 9 of 17 1 8) Clean-up 2 3. Storm Sewer Junction Box Removal 3 a. Measurement 4 1) Measurement for this Item will be per each storm sewer junction structure 5 to be removed. 6 b. Payment 7 1) The work performed and materials furnished in accordance with this Item 8 and measured as provided under"Measurement" shall be paid for at the 9 unit price bid per each"Remove Storm Junction Box"for: 10 a) Various sizes 11 c. The price bid shall include: 12 1) Removal and disposal of junction box 13 2) Removal,salvage and delivery of frame and cover to City, if applicable 14 3) Pavement removal 15 4) Excavation 16 5) Hauling 17 6) Disposal of excess materials 18 7) Furnishing,placement and compaction of backfill 19 8) Clean-up 20 4. Storm Sewer Junction Structure Removal 21 a. Measurement 22 1) Measurement for this Item will be per each storm sewer junction structure 23 being removed. 24 b. Payment 25 1) The work performed and materials fumished in accordance with this Item 26 and measured as provided under"Measurement"shall be paid for at the 27 lump sum bid per each"Remove Storm Junction Structure"location. 28 c. The price bid shall include: 29 1) Removal and disposal of junction structure 30 2) Removal, salvage and delivery of frame and cover to City,if applicable 31 3) Pavement removal 32 4) Excavation 33 5) Hauling 34 6) Disposal of excess materials 35 7) Furnishing,placement and compaction of backfill 36 8) Clean-up 37 5. Storm Sewer Inlet Removal 38 a. Measurement 39 1) Measurement for this Item will be per each storm sewer inlet to be 40 removed. 41 b. Payment 42 1) The work performed and materials furnished in accordance with this Item 43 and measured as provided under"Measurement" shall be paid for at the 44 unit price bid per each"Remove Storm Inlet"for: 45 a) Various types 46 b) Various sizes 47 c. The price bid shall include: 48 1) Removal and disposal of inlet 49 2) Pavement removal CITY OF FORT WORTH 2017 WATER LEAD SERVICES .� STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 02 41 14-10 UTILITY REMOVAUABANDONMENT �.. Page 10 of 17 1 3) Excavation 2 4) Hauling -F 3 5) Disposal of excess materials 4 6) Furnishing,placement and compaction of backfill 5 7) Clean-up �. 6 6. Storm Sewer Junction Box Removal 7 a. Measurement 8 1) Measurement for this Item shall be per linear foot of existing storm sewer 9 box to be removed. 10 b. Payment 11 1) The work performed and materials furnished in accordance with this Item 12 and measured as provided under"Measurement'shall be paid for at the 13 unit price bid per linear foot of"Remove Storm Junction Box"for all sizes. 14 c. The price bid shall include: 15 1) Removal and disposal of Storm Sewer Box 16 2) Pavement removal 17 3) Excavation 18 4) Hauling 19 5) Disposal of excess materials 20 6) Furnishing,placement and compaction of backfill 21 7) Clean-up 22 7. Headwall/SET Removal 23 a. Measurement 24 1) Measurement for this Item will be per each headwall or safety end 25 treatment(SET)to be removed. 26 b. Payment 27 1) The work performed and materials furnished in accordance with this Item 28 and measured as provided under"Measurement"shall be paid for at the 29 unit price bid per each"Remove Headwall/SET". 30 c. The price bid shall include: 31 1) Removal and disposal of Headwall/SET 32 2) Pavement removal 33 3) Excavation 34 4) Hauling 35 5) Disposal of excess materials 36 6) Furnishing,placement and compaction of backfill 37 7) Clean-up ~ 38 8. Trench Drain Removal 39 a. Measurement 40 1) Measurement for this.Item shall be per linear foot of storm sewer trench 41 drain to be removed. 42 b. Payment 43 1) The work performed and materials furnished in accordance with this Item 44 and measured as provided under"Measurement' shall be paid for at the 45 unit price bid per linear foot of"Remove Trench Drain"for: 46 a) Various sizes 47 c. The price bid shall include: 48 1) Removal and disposal of storm sewer line 49 2) Pavement removal CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 024114-11 UTILITY REMOVALIABANDONMENT Page 11 of 17 1 3) Excavation 2 4) Hauling 3 5) Disposal of excess materials 4 6) Furnishing,placement and compaction of backfill 5 7) Clean-up 6 1.3 REFERENCES [NOT USED] ,. 7 1.4 ADMINISTRATIVE REQUIREMENTS 8 A. Coordination 9 1. Contact Inspector and the Water Department Field Operation Storage Yard for 10 coordination of salvage material return. 11 1.5 SUBMITTALS [NOT USED] 12 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 13 1.7 CLOSEOUT SUBMITTALS [NOT USED] 14 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 15 1.9 QUALITY ASSURANCE [NOT USED] 16 1.10 DELIVERY,STORAGE,AND HANDLING 17 A. Storage and Handling Requirements 18 1. Protect and salvage all materials such that no damage occurs during delivery to the 19 City. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 024114-12 UTILITY REMOVAUABANDONMENT Page 12 of 17 1 1.11 FIELD [SITE) CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED) 3 PART 2- PRODUCTS 4 2.1 OWNER-FURNISHED[OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 5 2.2 MATERIALS 6 2.3 ACCESSORIES [NOT USED] 7 2.4 SOURCE QUALITY CONTROL [NOT USED) 8 PART 3- EXECUTION 9 3.1 INSTALLERS [NOT USED] 10 3.2 EXAMINATION [NOT USED] 11 3.3 PREPARATION [NOT USED] 12 3.4 REMOVAL,SALVAGE,AND ABANDONMENT 13 A. General 14 1. Manhole Abandonment 15 a. All manholes that are to be taken out of service are to be removed unless 16 specifically requested and/or approved by City. 17 b. Excavate and backfill in accordance with Section 33 05 10. �. 18 c. Remove and salvage manhole frame and cover as coordinated with City. 19 d. Deliver salvaged material to the City. 20 e. Cut and,plug sewer lines to be abandoned. 21 f. Backfill manhole void in accordance with City Standard Details. 22 B. Water Lines and Appurtenances 23 1. Water Line Pressure Plugs 24 a. Ductile Iron Water Lines 25 1) Excavate,embed, and backfill in accordance with Section 33 05 10. 26 2) Plug with an MJ Plug with mechanical restraint and blocking in accordance 27 with Section 33 11 11. 28 3) Perform Cut and Plug in accordance with Section 33 12 25. 29 b. PVC C900 and C905 Water Lines 30 1) Excavate,embed,and backfill in accordance with Section 33 05 10. 31 2) Plug with an MJ Plug with mechanical restraint and blocking in accordance 32 with Section 33 11 11. 33 3) Perform Cut and Plug in accordance with Section 33 12 25. 34 c. Concrete Pressure Pipe,Bar Wrapped, Steel Cylinder Type Water Lines 35 1) Excavate,embed,and backfill in accordance with Section 33 05 10 �. 36 2) Plug using; 37 a) A fabricated plug restrained by welding or by a Snap Ring in 38 accordance with Section 33 11 13; or CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-13 UTILITY REMOVAUABANDONMENT Page 13 of 17 1 b) A blind flange in accordance with Section 33 11 13 2 3) Perform Cut and Plug in accordance with Section 33 12 25. 3 d. Buried Steel Water Lines 4 1) Excavate,embed,and backfill in accordance with Section 33 05 10. 5 2) Plug using; 6 a) A fabricated plug restrained by welding in accordance with Section 33 7 11 14;or 8 b) A blind flange in accordance with Section 33 11 14 9 3) Perform Cut and,Plug in accordance with Section 33 12 25. 10 2. Water Line Abandonment Plug 11 a. Excavate and backfill in accordance with Section 33 05 10. 12 b. Plug with CLSM in accordance with Section 03 34 1.3. 13 3. Water Line Abandonment by Grouting 14 a. Excavate and backfill in accordance with Section 33 05 10. 15 b. Dewater from existing line to be grouted. 16 c. Fill line with Low Density Cellular Grout in accordance with Section 33 05 24 17 or CLSM in accordance with 03 34 13. 18 d. Dispose of any excess material. 19 4. Water Line Removal 20 a. Excavate and backfill in accordance with Section 33 05 10. 21 b. Cut existing line from the utility system prior to removal. 22 c. Cut any services prior to removal. 23 d. Remove existing pipe line and properly dispose as approved by City. 24 5. Water Valve Removal 25 a. Excavate and backfill in accordance with Section 33 05 10. 26 b. Remove and dispose of valve bonnet,wedge and stem. 27 c. Fill valve body with CLSM in accordance with Section 03 3413. 28 6. Water Valve Removal and Salvage 29 a. Excavate and backfill in accordance with Section 33 05 10. 30 b. Remove valve bonnet,wedge and stem. 31 c. Deliver salvaged material to the Water Department Field Operation Storage 32 Yard. .� 33 d. Protect salvaged materials from damage. 34 e. Fill valve body with CLSM in accordance with Section 03 34 13. 35 7. Water Valve Abandonment 36 a. Excavate and backfill in accordance with Section 33 05 10. 37 b. Remove the top 2 feet of the valve stack and any valve extensions. 38 c. Fill the remaining valve stack with CLSM in accordance with Section 03 34 13. - 39 8. Fire Hydrant Removal and Salvage 40 a. Excavate and backfill in accordance with Section 33 05 10. 41 b. Remove Fire Hydrant. 42 c. Place abandonment plug on fire hydrant lead line. 43 d. Deliver salvaged fire hydrant to the Water Department Field Operation Storage 44 Yard. 45 e. Protect salvaged materials from damage. 46 9. Water Meter Removal and Salvage 47 a. Remove and salvage water meter. 48 b. Return salvaged meter to Project Representative. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-14 UTILITY REMOVALABANDONMENT Page 14 of 17 1 c. City will provide replacement meter for installation. 2 d. Meter Box and Lid 3 1) Remove and salvage cast iron meter box lid. 4 2) Remove and dispose of any non-cast iron meter box lid. 5 3) Return salvaged material to the Water Department Field Operation Storage 6 Yard. 7 4) Remove and dispose of meter box. 8 10. Water Sample Station Removal and Salvage 9 a. Remove and salvage existing water sample station. 10 b. Deliver salvaged material to the Water Department Field Operation Storage 11 Yard. 12 11. Concrete Water Vault Removal 13 a. Excavate and backfill in accordance with Section 33 05 10. 14 b. Remove and salvage vault lid. 15 c. Remove and salvage valves. 16 d. Remove and salvage meters. 17 e. Deliver salvaged material to the Water Department.Field Operation Storage 18 Yard. 19 f. Remove and dispose of any piping or other appurtenances. 20 g. Demolish and remove entire concrete vault. 21 h. Dispose of all excess materials. ._ 22 12. Cathodic Test Station Abandonment 23 a. Excavate and backfill in accordance with Section 33 05 10 24 b. Remove the top 2 feet of the cathodic test station stack and contents. 25 c. Fill any remaining voids with CLSM in accordance with Section 03 34 13. 26 C. Sanitary Sewer Lines and Appurtenances 27 1. Sanitary Sewer Line Abandonment Plug 28 a. Excavate and backfill in accordance with Section 33 05 10. 29 b. Remove and dispose of any sewage. 30 c. Plug with CLSM in accordance with Section 03 34 13. 31 2. Sanitary Sewer Line Abandonment by Grouting 32 a. Excavate and backfill in accordance with Section 33 05 10. 33 b. Dewater and dispose of any sewage from the existing line to be grouted. 34 c. Fill line with Low Density Cellular Grout in accordance with Section 33 05 24 35 or CLSM in accordance with 03 34 13. 36 d. Dispose of any excess material. 37 3. Sanitary Sewer Line Removal 38 a. Excavate and backfill in accordance with Section 33 05 10. 39 b. Cut existing line from the utility system prior to removal. 40 c. Cut any services prior to removal. 41 d. Remove existing pipe line and properly dispose as approved by City. 42 4. Sanitary Sewer Manholes Removal 43 a. All sanitary sewer manholes that are to be taken out of service are to be 44 removed unless specifically requested and/or approved by City. 45 b. Excavate and backfill in accordance with Section 33 05 10. 46 c. Remove and salvage manhole frame and cover. 47 d. Deliver salvaged material to the Water Department Field Operation Storage. 48 e. Demolish and remove entire concrete manhole. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 024114-15 UTILITY REMOVAL/ABANDONMENT Page 15 of 17 1 f. Cut and plug sewer lines to be abandoned. 2 5. Sanitary Sewer Junction Structure Removal 3 a. Excavate and backfill in accordance with Section 33 05 10. 4 b. Remove and salvage manhole frame and cover. 5 c. Deliver salvaged material to the Water Department Field Operation Storage. 6 d. Demolish and remove entire concrete manhole. 7 e. Cut and plug sewer lines to be abandoned. ° 8 D. Storm Sewer Lines and Appurtenances 9 1. Storm Sewer Abandonment Plug 10 a. Excavate and backfill in accordance with Section 33 05 10. 11 b. Dewater line. 12 c. Plug with CLSM in accordance with Section 03 34 13. 13 2. Storm Sewer Line Abandonment by Grouting 14 a. Excavate and backfill in accordance with Section 33 05 10. 15 b. Dewater the existing line to be grouted. 16 c. Fill line with Low Density Cellular Grout in accordance with Section 33 05 24 17 or CLSM in accordance with 03 34 13. 18 d. Dispose of any excess material. 19 3. Storm Sewer Line Removal 20 a. Excavate and backfill in accordance with Section 33 05 10. 21 b. Remove existing pipe line and properly dispose as approved by City. 22 4. Storm Sewer Manhole Removal 23 a. All storm sewer manholes that are to be taken out of service are to be removed 24 unless specifically requested and/or approved by City. 25 b. Excavate and backfill in accordance with Section 33 05 10. 26 c. Demolish and remove entire concrete manhole. 27 d. Cut and plug storm sewer lines to be abandoned. 28 5. Storm Sewer Junction Box and/or Junction Structure Removal 29 a. Excavate and backfill in accordance with Section 33 05 10. 30 b. Demolish and remove entire concrete structure. 31 c. Cut and plug storm sewer lines to be abandoned. 32 6. Storm Sewer Inlet Removal 33 a. Excavate and backfill in accordance with Section 33 05 10. 34 b. Demolish and remove entire concrete inlet. 35 c. Cut and plug storm sewer lines to be abandoned. 36 7. Storm Sewer Box Removal 37 a. Excavate and backfill in accordance with Section 33 05 10. 38 b. Cut existing line from the utility system prior to removal. 39 c. Cut any services prior to removal. 40 d. Remove existing pipe line and properly dispose as approved by City. 41 8. Headwall/SET Removal 42 a. Excavate and backfill in accordance with Section 33 05 10. 43 b. Demolish and remove entire concrete inlet. 44 c. Cut and plug storm sewer lines to be abandoned. 45 9. Storm Sewer Trench Drain Removal 46 a. Excavate and backfill in accordance with Section 33 05 10. 47 b. Remove existing pipe line and dispose as approved by City. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-16 UTILITY REMOVALIABANDONMENT Page 16 of 17 a.. 1 3.5 REPAIR I RESTORATION [NOT USED] 2 3.6 RE-INSTALLATION [NOT USED] 3 3.7 FIELD [oR] SITE QUALITY CONTROL 4 3.8 SYSTEM STARTUP [NOT USED] 5 3.9 ADJUSTING [NOT USED] 6 3.10 CLEANING [NOT USED] 7 3.11 CLOSEOUT ACTIVITIES [NOT USED] OM 8 3.12 PROTECTION [NOT USED] 9 3.13 MAINTENANCE [NOT USED] 10 3.14 ATTACHMENTS [NOT USED] 11 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 0241 14-17 UTILITY REMOVALIABANDONMENT Page 17 of 17 1 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 1.2.C.3.c.—Include Frame and Cover in Payment description 12/20/12 D.Johnson Throughout—added abandonment of storm and sewer manholes when requested and/or approved by City 2 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 3201 17-1 PERMANENT ASPHALT PAVING REPAIR Page i of 5 I SECTION 32 0117 2 PERMANENT ASPHALT PAVING REPAIR 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section includes: 6 1. Flexible pavement repair to include,but not limited to: 7 a. Utility cuts(water,sanitary sewer,drainage,franchise utilities,etc.) 8 b. Warranty work 9 c. Repairs of damage caused by Contractor 10 d. Any permanent asphalt pavement repair needed during the course of 11 construction 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. Asphalt Pavement Repair,Water Services-The asphalt pavement repair work 14 covered by these Specifications is included in the unit bid price of the 15 appropriate water service to be installed.All asphalt paving repair as specified �- 16 under 1.2-A-2."Asphalt Pavement Repair for Utility Service Trench" up to 17 4-foot wide is considered subsidiary to the appropriate water service bid item 18 and specified in"Water Services 1-inch to 2-inch"(33-12-10).When asphalt 19 pavement repair in addition to the 4-foot wide trench repair is required as 20 directed by the City,the additional work will be paid for at the square yard 21 price bid for 113-inch Extra Width Asphalt Pavement Repair"as specified 22 under 1.2-A-4 below. 23 C. Related Specification Sections include,but are not necessarily limited to: 24 1. Division 0—Bidding Requirements,Contract Forms,and Conditions of the 25 Contract 26 2. Division 1 —General Requirements 27 3. Section 03 34 16—Concrete Base Material for Trench Repair 28 4. Section 32 12 16—Asphalt Paving 29 5. Section 32 13 13—Concrete Paving 30 6. Section 33 05 10—Utility Trench Excavation,Embedment and Backfill 31 1.2 PRICE AND PAYMENT PROCEDURES 32 A. Measurement and Payment 33 1. Asphalt Pavement Repair 34 a. Measurement 35 1) Measurement for this Item will be by the linear foot of Asphalt Pavement 36 Repair based on the defined width and roadway classification specified in the 37 Drawings. 38 b. Payment 39 1) The work performed and materials furnished in accordance with this Item 40 and measured as provided under"Measurement"will be paid for at the unit w- 41 price bid price per linear foot of Asphalt Pavement Repair. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 320117-2 PERMANENT ASPHALT PAVING REPAIR Page 2 of 5 1 c. The price bid shall include: 2 1) Preparing final surfaces ,. 3 2) Furnishing, loading,unloading,storing,hauling and handling all materials 4 including freight and royalty 5 3) Traffic control for all testing 6 4) Asphalt,aggregate,and additive 7 5) Materials and work needed for corrective action 8 6) Trial batches 9 7) Tack coat 10 8) Removal and/or sweeping excess material 11 2. Asphalt Pavement Repair for Utility Service Trench 12 a. Measurement 13 1) Measurement for this Item will be by the linear foot of Asphalt Pavement 14 Repair centered on the proposed sewer service line measured from the face of 15 curb to the limit of the Asphalt Pavement Repair for the main sewer line. ° 16 b. Payment 17 1) The work performed and materials furnished in accordance with this Item 18 and measured as provided under"Measurement"will be paid for at the unit 19 price bid price per linear foot of"Asphalt Pavement Repair,Service"installed 20 for: 21 a) Various types of utilities . 22 c. The price bid shall include: 23 1) Preparing final surfaces 24 2) Furnishing,loading,unloading,storing,hauling and handling all materials „ 25 including freight and royalty 26 3) Traffic control for all testing 27 4) Asphalt,aggregate,and additive 28 5) Materials and work needed for corrective action 29 6) Trial batches 30 7) Tack coat 31 8) Removal and/or sweeping excess material 32 3. Asphalt Pavement Repair Beyond Defined Width 33 a. Measurement 34 1) Measurement for this Item will be by the square yard for asphalt pavement " 35 repair beyond pay limits of the defined width of Asphalt Pavement Repair by 36 roadway classification specified in the Drawings. 37 b. Payment �- 38 1) The work performed and materials furnished in accordance with this Item 39 and measured as provided under"Measurement"will be paid for at the unit 40 price bid per square yard of Asphalt Pavement Repair Beyond Defined Width. 41 c. The price bid shall.include: 42 1) Preparing final surfaces 43 2) Furnishing,loading,unloading,storing,hauling and handling all materials 44 including freight and royalty 45 3) Traffic control for all testing 46 4) Asphalt,aggregate,and additive 47 5) Materials and work needed for corrective action 48 6) Trial batches 49 7) Tack coat CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 3201 17-3 PERMANENT ASPHALT.PAVING REPAIR Page 3 of 5 1 8) Removal and/or sweeping excess material 2 4. Extra Width Asphalt Pavement Repair 3 a. Measurement 4 1) Measurement for this Item will be by the square yard for surface repair 5 (does not include base repair)for: 6 a) Various thicknesses 7 b. Payment 8 1) The work performed and materials furnished in accordance with this Item 9 and measured as provided under"Measurement"will be paid for at the unit 10 price bid per square yard of Extra Width Asphalt Pavement Repair �. 11 c. The price bid shall include: 12 1) Preparing final surfaces 13 2) Furnishing,loading, unloading,storing,hauling and handling all materials 14 including freight and royalty 15 3) Traffic control for all testing 16 4) Asphalt,aggregate,and additive 17 5) Materials and work needed for corrective action 18 6) Trial batches 19 7) Tack coat 20 8) Removal and/or sweeping excess material 21 1.3 REFERENCES 22 A. Definitions ®" 23 1. H.M.A.C.—Hot Mix Asphalt Concrete 24 1.4 ADMINISTRATIVE REQUIREMENTS 25 A. Permitting 26 1. Obtain Street Use Permit to make utility cuts in the street from the Transportation 27 and Public Works Department in conformance with current ordinances. 