HomeMy WebLinkAboutContract 47385-CO2 FORT VVORTH City of Fort Worth CITY SECRETARY �2C}
Change Order Request CONTRACT NO.
Project Name:1 2014 CIP Year 2-Contract 2 1 City Sec No.: 47385
Project No.(s):1 DOE#7377-City Project#02433 DOE No. ECity Proj. No.: 02433
Project Description: 2014 CIP Year 2-Contract 2 Water, Sewer and Paving replacement Whitman Ave, Carlyle Dr&Walton Ave.
Contractor: Stabile&Winn, Inc. Change Order# Date: 4/19/2017
City Project Mgr.1 Kristian Sugrim City Inspector: I Edward D'avila
Phone Number:1 817-392-8902 Phone Number: (817)223-2268
Dept. Water Sewer Paving Totals Contract Time
(Calender days)
Original Contract Amount $570,605.25 $436,740.00 $975,759.95 $1,983,105.20 260
Extras to Date $57,800.00 $15,840.00 $73,640.00 30
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $628,405.25 $452,580.00 $975,759.95 $2,056,745.20 290
Go to ADD&DEL Tabs to Enter CO Backup $44,374.22 $44,374.22
Revised Contract Amount $628,405.25 $452,580.00 $1,020,134.17 $2,101,119.42 290
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding(if necessary) L $44,374.22 $44,374.22
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.95%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,478,881.50
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change order required to reconcile final quantities based on actual installed measured quantities.
OFFICIAL RECORD
CITY SECRETARY
�QF F0/'71 FT.WORTHl TX
J 7,,
:btnald7P. Go �XAS
males,Ass C ty Secretary
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Contractor Signature Date
Stabile&Winn, Inc.
Inspector Date Project Manager Date
Assistant Director(Water Dept) Date Construction Supervisor(TPW Dept) Date
Assistant City Attorney Date Assistant City Manager Date
Council Action (If Required)
M&C Number N/A M&C Date Approved N/A
FORT C�RT�I City of Fort Worth
Change Order Additions
Project Name 2014 CIP Year 2-Contract 2 City Sec No.: 47385
Project No.(s): DOE#7377-City Project#02433 DOE No. 7377 City Proj. No.: 02433
Project 2014 CIP Year 2-Contract 2 Water, Sewer and Paving replacement Whitman Ave,Carlyle Dr&Walton Ave.
Description
Contractor Stabile&Winn, Inc. Change Order: Date: 4/19/2017
City Project Mgr. Kristian Sugrim City Inspector F Edward Davila
ADDITIONS
��
PT 4, ' : Unit` UnivCost ` Total:, :
UNIT III PAVING IMPROVEMENTS
3-1 MISCELLANEOUS ADJUSTMENTS(UTILITIES) Paving 5.074665 LS $6,000.00 $30,447.99
3-4 REMOVE CONCRETE DRIVEWAY Paving 700.92 SF $3.00 $2,102.76
3-5 6"CONCRETE DRIVEWAY Paving 1018.92 SF $9.50 $9,679.74
3-9 Remove CONCRETE PAVEMENT Paving 666.99 ISY $12.00 $8,003.88
3-10 7"Concrete Pavement Paving 32.79 SY $69.15 $2,267.43
3-14 11"PAVEMENT PULVERIZATION Paving 115.40 SY $8.00 $923.20
3-15 3"ASPHALT PAVEMENT TYPE D Paving 115.40 SY $18.00 $2,077.20
3-16 CEMENT MODIFICATION, 13 LBS/SY Paving 0.86 TN $175.00 $150.50
3-19 WATER VALVE BOX ADJUSTMENTS(WITH CONCRETE COLLAR) Paving 15.000 EA $300.00 $4,500.00
3-20 MANHOLE ADJUSTMENTS(W/CONCRETE COLLAR) Paving 8.00 EA $800.00 $6,400.00
3-21 MISCELLANEOUS ADJUSTMENTS(WATER METER BOX) Paving 62.00 EA $50.00 $3,100.00
3-22 UNCLASSIFIED STREET EXCAVATION Paving 782.08 CY $25.00 $19,552.00
3-23 CURB ADDRESS PAINTING Paving 25.00 EA $20.00 $500.00
3-24 TOPSOIL Paving 136.00 CY $25.00 $3,400.00
3-25 BLOCK SOD REPLACEMENT Paving 2141.00 SY $6.00 $12,846.00
3-30 6"HMAC Transtion Paving 4.50 TN $250.00 $1,125.00
Water
Sewer
Page 1 of 2 Paving $107,075.70
Fc) WORTH City of Fort Worth
Change Order Deletions
Project Name 2014 CIP Year 2-Contract 2 City Sec No.: 47385
Project No.(s): DOE#7377-City Project#02433 DOE No. 7377 City Proj. No.: 02433
Project Description 2014 CIP Year 2-Contract 2 Water, Sewer and Paving replacement Whitman Ave, Carlyle Dr&Walton Ave.
