AMENDMENT No. 4 cONTRACT NO.
TO CITY SECRETARY CONTRACT
WHEREAS, the City of Fort Worth (CITY) and GSWW, Inc. , made and
entered into City Secretary Contract No. 32129, (CONTRACT) which was
authorized by M&C C-20821 on the 28th day of June, 2005 in the amount
of $102,340. 00; and
WHEREAS, GSWW, Inc. was subsequently acquired by and merged into
Burgess & Niple, Inc. (collectively and hereafter, ENGINEER) ; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment
Number 1 in the amount of $18, 875 . 00 which was authorized
administratively on September 19, 2006, Amendment Number 2 in the
amount of $21, 601. 00 which was authorized by M&C No. C-24112 on March
24, 2010 and Amendment No. 3 in the amount of $8, 863 . 00 which was
authorized administratively on August 8, 2012; and
WHEREAS, the CONTRACT involves engineering services for
the following project:
Water and Sanitary Sewer Replacement Contract 2004, STM-H;
and
WHEREAS, it has become necessary to execute Amendment No.
4 to the CONTRACT to include an increased scope of work and revised
fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and
through their duly authorized representatives, enter into the
following agreement, which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the
additional engineering services specified in a proposal dated August
26, 2013, a copy of which is attached hereto and incorporated herein.
The cost to City for the additional design services to be performed
by Engineer totals $5,780 . 00 .
2 .
OFFICIAL RECORD
���'► Page -1- CITY SECRETARY
Iv�p 6'1 ��0 FT.!NORTH, TX
RE�'�
Article II of the CONTRACT is amended to provide for an
increase in the fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that
the total fee paid by the City for all work and services
shall be an amount of $157, 459 . 00
3 .
All other provisions of the Contract, which are not
expressly amended herein, shall remain in full force and
effect .
ElECtTTED anti 1TITECrI IE4 as of the date last written by
a signatory, below.
APPROVED: ENGINEER
City of Fort Worth Burgess & Niple, Inc .
Fernando Costa Dr. Stev Sanders, P.E.
Assistant City Manager Vice President
Burgess & Niple, Inc .
DATE: DATE: %0Z ZZ 0
APPROV L RECOMMENDED:
S. Frank Crumb, P.E.
Director, Water Department
APPROVED AS TO FORM AND
LEGALITY: M&C:
[ U1�1 Date :I AA t,
Dougl-a-s-W,--Black (Ic
Assistant City Attorney
TTES / M -- ----
ar J. Kayser �8 %o
City Secretary
000
CX
Page
BURGESS & NIPLE
395o Fossil Creek Blvd. ( Suite 210 Fort Worth, TX 76137 817.306.1444
August 26, 2013
Mr. Rakesh Chaubey, P.E.
Project Manager
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102
Re: Supplemental Authorization Request #4
WATER AND SEWER REPLACEMENT CONTRACT 2004, STM-H
City Project No. 00193; DOE No. 4893; B&N No. PR51936/39318/0350-002
Water Project No. P 253 603170019383
Sewer Project No. P 258 703170019383
Proposed Amendment No. 4 to City Secretary Contract No. 32129
Mr. Chaubey:
This letter is our formal request for Supplemental Authorization to be compensated for additional
engineering services as requested by the City. Note that the original design contract was between GSWW,
Inc. and the City of Fort Worth. Since then, GSWW was purchased by Burgess & Niple. We operate as
Burgess & Niple. GSWW does not exist anymore.
Justification
City forces found an old, private sanitary sewer line draining the residence at 2917 Alton Road. This sewer
crosses 2913 Alton Road to get to the manhole at STA 3+60 of Sanitary Sewer L-2406. The private
sanitary sewer is damaged and needs to be replaced. As well, it needs to be a public sewer, requiring it to
be contained within a sanitary sewer easement. This amendment will incorporate the extra engineering
and surveying effort required for the additional work.
Our proposed Scope of Work is as follows:
We will have the existing sewer and the proposed alignment surveyed and we will provide a sanitary sewer
easement on 2917 Alton Road. Note that the needed sanitary sewer easement on 2913 Alton Road is
already being prepared under Supplemental Authorization #3. We will provide a single plan & profile sheet
of this design. After construction, we will provide a mylar record drawing. This construction work will be
performed by City forces. The City will expose the existing utility lines so that the Surveyor can locate them
and so we can design the replacement sewer line. We will not be responsible for obtaining Rights of Entry
from these property owners.
Based upon this scope of work, the additional design cost proposed for Amendment No. 4 is $5,780.00.
buraessniolexorn
d
City of Fort Worth
August 26, 2013
DOE #4893
Page 2
PROJECT FEE DETAILS
Contract Item Description Fee
Original Contract Water and SS Repl Contract 2004 $102,340.00
City Sec'y Contract# 32129
Approved Amendment No. 1 Permanent Easements, TCE's, and TROE's $18,875.00
City Sec'y Contract# 34016
Approved Amendment No, 2 Resurrect Archived Project $21,601.00
City Sec'y Contract #32129-A2
Approved Amendment No. 3 Relocating sanitary sewer in 2905/2909 $8,863.00
City Sec'y Contract#32129-A3 Alton Road
Proposed Amendment No. 4 Relocating sanitary sewer in 2913/2917 $5,780.00
Alton Road
REVISED TOTAL PROJECT FEE $157,459.00
MNVBE Consultant
ANA Consultants/ Non- M/WBE
Prime Mas-Tek Consultants/ Consultant for
PROJECT FEES Consultant Trevino Reproduction Reproduction
Base Contract $102,340.00 $68,442.00 $30,594.00 $3,304.00
Amendment 1 $ 18,875.00 $5,000.00 $13,875.00 $0.00
Amendment 2 $ 21,601.00 $20,775.00 $0.00 $826.00
Amendment 3 $ 8,863.00 $4,343.00 $4,500.00 $20.00
Amendment 4 5 780.00 $2,760.00 $3,000.00 $20.00
Total Contract $4.170.00
Percent of Total 64.35% 33.00% 2.65%
Please let me know if you have any questions or need additional information concerning this request.
Respectfully submitted,
Burgess & Niple, Inc.
TBPE FIRM REGISTRATION NO. F-10834
04;"w0
William D. Wendland, P.E.
Associate
Director, Fort Worth Municipal Projects Section
Enclosures
D$projeW350-0021Amendments to Eng Contract1350-002_Amendment 4_WDW_20130826.docx
burgessniple.com
B&N Project PR39318/51936 BURGESS & NIPLE
Engineers ■ Planners
2004 Capital Improvements Program-STM-H Amendment 4
WATER PROJECT NO.P 253 603170019383
SEWER PROJECT NO.P 258 703170019383
DOE PROJECT NO.4893
Design Services for relocating sanitary sewer in 2913/2917 Alton Road
PROPOSED HOURS FOR EACH TASK TOTAL
$ 220.00 $ 195.00 1 $113.00 $ 87.00 Direct AMOUNT
Task Work Task Descriptions Prin. P.M. P.E. CAD Tech Costs
a Site visit prior to design 1 1 $ 20.00 $ 328.00
Topographic survey and 1 sewer easement(ANA-
b sub-consultant) $ 3,000.00 $ 3,000.00
c Plan&Profile sheet of replacement sewer line 1 4 12 $ - $ 1,691.00
d Project Management 3 50.00 $ 635.00
e Mylar plan submittal assume 1 sheet and delivery) 1 $ 42.00 $ 129.00
TOTAL 23 hours 0 5 5 13 1 $ 3 112.00 1 $ 5,783.00
Rounded Fee=$5,780.00