Loading...
HomeMy WebLinkAboutContract 48148-CO1 City of Fort Worth CITYSECRETARY FORT WORTH. CONTRACTN0. qVqm ~^ Change Order Request Breakdown - - Project Namel FW South Pavement Replacement(FY 15-CD9) City Sec# 1 48148 Client Project#(s)l c02375&c02445 Contractorl McClendon Construction Co. PM Mary Hanna Inspectorl Gary Deyon Change Order Submittal# 0 Date 4/11/2017 Dept. Stormwater Water Sewer Contract Time Totals CD Original Contract Amount $126,018.00 $1,181,118.50 $82,200.00 $1,389,336.50 280 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $126,018.00 $1,181,118.50 $82,200.00 $1,389,336.50 280 Go to ADD&DEL Tabs to Enter CO Backup $11,250.00 $10,550.00 $23,540.00 $45,340.00 21 Revised Contract Amount $137,268.00 $1,191,668.50 $105,740.00 $1,434,676.50 301 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 $0.00 $0.00 Additional Funding(if necessary) $11,250.00 $10,550.00 $23,540.00 $45,340.00 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.26% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,736,670.63 Subsequent;to beginning construction of the project,a property owner along College Avenue approached staff with a request to upgrade the existing service lines to the property to accommodate its proposed new development.Staff required and the property owner agreed to pay for these upgrades by change order. This change order includes for these water and sewer upgrades.Also this CO includes replacing existing undersized storm drain laterals with 18"RCP at the following crossings College at Vickery,Lipscomb at Tucker,Lipscomb at Peter Smith, Lipscomb at Broadway, Lipscomb and Daggett. Aum"by: ary J. ay r, City Secretary y�F FORr Q:: o AS OFFICIAL RECORD CITY gECRVARY III. WC)RTHI TX FO_;ORTH City of Fort worth Change Order Additions Project Name J FW South Pavement Replacement(FY 15-CD9) City Sec# 48148 Client Project# F c02375&c02445 Contractor McClendon Construction Co. PM Mary Hanna Inspector Gary Deyon Change Order Submittal# Date 4/11/2017 ADDITIONS ITEM DE6UHIPHON ty Unit Unit Cost I o a Water Items 1-44 Cut in 12"x8"Tap&GV with Stub out to ROW Water 1.00000000 Ea 10,000.0 1-45 Remove&Cap/Plug 1"Water ervice Water 1.00009000 Ea 550.00 Storm Items IIB-5 18"RCP Class III Tormwater 90.00000000 LF 125.00 Sewer Items 11-21 Remove& ap/P ug 4"Sewer Service Sewer 00 11-22 Cut in 4'Manhole 8'Deep Sewer 1.00000000 Ea 1 ,500.00 11-23 8"DIP with CSS Backfill Sewer 29.000OUTOU LF 0 11- 20"Steel Casing ewer 10 OOOTW LF $160.05 11-25 Relocation of Equipement back to College SFewer 1.0000000 L7 2,800. 0 Stormwater $11,250.00 Water $10,550.00 Sewer $23,540.00 Sub Total Additions 5,340.00 Change Order Additions Page 1 of 1 FoaT_ OR H City of Fort Worth Change Order Deletions Project Name FW South Pavement Replacement(FY 15-CD9) CitySec# 48148 Client Project# c02375&c02445 Contractor McClendon Construction Co. PM Mary Hanna Inspector Gary Deyon Change Order Submittal# Date 4/1112017 DELETIONS ITEM DESCRIPT11 N DEPT Qty Unit Unit Cost Total Stormwater $0.00 Water $0.00 Sewer $0.00 Sub Total Deletions Change Order Deletions Page 1 of 1 M/SBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO N/A Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 CFW Change Order Approval SW-COAppr02 Page 2 of 3 FORTWURTH@C'ty of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: 1 Change Order No.: SW-COAppr02 Date Started: 2017-06-20 City Sec. No.: 48148 Date Due: 2017-08-09 Project Name: 02375 - FY15 - CD 9 Street Repair and Reconstruction Program 02375 DOE Numbers: Project Numbers: Project This is Round 1 of CD9 Street Repair and Reconstruction Description: Program (c02375) Project Manager: Mary Hanna City Inspector: Gary Deyon Contractor: McClendon Construction Company, Inc. COUNCIL ACTION (If Required): M&C Log Name: FW SOUTH PAVEMENT CO FUNDS M&C Number: G-19023 M&C Date: 2017-06-13 COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: Stormwater $ 11,250.00 59651-0200431-5740010-c02375-0( 0 Water $ 10,550.00 59601-600430-5740010-c02445-c0 6 Sewer $ 23,540.00 59607-700430-5330500-c02445-c0; 15 Total Cost: $ 45,340.00 Total Requested Days: 21 Approval Status: https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessI... 7/25/2017 CFW Change Order Approval SW-COAppr02 Page 3 of 3 Approved: Yes Comments: User: Justin Blair Date: 2017-06-20 2:31 PM Approved: Yes Comments: User: Mary Hanna Date: 2017-06-20 3:07 PM Approved: Yes Comments: User: Linda S. Young Date: 2017-06-20 4:32 PM Approved: No Comments: User: Greg Simmons Date: 2017-06-20 4:41 PM Approved: Yes Comments: User: Doug Wiersig Date: 2017-06-26 4:53 PM Approved: Yes Comments: User: Doug Black Date: 2017-07-14 10:34 AM Approved: Yes Comments: User: Jay Chapa Date: 2017-07-25 12:46 PM Action Required: Please Review, Approve and Submit https:Hproj ectpoint.buzzsaw.com/_bz_web/Forms/FormPrint.aspx?S iteld=515 00&ProcessI... 