Loading...
HomeMy WebLinkAboutContract 47635-CO2 H CITY SECRETARY FORT WORT .- C City of Fort Worth CONTRACT N0. Change Order Request Breakdown ProjectNamel 2014 CIP Sidewalk Contract 4 City Sec# 1 47635 Client Project#(s) T/PW Contractorl ADVANCED PAVING PM TARIQUL ISLAM Inspectorl WILLIAM MASON Change Order Submittal# 0 Date 4/15/2017 Dept. T/PW Contract Time Totals CD Original Contract Amount $553,112.50 $553,112.50 150 Extras to Date $0.00 55 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $553,112.50 $553,112.50 205 Amount of Proposed Change Order $0.00 105 Revised Contract Amount $553,112.50 $553,112.50 310 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) E�� CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.007 MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $691,390.63 JUSTIFICATION(REASONS) FOR CHANGE ORDER This Change Order is to request additional time to the contract for the following reasons:60 days for utility delays on Brentwood Stairs and Ray White,45 days for extra work on Acadame, Shaw Ln.and Ray White. 8� 89l lop �oP�N a aiy J. qXerjCity SBCTetaTy C � L � O SAS OFFICIAL RECORD CITY SECRETARY FM WORTH,TX ' y PORT�, WORrri City of Fort worth Change Order Additions Project Name 2014 CIP Sidewalk Contract 4 City Sec# 47635 Client Project# T/PW Contractor ADVANCED PAVING PM TARIQUL ISLAM Inspector WILLIAM MASON Change Order Submittal# 0 Date 4/15/2017 ADDITIONS Qty Unit Unit Cost Total TME ONLY 777-----=0001 DAYS T/PW $0.00 Sub Total Additions Change Order Additions Page 1 of 1 ' o Foer_ �TH City of Fort Worth Change Order Deletions Project Name 2014 CIP Sidewalk Contract 4 City Sec# 47635 Client Project# T/PW Contractor ADVANCED PAVING PM TARIOUL ISLAM Inspectorl WILLIAM MASON Change Order Submittal# 0 Date 4/15/2017 DELETIONS ITEM TESCRIP= DEPT Qty Unit Unit Cost Total T/PW $0.00 Sub Total Deletions Change Order Deletions Page 1 of 1 M/SBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT Total $0.00 CFW Change Order Approval St-COApp03 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links 1 fortworthgov/Infrastructure Proiects/02704 - 2014 CIP Sidewalk Contract 4/Contractor/Change Orders/Change Order Breakdown #2 02704.x1s Attachments(0) No Attachments have been added to this form. https://projectpoint.buzzsaw.com/ bz_web/Forms/FonnPrint.aspx?SiteId=51500&ProcessI... 6/15/2017 CFW Change Order Approval St-COApp03 Page 2 of 3 FORT WORTH. city of Fort Worth -- ..-- Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: St-COSub02 Change Order No.: St-COApp03 Date Started: 2017-06-01 City Sec. No.: Date Due: 2017-06-16 Project Name: 02704 - 2014 CIP Sidewalk Contract 4 Project Numbers: 02704 DOE Numbers: Project Sidewalk installation at various locations Description: Project Manager: Tariqul Islam City Inspector: William Mason Contractor: COUNCIL ACTION (If Required): M&C Log Name: M&C Number: M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: 105 Total Cost: $ 0.00 Total Requested Days: 105 Approval Status: https://proj ectpoint.buzzsaw.com/_bz_web/Forms/ForrnPrint.aspx?Siteld=51500&Processl... 6/15/2017 CFW Change Order Approval St-COApp03 Page 3 of 3 Approved: Yes Comments: User: Becky Garrett Date: 2017-06-01 12:05 PM Approved: Yes Comments: User: Tariqul Islam Date: 2017-06-01 12:14 PM Approved: Yes Comments: User: Riad Nusrallah Date: 2017-06-06 5:35 PM Approved: Yes Comments: User: Richard Martinez Date: 2017-06-07 2:31 PM Approved: Yes Comments: User: Doug Wiersig Date: 2017-06-08 2:11 PM Approved: Yes Comments: User: Doug Black Date: 2017-06-14 4:43 PM Approved: Yes Comments: User: Jay Chapa Date: 2017-06-15 10:44 AM Action Required: https:Hprojectpoint.buzzsaw.com/ bz_web/Forms/ForrnPrint.aspx?Siteld=51500&ProcessI... 6/15/2017 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Tariqul Islam q-n'V�4447j, ,Awl, Title ❑ This form is N/A as No City Funds are associated with this Contract Printed Name Signature