28 2. The Transportation and Public Works Department will inspect the paving repair 29 ager construction. 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 32 A. Asphalt Pavement Mix Design: submit for approval: see Section 32 12 16. 33 1.7 CLOSEOUT SUBMITTALS [NOT USED] 34 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 35 1.9 QUALITY ASSURANCE [NOT USED] 36 1.11 DELIVERY,STORAGE,AND HANDLING[NOT USED] 37 1.12 FIELD CONDITIONS 38 A. Place mixture when the roadway surface temperature is 45 degrees F or higher and 39 rising unless otherwise approved. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No. 100889 3201 17-4 PERMANENT ASPHALT PAVING REPAIR Page 4 of 5 1 1.13 WARRANTY[NOT USED] 2 PART 2- PRODUCTS 3 2.1 OWNER-FURNISHED [NOT USED] 4 2.2 MATERIALS 5 A. Backfill 6 1. See Section 33 05 10. 7 B. Base Material - 8 1. Concrete Base Material for Trench Repair: See Section 03 34 16. 9 2. Concrete Base: See Section 32 13 13. 10 C. Asphalt Paving: see Section 32 12 16. 11 1. R.M.A.C.paving: Type D. 12 2.3 ACCESSORIES [NOT USED] 13 2.4 SOURCE QUALITY CONTROL[NOT USED] 14 PART 3- EXECUTION 15 3.1 INSTALLERS [NOT USED] 16 3.2 EXAMINATION [NOT USED] 17 3.3 PREPARATION u 18 A. Surface Preparation 19 1. Mark pavement cut for repairs for approval by the City. 20 2. Contractor and City meet prior to saw cutting to confirm limits of repairs. 21 3.4 INSTALLATION . 22 A. General 23 1. Equipment 24 a. Use machine intended for cutting pavement. 25 b. Milling machines may be used as long as straight edge is maintained. 26 2. Repairs: In true and straight lines to dimensions shown on the Drawings. 27 3. Utility Cuts 28 a. In a true and straight line on both sides of the trench 29 b. Minimum of 12 inches outside the trench walls 30 c. If the existing flexible pavement is 2 feet or less between the lip of the existing 31 gutter and the edge of the trench repair,remove the existing paving to such 32 gutter. 33 4. Limit dust and residues from sawing from entering the atmosphere or drainage 34 facilities. 35 B. Removal CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 320117-5 PERMANENT ASPHALT PAVING REPAIR Page 5 of 5 1 1. Use care to prevent fracturing existing pavement structure adjacent to the repair 2 area. 3 C. Base 4 1. Install replacement base material as specified in Drawings. 5 D. Asphalt Paving 6 1. H.M.A.0 placement: in accordance with Section 32 12 16 7 2. Type D surface mix 8 3. Depth: as specified in Drawings 9 4. Place surface mix in lifts not to exceed 3 inches. 10 5. Last or top lift shall not be less than 2 inches thick. 11 3.5 REPAIR/RESTORATION[NOT USED] 12 3.6 RE-INSTALLATION[NOT USED] 13 3.7 FIELD QUALITY CONTROL [NOT USED] 14 3.8 SYSTEM STARTUP [NOT USED] 15 3.9 ADJUSTING [NOT USED) 16 3.10 CLEANING [NOT USED) 17 3.11 CLOSEOUT ACTIVITIES [NOT USED) 18 3.12 PROTECTION [NOT USED) 19 3.13 MAINTENANCE [NOT USED) 20 3.14 ATTACE[MENTS [NOT USED) 21 22 END OF SECTION 23 Revision Log DATE NAME SUMMARY OF CHANGE 1.2.A—Modified Items to be included in price bid;Added blue tent for clarification 12/20/2012 D.Johnson of repair width on utility trench repair;Added a bid item for utility service trench repair. 24 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 32 01 29-1 CONCRETE PAVING REPAIR Page I of 4 1 SECTION 32 0129 2 CONCRETE PAVING REPAIR 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section includes: 6 1. Concrete pavement repair to include,but not limited to: 7 a. Utility cuts(water,sanitary sewer,drainage,etc.) 8 b. Warranty work 9 c. Repairs of damage caused by Contractor .� 10 d. Any other concrete pavement repair needed during the course of construction 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. Concrete Pavement Repair,Water Services- The concrete pavement repair 13 work covered by these Specifications is included in the unit bid price of the 14 appropriate water service to be installed.All concrete paving repair up to 4- is foot wide is considered subsidiary to the appropriate water service bid item - 16 and specified in"Water Services 1-inch to 2-inch"(33-12-10).When concrete 17 pavement repair in addition to the 4-foot wide trench repair is required as 18 directed by the City,the additional work will be paid for at the square yard -- 19 price bid for"Concrete Pavement Repair"as specified below. 20 C. Related Specification Sections include,but are not necessarily limited to: 21 1. Division 0-Bidding Requirements,Contract Forms,and Conditions of the Contract 22 2. Division 1 -General Requirements 23 3. Section 32 01 18-Temporary Asphalt Paving Repair 24 4. Section 32 12 16-Asphalt Paving 25 5. Section 32 13 13-Concrete Paving 26 6. Section 33 05 10-Utility Trench Excavation,Embedment and Backfill 27 1.2 PRICE AND PAYMENT PROCEDURES 28 A. Measurement and Payment 29 1. Concrete Pavement Repair 30 a. Measurement 31 1) Measurement for this Item shall be by the square yard of Concrete 32 Pavement Repair for various: 33 a) Street types 34 2) Limits of repair will be based on the time of service of the existing 35 pavement. The age of the pavement will need to be determined by the 36 Engineer through coordination with the City.For pavement ages: 37 a) 10 years or less: repair entire panel .� 38 b) Greater than 10 years:repair to limits per Drawings 39 b. Payment CITY OF FORT WORTH 2017 WATER LEAD SERVICES .. STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 320129-2 CONCRETE PAVING REPAIR Page 2 of 4 1 1) The work performed and materials furnished in accordance with this Item 2 and measured as provided under"Measurement"shall be paid for at the 3 unit price bid per square yard of Concrete Pavement Repair 4 c. The price bid shall include: 5 1) Shaping and fine grading the placement area 6 2) Furnishing and applying all water required 7 3) Furnishing,loading and unloading,storing,hauling and handling all 8 concrete 9 4) Furnishing, loading and unloading,storing,hauling and handling all base 10 material 11 5) Mixing,placing,finishing and curing all concrete 12 6) Furnishing and installing reinforcing steel 13 7) Furnishing all materials and placing longitudinal,warping,expansion and 14 contraction joints,including all steel dowels, dowel caps and load 15 transmission units required,wire and devices for placing,holding and 16 supporting the steel bar,load transmission units,and joint filler in the 17 proper position;for coating steel bars where required by the Drawings 18 8) Sealing joints — 19 9) Monolithically poured curb 20 10)Cleanup 21 1.3 REFERENCES [NOT USED] ' 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Permitting 'p 24 1. Obtain Street Use Permit to make utility cuts in the street from the Transportation 25 and Public Works Department in conformance with current ordinances. 26 2. Transportation and Public Works Department will inspect paving repair after 27 construction. 28 1.5 SUBMITTALS [NOT USED] 29 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 30 A. Concrete Mix Design: submit for approval in accordance with Section 32 13 13. 31 1.7 CLOSEOUT SUBMITTALS [NOT USED] 32 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 33 1.9 QUALITY ASSURANCE [NOT USED] 34 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 35 1.11 FIELD CONDITIONS 36 A. Weather Conditions: Place concrete as specified in Section 32 13 13. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 320129-3 CONCRETE PAVING REPAIR Page 3 of 4 1 1.12 WARRANTY [NOT USED] 2 PART 2- PRODUCTS 3 2.1 OWNER-FURNISHED PRODUCTS [NOT USED] 4 2.2 MATERIALS 5 A. Embedment and Backfill: see Section 33 05 10. 6 B. Base material: Concrete base: see Section 32 13 13. 7 C. Concrete: see Section 32 13 13. 8 1. Concrete paving: Class H or Class HES. 9 2. Replace concrete to the specified thickness. 10 2.3 ACCESSORIES [NOT USED] 11 2.4 SOURCE QUALITY CONTROL [NOT USED] 12 PART 3- EXECUTION 13 3.1 INSTALLERS [NOT USED] 14 3.2 EXAMINATION [NOT USED] 15 3.3 PREPARATION 16 A. Replace a continuous section if multiple repairs are closer than 10 feet apart from edge 17 of one repair to the edge of a second repair. 18 B. If the cut is to be covered,use steel plates of sufficient strength and thickness to support 19 traffic. 20 1. Construct a transition of hot-mix or cold-mix asphalt from the top of the steel plate 21 to the existing pavement to create a smooth riding surface. 22 a. Hot-mix or cold-mix asphalt: conform to the requirements of Section 32 12 16. 23 C. Surface Preparation: mark pavement cut repairs for approval by the City. 24 3.4 INSTALLATION 25 A. Sawing 26 1. General 27 a. Saw cut perpendicular to the surface to full pavement depth. 28 b. Saw cut the edges of pavement and-appurtenances damaged subsequent to 29 sawing to remove damaged areas. 30 c. Such saw cuts shall be parallel to the original saw cut and to neat straight lines. 31 2. Sawing equipment 32 a. Power-driven -" 33 b. Manufactured for the purpose of sawing pavement 34 c. In good operating condition 35 d. Shall not spall or facture concrete adjacent to the repair area CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 320129-4 CONCRETE PAVING REPAIR Page 4 of 4 1 3. Repairs: In true and straight lines to dimensions shown on the Drawings 2 4. Utility Cuts 3 a. In a true and straight line on both sides of the trench 4 b. Minimum of 12 inches outside the trench walls 5 5. Prevent dust and residues from sawing from entering the atmosphere or drainage 6 facilities. 7 B. Removal 8 1. Use care in removing concrete to be repaired to prevent spalling or fracturing 9 concrete adjacent to the repair area. 10 C. Base: as specified in Drawings 1 I D. Concrete Paving I2 1. Concrete placement: in accordance with Section 32 13 13. 13 2. Reinforce concrete replacement: as specified in Drawings 14 3.5 REPAIR/RESTORATION [NOT USED] 15 3.6 RE-INSTALLATION [NOT USED] 16 3.7 FIELD QUALITY CONTROL[NOT USED] 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES [NOT USED] 21 3.12 PROTECTION [NOT USED] 22 3.13 MAINTENANCE [NOT USED] —. 23 3.14 ATTACHMENTS [NOT USED] 24 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 1.2.A—Modified Items to be included in price bid;Added blue text for clarification 12/20/2012 D.Johnson of repair width on utility trench repair 2.2.C.I—Changed to Class P to Class H 25 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No. 100889 321723-1 PAVEMENT MARKINGS Page I of 11 1 SECTION 3217 23 2 PAVEMENT MARKINGS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Pavement Markings .. 7 a. Thermoplastic,hot-applied,spray(HAS)pavement markings 8 b. Thermoplastic,hot-applied,extruded(HAE)pavement markings 9 c. Preformed polymer tape 10 d. Preformed heat-activated thermoplastic tape 11 2. Raised markers 12 3. Work zone markings 13 4. Removal of pavement markings and markers 14 B. Deviations from this City of Fort Worth Standard Specification 15 1. Pavement Markings—All pavement marldngs removal,repair and/or 16 replacement shall be subsidiary to the appropriate pavement repair bid item in 17 these contract specifications. 18 C. Related Specification Sections include, but are not necessarily limited to: 19 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 20 2. Division 1 —General Requirements 21 1.2 PRICE AND PAYMENT PROCEDURES 22 A. Measurement and Payment 23 1. Pavement Markings 24 a. Measurement 25 1) Measurement for this Item shall be per linear foot of material placed. 26 b. Payment 27 1) The work performed and materials furnished in accordance with this Item 28 and measured as provided under"Measurement"shall be paid for at the 29 unit price bid per linear foot of"Pvmt Marking"installed for: 30 a) Various Widths 31 b) Various Types 32 c) Various Materials 33 d) Various Colors 34 c. The price bid shall include: 35 1) Installation of Pavement Marking 36 2) Glass beads,when required 37 3) Surface preparation 38 4) Clean-up 39 5) Testing(when required) 40 2. Legends 41 a. Measurement CITY OF FORS'WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 321723-2 PAVEMENT MARKINGS Page 2 of I 1 1 1) Measurement for this Item shall be per each Legend installed. 2 b. Payment 3 1) The work performed and materials furnished in accordance with this Item 4 shall be paid for at the unit price bid per each"Legend"installed for: 5 a) Various types 6 b) Various applications 7 c. The price bid shall include: 8 1) Installation of Pavement Marking 9 2) Glass beads,when required 10 3) Surface preparation 11 4) Clean-up 12 5) Testing " 13 3. Raised Markers 14 a. Measurement 15 1) Measurement for this Item shall be per each Raised Marker installed. 16 b. Payment 17 1) The work performed and materials furnished in accordance with this Item 18 shall be paid for at the unit price bid per each"Raised Marker"installed 19 for: 20 a) Various types 21 c. The price bid shall include: 22 1) Installation of Raised Markers 23 2) Surface preparation 24 3) Clean-up 25 4) Testing 26 4. Work Zone Tab Markers 27 a. Measurement 28 1) Measurement for this Item shall be per each Tab Marker installed. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this Item 31 shall be paid for at the unit price bid per each"Tab Marker"installed for: 32 a) Various types 33 c. The price bid shall include: 34 1) Installation of Tab Work Zone Markers 35 5. Fire Lane Markings 36 a. Measurement 37 1) Measurement for this Item shall be per the linear foot. 38 b. Payment 39 1) The work performed and materials furnished in accordance with this Item 40 and measured as provided under"Measurement"shall be paid for at the -- 41 unit price bid per linear foot of"Fire Lane Marking"installed. 42 c. The price bid shall include: 43 1) Surface preparation 44 2) Clean-up 45 3) Testing 46 6. Pavement Marking Removal 47 a. Measurement 48 1) Measure for this Item shall be per linear foot. 49 b. Payment CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 �" 321723-3 PAVEMENT MARKINGS Page 3 of 11 1 1) The work performed and materials furnished in accordance with this Item 2 and measured as provided under"Measurement'shall be paid for at the 3 unit price bid per linear foot of"Remove Pvmt Marking"performed for: 4 a) Various widths 5 c. The price bid shall include: 6 1) Removal of Pavement Markings 7 2) Clean-up 8 7. Raised Marker Removal 9 a. Measurement 10 1) Measurement for this Item shall be per each Pavement Marker removed. 11 b. Payment 12 1) The work performed and materials furnished in accordance with this Item 13 shall be paid for at the unit price bid per each"Remove Raised Marker" 14 performed. 15 c. The price bid shall include: 16 1) Removal of each Marker 17 2) Disposal of removed materials 18 3) Clean-up 19 8. Legend.Removal 20 a. Measurement 21 1) Measure for this Item shall be per each Legend removed. 22 b. Payment 23 1) The work performed and materials furnished in accordance with this Item 24 and measured as provided under"Measurement'shall be paid for at the 25 unit price bid per linear foot of"Remove Legend"performed for: 26 a) Various types 27 b) Various applications 28 c. The price bid shall include: 29 1) Removal of Pavement Markings 30 2) Clean-up 31 1.3 REFERENCES 32 A. Reference Standards 33 1. Reference standards cited in this Specification refer to the current reference 34 standard published at the time of the latest revision date logged at the end of this 35 Specification,unless a date is specifically cited. 36 2. Texas Manual on Uniform Traffic Control Devices(MUTCD).201.1 Edition 37 a. Part 3,Markings 38 3. American Association of State Highway and Transportation Officials AASHTO) 39 a. Standard Specification for Glass Beads Used in Pavement Markings,M 247-09 40 4. Federal Highway Administration(FHWA) 41 a. 23 CFR Part 655,FHWA Docket No.FHWA-2009-0139 42 5. Texas Department of Transportation(TxDOT) 43 a. DMS4200,Pavement Markers(Reflectorized) -- 44 b. DMS4300,Traffic Buttons 45 c. DMS-8220,Hot Applied Thermoplastic 46 d. DMS-8240,Permanent Prefabricated Pavement Markings 47 e. DMS-8241,Removable Prefabricated Pavement Markings CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,20I3 City Project No.100889 321723-4 PAVEMENT MARKINGS Page 4 of 11 1 f. DMS-8242,Temporary Flexible-Reflective Road Marker Tabs 2 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 3 1.5 SUBMITTALS 4 A. Submittals shall be in accordance with Section 0133 00, 5 B. All submittals shall be approved by the City prior to delivery and/or fabrication for 6 specials. _ 7 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 8 1.7 CLOSEOUT SUBMITTALS [NOT USED] 9 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 10 1.9 QUALITY ASSURANCE [NOT USED] 11 1.10 DELIVERY,STORAGE,AND HANDLING 12 A. Storage and Handling Requirements 13 1. The Contractor shall secure and maintain a location to store the material in 14 accordance with Section 0150 00. 15 1.11 FIELD [SITE] CONDITIONS [NOT USED] 16 .1.12 WARRANTY [NOT USED] 17 PART 2- PRODUCTS 18 2.1 OWNER-SUPPLIED PRODUCTS 19 A. New Products 20 1. Refer to Drawings to determine if there are owner-supplied products for the Project. 21 2.2 MATERIALS 22 A. Manufacturers 23 1. Only the manufacturers as listed in the City's Standard Products List will.be 24 considered as shown in Section 0160 00. 25 a. The manufacturer must comply with this Specification and related.Sections. 26 2. Any product that is not listed on the Standard Products List is considered a 27 substitution and shall be submitted in accordance with Section 0125 00. 28 B. Materials 29 1. Pavement Markings 30 a. Thermoplastic,hot applied,spray ®- 31 1) .Refer to Drawings and City Standard Detail Drawings for width of 32 longitudinal lines. 33 2) Product shall be especially compounded for traffic markings. 34 3) When placed on the roadway,the markings shall not be slippery when wet, 35 lift from pavement under normal weather conditions nor exhibit a tacky 36 exposed surface. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 321723-5 PAVEMENT MARKINGS Page 5 of 11 1 4) Cold ductility of the material shall permit normal road surface expansion 2 and contraction without chipping or cracking. 3 5) The markings shall retain their original color,dimensions and placement 4 under normal traffic conditions at road surface temperatures of 158 degrees 5 Fahrenheit and below. 6 6) Markings shall have uniform cross-section,clean edges,square ends and no 7 evidence of tracking. 8 7) The density and quality of the material shall be uniform throughout the 9 markings. 10 8) The thickness shall be uniform throughout the length and width of the I l markings. 12 9) The markings shall be 95 percent free of holes and voids,and free of 13 blisters for a minimum of 60 days after application. 14 10)The material shall not deteriorate by contact with sodium chloride, calcium 15 chloride or other chemicals used to prevent roadway ice or because of the 16 oil content of pavement markings or from oil droppings or other effects of 17 traffic. 18 11)The material shall not prohibit adhesion of other thermoplastic markings if, 19 at some future time,new markings are placed over existing material. 20 a) New material shall bond itself to the old line in such a manner that no 21 splitting or separation takes place. i 22 12)The markings placed on the roadway shall be completely retroreflective 23 both internally and externally with traffic beads and shall exhibit uniform 24 retro-directive reflectance. 25 13)Traffic beads 26 a) Manufactured from glass 27 b) Spherical in shape - 28 c) Essentially free of sharp angular particles 29 d) Essentially free of particles showing cloudiness, surface scoring or 30 surface scratching 31 e) Water white in color 32 f) Applied at a uniform rate 33 g) Meet or exceed Specifications shown in AASHTO Standard 34 Specification for Glass Beads Used in Pavement Markings,AASHTO 35 Designation:M 247-09. 36 b. Thermoplastic,hot applied,extruded 37 1) Product shall be especially compounded for traffic markings 38 2) When placed on the roadway,the markings shall not be slippery when wet, 39 lift from pavement under normal weather conditions nor exhibit a tacky 40 exposed surface. .� 41 3) Cold ductility of the material shall permit normal road surface expansion 42 and contraction without chipping or cracking. 43 4) The markings shall retain their original color,dimensions and placement IBM 44 under normal traffic conditions at road surface temperatures of 158 degrees 45 Fahrenheit and below. 46 5) Markings shall have uniform cross-section,clean edges,square ends and no 47 evidence of tracking. 48 6) The density and quality of the material shall be uniform throughout the 49 markings. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 321723-6 PAVEMENT MARKINGS Page 6 of 11 1 7) The thickness shall be uniform throughout the length and width of the 2 markings. 3 8) The markings shall be 95 percent free of holes and voids,and free of 4 blisters for a minimum of 60 days after application. 