7/25/2017 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Name mployee/Signature UY- Yom( Title ❑ This form is N/A as No City Funds are associated with this Contract Printed Name Signature M&C Review Page 1 of 2 Official site of the City of Fort Worth,Texas CITY COUNCIL AGENDA FORTRT11 COUNCIL ACTION: Approved on 6/13/2017 - Ordinance Nos. 22757-06-2017 & 22758-06-2017 DATE: 6/13/2017 REFERENCE NO.: **G-19023 LOG NAME: 20FW SOUTH PAVEMENT CO FUNDS CODE: G TYPE: CONSENT PUBLIC NO HEARING: SUBJECT: Authorize Acceptance of Funds from La Vida Urban Living, LLC, in the Amount of $35,624.00 to Provide Additional Funds for the Near Southside Medical District Water and Sanitary Sewer Main Improvements Project, Authorize Transfer of Funds in the Stormwater Capital Projects Fund to the Council District 9 Street Repair and Reconstruction Project and Adopt Appropriation Ordinances (COUNCIL DISTRICT 9) RECOMMENDATION: It is recommended that the City Council: 1. Authorize the acceptance of funds from La Vida Urban Living, LLC, in the amount of$35,624.00; 2. Adopt the attached the appropriation ordinances increasing receipts and appropriations from available funds in the Water Capital Fund in the amount of$11,142.40 and in the Sewer Capital Fund — Legacy in the amount of$24,481.60 to provide additional funding for the Near Southside Medical District Water and Sanitary Sewer Main Improvements Project (CO2245); and 3. Authorize the transfer of appropriated funds in the Stormwater Capital Projects Fund in the amount of$12,481.00, from available funds to the Council District 9 Street Repair and Reconstruction Project (CO2375). DISCUSSION: On August 23, 2016, (Mayor and Council Communication (M&C) C-27883) the City Council authorized a contract with McClendon Construction, Company, Inc. (City Secretary Contract No. 48148) in amount of$3,079,663.55 for Round 1 of the combined Council District 9 Street Repair and Reconstruction Program (CO2375) and the Near Southside Medical District Water and Sanitary Sewer Main Improvements Project (CO2445) to address needed street improvements, water and sanitary sewer upgrades (to replace aging facilities and provide additional capacity to accommodate anticipated development) and to facilitate redevelopment and revitalization in identified areas of the Near Southside District. After construction started, a property owner on College Avenue, La Vida Urban Living, LLC, approached the City of Fort Worth about having its existing utility services upgraded to a larger size. An Agreement was made with the property owner to pay for the cost difference. The project would incorporate these upgrades by change order. This M&C is to accept and appropriate these private funds into the Near Southside Medical District Water and Sanitary Sewer Main Improvements Project. This M&C also authorizes a $12,481.00 transfer of Stormwater Capital Project Funds to cover a portion of Change Order No. 1 cost to replace existing undersized storm drain laterals in the Council District 9 Street Repair and Reconstruction Project. Authorizations provided with this M&C will result in no additional annual operating impacts to the Transportation and Public Works Department's or Water Department's operating budgets. The project is located in COUNCIL DISTRICT 9, Mapsco 76H, 76M, 77E and 77J. This M&C does not request approval of a contract with a business entity. http://apps.cfwnet.org/council_packet/mc_review.asp?ID=24708&councildate=6/13/2017 7/28/2017 M&C Review Page 2 of 2 FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinances, funds will be available in the current capital budget as appropriated, of the Stormwater Capital Projects Funds, the Water Capital Fund and the Sewer Capital Fund-Legacy. Responsibility for the collection and deposit of the donation is the responsibility of the Transportation & Public Works Department. TO Fund Department Account Project Program Activity Budget Reference# Amount ID ID Year Charlfield 2 FROM Fund Department Account Project Program Activity Budget Reference# Amount ID ID Year Chartfield 2 Submitted for City Manager's Office by: Jay Chapa (5804) Originating Department Head: Douglas Wiersig (7801) Additional Information Contact: Mary Hanna (5565) ATTACHMENTS 20FW SOUTH PAVEMENT CO FUNDS 59601 A017Rev.docx 20FW SOUTH PAVEMENT CO FUNDS 59607 A017.docx CD9 STREET REPAIR RECON FY15 AND NEAR SOUTHSIDE MEDICAL DISTRICT.pdf http://apps.cfwnet.org/council_packet/mc review.asp?ID=24708&councildate=6/13/2017 7/28/2017 Mills, Stephanie From: Simmons, Greg Sent: Wednesday,July 26,2017 3:21 PM To: Hanna, Mary Cc: Mills, Stephanie Subject: RE: Question Mary, Yes. I'm fine with this change order. Thx,greg Greg Simmons, P.E., CFM Assistant Director Transportation and Public Works Department Stormwater Management Division City of Fort Worth 200 Texas St. Fort Worth, Tx 76102 5817.392.7-62 (office) greg.simmonsgfortworthtexas.gov City of Fort Worth— Working together to build a strong community. FOR` WODTH "91V How am I doing?Please feel free to contact my supervisor: doU .w,� iersigg-fortworthtexas.QOV From: Hanna, Mary Sent: Wednesday,July 26, 2017 3:20 PM To:Simmons,Greg<Gregory.Simmons@fortworthtexas.gov> Cc: Mills, Stephanie<Stephanie.Mills@fortworthtexas.gov> Subject: Re: Question Hello Greg, Yes,this was approved by both Linda and Maenica. Can you please confirm that you are fine with the change order so City's Secretary sign it? Thanks, Mary Hanna On Jul 26, 2017, and at 2:24 PM, Simmons, Greg<Gregory.Simmons@fortworthtexas.gov>wrote: Mary, 1