Loading...
HomeMy WebLinkAboutContract 48366-CO1 CITY SECRETARY FORT WORTH City of Fort Worth CONTRACT N0. !M� Change Order Request Breakdown ProjectNamel Transportation Connections for Bicycles&Pedestrians Phaes II City Sec# 1 48366 Client Project#(s) Contractorl The Fain Group, Inc. PM Clarence Bryant Inspecto Eddie Walker Change Order Submittal# Date 7/12/2017 Dept. PACS Contract Time Totals CD Original Contract Amount $3,222,964.25 $3,222,964.25 220 Extras to Date 10 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $3,222,964.25 $3,222,964.25 230 Amount of Proposed Change Order $97,950.00 $97,950.00 Revised Contract Amount $3,320,914.25 $3,320,914.25 230 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) $97,950.00 $97,950.00 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.04% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $4,028,705.31 JUSTIFICATION(jR V,SONS) FOR CHANGE ORDER This is the formal change request to move Bent 5(16)'East,and therefore change the lengths of the bridges.This change was required due to site conditions being significantly different from the plans.Also,the 6'-24"tree count for removal was much higher that the plan quantities. It's assumed that the tree survey was taken several years ago,and that many trees have grown significantly over time.Also,the masonry veneer quantity on the plans,and what has been installed is much higher than what was bid.The installation matches the plans,but the bid item quantity is way too low. Also a change at the Mistletoe bridge was required due to site conditions being signigicantly different from the plans. The plans showed the east pier on the waters edge. Actual conditions and the location of the proposed pier located the pier in the water, which would have increased the cost of installing this peir in water signficantly. The pier was relocated 15 feet from the proposed location on to the bank by the engineer. This cost reflects the bridge manufacturer's reconstruction of the bridge spans. FOP T� :0 U < ` J. Kayser, City Se64taTy * _ �`XAS ,... �Ayg7 89x0 r 1 a 4110 LCORK a C�sF��TttiO�l� 3 OFFICIALE RETARY14,T'X FRrtHt t_tt,�c,e City of Fort Worth T Change Order Additions Project Name I Transportation Connections for Bicycles&Pedestrians Phaes II City Sec# 48366 Client Project# Contractor The Fain Group,Inc. PO Clarence Bryant Inspector Eddie Walker Change Order Submittal# Date 711 212 0 1 7 ADDITIONS ITEM DESCRIPM79-- DEPT Qty Unit Unit Cost Total 9608-6001 Bridge engt anges 0100-6MT Preparing Row(Tree) 6"to 24 dia) PA 00 L 425.00 71MUZ17F Preparing Row(Tree) to 24 dia)all 7. Landscape Amenity tone eneer 5 . PACS $97,950.00 Sub otaAdditions $97,950.0 Change Order Additions Page 2 of 4 Foo i%vokI t1 City of Fort Worth I-- Change Order Deletions Project Name Transportation Connections for Bicycles&Pedeslnans Phaes II City Sec# 48366 Client Project# Contractor The Fain Group,Inc. PM Clarence Bryant Inspector Eddie Walker Change Order Submittal# Date 711 212 0 1 7 OtLt HUNS ty unit Unit Cost I ota PACS $0.00 Sub I otal Deletions Change Order Deletions Page 3 of 4 MISBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO R&A Masonry Stone Coping $17,160.00 Total $17,160.00 Previous Change Orders co# DATE AMOUNT Total $0.00 EN FAIN July 14, 2017 Clarence Bryant Jr Landscape Architect/Project Manager City of Fort Worth Parks and Recreation Department 4200 South Freeway, St. 2200 Fort Worth, TX 76115 RE: Transportation Connections for Pedestrians and Bicycles Project Change Request 41 revised Mr. Bryant, This is the formal change request to move Bent 5 (16)' East, and therefore change the lengths of the bridges. This change was required due to site conditions being significantly different from the plans. Also,the 6'-24"tree count for removal was much higher that the plan quantities. It's assumed that the tree survey was taken several years ago, and that many trees have grown significantly over time. Also, the masonry veneer quantity on the plans, and what has been installed is much higher than what was bid. The installation matches the plans, but the bid item quantity is way too low. We're also requesting (10) additional days. DESCRIPTION EST.QTY UOM UNIT PRICE AMOUNT Bridge Length Changes 1.00 LS $11,250.00 $11,250.00 PREPARING ROW(TREE)(6"TO 24" DIA) 72.00 EA $425.00 $30,600.00 PREPARING ROW(TREE)(6"TO 24" 55.00 EA $474.00 $26,070.00 DIA)ALT LANDSCAPE AMENITY(TY1)(STONE 858 SF $35.00 $30,030.00 VENEER) TOTAL $97,950.00 If you have any questions, please feel free to contact me at 817-927-4388. Sincerely, Clint Syma .f CFW Change Order Approval Pa- COAppOI Page 2 of 3 FORT WORTH. C'ty of Fort Worth . - Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: 1 Change Order No.: Pa - COApp01 Date Started: 2017-07-14 City Sec. No.: 48366 Date Due: 2017-07-29 Project Name: 01734 - Transportation Connections for Bicycles & Pedestrians Project Numbers: 01734 DOE Numbers: Project Pedestrain bridges, trails,and retaining walls Description: Project Manager: Clarence Bryant City Inspector: Eddie Walker Contractor: The Fain Group COUNCIL ACTION (If Required): M&C Log Name: M&C Number: M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: PARD $ 97,950.00 39801-0800450-5740010-C01734- 10 C°5-880 Total Cost: $ 97,950.00 Total Requested Days: 10 Approval Status: https://proj ectpoint.buzzsaw.com/_bz_web/Forms/FonuPrint.aspx?Siteld=51500&ProcessI... 8/14/2017 CFW Change Order Approval Pa- COApp01 Page 3 of 3 Approved: Yes Comments: User: Nannette Long Date: 2017-07-26 4:16 PM Approved: Yes Comments: User: Perla Banda Date: 2017-07-27 2:22 PM Approved: Yes Comments: User: Clarence Bryant Date: 2017-07-27 3:40 PM Approved: Yes Comments: User: Joel McElhany Date: 2017-07-31 11:41 AM Approved: Yes Comments: User: Richard Zavala Date: 2017-07-31 6:17 PM Approved: Yes Comments: User: Doug Black Date: 2017-08-11 5:16 PM Approved: Yes Comments: User: Susan Alanis Date: 2017-08-13 7:11 PM Action Required: Please Review and Approve https:Hprojectpoint.buzzsaw.com/ bz_web/Forms/FormPrint.aspx?Siteld=51500&Processl... 8/14/2017 CFW Change Order Approval Pa- COApp01 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links 2 fortworthgov/PACS/01734 - Transportation Connections for Bicycles & Pedestrians Part 2/Contractor/Change Orders/Change Order Breakdown 1.xlsx fortworthgov/PACS/01734 -Transportation Connections for Bicycles & Pedestrians Part 2/Contractor/Change Orders/CO1/PCR-001 rev.pdf Attachments(0) No Attachments have been added to this form. https:Hproj ectpoint.buzzsaw.com/_bz_web/Forms/FonnPrint.aspx?Siteld=51500&Processl_.. 8/14/2017 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Name of Employee 710 EtlN�,IIk Title 0 This form is N/A as No City Funds are associated with this Contract 1 Printed Name Signature