5 9) The minimum thickness of the marking,as measured above the plane 6 formed by the pavement surface,shall not be less than 1/8 inch in the center 7 of the marking and 3/32 inch at a distance of/z inch from the edge. 8 10) Maximum thickness shall be 3/16 inch. 9 11) The material shall not deteriorate by contact with sodium chloride,calcium 10 chloride or other chemicals used to prevent roadway ice or because of the 11 oil content of pavement markings or from oil droppings or other effects of 12 traffic. 13 12) The material shall not prohibit adhesion of other thermoplastic markings if, 14 at some future time,new markings are placed over existing material.. New 15 material shall bond itself to the old line in such a manner that no splitting or 16 separation takes place. 17 13) The markings placed on the roadway shall be completely retroreflective 18 both internally and externally with traffic beads and shall exhibit uniform 19 retro-directive reflectance. 20 14) Traffic beads 21 a) Manufactured from glass 22 b) Spherical in shape 23 c) Essentially free of sharp angular particles 24 d) Essentially free of particles showing cloudiness,surface scoring or 25 surface scratching 26 e) Water white in color 27 f) .Applied at a uniform rate 28 g) Meet or exceed Specifications shown in AAS.HTO Standard 29 Specification for Glass Beads Used in Pavement Markings,AASHTO 30 Designation:M 247-09. 31 c. Preformed Polymer Tape , 32 1) Material shall meet or exceed the Specifications for SWARCO Director 35, 33 3M High Performance Tape Series 3801 ES,or approved equal. 34 d. Preformed Heat-Activated Thermoplastic Tape �. 35 1) Material shall meet or exceed the Specifications for HOT Tape Brand 0.125 36 mil preformed thermoplastic or approved equal. 37 2. Raised Markers 38 a. Markers shall meet the requirements of the Texas Manual on Uniform Traffic 39 Control Devices. 40 b. Non-reflective markers shall be Type Y(yellow body)and Type W(white 41 body)round ceramic markers and shall meet or exceed the TxDOT 42 Specification DMS-4300. 43 c. The reflective markers shall be plastic,meet or exceed the TxDOT 44 Specification DMS-4200 for high-volume retroreflective raised markers and be 45 available in the following types: 46 1) Type I-C,white body, 1 face reflects white 47 2) Type II-A-A,yellow body,2 faces reflect amber 48 3) Type.R-C-R,white body, 1 face reflects white,the other red 49 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 321723-7 PAVEMENT MARKINGS Page 7 of 11 1 3. Work Zone Markings 2 a. Tabs 3 1) Temporary flexible-reflective roadway marker tabs shall meet requirements 4 of TxDOT DMS-8242,"Temporary Flexible-Reflective Road Marker 5 Tabs." 6 2) Removable markings shall not be used to simulate edge lines. 7 3) No segment of roadway open to traffic shall remain without permanent 8 pavement markings for a period greater than 14 calendar days. 9 b. Raised Markers 10 1) All raised pavement markers shall meet the requirements of DMS-4200. 11 c. Striping 12 1) Work Zone striping shall meet or exceed the TxDOT Specification DMS- 13 8200. 14 2.3 ACCESSORIES [NOT USED] 15 2.4 SOURCE QUALITY CONTROL 16 A. Performance 17 1. Minimum maintained retroreflectivity levels for longitudinal markings shall meet 18 the requirements detailed in the table below for a minimum of 30 calendar days. Posted Speed m h :530 35-50 >55 _ 2-lane roads with centerline n/a 100 250 markings only(1 All other roads 2 n/a 50 100 19 (1)Measured at standard 30-m geometry in units ofmcd/m/lux. 20 (2)Exceptions: 21. A When raised reflective pavement markings(RRPMs)supplement or substitute for a �. 22 longitudinal line,minimum pavement marking retroreflectivity levels are not applicable as 23 long as the RRPMs are maintained so that at least 3 are visible from any position along that 24 line during nighttime conditions. 25 B.When continuous roadway lighting assures that the markings are visible,minimum 26 pavement marking retroreflectivity levels are not applicable. 27 PART 3- EXECUTION 28 3.1 EXAMINATION[NOT USED] 29 3.2 PREPARATION 30 A. Pavement Conditions 31 1. Roadway surfaces shall be free of dirt,grease,loose and/or flaking existing 32 markings and other forms of contamination. 33 2. New Portland cement concrete surfaces shall be cleaned sufficiently to remove the 34 curing membrane. 35 3. Pavement to which material is to be applied shall be completely dry. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 321723-8 PAVEMENT MARKINGS Page 8 of 11 1 4. Pavement shall be considered dry,if,on a sunny day after observation for 15 2 minutes,no condensation develops on the underside of a 1 square foot piece of ..� 3 clear plastic that has been placed on the pavement and weighted on the edges. 4 5. Equipment and methods used for surface preparation shall not damage the 5 pavement or present a hazard to motorists or pedestrians. �- 6 3.3 INSTALLATION 7 A. General 8 1. The materials shall be applied according to the manufacturer's recommendations. 9 2. Markings and markers shall be applied within temperature limits recommended by 10 the material manufacturer,and shall be applied on clean,dry pavement having a 11 surface temperature above 50 degrees Fahrenheit. 12 3. Markings that are not properly applied due to faulty application methods or being 13 placed in the wrong position or alignment shall be removed and replaced by the 14 Contractor at the Contractor's expense. If the mistake is such that it would be 15 confusing or hazardous to motorists,it shall be remedied the same day of 16 notification. Notification will be made by phone and confirmed by fax. Other ^- 17 mistakes shall be remedied within 5 days of written notification. 18 4. When markings are applied on roadways open to traffic, care will be taken to 19 ensure that proper safety precautions are followed,including the use of signs, 20 cones,barricades,flaggers,etc. 21 5. Freshly applied markings shall be protected from traffic damage and disfigurement. 22 6. Temperature of the material must be equal to the temperature of the road surface 23 before allowing traffic to travel on it. 24 B. Pavement Markings 25 1. Thermoplastic,hot applied,spray 26 a. This method shall be used to install and replace long lines—centerlines,lane 27 lines,edge lines,turn lanes,and dots. 28 b. Markings shall be applied at a 110 mil thickness. 29 c. Markings shall be applied at a 90 mil thickness when placed over existing 30 markings. 31 d. A sealer shall be used if concrete or asphalt is older than three(3)years. 32 e. Typical setting time shall be between 4 minutes and 10 minutes depending 33 upon the roadway surface temperature and the humidity factor. 34 f. Retroreflective raised markers shall be used to supplement the centerlines,lane 35 lines,and turn lanes. Refer to City Standard Detail.Drawings for placement. 36 g. Minimum retroreflectivity of markings shall meet or exceed values shown in 37 subparagraph 2A.A.1 of this Specification. 38 2. Thermoplastic,hot applied,extruded 39 a. This method shall be used to install and replace crosswalks and stop-lines. 40 b. Markings shall be applied at a 125 mil thickness. -� 41 c. Minimum retroreflectivity of markings shall meet or exceed values shown in 42 this Specification. 43 3. Preformed Polymer Tape -� 44 a. This method shall be used to install and replace crosswalks, stop-lines,and 45 legends. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 321723-9 PAVEMENT MARKINGS Page 9 of 11 I b. The applied marking shall adhere to the pavement surface with no slippage or 2 lifting and have square ends,straight lines and clean edges. 3 c. Minimum retroreflectivity of markings shall meet or exceed values shown in 4 this Specification. 5 4. Preformed Heat-Activated Thermoplastic Tape 6 a. This method shall be used to install and replace crosswalks,stop-lines,and 7 legends. 8 b. The applied marking shall adhere to the pavement surface with no slippage or 9 lifting and have square ends, straight lines and clean edges. 10 c. Minimum retroreflectivity of markings shall meet or exceed values shown in 11 this Specification. 12 C. Raised Markers 13 1. All permanent raised pavement markers on Portland Cement roadways shall be 14 installed with epoxy adhesive. Bituminous adhesive is not acceptable. 15 2. All permanent raised pavement markers on new asphalt roadways may be installed 16 with epoxy or bituminous adhesive. 17 3. A chalk line, chain or equivalent shall be used during layout to ensure that 18 individual markers are properly aligned. All markers shall be placed uniformly 19 along the line to achieve a smooth continuous appearance. 20 D. Work Zone Markings 21 1. Work shall be performed with as little disruption to traffic as possible. 22 2. Install longitudinal markings on pavement surfaces before opening to traffic. 23 3. Maintain lane alignment traffic control devices and operations until markings are 24 installed. 25 4. Install markings in proper alignment in accordance with the Texas MUTCD and as 26 shown on the Drawings. 27 5. Place standard longitudinal lines no sooner than 3 calendar days after the placement 28 of a surface treatment,unless otherwise shown.on the Drawings. 29 6. Place markings in proper alignment with the location of the final pavement 30 markings. 31 7. Do not use raised pavement markers for words,symbols,shapes,or diagonal or 32 transverse lines. 33 8. All markings shall be visible from a distance of 300 feet in daylight conditions and 34 from a distance of at least 160 feet in nighttime conditions, illuminated by low- 35 beam automobile headlight. 36 9. The daytime and nighttime reflected color of the markings must be distinctly white 37 or yellow. 38 10. The markings must exhibit uniform retroreflective characteristics. -� 39 11. Epoxy adhesives shall not be used to work zone markings. 40 3.4 REMOVALS 41 1. Pavement Marking and Marker Removal 42 a. The industry's best practice shall be used to remove existing pavement 43 markings and markers. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENT'S REPLACEMENT CONTRACT Revised November 22,2013 City Project No. 100889 321723-10 PAVEMENT MARKINGS Page 10 of 11 1 b. If the roadway is being damaged during the marker removal,Work shall be 2 halted until consultation with the City. *•� 3 c. Removals shall be done in such a matter that color and texture contrast of the 4 pavement surface will be held to a minimum. 5 d. Repair damage to asphaltic surfaces, such as spalling,shelling,etc.,greater than 6 1/a inch in depth resulting from the removal of pavement markings and markers. 7 Driveway patch asphalt emulsion may be broom applied to reseal damage to 8 asphaltic surfaces. 9 e. Dispose of markers in accordance with federal, state,and local regulations. 1.0 f. Use any of the following methods unless otherwise shown on the Drawings. 11 1) Surface Treatment Method 12 a) Apply surface treatment at rates shown on the Drawings or as directed. ' 13 Place a surface treatment a minimum of 2 feet wide to cover the 14 existing marking. 15 b) Place a surface treatment,thin overlay,or microsurfacing a minimum 16 of 1 lane in width in areas where directional changes of traffic are 17 involved or in other areas as directed by the City. 18 2) Burn Method 19 a) Use an approved burning method. 20 b) For thermoplastic pavement markings or prefabricated pavement 21 markings,heat may be applied to remove the bulk of the marking .. 22 material prior to blast cleaning. 23 c) When using beat,avoid spalling pavement surfaces. 24 d) Sweeping or light blast cleaning may be used to remove minor residue. 25 3) Blasting Method 26 a) Use a blasting method such as water blasting,abrasive blasting,water 27 abrasive blasting, shot blasting,slurry blasting,water-injected abrasive 28 blasting,or brush blasting as approved. 29 b) Remove pavement markings on concrete surfaces by a blasting method 30 only. 31 4) .Mechanical Method 32 a) Use any mechanical method except grinding. 33 b) Flail milling is acceptable in the removal of markings on asphalt and 34 concrete surfaces. 35 2. If a location is to be paved over,no additional compensation will be allowed for 36 marking or marker removal. 37 3.5 REPAIR/RESTORATION [NOT USED] �.. 38 3.6 RE-INSTALLATION [NOT USED] 39 3.7 FIELD QUALITY CONTROL 40 A. All lines must have clean edges, square ends,and be uniform cross-section. 41 B. The density and quality of markings shall be uniform throughout their thickness. 42 C. The applied markings shall have no more than 5 percent,by area,of holes or voids and 43 shall be free of blisters. - CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT �. Revised November 22,2013 City Project No. 100889 321723-11 PAVEMENT MARKINGS Page 1 I of 11 1 3.8 SYSTEM STARTUP [NOT USED] 2 3.9 ADJUSTING [NOT USED] 3 3.10 CLEANING 4 A. Contractor shall clean up and remove all loose material resulting from construction 5 operations. 6 3.11 CLOSEOUT ACTIVITIES [NOT USED] 7 3.12 PROTECTION[NOT USED] 8 3.13 MAINTENANCE [NOT USED] 9 3.14 ATTACHMENTS [NOT USED] 10 END OF SECTION �' 11 Revision Log DATE NAME SUMMARY OF CHANGE 11/22/13 S.Arnold Removed paint type marldng,updated references,added sealer language 12 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 329119-1 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page I of 3 1 SECTION 32 9119 2 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS 3 PART1- GENERAL 4 1.1 SUMMARY -- 5 A. Section Includes: 6 1. Furnish and place topsoil to the depths and on the areas shown on the Drawings. 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Topsoil Placement,Water Services-The topsoil placement work covered by 9 these Specifications is included in the unit bid price of the appropriate water 10 service to be installed.All topsoil placement as specified below is considered I l subsidiary to the appropriate water service bid item and specified in"Water 12 Services 1-inch to 2-inch"(33-12-10). ,.� 13 C. Related Specification Sections include but are not necessarily limited to 14 1. Division 0-Bidding Requirements,Contract Forms,and Conditions of the Contract 15 2. Division 1 -General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment "-" 18 1, Measurement 19 a. Measurement for this Item shall be by cubic yard of Topsoil in place. 20 2. Payment 21 a. The work performed and materials furnished in accordance with this Item and 22 measured as provided under"Measurement"will be paid for at the unit price 23 bid per cubic yard of Topsoil. -- 24 b. All excavation required by this Item in cut sections shall be measured in 25 accordance with provisions for the various excavation items involved with the 26 provision that excavation will be measured and paid for once,regardless of the 27 manipulations involved. 28 3. The price bid shall include: 29 a. Furnishing Topsoil 30 b. Loading 31 c. Hauling 32 d. Placing 33 1.3 REFERENCES [NOT USED] 34 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] -- 35 1.5 ACTION SUBMITTALS [NOT USED] 36 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 37 1.7 CLOSEOUT SUBMITTALS [NOT USED] 38 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 39 1.9 QUALITY ASSURANCE [NOT USED] CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project no. 100889 329119-2 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page 2 of 3 1 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] 3 1.12 WARRANTY[NOT USED] 4 PART 2- PRODUCTS 5 2.1 OWNER-FURNISHED [oR] OWNER SUPPLIEDPRODUCTS [NOT USED] 6 2.2 MATERIALS 7 A, Topsoil 8 1. Use easily cultivated,fertile topsoil that: 9 a. Is free from objectionable material including subsoil,weeds,clay lumps,non- 10 soil materials,roots,stumps or stones larger than 1.5 inches I 1 b. Has a high resistance to erosion 12 c. Is able to support plant growth 13 2. Secure topsoil from approved sources. 14 3. Topsoil is subject to testing by the City. 15 4. pH: 5.5 to 8.5. 16 5. Liquid Limit: 50 or less , 17 6. Plasticity Index:20 or less 18 7. Gradation:maximum of 1.0 percent passing No. 200 sieve 19 B. Water: Clean and free of industrial wastes and other substances harmful to the growth 20 of vegetation 21 2.3 ACCESSORIES [NOT USED] 22 2.4 SOURCE QUALITY CONTROL [NOT USED] 23 PART 3- EXECUTION 24 3.1 INSTALLERS [NOT USED] 25 3.2 EXAMINATION[NOT USED] 26 3.3 PREPARATION [NOT USED] 27 3.4 INSTALLATION 28 A. Finishing of Parkways 29 1. Smoothly shape parkways,shoulders,slopes,and ditches. 30 2. Cut parkways to finish grade prior to the placing of any improvements in or 31 adjacent to the roadway. 32 3. In the event that unsuitable material for parkways is encountered,extend the depth 33 of excavation in the parkways 6 inches and backfill with top soil. 34 4. Make standard parkway grade perpendicular to and draining to the curb line. 35 a. Minimum: 1/4 inch per foot 36 b. Maximum: 4:1 37 c. City may approve variations from these requirements in special cases. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project no. 100889 329119-3 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page 3 of 3 1 5. Whenever the adjacent property is lower than the design curb grade and runoff 2 drains away from the street,the parkway grade must be set level with the top of the 3 curb. 4 6. The design grade from the parkway extends to the back of the walk line. 5 7. From that point(behind the walk),the grade may slope up or down at maximum 6 slope of 4:1. 7 B. Placing of Topsoil 8 1. Spread the topsoil to a uniform loose cover at the thickness specified. 9 2. Place and shape the topsoil as directed. 10 3. Hand rake finish a minimum of 5 feet from all flatwork. 11 4. Tamp the topsoil with a light roller or other suitable equipment. 12 3.5 REPAUVRIESTORATION] [NOT USED] 13 3.6 RE-INSTALLATION [NOT USED] 14 3.7 FIELD QUALITY CONTROL [NOT USED] 15 3.8 SYSTEM STARTUP [NOT USED] 16 3.9 ADJUSTING [NOT USED] 17 3.10 CLEANING [NOT USED] 18 3.11 CLOSEOUT ACTIVITIES [NOT USED] 19 3.12 PROTECTION [NOT USED] 20 3.13 MAINTENANCE [NOT USED] 21 3.14 ATTACHMENTS [NOT USED] 22 END OF SECTION 23 Revision Log DATE NAME SUMMARY OF CHANGE 24 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project no,100889 329213-1 HYDROMULCH.ING,SEEDING AND SODDING w. Page I of 8 .. 1 SECTION 32 92 13 2 HYDROMULCHING, SEEDING AND SODDING 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Furnishing and.installing grass sod and permanent seeding as shown on Drawings, 7 or as directed. "-" 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. Hydro-mulching,Seeding and Sodding—The hydro-mulching,seeding and/or 10 sod placement work covered by these Specifications is included in the unit bid 11 price of the appropriate water service to be installed.All hydro-mulching, 12 seeding and/or sod placement as specified below is considered subsidiary to 13 the appropriate water service bid item and specified in"Water Services 1-inch 14 to 2-inch"(33-12-10). 15 C. Related Specification Sections include,but are not necessarily limited to: 16 1. Division 0-Bidding Requirements, Contract Forms,and Conditions of the Contract 17 2. Division 1 -General Requirements 18 3. Section 32 91 19—Topsoil Placement and Finishing of Parkways 19 1.2 PRICE AND PAYMENT PROCEDURES 20 A. Measurement and Payment w- 21 1. Block Sod Placement 22 a. Measurement 23 1) Measurement for this Item shall be by the square yard of Block Sod placed. 24 b. Payment 25 1) The work performed and materials furnished in accordance with this'Item 26 and measured as provided under"Measurement"will be paid for at the unit 27 price bid per square yard of Block Sod placed. 28 c. The price bid shall include: 29 1) Furnishing and placing all sod 30 2) Rolling and tamping 31 3) Watering(until established) 32 4) Disposal of surplus materials 33 2. Seeding 34 a. Measurement 35 1) Measurement for this Item shall be by the square yard of Seed spread. 36 b. Payment 37 1) The work performed and materials furnished in accordance with this Item 38 and measured as provided under"Measurement"will be paid for at the unit 39 price bid per square yard of Seed placed for various installation methods. 40 c. The price bid shall include: 41 1) Furnishing and placing all Seed 42 2) Furnishing and applying water for seed fertilizer 43 3) Slurry and hydraulic mulching CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 329213-2 HYDROMULCHING,SEEDING AND SODDING Page 2 of 8 1 4) Fertilizer 2 5) Watering and mowing(until established) ,.. 3 6) Disposal of surplus materials 4 3. Mowing 5 a. Measurement 6 1) Measurement for this Item shall per each. 7 b. Payment 8 1) The work performed and materials furnished in accordance with this Item 9 and measured as provided under"Measurement"will be paid for at the unit 10 price bid per each. 11 1.3 REFERENCES [NOT USED] 12 1A ADMINISTRATIVE REQUIREMENTS [NOT USED] 13 1.5 ACTION SUBMITTALS [NOT USED] 14 1.6 INFORMATIONAL SUBMITTALS 15 A. Seed 16 1. Vendors' certification that seeds Meet Texas State seed law including: 17 a. Testing and labeling for pure live seed(PLS) 18 b. Name and type of seed 19 2. All seed shall be tested in a laboratory with certified results presented to the City in 20 writing,prior to planting. 