Contractor Stabile&Winn, Inc. Change Order: F2 Date 4/19/2017
City Project Mgr. Kristian Sugrim City Inspector: Edward Davila
DELETIONS
ITEM.. DESCRIPTION .: DEPT Q Unit' Unit Cost Tofal
tY
UNIT III PAVING IMPROVEMENTS
3-2 REMOVE CONCRETE CURB&GUTTER Paving 215.00 LF $3.00 $645.00
3-3 6"CONCRETE CURB&GUTTER Paving 415.00 LF $26.00 $10,790.00
3-6 REMOVE SIDEWALK Paving 262.00 SF $3.00 $786.00
3-7 4"CONCRETE SIDEWALK Paving 312.00 SF $9.00 $2,808.00
3-8 7"CONCRETE VALLEY GUTTER Paving 21.20 SY $120.00 $2,544.00
3-11 CONCRETE JOINT SEALANT(MISCELLANEOUS USE) Paving 50.00 LF $5.00 $250.00
3-12 FLEX BASE,TYPE A, GR-2(MISCELLANEOUS USE) Paving 5.00 CY $100.00 $500.00
3-17 ROADBOND ENI (GA) Paving 1.00 $140.00 $140.00
3-26 4"SOLID YELLOW THERMOPLASTIC(HAS)LANE LINES Paving 160.00 LF $5.00 $800.00
3-27 STOP BARS PAVEMENT MARKINGS Paving 390.00 LF $10.00 $3,900.00
3-28 REMOBILIZATION(MISCELLANEOUS ONLY) Paving 1.00 LS $1,800.00 $1,800.00
3-29 PAVING CONSTRUCTION ALLOWANCE Paving 0.94369800000 EA $39,990.00 $37,738.48
Water
Sewer
Paving 1$62,701.48
Page 1 of 2 IDeletions Sub Total
M/WBE Breakdown for this Change Order
',MWBE Sub Typ �of`Sora�ice Amount for thi'Q
NONE This is a close out change order to reconcile final $0.00
uantities only
Total $0 00
Previous Change Orders
AMOUNTy
One 12/15/2016 $73,640.00
Total $73,640 DO
Page 1 of 1
CFW Change Order Approval St-COApp02 Page 1 of 3
Routing
Assigned To: Due Date:
Assigned By: Due Time:
Links 1
fortworthgov/Infrastructure Projects/02433 - 2014 CIP Year 2 — Contract 2/Contractor/Change Orders/Change Order
Breakdown #2.xls
Attachments(0)
No Attachments have been added to this form.
https://projeetpoint.buzzsaw.com/ bz web/Forms/FonuPrint.aspx?SiteId=51500&ProcessI... 6/28/2017
CFW Change Order Approval St-COApp02 Page 2 of 3
FORTWORTH®R City of Fort Worth
Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: '.2
Change Order No.: ;St-COApp02 Date Started: 2017-05-10
City Sec. No.: 47385 Date Due: 2017-06-29
Project Name: 00000 - Project Folder Template
02433 DOE Numbers:
Project Numbers: 'DOE No. 7377
Project Removal and replacement of nonfunctional curb and gutter,
Description: driveways and sidewalks; pulverization and stablilzation of
':the existing pavement, followed by HMAC overlay.
i
Project Manager: Kristian Sugrim City Inspector: Edward D'avila
Contractor:
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number: M&C Date: .
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
TPW $ 44,374.22 34014 5740010
Total Cost: $ 44,374.22 Total Requested Days: 0
Approval Status:
https://projectpoint.buzzsaw.com/ bz web/Foims/FoimPrint.aspx?SiteId=51500&ProcessI... 6/28/2017
CFW Change Order Approval St-COApp02 Page 3 of 3
Approved: Yes
'Comments:
User: Jerry Henderson
Date: 2017-05-25 11:02 AM
'Approved: Yes
Comments:
'User: Kristian Sugrim
Date: 2017-05-25 11:31 AM
;Approved: Yes
'Comments:
,User: Najib Fares
':Date: 2017-05-25 5:01 PM
'Approved: Yes
Comments:
User: Kim Arnold
'Date: 2017-06-07 2:55 PM
"Approved: Yes
;Comments:
'User: Doug Wiersig
;Date: 2017-06-08 2:09 PM
Approved: Yes
Comments:
'User: Doug Black
Date: 2017-06-14 4:38 PM
;Approved: Yes
';Comments:
!User: Jay Chapa
Date: 2017-06-14 4:58 PM
Action Required: