Amendment No. 1
STATE OF TEXAS § CITY SECRETARY NO. 31492
(No M&C Needed)
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and Baird, Hampton and
Brown, Inc. (Engineer) made and entered into City Secretary Contract No.
31492 (the Contract) which was authorized by the City Council by M&C
C-20513; and
WHEREAS, the Contract involves engineering services for the following
project:
2004 CIP Minor Drainage Projects — Contract A — Minor Projects A-1
through A-9
WHEREAS, it has become necessary to execute Amendment No. 1 to
said Contract to include an increased scope of work and revised maximum
fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly-authorized representatives, enter into the following agreement
which amends the Contract:
1.
Article I of the Contract is amended to include the additional
engineering services and provide additional contract time as specified in a
proposal letter dated December 13th, 2005, a copy of which is attached
hereto and incorporated herein. The cost to City for the additional services
to be performed by Engineer total $20,477. The additional contract time for
these services is 30 working days.
2.
Article II of the Contract is amended to provide for an increase in the
maximum fee to be paid to Engineer for all work and services performed
under the Contract, as amended, so that the total fee paid by the City for all
work and services shall not exceed the sum of $ 86,231 + $ 20,477 =
$ 106,708.
All other provisions of the Contract, essly amended
herein, shall remain in full force and effect. va��� ] , � �i
CITY � '� �
[[ryryee?7 y ��I1I7�!'l(1�r „/`
NA -
Contract Amendment No. 1
Page 1 of 2
�T:Tft�
Executed on this the day of , 2006, in
Fort Worth, Tarrant County, Texas.
APPROVAL RECOMMENDED: APPROVE /)
A. Douglas Rademaker, P.E. Ma A. O t
Director, Department of Assistant City Manager
Engineering
Baird, Hampton and Brown (BHB)
Engineering and Surveying
ENGINEER
ATTEST:
Marty Hend , City Secretary
By: ngl�
Konstaine B �NO
M&C REQUIRED
Vice Presesident
APPROVED AS TO FORM AND LEGALITY:
ry
Amy Ra y
AssistanirCity Attorney
Contract Amendment No. 1MR
Page 2 of 2
Baird, Hampton & Brown, Inc. o 0 o Engineering & Surveying
December 13, 2005
Ms.Joseph Bergeron PE, Project Manager
Department of Engineering
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102
Tel(817)871-7949, Fax 871-7854
RE: 104 CIP Minor Drainage Projects—Contract A
Al. Ha rlanwood-Overton Park West SD
A2.Woodway-Wedgway SD Extension
A3. 2008 Teakwood Trace SD Extension
A4. Kensington SD Extension
A5. Chapin-Guadalupe SD Extension
A6. Monticello Park SD Extension
A7. E. Lancaster-Dallas SD Extension—Deleted from Scope
A8. 3436 Clayton Road E. SD Extension
A9. 3804 So. Timberline Drive
A10. 2709 Fairway Drive
City Project No 00093, BHB No 04.129.00
Mr. Bergeron:
We are pleased to have been selected to assist the City of Fort Worth with the above referenced project;
submitted herewith, is our request for a contract amendment to address the additional scope of work
associated with the inclusion of Project A-10, 2709 Fairway Drive and other miscellaneous items.
The estimated construction cost for this additional scope of work has been estimated at $76,000; we
propose an engineering fee, which includes basic and additional services, of$20,477. Additional services
consist of topographic (design) surveys, drainage analysis, erosion control plan, storm water pollution
prevention plan, and other miscellaneous items.
We propose to continue to utilize the services of an M/WBE surveying firm to assist us with this project,
and thus provide 43% M/WBE participation, on this contract modification.
Thank you,
BHB Engineering &Surveying
Konstantine Bakintas, PE
Vice President
Enclosure
e:\2004.000.000\2004.129.000\docs\contract\amendment proposal.doc /t, a,
Bpp7 rt,:rGnnpq]�g�6LLRn�:io
1�U
6300 Ridglea Place, Ste 700 Fort Worth,Texas 76116 Tel: 817-338-1277 Fax:817-338-9245 E-Mail: mail@bhbinc.com
Baird, Hampton & Brown, Inc. Engineering & Surveying
Proposal for Contract Modification
Additional Scope of Work
1.Add Storm Drain Extension Project(A-10)at 2709 Fairway Drive
2. Modify Plans for Reconstruction of 29th Street Culverts at Tony's Creek
December 13, 2005
A. Basic Services:
Professional fees for Basic Services are determined per the procedures outlined in"A Manual of Practice for
Engaging the Services of a Consulting Engineer', published in 1982 by the Consulting Engineers Council
and the Texas Society of Professional Engineers. Proposed fees are based upon Curve"A".
Part A-Conceptual Design, and Part B- Plans & Specifications
Transportation & Public Works: (Construction Cost X ASCE Curve"A"X 85%)
Drainage Improvements (A-10)$76,000 X 8.6%X 85% = $5,556
Basic Services Total = $5,556
B. Additional & Surveying Services:
Surveying Services:
Topographic Survey (A-10) 500 LF X$3.75 = 1,875
Drainage Easement(A-10) 1 Ea X$300 = 300
Additional Survey on (A-2) 560 LF X$3.75 = 2,100
Additional Survey on (A-4) 533 LF X$3.75 = 2,000
Additional Survey on (A-6) 350 LF X$3.75 = 1,313
Additional Survey on (A-8) 350 LF X$3.75 = 1,313
Sub-Total for Surveying Services $ 8,901
Additional Services: Storm Drain Project(A-10)
Prepare Drainage Analysis (A-10) $14,240/8 = $ 1,708
Prepare Erosion Control Plan (A-10) $6,320/8 =$ 790
Prepare SW3P W/NOI & NOT $2,000/8 = 250
$2,820
Additional Services: Reconstruction of 29th Street Culverts at Tony's Creek
Modify Culvert Plans& Profiles $3,200 = $3,200
Additional Services Total =$14,921
Total for Basic and Additional Services =$20,477