21 3. All seed to be of the previous season's crop and the date on the container shall be 22 within 12 months of the seeding date. 23 1.7 CLOSEOUT SUBMITTALS [NOT USED] 24 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 25 1.9 QUALITY ASSURANCE [NOT USED] 26 1.10 DELIVERY,STORAGE,AND HANDLING 27 A. Block Sod 28 1. Protect from exposure to wind, sun and freezing. _. 29 2. Keep stacked sod moist. 30 B. Seed 31 1. If using native grass or wildflower seed,seed must have been harvested within 100 32 miles of the construction site. 33 2. Each species of seed shall be supplied.in a separate,labeled container for 34 acceptance by the City. 35 C. Fertilizer 36 1. Provide fertilizer labeled with the analysis. 37 2. Conform to Texas fertilizer law. 38 1.11 FIELD [SITE] CONDITIONS [NOT USED] 39 1.12 WARRANTY [NOT USED] CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 329213-3 HYDROMULCHING,SEEDING AND SODDING Page 3 of 8 1 PART 2- PRODUCTS [NOT USED] 2 2.1 OWNER-FURNISHED PRODUCTS [NOT USED] 3 2.2 MATERIALS AND EQUIPMENT " 4 A. Materials 5 1. Block Sod 6 a. Sod Varieties(match existing if applicable) 7 1) "Stenotaphrum secundatum"(St.Augustine grass) 8 2) "Cynodon dactylon"(Common Bermudagrass) 9 3) "Buchloe dactyloides"(Buffalograss) 10 4) an approved hybrid of Common Bermudagrass 11 5) or an approved Zoysiagrass 12 b. Sod must contain stolons, leaf blades,rhizomes and roots. 13 c. Sod shall be alive,healthy and free of insects, disease,stones,undesirable 14 foreign materials and weeds and grasses deleterious to its growth or which 15 might affect its subsistence or hardiness when transplanted. 16 d. Minimum sod thickness:3/4 inch. 17 e. Maximum grass height: 2 inches 18 f. Acceptable growing beds 19 1) St. Augustine grass sod: clay or clay loam topsoil 20 2) Bermuda grasses and zoysia grasses: sand or sandy loam soils 21 g. Dimensions 22 1) Machine cut to uniform soil thickness. 23 2) Sod shall be of equal width and of a size that permits the sod to be lifted, 24 handled and rolled without breaking. 25 h. Broken or torn sod or sod with uneven ends shall be rejected. 26 2. Seed 27 a. General 28 1) Plant all seed at rates based on pure live seed(PLS) 29 a) Pure Live Seed(PLS)determined using the formula: 30 (1) Percent Pure Live Seed=Percent Purity x[(Percent Germination+ 31 Percent Firm or Hard Seed)+ 100] ,.� 32 2) Availability of Seed 33 a) Substitution of individual seed types due to lack of availability may be 34 permitted by the City at the time of planting. 35 b) Notify the City prior to bidding of difficulties locating certain species. 36 3) Weed seed 37 a) Not exceed ten percent by weight of the total of pure live seed(PLS) 38 and other material in the mixture 39 b) Seed not allowed: 40 (1) Johnsongrass 41 (2) Nutgrass seed 42 4) Harvest seed within 1-year prior to planting 43 b. Non-native Grass Seed 44 1) Plant between April 15 and September 10 45 Lbs. Common Name Botanical Name Purity Germination PLS/Acre (percent) (percent) 25 Bermuda(unhulled) cynodon dactylon 85 90 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 329213-4 HYDROMULCHING,SEEDING AND SODDING Page 4 of 8 75 Bermuda(huffed) cynodon dactylon 95 90 1 � 2 2) Plant between September 10 and April 15 3 Lbs. Common Name Botanical Name Purity Germination PLS/Acre (percent) (percent) 220 Rye Grass folium multii lorum 85 90 75 Bermuda(unhulled) cynodon dactylon 95 90 4 5 c. Native Grass Seed 6 1) Plant between February 1 and October 1. 7 Lbs.PLS/Acre Common Name Botanical Name 1.6 Green Sprangletop Leptochloa dubia 5.5 Sideoats Grama* Bouteloua curtipendula . 3.7 Little Bluestem* Schizachyrium scoparium 17.0 Buffalograss Buchloe dactyloides 1.8 Indian Grass* Sorghastrum nutans 0.5 Sand Lovegrass* Eragrostis trichodes 6.0 Big Bluestem Andropogon gerardii 8.0 Eastern Grama Tripscacum dactyloides 1.2 Blue Grama Bouteloua gracilis 1.8 Switchgrass Panicum virgatum 10.0 Prairie Wildrye* Elymus canadensis 8 9 d. Wildflower Seed go 10 t) Plant between the following: 11 a) March 5 and May 31 12 b) September 1 and December 1 Fm 13 Lbs.PLS/Acre Common Name Botanical Name 3.0 Bush Sunflower Simia calva 5.0 Butterfly Weed Asclepias tuberosa 2.0 Clasping Coneflower* Rudbeckia amplexicaulis 3.0 Golden-Wave Coreopsis basalis 13.4 Illinois Bundleflower Desmanthus illinoensis 13.6 Partridge Pea Cassiafasciculala 2.0 Prairie Verbena Verbena bipinnat fda 8.0 Texas Yellow Star Lindheimeri tezana 8.0 Winecup Callirhoe involcrata 2.0 Black-eyed Susan Rudbeckia hirta 18.0 Cutleaf Daisy Engelmannia pinn atifida 2.0 Obedient Plant Physostegia intermedia 3.0 Pitcher Sage Salvia azurea 2.0 Plains Coreopsis Coreopsis tinctoria 8.0 Scarlet Sage Salvia coccinea 14 *not to be planted within ten feet of a road or parking lot or within three feet of a 15 walkway 16 17 e. Temporary Erosion Control Seed 18 1) Consist of the sowing of cool season plant seeds. 19 3. Mulch CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 329213-5 HYDROMULCHING,SEEDING AND SODDING Page 5 of 8 1 a. For use with conventional mechanical or hydraulic planting of seed. 2 b. Wood cellulose fiber produced from virgin wood or recycled paper-by-products 3 (waste products from paper mills or recycled newspaper). 4 c. No growth or germination inhibiting factors. 5 d. No more than ten percent moisture,air dry weight basis. 6 e. Additives: binder in powder form. 7 f. Form a strong moisture retaining mat. 8 4. Fertilizer 9 a. Acceptable condition for distribution 10 b. Applied uniformly over the planted area 11 c. Analysis 12 1) 16-20-0 13 2) 16-8-8 14 d. Fertilizer rate: 15 1) Not required for wildflower seeding 16 2) Newly established seeding areas- 100 pounds of nitrogen per acre 17 3) Established seeding areas- 150 pounds of nitrogen per acre 18 5. Topsoil: See Section 32 9119. 19 6. Water: clean and free of industrial wastes or other substances harmful to the 20 germination of the seed or to the growth of the vegetation. 21 7. Soil Retention Blanket 22 a. "Curlex I"from American Excelsior,900 Ave.H East,Post Office Box 5624, 23 Arlington,Texas 76001, 1-800-777-SOIL or approved equal. 24 25 2.3 ACCESSORIES [NOT USED] 26 2.4 SOURCE QUALITY CONTROL [NOT USED] 27 PART 3- EXECUTION [NOT USED] 28 3.1 INSTALLERS [NOT USED] 29 3.2 EXAMNATION [NOT USED] 30 3.3 PREPARATION 31 A. Surface Preparation: clear surface of all material including: 32 1. Stumps, stones,and other objects larger than one inch. 33 2. Roots,brush,wire, stakes,etc. 34 3. Any objects that may interfere with seeding or maintenance. 35 B. Tilling 36 1. Compacted areas:till 1 inch deep 37 2. Areas sloped greater than 3:1:run a tractor parallel to slope to provide less 38 seed/water run-off 39 3. Areas near trees: Do not till deeper than 1/2 inch inside"drip line"of trees. 40 3.4 INSTALLATION 41 A. .Block Sodding 42 1. General CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 329213-6 HYDROMULCHING,SEEDING AND SODDING Page 6 of 8 ' 1 a. Place sod between curb and walk and on terraces that is the same type grass as 2 adjacent grass or existing lawn. _ 3 b. Plant between the average last freeze date in the spring and 6 weeks prior to the 4 average first freeze in the fall. 5 2. Installation 6 a. Plant sod specified after the area has been completed to the lines and grades 7 shown on the Drawings with 6 inches of topsoil. 8 b. Use care to retain native soil on the roots of the sod during the process of .. 9 excavating,hauling and planting. 1.0 c. Keep sod material moist from the time it is dug until planted. 11 d. Place sod so that the entire area designated for sodding is covered. 12 e. Fill voids left in the solid sodding with additional sod and tamp. 13 f. Roll and tamp sod so that sod is in complete contact with topsoil at a uniform 14 slope, 15 g. Peg sod with wooden pegs(or wire staple)driven through the sod block to the 16 firm earth in areas that may slide due to the height or slope of the surface or 17 nature of the soil. 18 3. Watering and Finishing 19 a. Furnish water as an ancillary cost to Contractor by means of temporary 20 metering/irrigation,water truck or by any other method necessary to achieve 21 an acceptable stand of turf as defined in 3.13.B. -- 22 b. Thoroughly water sod immediately after planted. 23 c. Water until established. 24 d. Generally,an amount of water that is equal to the average amount of rainfall ., 25 plus 1/2 inch per week should be applied until accepted. If applicable, plant 26 large areas by irrigation zones to ensure areas are watered as soon as they are 27 planted. 28 B. Seeding 29 1. General 30 a. Seed only those areas indicated on the Drawings and areas disturbed by 31 construction. 32 b. Mark each area to be seeded in the field prior to seeding for City approval. 33 2. Broadcast Seeding 34 a. Broadcast seed in 2 directions at right angles to each other. 35 b. Harrow or rake lightly to cover seed. 36 c. Never cover seed with more soil than twice its diameter. 37 d. For wildflower plantings: 38 1) Scalp existing grasses to 1 inch 39 2) Remove grass clippings,so seed can make contact with the soil. 40 3. Mechanically Seeding(Drilling): 41 a. Uniformly distribute seed over the areas shown on the Drawings or as directed. 42 b. All varieties of seed and fertilizer may be distributed at the same time provided 43 that each component is uniformly applied at the specified rate. 44 c. Drill seed at a depth of 1/4 inch to 3/8 inch utilizing a pasture or rangeland type 45 drill. 46 d. Drill on the contour of slopes 47 e. After planting roll with a roller integral to the seed drill,or a corrugated roller 48 of the "Cultipacker"type. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 329213-7 HYDROMULCHING,SEEDING AND SODDING Page 7 of 8 1 f. Roll slope areas on the contour. 2 4. Hydromulching 3 a. Mixing: Seed,mulch,fertilizer and water may be mixed provided that: 4 1) Mixture is uniformly suspended to form a homogenous slurry. °- 5 2) Mixture forms a blotter-like ground cover impregnated uniformly with 6 grass seed. 7 3) Mixture is applied within 30 minutes after placed in the equipment. 8 b. Placing 9 1) Uniformly distribute in the quantity specified over the areas shown on the 10 Drawings or as directed. 11 5. Fertilizing:uniformly apply fertilizer over seeded area. 12 6. Watering 13 a. Fumish water by means of temporary metering/irrigation,water truck or by �. 14 any other method necessary to achieve an acceptable stand of turf as defined in 15 3.13.B. 16 b. Water soil to a minimum depth of 4 inches within 48 hours of seeding. 17 c. Water as direct by the City at least twice daily for 14 days after seeding in such 18 a manner as to prevent washing of the slopes or dislodgement of the seed. 19 d. Water until final acceptance. 20 e. Generally, an amount of water that is equal to the average amount of rainfall 21 plus 1/2 inch per week should be applied until accepted. 22 3.5 REPAIR/RESTORATION[NOT USED] 23 3.6 RE-INSTALLATION [NOT USED] 24 3.7 FIELD QUALITY CONTROL[NOT USED] 25 3.8 SYSTEM STARTUP [NOT USED] 26 3.9 ADJUSTING [NOT USED] 27 3.10 CLEANING[NOT USED] 28 3.11 CLOSEOUT ACTIVITIES 29 3.12 PROTECTION [NOT USED] 30 3.13 MAINTENANCE 31 A. Block Sodding 32 1. Water and mow sod until completion and final acceptance of the Project or as 33 directed by the City. 34 2. Sod shall not be considered finally accepted until the sod has started to peg down 35 (roots growing into the soil)and is free from dead blocks of sod. 36 B. Seeding 37 1. Water and mow sod until completion and final acceptance of the Project or as 38 directed by the City. 39 2. Maintain the seeded area until each of the following is achieved: 40 a. Vegetation is evenly distributed 41 b. Vegetation is free from bare areas 42 3. Turf will be accepted once fully established. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No. 100889 329213-8 HYDROMULCHING,SEEDING AND SODDING Page 8 of 8 1 a. Seeded area must have 100 percent growth to a height of 3 inches with I mow 2 cycle performed by the Contractor prior to consideration of acceptance by the 3 City. 4 C. Rejection 5 1. City may reject block sod or seeded area on the basis of weed populations. 6 3.14 ATTACHMENTS [NOT USED] 7 END OF SECTION 8 Revision Log DATE NAME SUMMARY OF CHANGE 9 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised December 20,2012 City Project No.100889 331210-1 WATER SERVICES 1-INCH TO 2-INCH Page 1 of 17 SECTION 33 12 10 WATER SERVICES 1-INCH TO 2-INCH PART1- GENERAL 1.1 SUMMARY A. Section.Includes: 1. Lead-free 1-inch to 2-inch water service lines from the water main to the right-of- way,fittings and water meter boxes complete in place,as shown on the Drawings, directed by the Engineer,and specified herein for: a. New Water Service b. New Water Service(Bored) c. Water Meter Service Relocate d. Private Water Service B. Deviations from this City of Fort Worth Standard Specification 1. Water Services—All water services for this contract have been categorized by service size,service length and surface restoration.The water service bid items in the proposal are for removing existing services,including corporation at main,and strapping the appropriate tap saddle over the remaining hole in mains of all sizes and pipe materials up to and including 12-inch in diameter. n The measurement for the services shall be from the tap of the main to the existing meter,unless otherwise designated by the Engineer.The payment for each service shall be for the service size,service length and surface restoration of the appropriate bid item.The price bid shall include all items as specified below,as well as,reconnection of the meter/private service,the surface restoration of street paving,top soil and grass as necessary to replace a complete water service.The surface restoration exceptions,which will be paid separately at the unit price bid,are 4-inch Concrete Sidewalk(32-13-20)and 6- inch Concrete Driveway(32-13-20).The unit price bid for water services includes the embedment and backfill as specified "Utility Trench Excavation, Embedment and Backfill'(33-05-10),the exception will be for"Imported Embedment/Backfill CLSM".The"Imported Embedment/Backfill CLSM" bid item will be paid for at the cubic yard bid price when required and W directed by the Engineer. 2. Water Service Relocation—When necessary to relocate the meter/service(i.e. out of driveways or splitting bullhead services),the service reconnection will be paid separately at the unit price bid per linear foot of"Private Water Service,Relocation'. 3. Removal of Existing Lead Service—As specified in"Summary of Work"(01- 11-00) and "Utility Removal/Abandonment"(0241-14)of these Specifications,the Water Service Bid Item will include the removal and disposal of the existing lead service line to be replaced. C. Products Installed but not Furnished Under this Section 1. Water meters for various sizes D. Related Specification Sections include,but are not necessarily limited to: CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 aw 331210-2 WATER SERVICES 1-INCH TO 2-INCH Page 2 of 17 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 2. Division I—General Requirements 3. Section 33 04 40—Cleaning and Acceptance Testing of Water Mains 4. Section 33 05 10—Utility Trench Excavation,Embedment and Backfill 5. Section 33 12 25—Connection to Existing Water Mains 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1, New Water Service a. Measurement 1) Measurement for this Item shall be per each new"Water Service"complete in place from the tap of the main to the installation of the meter box and associated appurtenances where the service line is installed by open cut = construction. b. Payment 1) The work performed and materials furnished in accordance with this Item and measured as provided under"Measurement"will be paid for at the unit "- price bid per each"Water Service"installed for: a) Various sizes c. The price bid shall include: ' 1) Furnishing and installing New Service Line as specified by the Drawings 2) Submitting product data 3) Tapping saddle = 4) Corporation stop 5) Curb stop 6) Fittings = 7) Service line installed by open cut 8) Connection to meter 9) Meter Box and Lid _ 10)Pavement removal 11)Excavation 12)Hauling 13)Disposal of excess material 14) Surface Restoration associated with Meter Box installation and connection, excluding grass(seeding,sodding or hydro-mulch paid separately) 15) Clean-up 16)Disinfection 17) Testing 2. New Bored Water Service a. Measurement 1) Measurement for this Item shall be per each new Water Service complete in place from the tap of the main to the installation of the meter box and = associated appurtenances where the service line is installed by trenchless method. b. Payment 1) The work performed and materials furnished in accordance with this Item and measured as provided under"Measurement"will be paid for at the unit price bid per each"Bored Water Service"installed for: CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT a. Revised February 14,2017 CityProject No.100889 331210-3 WATER SERVICES 1-INCH TO 2-INCH Page 3 of 17 a) Various sizes c. The price bid shall include: 1) Submitting product data 2) Tapping saddle 3) Corporation stop 4) Curb stop 5) Fittings 6) Service line installed by trenchless method 7) Connection to meter 8) .Meter Box and Lid 9) Pavement removal 10)Excavation 11)Hauling 12)Disposal of excess material 13) Surface restoration associated with Meter Box installation and connection, excluding grass(seeding,sodding or hydro-mulch paid separately) 14)Clean-up 15) Disinfection 16)Testing 3. Water Meter Service Reconnect a. Measurement 1) Measurement for this Item shall be per each Water Meter Service Reconnect complete in place from public service line connection to private service line connection. b. Payment 1) The work performed in conjunction with relocation of the meter,associated private service line,fittings and meter box 5 feet or less in any direction from centerline of existing meter location and the materials furnished in accordance with this Item will be paid for at the unit price bid per each "Water Meter Service,Reconnection"installed for: a) Various size of services c. The price bid shall include: 1) Private service line 2) Fittings 3) Private connection to water meter 4) Connection to existing private service line �- 5) Cut and crimp of existing service 6) Removal and Disposal or Salvage of existing 2-inch or smaller water meter, as directed by City 7) Pavement removal 8) Excavation 9) Hauling 10)Disposal of excess material 11) Surface restoration for area disturbed for installation of meter box, excluding grass(seeding,sodding or hydro-mulch paid separately) 12)Clean-up 13)Cleaning 14) Disinfection 15) Testing CrrY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 331210-4 WATER SERVICES 1-INCH TO 2-INCH Page 4 of 17 4. Private Water Service Relocation a. Measurement 1) Measurement for this Item shall be per linear foot of Private Service relocation complete in place from the meter box to a connection to the existing service line on private property. �. b. Payment 1) The work performed in conjunction with Private Service Line installation where the meter and meter boxes are moved more than 5 feet in any direction from centerline of existing meter location and materials furnished in accordance with the Item and measured as provided under "Measurement"will be paid for at the unit price bid per linear foot of "Private Water Service"performed for: ®" a) Various service sizes c. The price bid shall include: 1) Obtaining appropriate permit 2) Obtaining Right of Entry 3) Submitting product data 4) Private service line 5) Fittings 6) Backflow preventer,check valve,and isolation valve relocation,if applicable 7) Connection to existing private service line 8) Pavement removal and replacement 9) Excavation 10)Hauling 1.1)Disposal of excess material 12) Surface restoration,excluding grass(seeding,sodding or hydro-mulch paid separately) 13)Clean-up 14)Cleaning 15)Disinfection 16)Testing 1.3 REFERENCES A. Definitions 1. New Service a. Installation of new 1-inch to 2-inch Water Service Line by open cut construction from the water main to the right-of-way, including corporation stop,curb stop,fittings and water meter boxes complete in place,as shown on the Drawings. 2. New Service(Bored) a. Installation of new 1-inch to 2-inch Water Service Line by trenchless construction method from the water main to the right-of-way,including corporation stop,curb stop,fittings and water meter boxes complete in place,as shown on the Drawings. 3. Meter Service Reconnection a. Relocation and reconnection of the private service line from an existing meter to be abandoned and a new meter installed that lies within 5 feet of the existing meter. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised Febnwy 14,2017 City Project No.100889 331210-5 WATER SERVICES I-INCH TO 2-INCH Page 5 of 17 4. Private Service Relocation a. Relocation and reconnection of private service line behind the water meter where the existing meter to be abandoned and the new meter installed is greater than 5 feet of the existing meter. A licensed plumber is required to relocate the private service. 5. Lead-free a. Lead-free pipes and plumbing fittings and fixtures shall contain less than 0.25 percent lead in accordance with the reduction of Lead in Drinking Water Act (P.L. 111-380). B. Reference Standards 1. Reference standards cited in this Specification refer to the current reference standard published at the time of the latest revision date logged at the end of this Specification,unless a date is specifically cited. 2. ASTM International(ASTM): a. A48, Standard Specification for Gray Iron Castings. b. A536, Standard Specification for Ductile Iron Castings. c. B88, Standard Specification for Seamless Copper Water Tube. d. B98, Standard Specification for Copper-Silicon Alloy Rod,Bar and Shapes. e. C131, Standard Specification for Resistance to Degradation of Small-Size ._ Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine. f. C150, Standard Specification for Portland Cement. g. C330, Standard Specification for Lightweight Aggregates for Structural Concrete. h. C857(RL), Standard Practice for Minimum Structural Design Loading for Underground Precast Concrete Utility Structures i. D883, Standard Terminology Relating to Plastics. j. D1693, Standard Test Method for Environmental Stress-Cracking of Ethylene Plastics 3. American Water Works Association(AWWA): a. C700,Cold-Water Meters-Displacement Type,Bronze Main'Case. b. C800,Underground Service Line Valves and Fittings. _. 4. NSF International(NSF): a. 61,Drinking Water System Components-Health Effects. 5. Reduction of Lead in Drinking Water Act a. Public Law 111-380(P.L. 111-380) 6. General Services Administration(GSA): a. RR F-621E,Frames,Covers,Gratings, Steps, Sump and Catch Basin,Manhole 1.4 ADMINISTRATIVE REQUIREMENTS A. Scheduling 1. Provide advance notice for service interruptions and meet requirements of Division 0 and Division 1. 1.5 SUBMITTALS A. Submittals shall be in accordance with Section 0133 00. B. All submittals shall be approved by the City prior to delivery. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 33 1210-6 WATER SERVICES 1-INCH TO 2-INCH Page 6 of 17 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS A. Product Data, if applicable: 1. Tapping Saddle 2. Corporation stop ^ 3. Curb Stop 4. Service Line .s. 5. Meter Box 6. Meter.Box Lid B. Certificates and Test Reports 1. Prior to shipment of any Water Service components,the manufacturer shall submit the following: a. A Certificate of Adequacy of Design stating that the components to be furnished comply with all regulatory requirements identified in this Section including: 1) The Reduction of Lead in Drinking Water Act(P.L. 111-380) 2) AWWA C800 3) NSF 61 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Qualifications 1. Manufacturers a. Water Services shall meet or exceed the latest revisions of AWWA C800,NSF 61,the Reduction of Lead in Drinking Water Act and shall meet or exceed the requirements of this Specification. 1.10 DELIVERY,STORAGE,AND HANDLING A. Storage and Handling Requirements 1. Protect all parts such that no damage or deterioration will occur during a prolonged delay from the time of shipment until installation is completed and the units and equipment are ready for operation. 2. Protect all.equipment and parts against any damage during a prolonged period at the site. 3. Prevent plastic and similar brittle items from being directly exposed to sunlight or extremes in temperature. 4. Secure and maintain a location to store the material in accordance with Section 01 6600, CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 331210-7 WATER SERVICES I-INCH TO 2-INCH Page 7 of 17 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2- PRODUCTS 2.1 OWNER-FURNISHED PRODUCTS A. Water meters for various sizes 2.2 EQUIPMENT,PRODUCT TYPES,AND MATERIALS A. Manufacturers 1. Only the manufacturers as listed on the City's Standard Products List will be ,m considered as shown in Section 0160 00. a. The manufacturer must comply with this Specification and related Sections. 2. Any product that is not listed on the Standard Products List is considered a �.. substitution and shall be submitted in accordance with Section 0125 00. 3. The Water Services and appurtenances shall be new and the product of a manufacturer regularly engaged in the manufacturing of Water Services and appurtenances having similar service and size. B. Description 1. Regulatory Requirements a. All materials shall conform to the Reduction of Lead in Drinldng Water Act(P.L. 111-380). This Act defines"Lead-free"for pipes and other appurtenances to be less than 0.25 percent lead. b. Water Services shall meet or exceed the latest revisions of AWWA C800 and shall meet or exceed the requirements of this Specification. c. All Water Services components in contact with potable water shall conform to -- the requirements of NSF 61. C. Materials/Design Criteria 1. Service Lines a. Provide Type K Copper Tubing per ASTM B88. b. Furnish in the annealed conditions,unless otherwise specified in the Contract Documents. 2. Service Couplings a. Fitting Ends 1) Flared Copper Tubing with thread dimensions per AWWA C800 2) Provide coupling nuts with a machined bearing skirt of a length equal to the tubing outer diameter(O.D.). b. Provide with hexagonal wrench grip compatible with the coupling size. c. Provide lead-free service couplings in accordance with the Reduction of Lead in Drinking Water Act. 3. Corporation stops a. Provide brass castings per AWWA C800 for: 1) Bodies 2) Plugs - 3) D washers CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 1.4,2017 City Project No.100889 331210-8 WATER SERVICES 1-INCH TO 2-INCH Page 8 of 17 4) Bottom nuts b. Machining and Finishing of Surfaces 1) Provide 1 %inch per foot or 0.1458 inch per inch f 0.007 inch per inch taper of the seating surfaces for the key and body. 2) Reduce large end of the tapered surface of the key in diameter by chamfer or turning for a distance that will bring the largest end of the seating surface of the key into the largest diameter of the seating surface of the body. 3) Relieve taper seat in the body on the small end. 4) Extend small end of the key there-through to prevent the wearing of a shoulder and facilitate proper seating of key. 5) Design key,key nut and washer such that if the key nut is tightened to failure point,the stem end of the key shall not fracture. 6) Design nut and stem to withstand a turning force on the nut of at least 3 times the necessary effort to properly seat the key without failure in any manner. 7) Port through corporation stop shall be full size to eliminate turbulence in the flow way. 8) Design stop for rotation about the axis of the flow passageway inside the following minimum circles in order to properly clear the tapping machine: a) Two 7/8-inch for 1-inch corporation stops b) Four 15/16-inch for 1 1/2-inch and 2-inch corporation stops = c. Provide lead-free corporation stops in accordance with the Reduction of Lead in Drinking Water Act. 4. Curb Stops = a. Provide brass castings per AWWA C800. b. Valve plugs shall be: 1) Cylinder type 2) Plug type,or 3) Ball type c. Incorporate full flow porting. d. Provide for full 360 degree plug rotation clockwise or counter-clockwise. e. Overall Length 1) 3-5/16 inch±1/8 inch for 1-inch diameter 2) 4-1/32 inch+9.32 for 1-inch diameter f. Cylindrical Plug Type 1) Provide O-ring seal at top and bottom. a) O-ring at top only is acceptable if bottom of curb stop body is closed. ~� 2) Seals shall be Buna N. 3) 1 O-ring seal shall surround the outlet port of the curb stop and act to effectively seal in the closed position. 4) The port in the plug shall provide a straight through,full size flow way, so shaped as to eliminate turbulence. 5) All waterways shall be smooth and free of burrs or rough areas. 6) Design the curb stop to provide ease and accuracy of operation and positive shut-off of water. g. Tapered Plug Type 1) Provide O-ring seal at top and bottom. 2) The tapered plug and cylindrical recess in the valve body shall be machined to match within approved manufacturing tolerances. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT .. Revised February 14,2017 City Project No.100889 331210-9 WATER SERVICES 1-INCH TO 2-INCH Page 9 of 17 3) Inlet and outlet ports shall be sealed by O-rings or combination Teflon U- shaped seal rings backed with O-rings. 4) The port in the plug shall provide a straight through,full size flow way,so shaped as to eliminate turbulence. 5) All waterways shall be smooth and free of burrs or rough areas. 6) Design the curb stop to provide ease and accuracy of operation and positive shut-off of water. h. Ball Plug Type 1) Provide double O-ring seals on the stem. 2) The ball shall seal against rubber rings mounted in the valve body at the inlet and outlet ports. 3) The ball shall be bronze with a smooth Teflon coating. 4) The port in the plug shall provide a straight through,full size flow way, so shaped as to eliminate turbulence. 5) All waterways shall be smooth and free of burrs or rough areas. i. Provide lead-free curb stops in accordance with the Reduction of Lead in Drinking Water Act. 5. Straight Adapters a. Brass castings and threads per AWWA C800 b. Provide lead-free straight adapters in accordance with the Reduction of Lead in Drinking Water Act. 6. Three Part Copper Unions a. Brass castings and threads per AWWA C800 b. Provide lead-free Three Part Copper Unions in accordance with the.Reduction of Lead in Drinking Water Act. 7. Straight Meter Couplings a. Brass castings per AWWA C800 b. Threads per AWWA C700 c. Tailpiece with outside iron pipe thread -� d. Chamfer corners on threaded end of meter nut. e. Machine inside and outside of tailpiece. f. Provide lead-free Straight Meter Couplings in accordance with the Reduction of Lead in Drinking Water Act. 8. Branch Connections a. Brass castings per AWWA C800 b. Inlet and outlet connections per AWWA C800 c. Provide lead-free branch connections in accordance with the Reduction of Lead in Drinking Water Act. •- 9. Service Saddles a. Castings 1) Brass or Nylon coated ductile iron castings per AWWA C800 2) Free of porosity with sharp edges removed 3) Saddle a) Form to fit firmly against side of maximum diameter of water main with approximately 180 degrees wrap around. 4) Outlet a) Design outlet boss for no thread distortion by bending moments. b) Tapped for taper threaded corporation stop conforming to AWWA C800. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 331210-10 WATER SERVICES 1-INCH TO 2-INCH r„ Page 10 of 17 b. Straps 1) Conform to ASTM B98. —w 2) Form flat to fit uniformly against the wall of the water main. 3) Shall be double straps 4) Rod diameter not less than 5/8 inch flattened to 1 inch on one side. ,.. 5) Straps shall be threaded 5/8 inch(11-NC-2A)for a distance such that%z inch remains after clamp is fully tightened on the pipe. 6) Chamfer strap ends to protect the starting threads. 7) The threads shall be full and free from shear. 8) 4-inch and larger pipe shall be in accordance with Section 33 12 25. c. Nuts 1) Bronze material a) Same material as straps 2) Dimensions equal to or larger than heavy hexagon nuts 3) Tapped 5/8 inch(1.1-NC-2B) d. Gaskets 1) Neoprene rubber material 2) Cemented to saddle and positioned to facilitate installation 10. Brass Flanged Angle Valve a. For 1 1/2 inch and 2-inch services b. Brass castings per AWWA C800 c. Valve Body with integral outlet flange and inlet wrenching flat d. Fit together key and body by turning key and reaming body 1) Key with O-ring seal seat at the upper end 2) Lap key and body seat are to conform to corporation stop requirements of this Specification. 3) The outlet flange shall contain an O-ring seat or a uniform flat drop-in flange gasket surface. 4) Drop-in flange gasket surface shall contain gasket retaining grooves milled circular about the axis of the flange. 5) The size of the outlet flange and the diameter and spacing of the bolt holes shall conform to AWWA C700. 6) The flange on 2-inch angle valves shall be double drilled to permit connection to 1'/z-inch meters. y" 7) The inlet port of the valve shall be tapered to conform to AWWA C800 taper pipe thread. 8) The key cap shall include a wrenching tee marked with a raised or recessed -� arrow to show whether the valve is open or closed. 9) Valve Assembly(main body,key,key cap) a) Brass material per AWWA C800 b) O-ring seal on the top of the key between the key and body seat c) Key cap shall complete the assembly by attaching to the key by means of a strong bronze pin with phosphor bronze spring washer(s) depressed between the key cap and the top of the valve main body. d) Provide with padlock wings for locking the valve in the closed position. e) There shall be a uniform application of cold water valve grease between the body and the key. f) The valve shall be capable of being easily opened and stopping lugs. g) The waterway through the valve shall be smooth and rounded for minimum pressure loss,and shall be free of burrs or fins. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 33 12 10-11 WATER SERVICES 1-INCH TO 2-INCH Page 11 of 17 h) The valve shall be strong,well designed,neat in appearance,water- tight and entirely adequate for the intended purpose. i) Provide with either a high quality rubber drop-in gasket or an O-ring seal depending on the manufacturer's flange seal surface design choice. e. Provide lead-free brass flanged angle valves in accordance with the Reduction of Lead in Drinking Water Act. 11. Meter Boxes shall: a. Be constructed of: 1) Polymer,black polyethylene material as defined in ASTM D883. a) Minimum wall thickness of 3/8-inch throughout with no blowing agents or foaming plastics b) Body shall be black throughout,blended at the time of manufacture, and shall have a molded recycled emblem with a minimum of 35 percent Post Industrial/Pre Consumer Recycled Content-verified with a Leed Product Documentation. c) Have a tensile strength greater than 1700 pounds per square inch(psi). d) Smooth edges and corners and be free from sharp edges so the unit can be handled safely without gloves. e) Exterior free from seams or parting lines. f) Have crush resistant ribbing along the outside of the box. g) Have a flange around the lid opening to help prevent settling and aide in adjustment to grade. h) Not to be installed in roadway—designed to withstand loading in non- deliberate and incidental traffic only. 2) Concrete a) Frame of No.6 gauge wire welded closed b) Type I or Type H Portland cement, in accordance with ASTM C150, portioned with lightweight aggregate,in accordance with ASTM C330 (1) Percentage of wear not to exceed 40 per ASTM C131 (2) Minimum 28 day compressive strength of 3,000 psi b. Be able to withstand a minimum 15,000 pounds vertical load c. Withstand a minimum 400 pounds sidewall load. d. Have pipe holes measuring a minimum of 2-1/2"x 3-1/4". e. 1-inch Standard Meter Box (Class A) 1) For use with services utilizing 5/8-inch x 3/4-inch,3/4-inch or 1-inch meter Single or Dual service meter. 2) Polymer a) Size: working of not less than 10 inches x 16 inches, 12 inches high 3) Concrete a) Size: working area not less than 10-inches x 16-inches, 12 inches high f. 2-inch Standard Meter Box (Class C) 1) For use with services utilizing 1-1/2-inch or 2-inch Single service meter. 2) Polymer a) Size: working area not less than 14-inches x 28-inches, 12 inches high 3) Concrete a) Size:working area not less than 15-inches x 26-1/2-inches, 12 inches high g. Bullhead Standard Meter Box (Class B) T 1) For use with services utilizing two 5/8-inch x 3/4-inch or 3/4-inch or 1-inch Single service meter. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 33 1210-12 WATER SERVICES 1-INCH TO 2-INCH Page 12 of 17 2) Polymer a) Size: working area not less than 15-inches x 18-inches, 12 inches high 3) Concrete a) Size: working area not less than 15-inches x 18-inches, 12 inches high 12. Meter Box Lid ^ a. Meter Box Lids Shall: 1) Be solid throughout with reinforcing ribs. 2) Have City of Fort Worth`Molly' logo molded into the lid. 3) Bear the Manufacturer's IS(name or logo)and Country of Origin. 4) Be designed both with and without AMI receptacles 5) Have a molded tread-plate 6) Seat securely and evenly inside the meter box and shall not overlap the top edge of the meter box. 7) Have a molded pick bar for use by meter reading tool. 8) Have Automated Meter Infrastructure(AMI)snap locking slide mounts for number of meters/endpoints associated with meter box 9) Have an opening to accept the AMI end-point.Opening shall accommodate an endpoint with a 1-7/8 inches diameter. 10) Have recessed AMI end point area,to alleviate a trip hazard,centered over AMI slide mount.Recess area should be 4-1/2 inches in diameter and 3/8" deep. 11) Have built-in anti-flotation devices. b. Cast Iron or Ductile Iron -� 1) Lids for Concrete Meter Boxes shall be constructed out of a cast iron and meet RRF-621 specification. 2) Shall withstand a minimum vertical load of 15,000 pounds 3) Coat castings with a bituminous emulsified asphalt unless otherwise specified in the Contract Documents,ground smooth,and cleaned with shot blasting,to get a uniform quality free from strength defects and distortions. 4) Dimensions shall be within industry standards of f1/16 inch per foot. 5) Shall have a plug inserted in to the AM.I receptacle to avoid water entering through opening until the AMI receptacle is used 6) Be a minimum of 1-3/4 inches thick at reinforcing ribs. 7) Casting weights may vary f5 percent from drawing weight per industry standards. c. Plastic(Composite) 1) The lid shall: a) Constructed of Engineered Plastic as defined in ASTM D883 (1) Have a molded recycled emblem with a minimum of 50 percent -� Post Consumer Recycled and 50 percent Post Industrial/Pre Consumer Recycled Content-verified with a Leed Product Documentation. , (2) Be designed to fit a concrete box/cast iron box in retrofit installations. (3) Have a tensile strength greater than 1700 psi. (4) Have a`knock-out"plug to accept the AMI end-point.Knock-out diameter shall be 1-7/8 inch diameter.A removable plug may be substituted for the knock-out plug. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 33 12 10-13 WATER SERVICES 1-INCH TO 2-INCH Page 13 of 17 (5) Be constructed out of a composite material blend for maximum _. durability and corrosion resistance. (6) Be black throughout with no blowing agents or foaming plastics (7) Smooth edges and corners and be free from sharp edges so the unit can be handled safely without gloves. (8) Exterior free from seams or parting lines. (9) Have a molded tread-pattern-tread dimensions shall be.188-inch x .938-inch x.150-inch deep. (10) Have"City of Fort Worth"molded into the lid. (11) Have"Water Meter"molded into the lid-Font shall be standard Fadal CNC font with 1-inch characters x.150-inch deep. (12) Have a molded pick hole pocket-dimensions shall be 3-inch x 9/16-inch x Thru Hole with 3/16-inch 304 stainless steel rod. (13) Have 2 pieces of Y2-inch rebar located in lid pockets for ® locatability as shown in Drawings. (14) Have location capability using metal detector. b) Domestic Manufacture Only-Made in USA molded on Lid. c) Not to be installed in roadway or parking area d) Be designed to withstand H-10 loading for non-deliberate and incidental traffic only as . e) Have ultraviolet protection. 2) 1-inch Standard Plastic Meter Box Lid(Class A) a) For use with services utilizing 5/8-inch x%-inch,%-inch or 1-inch meter Single or Dual service meter. b) Size: 11-7/8-inch x 17-7/8-inch, 1-1/2 inches high c) For use with Class A Standard Meter Box. d) Polymer lid shall seat evenly inside meter box and shall not overlap the top edge of the meter box. 3) 2-inch Standard Plastic Meter Box Lid(Class C) a) For use with services utilizing 1-1/2-inch or 2-inch Single service meter. b) Size 27-inches x 15-1/4-inches, 1-7/8 inches high c) For use with Class C Standard Meter Box. d) Polymer lid shall seat evenly inside meter box and shall not overlap the top edge of the meter box. 4) Bullhead Standard Plastic Meter Box Lid(Class B) a) For use with services utilizing two 5/8-inch x 3/4-inch or 3/4-inch or f- inch Single service meter: b) Size: 16-5/8-inch x 14-5/8-inch, 1-3/4 inches high c) For use with Class B Standard Meter Box. d) Polymer lid shall seat evenly inside meter box and shall not overlap the top edge of the meter box. .., 13. Horizontal Check Valve a. Equip 1 '/cinch and 2-inch Water Services with a horizontal check valve,with pipe plug,only if specified in the Drawings. b. If an existing backflow preventer is present,the Contractor is to leave it,and is not required to provide an additional horizontal check valve. c. Provide lead-free horizontal check valves in accordance with the Reduction of Lead in Drinking Water Act. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No. 100889 331210-14 WATER SERVICES i-INCH TO 2-INCH Page 14 of 17 14. Service Marker a. 3 inch wide,5 mil blue vinyl tape 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL A. Tests and Inspections 1. At the City's option,the manufacturer shall be required to provide certification records showing conformance of materials, design and testing to these Specifications. 2. The test procedures shall conform to AWWA C800. a. In the event that a chosen valve fails the City's hydrostatic test,the cost of the test shall be at the expense of the supplier. b. Proof testing of the remainder of the valves shall be at the cost and responsibility of the supplier. c. These tests will be the basis of acceptance or rejection of the remainder of the shipment by the City. 3. The City reserves the right to select products at random for testing. The failure of materials to conform to the applicable Specification may result in the rejection of the entire shipment. B. Marking 1. Service saddle castings shall be clearly marked by letters and numerals cast thereon showing: a. Manufacturer's name b. Type c. Size of Pipe PART 3- EXECUTION 3.1 INSTALLERS A. A licensed plumber is required for installations on the outlet side of the service meter. 3.2 EXAMINATION[NOT USED] 3.3 PREPARATION[NOT USED] 3.4 INSTALLATION A. General 1. Install Water Services and appurtenances in accordance with AWWA C800. 2. Install Water Service Lines 5 feet north or east of center of lot frontage on lots 75 feet or wider,or where shown on Drawings. 3. Install Water Service Lines on lot center line on lots less than 75 feet wide,unless otherwise shown on the Drawings. 4. Install services at a minimum depth of 36 inches below final grade/proposed top of curb,unless otherwise specified in the Contract Documents. 5. Perform leak tests in accordance with Section 33 04 40. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 3312 10-15 WATER SERVICES 1-INCH TO 2-INCH Page 15 of 17 6. Replace existing'/4-inch Service Lines with 1-inch new Service Line,tap,and corporation. 7. Install replaced or relocated services with the service main tap and service line being in line with the service meter, unless otherwise directed by the City. 8. Excavate,embed and backfill trenches in accordance with Section 33 05 10. B. Handling 1. Haul and distribute Service Lines fittings at the project site and handle with care to avoid damage. a. Inspect each segment of Service Line and reject or repair any damaged pipe prior to lowering into the trench. b. Do not handle the pipe in such a way that will damage the pipe. 2. At the close of each operating day: a. Keep the pipe clean and free of debris,dirt,animals and trash—during and after the laying operation. b. Effectively seal the open end of the pipe using a gasketed night cap. C. Service Line Installation 1. Service Taps a. Only ductile iron pipe may be directly tapped. { b. Install service taps and/or tap assemblies of the specified size as indicated on the Drawings, or as specified by the Engineer. c. Perform taps on a water system that is either uncharged or under pressure. d. Taps consist of 1) For Concrete Pressure Pipe or Steel Pipe a) Standard internal pipe threaded holes in the pipe walls (1) Made during pipe fabrication (2) Provide tapered threaded outlet with cc threads for up to 2-inch. (3) Provide flange outlet with flange to thread insulator adaptor kits for 4-inch and larger taps. 2) Other pipe materials a) Bronze service clamp with a sealed,threaded port through which the pipe wall is drilled to complete a service port e. Tap Assemblies 1) Consist of corporation stop with iron to copper connection attached to: a) Copper tubing terminating as shown on the City's Standard Detail �. b) Maybe required adjacent to gate valves c) Install as shown on the Drawings,or as directed by the Engineer. d) When required, shall be included in the unit price bid for installing gate valve.. 2) Chlorination and testing purposes a) No separate payment will be made for taps required for testing and chlorination. 2. Installation of Water Services a. Install tap and Service Line in accordance with City Details. b. Install meter box in accordance with City Details. 1) Adjustment of the Service Line to proper meter placement height shall be considered as part of the Meter Box installation. 3. Trenching CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No. 100889 331210-16 WATER SERVICES 1-INCH TO 2-INCH dft Page 16 of 17 a. Provide a trench width sufficiently wide to allow for 2 inches of granular embedment on either side of the Service Line. .� 4. Bored Services a. Services shall be bored utilizing a pilot hole having a diameter 1/2 inch to% inches larger than the Service Line. �.. 5. Arrangement a. Arrange corporation stops,branches,curb stops,meter spuds,meter boxes and other associate appurtenances as shown in the City Detail,and to the approval of the Engineer. 6. Service Marker a. When Meter Box is not installed immediately subsequent to service installation: 1) Mark Curb Stop with a strip of blue vinyl tape fastened to the end of the service and extending through the backfill approximately 6 inches above ground at the Meter Box location. b. Installation of service taps only: 1) Attach service marker tape to the corporation stop or plug and extend upward and normal to the main through the backfill at the adjacent trench edge to at least 6 inches above ground to flag the tap location. 7. Corporation stops a. Fully open corporation stop prior to backfill. D. Removal of Existing Water Meters 1. Remove,-tag and collect existing Water Service meter for pickup by the City for reconditioning or replacement. 2. After installation of the Water Service in the proposed location and receipt of a meter from the City inspector, install the meter. 3. Reset the meter box as necessary to be flush with existing ground or as otherwise directed by the City. 4. All such work on the outlet side of the service meter shall be performed by a licensed plumber. 3.5 REPAIR/RESTORATION[NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD loR] SITE QUALITY CONTROL A. Field Tests and Inspections 1. Check each Water Service installation for leaks and full flow through the curb stop at the time the main is tested in accordance with Section 33 04 40. 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] �. 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] .. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100989 33 12 10-17 WATER SERVICES 1-INCH TO 2-INCH Page 17 of 17 3.14 ATTACHMENTS (NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE Added Blue Text for clarification 1.2 A.—Revision to items included in price bid Specification modified to be in accordance with the Reduction of Lead in Drinking 12/20/2012 D.Johnson Water Act—All materials shall be lead free in accordance with this Act. 1.2.A.3—Water Meter Service Relocate was renamed Water Meter Service Reconnect 1.6.B.—added certification submittals for compliance with regulatory requirements +■+ Added the phrase%.including grass'to lines; Part 1, 1.2.A.1.c.14,Parti, 1.2.A.2.c.13,Part 1, 1.2.A-2.c.13,Part 1,1.2.A.3.c.11, 2/13/2013 F.Griffin Parti,1.2.A.4.c.11 Added the phrase`and replacement'to line Part 1,1.2.&4.c.7 Revised lines with`including grass'replacing with`excluding grass(seeding, 4/26/2013 F.Griffin sodding or hydromulching paid separately)' Included in Part 1, 1.2,A,1,c, 14; Part 1, 1.22 A,2,c, 13;Part 1, 1.2,A,3,c,11; Part 1.1.2,A,4,2, 11 6/19/2013 D.Johnson 1.2.A.4.c—Addition of private water service appurtenances relocation to being included in the linear foot price of private water services 11/21/2016 W.Norwood Require meter box suitable for AMI meter.2.2,C,I1 &2.2,C,12 11/21/2016 W.Norwood Require service saddle with double straps.2.2,C,9,b 2/14/17 W.Norwood 2.2,C,9.a.3 Remove table"Fit Contour of pipe..." 2/14/17 W.Norwood 3.4,C.l.d.(2)Remove nylon sleeve inserts,require cc threads. �r CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 14,2017 City Project No.100889 331225-1 CONNECTION TO EXISTING WATER MAINS Page 1 of 8 1 SECTION 33 12 25 2 CONNECTION TO EXISTING WATER MAINS 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Connection to existing water mains to include,but not limited to: 7 a. Cutting in a tee for a branch connection 8 b. Extending from an existing water main 9 c. Installing a tapping sleeve and valve 10 B. Deviations from this City of Fort Worth Standard Specification 11 1. Measurement and Pa went—Due to the unique nature of this contract and the 12 process as outlined in the specification"Summary of Work"(01-11-00)/ 13 "Scope of Work"this item is considered subsidiary to the water service being 14 replaced.The work performed and materials furnished in accordance with this 15 item are subsidiary to the unit price per each water service complete in place 1.6 and minor pipe replacement,regardless of size and pipe material of the 17 existing main.No other compensation will be allowed. 18 C. Related Specification Sections include,but are not necessarily limited to: 19 1. Division 0—Bidding Requirements,Contract Forms,and Conditions of the 20 Contract 21 2. Division 1 —General Requirements 22 3. Section 33 04 40—Cleaning and Acceptance Testing of Water Mains '- 23 4. Section 33 05 10—Utility Trench Excavation,Embedment and Backfill 24 5. Section 33 05 30—Location of Existing Utilities 25 6. Section 33 1105—Bolts,Nuts,and Gaskets 26 7. Section 33 11 10—Ductile Iron Pipe 27 1.2 PRICE AND PAYMENT PROCEDURES 28 A. Measurement and Payment 29 1. Connection to an existing unpressurized Fort Worth Water Distribution System 30 Main that does not require the City to take part of the water system out of service 31 a. Measurement 32 1) This Item is considered subsidiary to the water pipe being installed. 33 b. Payment 34 1) The work performed and the materials furnished in accordance with this 35 Item are subsidiary to the unit price bid per linear foot of water pipe 36 complete in place,and no other compensation will be allowed. 37 2. Connection to an existing pressurized Fort Worth Water Distribution System Main 38 that requires a shutdown of some part of the water system 39 a. Measurement CITY OF FORT WORTH 2017 WATER LEAD SERVICES �.. STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 6,2013 City Project No.100889 33 1225-2 CONNECTION TO EXISTING WATER MAINS �. Page 2 of 8 1 1) Measurement for this Item shall be per each connection completed. �^ 2 b. Payment 3 1) The work performed and the materials furnished in accordance with this 4 Item shall be paid for at the unit price bid per each"Connection to Existing 5 Water Main"installed for: 6 a) Various sizes of existing water distribution main 7 c. The price bid shall include all aspects of making the connection including,but 8 not limited to: 9 1) Preparing submittals 10 2) Dewatering 11 3) Exploratory excavation(as needed) 12 4) Coordination and notification 13 5) Remobiliz.ation 14 6) Temporary lighting 15 7) .Polyethylene encasement 16 8) Make-up pieces 17 9) Linings 18 10)Pavement removal 19 11) Excavation 20 12)Hauling 21 13) Disposal of excess material 22 14) Clean-up 23 15) Cleaning 24 16) Disinfection 25 17) Testing 26 3. Connection to an existing pressurized Fort Worth Water Distribution System Main 27 by Tapping Sleeve and Valve: 28 a. Measurement 29 1) Measurement for this Item shall be per each connection completed. 30 b. Payment 31 1) The work performed and the materials furnished in accordance with this 32 Item shall be paid for at the unit price bid per each"Tapping Sleeve and 33 Valve"installed for: 34 a) Various sizes of connecting main 35 b) Various sizes of existing water distribution main 36 c. The price bid shall include all aspects of making the connection including,but 37 not limited to: 38 1) Preparing submittals 39 2) Dewatering 40 3) Exploratory excavation(as needed) 41 4) Coordination and notification 42 5) Tapping Sleeve and Tapping Valve 43 6) Remobilization 44 7) Temporary lighting 45 8) Polyethylene encasement 46 9) Make-up pieces 47 10)Linings 48 11) Pavement removal 49 12)Excavation CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 6,2013 City Project No.100889 331225-3 CONNECTION TO EXISTING WATER MAINS Page 3 of 8 1 13)Hauling 2 1.4)Disposal of excess material 3 15)Clean-up r 4 16) Cleaning 5 17)Disinfection 6 18)Testing w 7 1.3 REFERENCES 8 A. Reference Standards .� 9 1. Reference standards cited in this Specification refer to the current reference 10 standard published at the time of the latest revision date logged at the end of this 11 Specification,unless a date is specifically cited. .� 12 2. American Society of Mechanical Engineers(ASME): 13 a. B16.1,Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125 and 250) 14 3. ASTM International(ASTM): 15 a. A36, Standard Specification for Carbon Structural Steel. 16 b. A193, Standard Specification for Alloy-Steel and Stainless Steel Bolting for 17 High Temperature or High Pressure Service and.Other Special Purpose 18 Applications 19 c. A194,Specification for Carbon and Alloy Steel Nuts for Bolts for High 20 Pressure or High Temperature Service, or.Both 21 d. A242, Standard Specification for High-Strength Low-Alloy Structural Steel. 22 e. A283, Standard Specification for Low and Intermediate Tensile Strength 23 Carbon Steel Plates. 24 f. A285,Standard Specification for Pressure Vessel Plates,Carbon Steel,Low- 25 and Intermediate-Tensile Strength. 26 g. B117, Standard Practice for Operating Salt Spray(Fog)Apparatus. 27 h. D2000, Standard Classification System for Rubber Products in Automotive 28 Applications. 29 4. American Water Works Association(AWWA); 30 a. C200, Steel Water Pipe-6 IN and Larger. 31 b. C207, Steel Pipe Flanges for Waterworks Service—Sizes 4 IN through 144 IN. 32 c. C213,Fusion-Bonded Epoxy Coating for the Interior and Exterior of Steel 33 Water Pipelines. -. 34 d. C223,Fabricated Steel and Stainless Steel Tapping Sleeves. 35 5. American Water Works Association/American National Standards Institute 36 (AW WA/ANSI): 37 a. CI05/A21.5,Polyethylene Encasement for Ductile-Iron Pipe Systems. 38 b. CI I I/A21.11,Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and 39 Fittings. 40 c. CI 15A21/15,Flanged Ductile-Iron Pipe with Ductile Iron or Gray-Iron 41 Threaded Flanges. 42 6. NSF International(NSF): 43 a. 61,Drinking Water System Components—Health Effects. 44 7. Manufacturers Standardization Society of the Valve and.Fitting Industry Inc. 45 (MSS): 46 a. SP-60,Connecting flange Joint Between Tapping Sleeves and Tapping Valves. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 6,2013 City Project No.100889 33 1225-4 CONNECTION TO EXISTING WATER MAINS Page 4 of 8 1 1.4 ADMINISTRATIVE REQUIREMENTS 2 A. Pre-installation Meetings 3 1. Required for any connections to an existing,pressurized 16-inch or larger City 4 water distribution system main that requires a shutdown of some part of the water 5 system 6 2. May also be required for connections that involve shutting water service off to 7 certain critical businesses 8 3. Schedule a pre-installation meeting a minimum of 3 weeks prior to proposed time 9 for the work to occur. 10 4. The meeting shall include the Contractor,City Inspector and City Valve Crew. 11 5. Review work procedures as submitted and any adjustments made for current field 12 conditions. 13 6. Verify that all valves and plugs to be used have adequate thrust restraint or 14 blocking. 15 7. Schedule a test shutdown with the City. 16 8. Schedule the date for the connection to the existing system. 17 B. Scheduling 18 1. Schedule work to make all connections to existing 16-inch and larger mains: 19 a. During the period from November through April,unless otherwise approved by 20 the City 21 b. During normal business hours from Monday through Friday,unless otherwise 22 approved by the City 23 2. Schedule City Valve Crew by 1:00 P.M.a minimum of 1 business day prior to 24 planned disruption to the existing water system. 25 a. In the event that other water system activities do not allow the existing main to 26 be dewatered at the requested time, schedule work to allow the connection at an 27 alternate time acceptable to the City. 28 1) If water main Cannot be taken out of service at the originally requested 29 time,coordination will be required with the City to discuss rescheduling 30 and compensation for mobilization. 31 2) No additional payment will be provided if the schedule was altered at the 32 Contractor's request. 33 1.5 SUBMITTALS 34 A. Submittals shall be in accordance with Section 0133 00. 35 B. All submittals shall be approved by the City prior to delivery and/or fabrication for 36 specials. 37 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 38 A. Product Data,if applicable 39 1. Tapping Sleeve noting the pressure rating and coating system supplied including: .� 40 a. Dimensions,weights,material list,and detailed drawings 41 b. Maximum torque recommended by the manufacturer for the valve by size 42 B. Submittals CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 6,2013 City Project No.100889 33 1225-5 CONNECTION TO EXISTING WATER MAINS Page 5 of 9 1 1. Provide a detailed sequence of work for 16-inch,or larger,connections if required 2 by City that includes: 3 a. Results of exploratory excavation 4 b. Dewatering 5 c. Procedure for connecting to the existing water main 6 d. Time period for completing work from when the water is shut down to when 7 the main is back in service 8 e. Testing and repressurization procedures 9 2. Welders that are assigned to work on connection to concrete cylinder or steel pipe 10 must be certified and provide Welding Certificates,upon request, in accordance 11 with AWWA C200. 12 1.7 CLOSEOUT SUBMITTALS [NOT USED] 13 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 14 1.9 QUALITY ASSURANCE [NOT USED] 15 1.10 DELIVERY,STORAGE,AND HANDLING 16 A. Storage and Handling Requirements 17 1. Protect parts so that no damage or deterioration occurs during a prolonged delay 18 from the time of shipment until installation is completed. 19 2. Protect all equipment and parts against any damage during a prolonged period at the 20 site. 21 3. Protect the finished surfaces of all exposed flanges using wooden flanges, strongly 22 built and securely bolted thereto. 23 4. Protect finished iron or steel surfaces not painted to prevent rust and corrosion. 24 5. Prevent plastic and similar brittle items from being exposed to direct sunlight and 25 extremes in temperature. 26 6. Secure and maintain a location to store the material in accordance with Section 01 27 6600. 28 1.11 FIELD [SITE] CONDITIONS [NOT USED] 29 1.12 WARRANTY 30 A. Manufacturer Warranty 31 1. Manufacturer's warranty shall be in accordance with Division 1. 32 PART 2- PRODUCTS -� 33 2.1 OWNER-FURNISHED loR] OWNER-SUPPLIED PRODUCTS [NOT USED] 34 2.2 EQUIPMENT,PRODUCT TYPES AND MATERIALS 35 A, Manufacturers 36 1. Only the manufacturers as listed by the City's Standard Products List will be 37 considered as shown in Section 0160 00. 38 a. The manufacturer must comply with this Specification and.related Sections. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 6,2013 City Project No.100889 331225-6 CONNECTION TO EXISTING WATER MANS Page 6 of 8 1 2. Any product that is not listed on the Standard Products List is considered a — 2 substitution and shall be submitted in accordance with Section 0125 00. 3 B. Description 4 1. Regulatory Requirements 5 a. Tapping Sleeves shall meet or exceed AWWA C223 and the requirements of 6 this Specification. 7 b, All valve components in contact with potable water shall conform to the 8 requirements of NSF 61. 9 C. Tapping Sleeve Materials 10 1. Body 11 a. Body: Carbon Steel per ASTM A283 Grade C,ASTM A285 Grade C,ASTM 12 A36 Steel or equal 13 b. Finish: fusion bonded epoxy coating to an average 12 mil thickness. Fusion 14 applied per AWWA C213. 15 c. All buried tapping sleeves shall be provided with polyethylene encasement in. 16 accordance with AWWA/ANSI C105/A21.5. 17 1) Polyethylene encasement shall be in accordance with Section 33 11 10. 18 2. Flange 19 a. Carbon Steel per ASTM A36 in accordance with AWWA C207 and ASME 20 B16.1 Class 125. 21 b. Recessed for tapping valve per MSS SP-60 22 3. Bolts and Nuts 23 a. Flanged Ends 24 1) Meet requirements of AWWA Cl 15 or AWWA C207 depending on pipe 25 material. 26 2) Provide bolts and nuts in accordance with Section 33 1105. 27 4. Gaskets 28 a. Provide gaskets in accordance with Section 33 1105. 29 5. Test Plug 30 a. %-inch NPT carbon steel with square head and fusion bonded epoxy coating 31 2.3 ACCESSORIES [NOT USED] 32 2.4 SOURCE QUALITY CONTROL [NOT USED] 33 PART 3- EXECUTION 34 3.1 INSTALLERS [NOT USED] 35 3.2 EX►A,MINATION 36 A. Verification of Conditions 37 1. Verify by exploratory excavation, if needed,that existing water main is as depicted 38 in the Drawings and that the location is suitable for a connection to the existing 39 water main. 40 a. Excavate and backfill trench for the exploratory excavation in accordance with 41 3305 10. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 6,2013 City Project No.100889 331225-7 CONNECTION TO EXISTING WATER MAWS Page 7 of 8 1 2. Verify that all equipment and materials are available on—site prior to the shutdown 2 of the existing main. 3 3. Pipe lines shall be completed,tested and authorized for connection to the existing 4 system in accordance with Section 33 04 40. 5 3.3 PREPARATION [NOT USED] 6 3.4 INSTALLATION 7 A. General = 8 1. Upon disruption of the existing water main,continue work until the connection is 9 complete and the existing water main is back in service. 10 B. Procedure 11 1. Expose the proposed connection point in accordance with Section 33 05 10. 12 2. Dewater the existing water line so the chlorinated water is not unlawfully 13 discharged. 14 3. Maintain the water that may bleed by existing valves or plugs during installation 15 within the work area to a reasonable level. 16 a. Control the water in such a way that it does not interfere with the proper 17 installation of the connection or create a discharge of chlorinated water. 18 4, If any discharge of chlorinated water occurs,discharged water shall be de- 19 chlorinated in accordance with Section 33 04 40 20 5. Cut and remove existing water main in order to make the connection. 21 6. Verify that the existing pipe line is suitable for the proposed connection. 22 7. Place trench foundation and bedding in accordance with 33 05 10. 23 8. In the event that a tapping sleeve and valve is used,the coupon from the existing 24 water main shall be submitted to the City. "® 25 9. Prevent embedment,backfill,soil,water or other debris form entering the pipeline. 26 10. Establish thrust restraint as provided for in the Drawings. = 27 11. Clean and disinfect the pipeline associated with the connection in accordance with 28 Section 33 04 40. 29 12. Place embedment to the top of the pipe zone. 30 13. Request that the City Valve Crew re-pressurize the pipeline. 31 14. Directionally flush the connection in accordance with Section 33 04 40. 32 15. Request that City Valve Crew open all remaining valves. 33 3.5 REPAIRIRESTORATION [NOT USED] 34 3.6 RE-INSTALLATION [NOT USED) 35 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED] 36 3.8 SYSTEM STARTUP [NOT USED] 37 3.9 ADJUSTING[NOT USED] 38 3.10 CLEANING [NOT USED] CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 6,2013 City Project No. 100889 33 1225-8 CONNECTION TO EXISTING WA'T'ER MAINS Page 8 of 8 1 3.11 CLOSEOUT ACTIVITIES [NOT USED] �. 2 3.12 PROTECTION[NOT USED] 3 3.13 MAINTENANCE [NOT USED] 4 3.14 ATTACHMENTS [NOT USED] 5 END OF SECTION 6 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D.Johnson 2.2,0.3 and 4—Added reference to Section 33 1105 and removed bolt,nut and gasket materia]specification 2/6/2013 D.Townsend 3.4.B.4 Modified to refer to Section 33 04040 7 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised February 6,2013 City Project No.100889 347113-1 TRAFFIC CONTROL Page 1 of 6 1 SECTION 34 7113 2 TRAFFIC CONTROL 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Installation of Traffic Control Devices and preparation of Traffic Control Plans 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Traffic Control—The contractor will be required to obtain a"Street Use 9 Permit"(01-55-26)prior to starting work.As part of the"Street Use Permit", 10 a traffic control plan is required.The contractor shall be responsible for 11 providing traffic control during the construction of each work order consistent 12 with the provisions set forth in the latest edition of the"Texas Manual on 13 Uniform Traffic Control Devices"(TMUTCD). 14 Unless otherwise included as part of the work order,the contractor shall 15 submit a traffic control plan(duly sealed,signed and dated by a Registered 16 Professional Engineer(P.E.)in the State of Texas),to the City Traffic Engineer 17 at or before the start of each work order.The P.E.preparing the traffic 1.8 control plan may utilize standard traffic reroute configurations posted as 19 "Typicals"on the City's Buzzsaw website.Although the work will not begin 20 until the traffic control plan has been reviewed and approved,the contractor's 21 time will begin in accordance with the timeframe mutually established on the 22 issued work order and specified in"Summary of Work"(01-11-00). 23 Work shall not be performed on certain streets/locations during"peak traffic 24 periods"as determined by the City Traffic Engineer and in accordance with -- 25 the applicable provision of the"City of Fort Worth Traffic Control Handbook 26 for Construction and Maintenance Work Areas". 27 Given the unique nature of this contract Traffic Control has been categorized 28 by type of street/traffic density.The category that the Traffic Control fits in 29 (Residential,Arterial or Major Arterial)will be mutually established by the 30 City's Project Manager,Traffic Engineer and Contractor prior to the start of 31 each work order issued.Payment for Traffic Control shall cover the design, 32 installation and maintenance of the Traffic Control plan and devices required 33 at the appropriate unit price bid. 34 C. Related Specification Sections include,but are not necessarily limited to: 35 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 36 2. Division 1—General Requirements 37 1.2 PRICE AND PAYMENT PROCEDURES 38 A. Measurement and Payment 39 1, Installation of Traffic Control Devices 40 a. Measurement CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 347113-2 TRAFFIC CONTROL Page 2 of 6 1 1) Measurement for Traffic Control Devices shall be per month for the Project 2 duration. —. 3 a) A month is defined as 30 calendar days. 4 b. Payment 5 1) The work performed and materials furnished in accordance with this Item 6 and measured as provided under"Measurement"shall be paid for at the 7 unit price bid for"Traffic Control". 8 c. The price bid shall include: 9 1) Traffic Control implementation 10 2) Installation 11 3) Maintenance 12 4) Adjustments ' 13 5) Replacements 14 6) Removal 15 7) Police assistance during peak hours 16 2. Portable Message Signs 17 a. Measurement 18 1) Measurement for this Item shall be per week for the duration of use. 19 b. Payment 20 1) The work performed and materials furnished in accordance to this Item and 21 measured as provided.under"Measurement"shall be paid for at the unit 22 price bid per week for"Portable Message Sign"rental. 23 c. The price bid shall include: 24 1) Delivery of Portable Message Sign to Site 25 2) Message updating 26 3) Sign movement throughout construction 27 4) Return of the Portable Message Sign post-construction 28 3. Preparation of Traffic Control Plan Details 29 a. Measurement 30 1) Measurement for this Item be per each Traffic Control Detail prepared. 31 b. Payment 32 1) The work performed and materials furnished in accordance with this Item. 33 shall be paid for at the unit price bid per each."Traffic Control Detail" 34 prepared. 35 c. The price bid shall include: 36 1) Preparing the Traffic Control Plan Details for closures of 24 hours or 37 longer 38 2) Adherence to City and Texas Manual on Uniform Traffic Control Devices 39 (TMUTCD) 40 3) Obtaining the signature and seal of a licensed Texas Professional Engineer �. 41 4) Incorporation of City comments 42 1.3 REFERENCES 43 A. Reference Standards 44 1. Reference standards cited in this Specification refer to the current reference 45 standard published at the time of the latest revision date logged at the end of this �. 46 Specification,unless a date is specifically cited. 47 1 Texas Manual on Uniform Traffic Control Devices(TMUTCD). CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,201.3 City Project No.100889 3471 13-3 TRAFFIC CONTROL Page 3 of 6 1 3. Item 502,Barricades,Signs, and Traffic Handling of the Texas Department of 2 Transportation,Standard Specifications for Construction and Maintenance of 3 Highways, Streets,and Bridges. 4 1.4 ADMINISTRATIVE REQUIREMENTS 5 A. Coordination 6 1. Contact Traffic Services Division(817-392-7738)a minimum of 48 hours prior to 7 implementing Traffic Control within 500 feet of a traffic signal. 8 B. Sequencing 9 1. Any deviations to the Traffic Control Plan included in the Drawings must be first 10 approved by the City and design Engineer before implementation. 11 1.5 SUBMITTALS 12 A. Provide the City with a current list of qualified flaggers before beginning flagging 1.3 activities.Use only flaggers on the qualified list. 14 B. Obtain a Street Use Permit from the Street Management Section of the Traffic 15 Engineering Division,311 W. 10d'Street. The Traffic Control Plan(TCP)for the 16 Project shall be as detailed on the Traffic Control Plan Detail sheets of the Drawing set. 17 A copy of this Traffic Control Plan shall be submitted with the Street Use Permit. 18 C. Traffic Control Plans shall be signed and sealed by a licensed Texas Professional 19 Engineer. 20 D. Contractor shall prepare Traffic Control Plans if required by the Drawings or 21 Specifications. The Contractor will be responsible for having a licensed Texas 22 Professional Engineer sign and seal the Traffic Control Plan sheets. 23 E. Lane closures 24 hours or longer shall require a site-specific traffic control plan. 24 F. Contractor responsible for having a licensed Texas Professional Engineer sign and seal �. 25 changes to the Traffic Control Plan(s)developed by the Design Engineer. 26 G. Design Engineer will furnish standard details for Traffic Control, CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 347113-4 TRAFFIC CONTROL Page 4 of 6 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE [NOT USED] 5 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 6 1.11 FIELD [SITE] CONDITIONS [NOT USED] 7 1.12 WARRANTY [NOT USED] 8 PART 2- PRODUCTS 9 2.1 OWNER-FURNISHED(oR] OWNER-SUPPLIED PRODUCTS [NOT USED] 10 2.2 ASSEMBLIES AND MATERIALS 11 A. Description 12 I. Regulatory Requirements 13 a. Provide Traffic Control.Devices that conform to details shown on the 14 Drawings,the TMUTCD, and TxDOT's Compliant Work Zone Traffic Control 15 Device List(CWZTCDL). 16 2. Materials 17 a. Traffic Control Devices must meet all reflectivity requirements included in the 18 TMUTCD and TxDOT Specifications—Item 502 at all times during 19 construction. -„ 20 b. Electronic message boards shall be provided in accordance with the TMUTCD. 21 2.3 ACCESSORIES [NOT USED] 22 2.4 SOURCE QUALITY CONTROL [NOT USED] 23 PART 3- EXECUTION 24 3.1 EXAMINATION [NOT USED] 25 3.2 PREPARATION 26 A. Protection of In-Place Conditions 27 1. Protect existing traffic signal equipment. 28 3.3 INSTALLATION 29 A. Follow the Traffic Control Plan(TCP)and install Traffic Control Devices as shown on 30 the Drawings and as directed. 31 B. Install Traffic Control Devices straight and plumb. 32 C. Do not make changes to the location of any device or implement any other changes to 33 the Traffic Control Plan without the approval of the Engineer. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 3471 13-5 TRAFFIC CONTROL Page 5 of 6 1 1. Minor adjustments to meet field constructability and visibility are allowed. 2 D. Maintain Traffic Control Devices by taking corrective action as soon as possible. 3 1. Corrective action includes but is not limited to cleaning,replacing, straightening, 4 covering, or removing Devices. 5 2. Maintain the Devices such that they are properly positioned, spaced,and legible, 6 and that retroreflective characteristics meet requirements during darkness and rain. .- 7 E. If the Inspector discovers that the Contractor has failed to comply with applicable federal 8 and state laws(by failing to furnish the necessary flagmen,warning devices,barricades, 9 lights,signs,or other precautionary measures for the protection of persons or property),the 10 Inspector may order such additional precautionary measures be taken to protect persons 11 and property. 12 F. Subject to the approval of the Inspector,portions of this Project,which are not affected by 13 or in conflict with the proposed method of handling traffic or utility adjustments,can be 14 constructed during any phase. 15 G. Barricades and signs shall be placed in such a manner as to not interfere with the sight 16 distance of drivers entering the highway from driveways or side streets. 17 H. To facilitate shifting,barricades and signs used in lane closures or traffic staging may 18 be erected and mounted on portable supports. 19 1. The support design is subject to the approval of the Engineer. 20 I. Lane closures shall be in accordance with the approved Traffic Control Plans. 21 J. If at any time the existing traffic signals become inoperable as a result of construction 22 operations,the Contractor shall provide portable stop signs with 2 orange flags,as 23 approved by the Engineer,to be used for Traffic Control. 24 K. Contractor shall make arrangements for police assistance to direct traffic if traffic signal 25 tum-ons,street light pole installation,or other construction will be done during peak traffic 26 times(AM: 7 am—9 am,PM:4 pm-6 pm). 27 L. Flaggers 28 1. Provide a Contractor representative who has been certified as a flagging instructor 29 through courses offered by the Texas Engineering Extension Service,the American 30 Traffic Safety Services Association,the National Safety Council,or other approved 31 organizations. 32 a. Provide the certificate indicating course completion when requested. 33 b. This representative is responsible for training and assuring that all flaggers are 34 qualified to perform flagging duties. = 35 2. A qualified flagger must be independently certified by 1 of the organizations listed 36 above or trained by the Contractor's certified flagging instructor. 37 3. Flaggers must be courteous and able to effectively communicate with the public. 38 4. When directing traffic,flaggers must use standard attire,flags, signs,and signals 39 and follow the flagging procedures set forth in the TMUTCD. 40 5. Provide and maintain flaggers at such points and for such periods of time as may be 41 required to provide for the safety and convenience of public travel and Contractor's 42 personnel, and as shown on the Drawings or as directed by the Engineer. 43 a. These flaggers shall be located at each end of the lane closure. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.100889 347113-6 TRAFFIC CONTROL Page 6 of 6 1 M. Removal 2 1. Upon completion of Work,remove from the Site all barricades, signs,cones,lights 3 and other Traffic Control Devices used for work-zone traffic handling in a timely 4 manner,unless otherwise shown on the Drawings. 5 3.4 REPAIR/RESTORATION [NOT USED] 6 3.5 RE-INSTALLATION [NOT USED] 7 3.6 FIELD loR] SITE QUALITY CONTROL[NOT USED] 8 3.7 SYSTEM STARTUP[NOT USED] 9 3.8 ADJUSTING [NOT USED] 10 3.9 CLEANING [NOT USED] 11 3.10 CLOSEOUT ACTIVITIES [NOT USED] 12 3.11 PROTECTION[NOT USED] 13 3.12 MAINTENANCE [NOT USED] 14 3.13 ATTACHMENTS [NOT USED] _. 15 END OF SECTION 16 Revision Log DATE NAME SUMMARY OF CHANGE 11122/13 S.Arnold Added police assistance,requirement for when a site specific TCP is required 17 CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised November 22,2013 City Project No.10088..9 """� APPENDIX GC-4.01 Availability of Lands—None GC-4.02 Subsurface and Physical Conditions—None GC-4.04 Underground Facilities—None GC-4.06 Hazardous Environmental Condition at Site—None GC-6.06.1)Minority and Women Owned Business Enterprise Compliance MBE Specifications—Special Instructions for Bidders MBE Subcontractors/Suppliers Utilization Form MBE Prime Contractor Waiver Form MBE Good Faith Effort Form MBE Joint Venture Eligibility Form GC-6.07 Wage Rates 2013 Prevailing Wage Rates(Heavy and Highway Construction Projects) GC-6.09 Permits and Utilities—None GC-6.24 Nondiscrimination—None GR-01 60 00 Product Requirements—None CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1.2011 City Project No.100889 GC-4.01 Availability of Lands THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT ,,, Revised July 1,20I1 City Project No.100889 GC-4.02 Subsurface and Physical Conditions THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT ,, Revised July 1,2011 City Project No.100889 GC-4.04 Underground Facilities THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100999 GC-4.06 Hazardous Environmental Condition at Site THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 GC-6.06.1) Minority and Women Owned Business Enterprise Compliance MBE Specifications — Special Instructions to Bidders MBE — Subcontractors / suppliers Utilization Form MBE — Prime Contractor Waiver Form MBE — Good Faith Effort Form MBE — Joint Venture Eligibility Form .. CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2611 City Project No.100999 FORT WORT_ H City of Fort Worth Minority Business Enterprise Specifications SPECIAL INSTRUCTIONS FOR OFFERORS APPLICATION OF POLICY If the total dollar value of the contract is$50,000 or more,then a MBE subcontracting goal is applicable. POLICY STATEMENT It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minority Business Enterprises (MBE) in the procurement of all goods and services. All requirements and regulations stated in the City's current Business Diversity Enterprise Ordinance applies to this bid. MBE PROJECT GOALS The City's MBE goal on this project is 7 %of the base bid value of the contract. Note: If both MBE and SBE subcontracting goals are established for this project,then an Offeror must submit both a MBE Utilization Form and a SBE Utilization Form to be deemed responsive. COMPLIANCE TO BID SPECIFICATIONS On City contracts $50,000 or more where a MBE subcontracting goal is applied, Offerors are required to comply with .. the intent of the City's Business Diversity Enterprise Ordinance by one of the following: 1. Meet or exceed the above stated MBE goal through MBE subcontracting participation,or 2. Meet or exceed the above stated MBE goal through MBE Joint Venture participation,or, «<p 3. Good Faith Effort documentation, or, 4. Prime Waiver documentation. SUBMITTAL OF REQUIRED DOCUMENTATION The applicable documents must be received by the Purchasing Division, within the following times allocated, in order for the entire bid to be considered responsive to the specifications. The Offeror shall deliver the MBE documentation in person to the appropriate employee of the purchasing division and obtain a date/time receipt. Such receipt shall be evidence that the City received the documentation in the time allocated. A faxed and/or emailed copy will not be accepted. 1. Subcontractor Utilization Form, if goal is received no later than 2:00 p.m.,on the second City business day met or exceeded: after the bid opening date,exclusive of the bid opening date. 2. Good Faith Effort and Subcontractor received no later than 2:00 p.m., on the second City business day Utilization Form, if participation is less than after the bid opening date,exclusive of the bid opening date. .. stated goal: 3. Good Faith Effort and Subcontractor received no later than 2:00 p.m., on the second City business day Utilization Form, if no MBE participation: after the bid opening date, exclusive of the bid opening date. 4. Prime Contractor Waiver Form, if you will received no later than 2:00 p.m.,on the second City business day .. perform all subcontracting/supplier work: after the bid opening date, exclusive of the bid opening date. 5. Joint Venture Form,if goal is met or received no later than 2:00 p.m., on the second City business day exceeded: after the bid opening date,exclusive of the bid opening date. FAILURE TO COMPLY WITH THE CITY'S BUSINESS DIVERSITY ENTERPRISE ORDINANCE, WILL RESULT IN THE BID BEING CONSIDERED NON-RESPONSIVE TO SPECIFICATIONS. FAILURE TO SUBMIT THE REQUIRED MBE DOCUMENTATION WILL RESULT IN THE BID BEING CONSIDERED NON-RESPONSIVE.A SECOND FAILURE WILL RESULT IN THE OFFEROR BEING DISQUALIFIED FOR A PERIOD OF ONE YEAR. THREE FAILURES IN A FIVE YEAR PERIOD WILL RESULT IN A DISQUALIFICATION PERIOD OF THREE YEARS. Any questions,please contact the M/WBE Office at(817)212-2674. Rev.2/10/15 AT-rAcOMENT A Page 1 a[4 FORT WORTH Gity. of Fort Worth Minority Business Enterprise MBE Subcontractors/Suppliers Utilization Form OFFEROR COMPANY NAME: Check applicable block to describe offeror.fferor. PROJECT NAME: fVNV/VI DBE NON-MM IDBE BID ID DATE 2-0 t 7 WcAc,- L -3 3 City's MBE Project Goal: Project Commitment, PROJECT NUMBER 7 % Identify all subcontractors/suppliers you will use on this project Failure to complete this form, in its entirety with requested documentation, and received by the Purchasing Division no later than 2:00 p.m. on the second City business day after bid opening, exclusive of bid opening date, will result in the bid being considered non-responsive to bid specifications. ii The undersigned Offeror agrees to enter into a formal agreement with the MBE firm(s) listed in this utilization schedule, conditioned upon execution of a contract with the City of Fort Worth. The intentional and/or knowing misrepresentation of facts is grounds for cons'ideration of disqualification and will result in the bid being i considered non-responsive to bid specifications. MBEs listed toward.meeting the project goal must be located in the six(6) county marketplace at the time of bid or the business has a Significant Business Presence in the Marketplace. Marketplace is the geographic is area of Tarrant, Dallas, Denton,Johnson, Parker, and Wise counties. Prime contractors must identify by tier level of all subcontractorstsuppliers. Tier: means the level sof subcontracting below the prime contractor/consultant i.e. a direct payment from the prime contractor to a ii tier, a payment by a subcontractor to its supplier is considered 2nd tier. The prime II subcontractor is considered 1, T�4 contractor is responsible to provide proof of payment of all tiered subcontractors identified as a MBE and ij icountin-q those dollars towards meeting the contract committed goal. ALL MBEs MUST BE CERTIFIED BEFORE CONTRACT AWARD. ' ;Certification means those firms, located within the Marketplace, that have been determined to be a bondafide minorifty business enterprise by the North Central Texas Regional,Certification Agency(NCTRCA) or other cert9fying agencies that the City may deem appropriate and accepted by the City of Fort Worth. If hauling services are utilized, the Offeror will be given credit as long as the MBE listed owns and operates at least Or4q_.fully licensed and operationat truck to be used on the contract. The MBE may lease trucks from another MBE firm, including MBE owner-operated, and receive full MBE credit. The MBE may lease trucks from non-MBEs, including owner-operated, but will only receive credit for the fees and 'e lease agreement.T commissions earned by the MBE as outlined in th Rev'_V 10 115 i, FORT WORTH A�T#ZHMENT�•A C�PSc�e2of4 Offerors are required to identify ALL subcontractors/suppliers, regardless of status; i.e., IfAit2oti# ;2td ngn IVFBEs. MBE firm are to bs3 listed first,use additional sheets if necessary. Please note that only certified MBEs will be counted to meet an MBE goal. NCTRCA N e SUBCONTRACTORISUPPLIER ° n Company Name T Detail Detail Address i Subcontracting Supplies Dollar Amount Telephone/Fax e B B M Work Purchased Email r E E t3 Contact Person E R! � 'v /'.Jn.�:w.. • w A,• . i 0 0 u: I f 1 i�6 d IR i El q.. '1 e £,' 0 0 fE;,c '� •yrs;`.„', ! 37 — r' ' Pi i+l FORT�WORT_H ATTACHMENT 1A .. Page 3 of 4 Offerors are required to identify ALL subcontractors/suppliers, regardless of status; i.e., Minority and non-MBEs. MBE firms are to be listed first, use additional sheets if necessary. Please note that only certified MBEs will be counted to meet an MBE goal. NCTRCA N SUBCONTRACTOR/SUPPLIER ° Company Name T n Detail Detail Address i Subcontracting Supplies M W Dollar Amount Telephone/Fax ' B B B Work Purchased Email E E Contact Person E a F-1 F1 F-1 El a a a El a a a Rev.2/10/15 FORT► ORTH ATTACHMENT 1A Page 4 of 4 Total Dollar Amount of MBE Subcontractors/Suppliers $ j oz� o. b s:+ Total Dollar Amount of Non-MBE Subcontractors/Suppliers $ ,000. TOTAL DOLLAR AMOUNT OF ALL SUBCONTRACTORS/SUPPLIERS $ aoo „ The Offeror will not make additions, deletions, or substitutions to this certified list without the prior approval of the Minority and Women Business Enterprise Office through the submittal of a Request for Approval o; r.; Change/Additfon form. Any unjustified change or deletion shall be a material breach of contract and may resui in debarment in accord with the procedures outlined in the ordinance. The Offeror shall submit a detailed explanation of how the requested change/addition or deletion will affect the committed MBE goal. If the detail explanation is not submitted, it will affect the final compliance determination. J By affixing a signature to this form, the Offeror further agrees to provide, directly to the City upon request, f complete and accurate information regarding actual work performed by all subcontractors, including MBE(s) and any special arrangements with MBEs. The Offeror also agrees to allow an audit and/or examination of any books, records and files held by their company. The Offeror agrees to allow the transmission of interviews with owners, principals, officers, employees and applicable subcontractors/suppliers participating on the contract tha�„ will substantiate the actual work performed by the MBE(s) on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract M or debarment from City work for a period of not less than three (3) years and for initiating action under Federal, { State or Local laws concerning false statements. Any failure to comply with this ordinance creates a material breach of the contract and may result in a determination of an irresponsible Offeror and debarment from .' participating in City work for a period of time not less than one(1) year. Authorized SranatUry Printed signature r 1 TWO Contact NameTtle(if different) i,r,•''` 617- gor-8v9T Company Name Telephone and/or Fax o �,�� T.. Address E-mail Address 17� [• �' Rev.2110/15 ATTACHMENT IB FORT WORTH Page 1 of 1 _ City of Fort Worth Minority Business Enterprise Specifications Prime Contractor Waiver Form OFFEROR COMPANY NAME: Check applicable block to describe prime PROJECT NAME: MM//DBE NON-MMUDBE BID DATE City's MBE Project Goal: Offeror's MBE Project Commitment: PROJECT NUMBER % If both answers to this form are YES, do not complete ATTACHMENT 1C (Good Faith Effort Form). All questions on this form must be completed and a detailed explanation provided, if applicable. If the answer to either question is NO, then you must complete ATTACHMENT 1C. This form is only applicable if both answers are yes. Failure to complete this form in its entirety and be received by the Purchasing Division no later than 2:00 p.m., on the second City business day after bid opening,exclusive of the bid opening date,will result in the bid being considered non-responsive to bid specifications. Will you perform this entire contract without subcontractors? YES If yes, please provide a detailed explanation that proves based on the size and scope of this NO project, this is your normal business practice and provide an operational profile of your business. Will you perform this entire contract without suppliers? YES If yes, please provide a detailed explanation that proves based on the size and scope of this project, this is your normal business practice and provide an inventory profile of your business. NO .. The Offeror further agrees to provide, directly to the City upon request, complete and accurate information regarding actual work performed by all subcontractors, including MBE(s) on this contract, the payment thereof and any proposed changes to the original MBE(s) arrangements submitted with this bid. The Offeror also agrees to allow an audit and/or examination of any books, records and files held by their company that will substantiate the actual work performed by the MBEs on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment from City work for a period of not less than three (3) years and for initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this ordinance creates a material breach of contract and may result in a determination of an irresponsible Offeror and barred from participating in City work for a period of time not less than one(1)year. dER Authorized Signature Printed Signature Title Contact Name(if different) Mill Company Name Phone Number Fax Number Address Email Address CitylState/Zip Date Rev.2/10/15 ATTACHMENT 1C Page 1 of 4 FORT WORTH City of Fort Worth Minority Business Enterprise MBE Good Faith Effort Form OFFEROR COMPANY NAME: Check applicable block to describe Offeror PROJECT NAME: tVJ'lDBE11 N7N-P W41DBE BID DATE City's MBE Project Goal: Offeror's MBE Project Commitment: PROJECT NUMBER % % If the Offeror did not meet or exceed the MBE subcontracting goal for this project,the Offeror must complete this form. If the Offeror's method of compliance with the MBE goal is based upon demonstration of a "good faith effort", the Offeror will have the burden of correctly and accurately preparing and submitting the documentation required by the City. Compliance with each item, 1 thru 11 below, shall satisfy the Good Faith Effort requirement absent proof of fraud, intentional and/or knowing misrepresentation of the facts or intentional discrimination by the Offeror. Failure to complete this form, in its entirety with supporting documentation, and received by the Purchasing Division no later than 2:00 p.m. on the second City business day after bid opening, exclusive .. of bid opening date,will result in the bid being considered non-responsive to bid specifications. .., 1.) Please list each and every subcontracting and/or supplier opportunity for the completion of this project, regardless of whether it is to be provided by a MBE or non-MBE. (DO NOT LIST NAMES OF FIRMS) On all projects, the Offeror must list each subcontracting and or supplier opportunity regardless of tier. i (Use additional sheets,if necessary) List of Subcontracting Opportunities List of Supplier Opportunities Rev.2/10/15 M" ATTACHMENT 1C Page 2 of 4 2.) Obtain a current(not more than two(2)months old from the bid open date) list of MBE subcontractors and/or suppliers from the City's M/WBE Office. Yes Date of Listing f / No 3.) Did you solicit bids from MBE firms,within the subcontracting and/or supplier areas previously listed, at least ten calendar days prior to bid opening by mail,exclusive of the day the bids are opened? Yes (If yes,attach MBE mail listing to include name of firm and address and a dated copy of letter mailed.) No 4.) Did you solicit bids from MBE firms,within the subcontracting and/or supplier areas previously listed, at least ten calendar days prior to bid opening by telephone,exclusive of the day the bids are opened? Yes (If yes,attach list to include name of MBE firm,person contacted,phone number and date and time of contact.) No 5.) Did you solicit bids from MBE firms,within the subcontracting and/or supplier areas previously listed, at least ten calendar days prior to bid opening by facsimile(fax), exclusive of the day the bids are opened? Yes (If yes,attach list to include name of MBE firm,fax number and date and time of contact. In addition,if the fax is returned as undeliverable,then that"undeliverable confirmation"received must be printed directly from the facsimile for proper documentation. Failure to submit confirmation and/or"undeliverable confirmation" documentation may render the GFE non-responsive.) No 6.) Did you solicit bids from MBE firms,within the subcontracting and/or supplier areas previously listed, at least ten calendar days prior to bid opening by email,exclusive of the day the bids are opened? Yes (If yes,attach email confirmation to include name of MBE firm,date and time.In addition,if an email is returned as undeliverable,then that"undeliverable message"receipt must be printed directly from the email system for *�* proper documentation. Failure to submit confirmation and/or"undeliverable message"documentation may render the GFE non-responsive.) No NOTE: The four methods identified above are acceptable for soliciting bids, and each selected method must be applied to the applicable contract. The Offeror must document that either at least two attempts were made using two of the four methods or that at least one successful contact was made using one of the four methods in order to be deemed responsive to the Good Faith Effort requirement. NOTE: The Offeror must contact the entire MBE list specific to each subcontracting and supplier opportunity to be in compliance with questions 3 through 6. 7.) Did you provide plans and specifications to potential MBEs? Yes No 8.) Did you provide the information regarding the location of plans and specifications in order to assist the MBEs? Yes No Rev.2/10/15 ATTACHMENT 1C Page 3 of 4 9.) Did you prepare a quotation for the MBEs to bid on goods/services specific to their skill set? Yes (If yes,attach all copies of quotations.) ® No 10.) Was the contact information on any of the listings not valid? Yes (If yes,attach the information that was not valid in order for the M/WBE Office to address the corrections needed.) No 11.)Submit documentation if MBE quotes were rejected. The documentation submitted should be in the forms of an affidavit, include a detailed explanation of why the MBE was rejected and any supporting documentation the Offeror wishes to be considered by the City. In the event of a bona fide dispute concerning quotes, the Offeror will provide for confidential in-camera access to an inspection of any relevant documentation by City personnel. (Please use additional sheets,ff necessary,and attach.) Company Name Telephone Contact Person Scope of Work Reason for Rejection ADDITIONAL INFORMATION: Please provide additional information you feel will further explain your good and honest efforts to obtain MBE participation on this project. The Offeror further agrees to provide, directly to the City upon request, complete and accurate information regarding actual work performed on this contract, the payment thereof and any proposed changes to the original arrangements submitted with this bid. The Offeror also agrees to allow an audit and/or examination of any books, records and files held by their company that will substantiate the actual work performed on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment from City work for a period of not less than three (3) years and for initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this ordinance shall create a material breach of contract and may result in a determination of an irresponsible Offeror and debarment from participating in City work for a period of time not less than one (1) year. Rev.2/10/15 MW ATTACHMENT 1C Page 4 of 4 The undersigned certifies that the information provided and the MBE(s) listed was/were „ contacted in good faith. It is understood that any MBEs) listed in Attachment 1C will be contacted and the reasons for not using them will be verified by the City's M/WBE Office. MW Authorized Signature Printed Signature MW Title Contact Name and Title(if different) Company Name Phone Number Fax Number Address Email Address City/State/Zip Date MW Rev.2110115 Joint Venture FORT WORTH Page 1 of 3 CITY OF FORT WORTH MBE Joint Venture Eligibility Form All questions must be answered;use"N/A"if not applicable Name of City project: A joint ventre form must be completed on each project RFP/Bid/Purchasing Number: 1.Joint venture information: Joint Venture Name: Joint Venture Address: (7f applicable) Telephone: Facsimile: E-mail address: Cellular: �j Identify the firms that comprise the joint venture: Please attach extra sheets if additional space is required to provide detailed explanations of work to be performed by each firm comprising the joint venture MBE firm Non-MBE firm name: name: Business Address: Business Address: Am City,State,Zip: City,State,Zip: Telephone Facsimile E-mail Telephone Facsimile Cellular Cellular Certification Status: E-mail address Name of Certifying Agency: 2. Scope of work performed by the Joint Venture: Describe the scope of work of the MBE: Describe the scope of work of the non-MBE: wa .r Rev.2/10/15 Joint Venture Page 2 of 3 3.What is the percentage of MBE participation on this joint venture that you wish to be counted toward .. meeting the project goal? 4.Attach a copy of the joint venture agreement. 5. List components of ownership of joint venture: (Do not complete if this information is described in joint venture agreement) Profit and loss sharing: Capital contributions,including MW equipment: Mo Other applicable ownership interests: 6. Identify by name,race,sex and firm those individuals(with titles)who are responsible for the day-to-day management and decision making of the joint venture: Financial decisions (to include Account Payable and Receivable): Management decisions: a. Estimating — b Marketing and Sales c. Hiring and Firing of management personnel ------------------------------------------- d. Purchasing of major equipment and/or supplies "' Supervision of field operations The City's Minority and Women Business Enterprise Office will review your joint venture submission and will have final approval of the MBE percentage applied toward the goal for the project listed on this form. NOTE: From and after the date of project award, if any of the participants, the individually defined scopes of work or the dollar amounts/percentages change from the originally approved information, then the participants must s inform the City's M/WBE Office immediately for approval. Any unjustified change or deletion shall be a material breach of contract and may result in debarment in accord with the procedures outlined in the City's BDE Ordinance. Rev.2/10/15 ,..� Joint Venture Page 3 of 3 AFFIDAVIT The undersigned affirms that the foregoing statements are true and correct and include all material information necessary to identify and explain the terms and operation of the joint venture. Furthermore,the undersigned shall agree to provide to the joint venture the stated scope of work, decision-making responsibilities and payments herein. The City also reserves the right to request any additional information deemed necessary to determine if the joint venture is eligible. Failure to cooperate and/or provide requested information within the time specified is grounds for termination of the eligibility process. The undersigned agree to permit audits,interviews with owners and examination of the books, records and files of the joint venture by any authorized representatives of the City of Fort Worth. Failure to comply with this provision shall result in the termination of any contract, which may be awarded under the provisions of this joint venture's eligibility and may initiate action under Federal, State and/or Local laws/ordinances concerning false statements or willful misrepresentation of facts. Name of MBE firm Name of non-MBE firm s Printed Name of Owner Printed Name of Owner Signature of Owner Signature of Owner Printed Name of Owner Printed Name of Owner Signature of Owner Signature of Owner Title Title Date Date Notarization State of County of On this day of -->20 , before me appeared and to me personally known and who,being duly sworn,did execute the foregoing affidavit and did state that they were properly authorized to execute this affidavit and did so as their free act and deed. .. Notary Public Print Name Notary Public Signetum �• Commission Expires (sent) Rev.2/10/15 GC-6.07 Wage Rates 2013 Prevailing Wage Rates (Heavy and Highway Construction Projects) CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT �, Revised July 1,2011 City Project No,100889 2013 PREVAILING WAGE RATES (Heavy and Highway Construction Projects) CLASSIFICATION DESCRIPTION Wage Rate Asphalt Distributor Operator $ 15.32 Asphalt Paving Machine Operator $ 13.99 Asphalt Raker $ 12.69 Broom or Sweeper Operator $ 11.74 Concrete Finisher,Paving and Structures $ 14.12 Concrete Pavement Finishing Machine Operator $ 16.05 Concrete Saw Operator $ 14.48 Crane Operator,Hydraulic 80 tons or less $ 18.12 Crane Operator,Lattice Boom 80 Tons or Less $ 17.27 Crane Operator,Lattice Boom Over 80 Tons $ 20.52 w° Crawler Tractor Operator $ 14.07 Electrician $ 19.80 Excavator Operator,50,000 pounds or less $ 17.19 a Excavator Operator,Over 50,000 pounds $ 16.99 Flagger $ 10.06 Form Builder/Setter,Structures $ 13.84 Form Setter,Paving&Curb $ 13.16 Foundation Drill Operator,Crawler Mounted $ 17.99 Foundation Drill Operator,Truck Mounted $ 21.07 Front End Loader Operator,3 CY or Less $ 13.69 Front End Loader Operator,Over 3 CY $ 14.72 Laborer,Common $ 10.72 Laborer,Utility $ 12.32 Loader/Backhoe Operator $ 15.18 Mechanic $ 17.68 Milling Machine Operator $ 14.32 Motor Grader Operator,Fine Grade $ 17.19 Motor Grader Operator,Rough $ 16.02 Off Road Hauler $ 12.25 Pavement Marking Machine Operator $ 13.63 Pipelayer $ 13.24 Reclaimer/Pulverizer Operator $ 11.01 Reinforcing Steel Worker $ 16.18 Roller Operator,Asphalt $ 13.08 Roller Operator,Other $ 11.51 Scraper Operator $ 12.96 Servicer $ 14.58 Small Slipform Machine Operator $ 15.96 Spreader Box Operator $ 14.73 Truck Driver Lowboy-Float $ 16.24 Truck Driver Transit-Mix $ 14.14 Truck Driver,Single Axle $ 12.31 Truck Driver,Single or Tandem Axle Dump Truck $ 12.62 Truck Driver,Tandem Axle Tractor with Semi Trailer $ 12.86 Welder $ 14.84 Work Zone Barricade Servicer $ 11.68 The Davis-Bacon Act prevailing wage rates shown for Heavy and Highway construction projects were determined by the United States Department of Labor and current as of September 2013. The titles and descriptions for the classifications listed are detailed in the AGC of Texas'Standard Job Classifications and Descriptions for Highway, Heavy,Utilities,and Industrial Construction in Texas. Page 1 of 1 GC-6,09 Permits and Utilities THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 GC-6.24 Nondiscrimination THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889 No �w GR-01 60 00 Product Requirements THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH 2017 WATER LEAD SERVICES STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS REPLACEMENT CONTRACT Revised July 1,2011 City Project No.100889